PDD
PDD
PDD
PART -B
1. Explain iterative waterfall and spiral model for software life cycle and discuss various
activities in each phase. (16)
2. List several software process paradigms. Explain how both waterfall model and
prototyping model can be accommodated in the spiral process model. (16)
3. Explain in detail Boehm's spiral model for software life cycle and discuss various activities
in each phase. (16)
4. a) Which is more important-the product or process? Justify your answer. (4)
b) Identify the umbrella activities in software engineering process. (4)
c) With suitable illustration explain SPIRAL model evolutionary software development. (8)
5. Explain iterative waterfall and Prototyping model for software life cycle and various
activities in each phase. (16)
6. Explain about the generic process model with neat diagram. (16)
7. Explain in detail about the software process paradigms. (16)
8. Explain Spiral model and win-win spiral model in detail? (16)
9. Explain in detail about incremental and Rapid application development Model (RAD) and
mention its advantages and disadvantages. ` (16)
10. Distinguish between verification and validation process. (8)
11. Draw the system engineering hierarchy diagram and explain in detail. (8)
12. Explain the concept of Business process engineering with neat sketch. (16)
13. Explain the concept of Business process engineering with neat sketch. (8)
14. Discuss about the layers of software engineering. (8)
PART -B
1. Explain the need for software measures and describe various metrics. (16)
2. Explain in detail about the various levels of Capability Maturity Model(CMM) (16)
3. Explain the salient features of COCOMO model for cost estimation .Bring out Different
variant of this model. (16)
4. Explain in detail about Delphi Method. (16)
5.a. What are the different types of software Maintenance activities envisaged for an installed
software . (8)
b. Describe in detail about the standardization procedures of benchmarking (8)
6. Explain the features of a popular CASE tools that u are aware of. (16)
7.a. Give a detail note on SPICE . (8)
b. Write Detail notes on IS9000 series of quality management standards. (8)
8.a. What is an activity network? Explain. (8)
b. Explain the scheduling of a software project.How are PERT and CPM useful in project
scheduling? (8)
9. Discuss about the relationship between people and effort ,task set network.
10.Explain about the EVA (Earned Value Analysis) and project metrices.