Bill of Quantities: CONCRETE - 3000 PSI Footing 1.85 X 1.85 Columns
Bill of Quantities: CONCRETE - 3000 PSI Footing 1.85 X 1.85 Columns
Bill of Quantities: CONCRETE - 3000 PSI Footing 1.85 X 1.85 Columns
QUANTITIES
PROJECT NAME :
Proposed Modern House
SECTION
CE 401
PROJECT LOCATION :
IMUS, CAVITE
INSTRUCTOR ENGR. SIVA DAS ABAYA
DATE : 31-May-19
OWNER: Bunda, Jerby C. , Tabigne, John Renz D.
ITEM DESCRIPTION QUANTITY UNIT MATERIAL LABOR TOTAL UNIT AMOUNT
COST COST COST
I SITE PREPARATION
Site excavation 117 cu.m 0.00 75.00 75.00 8,775.00
Backfill and 117 cu.m 0.00 50.00 50.00 5,850.00
Compaction
Gravel Bedding 17 cu.m 430.00 50.00 480.00 8,160.00
Sub - Total ₱22,785.00
II CIVIL WORKS
2.1 Building
2.1.1 CONCRETE - 3000
PSI
Footing 1.85 x 1.85 12.32 cu.m 2,180.00 150.00 2,330.00 28,705.60
x 0.40m
Columns
0.30 x 0.30m from 4.81 cu.m 2,180.00 150.00 2,330.00 11,207.30
foundation to
Second Floor
0.20 x 0,20 For 0.37 cu.m 2,180.00 150.00 2,330.00 862.10
Second Floor
Beams
20mm Ø rebars
from Foundation 987 kg 36.00 3.00 39.00 38,493.00
to Second Floor
16mm Ø rebars 47 kg 36.00 3.00 39.00 1,833.00
for Second Floor
10mm Ø rebars 186 kg 36.00 3.00 39.00 7,254.00
for ties
Beams
16mm Ø rebars
for Footing Tie 467 kg 36.00 3.00 39.00 18,213.00
Beam
25mm Ø rebars 1,843 kg 36.00 3.00 39.00 71,877.00
for Upper Ground
Floor
20mm Ø rebars 949 kg 36.00 3.00 39.00 37,011.00
from Ground Floor
to Second Floor
10mm Ø For 1086 kg 36.00 3.00 39.00 42,354.00
Stirrups
Slab
10mm Ø rebars 940 kg 36.00 3.00 39.00 36,660.00
for Two way slab
12mm Ø rebars 104 kg 36.00 3.00 39.00 4,056.00
for one way slab
CHB Walls 10mm 200 kg 36.00 3.00 39.00 7,800.00
Ø rebars
2.1.3 Masonry Works
100mm Thick 72 sq.m 75.00 140.00 215.00 15,480.00
Concrete Hollow
Blocks
13mm Thick Wall 0.90 cu.m 1,750.00 120.00 1,870.00 1,683.00
Plastering
2.2 Swimming Pool
Rebars
150mm Concrete
Hollow Blocks
50 sq.m 100.00 160.00 260.00 13,000.00
Swimming Pool
Wall
20mm thick for 1 cu.m 1,750.00 120.00 1,870.00 1,870.00
Wall Plastering
Formworks
2.3 Columns
Beam
0.2 mm thick 1.25 21 pcs 1,000.00 80.00 1,080.00 22,680.00
m x 2.5m Phenolic
Board
2" x 2" Coco 29 pcs 300.00 24.00 324.00 9,396.00
Lumber 21 ft.
4" Wood Nail 8 kgs 50.00 4.00 54.00 432.00
Slab
0.2 mm thick 1.25 18 pcs 1000 80.00 1,080.00 19,440.00
m x 2.5m Phenolic
Board
2" x 2" Coco 16 pcs 300 24.00 324.00 5,184.00
Lumber 21 ft.
ITEM DESCRIPTION QUANTITY UNIT MATERIAL LABOR TOTAL AMOUNT
COST COST UNIT COST
2.4 Roofing
Waterproofing
8
BAGS 220.00 150.00 370.00 2960.00
Doors
600 x 2100mm 4 set 1500.00 150.00 1650.00 6600.00
PVC Louver 3 set
1700.00 300.00 2000.00 6000.00
Door: Hollow 2 set
2000.00 300.00 2300.00 4600.00
Core Flushed
Door: Marine
Plywood in
2''x4'' wood
900 x 2100mm
Panel Door
Windows
Aluminum 7 set 1500.00 150.00 1650.00 11550.00
Sliding Window 6 set 400.00 150.00 550.00 3300.00
with 6mm thick
clear glass,
Fixed Window:
8'' x 8'' Glass
Blocks
Fence
150mm thick
CHB non load
bearing
inclusive of
rebars
Sub - Total ₱32,050.00
ITEM DESCRIPTION QUAN UNI MATERI LABO TOTAL AMOUNT
TITY T AL COST R COST UNIT COST
IV FINISHES
Paint
sq. 31.51 150.00 181.51 5082.28
Application of Flat Latex Paint for 28 m
Interior
sq. 122.22 150.00 272.22 18510.00
Application of Semi-gloss Latex Paint 68
m
sq. 144.00 150.00 294 2352.00
Application of Quick Dry Enamel Paint 8
m
Floor and Wall Tiles
Sub - Total ₱
25,451.00
VI ELECTRICAL WORKS
Installation for Lighting Load 1 box 1,881.00 1,800.00 3,681.00 3,681.00
3.5mm THHN Wire 1/2'' Ø PVC Conduit 18 pcs 69.00 75.00 144.00 2,592.00
Pipe 1 box 1,881.00 1,800.00 3,681.00 3,681.00
Installation of Convenience Outlet 18 pcs 69.00 75.00 144.00 2,592.00
3.5mm THHN Wire 1/2'' Ø PVC Conduit 15 m pcs 20.00 300.00 320.00 4,800.00
Pipe 18 m 92.00 75.00 167.00 3,006.00
Installation of Water Pump 15 set 60.00 300.00 360.00 5,400.00
5.5mm THHN Wire 3/4'' Ø PVC Conduit 1 1,500.00 600.00 2,100.00 2,100.00
Pipe
14mm THHN Wire
Installation of Panel Board 95AT 230V 3
Wires 60htz
Sub - Total ₱
27,852.00
Total Amount ₱869,676.68
Eight