1 - Oberlender
1 - Oberlender
1 - Oberlender
Construction Costs
Fifth Edition
Robert L. Peurifoy
Garold D. Oberlender
Me
Graw
Hill
Boston Burr Ridge, IL Dubuque, IA Madison, Wi New York ‘ San Francisco St. Louis
Bangkok Bogota Caracas Kuala Lumpur Lisbon London Madrid Mexico City
Milan Montreal New Delhi Santiago Seoul Singapore Sydney Taipei Toronto
The M c G r a w H ill Companies
Me
Gravu
Hill
ESTIMATING CONSTRUCTION COSTS
Fifth Edition
International Edition 2004
Exclusive rights by McGraw-Hill Education (Asia), for manufacture and export. This book cannot be
re-exported from the country to which it is sold by McGraw-Hill. The International Edition is not
available in North America.
Published by McGraw-Hill, a business unit of The McGraw-Hill Companies, Inc., 1221 Avenue of
the Americas, New York, NY 10020. Copyright © 2002, 1989, 1975, 1958, 1953 by The McGraw-
Hill Companies, Inc. All rights reserved. No part of this publication may be reproduced or distributed
in any form or by any means, or stored in a database or retrieval system, without the prior written
consent of the publisher, including, but not limited to, in any network or other electronic storage or
transmission, or broadcast for distance learning.
Some ancillaries, including electronic and print components, may not be available to customers outside
the United States.
10 09 08 07 06 05 04 03 02 01
20 09 08 07 06 05 04
CTF ANL
Printed in Singapore
www.mhhe.com
DEDICATION
GAROLD D. OBERLENDER
iii
ABOUT THE AUTHORS
iv
CONTENTS
C H APT ER 2
C HAPT ER 1 Bid D ocum ents 22
Introduction 1
Bid Documents and Contract
Purpose of This Book 1 Documents 22
Estimating 2 Contract Requirements 23
Importance of the Estimator and the Arrangement of Contract Documents 23
Estimating Team 3 Building Construction Specifications 24
Purpose of Estimating 3 Heavy/Highway Specifications 25
Types of Estimates 4 Bidding Requirements 25
Approximate Estimates 5 Negotiated Work 32
Detailed Estimates 6 Addendum 32
Organization of Estimates 7 Alternates 32
Building Construction Projects 8 Change Order 32
Heavy Engineering Construction Projects 9 Warranties 33
Quantity Takeoff 11 General Conditions of the Contract
Labor and Equipment Crews 12 Documents 33
Checklist of Operations 12 Bonds 33
Bid Documents 13 Insurance 35
Addenda and Change Orders 14 Heavy/Highway Drawings 36
Overhead 14 Building Construction Drawings 37
Material Taxes 15 Symbols and Abbreviations 42
Labor Taxes 15 Problems 43
Workmen’s Compensation Insurance 15
Labor Burden 16
Bonds 16 CHAPT ER 3
Insurance 16 Estim ating P ro c ess 44
Representative Estimates 17 Decision to Bid 44
Instructions to the Readers 17 Estimating Process 44
Production Rates 17 The Estimating Team 46
Tables of Production Rates 18 Estimate Work Plan 47
vi Contents
Bonds for Stone Masonry 342 Terrazzo Placed on a Wood Floor 364
Mortar for Stone Masonry 342 Labor Required to Place Terrazzo
Weights of Stone 342 Floors 364
Cost of Stone 343 Vinyl Tile 366
Labor Setting Stone Masonry 344 Laying Vinyl Tile on a Concrete
Problems 345 Floor 366
Laying Vinyl Tile on a Wood Floor 366
CHAPT ER 16 Labor Laying Vinyl Tile 366
Floor S y ste m s 347 Problems 367
Introduction 445
Importance of the Estimator 446 APPENDIX
Use of Computers in Estimating 446 Exam ple Bid D ocum ents 498
Electronic Media 448
Evolution of Computer Programming 448 Index 549 »■
Fundamentals of Spreadsheets 449
PREFACE
This book presents the basic principles of estimating the time and cost of con
struction projects. To prepare an accurate estimate the estimator must perform a
careful and thorough analysis of the work to be performed. The analysis includes
the type and quantity of work, type and size of equipment to be used during con
struction, production rates of labor and equipment to install the work, and other
job-site conditions that are unique to the project that can impact the time and
cost of construction.
This book emphasizes the thought process that is required of the estimator
to analyze job conditions and assess the required labor, equipment, and method
of construction that will be necessary to perform the work. To assemble a com
plete estimate for bid purposes, the estimator must combine his or her knowl
edge of construction methods and techniques into an orderly process of calcu
lating and summarizing the cost of a project.
Estimating is not an exact science. Knowledge of construction, common
sense, and judgment are required. Experienced estimators agree that the proce
dures used for estimating vary from company to company, and even among indi
viduals within a company. Although there are variations, fundamental concepts
that are universally applicable do exist. The information contained in this book
presents the fundamental concepts to assist the reader in understanding the esti
mating process.
In preparing this fifth edition, the author has retained the fundamental con
cepts of estimating that have made this book successful. Numerous example
problems have been added to illustrate new construction methods and the vari
ous techniques of preparing cost estimates. Throughout the book, the example
problems are presented in a consistent format, beginning with quantities of
materials and production rates through pricing of labor, material, and equipment.
Many of the chapters have extensive revisions. The Conceptual Cost
Estimating chapter has been expanded with additional emphasis on preparing
early estimates. The Highways and Pavements chapter has been completely
rewritten to include modem equipment and illustrative examples of preparing
cost estimates for asphalt and concrete pavements.
This revised edition of the book has three new chapters: Bid Documents,
Estimating Process, and Computer Estimating. The reader is introduced to those
aspects of the contract document that specifically apply to preparing estimates.
The new chapter on Estimating Process presents the total estimating process,
including development of cost databases, establishment of estimating proce
dures, and retrieving costs from completed projects for use in preparing future
estimates. A discussion of assessing and assigning contingency is also covered
in this chapter.
x iii
x iv Preface
ESTIMATING
Estimating is not an exact science. Knowledge of construction, common sense,
and judgment are required. Estimating material costs can be accomplished with
a relatively high degree of accuracy. However, accurate estimating of labor and
equipment costs is considerably more difficult to accomplish.
Estimating material costs is a relatively simple and easy task. The quantity
of materials for a particular job can be accurately calculated from the dimensions
on the drawings for that particular job. After the quantity of material is calcu
lated, the estimator can obtain current unit prices from the supplier and then mul
Chapter 1 Introduction
tiply the quantity of material by the current unit price to estimate the cost of
materials. Applying a percentage for material waste is the only adjustment of the
material cost that may require judgment of the estimator.
Estimating labor and equipment costs is considerably more difficult than
estimating material costs. The cost of labor and equipment depends on produc
tivity rates, which can vary substantially from one job to another. The estimator
and his or her team should evaluate the job conditions for each job and use their
judgment and knowledge of construction operations. The skill of the laborers,
job conditions, quality of supervision, and many other factors affect the produc
tivity of labor. The wage rate of laborers can be determined with relative accu
racy. Also, the quantity of work required by laborers can be determined from the
plans and specifications for a job. However, the estimator must use his or her
judgment and knowledge about the job to determine the expected productivity
rate of laborers. Likewise, the estimator’s judgment and knowledge of equip
ment and job conditions are required to determine the expected equipment pro
ductivity rate.
PURPOSE OF ESTIMATING
The purpose of estimating is to determine the forecast costs required to complete
a project in accordance with the contract plans and specifications. For any given
project, the estimator can determine with reasonable accuracy the direct costs for
materials, labor, and equipment. The bid price can then be determined by adding
to the direct cost the costs for overhead (indirect costs required to build the proj
ect), contingencies (costs for any potential unforeseen work), and profit (cost for
compensation for performing the work). The bid price of a project should be
high enough to enable the contractor to complete the project with a reasonable
profit, yet low enough to be within the owner’s budget.
Estimating Construction Costs
There are two distinct tasks in estimating: determining the probable real cost
and determining the probable real time to build a project. With an increased
emphasis on project planning and scheduling, the estimator is often requested to
provide production rates, crew sizes, equipment spreads, and the estimated time
required to perform individual work items. This information, combined with
costs, allows an integration of the estimating and scheduling functions of con
struction project management.
Because construction estimates are prepared before a project is constructed,
the estimate is, at best, a close approximation of the actual costs. The true cost
of the project will not be known until the project has been completed and all
costs have been recorded. Thus, the estimator does not establish the cost of a
project: he or she simply establishes the amount of money the contractor will
receive for constructing the project.
TYPES OF ESTIMATES
There are many estimates and re-estimates for a project, based on the stage of
project development. Estimates are performed throughout the life of a project,
beginning with the first estimate and extending through the various phases of
design and into construction, as shown in Fig. 1.1. Initial cost estimates form the
basis to which all future estimates are compared. Future estimates are often
expected to agree with (i.e., be equal to or less than) the initial estimates.
However, too often the final project costs exceed the initial estimates.
Although each project is unique, generally three parties are involved: the
owner, the designer, and the contractor. Each has responsibility for estimating
costs during various phases of the project. Early in a project, prior to the design,
the prospective owner may wish to know the approximate cost of a project
before making a decision to construct it. As the design of the project progresses,
the designer must determine the costs of various design alternatives to finalize
the design to satisfy the owner’s budget and desired use of the project. The con
tractor must know the cost required to perform all work in accordance with the
final contract documents, and the plans and specifications.
Cost estimates can be divided into at least two different types, depending on
the purposes for which they are prepared and the amount of information known
when the estimates are prepared. There are approximate estimates (sometimes
Chapter 1 Introduction
APPROXIMATE ESTIMATES
The prospective owner of a project establishes the budget for a project. For
example, a government agency will need to know the approximate cost before
holding a bond election, or it may need to know the approximate cost to ensure
that the cost of a project does not exceed the funds appropriated during a fiscal
year. The prospective owner of a private construction project will generally con
duct a feasibility study during the developmental phase of a project. As a part of
the study, an economic analysis is undertaken to compare the cost of construc
tion with potential earnings that can be obtained upon completion of the project.
Privately owned utility companies, and other types of multiple-builder owners,
prepare annual construction budgets for all projects proposed during a fiscal
year. An approximate estimate is sufficiently accurate for these purposes.
The designer of a project must determine the costs of various design alterna
tives to obtain an economical design that meets the owner’s budget. An architect
may reduce a building to square feet of area, or cubic feet of volume, and then
multiply the number of units by the estimated cost per unit. An engineer may
multiply the number of cubic yards of concrete in a structure by the estimated cost
per cubic yard to determine the probable cost of the project. Considerable expe
rience and judgment are required to obtain a dependable approximate estimate for
the cost, because the estimator must adjust the unit costs resulting from the
Estimating Construction Costs
DETAILED ESTIMATES
A detailed estimate of the cost of a project is prepared by determining the costs
of materials, labor, equipment, subcontract work, overhead, and profit.
Contractors prepare detailed estimates from a complete set of contract docu
ments prior to submission of the bid or formal proposal to the owner. The
detailed estimate is important to both the owner and the contractor because it
represents the bid price—the amount of money the owner must pay for comple
tion of the project and the amount of money the contractor will receive for build
ing the project.
The preparation of the detailed estimate generally follows a systematic proce
dure that has been developed by the contractor for his or her unique construction
operations. The process begins with a thorough review of the complete set of con
tract documents—the bidding and contract requirements, drawings, and technical
specifications. It is also desirable to visit the proposed project site to observe fac
tors that can influence the cost of construction, such as available space for storage
of materials, control of traffic, security, and existing underground utilities.
The compilation of costs begins with a well-organized checklist of all work
items necessary to construct the project. The estimator prepares a material quan
tity takeoff of all materials from the drawings. This involves tabulating the quan
tity and unit of measure of all work required during construction. Upon comple
tion of the quantity takeoff, an extension of prices is performed. The quantity of
material multiplied by the unit cost of the material yields the material cost. The
quantity of work required of equipment is divided by the equipment production
rate and then multiplied by the unit cost of equipment to obtain the total cost of
equipment. Similarly, dividing the quantity of work required for labor by the
Chapter 1 Introduction
labor production rate and then multiplying by the unit cost of labor obtains the
cost of labor.
For many projects, a significant amount of work is performed by subcon
tractors who specialize in a particular type of work. For building type projects,
examples include clearing, drywall, painting, and roofing contractors. For
heavy/highway type projects, examples of subcontract work include guardrails,
striping, signs, and fences. The estimator provides a set of drawings and speci
fications to potential subcontractors and requests a bid from them for their par
ticular work. Subcontractors and suppliers normally quote the cost of their work
by e-mail, fax, or phone just prior to final submission of the bid.
The direct cost of a project includes material, labor, equipment, and sub
contractor costs. Upon completion of the estimate of direct costs, the estimator
must determine the indirect costs of taxes, bonds, insurance, and overhead
required to complete the project. Taxes on labor and materials vary, depending
on geographic locations. Bond requirements are defined in the specifications for
the project. Examples include bid bonds, material and labor payment bonds, and
performance bonds. Insurance requirements are also defined in the contract bid
documents. Examples include workmen’s compensation, contractor’s public lia
bility and property damage, and contractor’s builders risk insurance. The base
estimate is the total of direct and indirect costs.
A risk analysis of uncertainties is conducted to determine an appropriate
contingency to be added to the base estimate. Regardless of the effort and
amount of detailed estimating of a project, there is almost always some unfore
seen work that develops during construction. Caution must be used in assigning
contingency to an estimate. A contingency that is too low might reduce the prof
its in a project, while a contingency that is too high may prevent the bid from
being competitive.
Upon calculation of the direct and indirect costs, analysis of risk, and assign
ment of contingency, a profit is added to the estimate to establish the bid price.
The amount of profit can vary considerably, depending on numerous factors,
such as the size and complexity of the project, amount of work in progress by
the contractor, accuracy and completeness of the bid documents, competition for
work, availability of money, and volume of construction activity in the project
area. The profit may be as low as 5 percent for large projects or as high as 30
percent for small projects that are high risks or remodels of existing projects.
Table 1.2 lists the steps required to compile a detailed estimate for a project.
ORGANIZATION OF ESTIMATES
A comprehensive and well-defined organization of work items is essential to the
preparation of an estimate for any project. Each contractor develops her or his
own procedures to compile the cost of construction for the type of work the
company performs. The contractor’s system of estimating and use of forms
develop over years of experience in that type of w ork.,
Estimating Construction Costs
1. Review the scope o f project. Consider the effect of location, security, traffic, available storage
space, underground utilities, method of payment, etc. on costs.
2. Determine quantities. Perform a material quantity takeoff for all work items in the project, and
record the quantity and unit of measure for each item.
3. Obtain suppliers' bids. Receive and tabulate the cost of each supplier on the project.
4. Price material. Extend material costs:
5. Price labor. Based on probable labor production rates and crew sizes, determine labor costs:
6. Price equipment. Based on probable equipment production rates and equipment spreads,
determine equipment costs:
7. Obtain specialty contractors' bids. Receive and tabulate the cost for each specialty contractor
on the project.
8. Calculate taxes, bonds, insurance, and overhead. Tabulate the costs of material and labor
taxes, bonds, insurance, and job overhead.
9. Contingency and markup. Add costs for potential unforeseen work based on the amount of
risk.
10. Profit. Add costs for compensation for performing the work in accordance with the bid
documents.
Two basic approaches have evolved to organize work items for estimating.
One approach is to identify work by the categories contained in the project’s
written specifications, such as those of the Construction Specification Institute
(CSI) for building construction projects. The other approach uses a work break
down structure (WBS) to identify work items by their location on the project.
T A B L E 1 .3 I Example of building construction project bid summary using the CSI format.
HEAVY ENGINEERING
CONSTRUCTION PROJECTS
Heavy engineering construction contractors generally organize their estimates in
a WBS unique to the project to be constructed. An example of the WBS orga
nization of an estimate for an electric power construction project is illustrated in
10 Estimating Construction Costs
Tables 1.5 to 1.7. Major areas of the project are defined by groups: switch sta
tion, transmission lines, substations, etc., as shown in Table 1.5. Each group is
subdivided into divisions of work required to construct the group. For example,
Table 1 . 6 provides a work breakdown for all the division of work required to
construct group 2100, transmission line A: steel fabrication, tower foundations,
steel erection, etc. Each division is further broken down into components of
work required to construct each division. For example, Table 1.7 provides a
work breakdown for all the components of work required to construct division
2370, tower foundations: drilling, reinforcing steel, foundation concrete, and
stub angles. The WBS provides a systematic organization of all the information
necessary to derive an estimate for the project.
TA B LE 1.5 I Example of electric power construction bid summary using the WBS organization of work
group-level report for total project.
Labor and
No. Group Material Equipment Subcontract Total
1100 Switch station $1,257,295 $ 323,521 $3,548,343 $ 5,126,167
2100 Transmission line A 3,381,625 1,260,837 0 4,641,462
2300 Transmission line B 1,744,395 0 614,740 2,358,135
3100 Substation at Spring Creek 572,874 116,403 1,860,355 2,549,632
4200 Distribution line A 403,297 54,273 215,040 672,610
4400 Distribution line B 227,599 8,675 102,387 427,661
4500 Distribution line C 398,463 21,498 113,547 532,508
Total for project $7,985,548 + $1,872,215 + $6,453,412 $16,311,175
QUANTITY TAKEOFF
To prepare an estimate the estimator reviews the plans and specifications and
performs a quantity takeoff to determine the type and amount of work required
to build the project. Before starting the quantity takeoff, the estimator must
know how the project is to be constructed and he or she prepares a well-organized
checklist of all items required to construct the project.
The quantity of material in a project can be accurately determined from the
drawings. The estimator must review each sheet of the drawings, calculate the
quantity of material, and record the amount and unit of measure on the appro
priate line item in the estimate. The unit costs of different material should be
obtained from material suppliers and used as the basis of estimating the costs of
materials for the project. If the prices quoted for materials do not include deliv
ery, the estimator must include appropriate costs for transporting materials to the
project. The cost of taxes on materials should be added to the total cost of all
materials at the end of the estimate.
Each estimator must develop a system of quantity takeoff that ensures that
a quantity is not omitted or calculated twice. A common error in estimating is
completely omitting an item or counting an item twice. A well-organized check
list of work will help reduce the chances of omitting an item. A careful recheck
of the quantity calculations will detect those items that might be counted twice.
The estimator must also add an appropriate percentage for waste for those items
where waste is likely to occur during construction. For example, a 5 percent
waste might be added to the volume of mortar that is calculated for bricklaying.
The material quantity takeoff is extremely important for cost estimating
because it often establishes the quantity and unit of measure for the costs of
labor and the contractor’s equipment. For example, the quantity of concrete
material for piers might be calculated as 20,000 cubic yards (cy). The labor-
hours and the cost of labor required to place the concrete would also be based
on 20,000 cy of material. Also the number and the cost of the contractor’s equip
ment that would be required to install the concrete would be based on 2 0 , 0 0 0 cy
of material. Therefore, the estimator must carefully and accurately calculate the
quantity and unit of measure of all material in the project.
Estimating Construction Costs
The paving work can be subdivided into three categories: main line paving,
short run paving, curbs and gutters, and handwork paving. For each of these sub
divisions a different crew and equipment spread would be required. Table 1.9
shows a typical crew and equipment mix for asphalt work in an urban area, and
Table 1.10 shows a typical crew and equipment mix for a curb and gutter con
crete paving crew.
CHECKLIST OF OPERATIONS
To prepare an estimate, an estimator should use a checklist that includes all the
operations necessary to construct the project. Before completing an estimate,
Chapter 1 Introduction
Labor Labor
Supervisor Supervisor
Paving machine operator Concrete finisher—three total
Screed operator Concrete finisher helper
Steel wheel roller operator Form setter— stringline setter
Asphalt raker Form setter—stringline setter helper
Asphalt laborer Laborer
Asphalt distributor operator Equipment
Traffic flag person Supervisor’s pickup
Equipment Flatbed truck and hand tools
Supervisor's pickup Small tool storage van
Service truck and hand tools Slipform curb and gutter machine
Asphalt paver Miscellaneous steel forms/stringline equipment
Asphalt roller Concrete saw/cure spray machine
Asphalt distributor truck Air compressor
Front-end loader/box blade tractor Small tractor
Self-propelled sweeper
one should check this list to be sure that no operations have been omitted. The
CSI master format provides a uniform approach for organizing project informa
tion for building projects. Tables 1.3 and 1.4 illustrate the cost summary of an
estimate following the CSI format.
It is desirable for the operations to appear, as nearly as possible, in the same
order in which they will be performed during construction of the project. Other
checklists, serving the same purpose, should be prepared for projects involving
highways, water systems, sewerage systems, etc.
The checklist can be used to summarize the costs of a project by providing
a space for entering the cost of each operation, as illustrated in Tables 1.3 to 1.7.
A suitable symbol should be used to show no cost for those operations that are
not required. The total cost should include the costs for material, equipment, and
labor for the particular operation, as determined in the detailed estimate.
BID DOCUMENTS
The end result of the design process is the production of a set of bid documents
for the project to be constructed. These documents contain all the drawings and
written specifications required for preparing the estimate and submitting the bid.
Written specifications can be divided into two general parts: one part addresses
the legal aspects between the owner and contractor, while the other part
addresses the technical requirements of the project. The legal part of the written
specifications contains at least four items that are important to the estimator:
procedures for receipt and opening of bids, qualifications required of bidders,
owner’s bid forms, and bonds and insurance required for the project. Bid docu
ments are discussed further in Chapter 2.
Estimating Construction Costs
OVERHEAD
The overhead costs chargeable to a project involve many items that cannot be
classified as permanent materials, construction equipment, or labor. Some firms
divide overhead into two categories: job overhead and general overhead.
Job overhead includes costs that can be charged specifically to a project.
These costs are the salaries of the project superintendent and other staff person
nel and the costs of utilities, supplies, engineering, tests, drawings, rentals, per
mits, insurance, etc., that can be charged directly to the project.
General overhead is a share of the costs incurred at the general office of the
company. These costs include salaries, office rent, permits, insurance, taxes, shops
and yards, and other company expenses not chargeable to a specific project.
Some contractors follow the practice of multiplying the direct costs of a
project, materials, equipment, and labor by an assumed percentage to determine
the probable cost of overhead. Although this method gives quick results, it may
not be sufficiently accurate for most estimates.
While it is possible to estimate the cost of job overhead for a given project,
it is usually not possible to estimate accurately the cost of general overhead
chargeable to a project. Since the cost of general overhead is incurred in operat
ing all the projects constructed by a contractor, it is reasonable to charge a por
tion of this cost to each project. The actual amount charged may be based on the
duration of the project, the amount of the contract, or a combination of the two.
Chapter 1 Introduction 15
EXAMPLE 1.1
This example illustrates a method of determining the amount of general overhead
chargeable to a given project.
Average annual value of all construction = $6,000,000
Average annual cost of general overhead = 240,000
$240,000 x 100
= 4% of total project cost
$ 6 ,000,000
MATERIAL TAXES
After the direct costs for materials and labor have been determined, the estima
tor must include the applicable taxes for each. The tax rate for materials will
vary depending on the location. Generally a 3 percent state tax and a 2 to 3 per
cent city or county tax are assessed on materials. Therefore the tax on materials
will range from 3 to 6 percent. It is the responsibility of the estimator to include
the appropriate amount of tax in the summary of the estimate.
Some states and cities charge a tax on the value of equipment used on the
project. It is necessary for the estimator to obtain information on required taxes
for the particular location where the project is to be constructed.
Some owners, such as churches and schools, are tax exempt provided the
owner makes the purchase of material. Thus, the owner may wish to purchase
all materials and equipment that will be permanently installed in the project by
the contractor. For this situation, the contract documents will have a section that
describes how the owner will issue purchase orders for payment by the owner.
LABOR TAXES
There are two basic type of taxes on labor. The federal government requires a
7.65 percent tax on all wages up to $76,000 per year. In addition, an unemploy
ment tax of approximately 3 percent may be required. Therefore, the total tax on
labor is approximately 11 percent. The estimator must determine the appropri
ate tax on labor and include that amount in the summary of the estimate. A dis
cussion of labor costs is presented in Chapter 5.
Each state has laws and regulations that govern workmen’s compensation
insurance. The cost also varies, depending on the type of work that is performed
by each worker and by geographic location within the state. The cost for this
insurance can range from 10 to 30 percent of the base cost of labor.
LABOR BURDEN
The term labor burden refers to the combined cost of labor taxes and insurance
that a contractor must pay for workers. Some contractors multiply the base cost
of labor by a certain percentage to estimate the total cost of labor. The total labor
burden for construction labor generally ranges from 25 to 35 percent.
BONDS
Generally bidders are required to submit bonds as qualifications for submitting
a bid for a project. To provide financial and legal protection for the owner, the
contractor secures bonds from a surety company on behalf of the owner. Thus,
bonding is a three-party arrangement. It is issued by the security company, paid
by the contractor, for the protection of the owner.
Three types of bonds are commonly required in construction contracts: bid
bond, performance bond, and payment bond. The bid bond ensures the owner
that the contractor will sign the contract for the bid amount. The performance
bond ensures the owner that the contractor will perform all work in accordance
with the contract documents. The payment bond ensures the owner that all mate
rial and labor will be paid. If the contractor defaults, the bonding company
agrees to fulfill the contract agreement.
The purchase cost of bonds depends on the total bid price and the success of
the contractor in completing previous jobs. Chapter 2 provides further informa
tion on bonds and the estimating process.
INSURANCE
There are many risks involved in construction. Many types of insurance are
available for protection to contractors, employees, subcontractors, and the gen
eral public. The two most common types of insurance that are secured by the
contractor are basic builder’s risk, which covers the project that is being con
structed, and public liability and property damage, which covers actions of the
contractor’s employees while performing their work at the jobsite.
Basic builder’s risk insurance affords a contractor protection against loss
resulting from fire and lightning damage during the period of construction.
Public liability and property damage insurance protects the contractor against
injuries to the general public or public property due to actions of the employees
while performing work during construction.
Chapter 2 provides a detailed discussion of insurance costs that should be
included in preparing an estimate.
Chapter 1 Introduction
REPRESENTATIVE ESTIMATES
Numerous examples of estimates are presented in this book to illustrate the steps
to follow in determining the probable cost of the project. Nominal amounts are
included for overhead and profit in some instances to give examples of complete
estimates for bid purposes. In other instances, only the costs of materials, con
struction equipment, and labor are included. The latter three costs are referred to
as direct costs. They represent the most difficult costs to estimate, and they are
our primary concern.
In preparing the sample estimate, unit prices for materials, equipment, and
labor are used primarily to show how an estimate is prepared. Note that these
unit costs will vary with the time and location of a project. An estimator must
obtain and use unit prices that are correct for the particular project. Estimators
do not establish prices; they simply use them.
Remember that estimating is not an exact science. Experience, judgment,
and care should enable an estimator to prepare an estimate that will reasonably
approximate the ultimate cost of the project.
In a similar manner, the time and cost for the truck drivers are:
The terms “64 truck-hours” and “64 labor-hours” can be shortened to read 64 hr
without producing ambiguity.
PRODUCTION RATES
To determine the time required to perform a given quantity of work, it is neces
sary to estimate the probable rates of production of the equipment or labor.
These rates are subject to considerable variation, depending on the difficulty of
the work, skill of the laborer, job and management conditions, and the condition
of the equipment.
Estimating Construction Costs
COMPUTER APPLICATIONS
An estimator must assemble a large amount of information in an organized man
ner and perform numerous calculations to prepare a cost estimate. The estima
tor can use the computer to organize, store, and retrieve information and to per
form the many calculations necessary to prepare an estimate. It can be an
effective tool for decreasing preparation time and increasing the accuracy of cost
estimating.
The computer is used for estimating in at least five different applications:
quantity takeoff, price extensions and bid summary, historical cost database,
labor and equipment productivity database, and supplier database. Each appli
cation can be subdivided and should be linked together in an overall, integrated
system.
Chapter 1 Introduction
a contractor’s operation. Common cost codes can be used for each operation
to integrate, automate, and standardize the operations of a construction firm.
Chapter 25 presents a comprehensive discussion of computer estimating.
The CD-ROM included with this book has tutorial and example problems that
enable the reader to gain knowledge and experience in computer methods for
estimating.
-80 Add-ons
-811 Contingency 5% X $86,277 $4,314
-812 Profit 10% X $86,277 $8,628
Subtotal of add-ons $12,942
22
C hapter 2 Bid Documents
CONTRACT REQUIREMENTS
The contracting requirements section includes the contract agreements, require
ments of bonds and certificates, general and supplementary conditions, and
addenda. Each of these items must be included in the final estimate and subse
quent bid that is submitted to the owner.
The agreement is the actual contract that will be awarded to the contractor
and signed by the owner and contractor. Contracts are awarded to the contractor
from the owner by either competitive bidding or negotiation. Most municipal,
state, and federal projects are awarded by competitive bidding. This process
involves an advertisement for bids in the public media with an announced bid
opening date. Bid opening is performed in the open public. The contractor per
forms a detailed estimate and submits a bid price for building the project in
accordance with the contract documents. The engineer and owner perform the
evaluation of bids at a later date, then a final decision is made to award the con
tract. Most government agencies are required by law to award the contract to the
lowest bidder, provided all conditions of the contract have been met. Private
owners are not required to award the contract to the lowest bidder, but may
select the contractor deemed most desirable for the project.
Negotiated contracts are awarded to a contractor independent of the com
petitive bidding process. The owner, or agent of the owner, reviews the plans
and specifications with various contractors. Each contractor prepares a cost esti
mate and quotes the price to perform the various work in the project.
Adjustments in the scope of work, schedule, and cost of the project are negoti
ated to satisfy both the owner and contractor. Award of the contract is then made
to the contractor the owner feels can provide the best total performance, which
may or may not be lowest initial cost.
ARRANGEMENT OF
CONTRACT DOCUMENTS
Contract documents for construction projects consist of two general categories:
information related to business/legal matters and information related to techni
cal matters. Illustrative examples of the business/legal portions of the contract
documents are invitation to bid, instruction to bidders, information available to
bidders, bid forms, bond and insurance requirements, general conditions, and
supplementary conditions of the contract.
The technical portion of the bid documents consists of the plans (drawings)
and written specifications that describe the material, workmanship, and methods
of construction that are required to build the project. It is practically impossible
to describe by words alone how a project is to be built. The drawings are the pic
torial directory of how the project is to be built. To further clarify the quality of
Estimating Construction Costs
1 1 —Equipment
1 2 —Furnishings
13—Special Construction
14— Conveying Systems
15—Mechanical
16— Electrical
The introductory information of CSI Division 0 enables the estimating team
to understand the overall content and arrangement of the contract documents and
specific information applicable to the estimator. Division 0 is divided into three
Chapter 2 Bid Documents
HEAVY/HIGHWAY SPECIFICATIONS
For heavy/highway projects the technical specifications are standard for each
state department of transportation. Thus, all highway construction projects within
a state will use the same standard set of technical specifications. Typical arrange
ment of standard specifications for highway projects include these divisions:
1—General Provisions: general information, definition, and terms
2—Excavation and Embankment: soils, sodding
3—Base Courses: aggregate, lime, fly ash, subbases
4— Surfaces Courses: bituminous and concrete pavements
5—Structures: concrete, steel, and timber bridges and foundations
6 —Materials: aggregate, asphalt, concrete, conduits, testing
BIDDING REQUIREMENTS
The information contained in this section of the contract documents is extremely
important to the estimating team. Typical information in the bidding require
ments includes:
Bid Solicitation
Instructions to Bidders
Information Available to Bidders
Bid Forms and Supplements
Bidding Addenda
Estimating Construction Costs
Bid Solicitation
The bid solicitation, sometimes called the invitation to bid, contains the date and
time that bids must be submitted. The estimator must establish a plan to com
plete all work to meet the deadline of the bid date, otherwise the bid will be dis
qualified. The bid solicitation also gives the names and addresses of the owner
and design organization, with instructions on how to obtain the bid documents.
Table 2.1 lists typical items in the invitation to bidders. Figure 2.1 is an exam
ple bid solicitation.
Instructions to Bidders
The instructions to bidders section describes vital information that is required to
submit a bid. For example, bidders may be required to attend a prebid confer
ence. Another example that may appear in the instructions to bidders is a state
ment that the contractor must make provisions during execution of the contract
documents to allow the owner to take advantage of the owner’s tax exempt sta
tus for materials and equipment purchased for the project. Thus, no taxes would
be applied during preparation of the estimate. Early in the estimating process the
estimating team must become thoroughly aware of the requirements that are
placed on preparing the bid in accordance with the contract documents. Table
2 . 2 lists typical information in the instructions to bidders.
OWNER
BID SUBMISSION:
Each bid must be submitted in a sealed envelope bearing on the outside the name of the bidder, his
address, and the name of the project for which the bid is submitted, and addressed as specified in the Bid
Form.
SUB-CONTRACT:
Any person, firm, or other party to whom it is proposed to award a subcontract under this contract must
be acceptable to the Owner.
WITHDRAWAL OF BIDS:
Bids may be withdrawn on written or telegraphic or facsimile request received from bidders prior to the
time fixed for opening. Negligence on the part of the bidder in preparing the bid confers no right for the
withdrawal of the bid after it has been opened.
BASIS OF BID:
The bidder must include all unit cost items and all alternatives shown on the Bid Forms; failure to
comply may be cause for rejection. No segregated bids or assignments will be considered.
QUALIFICATION OF BIDDER:
The Owner may make such investigation as he deems necessary to determine the ability of the bidder to
perform the work, and the bidder shall furnish to the Owner all such information and data for this
purpose as the Owner may request.
TIME OF COMPLETION:
Bidder must agree to commence work on or before a date to be specified in a written “Notice to
Proceed” of the Owner and to substantially complete the project within 180 consecutive calendar days
thereafter.
OBLIGATION OF BIDDER:
At the time of the opening of bids, each bidder will be presumed to have inspected the site and to have
read and to be thoroughly familiar with the plans and contract documents (including all addenda).
Bid Forms
The bid form defines the format that is required for submission of the bid. The
format of the bid form impacts the assembly and summary of costs in the final
C hapter 2 Bid Documents
estimate. The owner may request the bid as a single lump sum, unit prices based
on predefined pay quantities in the bid documents, or a combination of both
lump and unit prices. For construction projects, the work may be priced by sev
eral methods: lump sum, unit price, cost plus a fixed fee or cost plus a percent
age of construction, cost plus a guaranteed maximum price, or a combination of
these pricing methods. The method selected depends on the distribution of risk
between the owner and contractors.
Bid form for lump-sum contracts For projects where a complete set of plans
and specifications have been prepared prior to construction and the quantity of
work is well defined, the estimate is normally prepared for the purpose of sub
mitting a lump-sum bid on the project. Building type projects are usually bid on
a lump-sum basis. When the cost of a project is estimated on this basis, only one
final total-cost figure is quoted. Unless there are changes in the plans or specifi
cations, this figure represents the amount that the owner will pay to the contrac
tor for the completed project. Since the contractor provides the lump-sum price
before construction starts, he or she is exposed to uncertainties during construc
tion and thereby assumes risk for the project.
It is common practice for projects to have one or more “alternates” attached
to the bid documents of lump-sum contracts. The alternate may be to add or
deduct a work item from the base lump-sum bid. This allows the owner the
option of selecting the number of alternates so that the total bid cost will be
within the amount specified by the owner’s budget.
A lump-sum estimate must include the cost of all materials, labor, equip
ment, overhead, taxes, bonds, insurance, and profit. It is desirable to estimate the
costs of materials, labor, and equipment separately for each operation; to obtain
a subtotal of these costs for the entire project; and then to estimate the cost of
overhead, taxes, bonds, insurance, and profit.
For a building type project the bid form consists of a page in the specifica
tions for bidders to record the total bid amount. If numerous alternates are in the
bid documents, the base bid is recorded and the bid price for alternates is listed
separately. Figure 2.3 is an example bid form for a building type project with
one alternate.
PROPOSAL OF __________________________________________________________________________
(hereinafter called “Bidder”)
Gentlemen:
The bidder, in compliance with your invitation for Bids for the:
having examined the plans and specifications with related documents and the site of the proposed work,
and being familiar with all of the conditions surrounding the work, including the availability of materials
and labor, hereby agree to furnish all labor, materials, equipment, and supplies, and to perform the work
required by the project in accordance with the contract documents, within the time set forth in
Instructions to Bidders, and at the prices stated below. These prices are to cover all expenses incurred in
performing the work required by the contract documents, of which this bid is a part.
All Bid amounts shall be shown in both WORDS and FIGURES. In case of discrepancy, the amount
shown in words will govern.
BASE BID:
Bidder agrees to perform all of the work described in the plans and specifications as being in the Base
Bid for the sum of:_____________ Dollars.
$ _______________
The Bidder agrees to perform all of the work described in the Drawings and Specifications, which has
been designated as Alternate Bids. Alternate Bids shall be add amounts to the Base Bid. Changes shall
include any modifications of the work or additional work that the Bidder may require to perform by
reason of Owner’s acceptance of any or all Alternate Bids.
ALTERNATE NO. 1 :
Add 3" thick Type “C” asphalt paving to compacted crushed limestone as shown on Sheet C -l.
ADD:____________________ Dollars $__________________.
The Bidder hereby agrees to commence work under this contract on or before a date to be specified in a
written “Notice to Proceed” by the Owner and to substantially complete the project within 180
consecutive calendar days thereafter. The Owner reserves the right to reject any and all bids. Bidder
agrees that this bid shall be good and shall not be withdrawn for a period of sixty (60) calendar days
after the opening thereof.
In the event a contract is awarded by the Owner to the Successful Bidder, it shall be executed within
thirty (30) days. The Bidder shall return with his executed contract the Performance Payment Bond,
Statutory Bond, and Warranty Bond as required by the Supplementary Conditions.
completed. Thus, the owner assumes the risk for uncertainty in the actual quan
tity of work.
The cost per unit, submitted in a bid, includes the furnishing of materials,
labor, equipment, supervision, insurance, taxes, profit, and bonds, as required,
for completely installing a unit. Typical designated units include square yards
(sy), cubic yards (cy), linear feet (lin ft) or feet (ft), tons, acres, etc. A separate
estimate should be prepared for each type or size of unit.
The costs of materials, equipment, and labor are determined for each unit.
These are called direct costs. To these costs must be added a proportionate part
of the indirect costs, such as moving in, temporary construction, overhead, insur
ance, taxes, profit, and bonds, since indirect costs are not bid separately.
Figure 2.4 is an example bid form for a unit-price highway project. The esti
mator must carefully check the pay quantities to ensure that they are accurate.
The list of bid items is crucial to the estimator because the contractor will be
paid only for work that is specified in this list of pay quantities.
During preparation of the estimate, the contractor must place all costs in the
pay quantity list. If an item of work required to complete the project is not on
the bid list, such as traffic control or laboratory testing, then the estimator must
include the cost for this work in one of the other unit-cost bid items. Thus, the
bid form is important to the contractor because it impacts the preparation and
Estimating Construction Costs
summarization of the cost estimate. This part of the specifications impacts the
requirements of summarizing the estimate in an acceptable format for submis
sion of the bid to the owner.
NEGOTIATED WORK
Sometimes the owner will negotiate the work for a project with a construction
firm prior to completion of a set of plans and specifications. This is usually done
when the owner wants to start construction at the earliest possible date to bene
fit from an early completion and use of the project. A representative of the owner
works with the contractor to evaluate alternatives to obtain a project configura
tion that meets the needs of the owner, yet with a cost within the owner’s allow
able budget.
The final contract agreement usually is a cost plus a fixed fee with a guar
anteed maximum amount. If the cost is above or below the guaranteed maximum
amount, then the owner and the contractor agree to a splitting of the difference.
For example, the contractor might incur 70 percent and the owner 30 percent of
the amount that exceeds the guaranteed maximum price, or the contractor may
receive 60 percent and the owner 40 percent of the amount that is below the
guaranteed maximum price.
ADDENDUM
An addendum is a change in the contract documents during the bidding process,
before award of the contract. An addendum is sometimes called a bulletin.
Typically addenda are issued to correct errors in the contract documents or clar
ify an issue, or it may concern addition to the work at the request of the owner.
The estimate and resulting bid must include all costs required to complete the
work in accordance with the drawings and specifications, together with all of the
addenda. Therefore, the estimating team must be certain that the costs of all
addenda are included in the estimate.
ALTERNATES
An alternate is an addition or subtraction to a base bid price for substitutions
requested by the owner during the bidding process. Each alternate is listed and
numbered separately in the bid documents. For example, an Alternate No. 1 may
be add the parking lot and Alternate No. 2 may be deduct the sidewalks.
CHANGE ORDER
A change order is issued by the designer, but signed by the owner and contrac
tor, to make a change in the contract documents during construction. Although
change orders usually add time and cost to the original contract, some change
orders are issued without extensions of time or changes in cost. Upon approval
by the owner, change orders become a part of the contract documents.
Chapter 2 Bid Documents
WARRANTIES
Warranties are guarantees by the contractor that specific components of the proj
ect will be free from defects due to materials or workmanship for a specified
warranty period. Warranties cover specific items, such as a roofing warranty or
an equipment warranty, that are part of the construction project. The type of war
ranty and warranty period are defined in the written specifications of the con
tract documents.
BONDS
Most owners require prospective bidders to submit bonds as qualifications for
submitting a bid for a project. The bonding company that issues the bond
requires the contractor to show financial stability and previous experience in
performing the type of work that is required to build the project. In addition, it
is common practice for the owner to require all prospective bidders to be pre
qualified before submitting a bid. The prequalification process usually involves
a review of the prospective contractor’s financial and safety records and an eval
uation of performance on previous projects.
The contractor secures bonds from a bonding company on behalf of the
owner as financial and legal protection for the owner. Three types of bonds are
commonly required in construction contracts: bid bond, performance bond, and
payment bond. The bid bond ensures the owner that the contractor will sign the
contract for the bid amount. The performance bond ensures the owner that the
contractor will perform all work in accordance with the contract documents.
The payment bond ensures the owner that all material and labor will be paid. If
the contractor defaults, the bonding company agrees to fulfill the contract
agreement.
Bid Bond
It is common practice to require each bidder on a project to furnish with the bid
a bid bond, a cashier’s check, or a certified check in the amount equal to 5 to 20
percent of the amount of the bid. In the event that the contract to construct the
project is tendered to a bidder and the bidder refuses or fails to sign the contract,
the owner may retain the bond or check as liquidated damages.
Estimating Construction Costs
For some projects, cashier’s checks are specified instead of bid bonds. The
bidder purchases these checks, which are issued to the owner of the project by a
bank. They can be cashed easily, whereas it is necessary for the owner to secure
payment on a bid bond through the surety, and the surety may challenge the pay
ment. The use of cashier’s checks requires bidders to tie up considerable sums
of money for periods that may vary from a few days to several weeks in some
instances.
There is no uniform charge for cashier’s checks. Some banks charge $0.23
per $ 1 0 0 . 0 0 for small checks, with reduced rates for large checks, while others
make no charge for checks furnished for regular customers. However, the inter
est cost for a cashier’s check for $ 1 0 0 , 0 0 0 for 2 weeks at 6 percent interest will
amount to approximately $240.00.
Performance Bond
All government agencies and many private owners require a contractor to fur
nish a performance bond to last for the period of construction of a project. The
bond is furnished by an acceptable surety to ensure the owner that the work will
be performed by the contractor in accordance with the contract documents. In
the event a contractor fails to complete a project, it is the responsibility of the
surety to secure completion. Although the penalty under a performance bond is
specified as 25, 50, or 100 percent of the amount of the contract, the cost of the
bond usually is based on the amount of the contract and duration of the project.
The cost for a contractor to purchase a performance bond varies, depending
on the capacity of the contractor to perform the work and the financial stability
of the contractor. Representative costs of performance bonds per $1,000.00 are:
For buildings and similar projects:
First $ 500,000 = SI 4.40
Next $ 2 ,0 0 0 , 0 0 0 = 8.70
Next $2,500,000 = 6.90
Next $2,500,000 ....6.90
All over $7,500,000 - 5.75
For highways and engineering con;
First $ 500,000 = $ 1 2 . 0 0
Next $ 2 ,0 0 0 , 0 0 0 = 7.50
Next $2,500,000 = 5.75
Next $2,500,000 = 5.25
All over $7,500,000 4.80
to pay labor and material costs, the Surety company assumes that responsibility.
Typically, the performance bond and the material and labor payment bond are
secured by the contractor as a package.
INSURANCE
The contractor, as required in the contract documents, secures insurance. The
contractor supplies a certificate of insurance to verify insurance coverage. Due to
the many risks involved in construction, most contractors carry insurance in addi
tion to the requirements in the contract documents. The precise losses that are
reimbursable from insurance are based on predetermined losses named in the
insurance policy. Many types of insurance for construction projects are available.
Cost of premiums
per $ 10 0 .00 of value for
Type of construction basic builder’s risk
Framed construction $4,539
Joisted masonry $1,817
Noncombustible $0,626
safety record of the contractor. The cost can range from 2 to 8 percent of the base
cost of labor.
HEAVY/HIGHWAY DRAWINGS
The drawings for highway projects consist of plan and profile sheets, earthwork
cross sections, pavement cross sections, details, reinforcing steel schedules, and
any supplemental drawings that show the location, dimensions, and details of the
work to be performed.
Chapter 2 Bid Documents
The plan and profile sheets, combined with the earthwork cross sections,
provide a pictorial description of the three dimensions of the work to be per
formed. The top half of the plan and profile sheets show a vertical view looking
down on the highway project and the bottom half shows the corresponding hor
izontal view along the centerline of the highway. The cross section sheets show
horizontal views along the highway, perpendicular to the centerline of the high
way. The plan and profile sheets are arranged to show the project from the
beginning to the final station.
Cross sections of pavements show the width, thickness, and slope of the
paving surfaces. Details are views that show specific areas of the project.
1" Away
Overhead Door Slope Grade Away From From All Doors
.WEST ELEVATION Building at Minimum of \EAST ELEVATION
' SCALE: 3/32 5 I'-O’ 6" in 10’-0 " ) SCALE:3/32 0
= r- "
SEAL
HEPA Filter
San. Vent Exhaust Stack
(Typical)
BUILDING NO.
PROJECT NO.
WORK ORDER
'SOUTH ELEVATION
I SCALE: 3/32 = 1-0"
Plot: SCALE: 3/325 l'-0”
VPlojcctsVBuilding\Drawings\BOV-A-3.
#5 Bars Cont. Top and Bottom #5 Bars Cont. Top and Bottom
with #3 Strusses at 24" O.C. with #3 Strusses at 24" O.C.
Line Work
Several types of line work that are used in preparing drawings include:
Thick lines— outline edges of objects (plans and elevations)
Thin lines—denote lengths (dimension lines)
Long lines with short dashes— denote the centerline of an object
Phantom lines— show the path of moving parts
Broken lines—denote the object is longer than shown
Short dashed lines—denote edges on the object that cannot be seen from
the near side surface of the object
Scales
Usually the type of scale used is identified at the bottom of the page on the draw
ings. However, several different scales may be used on a single sheet. Therefore,
it is important to be certain that the correct scale is used in determining the quan
tities for estimating. Occasionally, a portion of the drawing is shown without any
scale. When this condition exists, there should be a note that states the drawing
is not to scale. The estimator must also be cautious because sometimes the draw
ings are reduced in size, such as a half-size drawing, to permit easier handling
during construction.
Two types of scales are used in construction drawings, the architect’s scale
and the engineer’s scale. The architect’s scales that are commonly used for plans
and elevations include 5 5 in. = 1 ft and 77; in. = 1 ft. Complicated areas often use
the 4 in. = 1 ft, or \ in. = 1 ft on the architect’s scale. Special applications that
require high details are I 5 in. = 1 ft, or 3 in. = 1 ft, or may be drawn to a half
or even a full scale.
The engineer’s scale, graduated in tenths of an inch, is often used for civil,
structural, and mechanical drawings. The scales are 10, 20, 30, 40, 50, and 60.
The higher numbers of 50 or 60 are used for large areas, such as site-work or
plot plans. Details of drawings often use the smaller numbers, such as 10, 20, or
30. The 40 on the engineer’s scale is equivalent to the \ in. on the architect’s
scale.
Schedules
To simplify the presentation of repetitious items (such as footings, columns,
doors, windows, room finishes, etc.) a schedule is frequently used. A schedule
is a tabular listing of the repetitive items in the project. For example, a room
schedule is a tabular list of all rooms in the structure, showing the type of floor
covering, wall covering, and type of ceiling. Likewise, a footing schedule is a
listing of all footings in the foundation, showing the diameter, depth, type, size,
42 Estimating Construction Costs
Wails
North East South West Ceiling
Room Description Floor Base Mat. Fin. Mat. Fin. Mat. Fin. Mat. Fin. Mat. Fin.
A Corridor VCT 4" VC Gyp Pt Gyp Pt Gyp Pt Ex Pt AC 8'-0"
B Office VCT 4" VC Gyp Pt Gyp Pt Gyp Pt Ex Pt AC 8'-0"
C Office VCT 4" VC Gyp Pt Gyp Pt Gyp Pt Ex Pt AC 8'-0"
D Office VCT 4" VC Gyp Pt Gyp Pt Gyp Pt Ex Pt AC 8'-0"
E Storage VCT 4" VC Gyp Pt Gyp Pt Gyp Pt Ex Pt Cone varies
F Storage VCT 4" VC Gyp Pt Gyp Pt Gyp Pt Ex Pt Ex Ex
G Corridor VCT 4" VC Gyp Pt Gyp Pt Gyp Pt Ex Pt Ex Ex
Abbreviations: VCT— 3/32" vinyl clay tile to match existing Pt— paint, latex
VC— vinyl cove base to match existing Ex— existing items
Gyp— 5/8" fire rated gypsum wall board Cone— concrete
AC— 2 ' x 4 ' lay-in acoustical ceiling tile
PROBLEMS
2.1 As discussed in this chapter, the bid document becomes a legal document when
the owner and contractor sign the contract agreement. Prepare a list of items that
are in the bid documents that are no longer applicable when the contract is
signed.
2.2 Obtain the standard specifications from two organizations: your local State
Department of Transportation and the Federal Highway Administration.
Compare the list of major divisions of these two organizations.
2.3 Review Division 0 of the Construction Specification Institute and prepare a list
of items for introductory information, bidding requirements, and contracting
requirements.
2.4 Secure copies and compare the general conditions to the contract from three
sources: the American Institute of Architects (AIA), the Associated General
Contractors (AGC), and the Engineers Joint Contract Documents Committee
(EJCDC).
2.5 Discuss problems that may arise during contract negotiations between the owner
and contractor when the contractor’s bid summary is by materials (such as con
crete, metals, etc.), rather than by completed facilities such as Building A,
Building B, Parking Lot, etc.
2.6 List problems that may occur for the owner during the bidding phase of a project
when the estimated pay quantities in a unit-price contract are lower than the
actual amount.
2.7 List problems that may occur for the contractor during construction when the
actual quantity of work is lower than the pay quantities in the bid documents.
Estimating Process
DECISION TO BID
Prior to starting the estimating process, upper management must assess the
desirability to bid the job. A contractor has to consider the investment of time
and money to prepare an estimate and compare that investment to the probabil
ity of winning the bid, the risks that may occur during construction, and the
potential of making a profit after the project is completed.
Numerous factors are considered in determining which projects to bid.
Contractors must determine whether or not the skills and availability of their
labor and equipment will match the requirements of the job to be bid. For a job
to be profitable, the contractor should have experience in building projects sim
ilar to the one being considered for bidding.
They must also assess the dollar amount of work currently under construc
tion by their company to ensure the amount of available bonding credit for bid
ding additional work. Thus, the contractor must consider the amount of work in
progress and the available bonding capacity, compared to the size of the project
that is being considered for bidding.
Other factors that play a role in determining which project to bid include
geographic location, complexity of the project, owner and designer’s reputation,
available working capital, and how much the contractor wants to expand their
construction operations.
After the decision has been made to bid the project, the estimating process
can be started. Management assigns the project to an estimator who will handle
the estimating process.
ESTIMATING PROCESS
After the decision has been made to bid a job, preparation of the estimate can be
started. Estimating is a process, just like any endeavor that requires an end prod
uct. Information must be assembled, evaluated, documented, and managed in an
Chapter 3 Estimating Process 45
organized manner. For any process to work effectively, key information must be
defined and accumulated at critical times. Standardization is a key word in
preparing reliable estimates. The estimating team must establish a standard pro
cedure for preparing estimates to ensure organization and consistency, and to
reduce the potential for errors.
People involved in preparing the estimate must know their role, responsi
bility, and authority. Effective communications among members of the estimat
ing team are essential to selecting the estimate methodology commensurate with
the desired level of accuracy, collecting project data and confirming historical
cost information, organizing the estimate into the desired format, reviewing and
checking the estimate, and documenting the estimate after it is complete.
The estimating work process is illustrated in Fig. 3.1. The first step is the
kickoff meeting, which provides background information about the project to
the estimating team, expectations of the team, and any pertinent information that
may be needed to prepare the estimate. After orientation of the estimating team,
a work plan for preparing the estimate is established before starting the estimat
ing process. Preparing the estimate involves calculating the quantities of mate
rials, pricing labor and material, soliciting subcontractor bids, summarizing
direct costs, and adding indirect costs to determine the base estimate. After the
estimate is prepared, there must be a clear documentation and thorough review,
followed by necessary adjustments.
Effective communication is necessary during the estimating process. A sup
port document should be developed and available for presentation, review, and
future use of the estimate. A thorough documentation of the estimate forms a
baseline for project control, so decisions during project execution can be made
with a better awareness of the budget, thereby improving the overall outcome of
the project.
Well-executed estimate reviews will increase the credibility and accuracy of
the estimate. They also help the team and project management to know the level
of scope definition and the basis of the estimate. The review of estimates is an
important part of the estimating process because it helps the customer to under
stand the contents and level of accuracy of the estimate, enabling the customer
to make better business decisions.
Estimating Construction Costs
One of the key responsibilities of the lead estimator is to ensure the team has all
of the necessary resources to perform their work.
1. What are the driving principles and expectations for the project?
2. What is the level of quality and completeness of the plans and specifications?
3. What level of accuracy and detail is expected in the estimate?
4. Who are potential competitors?
5. What are the experiences with the designer and/or owner?
6. Does the project have unique or unusual characteristics?
7. What is the estimate due date and the anticipated project start and completion dates?
8. What level of confidentiality is required of the team?
9. Who are the customer’s contacts with the team?
10. What is the availability of material suppliers and subcontractors?
11. What is the availability of labor at the construction site?
12. Are there other information sources that can aid the estimating?
13. Have similar projects/estimates been developed previously?
14. What owner-furnished items are to be excluded from the estimate?
15. What owner-furnished costs are to be included in the estimate?
16. Are there specific guidelines to be used in preparing the estimate?
17. Are there special permitting requirements that may affect the cost and schedule?
18. Are there any special regulations that might influence the final total installed cost?
19. Are there other issues that could affect the cost or schedule of the project?
20. What are the company’s current commitments of personnel and equipment?
21. Are there any special licensing requirements?
22. What is the time allowed for construction?
23. Are there liquidated damages?
24. What is the owner’s ability to pay?
25. What are the impacts of community relations?
preparing the estimate and the process used in preparing the estimate. It is
important to implement and maintain effective control over the estimating
process. Procedures must be in place for
■ Disseminating knowledge and sharing expertise among the estimating staff.
■ Assigning and sharing the workload among estimators to improve
efficiency.
■ Reviewing, checking, and approving work for quality control.
owner wants only a quick cost estimate to evaluate the economic feasibility of
pursuing the project. For this situation, a conceptual cost estimate using the
square-foot method of estimating would be appropriate. Methods of conceptual
estimating are discussed in Chapter 4.
The level of scope definition may be a complete set of final design drawings
and specifications that define and show everything that must be in the completed
building, including foundations; structural, mechanical, electrical, and architec
tural finishes; etc. The final drawings and specifications are provided to a list of
contractors for bidding the job to select a contractor to build the project. For this
situation, a detailed estimate would be appropriate. This book illustrates meth
ods of detailed estimating for various types of specific construction work, such
as earthwork, concrete structures, roofing, plumbing, painting, etc.
PREPARING ESTIMATES
While preparing an estimate, there must be two-way communications between
the estimating team and management. The estimating team must keep manage
ment informed of the work being performed and management must respond to
questions that may arise from the estimating team. The estimating process can
assist management in identifying areas of uncertainty and additional information
that may be needed, or assumptions that must be made in lieu of definitive infor
mation about the project.
As the estimate is being prepared, it is important to perform periodic “real
ity checks” to make sure the costs developed are within reason. Based on esti
mator experience and familiarity with the project, this can include
The plans and specifications of the project are determined by the design
organization, and the project sponsor determines the completion date for an esti
mate. Therefore, these two elements may be beyond the control of the estimator.
However, the estimator does have control over the selection of the tools and
methodology to be used in preparing the estimate. The approach to selecting the
method of estimating should be commensurate with the expected level of accu
racy of the estimate and the constraints of time.
ESTIMATING PROCEDURES
To prepare an estimate for the entire project, a procedure must be established to
assemble all of the costs. The preparation of a comprehensive detailed estimate
involves five overlapping activities that must be closely coordinated and inte
grated. These activities are development of construction methods, preparation of
the construction schedule, material quantity takeoffs, the estimate of costs, and
assessment of risks for contingency.
To develop an accurate estimate, a site investigation must be conducted. The
primary objective of a site visit is the investigation of the physical characteris
tics of the project site. The investigation team collects information and evaluates
any constraints or limitations observed during the investigation, including
capacity of roads and bridges for transporting material and equipment to the job,
available storage space, and any other factors that can impact the cost of build
ing the project.
The estimate must be based on the planned method of construction. The
selection of construction methods must be established early in the estimating
process because the construction method will affect all other aspects of the esti
mate. A decision must be made to plan the construction operations to be fol
lowed, to allow the estimating team to separate operations to be performed by
contractor’s personnel and the work to be subcontracted to specialty contractors.
These decisions will depend on availability of contractor-owned equipment and
the skills and experience of the contractor’s personnel. For some projects, it may
be necessary to prepare a preliminary estimate for each of the potential con
struction methods, to determine the relative cost of each scheme. These studies
should be in sufficient detail to identify the most economical methods.
The schedule is an integral part of the estimate. It should be prepared fol
lowing the decision on construction method and before estimating the costs. In
preparing the schedule, the estimating team must consider the requirements of the
project, including milestones established by the bid documents. The sequence of
work may be dictated by the needs of the owner, weather, safety, lead-time for
materials or special equipment, and many other factors. Each of these factors may
have a significant impact on the costs. For example, placing concrete during the
winter season would cost more than placing concrete in the summer season.
The time required or the duration of each activity will be consistent with
the productivity rates selected for the estimate and resource limitations of the
contractor, including labor, equipment, material, and money. The total time for
each phase of the project and for the project as a whole will affect the direct
and indirect costs. The construction schedule can be used to determine resource
Estimating Construction Costs
requirements. Crews may be scheduled for each of the work items to determine
average peak workload requirements as well as total work-hours (WHs)
required. Based on payment provisions in the bid documents, the schedule can
be used to develop a cash flow projection form in which the cost of contractor
financing can be established. In each case, the schedule must integrate with and
confirm determinations made in the detailed cost estimate.
The material quantity takeoff is the systematic breakdown of the project into
units of work for the purpose of evaluating the required cost and time to build
the project. Prior to starting the quantity takeoff, the plans and specifications
must be thoroughly reviewed for requirements that will affect the way in which
quantities will be taken off and assembled. Consideration must be given to the
breakdown required in the bid documents, alternates required, unit prices
required, method of measurement for payment, and bills of materials. The mate
rial quantity takeoff should be handled in a consistent order for all estimates,
generally following the sequence of construction. Each estimator must develop
a system of quantity takeoff to ensure that a quantity is not omitted or calculated
twice, which is a common error in estimating. A well-organized checklist of
work will help reduce the chances of making such an error.
After the quantity takeoff is completed, the direct costs can be calculated.
Direct costs consist of material, labor, equipment, and subcontracts. Material cost
is calculated by multiplying the quantity of material by the unit cost of the mate
rial. The unit cost of material can be obtained from material suppliers. The cost
of labor is calculated by dividing the quantity of work by the production rate of
laborers, multiplied by the labor rate. Labor rates include base wages plus payroll
taxes and insurance. The cost of equipment is calculated by dividing the quantity
of work by the production rate of equipment, multiplied by the equipment rate.
Equipment rates include both ownership cost and operation expenses. Each indi
vidual subcontractor submits the cost of subcontractors’ work. Contractors
develop and continually update a cost database for their particular type of work.
The estimating work process shown in Fig. 2.1 illustrates the feedback loops dur
ing construction to record actual costs and productivity rates into the database.
The indirect costs are estimated after the direct costs have been completed.
Many of the indirect costs depend on the results of the direct costs. Indirect costs
consist of mobilization, field office expenses, insurance, bonds, taxes, final
cleanup, and other expenses required to complete the project.
After the direct and indirect costs are completed and summarized, a risk
analysis of uncertainties is made to determine an appropriate contingency for the
estimate. Contingency is discussed later in this chapter.
ESTIMATE CHECKLISTS
Checklists are valuable tools to reduce the potential of overlooking a cost item.
Checklists act as reminders to the estimator by
■ Listing information required to prepare the early estimate.
■ Listing miscellaneous other costs that may be required in the estimate.
Chapter 3 Estimating Process 53
■ Listing work items that may be required to build the project in accordance
with the plans and specifications.
A listing of information required to prepare an estimate in the process indus
try may include type of unit, feed capacity, and project location. For a computer
generated estimate in the process industry, the required information includes soil
and site data, building requirements, plot plan dimensions, and other specific
engineering requirements. For projects in the building sector, a listing of infor
mation to prepare an estimate may include type of building, functional use of
building, number of occupants, building location, and project location.
Typical examples of miscellaneous cost items may include spare parts, per
mits, training, or other items. Typical scope items that may be required, but are
not identified in the definition provided for the estimate, may include certain util
ity and auxiliary systems. Checklists are also useful during initial client-customer
meetings where they serve as agenda items for discussion. Checklists also assist
in preparing an “estimate work plan” by identifying important points to empha
size in the write-up for the execution of the estimate. Table 3.2 is an illustrative
example of an early estimate checklist for a project in the process industry.
Table 3.3 is an example checklist for a detailed estimate for concrete work.
T A B L E 3 .2 I Checklist for an early estimate in the T A B L E 3 .3 I Checklist for detailed estimate for
process industry. concrete work.
1. Process unit description (delayed coker, hydrogen plant, etc.) 1. Are anchor bolts included?
2. Process licenser 2. Is reinforcing steel included?
3. Feed capacity 3. Is insulation of the slab included?
4. Production capacity 4. Is vapor barrier under the slab included?
5. Product yield 5. Is cost of pumping concrete included?
6. Utility levels at process unit location 6. Are shop drawings for tilt-up panels included?
7. Feedstock specifications 7. Is caulking of the tilt-up panels included?
8. Integration of multiple units 8. Is hardware and rigging included for tilt-up panels?
9. Process pressure and temperature operating levels 9. Is the lifting crane included?
10. Provision for future expansion of capacity 10. Are form liners included?
11. Provision for processing multiple or different feedstocks 11. Is grouting under the wall panels included?
12. Single-train versus multiple-train concept 12. Is waste included in the concrete?
13. Project location 13. Are architectural finishes included?
14. Miscellaneous costs (spare parts, training, chemicals, etc.) 14. Are concrete curing compounds included?
15. Other items, such as unusually high or low recycle rates 15. Is the portable compressor included?
DOCUMENTATION OF ESTIMATE
After the estimate is completed, a document should be prepared that defines the
basis of the estimate. Estimate documentation is essential for presentation,
review, and future use of the estimate. The documentation for an estimate
improves communications between the estimating team and management, estab
lishes a mechanism for estimate reviews, and forms a basis for early project cost
control. The estimating team should develop a standard format for presentation
of the estimate that is easily understood by management.
Estimating Construction Costs
Inaccurate cost estimates are often the result of omissions in the estimate,
miscommunications of project information, or nonaligned assumptions.
Documenting the estimate will minimize these inaccuracies by
■ Improving communications among all project participants.
■ Establishing a mechanism for review of the estimate.
■ Forming a solid basis for project controls.
As the estimate is being developed, the act of preparing documentation
facilitates communications between the estimating team and management.
Estimate documentation improves the outcome of the estimate through
■ Sharing information.
■ Identifying items that require clarification.
■ Helping the estimator obtain and organize information needed for the
estimate.
■ Avoiding confusion over what is covered, and not covered, by the
estimate.
■ Providing useful information for future estimates.
■ Highlighting weak areas of the estimate.
■ Increasing the credibility of the estimate.
A portion of the documentation may be developed by sources other than the
estimator. For example, procurement personnel may obtain material quotes,
labor information may be obtained from field personnel, etc. However, the esti
mator has overall responsibility for collecting and organizing this information.
Reviewing and clarifying the information with the originator improves the esti
mate accuracy.
A standard default format or outline should be developed to organize and
prepare documentation for the cost estimates. A different standard can be devel
oped for different types of estimates. The process of developing, utilizing, and
storing the documentation for future use should be built into the cost estimate
work process. The items that should be documented are shown in Table 3.4.
ESTIMATE REVIEWS
Once the estimate is complete, a detailed review should be made of the entire
estimate package, including the backup materials, assumptions, unit prices, pro
ductivity rates, etc. The estimate should also be checked against the project
schedule requirements to ensure they are compatible with such elements as over
time rates assumed during outages, price escalation, etc.
The number of reviews will vary depending on the size of project, type of
estimate, length of time allowed for preparing the estimate, and other factors.
For any estimate there should be at least two reviews: an internal review dur
ing development of the estimate and a final review at or near completion of the
estimate.
Chapter 3 Estimating Process
1. Standard format for presenting cost categories (codes)—summary and backup levels
2. Basis of estimate—clear understanding of what constitutes the estimate
3. Level of accuracy— expected for the estimate
4. Basis for contingency— risk analysis, if applicable
5. Boundaries of the estimate— limitations of the estimate
6. Scope of work—the quality and completeness of the plans and specifications
7. Labor rates— breakdown and basis of labor rate
8. Assumed quantities—conceptualized etc.
9. Applied escalation— dates and basis of escalation
10. Work schedule— shifts, overtime, etc. to match the milestones (not contradictory)
11. Other backup information— quotes, supporting data, assumptions
12. Checklists used—a list of completed checklists
13. Description of cost categories— codes used in preparing the estimate
14. Excluded costs— list of items excluded from the cost estimate
1. Either report to upper management that the costs have gotten outside of
the boundaries established as a target for the project, or
2. Give the team the “go ahead” to proceed with the remaining estimate
process to complete the estimate.
The final estimate review is a more structured process. The depth of the
review depends on the type or class of estimate that is being prepared. The meet
ing is intended to validate assumptions used in preparing the estimate, such as
construction sequence, key supplier selection, and owner’s cost.
The final estimate review may be a lengthy meeting. For a final estimate
review, the attendees should include the lead estimator, experienced field per
sonnel, and a representative of upper management. To be effective, the final esti
mate review meeting should be conducted with a written agenda. The meeting
should be documented with written minutes that are distributed to all attendees.
The estimator must come to the review meeting prepared with this information
for comparisons:
■ Historical data used in preparing the estimate.
■ Actual total installed costs of similar projects.
■ Percentage of total installed cost on key cost accounts.
Estimating Construction Costs
RISK ASSESSMENT
Assessing risk and assigning contingency to the base estimate is one of the most
important tasks in preparing early estimates. Risk assessment is not the sole
responsibility of the estimators. Key members of the project management team
must provide input on critical issues that should be addressed by the estimators
in assessing risk. Risk assessment requires a participatory approach with
involvement of all project stakeholders including the business unit, engineering,
construction, and the estimating team.
The owner is responsible for overall project funding and for defining the
purpose and intended use of the project. The design organization is responsible
for producing the contract documents, the plans and specifications, to construct
the project. The estimating team is responsible for preparing an estimate of the
probable final cost to construct the project, including direct and indirect costs,
and assessing risk and assigning contingency.
RISK ANALYSIS
Typically, risk analysis is a prerequisite to assigning contingency. Based on the
acceptable risks and the expected confidence level, a contingency is established
for a given estimate. Risk analysis and the resultant amount of contingency help
management to determine the level of economic risk involved in pursuing a proj
ect. The purpose of risk analysis is to improve the accuracy of the estimate and
to instill management’s confidence in the estimate.
Numerous publications have been written to define risk analysis techniques.
Generally, a formal risk analysis involves either a Monte Carlo simulation or a
statistical range analysis. There are also numerous software packages for risk
analysis. The lead estimator for a project must assess the uniqueness of each
project and select the technique of risk analysis that is deemed most appropriate.
For very early estimates, the level of scope definition and the amount of estimate
detail may be inadequate for performing a meaningful cost simulation.
CONTINGENCY
Contingency is a real and necessary component of an estimate. Engineering and
construction are risk endeavors with many uncertainties, particularly in the early
stages of project development. Contingency is assigned based on uncertainty.
Contingency may be assigned for many uncertainties, such as pricing, escala
tion, schedule, omissions, and errors. The practice of including contingency for
possible scope expansion is highly dependent on the attitude and culture toward
changes, particularly within the business unit.
In simple terms, contingency is the amount of money that should be added
to the base estimate to better predict the total installed cost of the project.
Contingency can be interpreted as the amount of money that must be added to
the base estimate to account for work that is difficult or impossible to identify at
58 Estimating Construction Costs
the time a base estimate is being prepared. In some owner or contractor organi
zations, contingency is intended to cover known unknowns. That is, the estima
tor knows there are additional costs, but the precise amount is unknown.
However, sometimes an allowance is assigned for known unknowns and a con
tingency is assigned for unknown unknowns.
AACE International document 18R-97 defines contingency as “An amount
of money or time (or other resources) added to the base estimate to: (a) achieve
a specific confidence level; or (b) allow for changes that experience shows will
likely be required.”
TRADITIONAL METHODS OF
ASSIGNING CONTINGENCY
The most effective and meaningful way to perform risk analysis and assign con
tingency is to involve the project management team. Estimators have insights
and can assess imperfections in an estimate to derive an appropriate contin
gency. However, the interaction and group dynamics of the project management
team provide an excellent vehicle to assess the overall project risk. The integra
tion of the project management team’s knowledge and the estimator’s ability to
assign contingency provides management with an appreciation of and confi
dence in the final estimate. The end result is an estimate that represents the
judgment of the project management team, not just the estimator’s perspective.
Figure 3.3 illustrates the risk assessment process. The estimator must select
the method deemed most appropriate for each project, based on information pro
vided by the project management team and based on the intended use of the esti
mate by the business unit. The estimator must communicate the method selected,
risk, accuracy, and contingency for the estimate.
Simulation
A formal risk analysis for determining contingency is usually based on simula
tion. A simulation of probabilistic assessment of critical risk elements can be per
formed to match the desired confidence level. Monte Carlo simulation software
Estimating Construction Costs
packages are useful tools for performing simulation. However, knowledge of sta
tistical modeling and probability theory is required to use these tools properly.
Range estimating is a powerful tool that embraces Monte Carlo simulation
to establish contingency. Critical elements are identified that have a significant
impact on the base estimate. For many estimates, there are less than 20 critical
elements. The range of each critical element is defined and probability analysis
is used to form the basis of simulation. Using this method, noncritical elements
can be combined into one or a few meaningful elements.
Range estimating is probably the most widely used and accepted method of
formal risk analysis. In range estimating the first step requires identification of
the critical items in the estimate. The critical items are those cost items that can
affect the total cost estimate by a set percentage, for example ± 4 percent. Thus,
a relatively small item with an extremely high degree of uncertainty may be crit
ical, whereas a major equipment item for which a firm vendor quote has been
obtained would not be considered critical. Typically, no more than 20 critical
items are used in the analysis. If more than 20 critical items are identified, the
set percentage can be increased to reduce the number of critical items.
Once the critical items are identified, a range and a target are applied to each
item. For example, the range may include a minimum value so there is only a
1 percent chance that the cost of the item would fall below that minimum.
analysis of the components of the estimate, a process that can identify mistakes
and poor assumptions. However, precautions must be taken when using simula
tion methods for early estimates. For many early estimates there is not enough
detailed information or an adequate number of cost items for a valid simulation.
PROBLEMS
3.1 Describe the purpose of a kickoff meeting of an estimating team. What are typi
cal issues that should be discussed?
3.2 List and briefly describe the important factors that should be included in estimat
ing procedures.
3.3 Develop a checklist of items that should be included in a detailed estimate for a
grading operation for a highway project. A review of Chapter 7 provides the
work items necessary for earthwork.
3.4 What values can be obtained from documenting an estimate, other than minimiz
ing inaccuracies?
3.5 Discuss the difference between internal and external reviews of an estimate and
describe a situation when an external review might be especially valuable.
3.6 Review published articles that describe methods of risk assessment and assign
ment of contingency to estimates.
3.7 Interview three estimators, one working for an owner, a designer, and a contrac
tor, respectively, to identify factors that each estimator believes is important for
preparing accurate estimates.
Conceptual Cost Estimating
At the inception of a project by the owner, prior to any design, only limited
information is known about a project. However, the owner must know the
approximate cost to evaluate the economic feasibility of proceeding with the
project. Thus, there is a need to determine the approximate cost of a project dur
ing its conceptual phase.
As discussed in Chapter 1, cost estimates can be divided into at least two
different types, depending on the purposes for which they are prepared and the
amount of information known when the estimate is prepared: approximate esti
mates (sometimes called preliminary, conceptual, or budget estimates) and
detailed estimates (sometimes called final or definitive estimates). Each of these
estimates may be subdivided.
Later chapters of this book discuss methods and procedures of estimating
the construction costs of engineering projects for which detailed information is
known. For example, the cost of excavation is determined for a known quantity
and type of soil, size of excavator, and job conditions. The cost of concrete
forms is determined based on specific sizes, shapes, and numbers of concrete
columns, beams, walls, etc.
This chapter presents methods and procedures for estimating project costs
during the preliminary or conceptual phase. Because there is little definition of
a project at this stage, the accuracy of the estimate will be less than that of a
detailed estimate. However, the conceptual cost estimate is important because
the owner will examine this estimate before continuing with development of the
project.
64
Chapter 4 Conceptual Cost Estimating
LIABILITY OF CONCEPTUAL
COST ESTIMATES
Generally the designers are not obligated under standard-form contracts to guar
antee the construction cost of a project. However, as a part of their design
responsibility, designers prepare an estimate of the probable construction cost
for the project for which they have prepared the design.
Major decisions are often made by the owner from information contained in
the conceptual cost estimate. This places a responsibility on the estimator.
Although the initial estimate may be prepared from little-known information, it
is the duty of the estimator to re-estimate the project as additional information
about the project becomes available. This is particularly important for a cost-
plus construction contract where the designer has the responsibility to monitor
costs during construction.
PREPARATION OF
CONCEPTUAL ESTIMATES
There are many variations in the contract arrangements among the three princi
pal parties in a project (owner, designer, and contractor). The conceptual esti
mate is generally prepared by the owner during the owner’s feasibility study or
by the designer during the design phase. It may be prepared by the contractor for
negotiated work between an owner and a contractor.
Multibuilder owners are involved with the construction of projects on a con
tinual basis. Examples are electrical utilities, oil and gas firms, retail stores with
nationwide locations, etc. To initiate a project, these firms generally conduct an
owner’s study. The owner’s study consists of a technical feasibility study and an
economic feasibility study of the proposed project. A conceptual cost estimate is
prepared by the owner as part of the economic feasibility analysis.
Designers prepare conceptual cost estimates throughout the design process.
The estimate is used in the selection of design alternatives and to keep the owner
informed of forecast costs. It is the responsibility of the designer to develop a
66 Estimating Construction Costs
design that will produce a completed project within the amount of money
authorized in the owner’s budget.
Some projects are of an emergency nature and must be completed in the
least time possible. For such projects the owner will negotiate a contract with a
contractor. The contractor may be asked to prepare a conceptual cost estimate
for the project for which there are no, or limited, plans and specifications.
The preparation of conceptual cost estimates requires knowledge and expe
rience with the work required to complete the project. Cost information from
previous projects of similar type and size is essential. The estimator must com
bine all known information with his or her personal experience and use consid
erable judgment to prepare a reliable conceptual estimate.
EXAMPLE 4 .1
Cost information from eight previously constructed parking garage projects is shown
in the table.
Chapter 4 Conceptual Cost Estimating 67
Use the weighted unit cost to determine the conceptual cost estimate for a proposed
parking garage that is to contain 135 parked cars.
The unit cost per car can be calculated as:
The average cost per car is $30,431.50 ^ 8 = $3,803.94. From Eq. [4.1] the fore
cast unit cost will be
the difference in time between the two projects. The adjustment should represent
the relative inflation or deflation of costs with respect to time due to factors such
as labor rates, material costs, interest rates, etc.
Various organizations publish indices that show the economic trends of the
construction industry with respect to time. The Engineering News Record (ENR)
quarterly publishes indices of construction costs. An index can be used to adjust
previous cost information for use in the preparation of a conceptual cost estimate.
The estim ator can use the change in value of an index between any two
years to calculate an equivalent compound interest rate. This equivalent interest
rate can be used to adjust past cost records, to forecast future project costs.
Example 4.2 illustrates the use of indices for time adjustments.
EXAMPLE 4 . 2
Suppose the indices for building construction projects show these econom ic trends:
Year Index
3 yr ago 358
2 yr ago 359
1 yr ago 367
Current year 378
An equivalent com pound interest can be calculated based on the change in the cost
index during the 3-yr period:
/ = 1.83%
Suppose that cost information from an $843,500 project com pleted last year is to be
used to prepare a conceptual cost estimate for a project proposed for construction
3 yr from now. The cost of the proposed project should be adjusted for time as follows:
= $906,960
a publisher of location cost indices. Example 4.3 illustrates the use of indices for
location adjustments.
EXAMPLE 4 . 3
The location indices for construction costs show this information:
Location Index
City A 1,025
City B 1,170
City C 1,260
City D 1,105
City E 1,240
Suppose that cost information from a $387,200 project com pleted in city A is to
be used to prepare a conceptual cost estimate for construction of a proposed proj
ect in city D. The cost of the proposed project should be adjusted for location as
Cost = h H X $ 3 8 7 ’2 0 0 = $ 4 1 7 '4 2 0
COMBINED ADJUSTMENTS
The conceptual cost estimate for a proposed project is prepared from cost
records of a project completed at a different time and at a location with a differ
ent size. The estimator must adjust the previous cost information for the combi
nation of time, location, and size.
Example 4.4 illustrates the use of combined adjustments for preparation of
a conceptual cost estimate.
EXAMPLE 4 . 4
Use the time and location indices presented in Examples 4.2 and 4.3 to prepare the
conceptual cost estimate for a building with 62,700 sf of floor area. The building is
to be constructed 3 yr from now in city B. A similar type of building that cost
$2,197,540 and contained 38,500 sf was com pleted 2 yr ago in city E. Estimate the
probable cost of the proposed building.
70 Estimating Construction Costs
Proposed cost
= Previous cost x Time adjustm ent x Location adjustm ent x Size adjustment
K 1,170 62,700
= $ 2 ,1 9 7 ,5 4 0 X (1 + 0 .0 1 8 3 )' « — X —
= $3,700,360
UNIT-COST ADJUSTMENTS
Although the total cost of a project will increase with size, the cost per unit may
decrease. For example, the cost of an 1,800-sf house may be $53.50 per square
foot whereas the cost of a 2 ,2 0 0 -sf house of comparable construction may be
only $48.75 per square foot. Certain items, such as the kitchen appliances,
garage, etc., are independent of the size of the project.
Size adjustments for a project are unique to the type of project. The estima
tor must obtain cost records from previous projects and develop appropriate
adjustments for his or her particular project. Example 4.5 illustrates a method of
size adjustments for preparation of a conceptual cost estimate.
EXAMPLE 4 . 5
Cost records from previous projects show this information:
Y = b + mX
C hapter 4 Conceptual Cost Estimating 71
30
3
S, 20
10
0
0 50 100 150 200 x
Number of units
FIGURE 4.1 I Comparison of size and cost per unit.
where b = intercept of the line and m = slope of the line. Substituting in values for
b and m, we get
The equation for unit cost with respect to the num ber of units can be written as:
= $18.95
As illustrated in Example 4.5, the adjustment of unit costs based on the size
of a project is unique and can be obtained only from previous cost records.
The cost data for some types of projects could be nonlinear, rather than lin
ear as previously illustrated. For example, a second-order equation may better fit
the data for some types of projects. The technique presented in Example 4.5 can
also be applied for nonlinear data.
The estimator must evaluate his or her own particular cost records and
develop a unit cost-size relationship. There are numerous methods of curve fit
ting, such as linear regression or least squares.
Estimating Construction Costs
NARROW-SCOPE CONCEPTUAL
COST ESTIMATES
As the design of a project progresses and more information becomes known
about the various components, a narrow-scope conceptual cost estimate can be
prepared. For example, upon completion of the foundation design, the number
of cubic yards of concrete will be known. When the structural-steel design is
complete, the number of tons of structural steel will be known.
A narrow-scope conceptual estimate is prepared in a manner similar to that
for a broad-scope estimate, except the project is subdivided into parameters. For
a building construction project the parameters might be square yards of asphalt
parking, cubic yards of concrete foundations, tons of structural steel, square feet
of finished floor, number of doors, etc. For a steel-pole electric transmission
line, the parameters might be acres of clearing land, cubic yards of concrete
foundations, tons of steel pole, linear feet of conductor wire, number of insula
tor strings, etc.
The cost of a proposed project is prepared from historical cost records of
previous projects, with an appropriate adjustment for time, size, and location, as
already discussed.
EXAMPLE 4 . 6
Cost capacity curves for process units in a chem ical plant are shown in the figure.
What is the estimated cost for a project that has a Process Unit C with a capacity of
6,000 barrels per day?
74 Estimating Construction Costs
Locating the 6,000 barrels per day capacity along the abscissa, draw a vertical
line upward until it intersects the Process Unit C cost curve. Then, draw a horizontal
line to the left to read the estimated cost as $151,000.
EXAMPLE 4 . 7
The cost of a 320 cu b ic feet per hour (cf/hr) process unit is $675,000. From histori
cal cost records, the capacity ratio exponent of a process unit is 0.72. Estimate the
cost of a similar process unit with a ca pacity of 450 cf/hr.
= ($675,000) X (1.2782183)
= $862,797
Equipment-Factored Estimates
For the process industry, equipment-factored estimates are derived by applying
various factoring techniques to estimated equipment costs. The factors used are
developed and updated utilizing return cost data from completed. This information
Estimating Construction Costs
is normalized to a location, usually U.S. Gulf Coast, and base timeline such as
December of a particular year. The estimated total installed cost of a normalized
unit is defined to include these costs:
■ Direct equipment costs
■ Direct bulk material costs
■ Subcontract costs
■ Construction labor costs
■ Construction indirect costs
■ Home office services costs
One example of the factoring technique is the “equipment cost” to “total
installed cost” factor. This factoring technique is relatively simple for projects
where equipment costs have been estimated. As the name implies, “total
installed cost” factors are developed by dividing the equipment costs of a par
ticular process unit into the total installed cost of that unit. The estimated cost of
the project is determined by multiplying the “equipment costs” by the “total
installed cost” factor, or multiplier. The factors for process plants generally
range between 2.5 and 6.0, depending on the nature of the process unit.
Conditions that affect the equipment to “total installed cost” factors are
■ Equipment sizes
■ Pressure
■ Metallurgy
■ Degree of prefabrication
■ Site conditions
■ Equipment costs
■ Special conditions (large structures, pits, buildings, etc.)
■ Explanation of engineering costs included
Another equipment-factored estimating technique develops equipment costs
manually or by utilizing commercially available computer software systems.
Bulk material costs are factored from the estimated equipment costs, using his
torical cost data for the same or similar type units. Field labor work-hours are
estimated for each individual equipment item and bulk material installation work-
hours are ratioed from the bulk material costs by individual bulk material cate
gory. The resultant field labor work-hours are adjusted for productivity and labor
costs by applying local labor rates to the estimated construction work-hours.
Construction indirect costs are developed for the major categories by percentages
of direct labor costs. Home office costs are estimated as a percentage of the total
installed cost. The equipment factored estimating techniques described can be
utilized when there is sufficient technical definition available, consisting of
■ Process flow diagram
■ Equipment list
■ Equipment specifications
Chapter 4 Conceptual Cost Estimating 77
■ Project location
■ General site conditions (assumed if not specified)
■ Construction labor information
■ Project schedule
EXAMPLE 4 . 8
The estimating departm ent of a process industry com pany has developed the equip
ment factors from cost records of previously com pleted projects as shown.
Equipment Factor
Condensers 2.4
Control instruments 4.1
Compressors 2.5
Fans 2.7
Furnaces 2.0
Generators 1.7
Heat exchangers 4.5
Motors 1.8
Pumps 5.3
Reactors 4.0
Tower vessels 3.5
Tanks 2.7
Engineering design has progressed such that the size and specifications of major
equipm ent have been determ ined to the level of detail that price quotes can be
obtained from the manufacturers of the equipm ent. Use the listed equipm ent factors
to estimate the cost of the project based on the m anufacturer’s quotes given next.
Equipment quote
Item from manufacturer Factor Plant cost
Condenser $15,000 X 2.4 = $36,000
Control instruments $22,000 X 4.1 = $90,200
Compressors $85,000 X 2.5 = $212,500
Fans $15,000 X 2.7 = $40,500
Furnaces $140,000 X 2.0 = $280,000
Generators $25,000 X 1.7 = $42,500
Heat exchangers $95,000 X 4.5 = $427,500
Motors $55,000 X 1.8 = $99,000
Pumps $18,000 X 5.3 = $95,400
Reactors $120,000 X 4.0 = $480,000
Tower vessels $325,000 X 3.5 = $1,137,500
Tanks $140,000 X 2.7 $378,000
Total $1,055,000 $3,318,900
For this project, the delivered equipm ent cost is $1,055,000, but the estimated cost
of the equipm ent installed in the plant is $3,318,900.
Estimating Construction Costs
Computer-Generated Estimates
Numerous commercial computer software systems exist for estimating capital
costs for different types of industries, including the process industry, building
construction industry, and the heavy/highway infrastructure industries. These
systems can be simple or very sophisticated. Most of the software packages can
operate on a personal computer and are furnished with a cost database, which is
updated on an annual basis. The more flexible systems enable the purchaser to
customize the database.
These computer software packages are available to assist the estimator in
generating conceptual estimates. They can also be used for detailed material
quantities as well as equipment and material costs, construction work-hours
and costs, indirect field costs, and engineering work-hours and costs. The
detailed quantity and cost output enables early project control, which is essen
tial in the preliminary phases of a project, before any detail engineering has
started. The accuracy of an estimate can be improved because some systems
allow vendor costs, takeoff quantities, project specifications, site conditions,
etc., to be introduced into the program. To maximize benefits of these software
programs, the use of system defaults should be minimized and replaced with
definitions as follows:
PROBLEMS
4.1 Use the time and location indices presented in this chapter to estimate the cost of
a building that contains 32,500 sf of floor area. The building is to be constructed
2 yr from now in City A. The cost of a similar type of building that contained
48,300 sf was completed last year in City C for a cost of $3,308,500.
4.2 Calculate the weighted unit cost per square foot for the project data shown, and
determine the cost of a 2,700-sf project.
4.3 Determine the relationship between unit cost and size for the project data shown
in Prob. 4.2, to estimate the cost of a 2,200-sf project.
4.4 Early estimates are extremely important to the owner. From the perspective of
the owner, give examples of problems that may arise if an early estimate is sig
nificantly lower than the final actual cost of a project.
4.5 From the perspective of the owner, give examples of problems that may arise if
an early estimate is significantly lower than the final actual cost of a project.
4.6 Early estimates are important to the designer. From the perspective of the
designer, give examples of problems that may arise if an early estimate is signifi
cantly lower than the final cost of a project.
4.7 Describe the purpose of a kickoff meeting for preparing an early estimate of a
project. What are typical items that should be addressed and confirmed before
starting estimate preparation?
4.8 The cost of a 540-cf/hr process unit is $850,000. From historical cost records,
the capacity ratio exponent of a process unit is 0.6. Use the capacity ratios raised
to an exponent method to determine the estimated cost of a similar process unit
with a capacity of 490 cf/hr.
Estimating Construction Costs
4.9 Shown are cost capacity curves for process units in a refinery. What is the esti
mated cost for a project that has a Process Unit B with a capacity of 4,000
barrels/day?
Process
Cost in $1 Million
81
Estimating Construction Costs
COST OF LABOR
The rates listed in Table 5.1 are representative base rates. In addition to paying
the base rate, an employer must pay or contribute amounts for such items as
social security tax, unemployment tax, workers’ compensation insurance, public
liability and property damage insurance, and any fringe benefits. Fringe benefits
include such items as apprenticeship plans, pension plans, and health and wel
fare insurance. Base rates normally apply to work done during the 40-hr work
week, 8 hr/day and 5 days/week. For work in excess of 8 hr/day or 40 hr/week,
the base rate is generally increased to l j or 2 times the base rate. The base rates
in Table 5.1 are used to determine the costs in the examples in this book. The
effect of fringe benefits, taxes, and insurance is not included in the rates.
which is paid by the contractor. This rate may be reduced by establishing a high
degree of employment stability, with few layoffs, during a specified period.
FRINGE BENEFITS
As a part of the agreement of employment, the contractor often agrees to pay
benefits for the employee. Examples are health insurance, pension plan, training
programs, paid holidays, and vacations. The cost of these fringe benefits will
depend on the number of different coverages and the amount of coverage.
Generally the costs range from 10 to 20 percent of base wage.
Example 5.1 illustrates the costs that a contractor must incur to hire an
employee. For estimating and bidding purposes, the estimator normally deter
mines the total cost of all labor, using the base wages. The final cost of labor is
then determined by multiplying the base-wage costs by a percentage to account
for taxes and insurance.
EXAMPLE 5 .1
An ironworker works 10 hr/day, 6 days/week. A base w age of $20.97 per hour is paid
for all straight-time work, 8 hr/day, 5 days/week. An overtime rate of time and one-
half is paid for all hours over 8 hr/day, Monday through Friday, and double time is
paid for all Saturday work. The social security tax is 7.65 percent, and the unem
ployment tax is 3 percent of actual wages. The rate for w orker’s com pensation insur
ance is $12.50 per $100.00 of base wage, and public liability and property dam age
insurance rate is $3.25 per $100.00 of base wages. Fringe benefits are $3.15 per
hour. Calculate the average hourly cost to hire the ironworker.
Pay hours and actual hours:
Actual hours: 10 hr/day x 6 days/week = 60 hr
Pay hours = w eekly straight-time + weekly overtime + Saturday overtime
= (5 days x 8 hr/day @ 1.0) + (5 days X 2 hr/day @ 1.5) +
(10 hr x 1 day @ 2 .0 )
= 40 hr + 15 hr + 20 hr
= 75 hr
Base wage and average hourly pay:
Base w age = $20.97/hr
Average hourly pay = (pay hours/actual hours) x base wage
= (75 hr/60 hr) X $20.97/hr = $26.2125/hr
The cost to hire the ironworker will be:
Taxes are paid on actual wage and insurance is paid on base wage.
Average hourly pay: 75/60 x $ 20 .97/hr = $26.2125
Social security tax: 7.65% X $26.2125 = 2.0053
Unemploym ent tax: 3% x $26.2125 = 0.7864
W orkers’ com pensation: $12.50/$100.00 X$20.97/hr = 2.6213
Public liability/property damage: $3.25/$100.00 x $20.97/hr = 0.6815
Fringe benefits are $ 3 .15/hr = 3.1500
Average hourly cost = $35.4570/hr
Chapter 5 Cost of Construction Labor and Equipment 85
rate at which each type of brick was laid under different working conditions, con
sidering the climatic and any other factors that might have affected production
rates. All experienced construction workers know that the production of labor is
usually low during the early stages of construction. As the organization becomes
more efficient, the production rates will improve; then as the construction enters
the final stages, there will usually be a reduction in the production rates. This is
important to an estimator. For a small job it is possible that labor will never reach
its most efficient rate of production because there will not be sufficient time. If a
job is of such a type that laborers must frequently be transferred from one opera
tion to another or if there are frequent interruptions, then the production rates will
be lower than when the laborers remain on one operation for long periods with
out interruptions.
In this book numerous tables give the rates at which laborers should perform
various operations. These rates include an adjustment for nonproductive time,
by assuming that a person will actually work about 45 to 50 min/hr. Conditions
on some projects may justify a further adjustment in the rates. The frequent use
of a range in rates instead of a single rate will enable the estimator to select the
rate that she or he believes is most appropriate for the project.
EXAMPLE 5 . 2
This exam ple illustrates a method of determ ining the probable rate of placing rein
forcing steel for a given project.
Steel bars are to be used to reinforce a concrete slab 57 ft w ide and 70 ft long.
The reinforcing steel will be #4 bars, 5-in. diameter, with no bends, maximum length
limited to 20 ft, and spaced 12 in. apart both ways. All laps will be 18 in. Precast con
crete blocks, spaced not over 6 ft apart each way, will be used to support the rein
forcing. The bars will be tied at each intersection, by bar ties. The steel will be stored
in orderly stock piles, according to length, about 80-ft average distance from the
center of the slab. The slab will be constructed on the ground.
Quantity of work:
The length of the bars parallel to the 57-ft side will be
Length of the side = 57 ft
Length of laps: 2 x 18in = 3 ft
Total length of bars per row = 60 ft
Use 3 bars 20 ft long = 60 ft
Total num ber of bars required: 3 x 70 = 210
Total length of the bars: 210 x 20 ft = 4,200 ft
The tim e required to place the reinforcing, using 2 steel setters, should be about
Cycle times:
Carrying bars to slab site:
Time to walk 160 ft @ 100 ft/min = 1 , 6 min
A dd time to pick up and put down reinforcing = 1.0 min
Time for round trip = 2.6 min
Assume that the 2 persons can carry 6 bars, weighing
approxim ately 80 lb each trip
Number of trips required: 438 bars + 6 bars per trip = 73 trips
Total time to carry reinforcing: 73 trips x 2.6 min/trip 60 min/hr = 3.17 hr
If the reinforcing steel is bent to furnish negative reinforcing over the beams
or if it has hooks on the ends and if, in addition, it must be hoisted to the second
floor of a building, then it will require extra time to hoist and place it. An esti
mator should adjust the production rate accordingly instead of using flat rates for
all projects.
CONSTRUCTION EQUIPMENT
All projects involve the use of construction equipment to some extent. The pur
chase of equipment represents a capital investment by the construction contrac
tor. The contractor must recover sufficient money to pay the ownership and
operating costs of the equipment during its useful life, and at the same time make
a profit on the investment. Any estimate must include the cost of equipment used
on the project.
SOURCES OF EQUIPMENT
Construction equipment can be purchased or rented. The choice between pur
chase and rental usually depends on the amount of time the equipment will be
used in the contractor’s operations. If extensive use of the equipment is required,
the equipment is often purchased. If the equipment is to be used a limited
amount of time, it is typically rented.
In some situations the contractor may secure equipment by a lease with an
option to purchase the equipment. In this arrangement the contractor will lease the
equipment at a specific monthly rate, then purchase the equipment at a later date
with the option of applying a part of the monthly rate to the purchase amount.
EQUIPMENT COSTS
When equipment is rented, the estimator should include the rental cost in the
estimate. The rental cost for a particular type and size of equipment can be
obtained from the business from which the equipment will be rented. Usually the
rental cost does not include operating cost such as fuel, oil, and lubricants.
Rental Rate Blue Book by Dataquest, Inc. (Equipment Guide-Book Company,
Palo Alto, Calif.) provides a comprehensive list of the rental and operating costs
for all types of construction equipment. This publication is periodically updated
and has become an industry standard for equipment rental rates.
Chapter 5 Cost of Construction Labor and Equipment
Ownership costs
Investment
Depreciation
Taxes and insurance
Operating costs qhj
Maintenance and repairs
Fuel and lubricating oil
Investment Costs
The purchase of construction equipment requires a significant investment of
money. The money to purchase the equipment will be either borrowed from a
lender, or it will be taken from reserve funds of the contractor. In either situation,
there will be interest costs to the contractor. Either the lender will charge an inter
est rate for the borrowed money, or the contractor will lose any interest money
that could be gained from the money that is withdrawn from the reserve fund. The
interest expense, or the interest-income loss, is part of the ownership cost.
Selection of an appropriate interest rate for money depends on economic
conditions. Most companies use the current rate of interest for borrowing money
and add to it an additional amount to account for the risk involved in purchasing
equipment and potential variations in interest rates over the life of the equipment.
Depreciation Costs
Depreciation is the loss in value of equipment resulting from use and age. With
time, the value of a unit of equipment decreases due to wear and tear, deteriora
tion, obsolescence, or reduced need. Thus, at the end of its useful life the value
of the equipment is substantially less than its purchase amount. This loss in
value is depreciation. For example, if a unit of equipment is purchased for an
amount (P ) and sold at a future date for a salvage value (F), then the total depre
ciation is (P — F). Straight-line depreciation is the most simple and probably the
most widely used method in construction. For a purchase amount (P ) and future
salvage value (F) after n years of useful life, the yearly depreciation can be cal
culated as (P - F)/n.
90 Estimating Construction Costs
OWNERSHIP COSTS
Discussions and examples presented next will illustrate methods of estimating
the hourly cost of owning and operating equipment. These examples are
intended to show the estimator how to determine the probable hourly cost for
any type of construction equipment. The costs that are determined in these
examples apply for the given conditions only, but by following the same proce
dure and using appropriate prices for the particular equipment, the estimator can
determine hourly costs that are suitable for use on any project.
The method described next is widely used by construction contractors for
estimating the probable ownership cost of construction equipment. This method
uses time-value-of-money equations. The development of these equations can be
found in many books on the topic economic analysis. A complete description of
their derivations can be found in Project Management fo r Engineering and
Construction (by G. Oberlender, McGraw-Hill, 2nd ed., 2000). For estimating
the ownership costs of equipment, these capital recovery and sinking fund equa
tions can be used:
;(i + *)"
A = P [5.1]
(l + i)n - l
C hapter 5 Cost of Construction Labor and Equipment 91
r( r T ^ r ] [5-2J
where A = equivalent annual value
F = future salvage value
i = annual interest rate
n = useful life, in years
The sinking fund equation gives the equivalent annual value (A) of the
future salvage value (F), assuming an annual interest rate of (;) during the use
ful life of (n).
These steps are used to estimate the annual ownership costs:
1. Obtain the purchase price (P) of the delivered equipment and estimate the
probable future salvage value (F ) and expected useful life («). Historical
records or manufacturers can provide valuable information on salvage
values and useful life.
2. Select an appropriate interest rate for borrowing money. Most contractors
use the current rate of interest for borrowing money and add an additional
amount for risk.
3. Estimate the average cost for taxes, insurance, and storage each year and
convert these costs into an equivalent interest rate based on the value of
the equipment at any time.
4. Combine the interest rate from steps 2 and 3 to define the annual interest
rate ( i) and use the capital recovery and sinking fund equations to estimate
the equivalent annual ownership cost of the equipment. This annual
interest rate (i) is called the minimum attractive rate o f return (MARR) on
the investment.
EXAMPLE 5 . 3
The purchase price of new equipm ent is $145,000. The estimated salvage value is
$25,000 after the end of its expected useful life of 6 years. Assume interest for bor
rowing money is 9 percent, 5 percent for risk and 3 percent as the equivalent interest
Estimating Construction Costs
rate for taxes, insurance, and storage. Thus, the total com bined annual interest rate
will be 17 percent, or MARR = 17%. The annual ownership costs can be calculated
using the capital recovery Eq. [5.1] and the sinking fund Eq. [5.2] as
= $38,742
The $38,742 equivalent annual cost will accrue, whether or not the equipm ent
is used. It includes investment, depreciation, insurance, taxes, and storage costs.
To recover this cost, an appropriate amount must be charged for use of the equip
ment. The amount charged depends on the expected num ber of hours the equip
ment will be used. Considering 40 hr/week and 52 weeks/year, it is possible the
equipm ent could be used 2,080 hr/yr. Deducting 2 weeks of vacation time, there
would be 2,000 hr/year. Also, there will be time when the equipm ent may be idle,
due to absence of an operator or downtime of the equipm ent for servicing or repairs.
Therefore, it is likely the equipm ent will be used less than 2,000 hr/year.
Several m ethods can be used for charging ownership costs. One method is to
charge a per hour use based on the expected use rate per year. For example, if
the equipm ent is expected to be used 1,200 hr/year, the hourly ownership charge
w ould be
$38,742
Hourly ownership charge = ^ ^ = $32.29/hr
If the expected use is 1,500 hr/year the ownership charge per hour will be
$38,742 „
Hourly ownership charge = ^ ^ = $25.8 3/hr
Another method is to charge the equipm ent on a daily, weekly, or monthly rate
that the equipm ent is available on the job, whether or not it is used. For example, if
historical records indicate that this type of equipm ent is assigned to projects about
250 days/year, then the ownership cost of availability will be:
The $38,742 represents the total cost of owning the equipm ent over the 6-year
time frame, regardless of the number of hours it is used each year. The hourly
charge for the equipm ent is a function of the num ber of hours used per year as
shown in Fig.5.1. It is desirable to use purchased equipm ent as much as possible
because as the num ber of hours used per year decreases, the cost for charging the
equipm ent to a job increases. If the equipm ent is not used a sufficient num ber of
hours per year, it may be more econom ical to rent the equipm ent.
Chapter 5 Cost of Construction Labor and Equipment 93
-c
I3
o
Q<
j5
5c
£
o
X
OPERATING COSTS
Operating costs accrue only when the unit of equipment is being used, whereas
ownership costs accrue whether or not the equipment is used. Operating costs
include maintenance and repairs, fuel, oil, and lubricants. Maintenance and
repairs may be defined as major or minor. Major maintenance and repairs are
often included in ownership costs, whereas minor maintenance and repairs are
included in operating costs.
Construction equipment that is driven by internal combustion engines
requires fuel and lubricating oil, which should be considered as an operating cost.
Whereas the amounts consumed and the unit cost of each will vary with the type
and size of equipment, the conditions under which it is operated, and the location,
it is possible to estimate the cost with reasonable accuracy for a given condition.
An estimator should be reasonably familiar with the conditions under which a
unit of equipment will be operated. Whereas a tractor may be equipped with a 200-
hp engine, this tractor will not demand the full power of the engine at all times,
possibly only when it is used to load a scraper or to negotiate a steep hill. Also,
equipment is seldom, if ever, used 60 min/hr. Thus, the fuel consumed should be
based on the actual operating conditions. Perhaps the average demand on an
engine might be 50 percent of its maximum power for an average of 45 min/hr.
These costs vary considerably with the type of equipment, operating conditions,
frequency of oil and lubricant services, and skill of the operator. For example, if
an excavator is used to excavate soft earth, the replacement of parts will be con
siderably less often than when the same excavator is used to excavate rock. If a
bearing is greased and adjusted at frequent intervals, its life will be much longer
than if it is neglected.
Historical cost records of maintaining and servicing equipment are the most
reliable guide in estimating maintenance and repair cost. If this information is
not available, the manufacturers of construction equipment provide information
showing recommended costs for maintenance and repairs for the equipment they
manufacture. The annual cost of maintenance and repairs is often expressed as a
percentage of the purchase price or as a percentage of the straight-line depreci
ation costs (P - F)/n. For example, the average cost of maintenance and repairs
for an excavator may vary from 80 to 1 2 0 percent of the depreciation cost, with
100 percent as a fair average value. The annual cost for certain types of rock-
crushing equipment may be much higher, whereas the cost for a compressor will
be lower.
Fuel Consumption
When operating under standard conditions, namely at a barometric pressure of
29.9 in. of mercury and at a temperature of 6 8 °F, a gasoline engine will consume
approximately 0.06 gal of fuel for each actual horsepower-hour developed [0.06
gal/(hp*hr)]. A diesel engine will consume approximately 0.04 gal of fuel for
each actual horsepower-hour developed [0.04 gal/(hp-hr)].
Consider a shovel with a diesel engine rated at 160 hp. During a cycle of 20
sec, the engine may be operated at full power while filling the bucket in tough
ground, requiring 5 sec. During the balance of the cycle, the engine may be oper
ated at not more than 50 percent of its rated power. Also, the shovel may not
operate more than 45 min/hr on average. For this condition the approximate
amount of fuel consumed during 1 hr is determined as
For other operating conditions the quantity of fuel consumed can be estimated
in a similar manner.
Chapter 5 Cost of Construction Labor and Equipment
EXAMPLE 5 . 4
Determine the probable cost per hour of owning and operating a 165-hp diesel engine
shovel. No future salvage value is assumed for this equipment; the owner prefers to
depreciate the equipm ent to zero and use any salvage value, or trade-in, for acquisi
tion of replacement equipment. Maintenance and repair costs are expected as 80 per
cent of the annual straight-line depreciation cost. This information will apply:
Cost to owner:
Price f.o.b. factory = $ 1 4 5 ,8 6 0
Freight: 42,000 lb x $2.57 per cw t = 1,079
Unloading and assem bling = 700
Sales tax: 5% x $145,860 = 7,293
Total cost to owner = $154,934
Ownership cost:
Interest on money = 9%
Risk addition = 3%
Taxes and insurance = 5%
Total interest i= 17%
Thus, the MARR is 17 percent. Since salvage value is not considered, only the capital
recovery equation (Eq. [5.1]) is required for calculating the hourly ownership costs:
/(1 + i)n
Annual ownership cost = P
(1 + /)" - 1
0,17(1 + 0.17)6
$154,934 $43,167/yr
(1 + 0.1 7 )6 - 1_
Operating costs:
Annual straight-line depreciation cost = $154,934/6 yr = $25,822/yr
Maintenance and repairs cost: 80% ($25,822)/1,800 hr = $ 1 1.48/hr
Fuel: 0.60 X 165 hp x (0.04 gal/hp*hr)
= 3.96 gal/hr @ $1.40/gal = 5.54
Lubricating oil: 0.14 gal/hr x $ 2 .00/gal = 0.28
Grease: 0.5 lb/hr x $0.50/lb = 0.25
Hourly operating cost = $17.55/hr
EXAMPLE 5 . 5
Determine the probable cost per hour of owning and operating a bottom -dum p truck
with rubber tires. Maintenance and repairs are expected as 50 percent of the
straight-line depreciation costs. Because the tires will have a different life from the
truck, they are treated separately. This information applies:
Cost to owner:
Cost delivered = $92,700
Less tires = 12,500
Net less tires = $80,200
= 0.23 g a l/h r
98 Estimating Construction Costs
Ownership cost:
Interest on money = 9%
Risk addition = 3%
Taxes and insurance = 5%
Total interest i =17%
/(1 + i ) n /
A- P P
(1 + i ) n - 1_ L(i + o nJ
As noted, the calculated cost in Example 5.4 neglected salvage, whereas the
costs in Example 5.5 included salvage value of the equipment to illustrate meth
ods of estimating equipment costs under both scenarios. Any unit of construc
tion equipment will have some value at trade-in time or some resale value at the
Chapter 5 Cost of Construction Labor and Equipment
conclusion of its use. As discussed earlier in this chapter, many owners prefer to
depreciate their equipment to zero and to use the residual value, or salvage, as a
trade-in for replacement of the equipment.
The hourly cost of owning and operating construction equipment, as illus
trated in Examples 5.4 and 5.5, will vary with the conditions under which equip
ment is operated. The estimator should analyze each job to determine the proba
ble conditions that will affect the cost and should appropriately adjust costs. As
interest rates change, the interest rate applied to equipment costs should be appro
priately adjusted and new hourly costs should be applied to charging the equip
ment to projects and to preparing cost estimates that will use the equipment.
If a crawler tractor is used on rock surfaces, the life of the undercarriage will
be significantly reduced. Undercarriage costs can represent a major portion of
operating costs of track-type equipment. Undercarriage costs can be determined
similarly to tire costs, based on the cost of undercarriage replacement and its
useful life. The costs should be based on local costs of parts and labor.
If trucks are operated over smooth and level haul roads that are well main
tained, the cost of repairs will be significantly lower than when the same trucks
are operated over rough and poorly maintained haul roads. Therefore, the esti
mator must know the job-site conditions before appropriate costs can be
assigned to construction equipment.
PROBLEMS
5.1 A crew of four carpenters and two laborers will be used to build the formwork
for a concrete structure. Work is scheduled for 9 hr/day on Monday through
Friday and 8 hr on Saturday. Overtime at a rate of one and one-half will be paid
for all hours over 8 hr/day during the week and double time for all Saturday
work. The base wage, taxes, and insurance rates are given in the table. Calculate
the hourly, weekly, and monthly cost for the crew.
5.2 A backhoe will be purchased for a cost of $109,750. After a useful life of 5 years
it is assumed the equipment will be sold for $35,000. Assume interest of 8 per
cent for borrowing money, 4 percent for risk, and 2 percent as the equivalent
interest rate for taxes, insurance, and storage. Calculate the annual ownership
cost and the cost per hour assuming the equipment will be used 1,800 hr/year.
5.3 A scraper with a 180-hp diesel engine will be used to excavate and haul earth for
a highway project. An evaluation of job conditions indicates the scraper will
100 Estimating Construction Costs
operate 40 min/hr. For this project it is anticipated that the total cycle time will
be 18 min for a round-trip. Previous job records show the scraper operated at full
power during the 2.3 min required to fill the bowel of the scraper and at 70 per
cent at its rated horsepower for the balance of the cycle time. Calculate the gal
lons per hour for fuel consumption of the scraper.
5.4 A 250-hp diesel truck is used for hauling gravel from the rock quarry to a stock
pile at a paving operation. The crankcase capacity is 5 gal and the expected time
between oil changes is 120 hr. Calculate the gallons per hour of lubricating oil
for this operation of the truck.
5.5 Calculate the probable cost per hour of owning and operating a dozer that has a
212-hp diesel engine. The purchase price is $285,000 delivered, including ship
ping and taxes. It is anticipated the dozer will be operated 1,500 hr/year and sold
for $65,000 after 5 years. Assume 17 percent total interest, which includes inter
est on money, risk, taxes, and insurance. Assume a 0.6 operating factor, 0.6 lb/hr
for grease, 6 gal crankcase capacity, and 100 hr between oil changes. Use
$1.65/gal for fuel and $ 2 .15/gal for oil, and $0.85/lb for grease.
5.6 Determine the probable cost per hour for owning and operating the scraper of
Prob. 5.5 when the equipment will be operated 6 years at 1,800 hr/year.
Handling and
Transporting Material
INTRODUCTION
Although material suppliers generally deliver to the jobsite the construction
materials that have been purchased by the contractor, sometimes the materials
must be obtained by the contractor at the storage yard of the material supplier.
Also, the contractor must move material from stockpiles on the jobsite to the
location where the material will be permanently installed.
Some projects require the use of aggregates, sand and gravel, or crushed
stone, which are produced from natural deposits or quarries and hauled to the
project in trucks. A contractor using his or her laborers and equipment may do
the handling and hauling, or it may be accomplished through a subcontractor.
Regardless of the method used, it will involve a cost that must be included in the
estimate for a project.
When estimating the time required by a truck for a round-trip, the estimator
should divide the round-trip time into four elements:
1. Load
2. Haul, loaded
3. Unload
4. Return, empty
These four elements define the cycle time for transporting material. The
time required for each element should be estimated. If elements 2 and 4 require
the same time, they can be combined. Since the time required for hauling and
returning will depend on the distance and effective speed, it is necessary to
determine the probable speed at which a vehicle can travel along the given haul
road for the conditions that will exist. Speeds are dependent on the vehicle, traf
fic congestion, condition of the road, and other factors. An appropriate operat
ing factor should be used in determining production rates. For example, if a
102 Estimating Construction Costs
truck will operate only 45 min/hr, this time should be used in determining the
number of round-trips the truck will make in 1 hr.
EXAMPLE 6 .1
Given 175 T of sand with a density of 100 lb/cf that must be transported 7 mi using
a 12-cy dum p truck. Two laborers and a driver, at a rate of 1.5 cy/hr each, will load
the truck. Assume a haul speed of 30 mph, return speed of 40 mph, and 3 min to
dum p the load. The cost of the truck is $25/hr, the driver is $18/hr, and the laborers
cost $15/hr each. What is the total time, total cost, and cost per unit for transporting
the material?
Quantity of work:
Volume of sand = 175 T X 2,000 Ib/T X cf/100 lb x cy/27cf = 130 cy
Cycle time:
Load = 1 2 cy/(3 x 1.5 cy/hr) = 2.667 hr
Haul = 7 mi/30 mph = 0.233 hr
Dump = 3 min/(60 min/ hr) = 0.050 hr
Return = 7 mi/40 mph = 0.175 hr
Total cycle time = 3.125 hr/trip
Chapter 6 Handling and Transporting Material 103
Production rate:
Num ber of trips per hour = 1.0/(3.125 hr/trip) = 0.32 trips/hr
Quantity hauled per trip = 12 cy/trip x 0.32 trips/hr = 3.84 cy/hr
Assume 45 min/hr as productive,
Production rate = 3.84 cy/hr x 45/60 = 2.88 cy/hr
Time:
Using 1 truck and 2 laborers = 130 cy/2.88 cy/hr = 45.1 hr
Cost:
Truck = 45.1 hr X 1 truck @ $25/hr = $1,127.50
Driver = 45.1 hr X 1 driver @ $ 18/hr = 811.80
Laborers = 45.1 hr X 2 laborers @ $ 15/hr= 1,353.00
Total cost = $3,292.30
Unit cost:
Cost per cubic yard = $3,292.30/130 cy = $25.33/cy
Cost per ton = $3,292.30/175 T = $18.81/7
The time, cost, and cost per unit of work are high using only laborers to load the
sand. These high costs are a result of the truck sitting idle while the laborers are
loading the truck. Example 6.2 illustrates the econom y of bringing equipm ent to the
job to load the sand.
EXAMPLE 6 . 2
Note that in Example 6.1 the load time is significantly greater than the travel time,
2.667 > 0.458, w hich indicates an im balance between loading and hauling. Assume
a small tractor loader can be rented at a cost of $50/hr with a load production rate
of 95 cy/hr. The loader operator costs $21/hr. Assuming the cost of transporting the
loader to the job is $400.00, what is the time, cost, and cost per cubic yard for trans
porting the 175 T of sand?
Quantity of work:
Volume of sand = 175 T x 2000 Ib/T x cf/100 lb x cy/27cf = 130 cy
Cycle time:
Load = 12 cy/(95 cy/hr) = 0.126 hr
Haul = 7 mi/30 mph = 0.233 hr
Dump = 3 min/(60 m in/ hr) = 0.050 hr
Return = 7 mi/40 mph = 0.175 hr
Total cycle time = 0.584 hr/trip
Production rate:
Number of trips per hour = 1.0/(0.584 hr/trip) = 1.71 trips/hr
Quantity hauled per trip = 12 cy/trip x 1.71 trips/hr = 20.5 cy/hr
104 Estimating Construction Costs
The time, cost, and cost per unit using the equipm ent loader are significantly lower
than using the laborers in Example 6.1. Thus, it is justifiable to rent the equipm ent
and pay the cost to bring it to the job. The number of cubic yards of sand required
to justify the equipm ent loader can be calculated as
($ 2 5 .3 5 /h r)X = ($ 7 .4 /c y )X + $400.00
X= 22.3 cy
Thus, if there is less than 22.3 cy of sand it is more economical to use the
two laborers and one truck to transport the sand, whereas if there is more than
22.3 cy, it is more economical to use the rented equipment to load the truck.
In this example the loader remains idle for a significant amount of time
while the single truck is transporting the sand. Thus, it is desirable to add addi
tional trucks to the operation to balance the cycle time of the loader and trucks,
to reduce idle time of equipment on the job. Example 6.3 provides an analysis
of using multiple trucks with the loader.
E X A M P LE 6.3
Note that in Example 6.2 the travel time is significantly greater than the load time,
0.458 > 0.126, w hich indicates an inadequate num ber of trucks to keep the loader
busy. Determine the econom ical num ber of trucks to balance the loader. The
Chapter 6 Handling and Transporting Material 105
required number of trucks to balance the loader can be calculated by dividing the
cycle time by the load time as
Production rate:
For 1 truck = 12 cy/truck/0.584 hr/trip = 20.5 cy/hr
For 4 trucks = 20.5 cy/hr x 4 trucks = 82.0 cy/hr
Cost:
Loader = 1 .6 hr @ $50/hr = $80.00
O perator = 1.6 hr @ $ 2 1 /hr = 33.60
Trucks = 1 .6 hr X 4 trucks @ $25/hr = 160.00
Drivers = 1.6 hr x 4 drivers @ $18/hr = 115.20
Total labor and equipm ent = $388.80
Add transporting loader = 400.00
Total cost = $788.80
Cost:
Loader = 1.4 hr @ $50/hr = $70.00
Operator = 1.4 hr @ $21/hr = 29.40
Trucks = 1.4 hr X 5 trucks @ $25/hr = 175.00
Drivers = 1.4 hr X 5 drivers @ $ 18/hr = 126.00
Total labor and equipm ent = $400.40
Add transporting loader = 400.00
Total cost = $800.40
HANDLING LUMBER
Lumber is usually loaded onto flatbed trucks by a forklift or laborers at the lum
beryard and hauled to the job. At the jobsite, the lumber is unloaded and stacked
according to size.
A laborer should be able to handle lumber at a rate of 2,000 to 4,000 board
feet per hour (bf/hr). A reasonable average rate should be about 3,000 bf/hr. For
lumber, one board foot is 1 in. thick by 1 2 in. wide by 1 ft long.
Trucks of the type generally used will haul 2 to 6 T, corresponding to 1,000
to 3,000 bf per load. The average speed will vary with the distance, type of road,
traffic congestion, and weather.
E X A M P LE 6.4
Estimate the cost of transporting 40,000 bf of lumber from a lumberyard to a jobsite.
Trucks that can carry 2,000 bf per load will transport the lumber. The jobsite is 2 mi
from the lumberyard.
An examination of the haul road indicates an average speed of 20 mi/hr for the
trucks, including necessary delays. Assume that a laborer will handle 3,000 bf/hr of
lumber. Based on using 2 workers, a truck driver and a laborer, and 1 truck, the time
and cost of the job can be determined as
Quantity of work:
Lumber to be handled = 40,000 bf
Cycle time:
Assume both the truck driver and a laborer will load a truck.
Rate of loading a truck, 2 workers x 3,000 bf/hr = 6,000 bf/hr
Time:
Total time = 40,000 bf/2,320 bf/hr = 17.2 hr
EX A M P LE 6.5
Estimate the time and cost for transporting the 40,000 bf of lumber in Example 6.4
based on using two laborers who will remain at the yard to load trucks and two labor
ers who will remain at the job to unload trucks. Estimate the time and cost based on
the econom ical num ber of trucks. Assume the driver of each truck will assist in load
ing and unloading the truck. The cost can be determ ined as
Quantity of work:
Lum ber to be handled = 40,000 bf
Cycle time:
Rate of loading a truck: 3 workers x 3,000 bf/hr = 9,000 bf/hr
Production rate:
Number of trips per hour per truck: 1.0/0.644 hr/trip = 1.55 trips/hr
Number of trucks required: (round-trip time)/(time to load) = 0.644/0.222 =
2.9
Production rate:
For 1 truck: 1.55 trips/hr x 2,000 bf/trip = 3,100 bf/hr
For 2 trucks: 2 trucks x 3,100 bf/hr = 6,200 bf/hr
Total time required for the job: 40,000 bf/6,200 bf/hr = 6.5 hr
Cost:
Trucks: 4.5 hr x 3 trucks @ $25.32/hr = $341.82
Truck drivers: 4.5 hr x 3 drivers @ $18.17/hr = 245.30
Laborers: 4.5 hr x 4 laborers @ $15.56/hr = 280.08
Total cost = $867.20
Since the cost using 3 tracks is $867.20 and the cost using 2 tracks is
$969.93, the economical number of tracks is 3. The costs determined in this
example are the minimum amounts, based on the assumption that the durations
can be limited to 4.5 or 6.5 hr. It may be impossible or impractical to limit the
costs to these respective durations. If such is the case, the appropriate duration
should be used. Also, note that the total costs are based on labor and track costs
for the actual time at work, with no allowance for laborers and tracks while they
are waiting their turn to start working. If there will be costs during such nonpro
ductive times, the total cost of the job will be higher than the value calculated.
loaded into trucks, and transported to a central location for later distribution to
prospective buyers. Similarly, gravel is trip-mined from a rock quarry, crushed
in a rock-crushing machine, screened, and transported by trucks to a central
gravel yard. Several types of equipment, such as clamshells, front-end loaders,
or portable conveyers can handle sand and gravel. Common laborers can handle
small quantities.
Portable belt conveyers are used frequently for handling and transporting
material such as earth, sand, gravel, crushed aggregate, concrete, etc. Because of
the continuous flow of material at relatively high speeds, belt conveyers have
high capacities for handling material.
The amount of material that can be handled by a conveyer depends on the
width and speed of the belt and on the angle or repose for the material. Portable
belt conveyers are available in lengths of 30 to 60 ft, with belt widths of 18 to
30 in. The maximum speeds of conveyer belts range from 250 to 450 ft/min. A
300-ft/min belt speed is representative for many jobsites. Table 6.1 gives the
areas of cross section of materials with various angles of repose.
Angle of repose
Width of belt, in. 10° 20° 30°
18 0.134 0.274 0.214
24 0.257 0.331 0.410
30 0.421 0.541 0.668
EXAMPLE 6 . 6
A portable belt conveyer is used to load sand from a stockpile into trucks. The con
veyer has a 24-in.-wide belt that has a travel speed of 300 ft/min. The conveyer will
load 12-cy dum p trucks that will haul the sand 4 mi at an average travel speed of 30
mi/hr. Assume a dum p time of 2 min and an angle of repose of sand of 20°.
Determine the num ber of trucks required to balance the production rate of the belt
conveyer.
Production rate of conveyer:
Production rate of conveyer: 300 ft/min x 0.331 sf = 99.3 cf/min
Hourly production rate: (99.3 cf/m in)/(27 sf/sy) x 60 min/hr = 220.7 cy/hr
Cycle time of construction operation:
Time to load a truck: 12 cy/220.7 cy/hr = 0.05 hr
Time to haul: 4 mi/30 mph = 0.13 hr
Time to dump: 2 min/60 min/hr = 0.03 hr
Time to return: 4 mi/30 mph = 0.13 hr
Total cycle time = 0.34 hr
110 Estimating Construction Costs
Therefore, 6 or 7 trucks are required to balance the production rate of the belt con
veyer.
EXAMPLE 6 . 7
Estimate the probable time and cost of loading 1,925 cy of gravel from a stockpile
into trucks and hauling it 18 miles to a project. A 1-cy clamshell will be used to load
15-cy dum p trucks. The trucks can maintain an average speed of 40 mph hauling
and returning to the stockpile. The truck time at the dum p will average 8 min, includ
ing delays.
The clamshell should handle an average of 53 cy/hr, allowing time for moving
the clamshell and for other minor delays. The cost of moving the clamshell to and
from the job will be $1,200. The estimated time and cost can be determ ined as
Quantity of work:
Gravel to be transported = 1,925 cy
Cycle time:
Time to load a truck: 15 cy/53 cy/hr = 0.28 hr
Travel time, round-trip: 36 mi/40 mph = 0.90 hr
Time at dump: 8 min/60 min/hr = 0.13 hr
Total cycle time = 1.32 hr
Production rate:
Number of trips per hour per truck: 1.0/1.32 hr/trip = 0.76 trips/hr
Volume hauled per truck per hour: 15 cy x 0.76 trips/hr = 1 1 .4 cy/truck-hr
Production rate:
For 1 truck = 1 1 .4 cy/hr
For 4 trucks: 11.4 cy/hr x 4 trucks = 45.6 cy/hr
Cost:
Clamshell: 42.2 hr @ $75.50/hr = $3,186.10
Operator: 42.2 hr @ $21.67/hr = 914.47
Trucks: 42.2 hr X 4 trucks @ $34.30/hr = 5,789.84
Drivers: 42.2 hr X 4 drivers @ $ 18.17/hr = 3,067.10
Laborers: 42.2 hr x 2 laborers @ $15.56/hr = 1,313.26
Moving clamshell to and from the job = 1,200.00
Total cost = $15,470.77
Production rate:
Based on clamshell loading = 53 cy/hr
Cost:
Clamshell: 36.3 hr @ $75.50/hr = $2,740.65
Operator: 36.3 hr @ $21.67/hr = 786.62
Trucks: 36.3 hr x 5 trucks @ $34.30/hr = 6,225.45
Drivers: 36.3 hr X 5 drivers @ $18.17/hr = 3,297.86
Laborers: 36.3 hr X 2 laborers @ $15.56/hr= 1,129.66
Moving clamshell to and from the job = 1,200.00
Total cost = $15,380.24
E X A M P LE 6.8
The cost for 60,000 bricks from a supplier includes delivering, unloading, and stack
ing the bricks at a central location at the jobsite. Estimate the cost of transporting the
bricks from the central location where they are stacked by the supplier to the struc
ture where they will be installed by a brick mason. The bricks will be hauled by a
small four-wheel tractor at a rate of 1,800 bricks per hour.
Laborers will be located around the perimeter of the structure to carry the bricks
to the brick masons. Assume each laborer will carry 8 bricks per load and will aver
age | min per trip each way.
Quantity of work:
Material to be transported = 60,000 bricks
Chapter 6 Handling and Transporting Material 113
Production rate:
Laborer production rate: 8 b ric k s /trip /f min per trip = 10.7 bricks/m in
Labor hourly production rate: 10.7 bricks/m in x (60 min/hr) = 640 bricks/hr
Tractor production rate = 1,800 bricks/hr
Time:
Tractor-hours: 60,000 bricks/1,800 bricks/hr = 33.3 hr
Labor-hours: 60,000 bricks/640 bricks/hr = 93.8 hr
Cost:
Tractor: 33.3 hr @ $31.25/hr = $1,040.63
Operator: 33.3 hr @ $21.67/hr = 721.61
Laborers: 93.8 hr @ $15.56/hr = 1,459.53
Total cost = $3,221.77
The costs determ ined in this exam ple are minimum amounts, based on the
assumption that the durations can be limited to 33.3 hr for the equipm ent and 93.8 hr
for the laborers. For this project, it is desirable to use 2 laborers who com bined will
have a production rate of 1,280 bricks/hr, which is close to the equipm ent produc
tion rate of 1,800 bricks/hr. If such is the case, the time the equipm ent and laborers
will be on the job will be governed by the lower production rate of the laborers. For
this scenario the cost w ould be calculated as
Production rate:
Equipm ent production rate = 1,800 bricks/hr
Laborer production rate = 2 laborers x 640 bricks/hr = 1,280 bricks/hr
Time:
Time the crew will be on the job: 60,000 bricks/1,280 bricks/hr = 46.9 hr
Rounding to a full 8-hr day, the expected time = 48 hr
Cost:
Tractor: 48 hr @ $31.25/hr = $1,500.00
Operator: 48 hr @ $21.67/hr = 1,040.16
Laborers: 48 x 2 laborers @ $15.56/hr = 1,493.76
Total cost = $4,033.92
The cost under this scenario is substantially higher because the equipm ent will
be idle on the job due to its higher production rate. Another scenario w ould be to
use the equipm ent to distribute the bricks around the perimeter of the building and
then move the equipm ent to another project. Then at a later date any number of
laborers could be used to transport the bricks to the masons for installation. For
example, if 4 laborers are used, they would be on the job for about 23.4 hr, or 3 full
8-hr working days. Thus, the cost would be as calculated in the first part of this
example.
114 Estimating Construction Costs
EX A M P LE 6.9
Estimate the time and cost of hauling 60,000 bricks from the brickyard of a supplier
to a job 15 mi away. Each truck will haul 3,000 bricks per load and can travel at an
average speed of 40 mph loaded and at 50 mph empty, allowing for lost time.
Three laborers will be stationed at the yard to load the trucks, and another 3 labor
ers will be at the jobsite to unload the trucks. The truck drivers will not be involved
in loading or unloading the trucks. Each laborer will carry 8 bricks at the yard and
at the jobsite. Assum e that a laborer will average f min per trip atthe yard and at
the job.
Quantity of work:
Material to be transported = 60,000 bricks
Cycle time:
Loading truck: 3,000 bricks/1,920 bricks/hr = 1.56 hr
Hauling to jobsite: 15 mi/40 mph = 0.38 hr
Unloading truck: 3,000 bricks/1,920 bricks/hr = 1.56 hr
Returning to yard: 15 mi/50 mph = 0.30 hr
Total cycle time = 3.80 hr/trip
It will be necessary to use either 2 or 3 trucks. If 2 trucks are used, the cost
will be determ ined as
Production rate:
For 1 truck = 780 bricks/hr
For 2 trucks = 2 x 780 bricks/hr = 1,560 bricks/hr
Cost:
Trucks: 40 hr X 2 trucks @ $34.30 = $2,744.00
Drivers: 40 hr X 2 drivers @ $ 18.17/hr = 1,453.60
Laborers: 40 hr x 6 workers @ $15.56/hr = 3,734.40
Total cost = $7,932.00
Cost per 1,000 bricks: $7,932.00/60 = $132.20/1,000 bricks
Cost:
Trucks: 32 hr x 3 trucks @ $34.30 = $3,292.80
Drivers: 32 hr X 3 drivers @ $ 18.17/hr = 1,744.32
Laborers: 32 hr x 6 workers @ $15.56/hr = 2,987.52
Total cost = $8,024.64
Determine the number of trucks and the direct cost per foot for transporting
the pipe.
Cycle time fo r 1 truck:
Loading a truck: 14 joints X 3 min/joint
= 42 min/60 min/hr = 0.70 hr
Hauling to the job: 5 mi/25 mph = 0.20 hr
Unloading a truck: 14 joints X 3 min/joint
= 42 min/60 min/hr = 0.70 hr
Returning to the supplier: 5 mi/30 mph = 0.17 hr
Total cycle time = 1.77 hr/trip
Production rates:
Number of trips per hour: 1.0/(1.77 hr/trip) = 0.56 trips/hr
Number of joints hauled per hour per truck: 0.56 hr/trip X 14 joints/trip =
7.9 joints/hr
Number of joints unloaded per hour: 14 joints/0.7 hr = 20 joints/hr
Number o f trucks required:
Required number of trucks = (20 joints/hr/7.9 joints/hr) = 2.5
An alternative solution is (total cycle time)/(load time) = 1.77/0.70 = 2.5
Hourly cost o f labor and equipment:
Using 3 trucks the hourly cost for labor and equipment for this job will be
Crane: 1 hr @ $73.40/hr = $73.40
Operator: 1 hr @ $21.67/hr = 21.67
Trucks: 1 hr X 3 trucks @ $34.30/hr = 102.90
Truck drivers: 1 hr X 3 drivers @ $18.17/hr = 54.51
Laborers: 1 hr X 6 laborers@$ 15.56/hr = 93.36
Foreman: 1 hr @ $25.00/hr = 25.00
Total crew cost = $370.84/hr
PROBLEMS
6.1 Estimate the total direct cost and the cost per 1,000 bf of lumber for transporting
75,000 bf of lumber from the lumberyard to a job, which is 8 mi from the yard.
Each truck can haul 3,000 bf per load and can average 25 mi/hr loaded and 35
mi/hr empty. Assume $28.50/hr for each truck and $18.50/hr for each driver.
Chapter 6 Handling and Transporting Material 117
One laborer plus a driver will load lumber onto the truck at the lumberyard,
and another laborer plus the truck driver will unload the truck and stack the lum
ber at the job. Each worker will handle 1,200 bf/hr when working. Assume
laborers cost $15.56/hr. Assume that the laborers and the tracks operate 50
min/hr. Determine the most economical number of trucks to use.
Will placing an additional laborer at the yard and at the job reduce the cost
of handling and hauling the lumber?
6.2 Using the information given in Prob. 6.1, is it less expensive to keep two labor
ers at the yard and two other laborers at the jobsite, or to use only two laborers
who will ride with the truck driver to load and unload a truck?
6.3 The owner of a sand and gravel quarry is considering the purchase of trucks to
deliver aggregate to customers. Two sizes are being considered, namely, 10- and
15-cy diesel engine dump trucks. The haul distances will vary from 6 to 20 mi,
with an average distance of about 12 mi.
It is estimated that the 10-cy trucks can travel at an average speed of 40
mi/hr loaded and at 50 mi/hr empty, while the 15-cy trucks can travel at average
speeds of 35 mi/hr loaded and at 45 mi/hr empty. The trucks will be loaded from
stockpiles of aggregate, using a loader that has a production rate of 115 cy/hr.
The average truck time at the dump will be 4 min for 10-cy trucks and 5 min for
15-cy trucks. Assume that the trucks and the loader will operate 45 min/hr.
The cost of the 10-cy truck is $27.50/hr and the 15-cy truck is $34.75/hr.
A truck driver will be paid $18.50/hr. Determine which size truck is more eco
nomical.
6.4 Two sizes of loaders are being considered, a 1-cy loader with a 65 cy/hr produc
tion rate and a 2-cy loader with a 140 cy/hr production rate. Diesel dump trucks
with 12-cy capacity will be used to haul the material. In addition to the time
required by the loader to load a truck, there will be an average delay of 2 min
waiting for another truck to move into position for loading. Assume a 50-min
hour for both the loader and the trucks.
This cost information applies:
1-cy loader = $64.50/hr
2-cy loader = $105.00/hr
Truck = $32.45/hr
Driver = $21.95/hr
Loader operator = $24.50/hr
Determine which size loader is more economical based on the cost of loading
the material into the trucks.
6.5 A total of 180,000 bricks is to be hauled from a brickyard with 5-T trucks to a
project 9 mi from the yard. A truck, which can haul 3,000 bricks per load, will
average 30 mi/hr loaded and 40 mi/hr empty. Assume 45 min/hr efficiency for
the loading and hauling operation.
Assume trucks at $32.50/hr, drivers at $ 19.50/hr, and laborers at $ 14.20/hr.
Determine the total cost and the cost per 1,000 bricks for each of the following
conditions:
a. Three laborers plus a truck driver will each load 450 bricks/hr onto a truck,
and 3 other laborers plus a truck driver will unload the bricks from a truck
at the job at the same rate.
Estimating Construction Costs
b. Three laborers plus a truck driver will each load 450 bricks/hr onto a truck,
then the truck driver and the 3 laborers will ride on the truck to the job
where they and the truck driver will unload the bricks at the same rate as at
the yard.
6.6 The operator of a rock quarry is invited to bid on furnishing 3,500 cy of aggre
gate for a job. The gravel is to be delivered to a job, which is 12 mi from the
quarry. The aggregate will be loaded into trucks by a loader that can load at a
rate of 80 cy/hr. The trucks will haul 12 cy/load and average 35 mi/hr loaded and
45 min/hr empty. The estimated time to dump a load is 5 min. Assume 45 min/hr
efficiency for the loading and hauling operation.
This cost information applies:
Royalty paid for aggregate: $0.85/cy
Overhead: $0.30/cy
Profit: $0.35/cy
Loader: $75.00/hr
Trucks, each: $24.50/hr
Operator: $21.67/hr
Truck drivers: $17.30/hr
Foreman: $26.70/hr
JOB FACTORS
Job factors involve the type or classification of soil, extent of water present,
weather conditions, freedom of workers and equipment to operate on the job,
size of the job, length of haul for disposal, etc. It is difficult for the contractor to
change job conditions. The contractor must analyze each job to determine the
conditions that can affect construction operations that will impact the time and
cost of performing the work. The analysis of job factors requires a thorough
review of the plans and specifications of the bid documents, an evaluation of the
soil investigation report, and a visit to the jobsite where the project is to be con
structed. For earthwork projects, the bid documents usually contain a soil report
that provides geotechnical information about the soil and subsurface conditions.
The estimator can also use other sources, such as topographic maps, geologic
maps, agriculture maps, or aerial photographs. Information related to job factors
must be collected and considered before preparing a cost estimate.
MANAGEMENT FACTORS
Management factors involve organizing for the job, maintaining good morale
among workers, selecting and using suitable equipment and construction meth
ods, exercising care in servicing equipment, establishing good field supervisory
personnel, and others. These factors are under the control of the contractor. The
contractor has control of his or her operations and can often overcome adverse
119
120 Estimating Construction Costs
job conditions by good management practices. For example, the haul road can
be properly maintained to increase the efficiency and productivity of scrapers or
trucks that must operate over the haul roads.
unit, earth and rock will occupy a larger volume, with a corresponding reduction
in weight per unit of volume. This increase in volume is described as swell and is
expressed as a percentage gain compared with the original volume. In the haul
condition, earth generally will weigh from 80 to 95 lb/cf. The amount of swell
depends on the type of soil and the amount of loosening during excavation.
Earth that is to be compacted is called fill or compacted measure. When the
earth is placed in a fill area and compacted with compaction equipment, it occu
pies a smaller volume than in its natural state in the cut or bank measure. This
decrease in volume is described as shrinkage and is expressed as a percentage of
the original volume, or bank measure. In the compacted fill area, the unit weight
of soil can vary from 110 to 120 lb/cf. The amount of shrinkage depends on the
type and moisture content of the soil and on the type and number of passes of
the compaction equipment. Shrinkage can vary from 5 to 15 percent, depending
on these factors.
The correlation between unit weights, volumes, swell, and shrinkage can be
obtained from Eqs. [7.1] to [7.4], Eqs. [7.1] and [7.2] apply to volume measures
and Eqs. [7.3] and [7.4] apply to weight measures.
By volume:
[7.1]
[7.2]
By weight:
paid by any one of the three units of measure. The contract documents define the
measure of payment to the contractor for earthwork. For example, the bid form in
the contract documents may stipulate that the contractor will be paid based on the
amount of soil excavated (bank measure), the amount of soil hauled (loose mea
sure), or the amount of soil compacted (compacted measure).
The estimator can prepare the estimate in any unit of measure, but the final
bid amount must correspond to the unit of measure specified in the contract bid
documents. Equations [7.1] through [7.4] can be used to convert between these
three units of measure. Table 7.1 provides the range of percentage of swell for
various soils. Table 7.2 provides representative unit weights for various types of
earth and rock.
EXAMPLE 7 .1
Clay soil whose bank unit w eight is 105 Ib/cf is excavated and hauled by 22-cy
(loose measure) trucks that have an em pty w eight of 67,500 lb. An evaluation of the
physical properties of the soil indicates a swell factor of 30 percent. Based on four
passes of the com paction equipm ent it is anticipated the shrinkage factor will be 15
percent. For each 22-cy truckload of soil that is hauled, calculate the equivalent
bank measure and loose measure volume. Also, what is the total vertical w eight of
the hauling unit and payload of soil that is hauled on each truck-trip?
Equivalent loose and compacted measure volumes, using Eqs. [7.1] and [7.2]:
22cy-(1+^)B
Chapter 7 Earthwork and Excavation 123
B= -----— —
1 + 0.30
= 16.9 cy bank volume
c- ( ' - 4 ) s
= (1 - 0.15) 16.9 cy
= 14.4 cy com pacted volume
Total vertical weight of a truck and its soil payload, using Eq. [7.3]:
B
L=
1 + S J100
105 lb /c f
1 + 30/100
= 80.8 Ib /c y loose w eight of soil
Thus, for each truck-trip the amount of soil that is handled is equivalent to 16.9 cy
bank, 22 cy loose, or 14.4 cy com pacted. Each truckload w eighs 115,495 lb.
EXCAVATING BY HAND
Numerous types and sizes of excavating equipment are available. The selection
of excavating equipment for a particular project depends on many factors: the
type and quantity of material to be excavated, the depth of excavation, the
amount of groundwater in the construction area, the required haul distance, and
the space available for operation of the equipment. For some jobs, space and
working room are not available for excavating equipment to operate, which
requires excavation by laborers.
Generally, it is desirable to use excavating equipment instead of excavation
by laborers; however, at some jobsites the space is not sufficient for equipment
to operate. For example, excavation for a motor-pump foundation for a unit in a
refinery may be located in a confined space that prevents access by an excava
tor. An excavator may be able to access an excavation area, but may not be able
to operate because of an overhead pipe rack that blocks the clearance necessary
for the equipment to operate. Excavation may be required in an area where there
are numerous underground electric or telephone cables. For each of these situa
tions, excavating by hand methods may be necessary.
124 Estimating Construction Costs
The rate at which a laborer can excavate varies with the type of material,
extent of digging required, height to which the material must be lifted, and cli
matic conditions. If loosening is necessary, a pick is most commonly used.
Lifting is generally done with a round-pointed, long-handled shovel; 150 to 200
shovels of earth are required to excavate 1 cy in its natural state. Representative
rates of excavating and hauling earth are given in Table 7.3.
E X A M P L E 7 .2
EXAMPLE 7 . 3
Estimate the total cost and cost per linear foot for excavating 16,850 ft of trench in
hard clay for an underground cable. The trench will be 9 in. w ide and the average
depth will be 66 in. A rubber-tire-trenching m achine (similar to the one shown in
Fig. 7.1) with 65 hp will be used. The cable will be installed in open terrain so there
will be no major obstructions to retard the progress of the machine. Assume a 45-min
hour to account for normally expected delays.
Probable digging speed:
From Table 7.5, C= 40 for hard clay, and using Eq. [7.5] for speed,
Cx hp
S= Dx W
_ 40 X 65
66 X 9
= 4.4 ft/m in
Cost:
Trenching machine: 88 hr @ $32.50/hr = $2,860.00
Machine operator: 88 hr @ $21.67/hr = 1,906.96
Utility truck: 88 hr @ $7.50/hr = 660.00
Laborer: 88 hr @ $15.56/hr = 1,369.28
Foreman: 88 hr @ $25.00/hr = 2,200.00
Moving equipm ent to and from job = 500.00
Total cost crew = $9,496,24
of the machine. Cutter teeth and buckets are attached to endless chains that travel
along the boom. As the machine advances, the earth is excavated and cast along
the trench. The depth of cut is adjusted by raising or lowering the boom. By
adding side cutters, the width of the trench can be increased. This type of machine
can excavate trenches from 16 to 36 in. wide and depths up 12 ft. Table 7.7 pro
vides data on ladder-type trenching machines.
EXAMPLE 7 . 4
Estimate the total cost and cost per linear foot for excavating a trench 30 in. w ide
with an average depth of 7 ft. The trench is 2,940 ft long in common earth. A ladder-
type trenching machine will be used, There will be no obstructions to retard the
progress of the machine. Assume an efficiency of 45 min per hour. Table 7.7 indi
cates a d igging speed between 30 and 60 ft/hr. Assume an average speed of
40 ft/hr.
Time to complete the job:
Time for d igging trench: 2,940 ft/40 ft/hr = 73.5 hr
For a 45-min hr, the time = 73.5 X (60/45) = 98 hr
Rounding to a full 8 -hr day, time = 104 hr
Chapter 7 Earthwork and Excavation 129
Cost:
Trenching machine: 104 hr @ $87.50/hr = $9,100.00
Machine operator: 104 hr @ $21.67/hr = 2,253.68
Laborer: 104 hr @ $15.56/hr = 1,618.24
Foreman: 104 hr @ $25.00/hr = 2,600.00
Pickup truck: 104 hr @ $ 1 2 .00/hr = 1,248.00
Transporting machine to and from job = 1,500.00
Total cost = $18,319.92
handling the material. Draglines are excellent for excavating trenches when the
sides are permitted to establish their angles of repose without shoring.
The size of the dragline is indicated by the size of the bucket, expressed in
cubic yards. Most draglines can handle more than one size bucket, depending on
the length of boom and class and weight of material excavated. If the material is
difficult to excavate, the use of a smaller bucket will reduce the digging resis
tance, which may permit an increase in production rate.
The dragline will produce its greatest output if the job is planned to permit
excavation at the optimum depth of cut where possible. Table 7.8 gives ideal
outputs, in bank cubic yards, for short-boom draglines when excavating at opti
mum depth of cut with an angle of swing of 90°, based on a 60-min hour. The
upper figure is the optimum depth in feet and the lower number is the ideal out
put in cubic yards, with no delays. Table 7.9 gives adjustment factors that can
be used to determine outputs for other depths and angles of swing. The produc
tion rates determined from Tables 7.8 and 7.9 must be corrected for an efficiency
less than 60 min/hr.
Size of bucket, cy
Class of material 3
8
1
2
3
4 1 1| 12
n 4 2 2|
Moist loam or light 5.0 5.5 6.0 6.6 7.0 7.4 7.7 8.0 8.5
sandy clay* 70 95 130 160 195 220 245 265 305
Sand and gravel* 5.0 5.5 6.0 6.6 7.0 7.4 7.7 8.0 8.5
65 90 125 155 185 210 235 255 295
Good common earth* 6.0 6.7 7.4 8.0 8.5 9.0 9.5 9.9 10.5
55 75 105 135 165 190 210 230 265
Hard, tough clay* 7.3 8.0 8.7 9.3 10.0 10.7 11.3 11.8 12.3
35 55 90 110 135 160 180 195 230
Wet, sticky clay* 7.3 8.0 8.7 9.3 10.0 10.7 11.3 11.8 12.3
20 30 55 75 95 110 130 145 175
Angie of swing
Percentage of
optimum depth 30° 45° 60° 75° 90° 120° 150° 180°
20 1.06 0.99 0.94 0.90 0.87 0.81 0.75 0.70
40 1.17 1.08 1.02 0.97 0.93 0.85 0.78 0.72
60 1.24 1.13 1.06 1.01 0.97 0.88 0.80 0.74
80 1.29 1.17 1.09 1.04 0.99 0.90 0.82 0.76
100 1.32 1.19 1.11 1.05 1.00 0.91 0.83 0.77
120 1.29 1.17 1.09 1.03 0.98 0.90 0.82 0.76
140 1.25 1.14 1.06 1.00 0.96 0.88 0.81 0.75
160 1.20 1.10 1.02 0.97 0.93 0.85 0.79 0.73
180 1.15 1.05 0.98 0.94 0.90 0.82 0.76 0.71
200 1.10 1.00 0.94 0.90 0.87 0.79 0.73 0.69
EXAMPLE 7 . 5
Estimate the total cost and cost per cubic yard for excavating a drainage ditch 10 ft
w ide at the bottom, 36 ft w ide at the top, 12 ft deep, and 15,100 ftlong in good com
mon earth. The excavated earth can be cast on one or both sides of the ditch. Use
a 1g cy dragline and an average angle of swing of 120°. It will require 2 days to set
up and remove the dragline. Two laborers will assist the excavating operation, which
will be supervised by a foreman. Assume the dragline will operate an average of
45 min/hr.
Quantity of material:
Volume of earth = \ (10 ft + 36 ft) X 12 feet x 15,110 ft = 4,170,360 cf
Converting to cubic yards, 4,170,360 cf/(27cf/cy) = 154,458 cy, bank measure
Production rate:
From Table 7.8, the ideal output = 190 cy/hr bank measure
From Table 7.8, the optimum depth of cut is 9.0 feet
Percent of optimum = 12.0 ft/9 ft = 1.33, or 133%
From Table 7.9, for 133% optimum and 120° angle of swing, the depth-swing
adjustm ent factor will be 0.89
60-min hour production rate = 0.89 (190 cy/hr) = 169.1 cy/hr
45-min hour production rate = 169.1 cy/hr (45/60) = 126.8 cy/hr bank measure
Time:
Time required to excavate the earth = 154,458 cy/126.8 cy/hr = 1,218 hr
Cost:
Costs during dragline operation:
Dragline: 1,218 hr @ $87.69/hr = $106,806.42
M achine operator: 1,218 hr @ $21.67 = 26,394.06
Laborers: 1,218 hr x 2 laborers @ $15.56/hr = 37,904.16
Foreman: 1,218 hr @ $25.00/hr = 30,450.00
Cost to set up and remove dragline:
Operator: 16 hr @ $21.67/hr = 346.72
Laborers: 16 hr x 2 laborers @ $15.56/hr = 497.92
Foreman: 16 hr @ $25.00/hr = 400.00
Cost to move dragline to and from the job = 2,500.00
Total direct cost = $204,999.28
suited for lifting materials vertically from one location to another, such as
depositing material in hoppers and overhead bins. The vertical movement capa
bility can be relatively large when clamshells are used with long crane booms.
A clamshell is not effective in loosening solid earth, such as compacted earth,
clay, and other solid materials.
The bucket is lowered into the material to be handled with the jaws open. Its
weight will cause the bucket to sink into the material as the jaws are closed.
Then it is lifted vertically, swung to the emptying position, over a truck or to
spoil, and the jaws are opened to permit the load to flow out. The clamshell oper
ator controls all these operations.
The size of the clamshell is indicated by the size of the bucket, expressed in
cubic yards. Manufacturers supply buckets either with removable teeth or with
out teeth. Teeth are used in digging the harder types of materials, but are not
required when a bucket is used for handling purposes.
The output of the clamshell is affected by the looseness of the materials
being handled, type of material, height of lift, angle of swing, method of dis
posing of the materials, and skill of the operator. Because of the variable factors
that affect the operations of a clamshell, it is difficult to give dependable pro
duction rates. For example, if the material must be discharged into a hopper, the
time required to spot the bucket over the hopper and to discharge the load will
be much greater than when the material is discharged freely onto a large stock
pile. The values given in Table 7.10 are approximate outputs of clamshells of
different sizes for various angles of swing. To accurately estimate the produc
tion rate of a clamshell, a cycle time should be determined based on job condi
tions and operating specifications for the equipment. Manufacturers provide
operating specifications, such as speed of the hoist line and swing speed.
T A B L E 7 .1 0 I Approximate output of clamshells, cy/hr.
Type of material
Size of Angle of
bucket, swing, Light Sand Crushed
cy deg. loam gravel stone
3
4 45 63 56 49
90 53 48 42
180 41 37 32
1 45 81 73 63
90 68 61 53
180 54 48 42
2 45 134 120 104
90 113 102 88
180 87 78 68
EXCAVATING WITH
HYDRAULIC EXCAVATORS
There are two basic types of hydraulic excavators, depending on their type of
digging action. Hydraulic excavators that have their digging action in an upward
Chapter 7 Earthwork and Excavation 133
direction are called front shovels, or simply shovels. Hydraulic excavators that
have their digging action in a downward direction are called by several names,
such as hoe, backhoe, or trackhoe.
FRONT SHOVELS
Front shovels maneuver on tracks, similar to bulldozers, because they are used
mostly in pit excavations of rock quarries (Fig. 7.4). When operating on rock, a
track has a longer life than rubber tires. Shovels are used mostly for pit excava
tion where the bucket load is obtained from the vertical face of the excavation
pit above and in front of the excavator. The excavated material is loaded into
trucks and hauled to another location.
Shovels are excavating machines that can handle all classes of earth without
prior loosening; but in excavating solid rock it is necessary to loosen the rock
first, usually by drilling holes and discharging explosives in them. The exca
vated material is loaded into trucks or tractor-pulled wagons, which haul it to its
final destination. For the shovel to maintain its maximum output, sufficient haul
ing units must be provided.
In estimating the output of a shovel, it is necessary to know the class of earth
to be excavated, the height of cut, the ease with which hauling equipment can
approach the shovel, the angle of swing from digging to emptying the bucket,
and the size of the bucket.
There are four elements in the production cycle of a shovel: load bucket,
swing with load, dump load, and return swing. Adding the time of these ele
ments provides the cycle time of the shovel. The production rate can then be
determined by dividing the bucket capacity by the cycle time. The best method
for determining cycle times is to develop historical data for a particular type of
machine and job conditions. Table 7.12 provides the range of element times for
shovels with bucket sizes ranging from 3 to 5 cy. A 30- to 45-min productive
hour should be applied to these values.
T A B L E 7 .1 3 I Conversion factors for depth of cut and angle of swing for a power
shovel.
Angle of swing
Percentage of
optimum depth 45° 60° 75° 90° 120° 150° 180°
40 0.93 0,89 0.85 0.80 0.72 0.65 0.59
60 1.10 1.03 0.96 0.91 0.81 0.73 0.66
80 1.22 1.12 1.04 0.98 0.86 0.77 0.69
100 1.26 1.16 1.07 1.00 0.88 0.79 0.71
120 1.20 1.11 1.03 0.97 0.86 0.77 0.70
140 1.12 1.04 0.97 0.91 0.81 0.73 0.66
160 1.03 0.96 0.90 0.85 0.75 0.67 0.62
EXAMPLE 7 . 6
Estimate the probable output of a 4-cy shovel for excavating common earth. For this
shovel, the maximum digging height is 34 ft. The average face of cut is 15 ft.
Assume a 120° angle of swing for the shovel to load the haul units. Assume an effec
tive 35-min hour for the excavation operation.
136 Estimating Construction Costs
Cycle time:
From Table 7.12, using median values
Load bucket = 8 sec
Swing with load = 5 sec
Dump bucket = 3 sec
Return swing = 4 sec
Total time = 20 sec/cycle
Cycles per min = (cycle /20 sec) x (60 sec/m in) = 3 cycles/m in
Production rate:
Bucket fill factor for common earth from Table 7.11 = 105%
Average bucket payload, 4.0 cy x 105% = 4.2 cy
Ideal production rate = (4.2 cy/cycle) x (3 cycles/m in) = 12.6 cy/min
Adjustm ent for 110% optimum depth of cut and 120% angle of swing
From Table 7.13, adjustm ent factor = 0.87
Probable production rate = (384 cy/hr)/( 1 + 0.25) = 307 cy/hr bank measure
expressed as struck or heaped. The struck capacity is the volume that a unit will
hold when it is filled even with, but not above, the sides. This volume depends
on the length, width, and depth of the unit. The heaped capacity is the volume
that a unit will hold when the earth is piled above the sides. Although the struck
capacity of a given unit is fixed, the heaped capacity will depend on the depth
of the earth above the sides and on the area of the bed. The Society of
Automotive Engineers (SAE) specifies the heaped capacity based on a 1:1
slope of the earth above the sides. The actual capacity of a unit should be deter
mined by measuring the volume of earth in several representative loads, then
using the average of these values. Units are available with capacities varying
from 12 to 30 cy.
Since shovel production rates are normally calculated in bank measure, it is
desirable to express the loose volume of hauling trucks in bank measure.
Equation [7.1] can be used for converting the loose measure to bank measure.
For example, if a 15-cy truck is hauling ordinary earth that has a swell of 25 per
cent, the bank measure will be 15 cy/(l + 0.25) = 12 cy.
The size of the hauling units should be balanced against the bucket capacity
of the shovel. For best results, considering output and economy, the capacity of
a hauling unit should be four to six times the bucket capacity.
The volume that a truck can haul in a given time depends on the volume per
load and the number of trips it can make in that time. The number of trips
depends on the distance, speed, time at loading, time at the dump, and time
required for servicing. Higher travel speeds are possible on good open highways
than on streets with heavy traffic. For example, top speeds in excess of 65 mph
may be possible on some paved highways, whereas speeds on crowded city
streets may be not more than 10 to 15 mph. Delays can occur at loading, dump
ing, and servicing trucks. Therefore, the actual operating time may be only 45 or
50 min/hr. An appropriate multiplier should be applied in determining the num
ber of trips per unit of time.
EXAMPLE 7 . 7
Assume the shovel and job conditions given in Example 7.6 apply to a project that
requires excavation and hauling of 58,640 cy, bank measure, of comm on earth. The
production rate of the shovel was calculated as 307 cy/hr, bank measure. The earth
will be hauled 4 mi by 20-cy, loose measure, trucks at an average speed of 30 mph.
The expected time at the dum p is 4 min. The truck time waiting at the shovel to move
into loading position will average 3 min. Assume a 45-min hour and calculate the
total cost and cost per cubic yard based on using sufficient trucks to balance the
production rate of the shovel.
Quantity of work:
Volume of earth = 58,640 cy, bank measure
Volume of truck = 20 cy (1 + 0.25) = 16 cy, bank measure
138 Estimating Construction Costs
BACKHOES
Backhoes are used to excavate below the natural surface, such as trenches, base
ments, and general excavation that requires precise control of depths (Fig. 7.5).
A backhoe may be a wheel type or track type. Track-type backhoes are com
monly called trackhoes.
Backhoes have become one of the most widely used types of excavating
equipment. Because of their rigidity, they are superior to draglines for loading
Chapter 7 Earthwork and Excavation 139
into dump trucks. Due to their direct pull of the bucket, they can exert greater
tooth pressure than shovels. For some job conditions, they are superior to trench
ing machines, especially for digging utility trenches whose banks are permitted
to establish natural slopes and for which trench shoring will not be used.
Backhoes can remove the earth as it caves in to establish natural slopes, whereas
trenching machines cannot do this easily.
The production rate depends on the bucket payload, average cycle time, and
job efficiency. If an estimator can predict the excavator cycle time and the
bucket payload, the probable production rate for excavation can be determined.
The cycle time will depend on the particular job conditions, such as the diffi
culty in loosening the soil, the angle of swing, the size of the truck that the back
hoe must load, and the skill of the operator. The estimator must use judgment
and knowledge of actual job conditions to predict the cycle time for a particular
job. Table 7.14 provides representative cycle time for backhoes under average
conditions.
The average bucket payload is equal to the heaped bucket capacity payload
multiplied by the bucket fill factor. The bucket fill factor will depend on the type
of soil to be excavated. Table 7.15 provides representative values of the bucket
fill factor for backhoes.
EXAMPLE 7 . 8
Estimate the probable output of a 2-cy backhoe for excavation of hard, tough clay.
Assume a swell of 30 percent and a 45-min. hour for the backhoe.
Cycle time:
From Table 7.14,
Load bucket = 6 sec
Swing loaded = 3 sec
Dump bucket = 3 sec
Return swing = 4 sec
Total time = 16 sec/cycle
1? 1 5 0 -3 0 0
1| 1 5 4 -3 6 0
1? 1 8 0 -4 2 0
2 2 0 5 -4 2 0
ol 2 3 1 -4 7 2
^4
from the cycle time; the time required to load, haul, dump, and return. An appro
priate efficiency factor, such as a 45- or 50-min hour, should be used in deter
mining the number of trips per hour, to allow for nonproductive time. Frequently
it is desirable to express the speed of a scraper in feet per minute as well as miles
per hour. A speed of 1 mph is equal to 5,280 ft in 60 min, which equals 8 8 ft/min.
Manufacturers provide data on the typical fixed time of scrapers. The fixed
time is the amount of time to load, maneuver, and spread or dump a load. The
time to load a scraper ranges from 0.4 to 1.1 min, depending on the type of soil
and skill of the operator. A load time of about 0.8 min is reasonable for most
scraper operations. The time to maneuver and spread or dump a load is about
0.7 min. Thus, a reasonable total fixed time to load and dump a scraper is about
1.5 min. The estimator should also evaluate the job conditions at each project
and include a reasonable amount of time for acceleration, deceleration, and turns
that are necessary for a scraper to operate.
Equipment manufacturers also publish production rate charts that show the
production rate with respect to haul distance for a particular size of scraper.
These charts are valuable to the estimator when multiple haul distances are
involved in a scraper operation, such as multiple cut and fill balance points in
mass diagrams of highway projects.
EXAMPLE 7 . 9
Estimate the probable production rate for a scraper whose struck ca pacity is 14 cy,
loose measure. The material will be common earth with a swell of 25 percent. An
evaluation of the haul road shows an average haul distance of 860 ft and return haul
of 940 ft. Based on the condition of the haul road it is anticipated that haul speed is
9 mph loaded and 11 mph empty. From the m anufacturer’s information the load time
is 0.8 min and the dum p time is 0.7 min. Assume 0.5 min for turning, acceleration,
etc. Assume a 45-min productive hour.
Cycle time:
Haul speed: 9 mph x (5280 ft/ mi) x (1.0 hr/60 min) = 792 ft/min
Return speed: 11 mph x (5280 ft/mi) x (1.0 hr/60 min) = 968 ft/min
Load time = 0.80 min
Haul: (860 ft)/(792 ft/min) = 1.08 min
Dump time = 0.70 min
Return: 940 ft/968 ft/min. = 0.97 min
Turns, acceleration, etc. = 0.50 min
Total cycle time = 4.05 min/trip
Production rate:
Number of trips per hour: (1 trip/4.05 min) x (45 min/hr) = 1 1 . 1 trip/hr
Volume per hour: 11.1 trips/hr x 14 cy/trip = 155.4 cy/hr loose measure
For a 25% swell, (155.4 cy/hr)/(1 + 0.25) = 124.3 cy/hr bank measure
144 Estimating Construction Costs
Thus, it appears that a bulldozer can assist 5 scrapers. Assuming that a bulldozer
can assist 5 scrapers, then one-fifth (0.20) of the cost of a bulldozer should be
charged to each scraper. The hourly cost will be
If job records are available from previously completed projects, the produc
tion rate of scrapers can be estimated by load counts. A load count is simply the
number of loads a scraper can haul in a day of operation. Using this method, his
torical data are obtained from actual jobs that provide the number of loads per
day for a particular size scraper and haul distance. For example, job records may
show that an 18-cy scraper can haul 42 loads per day for a haul distance between
1,200 and 1,500 ft. Thus, the production rate can be calculated as
The same procedure can be used on an hourly basis. For example, the number of
loads per hour can be multiplied by the capacity of the scraper. Then, the cost per
cubic yard can be estimated by dividing the hourly cost of a scraper by the hourly
production rate to obtain the cost per cubic yard for the scraper operation.
Chapter 7 Earthwork and Excavation 145
Existing grade
EXAMPLE 7 .1
Determine the total cost and the cost per cubic yard for the earthwork of the first bal
ance point of the mass diagram in Fig. 7.8. A self-loading scraper with a struck
capacity of 15 cy will be used to excavate and haul the soil. The scraper has a load
146 Estimating Construction Costs
time of 0.8 min and dump time of 0.7 min. Assume an 18 mph haul speed and a 22
mph return speed. The material is common earth, with a swell of 25 percent.
The mass diagram can be arbitrarily divided into three 200-cy sections. For
each section the average haul distance can be determined from the diagram. The
haul distance, cycle time, number of trips per 45-min hour, quantity hauled per trip,
production rate, and time required for each section will be:
Quantity hauled per trip:
Capacity of scraper = 15 cy loose measure
However, from Eq (7.1),
15cy-(' *§j)B
B - 12 cy bank measure
Quantity Pro
Quan Dis hauled duction Total
Sec tity, Cycle time, min per trip, rate, time,
tance,
tion cy ft Load Haul Dump Return Total cy cy/hr hr
1 200 2,000 0.8 1.26 0.7 1.03 3.79 12 142.8 1.4
II 200 3,400 0.8 2.14 0.7 1.76 5.40 12 99.6 2.0
III 200 4,300 0.8 2.71 0.7 2.22 6.43 12 84.0 2.4
600 cy Total time = 5.8 hr
rollers, vibrating rollers, or other types of equipment. For some projects, the best
results are obtained by using more than one type of equipment. Regardless of the
type of equipment selected, there should be enough units to shape, wet, and
compact the earth at the rate at which it will be delivered.
EXAMPLE 7 .1 1
Estimate the total cost per cubic yard for shaping, sprinkling, and compacting earth
in a fill such as a dam or highway. Scrapers at a rate of 465 cy/hr, bank measure,
will place the earth. Assume a 15 percent shrinkage factor. The earth will be placed
in layers not to exceed 6 in. thick when compacted. The moisture content will aver
age 8 percent when the earth is placed in the fill, but it must be increased to 12 per
cent during the compaction operation. The water will be transported to the fill area
by trucks with water sprinklers.
Estimating Construction Costs
A motor grader with a 12-ft blade should cover a strip or lane whose effective width
will be about 8 ft for each pass of the grader. The grader should be able to travel at
an average speed of at least 2 mph, allowing for stops and lost time turning around.
The area covered by 1 hr by a grader should be
Production rate of grader: 2 mph X 5,280 ft/mi X 8 ft = 84,500 sf/hr
Since the production rate of 84,500 sf/hr for the grader to spread the load is greater
than the 21,330 sf/hr that the scrapers will be delivering the soil to the compaction
area, one grader is sufficient to do the job.
Compaction:
The earth will be compacted by sheep’s-foot rollers pulled by a tractor. It is esti
mated that 10 passes will be required to attain the specified compaction. The equiv
alent area that the rollers must cover in 1 hr will be
Required area for the compactor: 10 passes x 21,330 sy/hr = 213,300 sf/hr
If roller drums are 4 ft long and are operated at an average speed of 2 | mph, allow
ing for lost time, the area covered by one drum in 1 hr will be
Production rate of compactor: 2 f mph x 4 ft x 5,280 ft/mi = 58,080 sf/hr
Since water weighs 62.4 lb/cf and there are 7.48 gal/cf, (62.4 gal/cf)/(7.48 gal/cf) =
8.34 lb/gal
If a 2,000-gal sprinkler truck can make one trip in 40 min, the production rate of
a single sprinkler truck will be
Output of sprinkler truck, (2,000 gal/trip/40 min/trip) x (60 min/hr) = 3,000 gal/hr
FIGURE 7 .1 1 I Gasoline-engine-
operated hand drill.
to the lower end of a drill stem (see Fig. 7 .14). Either water or compressed air
can be used to remove the rock cuttings.
ANFO is frequently used as the explosive, although several other types of
explosives are available. Dynamite is available in sticks of varying sizes, which
are placed in the holes. The strength, which is specified as 40, 60, etc., percent,
indicates the concentration of the explosive agent, which is nitroglycerin. The
dynamite is usually exploded by a blasting cap, which is detonated by an elec
tric current. At least one blasting cap is required for each hole. The charges in
several holes can be shot at one time.
The amount of ANFO required to loosen rock will vary from about 0.25 to
more than 1 Ib/cy, depending on the type of rock, the spacing of holes, and the
degree of breakage desired.
compressor, and hose. Since each of these items may have a different life, it
should be priced separately.
Drill steel is purchased by size, length, and quality of steel used, with the
cost of steel based on its weight. While the life of a drill steel will vary with the
class of rock drilled and the conditions under which the steel is used, records
from drilling projects show consumptions varying from ^ to ^ lb/cy of rock to
be representative, with the higher consumption applicable to the harder rocks.
Thus, if a drill steel for a wagon drill, 12 ft long, weighing 4.6 lb/ft, whose total
weight is about 55 lb, is consumed at the rate of ^ lb/cy of rock, this steel should
drill enough hole to produce about 660 cy of rock.
Detachable bits are commonly used with jackhammers, drifters, and wagon
drills. The depth of hole that can be drilled with a bit before it must be resharp
ened or discarded will vary considerably with the class of rock and the type of
bit, with values ranging from less than a foot to as much as 1 0 0 ft or more for
steel bits. Bits with carbide inserts will give much greater depths.
TAB LE 7 .17 I Representative rates of drilling rock with various types of drills.
Holes should be drilled 1 ft, or more, deeper than the desired effective depth
of rock loosened. This is necessary because the rock usually will not break to the
full depth of the holes over the entire area blasted.
EXAMPLE 7 . 1 2
Estimate the cost of drilling and blasting limestone rock. An analysis of the job indi
cates that 3-in.-diameter holes will be drilled 14 ft deep at a spacing of 8 ft by 8 ft.
Two medium-size wagon drills will be used for the drilling at a rate of 24 ft/hr each.
It is anticipated that 1.0 lb of ANFO will be required to loosen each cubic yard of
rock. Base all quantities and costs on operating 1 hour.
Job requirements:
Diameter of holes: 3 in.
Depth of holes: 14 ft
Effective depth of holes: 13 ft
Spacing of holes: 8 ft X 8 ft
Equipment and production rates:
Two medium-size wagon drills will be used, each with 50 ft of 1^-in. hose and
connections
Estimated rate of drilling: 24 ft/hr
Total production rate: 2 drills x 24 ft/hr = 48 ft/hr
Effective depth of hole drilled: 48 ft/hr x 13/14 = 44.6 ft/hr
Volume of rock produced: (44.6 ft X 8 ft x 8 ft)/(27cf/cy) = 106 cy/hr
Number of holes drilled per hour: (48 ft/hr)/(14 ft/hole) = 3.44 holes/hr
Materials for drilling and blasting:
ANFO required: 1.0 Ib/cy of rock
Unit cost of explosive: $1.75/lb
Cost of bits: $24.10 each
Number of times sharpened: 3
Cost of sharpening bit: $3.15 each time
Depth of hole before sharpening bit: 36 ft
Drill steel consumed: ^ Ib/cy of rock
The estimated hourly cost for drilling and blasting are calculated as
Drill bit consumption and cost:
Original cost of bit: each = $24.10
Sharpening: 3 x $3.15 = 9.45
Total cost per bit = $33.55
Number of uses per bit: original bit + 3 sharpenings = 4 uses/bit
154 Estimating Construction Costs
PROBLEMS
7.1 A truck will haul an average load of 12-cy, heaped capacity, loose measure per
load. Determine the volume in band measure when the material is sand, ordinary
earth, dense clay, and well-blasted rock.
7.2 Earth whose bank measure is 100 lb/cf has a swell factor of 25 percent. The
earth is loaded in a 45,000-lb empty weight truck that has a struck capacity of
15 cy loose measure.
a. What is the total vertical weight, truck plus payload?
b. If the shrinkage factor is 10 percent, what is the volume of earth in the
compacted fill?
Chapter 7 Earthwork and Excavation 155
7.3 Estimate the total direct cost and the cost per foot for excavating a sewer trench
20 in. wide, 48 in. deep, and 3,480 ft long in firm clay by using an 85 hp trench
ing machine. Use the data shown in Tables 7.4 and 7.5 to determine the produc
tion rate of the trencher. It will cost $1,800.00 to transport the machine to the
job, get it ready to operate, then return it to the storage yard.
There will be no obstructions to delay the machine. Assume a 50-min hour
efficiency for the trenching operation. This crew and the specified hourly wage
rates will apply:
Trenching machine $38.50/hr
Trencher operator $21.72/hr
Utility truck $7.85/hr
Laborer $15.56/hr
Foreman $26.00/hr
7.4 What is the maximum length of trench that can be excavated by hand economi
cally rather than by a trenching machine? It will cost $900.00 to transport a
trenching machine to the job and back to the storage yard. The trenching
machine can excavate 265 lin ft/hr.
Use hand excavation data from Table 7.3 to obtain the production rates to
loosen earth with a pick, shovel earth from the trench, and shovel earth back
from the edge of the trench. Assume that 4 laborers plus a foreman will be used.
Assume a 40-min hour for the hand labor operation and a 45-min hour for the
trenching machine. The following cost information applies:
Trenching machine $42.82/hr
Trencher operator $20.45/hr
Laborers, each $ 16.65/hr
Foreman $28.30/hr
7.6 A project requires 692,500-cy, bank measure, of rock-earth mixture, which will
be excavated by a 2-cy front shovel. The material will be loaded into 15-cy,
loose measure truck, and hauled 4 mi to the project. The trucks will average
25 mi/hr loaded and 30 mi/hr empty.
The front shovel can excavate the rock-earth mixture at the optimum depth
of cut and at a 120° average angle of swing. It will cost $2,400 to transport the
shovel to the job, set it up to operate, and return it to the storage yard.
Estimate the total cost and the cost per cubic yard, bank measure, for exca
vating and hauling the earth. Assume that the shovel and trucks will operate at a
45-min/hr efficiency. Determine the economical number of trucks to balance the
production rate of the backhoe with the hauling rate of the trucks. This cost
information applies:
Front shovel $105.00/hr
Trucks, each $34.85/hr
Shovel operator $23.50/hr
Truck drivers, each $19.75/hr
Foreman $29.80/hr
7.7 A Ij-cy dragline will be used to excavate a ditch in dense clay. The ditch will be
trapezoidal in cross section, 16 ft wide at the bottom, 36 ft wide at the top, 8 ft
deep, and 6,480 ft long.
There will be no obstructions to affect the rate of excavating the earth. The
excavated earth will be cast along the edge or edges of the ditch. The average
angle of swing will be 145°. Assume a 50-min hour efficiency. It will cost
$3,200 to transport the dragline to the job, set it up for operation, and return it to
the storage yard. Estimate the total cost and the cost per cubic yard, bank mea
sure, for excavating the ditch. This cost information applies:
Dragline $74.50/hr
Operator $21.97/hr
Foreman $27.35/hr
7.8 Ordinary earth will be excavated and hauled by scrapers, whose capacities are
14 cy struck and 18 cy heaped, loose measure. The distance from the borrow pit
to the dumpsite will average 2,680 ft over a level earth haul road. The scrapers
can average 15 mi/hr loaded and 20 mi/hr empty.
The fixed time for the scraper, including loading, dumping, turning, waiting
to load or dump, etc., should average about2\ min per trip.Assume an average
capacity of scrapers of 16 cy loose measure.Use a swell factor of 25 percent for
the ordinary earth.
One dozer will be used to assist the scrapers in loading. For this project,
determine the number of scrapers that one dozer can serve. It is expected that it
will require from 50 to 70 sec to load a scraper with the assistance of the dozer.
Thus, a dozer should be able to serve a scraper about every 2\ to 3 min.
Assume a 50-min hour efficiency and estimate the cost per cubic yard using
this cost information:
Scrapers $68.25/hr
Dozer $59.20/hr
Operators $21.25/hr
Chapter 7 Earthwork and Excavation 157
7.9 To construct a fill, it is necessary to excavate ordinary earth and haul it 1,800 ft
along an approximately level haul road. The earth will be excavated and hauled
by 15-cy, loose measure, self-loading scrapers. The scrapers will average
12 mi/hr loaded and 18 mi/hr empty. The fixed time, including loading, dump
ing, and waiting in the pit, will average 2\ min per trip. Assume a 50-min hour
efficiency.
Assume a swell factor of 25 percent and estimate the probable direct cost
per cubic yard, bank measure, for excavating and hauling the earth. This cost
information applies:
7.10 Estimate the total time and cost and the cost per cubic yard for the second bal
ance point, sections IV and V, of the mass diagram in Fig. 7.8. A self-loading
scraper with 12-cy loose measure capacity will be used for the excavating and
hauling.
Assume an average haul speed of 15 mi/hr and an average return speed of
20 mi/hr. Use a 2^-min load time and a 2-min dump time. Assume a 50-min
hour efficiency and a swell of 8 percent. The hourly cost of equipment and labor
will be
Scraper $65.40/hr
Operator $21.85/hr
Foreman $27.20/hr
7.11 A compacted fill is being built with two sheep’s-foot drum rollers, 5 ft wide,
operating at 1.5 mi/hr. Four passes are required to obtain the 5-in. depth of com
pacted fill to meet the specifications density. Your company has a spread of
15-cy, loose measure, trucks to haul the fill dirt to the compacted area. Analysis
of the soil conditions indicates a 15-cy loose measure truck is equivalent to
10.8-cy compacted measure.
a. If the cycle time of a single truck is 15 min, how many trucks are required?
b. If 140,000 cy of compacted fill are required using the type of compaction
drums described, how many drums are required if the project is to be
completed in 25 working days?
Highways and Pavements
OPERATIONS INCLUDED
The chapter is organized into three parts: clearing land, concrete pavem ents, and
asphalt pavem ents. E ven though the coverage is lim ited to only a few o f the
m ethods used, the discussion and exam ples presented illustrate how estim ates
can be prepared for projects constructed by other methods.
1. C om plete rem oval o f all trees and stum ps, including tree roots
2. Rem oval o f all vegetation above the surface o f the ground only, leaving
the stum ps and roots in the ground
3. D isposal o f the vegetation by stacking and burning it
Light Clearing
L ight clearing includes rem oval o f vegetation up to 2 in. in diam eter. If the clear
ing involves only cutting at or above ground level, axes, m achetes, brush hooks,
and w heel-m ounted circular saws can be used. H eavy-duty sickle m ow ers are
available for rem oval o f vegetation up to 1 \ in. in diam eter. T ractor-m ounted
circular saws are also used.
158
Chapter 8 Highways and Pavements 159
W hen the vegetation m ust be knocked dow n to the ground, a bulldozer blade
is com m only used. A small- to interm ediate-size bulldozer is generally adequate.
Also, an anchor chain draw n betw een tw o craw ler tractors can be used to clear
the land. O ften light clearing includes incorporating the cleared vegetation into
the soil. D isc plow s and disc harrow s are used for this purpose. The ground is
w orked w ith the plow s and harrow s to blend the cleared m aterial with the soil.
Intermediate Clearing
F or vegetation from 2 to 8 in. in diam eter, a bulldozer blade, shearing blade, or
angling blade can be used. F or clearing the vegetation at the ground level, the
equipm ent m ay include pow er chain saws, tractor-m ounted circular saws, and
single scissor-type tree shears. H ydraulic cylinders that cut the trees at ground
level operate the scissor shear.
A bulldozer w ith a V blade is effective for shearing trees, stumps, and brush
at ground level. T he special V blade has a protruding stinger at its lead point, as
illustrated in Fig. 8.1. The dozer m oves at a steady speed as the blade slides
along the surface o f the ground, cutting vegetation flush w ith the surface and
casting the rem oved m aterial to the sides.
Large Clearing
F or vegetation o f 8 in. in diam eter and larger, bulldozers w ith special blades are
generally used. B efore felling large trees, the bulldozers m ust excavate the earth
from around the trees to cut the m ain roots. W hen stacking the felled trees and
other vegetation, bulldozers transport earth into the piles o f trees, w hich m akes
burning m ore difficult.
A variety o f rakes are available that attach to the front o f bulldozers for land
clearing. They can penetrate the soil to rem ove sm all stum ps, rocks, and roots.
Figure 8.2 illustrates a tractor-m ounted rake that can be used to group and pile
Width of cut is the effective working width of the equipment, measured per
pendicular to the direction of tractor travel. The width of cut for clearing may
not be the same as the rated width of the blade. An angle blade is not equivalent
to the width of the blade. Even when working with a straight blade, it may not
be the same as the blade width. Although the width of cut is sometimes esti
mated as a percentage of the rated width, it is better to measure the width of cut
on the job.
EXAMPLE 8 .1
A 165-hp crawler tractor will be used to clear small trees and brush from a 25-acre
site. By operating in first gear, the tractor should be able to maintain a continuous
forward speed of 0.9 mph. An angle-clearing blade will be used. From past experi
ence the average effective width of cut will be 8 ft. Assume normal efficiency, and
estimate the time required to clear the vegetation.
Chapter 8 Highways and Pavements 161
Quantity of work:
Clearing light vegetation = 25 acres
Production rate:
width of cut (ft) x speed (m ph)
Production rate (a cre /h r) = ---------------------- —---------------------- [ 8 .2]
= (8 ft) x (0.9 m ph )/1 0
= 0.72 acres/hr
TABLE 8.1 I Production factors for felling trees with Rome K/G blades.
Diameter range
Base minutes
Tractor, per acre, 1-2 ft, 2-3 ft 3-4 ft, 4-6 ft, >6 ft,
hp B* M, m2 m3 m4 F
*0 is based on power-shift tractors working on reasonable level terrain, (10%) maximum grade, with good footing
and not stones and an average mix of soft and hardwoods.
Source: Caterpillar, Inc.
162 Estimating Construction Costs
2-3 ft
3 -4 ft
4 -6 ft
5. Sum of diameter of all trees per acre above 6 ft in diameter at the
ground level
E X A M P LE 8.2
Trees must be cleared for a highway project. The site is reasonably level terrain with
firm ground and less than 25 percent hardwood. A 215-hp tractor equipped with a
K/G blade will be used to fell trees. The highway specifications require the grubbing
Chapter 8 Highways and Pavements 163
of tree stum ps greater than 12 in. in diameter. Estimate the production rate to fell the
trees. A field survey has been conducted and these data have been collected:
Average num ber of trees per acre = 700
Number of 1- 2 ft dia. = 150 trees
Number of 2 -3 ft dia. = 18 trees
Number of 3 -4 ft dia. = 7 trees
Number of 4 -6 ft dia. = 3 trees
Sum of diameter increments above 6 feet = none
Input data based on the field survey:
H = 0.7 based on percentage of hardwoods,< 25% hardwoods
A = 2.0 based on dense num ber of trees, > 600 trees/acre
Production factors from Table 8.1:
B= 23.48 for 215-hp tractor
= 0.5 for 1- to 2-ft-dia. trees
M2 = 1.7 for 2 - to 3-ft-dia. trees
M3 = 3.6 for 3- to 4-ft-dia. trees
M4 = 10.2 for 4- to 6-ft-dia. trees
F = 3.3 for diam eter of increments above 6 ft
Production rate to fell trees:
Time (m in/acre ) = H[A(B) + + M2NZ + M3N3 + M4N4 + DF] [8.3]
= 0.7[2,0(23.48) + 0.5(150)
= 208.4 m in/acre
Because the operation will include grubbing, the time must be increased by
25 percent.
60-min hour production rate = 1.25 x 208.4 m in/acre = 260.5 min/acre
Converting to hours/acre = 260.5 m in/acre x hr/60 min. = 4.3 hr/acre
For a 45-min hour, production rate = 60/45 x 4.3 hr/acre = 5.8 hr/acre
Cost:
If the tractor with blade and operator cost $185/hr, the cost per acre of land cleared
can be calculated as
Table 8.2 have the same definitions as when used previously in Eq. [8.3] and
Table 8.1. Piling-up grubbed vegetation increases the total piling-up time by 25
percent.
Time (min/acre) = B + M lN ] + M2N2 + M3N3 + M4N4 + DF [8.4]
Diameter range
Base minutes
Tractor, per acre, 1-2 ft, 2-3 ft 3-4 ft, 4-6 ft, >6 ft,
hp B M, m2 m 3 m4 F
’ Can be used with most types of raking tools and angled shearing blades.
Windrows to be spaced approximately 200 ft apart.
Source: Caterpillar, Inc.
EXAMPLE 8 . 3
The vegetation cut in Example 8.2 is to be piled into a stack for burning. Estimate
the cost for piling-up the cut vegetation.
= 151.5 hr
Because the operation will include grubbing, the time must be increased by
25 percent,
60-min hour production rate = 1.25 x 151.5 m in/acre = 189.4 min/acre
Converting to hours/acre = 189.4 min/acre x hr/60 min, = 3.2 hr/acre
For a 45-min hour, production rate = 60/45 x 3.2 hr/acre = 4.2 hr/acre
Cost:
If the labor and equipm ent cost is $185/hr, the cost per acre for piling and stacking
trees can be calculated.
Cost per acre, $185/hr x 4.2 hr/acre = $777/acre
DISPOSAL OF BRUSH
When brush is to be disposed of by burning, it should be piled in stacks and
windrows, with a minimum amount of earth included. Felled trees and grubbed
brush often have earth around their roots, which impedes burning. Shaking the
Chapter 8 Highways and Pavements 165
rake while transporting the material to piles or into windrows will help remove
the earth.
Because burning is usually necessary while the brush contains considerable
moisture, it may be desirable to provide a continuous external source of fuel and
heat to assist in burning the material. The burner illustrated in Fig. 8.3, which
consists of a gasoline-engine-driven pump and a propeller, is capable of dis
charging the liquid fuel onto the pile.
DEMOLITION
For remodels of buildings or replacement of infrastructures, it is necessary to
remove a portion or all of an existing structure. The time and cost to perform this
work is difficult to estimate because there are many factors that can affect the
work. For example, removal of an existing concrete pavement depends on the
thickness of the slab, amount of reinforcement, state of deterioration of the pave
ment, job conditions, type and size of demolition equipment, and skill of the
operator.
CONCRETE PAVEMENTS
GENERAL INFORMATION
The cost of concrete pavement in place includes the cost of fine-grading the sub
grade; side forms, if required; steel reinforcing, if required; aggregate; cement;
mixing, placing, spreading, finishing, and curing concrete; expansion-joint
material; saw cutting; and shaping the shoulders adjacent to the slab. For most
paving operations, a slip-form paver is used to place the concrete, which elimi-
166 Estimating Construction Costs
nates the need for setting side forms. Some concrete pavements are designed for
construction without reinforcing steel. If the subgrade is dry, it may be neces
sary to wet it before placing the concrete.
If the pavement is not uniformly thick, the average thickness can be deter
mined to find the area of the cross section. This multiplied by the length will
give the volume of concrete required, usually expressed in cubic yards. Payment
for concrete pavement usually is at the agreed price per yard of surface area.
compact the subgrade after the fine-grading is completed, with water added if
necessary.
paving project, more than one setup of the concrete plant may be justified to
reduce the length of haul for the batched materials. A cost study should be made
prior to locating the plant to determine if more than one location is desirable.
Bulk quantities of cement, sand, and aggregate are stored at the jobsite for
the batching operation. The equipment for operating a batch plant will include
bulk cement bins; overhead bins for aggregate storage, equipped with weight
batchers; and a front-end loader or portable conveyors to handle aggregate. The
cement is supplied to the jobsite in bulk quantities from cement transport trucks,
each holding 20 T or more. Small quantities of cement can be purchased in paper
bags, each containing 1 cf loose measure and weighing 94 lb net.
Most concrete batch plants have the capacity to mix about 8 to 12 cy per
batch and can produce from 100 to 400 cy of concrete per hour. A small batch
plant can mix about 20 cy/hr and is used for small jobs, less than 500 cy total. If
the batch is fully mixed at the batch plant, it usually is transported to the job in
dump trucks, or end-dump trailers for slip-form paving. For smaller projects or
for fixed-side-form paving, many contractors load the batched concrete into
mixer trucks, or trucks with open-top agitators, which transport the fresh con
crete to the jobsite. Concrete that is not fully mixed at the batch plant is trans
ported to the job in transit-mixer trucks.
straight edge finish to the surface of the pavement. Figure 8 . 6 shows a slip-form
paving machine in operation.
The tine and cure machine follows the paver and performs two functions. It
produces the desired texture on the surface of the pavement and it applies a cur
ing compound. It provides a microtexture with a burlap drag, a macrotexture
with transverse tines, and applies curing compound to the pavement. Figure 8.7
shows the tine and cure machine in operation.
For a high-production paving operation, a paving train consisting of two
concrete placer spreader machines, one slip-form paver, and two tine and cure
machines can produce up to 500 cy/hr.
placement operation is stopped at the end of a working day. Transverse joints are
at a right angle to the road centerline to allow for expansion and contraction of
the concrete pavement. Longitudinal joints are installed to tie together adjacent
lanes of the pavement. Transverse and longitudinal joints are sawed in the
pavement after the concrete is placed. Figure 8 . 8 shows sections through several
types of joints.
Prior to placing concrete, smooth steel bars called dowels are set at \ the
concrete thickness at the location of transverse joints. The dowels are generally
1 in. in diameter and 24 in. long, spaced at 12 in. on centers along the transverse
joint. For longitudinal joints, §- to f-in.-diameter deformed reinforcing bars are
commonly used, placed at 24 in. on centers.
Transverse joints are sawed across the pavement at spacings that vary from
15 to 20 ft. Longitudinal center joints are installed along the length of the pave
ment usually when the width exceeds 1 2 ft and the thickness is less than 1 2 in.
The width of joints specified may vary from f to \ in., and the depth is normally
\ to 5 of the concrete thickness. It is common practice to perform two saw-
cutting operations. For example, for a 12-in.-thick pavement the first saw cut
might be 5 in. wide and 3 in. deep to control the location of the crack. After about
72 hr a second cut that is \ in. wide and 1 in. deep is made through the first cut.
A backer-rod made of styrofoam is placed in the l-in.-deep cut, then sealant
material is placed.
172 Estimating Construction Costs
2/8 to W
Ll w t |
| T
Filler—* Smooth dowel )
optional \
Curing can also be accomplished by covering the fresh slab with Visqueen
plastic film or waterproof paper to reduce the evaporation of initial water in the
concrete. Burlap or cotton mat can also be used, but they must be kept wet for the
specified time to reduce evaporation of water from the newly placed concrete.
174 Estimating Construction Costs
EXAMPLE 8 . 4
Estimate the total cost and the cost per square yard, for bid purposes, for placing a
concrete pavement 26 ft wide, of 10-in. average thickness, and 5.78 mi long.
Smooth steel dowels will be placed at 12 in. along transverse joints and f-in .
deform ed steel bars will be placed at 24 in. along longitudinal joints. No reinforcing
steel will be placed in the pavement.
A single longitudinal saw cut is required in the center of the pavement, and
transverse saw cuts are required at 15 ft intervals for the full length of the pavement.
Two saw cuts will be made: one will be 25 percent of the depth and § in. wide and
another will be 1 in. deep and \ in. wide.
A portable central-m ix plant will be set up near the m idpoint of the project. The
plant has a capacity of 8 cy/batch. Concrete trucks with a capacity of 8 cy each will
haul the material an average of 2.5 mi at an average speed of 30 mph. A front-end
loader and portable conveyor will be used to charge the aggregate into the bins.
W ater will be obtained from a private pond, requiring a 3-in. gasoline-engine-
operated pum p having a capacity of 20,000 gal/hr. A royalty of $0.42/1,000 gal will
be paid for the water. The water will be hauled an average distance of 3 mi by trucks
whose capacities are 2,500 gal each. The average haul speed is estimated to be 25
mph. It will require 10 min to fill a truck and 10 min. to em pty a truck. The truck driver
will operate the pum p at the pond.
Quantity of materials:
Volume of concrete:
(5.78 mi x 5,280 ft/mi x 26 ft. x 10/12 ft)/(27 cf/cy) = 24,490 cy
Add 5% waste = 1,225 cy
Total = 25,715 cy
Bulk materials:
Cement: (25,715 cy X 526.4 lb/cy)/2,000 Ib/T = 6,768 T
Sand: (25,715 cy x 1,438 lb/cy)/2,000 Ib/T = 18,489 T
Gravel: (25,715 cy x 1,699 lb/cy)/2,000 Ib/T = 21,845 T
Water: (25,715 cy x 39 gal/cy) = 1,002,885 gal
Curing com pound: (88,164 sy/40 sy/gal) = 2,204 gal
Sealing com pound: (83,417 lin ft)/( 125 lin ft/gal) = 667 gal
If the mixer discharges the entire load into one truck, the time per cycle can
be calculated
Charging mixer = 0.75 min
Mixing concrete = 2.25 min
D ischarging mixer = 0.50 min
Lost time = 0.25 min (average time of mechanical problems)
Total cycle time = 3.75 m in/batch
W ater hauled per trip: 2,500 gal/trip x (1.0 trip/0.574 hr) = 4,355 gal/hr
For a 45-min hour: water hauled per trip = 4,355 gal/hr X 45/60 = 3,266
gal/hr
Quantity of water needed for concrete: 96 cy/hr x 39 gal/cy = 3,744 gal/hr
Number of water trucks needed: 3,744/3,266 = 1.1 trucks required
Use 2 water trucks to ensure continuous operation of batch plant.
C ubic yards hauled per trip: 8 cy x (1.0 trip/0.208 hr) = 38.5 cy/hr
For a 45-min hour, production rate = 38.5 cy/hr X 45/60 = 28.8 cy/hr
Number of trucks needed: 96/28.8 = 3.3 trucks required
Use 4 transit mix trucks to ensure a continuous paving operation.
Number of saw crew required: 728 hr/272 hr = 2.7 needed, therefore use 3
crews
Cost to construct the pavement:
Materials costs:
Cement: 6,768 T @ $85/7 $575,280
Sand: 18,489 T @ $ 6 .59/T 121,843
Chapter 8 Highways and Pavements 177
Labor costs:
Batch plant operator: 272 hr @ $24.30/hr = $6,610
Batch plant laborer: 272 hr @ $15.56/hr = 4,232
Front-end loader operator: 272 hr @ $21.67/hr = 5,894
Water truck drivers: 272 hr x 2 drivers @ $ 18.17/hr = 9,884
Mixer truck drivers: 272 hr x 4 drivers @ $ 18.17/hr = 19,769
Fine-grader operator: 272 hr @ $21.67/hr = 5,894
178 Estimating Construction Costs
Taxes:
W orkm an’s com pensation: $19.80 per $100 x $208,046 $41,193
Social security tax: 7.65% X $208,046 15,916
Unemploym ent tax: 4% X $208,046 8,322
Material taxes: 6 % x $1,051,986 63,119
Subtotal of taxes $128,550
ASPHALT PAVEMENTS
AGGREGATES
The load applied to an asphalt pavement is primarily carried by the aggregates
in the mix. The aggregate portion of a mix accounts for 90 to 95 percent of the
180 Estimating Construction Costs
ASPHALTS
The asphalts used in asphalt pavements can be divided into three categories: cut
back asphalts, emulsified asphalts, and asphalt cements. Cutbacks and emulsions
are used mostly for prime coats and stockpiled patching material. Asphalt
cement is the type of asphalt most commonly used for main-line road construc
tion. Liquid asphalt is rated with a performance (PG) system. For example, a
PG64-22 designates the high and low temperature at which an asphalt binder
would be expected to perform satisfactorily.
Cutback asphalt is produced by adding volatile products to asphalt cement.
Emulsified asphalts are a mix of asphalt cement and water, using an emulsifying
Chapter 8 Highways and Pavements 181
agent to control separation. Asphalt cement used as the binder in paving mixes is
usually classified by the AASTHO standard penetration test, which consists of
measuring the depth of penetration into a 77°F asphalt cement sample by a stan
dard 100-gram weighted needle in a 5-sec time duration. The asphalt penetration
grades are 40-50, 60-70, 85-100, 120-150, and 200-300.
The quantity of asphalt binder varies from 4 to 9 percent of the weight of the
finished product. The cost of asphalt materials is highly dependent on the price
of crude oil, which is subject to fluctuating changes. Therefore, it is necessary to
obtain a firm quote from the supplier of asphalt material before preparing a cost.
ASPHALT PLANTS
Hot-mix asphalt is produced in plants that proportion the aggregates, dry them,
and combine them with asphalt cement that has been heated from 275°F to
375°F. There are two types of asphalt plants: batch-type plants and continuous
mixing drum-type plants. They differ only in the way the aggregates are pro
portioned and how the liquid asphalt is mixed with the aggregate.
Batch-type plants have been used for years in the asphalt paving industry.
They are economical for operations that require production of several different
mixes during a single production time frame. Batch-type plants are efficient
because they can rapidly change the production mix with little wasted material.
Continuous mixing drum-type plants can produce higher volumes of output at
faster rates than batch-type plants. Both types of plants require storage bins for
aggregate, a burner for heating the materials, a mixing unit, and dust collectors
to control pollution.
is pumped through spray bars into the pubmill mixer. The mixer is sufficiently
high to allow tracks to pass directly below for loading. Figure 8.10 shows a track
receiving a mix at a batch-type asphalt plant.
asphalt mix is deposited from the silo into a truck and transported to the job
when the paver needs the material.
Another method to help compensate for truck delays at the jobsite and to
ensure continuous operation of the paver is to use a material transfer vehicle (see
Fig. 8.13). Material transfer vehicles are available with capacities of 25 to 30 T
of asphalt mix. This machine operates ahead of the paver to feed the asphalt
material into the paver. As the paver approaches the material transfer vehicle, it
is refilled before the material transfer vehicle moves forward to receive the next
truck discharge. An insert can be installed in the paver, allowing storage of 15
to 20 T of mix in the paver and providing a combined paver and material trans
fer vehicle storage capacity of 45 to 50 T. With storage of this capacity, the
paver can operate continuously. When a material transfer vehicle is used, trucks
can be stopped 1 0 0 to 2 0 0 ft ahead of the paver and dump their loads safely with
out moving.
Figure 8.14a shows a paving operation with trucks depositing the mix
directly in the paver, and Fig. 8.14b shows a paving operation with a material
transfer vehicle providing the asphalt mix to the paver.
R OL LE R 1 ROLLER 2 PAV ER
(a) Asphalt paving train with the mix deposited directly into the paver
ROLLERS PA VE R MTV
(b) Asphalt paving operation with a material transfer vehicle providing mix to the paver
F IG U R E 8 .1 4 I Methods of supplying asphalt mix material to the paver.
Courtesy: Astec Industries, Inc.
After a fresh layer of hot mix asphalt concrete is placed, a steel-wheel roller is
usually used for initial compaction. After the initial compaction, hairline cracks
or marks will be left by the steel drum rollers. A pneumatic-tired roller is used
to smooth the pavement surface to remove these marks or lines.
Steel-wheel rollers are typically 4 to 5 ft wide and weigh from 8 to 14 T with
penetration depths from to \ in. Pneumatic-tired rollers weigh between 2,000 and
10,000 lb and have from 4 to 7 tires on the front of the roller and 3 to 6 tires on
the rear of the rollers. The operating speed of compactors ranges from 1 to 4 mph.
COST OF HOT-MIX
ASPHALTIC-CONCRETE PAVEMENT
An asphalt plant is expensive to purchase and operate. Also, the cost of setting
up and operating an asphalt plant for producing hot-mix asphaltic-concrete
pavement is high. Consequently, a single setup is generally made for a given job.
The cost will include the cost of aggregate, asphalt, moving the plant to the loca
tion, setting it up, operating the plant, hauling the material to the job, spreading,
Chapter 8 Highways and Pavements 187
and rolling. The cost of operating the plant will include depreciation, interest,
insurance and taxes, maintenance and repairs, and fuel. Additional costs may
include the rental of land at the jobsite to stockpile material and operate the
asphalt mixing plant.
EXAMPLE 8 . 5
Estimate the total direct cost and cost per ton for mixing and placing hot-mix
asphaltic-concrete pavement 18 mi long, 24 ft wide, and 5 in. thick. The pavement
consists of a 3-in.-thick base course and a 2 -in.-thick wearing course.
A portable drum -mix plant with a 150 T/hr ca pacity will be used to provide con
tinuous mix of the asphalt material. Assuming a 50-min effective hour, the p ro d u c
tion rate of the asphalt plant will be 50/60 x 150 = 125 T/hr.
The asphalt plant will be located at the m iddle of the projects. Dump trucks with
20-T ca pacity will haul the asphalt mix to the paver. Assume trucks will haul an aver
age of 9 mi at 30 mph and return at 35 mph. Assume a 45-min effective hour for the
hauling operation.
The pavement will be placed on a previously prepared subbase. Prior to p la c
ing the 3-in.-thick base, an asphalt prime coat will be applied to the subbase at the
rate of 0.3 gal/sy. A 2-in.-thick wearing course will be placed on top of the base with
no tack coat required.
The specifications require 6 percent asphalt cem ent content by w eight m ea
surement. The asphalt plant will require 60 percent coarse aggregate, larger than a
no. 10 sieve, and 40 percent fine aggregate and filler. Assume that 5 percent of the
coarse aggregate, 10 percent of the fine aggregate, and 2 percent of the asphalt
will be lost through waste or other reasons.
The com bined material will weigh about 3,600 Ib/cy when com pacted. The
paving mixtures shall meet the requirements for grading and mix com position shown
in the table.
Quantity of materials:
Total surface area = [18.0 mi x 5280 ft/mi x 24 ft]/(9 sf/sy) = 253,440 sy
Material for 3-in. (-§-ft) base course:
[(253,440 sy x ^ ft x 3,600 lb/cy)/(3 ft/yd)]/[2,000 Ib/T] = 38,016 T
Material for 2-in. (^ -ft) wearing course:
[(253,440 sy x ^ ft x 3,600 lb/cy)/(3 ft/yd)]/[2,000 Ib/T] = 25,344 T
Total aggregate w eight = 63,360 T
Quantity of asphalt mix per trip: 20 T/trip X 1.0 trip/0.92 hr = 21.7 T/hr
For a 45-min hour, asphalt mix hauled per trip = 21.7 T/hr x 45/60 = 16.3 T/hr
Required truck: plant production/truck production, 125/16.3 = 7.6 trucks
required
Therefore, need 8 trucks with 20-T capacity to serve the paver
Using 8 trucks, the haul rate will be greater than the plant production rate
Thus, the MARR is 17%. Since salvage value is not considered, only the capital
recovery equation is required for calculating the hourly ownership costs as follows:
/(1 + i)n
Annual ownership cost = P [5.1]
(1 + /)" - 1
0.17(1 + 0 .1 7 )12
= $1,300,000 (1 + Q 1/)12 _ .|
= $260,605/year
Material costs:
Coarse aggregate: 37,522 T @ $8.32/T = $312,183
Fine aggregate: 26,205 T @ $7.92/T = 207,548
Asphalt cement: 3,878 T @ $ 1 5 7 /T = 608,846
Prime coat: 76,032 gal @ $0.61/gal = 46,380
Total cost = $1,174,957
190 Estimating Construction Costs
These costs do not include setup and takedown drum -mix plant or the indirect
costs, such as taxes on labor and material, bonds and insurance, job-site office, and
general overhead. Also, contingency and profit are excluded.
COMPUTER ESTIMATING OF
HIGHWAY PROJECTS
The previous sections of this chapter presented methods, materials, and exam
ples of estimating the cost of highway construction projects. To accurately esti
mate the cost the estimator must know the method of construction and the mix
of labor and equipment that will be used on a particular job.
Estimating software programs are commercially available for estimating the
cost of highway pavements. These programs store the contractor’s equipment
and labor rates, and indirect costs. They also store crew configurations and asso
ciated equipment spreads for specific operations such as shouldering, small con
crete structures, main-line paving, etc. Since highway contracts are unit-price
format with the estimated quantities provided, the estimator only has to select a
crew from a menu in the software and determine the applicable production rate.
Chapter 25 is devoted to computer estimating with emphasis on infrastructure
type projects, such as highways.
PROBLEMS
8.1 Estimate the total cost and the cost per acre for clearing and grubbing 64 acres of
light vegetation, small trees, and brush. A 285-hp dozer, operating with a 14-ft
effective cutting blade, will perform the clearing. The dozer will operate in first
gear at 2.2 mi/hr during clearing.
192 Estimating Construction Costs
It will cost $1,500 to transport the dozer to and from the job. The hourly
cost for the dozer and operator is $125.00/hr. Assume a 45-min effective hour
and estimate the total time and cost, and the cost per acre for clearing.
8.2 A highway project must be cleared of trees before the grading operation can be
started. The site is reasonably level terrain with firm ground, and a site survey
reveals 25 to 75 percent hardwoods.
A 215-hp dozer will be used to fell trees. The cost of the dozer and operator
is $185.00/hr. The cost of moving to the job and back to storage will be $960.00.
Assume a 45-min effective hour and estimate the total cost and cost per acre to
fell the trees based on the following tree count:
Average number of trees per acre = 8 0 0
Number of 1 to 2 ft dia. =185
Number of 2 to 3 ft dia. = 78
Number of 3 to 4 ft dia. = 12
8.3 The trees in Prob. 8.2 are to be piled into a stack for burning. A 165-hp dozer
will be used to grub and stack the felled trees. Assume a 45-min/hr efficiency for
this operation. Estimate the cost of piling-up the trees if the cost of the dozer and
operator is $125.00/hr.
8.4 A paving operation is using a 150-cy/hr batch plant to pave a concrete highway,
15.43 mi long, 24 ft wide, and 9 in. thick. One longitudinal saw joint will be
installed along the centerline of the pavement and transverse saw joints are
required at 15 ft on centers. Water will be transported to the job for the concrete
batch plant by water trucks, each with a 3,000 gal capacity. Preliminary esti
mates of production rates have been determined as
Concrete batch plant = 1 5 0 cy/hr
Transporting water = 0.75 hr/trip
Saw cutting joints = 245 lin ft/hr
For this project, determine the number of water trucks and the number of saw
cutting crews to ensure a continuous paving operation. What production rate, in
square yards per day, is necessary of the slipform paver?
8.5 Estimate the total cost and cost per square yard of concrete, for bid purposes, for
furnishing materials, equipment, and labor for construction of a pavement 24 ft
wide, 9 in. thick, and 7.24 mi long.
Use the same job conditions, types of equipment, equipment costs, wage
rates, material costs, and overhead cost as those in Example 8.4.
8.6 Estimate the total direct cost and the cost per ton for furnishing materials and for
mixing and placing hot-mix asphalt pavement 16.5 mi long, 28 ft wide, and 4 in.
thick on a previously prepared base. The pavement will be placed in two layers,
each 2 in. thick after compaction.
Use the same methods, material costs, equipment, equipment costs, wage
rates, and production rates as those used in Example 8.5, except change the
asphalt cement to 7 percent of the combined weight of the concrete.
Foundations
TYPES OF FOUNDATIONS
Foundations that support structures include footings, piles, and drilled shaft
foundations. Footings are shallow foundations that are constructed by excavat
ing the soil from the ground and then installing reinforced concrete. Piles and
drilled shaft foundations are deep foundations. A pile foundation is constructed
by driving the pile directly into the ground, whereas a drilled shaft foundation is
constructed by drilling a hole in the ground and installing reinforced concrete.
Footings are foundations placed at shallow depths, usually less than 5 ft.
Footings may be placed at one location, called isolated or spot footings, to sup
port a column that is placed on the footing. Some footings are continuous, such
as a footing to support a wall of a building.
Pile foundations are driven into the ground by the hammer of pile-driving
equipment. The piles may be timber, steel, or concrete. The driving depth
depends on the magnitude of the load that will be placed on the pile from the
structure above and the strength of the soil. Load-bearing piles resist loads by
skin-friction or end bearing, or a combination of both. Piles are driven from 30
to 2 0 0 ft.
Drilled shaft foundations are installed by drilling holes to depths in the soils
that have sufficient strength to support the loads from the structure above the
foundation. For sandy soils, a steel casing may be required to stabilize the soil
during the drilling operation. After the hole is drilled, a belling tool can be used
to widen the bottom of the drilled hole, to increase the load-bearing capacity of
the foundation. Reinforced concrete is installed after the shaft has been drilled
and belled. Drilled shafts can be installed with diameters from 18 to 96 in. and
at depths from 5 to 60 ft. Anchor bolts are installed at the top of the foundation
Co c o n n e ct Che fo u n d a tio n Co Che stru ctu re a b o ve , su c h a s a s te e l c o lu m n .
193
194 Estimating Construction Costs
FOOTINGS
Construction of a footing includes excavating the soil to the required depth,
erecting formwork, setting reinforcing steel, placing concrete, removing form
work, and backfilling soil above the footing to the surface of the ground.
A trench is excavated into the soil to construct a continuous footing. For
some shallow continuous footings, the sides of the excavated soil may be stable
enough to support itself without caving in. After the trench is excavated, rein
forcing steel is installed and concrete is placed directly into the open trench
without any formwork.
For some shallow continuous footings, the sides of the excavated soil are
unstable. Thus, the trench is excavated wider than the footing, formwork is
installed, and reinforced concrete is placed in the formwork. After the concrete
has sufficiently cured, the formwork is removed and the sides of the footing are
backfilled with soil. Chapter 10 presents the cost for formwork, reinforcing
steel, and placing concrete.
Some projects require excavation into soil that is so unstable that the walls
of the excavated earth must be supported to prevent them from caving into the
pit or trench. For these situations, it will be necessary to install a system of
shores, braces, and solid sheeting along the excavated walls to hold the earth in
position. If groundwater is present, it may be necessary to install semi-watertight
sheeting around the walls to exclude or reduce the flow of water into the pit.
Another alternative is to pump the water out of the trench area where the foot
ing is to be installed. Timber and steel are used for braces and sheeting.
SHEETING TRENCHES
If the earth is so unstable that it must be restrained for the full area of the wall
of a trench, it will be necessary to install a trench box, as illustrated in Fig. 9.1.
The sheeting of a trench box is typically constructed with 2-, 3-, or 4-in.-thick
lumber, placed side by side or overlapping along the entire length of the trench.
Wales, consisting of 4 X 6 -in.-thick lumber, can be placed in a horizontal direc
tion to provide additional support for the sheeting. The lumber may be rough
sawed or S4S. Depending on the stability of the earth, it may be necessary to
drive the sheeting and install some of the braces ahead of excavating. The sheet
ing may be driven with power equipment, such as a pneumatic hammer.
Estimate the cost of installing and removing solid sheeting and bracing for a trench
box, as shown in Fig. 9.1. The trench is 100 ft long and 7 ft deep. The sheeting will
be 2 x 12-in. S4S lumber, 8 ft long. Two horizontal rows of 4 x 6-in. wales will be
placed on each side of the trench for the full length of the trench. Trench braces will
be placed 4 ft apart along each row of wales. The sheeting will be driven one plank
at a time by using an air com pressor and a pneum atic hammer.
Chapter 9 Foundations 195
Quantity of materials:
Sheeting, actual dimension of 2 x 12 lumber is 1.5 in. x 11.25 in.
Number of pieces for 2 sides: [(100 ft)/(11.25 in./12 ft)] x 2 sides = 214
pieces
Quantity of sheeting, 214 pieces x [(2 x 1 2)/( 1 x 12)] x 8 ft = 3,424 bf
Wales:
Number of pieces for 1 row, 100 ft /8 ft/wale = 12.5, therefore need 13
pieces
Quantity of lumber: 13 pieces x 2 rows x 2 sides x [(4 x 6)/(1 x 1 2 )] x
8 ft = 832 bf
Trench braces:
Num ber of braces: (100 ft/4 ft/brace) 2 rows = 50 braces
Time to perform the job:
Two laborers installing sheeting: 214 pieces/4 pieces/hr = 53.5 hr
Two laborers installing wales and braces: (50 + 13) = 63 pieces/3 pieces/hr
= 21.0 hr
196 Estimating Construction Costs
Material cost:
Sheeting: 3,424 bf @ $0.73/bf = $2,499.52
Wales: 832 bf @ $0.92/bf = 765.44
Braces: 50 @ $3.50 each = 175.00
Total material cost = $3,439.96
Labor cost:
Laborers driving sheeting: 53.5 hr x 2 laborers @ $21.67/hr = $2,318.69
Installing wales and braces; 21.0 hr x 2 laborers @ $18.17/hr = 763.14
Total labor cost = $3,081.83
Equipment cost:
Air compressor: 53.5 hr @ $ 8 .75/hr = $468.13
Air hammer, hose, etc.: 53,5 hr @ $ 1 .75/hr = 93.63
Total equipm ent cost = $561.76
Summary of costs:
Material = $3,439.96
Labor = 3,081.83
Equipm ent = 561.76
Total cost = $7,083.55
PILE-DRIVING EQUIPMENT
Equipment used to drive piles usually consists of a truck-mounted or crawler-
mounted crane, leads, a hammer, and a source of compressed air or steam to
drive the hammer. When piles are driven into water, the driving rig is usually
mounted on a barge. The actual driving of piles is accomplished with hammers.
Several types are available, including the drop hammer, single-acting air or
steam hammer, double-acting air or steam hammer, self-contained diesel-
operated hammer, and vibratory hammer. Figure 9.2 illustrates a single-acting
steam hammer driving a steel shell for a cast-in-place concrete pile.
The size of a drop hammer is indicated by the weight of the hammer,
whereas the size of an air, steam, or diesel hammer is indicated by the theoreti
cal foot-pounds of energy delivered by each blow.
A drop hammer is a heavy metal weight that is lifted by a hoist line, then
released and allowed to fall onto the top of the pile. Due to high dynamic forces,
a pile cap is positioned between the hammer and the pile head. The pile cap pro
vides a uniform distribution of the blow to the pile head and acts as a shock
absorber. The cap contains a cushion block, which is commonly fabricated from
wood. Drop hammers are suitable for driving piles on remote projects that
Chapter 9 Foundations 197
F IG U R E 9 .2 I Single-acting hammer
driving a steel shell for a cast-in-place
concrete pile.
require only a few piles, or when the time of completion is not important. A drop
hammer normally can deliver from four to eight blows per minute.
A single-acting air hammer has a free-falling weight, called a ram, that is
lifted by steam or compressed air that flows to the underside of a piston, which
is connected to the ram through a piston rod. When the piston reaches the top
of the stroke, the steam or air pressure is released and the ram falls freely to
strike the top of a pile. Whereas a drop hammer may strike 4 to 8 blows/min, a
single-acting steam or air hammer will strike 40 to 60 blows/min when deliv
ering the same energy per blow. A pile cap is used with a single-acting steam
or air hammer. The cap is mated to the case of the hammer. This cap is com
monly called an anvil or a helmet.
198 Estimating Construction Costs
T A B L E 9.1 I Recommended sizes of hammers for driving piles, in theoretical foot-pounds of energy per blow.
injects the fuel into the combustion chamber between the ram and the anvil. The
continued down stroke of the ram compresses the air and the fuel to ignition
heat. The resulting explosion drives the pile downward and the ram upward to
repeat its stroke. The energy per blow, which is controlled by the operator, can
be varied over a wide range. Diesel hammers deliver about 40 to 50 blows/min.
Typically, the diesel hammer is set in leads on the crane. Table 9.3 gives infor
mation on diesel hammers of a manufacturer of pile driving equipment.
SHEET PILING
Sheet piles are used to form a continuous wall by installing sheets of steel that
interlock. The cost of sheet piling in place will include the cost of the piling
material, driving equipment, and labor. If the piling is to be salvaged, there will
be an additional cost for extracting it. It is common practice to drive two piles
simultaneously.
Sheet piling is manufactured in both flat and Z-section sheets that have inter
locking longitudinal edges. The flat sections are designed to interlocking strength,
which makes them suitable for construction of cellular structures. The Z-sections
are designed for bending, which makes them more suitable for construction of
retaining walls, bulkheads, cofferdams, and for supporting excavation.
Table 9.4 gives information for sheet piles manufactured by steel compa
nies in the United States. Table 9.5 gives representative rates for driving steel-
sheet piles when they are driven in pairs with the size hammer recommended in
Table 9.1.
Weight
Type and Ib/lin ft Ib/sf
section no. Width, in. Area, sq. in. of pile of wall
Straight type
PS31 19.69 14.96 50.9 31.0
PS27.5 19.69 13.27 45.1 27.5
Angle type
PSA23 16 8.99 30.7 23.0
Z-type
PZ22 22 11.86 40.3 22.0
PZ27 18 11.91 40.5 27.0
PZ35 22.64 19.41 66.0 35.0
PZ40 19.69 19,30 65.6 40.0
E X A M P L E 9 .2
Estimate the cost of furnishing and driving steel-sheet piling for a cofferdam to
enclose a rectangular area 60 by 100 ft. The piles will be 16 in. wide, 24 ft long, and
w eigh 30.7 lb/ft (see Table 9.4 section no. PSA23). The piles will be driven in pairs
to full penetration into soil having normal frictional resistance.
A hammer delivering approxim ately 6,000 ft-lb of energy per blow should be
used. A suitable steel cap should be placed on top of the piles to protect them from
dam age during driving. The hammer will be suspended from a crawler-mounted
crane. A portable air com pressor will supply air.
Chapter 9 Foundations 201
W eight o f pile,
Ib/lin ft
L ength of D epth of
pile, ft pen etration 20 30 40
20
i 6 5f 5|
2
Full 5£ 51 53
1
25 2 5 4| 4s
Full ^4 4 4
1
30 2 45 4| 4
o3
Full 4 O4 3£
q3
35 1
2 4 o4 3i
Full 3j 3l 3
1
40 2 — 3? 3
o3
Full — 3 ‘- A
1 —
45 2 — 2f
Full — — 2|
1 pi
50 2
Full pi
4
Quantity of material:
Perimeter of wall: (60 ft + 100 ft + 60 ft + 100 ft) = 320 ft
Labor costs, allow 8 hr for crew to set up and take down equipm ent:
Foreman: (60 hr + 8 hr) = 68 hr @ $25.00/hr = $1,700.00
Crane operator: 68 hr @ $21.67/hr = 1,473.56
General laborers: 68 hr x 3 laborers @ $15.56/hr = 3,174.24
Total labor cost = $6,347.80
Summary of costs:
Material = $59,928.96
Equipm ent = 6,810.00
Labor = 6,347.80
Total cost = $73,086,76
WOOD PILES
The cost of wood load-bearing piles in place will include the cost of the piles
delivered to the job; the cost of moving the pile-driving equipment to the job,
setting it up, taking it down, and moving out; the cost of equipment and labor
driving the piles. Since the cost of moving in, setting up, taking down, and mov
ing out is the same regardless of the number of piles driven, the cost per pile will
be lower for a greater number of piles.
The cost of wood piles is usually based on the length, size, quality, treat
ment, and location of the job. Wood piles are tapered from an endpoint diame
ter of 6 to 8 in. to a butt diameter of 12 to 14 in. Lengths vary from 30 to 50 ft.
For piles that are to be driven over 50 ft in depth, a splice of two sections of piles
is required.
A preservative treatment of creosote or pentachlorophenol is generally
applied to wood piles. Treatments reduce the tendency of decay but often
increase the brittleness of wood, which increases the possibility of breakage dur
ing the driving process. A steel boot can be placed on the pile point to reduce the
tendency of breakage during driving of the pile.
Because piles are sometimes broken during the driving process, a reasonable
allowance for extra piles should be included in the estimate. If the contractor is paid
for the total number of linear feet of piles driven, any piles that cannot be driven
to full penetration will result in some wastage. When it is necessary to cut off the
tops of piles to a fixed elevation, the estimate should include the cost of cutting.
The estimator should thoroughly evaluate each project to determine the
number and length of piles, number of splices, desired steel boots for pile points,
potential for breakage, and waste for cutting the tops of piles to match the ele
vation of the pile caps.
Chapter 9 Foundations 203
EXAMPLE 9 . 3
Estimate the cost of furnishing and driving 160 wood piles 36 ft long into a soil hav
ing normal frictional resistance. The piles will be purchased in 40-ft lengths and the
tops will be cut to the required elevation after driving. The piles will be approxim ately
14 in. in diam eter at the butt and 7 in. at the tip. The piles will be treated with cre
osote preservative at a rate of 2.5 Ib/cf, therefore breakage should be considered.
The average w eight of a pile will be about 37 Ib/lin ft. Reference to Table 9.1
indicates that the hammer should deliver approxim ately 7,000 theoretical ft-lb of
energy per blow. Use a Vulcan size 2 single-acting hammer.
Quantity of materials:
Number of piles to be driven = 1 6 0 piles
Add 5% for breakage, 5% x 160 = 8 piles
Total = 168 piles
Labor costs, allow 8 hr for the crew to set up and take down equipm ent:
Foreman: (56 hr + 8 hr) = 64 hr @ $25.00/hr = $1,600.00
Crane operator: 64 hr @ $21.67/hr = 1,386.88
General laborers: 64 hr x 3 laborers @ $15.56/hr = 2,987.52
Total labor cost = $5,974.40
Summary of costs:
Material = $83,795.04
Equipm ent = 7,382.48
Labor = 5,974.40
Total cost = $ 9 7 ,1 5 1 .9 2
This cost does not include taxes, insurance, overhead, contingency, or profit.
The cost of concrete piles will depend on the length, diameter, and strength,
and the distance from the fabrication yard of the supplier to the jobsite. The
weight of concrete piles is high; therefore the cost of transporting the piles to the
job can be significant.
Because of the varied conditions that can affect the costs, it is not possible to
prepare a general estimate that will apply to a particular project without the infor
mation that must be obtained from a concrete supplier that is to furnish the piles.
To estimate the cost, the estimator must obtain price quotes from the supplier.
F IG U R E 9 .3 I Monotube pile.
206 Estimating Construction Costs
J-type
0.24 in./ft 8 in, x 12 in. x 17 ft 17 20 23 27 0.32
0.24 in./ft 8 in, x 12 in. x 17 ft 18 22 26 30 0.58
0.24 in./ft 8 in. x 12 in. x 17 ft 18 24 28 32 0.95
0.24 in./ft 8 in. x 12 in. x 17 ft — 26 30 35 1.37
/-type
0.40 in./ft 8 in. x 12 in. x 17 ft 17 20 224 28 0.18
0.40 in./ft 8 in. x 14 in. x 15 ft 19 22 26 30 0.34
0.40 in./ft 8 in. x 16 in. x 2 0 ft 20 24 28 33 0.56
0.40 in./ft 8 in. x 18 in. x 25 ft — 26 31 35 0.86
The rate of driving varies with the length of the piles, class of soil into which
they are driven, type of driving equipment used, spacing of the piles, topogra
phy of the site, and weather conditions. If a project requires the driving of a sub
stantial number of piles, it may be desirable to make subsoil tests, to obtain reli
able information related to the difficulty of driving piles and the lengths of piles
required.
STEEL PILES
Steel piles are especially suited to projects where it is necessary to drive piles
through considerable depths of poor soil to reach solid rock or another forma
tion having high load-supporting properties. Standard rolled steel ///^-sections or
wide-flange beams are most frequently used, although fabricated sections are
sometimes used for special conditions. Standard sections are less expensive than
fabricated sections.
Chapter 9 Foundations 207
Driving operations are similar to those of other piles. Steel piles do not
require the care in handling that must be observed in handling precast-concrete
piles. A cap can be installed on the top of piles to reduce the potential for dam
age during the driving operation.
Table 9.8 gives data for various steel piles and Table 9.9 gives approximate
rates for driving steel piles when one is using an appropriate size hammer.
Cross-sectional
dimensions, in., Weight,
Designation depth x width Area, sq. in. ib/lin ft
HP14x117 14.21 X 14.89 34.4 117
14x102 14.04 X 14.79 30.0 102
14x89 13.83 X 14.70 26.1 89
14x73 13.01 X 14.59 21.4 73
HP 12x84 13.15 x 13.21 24.6 84
12x74 12.95 x 13.11 21.8 74
12x63 12.75 x 13.00 18.4 63
12x53 12.54 X 12.90 15.5 53
HP10X57 9.99 X 10.25 16.8 57
10x42 9.70 X 10.08 . 12.4 42
HP8x36 8.02 X 8.155 10.6 36
‘ These rates are based on piles being delivered to the job in lengths up to 40
ft. For lengths greater than 40 ft, a field weld will be required for each pile.
EXAMPLE 9 . 4
Estimate the cost for bid purposes for furnishing and driving 180 steel piles, 40 ft
long. The piles are designated as HP14x73. The piles will be driven to full penetra
tion into soil having high frictional resistance. It will cost $9,000 to move the pile driv
ing equipm ent to and from the job.
208 Estimating Construction Costs
A single-acting air-driven pile hammer will be used. Table 9.1 indicates that a
hammer with 12,000 ft-lb of energy is required. Table 9.2 shows several models of
pile driving equipm ent are available. For this project a 5,000-lb hammer that can
deliver at least 15,000 ft-lb of energy will be used. The pile-driving hammer will be
mounted on the leads of a craw ler crane, which will be used to lift the piles into posi
tion, support the leads, and lift the hammer. The cost can be determ ined as
Quantity of materials:
Linear feet of piles: 180 piles x 40 ft = 7,200 ft
Total weight of piles: 7,200 ft x 73 lb/ft = 525,600 lb
Labor costs, allow 8 hours for crew to set up and take down equipm ent:
Foreman: (112 hr + 8 hr) = 120 hr @ $25.00/hr = $3,000.00
Crane operator, 120 hr @ $21.67/hr = 2,600.40
General laborers: 120 hr x 3 laborers @ $15.56/hr = 5,601.60
Total labor cost = $11,202.00
Taxes:
W orkm an’s com pensation: $4.37 per $100 x $ 11,202 = $489.53
Social security tax: 7.65% x $11,202 = 856.95
Unemploym ent tax: 4% x $ 11,202 = 448.08
Material taxes: 5% x $183,852 = 9,192.60
Subtotal of taxes = $10,987.16
Chapter 9 Foundations 209
Performance bond:
$258,342.58 @ $12.00 per $1,000 = $3,100.11
possible; however, most drilled shafts range from 6 to 50 ft deep. The bottom of
the drilled hole can be underreamed with a belling tool to provide an increased
bearing capacity of the foundation.
Two types of belling tools are available to underream drilled shafts; one
opens out from the top, as shown in Fig. 9.4a and one opens out from the bot
tom, as shown in Fig. 9.4b. Equation [9.1] can be used to determine the volume
of the shaft for the underream of the type of hole illustrated in Fig. 9.4b.
(Df ~ h ) + ~ - { d ] + dsdb + d2
b) [9.1]
where
Vc = total volume of concrete in the shaft, cf
Df = depth of foundation, ft
h = depth from the bottom of shaft to top of bell, ft
ds = diameter of shaft, ft
dh = diameter of bell, ft
Steel reinforcing
Ground
777777777777777771 [77777777777777777777777-
impress
ta p
m m
p & itew
w m . Round shaft,
variable diameter ® i§
if #
Tie bars
|a
Underream
•' LiJ-.•
Cohesive soils, such as dry clays, generally have sufficient strength to pro
vide natural stability of the sides of the drilled shaft. However, if water is pres
ent the sides of the shaft drilled into clay may become unstable. Cohensionless
soils such as sands are unstable in both the dry and wet condition. When drilling
into unstable soils or where water may be present, it is usually necessary to
install cylindrical steel casing to hold the sides of the shaft until the reinforcing
steel and concrete are placed. The casing is pulled from the hole during place
ment of the concrete.
Table 9.10 provides representative rates of drilling various diameters of
shafts into soils. Table 9.11 gives approximate rates for drilling into soft rock,
such as shales. These rates can vary, depending on the moisture and hardness of
the soil and the size of the rotary drilling rig. A thorough evaluation of the soil
test borings is necessary to determine the rate of drilling.
EXAMPLE 9 . 5
A 15-mi-long electric transmission line requires 64 steel truss towers to support the
conductors and shield wires. There are four drilled shaft-foundations for each tower,
one for each leg of the earth tower, similar to the type shown in Fig. 9.4b. Each foun
dation is to be installed with a 24-in, diam eter at a depth of 9 ft in dry clay; therefore,
no casing will be required. A 42-in.-diam eter bell is required for each foundation.
Reinforcing steel consists of eight vertical bars 9 ft long with § in. diameters.
Horizontal ties will be placed at 12 in. on centers. Tie bars will have §-in. diameters
and will have a 3-in. overlap on their ends, A 3-in. clear cover is required on all rein
forcing steel. Ready-mix concrete will be obtained from a local concrete supplier.
The concrete will be delivered to the job and placed directly into the drilled holes.
Quantity of materials:
Number of drilled shafts, 64 structures x 4 foundations/structure = 256 drilled
shafts
Total linear feet of drilling, 256 shafts x 9 ft/shaft = 2,304 lin ft
Concrete:
Volume of concrete per drilled shaft from Eq. [9.1]:
^ = IM t {Df_h)+Il^{d2+ d$db+d2
b) 9
[ ii]
3.14 x (2 ft )2
= ----------- ----- -- [9.0 ft - 1.3 ft
4
Reinforcing steel:
Vertical bars (§ in. diameter):
Total length: 256 shafts X 8 bars/shaft X 9 ft/bar = 18,432 lin ft
Total weight: 18,432 lin ft @ 1.502 lb/ft = 27,685 lb
Horizontal tie bars (§ in. diameter):
Centerline diameter: [24 in. dia. - ( 2 x 3 in. cover) - § in.] = 17.625 in.
C ircum ference: (3.14 x 17.625 in. + 3-in. lap )/(12 in./ft) = 4.86 ft
Chapter 9 Foundations 213
Labor costs:
Drill operator: 192 hr @ $21.67/hr = $4,160.06
Laborers: 192 hr X 2 laborers @ $15.56/hr = 5,975.04
Foreman: 192 hr @ $25.00/hr = 4,800.00
Total labor cost = $14,935.10
Summary of costs:
Material = $33,526.25
Equipm ent = 37,256.00
Labor = 14,935.10
Total cost = $85,717.35
PROBLEMS
9.1 Estimate the total cost and the cost per linear foot for furnishing and driving 96
creosote-treated wood piles to full penetration into soil having high frictional
resistance. The piles will be 40 ft long, with 14-in minimum diameters at the butt
and 6-in minimum diameters at the tip. The tip of each pile will be fitted with a
metal point to facilitate driving.
214 Estimating Construction Costs
The cost of moving the pile driving equipment to the job and back to the
storage yard will be $1,950.00. The cost of piles is $9.72/lin ft and the cost of
pile points is $54.50 each. Use the information in Table 9.6 and estimate the
total cost and cost per linear foot of driven pile.
9.2 Estimate the total direct cost and cost per linear foot for furnishing and driving
the piles of Prob. 9.1 to full penetration into soil having normal frictional resis
tance. Use a metal point on the tip of each pile.
9.3 Estimate the total direct cost and the cost per linear foot for furnishing and driv
ing steel-sheet piling for construction of the basement of a building, 150 by
240 ft. The piles will be 22 in. wide, 18 ft. long, and weigh 40.3 Ib/lin ft (see
Table 9.4, section no. PZ22). The piles will be driven in pairs to full penetration
into soil having normal frictional resistance.
Assume the cost of moving the equipment to and from the job will be
$1,540.00. Use the same material costs, equipment, equipment costs, and wage
rates as in Example 9.2.
9.4 Estimate the total direct cost and cost per linear foot for furnishing steel piles,
HP 14 X 73, into soil having high frictional resistance. The piles will be driven
to full penetration. The piles will be 40 ft long. The material costs, equipment
costs, wage rates, and other conditions will be the same as in Example 9.4.
9.5 Estimate the total cost and cost per cubic yard for installing 95 drilled-shaft
foundations in hard clay soil. Each foundation is to be installed, similar to the
type shown in Fig. 9.4(b), with a 30-in.-diameter shaft and a 54-in.-diameter
underream at a depth of 14 ft.
Vertical reinforcing steel consists of twelve f-in.-diameter bars, 14 ft long.
Horizontal ties are to be placed at 15 in. on centers and a 6-in. lap. Ties are j-in.
in diameter. The material costs, equipment costs, and wage rates will be the
same as in Example 9.5.
Concrete Structures
COST OF CONCRETE STRUCTURES
The items that govern the total costs of concrete structures include
1. Forms
2. Reinforcing steel
3. Concrete
4. Finishing, if required
5. Curing
Formwork for concrete structures is usually measured in square feet of con-
tact of area (SFCA). The SFCA is the surface area that concrete will be in con-
tact with the forms. For example, an 8 -ft-high wall, 200 ft long, would have
3,200 SFCA, calculated as 8 ft X 200 ft X 2 sides = 3,200 SFCA. The unit of
measure for reinforcing steel is pounds of weight, whereas the unit of measure
for concrete is cubic yards of volume. The finishing and curing of concrete is
measured in square feet.
When preparing an estimate, the cost of each of these items should be deter
mined separately and a code number should be assigned to each item. The cost
of an item should include all materials, equipment, and labor required for that
item. Then, after all the costs are determined, the total cost can be divided by the
SFCA. Following this procedure will simplify the preparation of an estimate of
concrete structures.
Since the major cost of a concrete structure frequently results from the cost
of forms, the designer of a structure should consider the effect that the shape of
the structure will have on the cost of forms.
Forms for concrete are fabricated from lumber, plywood, steel, aluminum,
and various composite materials, either separately or in combination. If the form
material will be used only a few times, the lumber will usually be more eco
nomical than steel or aluminum. However, if the forms can be fabricated into
panel sections or other shapes, such as round column forms, that will be used
many times, then the greater number of uses obtainable with steel and aluminum
may produce a lower cost per use than with lumber.
The material should be selected for the form that will give the lowest total
cost of a structure, considering the cost of the forms plus the cost of finishing the
surface of the concrete, if required, after the forms are removed. The use of lum
ber will usually leave form marks that may have to be removed at considerable
cost, whereas the use of smooth-surface plywood or metal forms can reduce the
cost of removing form marks. It is a better practice to spend extra money on
good-quality form materials, than it is to spend money on labor to hand-finish
concrete.
The cost of forms will include the cost of materials, such as lumber, nails,
bolts, form ties, and the cost of labor making, erecting, removing, and cleaning
the forms. Frequently there will be a cost of power equipment, such as saws and
drills, and a small lifting crane for handling materials. If it is possible to reuse
the forms, an appropriate allowance should be made for salvage value. If the
forms are treated with oil prior to each use, the cost of the oil should be included.
necessary to install the plywood with the outer layers perpendicular to the
studs or joists to obtain maximum strength. Plywood and Plyform are priced
by the sheet.
The plywood industry manufactures a special product, designated as
Plyform, for use in forming concrete. Plyform is an exterior-type plywood lim
ited to certain species of wood and grades of veneer to ensure high performance
as a form material. The panels are sanded on both sides and oiled by the manu
facturer. Plyform can be reused more times than plywood. A special high-
density overlay (HDO) can be applied to the surface of Plyform by the manu
facturer, which will allow the HDO Plyform to be used in excess of 100 uses.
Form Oil
Form oil is applied to surfaces of the forms that will come in contact with con
crete. It prevents the concrete from attaching to the form material and facilitates
218 Estimating Construction Costs
removal of the forms. Sometimes form oil is called bond-breaker. Form oil can
be applied with mops, brushes, or pressure sprayers. Generally it is applied as a
rate of 300 to 500 sf/gal.
Form Ties
To resist the internal pressure resulting from the concrete, form ties are placed
between the forms, as shown in Fig. 10.1. Form ties serve two purposes: they
hold the forms apart prior to placing the concrete, and they resist the lateral pres
sure of the freshly placed concrete. A tie clamp is used to secure both ends of
the tie. Thus, two tie clamps are required for each tie. Sometimes cam-lock
brackets are used in place of wedge tie clamps.
Many varieties of ties are available. The snap tie and coil tie are most com
monly used. Both of these ties are designed to break off inside the concrete after
the forms are removed. The coil tie has a plastic cone at each end of the tie that
enables a cleaner break upon removal, which may be required for architectural
finished concrete surfaces. The holes on the surface can be filled with concrete
to obtain a smooth surface. Manufacturers specify the safe loads that can be
resisted by their ties, which generally range from 3,000 to 5,000 lb.
A taper tie is available that can be reused. It consists of a tapered rod that is
threaded at each end. Wing nuts or coil nuts with washers are attached at each
end to secure the tie. Taper ties have larger strength than snap or coil ties. In
ordering form ties it is necessary to specify the thickness of the wall, sheathing,
studs, and wales.
Form Liners
Architectural concrete form liners can be used to create a virtually unlimited
variety of textured or sculpted finishes on concrete surfaces. The surfaces can
simulate wood grains, rough brick, blocks, or an irregular texture. Form liners
may be rigid or flexible.
Polyvinyl chloride (PVC) sheets of rigid form liners are attached to the form
work prior to placing the concrete. Following placement and normal curing time,
the formwork and liner are stripped, leaving a textured concrete surface. The
sheets generally are 4 ft wide and 10 ft long with square edges to allow the place
ment of adjacent sheets for large areas of concrete. Sheets of rigid form liners are
lightweight and easily stripped. A releasing agent should be applied to the form
liner to ensure uniformity of the concrete surface and to protect the form liner for
possible reuse. Flexible form liners are also available that are made of urethanes,
which can be peeled away from the concrete surface, revealing the desired texture.
Form liners are expensive, often more than the cost of the plywood and lum
ber. The cost depends on the type of liner selected. The estimator must obtain a
price quote from the concrete supplier who will provide the form liner for a par
ticular job.
B-l 1 Flat washer Wales
Studs
(d) Taper tie
F IG U R E 10.1 I Ties for concrete formwork: (a) snap tie with washer spreader,
(b) snap tie with cone, (c) coil tie with cone, and (d) taper tie.
Courtesy: Dayton Superior Corporation. 219
220 Estimating Construction Costs
3/4 " p l y w o o d s h e a th in g
2"x4"x3;0"
(a) & 0“
•Side elevation
Section through
the wall
E X A M P L E 10.1
Estimate the quantity of material to form a concrete wall 9 ft 6 in. high and 25 ft 4 in.
long. The sheathing will be f-in. plywood sheets, 4 ft w ide by 8 ft long. The plywood
sheathing will be placed with the 4 ft width in the vertical direction and the 8 ft length
in the horizontal direction. Vertical studs will be 2 x 4 lumber placed at 12 in. on cen
ters and the horizontal double 2 X 4 wales will be placed at 24 in. on centers. The
tie spacing will be 24 in., center to center.
Because the height of the wall is not evenly divisible by 4 or 8 ft, there will be
waste in the 4-ft by 8-ft plywood. Also, due to the height and length of the wall there
will be waste in the studs and wales.
222 Estimating Construction Costs
Prepare a list of materials and calculate the quantity of lumber per 100 sf of wall.
Include all of the material to form the wall, including braces, scab splices, and
stakes.
Plywood sheathing:
Height of wall (9 ft 6 in.) = 9.5 ft
Num ber of sheets in vertical direction: (9,5 ft)/(4 ft/sheet) = 2.4
Number of sheets of plywood for each 8-ft length of wall: 2.4 x 2 sides =
4.8 sheets
Cutting one sheet down the center, then 5 sheets are sufficient for vertical
direction
Studs required:
Length of wall (25-ft 4-in.) = 304 in.
S pacing of studs: 18 in.
Number of studs per side: [(304 in.)/(12 in/stud)] + 1 = 27 studs per side
Number of studs required for one side of wall: 27 studs x 2 sides = 54
studs total
Wales required:
Height of wall (9 ft 6 in.) = 114 in.
S pacing of wales: 24 in.
Number of wales required per side: (114 in.)/(24 in./wale) = 4.8, use 5
Lum ber for one row: (2 wales x [(2 x 4)/(1 x 12)] x 14 ft} x 2 = 37.3 bf
Lum ber required for one side of wall: 5 rows x 37.3 bf = 186 bf
Lumber required for both sides of wall: 186 bf /side X 2 sides = 372 bf
Sills required:
Top sill: 2 pieces x [(2 x 4)/(1 x 12)] x 14 ft long = 19 bf
Bottom sill: 2 pieces x [(2 x 4)/( 1 x 12)] x 14 ft long = 19 bf
Braces required:
Braces on one side only, spaced at 6 ft with one brace at each end
Number of braces required: (25,3 ft )/(6 ft/brace) + 1 = 5 required
Lum ber required: 5 braces x [(2 x 4)/(1 x 12)] x 10 ft long = 33 bf
Stakes required:
Lumber required: 5 stakes x [(2 x 4)/(1 x 12)] X 3 ft long = 10 bf
Total quantity of lum ber = 840 bf
Nails required:
Pounds of nails: (10 lb/1,000 bf) x (840 bf) = 8.4 lb
Summary of materials:
Plywood = 20 sheets
Lumber = 840 bf
Nails = 8.4 lb
Ties = 74
T A B L E 10.1 I Quantities of plywood, lumber, and form ties and the labor-hours required for 100 SFCA of
wall forms.*
•These quantities are based on a rate of fill of approximately 4 ft/hr and at a temperature of 70°F using normal weight concrete. If the concrete is
pumped, the quantities of material may be greater than shown.
necessary. Double rows of braces should be used for walls over 12 ft high, one
near the middle and the other near the top of the wall.
Fabrication of concrete forms by a carpenter will range from 60 to 80 bf/hr,
depending on the size of material that is fabricated. Generally a laborer will
assist two or more carpenters during the fabrication process.
E X A M P L E 10.2
Estimate the cost for building, erecting, and removing concrete forms for a 12-ft
high, 85-ft 6-in.-long wall for an industrial plant. The forms will be used three times.
Thus, it will be only necessary to build 28.5 ft of the wall forms, but 85.5 ft of forms
must be erected and removed.
Plyform sheets will be used for sheathing and dimension lumber will be used for
studs and wales. A material supplier quotes these prices: $0.55/bf for lumber,
$28/sheet for 4-ft by 8 -ft Plyform, $0.49/lb for nails, and $7.50/gal for form oil.
Carpenters cost $21.56/hr and laborers cost $15.56/hr.
Quantity of materials:
Forms to be erected and removed: (12 ft x 85.5 ft) x 2 sides = 2,052 SFCA
Forms to be built: 2,052 SFCA/3 uses = 684 SFCA
Use Table 10.1 median value for quantities of material:
Plyform sheathing: (684 SFCA) x (105 sf/100 SFCA) = 718.2 sf
718.2 sf/(32 sf/sheet) = 22.4 sheets, use 23 sheets of Plyform
Lumber: (684 SFCA) X (225 bf/100 SFCA) = 1,539 bf
Form ties: 2,052 SFCA x (18 ties/100 SFCA) = 370 ties
Form oil: (2,052 SFCA)/(400 SFCA/gal) = 5.1 gal
Nails for first use: (1,539 bf) x (15 lb/1,000 bf) = 23.1 lb
Nails for 2 reuses: (1,539 bf) x 2 x (10 lb/1000 bf) = 30.8 lb
Total = 53.9 lb
Chapter 10 Concrete Structures 225
Labor-hours required:
Reference Table 10.1 for labor-hours:
Making forms:
Carpenter: 684 SFCA x (2.25 hr/100 SFCA) = 15.4 hr
Helper: 684 SFCA X (1.75 hr/100 SFCA) = 12.0 hr
Erecting and removing forms:
Carpenter: 2,052 SFCA x (4.75 hr/100 SFCA) = 97.5 hr
Helper: 2,052 SFCA X (4.25 hr/100 SFCA) = 87.2 hr
Foreman, based on 4 carpenters: (15.4 + 97.5)14 = 28.2 hr
Cost of labor and material:
Labor costs:
C arpenter making forms: 15.4 hr @ $21.56/hr = $332.02
Helper making forms: 12.0 hr @ $15.56/hr = 186.72
C arpenter erecting and removing: 97.5 hr @ $21.56/hr = 2,102.10
Helper erecting and removing: 87.2 hr @ $15.56/hr = 1,356.83
Foreman based on 4 carpenters: 28.2 hr @ $28/hr = 789.60
Labor cost = $4,767.27
Material costs:
Plyform: 23 sheets @ $28/sheet = $644.00
Lumber: 1,539 bf @ $0.55/bf = 846.45
Form ties: 370 ties @ $0.47/tie = 173.90
Nails: 53.9 lb @ $0.49/lb = 26.41
Form oil: 5.1 gal @ $7.50/gal = 38.25
Material cost = $1,729.01
Summary of costs:
Total labor and material: $4,767.27 + $1,729.01 = $6,496.28
Cost/SFCA: $6,496.28/2,052 SFCA = $3.17/SFCA
These costs do not include reinforcing steel, concrete, taxes, overhead, or profit.
E X A M P L E 10.3
Estimate the cost of formwork for a concrete wall 12 ft high and 126 ft long, assum
ing the forms will not be reused. Plyform sheets will be used for sheathing and
dimension lumber will be used for studs and wales.
226 Estimating Construction Costs
A material supplier quotes these prices: $0.55/bf for lumber, $28/sheet for 4-ft
by 8 -ft Plyform, $0.49/lb for nails, and $7.50/gal for form oil. C arpenters cost
$21.56/hr and laborers cost $15.56/hr.
Quantity of material:
Total surface area of wall forms: 12 ft x 126 ft x 2 sides = 3,024 SFCA
Quantity of forms to be built, erected, and removed = 3,024 SFCA
Materials from Table 10.1:
Plyform sheathing: 3,024 SFCA X (105 sf/100 SFCA) = 3,175 sf
3,175 sf/(32 sf/sheet) = 99.2, use 100 sheets
Lumber: 3,024 SFCA x (225 bf/100 SFCA) = 6,804 bf
Form ties: 3,024 SFCA x (18 ties/100 SFCA) = 545
Nails: 6,804 bf x (15 lb/1,000 bf) = 102 lb
Form oil: (3,024 sf)/(400 sf/gal) = 7.6 gal
Labor cost:
Making forms:
Carpenter: 3,024 SFCA x
(2.25 hr/100 bf) = 68.0 hr @ $21.56/hr = $1,466.08
Helper: 3,024 SFCA x
(1.75 hr/100 bf) = 52.9 hr @ $15.56/hr = 823.12
Erecting and removing forms:
Carpenter: 3,024 SFCA x
(4.75 hr/100 SFCA) =143.6 hr @ $21.56/hr = 3,096.02
Helper: 3,024 SFCA x
(4.25 hr/100 SFCA) = 128.5 hr @ $15.56/hr = 1,999.46
Foreman based on 4 carpenters:
(68.0 + 143.6)/4 = 52.9 hr @ $28/hr = 1,481.20
Summary of costs:
Total labor and material cost: $8,865.88 + $6,987.08 = $15,812.96
Cost/SFCA = $15,812.96/3,024 SFCA = $5.23/SFCA
These costs do not include reinforcing steel, concrete, taxes, overhead, or profit.
Chapter 10 Concrete Structures 227
Estimate the cost of formwork for the 12-ft-high 126-ft-long concrete wall of Example
10.3, assuming the forms will be used three times. Calculate the cost savings that
can be achieved by reusing the forms.
Quantity of material:
Total surface area of wall forms: 12 ft x 126 ft x 2 sides = 3,024 SFCA
Quantity of forms to be built: 3,024 SFCA/3 uses = 1,008 SFCA
Quantity of forms to be erected and removed = 3,024 SFCA
Materials from Table 10.1:
Plyform sheathing: 1,008 SFCA x (105 s f / 100 SFCA) = 1,058 sf
1,058 sf/(32 sf/sheet) = 33.1, use 34 sheets
Lumber: 1,008 SFCA X (225 bf/100 SFCA) = 2,268 bf
Ties: 3,024 SFCA X (18 ties/100 SFCA) = 545 ties
Nails: 2,268 bf x (10 lb/1,000 bf) = 23 lb
Form oil: (3,024 sf)/(400 sf/gal) = 7.6 gal
Labor cost:
Making forms:
Carpenter: 1,008 SFCA X (2.25 hr/100 bf)
= 22.7 hr @ $21.56/hr = $489.41
Helper: 1,008 SFCA x (1.75 hr/100 bf)
= 17.6 hr @ $15.56/hr = 273.86
Erecting and removing forms:
Carpenter: 3,024 SFCA x (4.75 hr/100 SFCA)
= 143.6 hr @ $21.56/hr = 3,096.02
Helper: 3,024 SFCA x (4.25 hr/100 SFCA)
= 128.5 hr @ $15.56/hr = 1,999.46
Foreman based on 4 carpenters: (22.7 + 143.6)/4
= 41.6 hr @ $28/hr = 1,164.80
Total labor cost = $7,023.55
Material cost:
Plywood: 34 sheets @ $28/sheet $952.00
Lumber: 2,268 bf @ $0.55/bf 1,247.40
Ties: 545 @ $0.62/tie 337.90
Nails: 23 lb @ $0.49/lb 11.27
Form oil: 7.6 gal @ $7.50/gal = 57.00
Total material cost = $2,605.57
Summary of costs:
Total labor and material cost: $7,023.55 + $2,605.57 = $9,629.12
228 Estimating Construction Costs
/ x!0 x 24 gouge , „
z : steel band________^ -2 x 4 x 8-0
J
- 8- 0 " -
Sid e view
End
view
Figure 10.4 shows a typical set of forms for a foundation wall using prefab
ricated panels. The bottoms of the forms are held together by steel tie bands,
which pass under the concrete wall and are nailed to the bottom members of the
panel frames. The tops of the forms may be held together by lumber, as shown
in Fig. 10.4, or with steel tie bands. The top and bottom edges of the panels may
be grooved slightly to receive the form ties.
Chapter 10 Concrete Structures 229
f \ 4 " x 2'-0"plank § 3 -0
Plywood sheathing
Footing
-U
1
W
IT
W + 3/4*
L + 3/4"
be such that the column forms will safely resist the maximum possible internal
pressure of the concrete against the column forms.
For small columns, lumber is placed horizontally around all four sides of the
column form. The 2 X 4 or 2 X 6 lumber overlaps the comers of the form and
is secured by nailing the overlaps together, or by using a patented comer lock.
For larger column forms, steel clamps are commonly used, as illustrated in
Figure 10.6. The steel clamps are adjustable for a wide range of sizes and can be
reused several hundred times. Steel wedges are used to attach and secure the col
umn clamps. The clamps automatically square the column as the wedge is tight
ened. Manufacturers provide recommendations for spacing of their column
clamps. If it is expected that column clamps will be needed for many uses, it will
be more economical to purchase or rent adjustable steel clamps.
232 Estimating Construction Costs
SNi
is
10-0" '
Ss
12‘-0"' “a ;’
“a2 s,,
10
14 -0 “ ■
"~aV ’‘
12
13 _,§ :
17-0" 14 ~s>
15
16 ~ v
19-0 “ ' 17 s.
18 -fea.
20-0" ■
Steel clomps
FIGURE 1 0 .7 I
Approximate spacing
of column clamps.
EXAMPLE 1 0 . 5
Estimate the quantity of material for a 22-in. by 22 -in. square column form. The col
umn is 11 ft 6 in. high. The form will be constructed with f-in . Plyform sheathing (4 ft
by 8 ft) and three 2 x 4 vertical w ood battens on each side of the column form. The
Plyform will be placed in the horizontal direction for maximum strength. Lumber will
be purchased in 12 -ft lengths.
Plyform sheathing:
Height of column: 11 ft 6 in. = 11.5 ft
Number of sheets in vertical direction:
(11.5 ft)/(4 ft/sheet) = 2.9, use 3 sheets
Perimeter of column: 22 in. x 4 sides = 88 in., or 7.3 ft
Number of sheets in horizontal direction:
(7.3 ft )/(8 ft/sheet) = 0.9, use 1 sheet
Total = 4 sheets
T A B L E 1 0 .2 I Quantities of plywood, lumber, and labor-hours required for 100 SFCA of column forms.
Column forms are usually prefabricated at the job prior to erecting in place.
The lumber and sheathing are cut to the proper sizes. The four sides are assem
bled and fastened together with column clamps. After the forms are assembled,
they are set into templates that have been accurately and securely located. It may
be necessary to support the forms above the floor or column base until the col
umn reinforcement is tied in place. Some contractors prefer to place the column
reinforcing steel first and then assemble the forms around it.
If it is not necessary to rebuild the forms for each use, the estimator should
separate the labor into two operations, making the forms and then erecting and
removing them. For subsequent uses, if the sizes are not altered, only the labor
for removing, cleaning, and erecting the forms should be considered.
Chapter 10 Concrete Structures 235
EXAMPLE 1 0 . 6
Use the information in Table 10.2 to estimate the quantities of material and labor-
hours to form 40 columns 30 in. by 30 in. by 14 ft 6 in. long. Assume the lumber will
be used four times. The 4-ft by 8-ft plywood sheathing will cost $28/sheet, lumber will
cost $0.55/bf, and nails cost $0.49/lb. Steel column clam ps will be rented at $3.50
each. The hourly rate for carpenters is $21.56/hr and helpers labor rate is $15.56/hr.
Quantity of materials:
Total surface area: 40 colum ns x (30 in./12 in./ft) x 4 sides x 14.5 ft =
5,800 SFCA
Number of columns placed simultaneously: 40 colum ns/4 uses = 10 columns
Columns to be built: 5,800 SFCA/4 uses = 1450 SFCA
Columns to be erected and removed = 5,800 SFCA
Since the 30 in. is not evenly divisible by a 4-ft x 8-ft sheet and the 14-ft 6-in.
height is not com patible with a 2 -ft increment, there will be waste for the plywood
and lumber. Average values from Table 10.2 will be used for quantities.
EXAMPLE 1 0 . 7
Estimate the cost of the 40 columns in Example 10.6 assuming the forms will not be
reused. Assume the column dimensions, material, and labor unit costs remain the
same as given in Example 10.6.
Quantity of materials:
Total surface area: 40 colum ns x (30 in,/12 in./ft) x 4 sides x 14.5 ft =
5,800 SFCA
Number of columns placed simultaneously = 40 columns
A verage values from Table 10.2:
Plywood: (125 sf/100 SFCA) X 5,800 SFCA = 7,250 sf
Number of sheets: (7,250 sf)/(32 sf/sheet) = 226.6, use 227 sheets
Lumber: (165 bf/100 SFCA) X 5,800 SFCA = 9,570 bf
From Fig. 10.7, 40 columns x 10 clam ps/colum n = 400 clam ps
Form oil: (5,800 SFCA)/(400 gal/SFCA) = 14.5 gal
Material cost:
Plyform: 227 sheets @ $28 = $6,356.00
Lumber: 9,570 bf @ $0.55/bf = 5,263.50
Column clamps: 400 @ $3.50 = 1,400.00
Form oil: 14.5 gal @ $7.50/gal = 108.75
Total = $13,128.25
Chapter 10 Concrete Structures 237
Labor cost:
Making forms:
Carpenter: 5,800 SFCA X
(3.5 hr/100 SFCA) = 203 hr @ $21.56/hr = $4,376.68
Helper: 5,800 SFCA X
(1.5 hr/100 SFCA) = 87 hr @ $15.56/hr = 1,353.72
Total cost making forms = $5,730.40
Erecting and removing forms:
Carpenter: 5,800 SFCA X
(6.5 hr/100 SFCA) = 377 hr @ $21.56/hr = $8,128.12
Helper: 5,800 SFCA x
(5.0 hr/100 SFCA) = 2 9 0 hr @ $15.56/hr = 4,512.40
Total cost erecting and removing = $12,640.52
Summary of costs:
Material = $13,128.25
Labor = 22,430.92
Total = $35,559.17
purlins and screw jacks can be installed under the lower shore. The screw jacks
provide adjustments of the shore height to the correct position.
Single-post steel shores are manufactured and available for purchase or rent
by many manufacturers. Each post shore typically consists of two parts: a base
post with a threaded collar for adjusting the shore height and a staff member that
fits into the base post.
Tubular scaffolding is available to support high and heavy loads, such as
elevated concrete floor slabs. The contractor often rents scaffolding for a partic
ular job. However, if the scaffolding can be used often on many jobs it may be
justifiable to purchase the scaffolding. Figure 10.10 shows forms for a floor slab
supported by the tubular steel frames.
(a) Dim ension lum ber beam bottom (b ) Plywood beam bottom backed
with lum ber cleated together with lum ber laid flat
The beam bottom can also be plywood, backed by dimension lumber laid in
the flat position, as illustrated in Fig. 10.11b. Plywood panels are placed on the
top of the runners to provide a continuous smooth surface for the beam bottom.
As illustrated in Fig. 10.1 lc, the beam bottom can also be plywood, backed with
dimension lumber placed in the vertical direction to provide more resistance to
bending and deflection. The side forms are made of plywood panels, held
together by form ties. Side forms can also be made with lumber, held together
with 2 X 4 cleats. The ledgers attached to the vertical 2 X 4 cleats assist in sup
porting the ends of the joists.
The quantities of material and labor-hours to build 100 SFCA of forms for
concrete beams of various sizes are shown in Table 10.3. For concrete beam
24 2 Estimating Construction Costs
T A B L E 1 0 .3 I Approximate quantities of material and labor-hours required for 100 SFCA of concrete beams.
forms the amount of time for carpenters is significantly greater than for helpers,
compared to walls and column because of the complexity of the formwork.
Table 10.3 provides data on multiple uses of the forms.
EXAMPLE 1 0 . 8
Estimate the cost of forms for 15 concrete beams for a building. The beams are 12
in. wide, 19 in. deep, and 20 ft 6 in. long. The forms will be used three times.Use
average values from Table 10.3 to determine the quantities of materials.
A material supplier quotes these prices: $0.55/bf for lumber, $0.49/lb for nails,
and $7.50/gal for form oil. Carpenters cost $21.56/hr and laborers cost $15.56/hr.
Quantity of material:
Surface area of forms: 15 beams x ^ ■■n ' + ^ In' + 19 'n ' x 20.5 ft = 1,281 SFCA
12 in ./ft
From Table 10.3 for 3 uses,
Quantity of lumber = 1,281 SFCA X (110 bf/100 SFCA) = 1,409 bf
Quantity of plywood: 1,281 SFCA x (40 sf/100 SFCA) = 512 sf
Number of sheets required: (512 sf)/(32 sf/sheet) = 16 sheets
Material costs:
Lumber: 1,409 bf @ $0.55/bf = $774.95
Plywood: 16 sheets @ $28/sheet = 448.00
Form ties: 154 ties @ $0.47/tie = 72.38
Nails: 16.9 lb @ $0.49/lb = 8.28
Form oil: 3.2 gal @ $7.50/gal = 24.00
Material cost = $1,327.61
Summary of costs:
Total labor and material: $4,155.76 + $1,327.61 = $5,483.37
Cost/SFCA: $5,483.37/1,281 SFCA = $4.28/SFCA
The quantity of material depends on the thickness of the slab and the height
of the slab above the supporting floor. Table 10.4 gives the quantity of materi
als and number of labor-hours per 100 SFCA to build and remove forms for flat-
slab concrete floors.
Labor-hours
Ceiling height, Thickness
ft of slab, in. Plywood, sf Lumber, bf Carpenter Helper
10 6 100-105 150-155 6.0-6.5 2.0-2.5
8 100-105 165-170 6.0-6.5 2.0-2.5
10 100-105 180-190 6.0-6.5 2.0-2.5
12 6 100-105 150-155 6.5-7.0 2.5-3.0
8 100-105 165-170 6.5-7.0 2.5-3.0
10 100-105 180-190 6.5-7.0 2.5-3.0
14 6 100-105 150-155 7.0-7.5 3.0-3.5
8 100-105 165-170 7.0-7.5 3.0-3.5
10 100-105 180-190 7.0-7.5 3.0-3.5
Chapter 10 Concrete Structures 245
EXAMPLE 1 0 . 9
Estimate the direct cost of furnishing, building, and removing forms for a flat-slab
concrete floor whose size is 56 ft 8 in. by 88 ft 6 in. The ceiling height will be 11 ft
8 in. and the slab will be 6 in. thick.
Lumber will be 4 x 4 joists and 4 x 6 stringers, no. 2 Southern Pine, and the
cost will be $0.97/bf. The g-in.--thick plywood will cost $35 for a 4 ft by 8 ft sheet. Nails
cost $0.49/lb and form oil costs $7.50/gal. Assume carpenters cost $ 2 1 .56/hr and
laborers cost $15.56/hr.
Scaffolding, similar to that shown in Fig. 10.9, will be rented from a local build
ing supplier at a rate of $0.30/sf of floor area. It will require 1 hr to set up and take
down 100 sf of scaffolding.
Quantity of material:
Total surface area: 56 ft 8 in. X 88 ft 6 in. = 56.67 ft x 88.5 ft = 5,015 SFCA
Total cost:
Form costs + scaffolding cost = $24,704.82 + $2,285.61 = $26,990.43
Total cost per SFCA: $26,990.43/5,015 SFCA = $5.38/SFCA
Cross section
Longitudinal section
Non holes perm it FLANGE TYPE
variation m depth o f
I jo is t from 6 "to !4"\
»*!■_ I. I J
-Steelform
^ —■>?
'Meyer a d ju sta b le Meyer gdjustobie^>\
- steel shores Cross section steel shores
Longitudinal section
ADJUSTABLE TYPE
F IG U R E 1 0 .1 3 I Supporting forms for metal pans.
Chapter 10 Concrete Structures 247
Fiberglass domes are available for forming a two-way floor system, some
times called a waffle slab. Domes are available in depths of 12 in. to 24 in. and
widths of 4 ft. Manufacturers of metal pan forms or domes furnish dimensions
of their forms and other pertinent information.
When using commercial pans or domes, the total quantity of concrete is less
than flat-slab floors, which reduces the cost of materials and also permits the use
of smaller beams, columns, and footings. If the pans are used enough times, the
cost per square foot of use, including the labor cost of installing and removing,
can compare favorably with forms built entirely of lumber.
The structural designer specifies the particular system that is to be used. The
structure is designed for a specific size and type of pan. Since the pans are
designed for a specific job, contractors typically rent the pans at an agreed price
per square foot per use, with a minimum number of uses.
Labor-hours
Ceiling height, ft Floor thickness, in. Lumber, bf Carpenter Helper
12 10 120 3.5 4.0 4.0-4.5
12 130 4.0-4.5 4.5-5.0
14 140 4.0-4.5 4.5-5.0
14 10 130 3.5-4.0 4.0-4.5
12 140 4.0-4.5 4.5-5.0
14 150 4.1-4.5 4.5-5.0
16 10 140 3.5-4.0 4.0-4.5
12 150 4.0-4.5 4.5-5.0
10 160 4.0-4.5 4.5-5.0
Note: The thickness of the floor equals the depth of the pan plus the slab thickness.
E X A M P L E 1 0 .1
Estimate the cost of form lumber and metal pans in place and removed from a total
floor area 39 ft 6 in. wide by 96 ft 6 in. long. The floor thickness will be 12 in. The joints
will run one way only. The ceiling height will be 14 ft.
248 Estimating Construction Costs
Rental cost of the metal pans is $2.30/sf and scaffolding will be rented at
$0.30/sf. Assume 4 x 4 centering lumber and 4 x 6 stringers costs $0.97. W age rate
for carpenters is $21.56/hr and $15.56/hr for laborers.
Quantity of materials:
Total floor area: 39.5 ft x 96.5 ft = 3,812 sf
From Table 10.5, lumber = 3,812 sf x (140 bf/100 sf) = 5,337 bf
Material costs:
Lumber: 5,337 bf @ $0.9.7/bf = $5,176.89
Nails: 26.7 lb @ $0.49/lb = 13.08
Form oil: 9.5 gal @ $7.50/gal = 71.25
Material cost = $5,261.22
Labor costs:
Carpenter: 3,812 SFCA x
(4.2 hr/100 SFCA) = 160.1 hr @ $21.56/hr = $3,451.76
Laborer: 3,812 SFCA X
(4.7 hr/100 SFCA) = 179.2 hr @ $15.56/hr = 2,788.35
Foreman based on 4 carpenters:
160.1 hr/4 = 40 hr @ $28.00/hr = 1,120.00
Total labor = $7,360.11
Rental costs:
Rental cost of metal-pan forms: 3,812 sf @ $2.30/sf = $8,767.60
Rental cost of scaffolding: 3,812 sf @ $0.30/sf = 1,143.60
Labor to set up and take down scaffolding = 500.00
Total cost = $10,411.20
Summary of costs:
Material costs = $5,261.22
Labor costs = $7,360.11
Rental costs = $10,411.20
Total costs = $23,032.53
CORRUGATED-STEEL FORMS
Corrugated-steel sheets are sometimes used as forms for concrete floor and roof
slabs supported by steel joists, steel beams, and precast concrete joists. The sheets
are available in several gauges, widths, and lengths to fit different requirements.
The sheets are laid directly on the supporting joists or beams with the cor
rugations perpendicular to the supports. Side laps should be one-half of a corru
gation and end laps should be at least 3 in., made over supporting joists or
Chapter 10 Concrete Structures 249
beams. The sheets are fastened to the supports with special clips. The edges of
adjacent sheets are fastened together with steel clips.
CONCRETE STAIRS
The construction of concrete stairways is complicated and presents a problem
for the estimator. The costs per unit of volume or area varies greatly, depending
on the length of the tread, the width of the tread, the height of the riser, the shape
of the supporting floor for the shores, whether the treads are square or rounded,
and whether the ends of the treads and risers are open or closed with curbs. Some
stairs are straight-run, while others have an intermediate landing. Some stairs are
completely in the open, while others have a wall on one or both sides. All of
these conditions affect the cost of stairs.
The width of treads varies from 8 to 12 in., and the height of the risers varies
from 6 to 8 in. for different stairs. Steel dowels should be set in the concrete floor
and the beam supporting the landing prior to placing the concrete in the floor and
landing. These dowels are tied to the reinforcing steel for the stairs as it is placed.
EXAM PLE
Estimate the quantity of materials and cost for building the forms for the stairs illus
trated in Fig. 10.14, assuming the stairs are 6 ft wide. Plywood will be used for
sheathing under the stairs.
Quantity of material:
Diagonal side stringers:
2 pieces: 2 x 12 lumber x 20 ft long = 80 bf
2 pieces: 2 x 4 lumber x 22 ft long = 29 bf
Joists, 5 pieces: 2 X 8 lumber x 16 ft long = 107 bf
The cost just given is for a single use. If the forms can be removed and reused
on stairs of the same design, the cost per use will be reduced by the number of
times the forms will be used. Frequently, forms for stairs are supported by shores
that rest on existing lower stairs. If this construction is used, the lengths of all shores
will be increased to 9 ft for Fig. 10.14.
REINFORCING STEEL
TYPES AND SOURCES OF
REINFORCING STEEL
Reinforcing for concrete may consist of steel deformed bars or welded-wire fab
ric, used separately or together. The cost of reinforcing steel bars is estimated by
the pound, hundredweight, or ton, while the cost of welded-wire fabric is esti
mated by the pound or square foot.
252 Estimating Construction Costs
Usually reinforcing steel is cut to the required lengths and bent into the
required shapes by steel suppliers prior to delivery to a job. Such shops are
equipped with machines that will perform the fabricating operations more eco
nomically than when fabricating is performed on the job. Upon request, these
shops will furnish quotations covering the supplying and fabricating of all rein
forcing for a given project. Estimators frequently request such quotations before
preparing estimates.
assigned a number or a letter of the alphabet. Such designations are called piece
marks or bar marks.
For a particular project there may be many rebar schedules. For example,
there may be a separate rebar schedule for drilled shaft foundations, grade
beams, columns, beams, and floor slabs.
Placement of reinforcing steel where round members intersect with flat mem
bers, comers, and other complicated connections greatly increases the time to set
and tie the steel in place.
Reinforcing steel should be stored as near the structure as possible, prefer
ably not more than 50 to 100 ft away, to reduce the time required to carry them.
If steel must be carried to upper floors or parts of a structure, additional time will
be required. For some projects the lay-down area for materials is limited, which
requires storage of bulk material in a remote location on the job. When bulk
shipments of material, such as reinforcing steel, are delivered to the job a spe
cial effort should be made to store the material so it can be easily identified and
moved to the work area without having to restack the material.
Rigid tolerances on the spacing of reinforcing bars will reduce the rate of
placing steel. The estimator should review the contract documents and appro
priate standards that apply to a particular job to determine the dimensional tol
erances that must be used for setting the steel.
More time is required to tie bars at every intersection than when little or no
tying is required. The estimator must review the contract documents to deter
mine the requirements that apply.
Laborers or skilled steel setters may place reinforcing steel. The cost per
hour of skilled steel setters will be higher than that of laborers, but they should
be able to better read the drawings, place the steel at a faster rate, and require lit
tle or no supervision. The labor-hours to place reinforcing steel will vary
depending on these factors.
Table 10.8 gives representative rates of placing reinforcing steel bars. The
rates are based on carrying the steel by hand not more than 1 0 0 ft from the stor
age area to the structure. To estimate the cost of placing reinforcing steel, the
Bar size
Type of work | and less | and over
Beams and girders 19-21 11-12
Columns 20-22 13-15
Elevated slabs 10-12 10-12
Footings 14-16 8-9
Slab on grade 13-15 13-15
Spirals and stirrups 12-14 12-14
Walls 10-11 8-9
estimator must determine the quantity of steel (in pounds or tons) for each type
of work and then use the data in Table 10.8 to determine the labor-hours. The
total labor cost can then be determined by multiplying the labor-hour by the
labor rate.
WELDED-WIRE FABRIC
For certain types of concrete projects, such as sidewalks, pavements, floors,
canal linings, etc., it may be more economical to use welded-wire fabric for rein
forcing instead of steel bars. This fabric is made from cold-drawn steel wire,
electrically welded at the intersections of longitudinal and transverse wires, to
form rectangular or square patterns. It is available in flat sheets or rolls, the lat
ter frequently being 60 in. wide and 150 ft long. It is usually priced by the square
foot or roll, the price depending on the weight.
The quantity required will equal the total area to be reinforced, with 5 to 10
percent of the area added for side and end laps. The fabric to be used is desig
nated by specifying the style, such as 412-610. This style designates a rectangu
lar fabric with longitudinal wires spaced 4 in. apart and transverse wires spaced
1 2 in. apart, using no. 6 gauge longitudinal wires and no. 1 0 gauge transverse
CONCRETE
COST OF CONCRETE
The cost of concrete includes the cost of sand, aggregate, cement, water, admix
tures, mixing, transporting, and placing the concrete. Concrete mixed at the job
site is rarely used, except in small quantities that do not require rigid quality.
Ready-mix concrete is used for most concrete structures, rather than mixing the
concrete at the jobsite. The cost of concrete delivered to the job will vary with
the size of the job, the location, and the quality of concrete. The cost to place the
concrete after it arrives at the job depends on the extent to which equipment is
Chapter 10 Concrete Structures 257
Sectional area of
Spacing of wire, in. Gauge number wires, in.2/ft
Weight,
lb per Longi- Trans Longi Trans Longi Trans
Style 100 sf tudinal verse tudinal verse tudinal verse
44-1010 31 4 4 10 10 0.043 0.043
44-88 44 4 4 8 8 0.062 0.062
44-66 62 4 4 6 6 0.087 0.087
44-44 85 4 4 4 4 0.120 0.120
66-1010 . 21 6 6 10 10 0.029 0.029
66-88 30 6 6 8 8 0.041 0.041
66-66 42 6 6 6 6 0.058 0.058
66-44 58 6 6 4 4 0.080 0.080
66-22 78 6 6 2 2 0.108 0.108
48-1012 20 4 8 10 12 0.043 0.013
48-912 23 4 8 9 12 0.052 0.013
48-812 27 4 8 8 12 0.062 0.013
412-1012 19 4 12 10 12 0.043 0.009
412-812 25 4 12 8 12 0.062 0.009
412-610 36 4 12 6 10 0.087 0.014
412-49 49 4 12 4 9 0.120 0.017
412-48 51 4 12 4 8 0.120 0.021
416-812 25 4 16 8 12 0.062 0.007
416-610 35 4 16 6 10 0.087 0.011
416-49 48 4 16 4 9 0.120 0.013
416-28 64 4 16 2 8 0.162 0.015
612-66 32 6 12 6 6 0.058 0.029
612-44 44 6 12 4 4 0.080 0.040
612-22 59 6 12 2 2 0.108 0.054
612-14 61 6 12, 1 4 0.126 0.040
612-03 72 6 12 0 3 0.148 0.047
used. For example, the concrete* may be placed directly into the forms using
laborers to distribute the concrete. The concrete may also be placed using a crane
with a bucket attached, or pumped by a concrete pump truck.
QUANTITIES OF MATERIALS
FOR CONCRETE
The estimator should determine the cubic yards of each class of concrete in the
job. A reasonable amount should be included for waste, such as 10 percent for a
small job or 5 percent for larger jobs.
Concrete structures are designed for concretes having specified strengths,
usually expressed in pounds per square inch in compression 28 days after it is
placed in the structure. To produce a concrete with a specified strength, it is
common practice to employ a commercial laboratory to design the mix. Such a
258 Estimating Construction Costs
Weights of saturated
surface-dry aggregate, lb
Sacks of 28-day compressive
cement Water, gai Fine Coarse strength, psi
1 -in. coarse aggregate
4.9 39.1 1,370 1,860 2,250
5.6 39.1 1,345 1,847 2,750
6.0 39.0 1,260 1,860 3,000
6.5 39.0 1,235 1,820 3,300
7.2 39.8 1,150 1,875 3,700
8.0 40.0 1,120 1,840 4,250
operated by gasoline engines are used to consolidate the concrete. For flat-work
concrete, laborers screed the top of the concrete to the required level. The finisher
applies the required surface texture. The surface of the concrete can be broom fin
ished, hand toweled, or machine toweled.
The labor-hours required to place concrete will vary with the rate of deliv
ery, type of structure, and location of the structure. Depending on the type of
work, the concrete may be placed below the ground, on the ground, or above the
ground.
Deep foundations require placement of the concrete into holes drilled into
the ground. The concrete is discharged from the truck into a trimie to prevent
separation of the concrete mix as it is dropped to depths from 5 to 50 ft below
the surface of the ground. The trimie is a flexible hose that extends from the
ground to the bottom of the drilled shaft. The trimie is pulled as the concrete
placement moves from the bottom to the top of the drilled shaft. Generally a
crew of not more than two to four workers is required.
For shallow foundations, such as spread footing, grade beams, and small
slabs on grades, it may be possible to discharge the concrete directly into the
forms from the chute on the back of the delivery truck. If the job conditions are
such that the delivery truck cannot place the concrete directly into the forms,
hand buggies and wheelbarrows may be used to transport from 4 to 9 cy of con
crete, provided there are smooth and rigid runways on which to operate. Hand
buggies are safer than wheelbarrows because they have two wheels rather than
one. Hand buggies and wheelbarrows are recommended only for distances less
than 2 0 0 ft.
For large slabs on grade, where the concrete delivery truck cannot be placed
sufficiently close to directly discharge the concrete in the forms, it can be desir
able to pump the concrete, otherwise the workers using concrete buggies must
transport the concrete.
For elevated concrete structures, such as columns, beams, girders, and floor
slabs, etc., two methods can be used: crane and bucket or pumping. If concrete
is placed using a crane with a bucket, it is desirable to have two buckets avail
able for the crane. Concrete can be discharged from the concrete truck into one
bucket on the ground while the crane transports the filled bucket for placement
of concrete in the elevated forms.
For large volumes of concrete placement, or concrete that must be placed at
high elevations, it may be more economical to use a pump to place the concrete
directly into the forms. Pumps require a steady supply of concrete to be effec
tive. Pumps can be mounted on trucks, trailers, or skids. The concrete is placed
into a hopper of the pump truck, which pumps the concrete through rigid pipes
or flexible tubes to the location of placement. Truck-mounted pump and boom
combination is particularly effective and cost-effective in saving labor.
Generally, the contractor hires the services of a company that specializes in
pumping concrete. Pumps are available in a variety of sizes, capable of deliver
ing concrete at sustained rates of 10 to 150 cy/hr. Effective pumping ranges from
300 to 1,000 ft horizontally and from 100 to 300 ft vertically.
260 Estimating Construction Costs
Belt conveyors are available for rapid movement of fresh concrete. They
may be portable or self-contained conveyors. Some models are designed to work
in series, to carry the concrete from one conveyor to another until it is dis
charged. Units are available that have the capability to side-discharge and spread
the concrete, for example, to place fresh concrete on a bridge deck.
Table 10.11 gives approximate labor-hours for various types of work
required to place concrete.
Method of handling
Type of work Direct chute Crane bucket Pumped
Continuous footings 0.3-0.4 0.6-0.8 0.4-0.5
Spread footings 0.6-0.7 1.0-1.3 0.6-0.8
Grade beams 0.3-0.4 0.5-0.7 0.3-0.4
Slabs on grade 0.3-0.4 0.5-0.6 0.4-0.5
Walls 0.4-0.5 0.7-0.9 0.5-0.6
Beams and girders — 1.4-1.8 1.0-1.2
Columns — 1.1-1.3 0.6-0.8
Elevated slabs — 0.6-0.8 0.4-0.5
LIGHTWEIGHT CONCRETE
When the strength of concrete is not a primary factor, and when a reduction in the
weight is desirable, lightweight aggregate, such as cinders, burned clay, vermicu-
lite, pumice, or other materials, may be used instead of sand and gravel or crushed
stone. Concrete made with this aggregate and Portland cement may weigh 40 to
1 0 0 lb/cf, depending on the aggregate and the amount of cement used, which is
substantially lighter than 150 lb/cy for normal weight concrete. Also, lightweight
concrete has better insulating properties than conventional concrete.
PROBLEMS
10.1 A concrete basement wall for a building has dimensions of 85 ft wide and 140 ft
long. A single monolithic placement of the concrete into the walls is planned.
Thus, the entire formwork system is to be built and erected before placement of
the concrete, thereby preventing any reuse of the forms.
The forms will be constructed using plywood and dimension lumber. Use
average values from Table 10.1 and the unit cost of material and labor as shown
in Example 10.3 to estimate the total cost and cost per SFCA for the formwork.
10.2 Estimate the cost of the formwork of Prob. 10.1, assuming the forms will be
used three times. Calculate the cost savings that can be achieved by reusing the
forms.
10.3 Construction of a building requires 24 in. by 24 in. square concrete columns. The
columns will be 14 ft high. A total of 75 columns are required in the structure.
All of the concrete will be placed in the columns at one time, thereby preventing
any reuse of the forms.
The forms will be constructed using plywood and dimension lumber. Use
average values from Table 10.2 and the unit cost of material and labor as shown
in Example 10.6 to estimate the total cost and cost per SFCA for the formwork.
10.4 Estimate the cost of formwork of Prob. 10.2, assuming the forms will be used
four times. Calculate the cost savings that can be achieved by reusing the forms.
10.5 Estimate the cost of forms for 68 concrete beams for a building. The beams are
15 in. wide, 22 in. deep, and 34 ft long. The forms will be used four times. The
formwork will be constructed with plywood and dimension lumber. Use average
values from Table 10.3 and the unit cost of material and labor as shown in
Example 10.8 to estimate the total cost and cost per SFCA for the formwork.
10.6 Estimate the direct cost of furnishing, building, and removing forms for a flat-
slab concrete floor whose size is 240 ft by 385 ft. The ceiling height will be 12 ft
and the slab will be 8 in. thick.
The forming system will be as shown in Figure 10.12, using plywood and
lumber, with 4 X 4 joists and 4 X 6 stringers. Use average values from Table
10.4 and the unit cost of material and labor as shown in Example 10.9 to esti
mate the total cost and cost per SFCA.
10.7 Estimate the total cost and cost per pound of reinforcing steel for a concrete slab
on grade. The floor will be 66 ft 8 in. long, 52 ft 4 in. wide, and 6 in. thick. The
reinforcing steel will be no. 4 bars (j in. dia) spaced not more than 12 in. apart
each way in the slab. The bars laid next to and parallel to the edges of the slab
will be placed 3 in. from the edges of the slab. The ends of the bars will extend
to within 2 in. from the edges of the slab.
Skilled steel setters will be used at a cost of $19.50/hr. The cost of reinforc
ing steel delivered to the job will be $0.28/lb. Use average values from
Table 10.8.
10.8 If the concrete wall is 9 in. thick, estimate the labor cost for placement of the
concrete by direct chute from the concrete delivery truck. Use average values
from Table 10.11 and assume the unit cost of labor is $ 21 .50/hr.
Steel Structures
TYPES OF STEEL STRUCTURES
Steel is used to erect such structures as multistory buildings, auditoriums, gymna
siums, theaters, churches, industrial buildings, roof trusses, stadiums, bridges,
towers, etc. In addition to steel structures, steel members are frequently used for
columns, beams, roof purlins, decking, joists, studs, lintels, and for other purposes.
Due to its high strength, steel is ideal for long spans and tall structures. Steel
consisting of standard shapes or fabricated plate girders is used for many multiple-
span bridges. Trusses made of steel can span large arenas for entertainment or
educational facilities. Galvanized steel angles are fabricated into space-truss
towers to support conductors and shield wires for electrical transmission struc
tures. Transmission towers often are 120 to 200 ft tall. Steel is also used to sup
port water towers and other types of elevated storage units. Skyscrapers are typ
ically constructed of steel.
erection, and the cost of field welding and painting as required. To these costs
the contractor will add the contractor’s cost for job overhead, general overhead,
and profit.
ITEMS OF COST IN A
STRUCTURAL-STEEL ESTIMATE
The items of cost that should be considered in preparing a comprehensive
detailed estimate for a steel structure include:
additional information. The steel supplier must prepare shop drawings before the
steel can be fabricated.
Steel suppliers maintain engineering and drafting departments, which pre
pare shop drawings in sufficient detail to enable their shops to fabricate the
members. These drawings show actual cut-lengths of each member, precise
location of drilled or punched holes, details of welded assemblies, and all other
dimensions necessary to fabricate the steel. Figure 11.1 is an example of the fab
rication details for a steel beam with bolted connections. The W16 X 40 wide
flange beam has a cut-length of 18 ft 4 5 in. with three f-in.-thick stiffener plates
and four drilled holes at each end. Each member in a structural steel project is
identified with its unique designation, called a piece mark, and detailed as illus
trated in this figure. After all the members are detailed in the shop drawings, a
bill of material is prepared for the entire project. The bill of material lists each
piece of steel, its size, type, length, and weight. The bill of material for the W16
X 40 beam is shown in Fig. 11.1.
it" 9'-2" 1 8 -2 4 __
vr
Vi
Bill of Material:
Item Dwg. Piece
no. no. mark Quant Type and size Notes Length Weight
FIGURE 11. 1 I Example of details for a bolted connection beam on a shop drawing.
Courtesy: W&W Steel Company.
Shop drawings are usually prepared on 24- by 36-in. size sheets. The num
ber of shop drawings required depends on the size and complexity of a job. One
job may require as few as one or two sheets of structural details, while another
job may require more than 100 sheets. The cost of preparing the drawings is
based on the complexity of the detailing and the number of sheets required.
Since the total cost of the drawings is charged to the steel that will be furnished
for a job, the cost per unit weight of steel will vary with the total cost of the
drawings and the quantity of steel. If only one member is fabricated, the cost per
member is high, whereas if a great many members are fabricated, the cost per
member will be much lower.
Chapter 11 Steel Structures 267
After the shop drawings are prepared, they are provided to the contractor,
who submits them to the designer for approval. The cost of preparing shop draw
ings is approximately 5 to 10 percent of the base price of steel.
EXAMPLE 1 1 . 1
Structural steel, consisting of beams, colum ns, angles, and plates, is used for a
framed building. All members are to be fabricated at a shop for high-strength bolted
connections. W ide flange beams will be used for beams and columns.
A list of members and details is given in the accom panying table. The small-size
beams are used for short spans and larger-size beams will be used for the longer
spans. The larger column sizes will be used for the lower floors, whereas the smaller
column sizes are used for the upper floors. Angles are used as seats and clips for
beam-to-column connections for joining together the structural members. Steel
plates are used for column base plates and splicing of column members.
Based on current econom ic conditions, the base price of steel quoted from the
supplier is $24.96/cwt for beams and columns, $28.43/cwt for plates, and $22.17/cwt
for angles. The steel will be delivered by 20-T trucks from the steel supplier a dis
tance of 134 mi to the job at a rate of $2.75/mi.
An illustrative breakdown of the base, fabrication, and delivery cost of the steel
is shown in this example. The percentage values given in the preceding paragraphs
of this book are used for fabrication, shop drawings, and painting.
Fabricating costs:
Columns: 1,123.87 cw t @ 85% X $24.96/cwt = $23,884.03
Beams: 1,173.93 cwt @ 85% x $24.96/cwt = 24,906.10
Plates: 60.30 cw t @ 95% x $28.42/cwt = 1,628.04
Angles: 3 in., 47.87 cw t @ 85% X $22.17/cwt = 902.09
Angles: 2 \ in., 5.77 cwt @ 90% X $22.17/cwt = 115.13
Total fabricating costs = $51,435.39
Shop painting:
7.5% X $60,256.62 = $4,519.25
Shop drawings:
10.0% X $60,256.62 = $6,025.66
Summary of costs:
Cost per pound, $139,441.67/241,174 lb = $0.58/lb
Cost per hundredweight, $139,441.67/2,411.74 = $57.79/cwt
Cost per ton, $139,441.67/120.59 T = $ 1 ,156/T
270 Estimating Construction Costs
Because cranes are used to hoist and move loads from one location to another,
it is necessary to know the lifting capacity and working range of a crane selected
to perform a given service. The lifting capacity of cranes for erecting steel struc
tures typically varies from 20 to 100 T. However, lifting capacities up to 500 T are
available. Individual manufacturers of equipment furnish specifications and infor
mation that describes the lifting capabilities and tipping loads of their equipment.
Steel erection contractors typically own the lifting equipment. However, for
special jobs that may require an unusually heavy or high lift, the crane may be
rented. The cranes can be rented per day, week, or month.
If welding girders to columns or beams to columns and girders, the top flanges
should be welded first and allowed to cool to the atmospheric temperature prior to
welding the bottom flanges. As the welds for the bottom flanges cool, the bottom
flanges at the ends of the beams will be subjected to tension. Since this stress is
opposite the stress to which the beams will be subjected under loaded conditions,
the effect of welding is to reduce the ultimate bending stresses in the beams. The
correct procedure in welding beams to columns is illustrated in Fig. 11.5.
— -V — ------1------
-Plate
/
j---------------------------------------------------------------------------------------------------------- ----------
-*---------------------------------------------------------------------------------------------------♦ ------------- !
ii Plate
iij Plate * 1
S h e lf/*
L
r \ - /
1
ft Shelf
L
------ \ ------ — \ ------
-|
Section A-A
F IG U R E 1 1 .5 I Details of beam-to-column welds.
Chapter 11 Steel Structures
Crew-hours
Type of work per 1,000 lin ft
Erecting steel beams, bolted connections
Crew: 4 ironworkers, 1 crane operator, 1 foreman
Equipment: 1 crane
W-sections, 8 in. deep 15.6-17.3
W-sections, 10 in. deep 15.2-16.8
W-sections, 12 in. deep 12.6-13.8
W-sections, 14 in. deep 11.0-12.1
W-sections, 16 in. deep 10.5-11.6
Erecting steel beams, welded connections
Crew: 5 ironworkers, 1 crane operator, 1 welder, 1 foreman
Equipment: 1 crane, 1 welding machine
W-sections, 18 in. deep 10.3-11.4
W-sections, 21 in. deep 9.3-10.2
W-sections, 24 in. deep 8.9-9.7
W-sections, 30 in. deep 8.6-9.4
W-sections, 36 in. deep 8.5-9.3
Erecting steel columns
Crew: 4 ironworkers, 1 crane operator, 1 foreman
Equipment: 1 crane
W-sections, 8 in. deep 8.6-9.6
W-sections, 10 in. deep 8.9-9.9
CD
Note: These crew-hours should be increased by 20 percent for erecting steel structures over six stories
high.
276 Estimating Construction Costs
E X A M P L E 1 1 .2
Estimate the cost of labor for erecting 7,931 lin ft of IV14 x 53 w ide flange beams
and 1,388 lin ft of I/V12 x 50 columns. The structure is two stories high and bolted
connections will be used. Use average values in Table 11.1 and assume these rates
for labor and equipm ent: $20.97/hr for ironworkers, $21.67/hr for the crane operator,
and $28.50/hr for the foreman. A 40-T crane will be used at a rate of $125.50/hr.
Quantity of materials:
Beams: 7,931 lin ft x 53 lb/ft = 420,343 lb
Columns: 1,388 lin ft x 50 lb/ft = 69,400 lb
Total w eight = 489,743 lb
If the fabricated steel for these beams and columns cost $1,156/T, then the total
installed cost will be: $1,156/T + $111/T = $1,267/T. This cost does not include the
cost for lateral bracing, steel joists, field painting, tools, overhead, taxes, insurance,
or profit.
PROBLEMS
11.1 The plan and elevation views of a five-story structural steel building are shown
in the accompanying drawing. A column schedule is also given for the building.
All beams will be W14 X 125 with 20-ft span lengths. Estimate the cost of erect
ing the beams and columns using average rates from Table 11.1 and the type of
crew and equipment, unit labor rates, and unit equipment rates as shown in
Example 11.2.
Column Schedule
Floor 1 W10 x 112
Floor 2 1/1/10 X 89
Floor 3 M/10 x 72
Floor 4 M/10 x 60
Floor 5 M/10 x 60
i ' 'C
\ Column 1
Five-story building
. f
WU X 125
Typical floor plan
60 ft
Carpentry
INTRODUCTION
Carpentry is classified as rough or finish. Rough carpentry involves the framing
of structural components, such as floors, walls, window and door openings, and
roof members. Finish carpentry involves installation of wood trim around doors
and windows, cabinetry, moldings, and related work. Sometimes frame carpen
ters are called rough carpenters and finish carpenters are called trim carpenters.
Carpenters are used in both heavy and building type projects. They fabricate
and install formwork for concrete structures, including foundations, box cul
verts, and bridge decks. They also frame and trim finished wood in residential
and commercial building construction. Thus, carpenters are used in all types of
construction.
CLASSIFICATION OF LUMBER
Lumber is classified by size, grade, and species. Lumber is measured and priced
by board feet (bf). A board foot is a piece of lumber whose nominal dimensions
are 1 in. thick, 12 in. wide, and 1 ft long. Thus, a 2 X 4 piece of lumber is equiv
alent to 0.67 bf per foot of length, whereas a 2 X 8 piece of lumber is equiva
lent to 1 . 2 2 bf per foot of length.
Lumber Sizes
The sizes of lumber, with the exception of certain specialties such as moldings,
are designated by the nominal dimensions of the cross sections, which are the
dimensions prior to finishing the lumber at the mill. After lumber is sawed
lengthwise at the mill, it may be passed through one or more finishing opera
tions, which will reduce its actual size to less than the identifying dimensions.
Thus, a 2-in. by 4-in. plank (nominal size) will actually be I 5 in. thick and 3 5 in.
wide (actual size) after it is surfaced on all four sides (S4S). This lumber is
called dimension lumber and it is designated by its nominal size as 2 X 4 S4S.
280 Estimating Construction Costs
Note that the side and end wastes are determined on the basis of the dimensions
of lumber required instead of the nominal dimensions.
Table 12.1 lists the commonly used sizes of lumber, with the nominal and
actual cross-sectional dimensions. In the table, the first dimension is the thick
ness and the second dimension is the width. Thinner members, 1 in. and 2 in.,
are often called lumber, whereas thicker, 3-in. to 12-in. members are referred to
as timber.
Select grades are used for trim, facings, moldings, etc., which may be fin
ished in natural color or painted. Grade A is the best quality, and grade D is the
poorest. Common grades are used for structural members such as sills, joists,
studs, rafters, planks, etc. Grade 1 is the best quality, and grade 3 is the poorest.
The lumber used for timber structures is generally designated as stress grade.
For example, timber marked with a “P” is designated for posts and timber
marked with a “B” is designated for beams.
PLYWOOD
Plywood is used for subfloors, siding, roof decks, and other similar purposes.
Panels of plywood are available in 4-ft widths and 8 -ft lengths with thicknesses
from \ in. through if in. Larger sizes are available, such as 5 ft wide and 12 ft long.
Plywood is manufactured with odd numbers of wood plies, each placed at
right angles to the adjacent ply, which accounts for the physical properties that
make it efficient in resisting bending, shear, and deflection. Therefore, the posi
tion in which a panel is attached to the supporting members will determine its
strength. For example, for a panel 4 ft wide and 8 ft long, the fibers of the sur
face plies are parallel to the 8 -ft length. Such a panel, installed with the outer
fibers perpendicular to the supporting members, such as studs, joists, or rafters,
is stronger than it would be if the panel were attached with the outer fibers par
allel to the supporting members.
Plywood is graded by the veneers of the plies. Veneer grade N or A is the
highest grade level. Grade N is intended for a smooth surface and a natural fin
ish, while grade A is intended for a smooth surface without a natural finish.
Plywood graded as N or A has no knots or restricted patches. Veneer grade B
has a solid surface, but may have small round knots, patches, and round plugs.
Grade C has small knots, knotholes, and patches. Grade D has larger and more
numerous knots, knotholes, and patches. Plywood can be purchased with differ
ent grades on opposite sides. For example, a plywood sheet may be j-in. AC,
which designates a j-in.-thick panel with grade A on one side and grade C on the
opposite.
The most commonly used thicknesses of plywood, in inches, are f, f, |, 1,
and if. Table 12.2 gives the thickness and approximate weight of 4-ft by 8 -ft
plywood panels.
COST OF LUMBER
Lumber is usually priced by the board foot or 1,000 bf, with the exception of cer
tain types used for trim, moldings, etc., which may be priced by the linear foot.
The cost varies with many factors, including:
The better grades of lumber cost more than the poorer grades. Select grades
are more expensive than common grades. In the select grades, the costs decrease
in the order A, B, C, and D, while the costs of common grades decrease in the
order 1, 2, and 3.
The cost of lumber is higher for thick and wide boards than for thin and nar
row ones. Lengths in excess of 20 to 24 ft may require special orders. Prices
quoted may be for lengths through 2 0 ft, with increasingly higher prices charged
for greater lengths.
Rough lumber is the product of the sawing operation, with no further sur
facing operation. After the lumber is sawed, it may be given a smooth surface
on one or more sides and edges, in which case it is designated surfaced one edge
(S IE), surfaced two sides (S2S), or surfaced on all edges and sides (S4S). It may
be surfaced on both sides with the edges matched with tongue and grooves, des
ignated as dressed and matched, D and M. These operations reduce the thickness
and width and increase the cost.
Freshly cut lumber contains considerable moisture that should be removed
before the lumber is used, to prevent excessive shrinkage after it is placed in the
structure. It usually is placed in a heated kiln to expel the excess moisture.
Trade name
Roofing
Length,
Size in. cjommon Spikes Casing Finishing Shingle Barbed No. 8 No. 9 No. 10
3 T
4 — — — — 714 205 252 290
7
8 — ■— — — — 469 179 219 253
2d 1 876 — 1,010 1,351 — 411 158 193 224
3d 1? 568 — 635 807 429 251 128 156 183
4d 316 — 473 584 274 176 108 131 154
5d , 1 | 271 — 406 500 235 151 93 113 133
6d ; 2 181 — 236 309 204 103
7d Pi 161 — 210 238
8d pi 106 — 145 189
9d * -4 96 — 132 172
10d 3 69 41 94 121
12d 3} 63 38 87 113
16d 3i 49 30 71 90
20d 4 31 23 52 62
30d 45 24 17 46
40d 5 18 13 35
50d 5i 14 10
60d 6 11 9
7 — 7
8 — 4
9 — 3j
10 — 3
12 — 2§
Two methods are used for driving nails into wood, hand driven or by pneu
matic nail guns. For rough carpentry framing, the use of nail guns can substan
tially reduce the time for driving nails, particularly for repetitive work such as
roofing shingles.
Note: If different sizes of common nails are used, make the following changes: increase the weight by 53 percent when substituting 10d for 8d
nails; increase the weight by 58 percent when substituting 20d for 16d nails.
286 E stim a ting C o n stru ctio n C osts
TABLE 12.5 I Weights of bolts with square heads and hexagonal nuts in pounds per 100.
D ia m e te r of b o lt, in
L e n g th u n d e r
1 5 3 7 1 5 3 7
h e a d , in. 16 2 s 4 6 1 1 ’s
4 16 8
85
_ 2 1.3 3 0.7 43.1 5 6.6 93 136 192 259 341 434
9 _ 2 2 .4 3 2.3 4 5.2 5 9.4 98 143 2 00 2 70 356 451
lengths. Lag screws require prebored holes of the proper sizes. The lead hole for
the shank should be of the same diameter as the shank. The diameter of the lead
hole for the threaded part of the screw should vary from 40 to 50 percent of the
shank diameter for lightweight species of wood, and 60 to 85 percent for dense
hardwoods. During installation, some type of lubricant should be used on the lag
screw or in the lead hole to facilitate insertion and to prevent damage to the lag
screw. Lag screws should be turned, not driven, into the wood.
TIMBER CONNECTORS
The strength of joints between wood members can be increased substantially by
using timber connectors. They are often used to securely connect wood members
in prefabricated wood trusses. Several types are available, including split rings,
shear plates, flat grids, flat clamping plates, and flanged clamping plates. Figure
12.1 illustrates various types of timber connectors. Table 12.6 gives weights and
dimensions of timber connectors.
Flat grid Single curved grid Flat clamping plate Flanged clamping plate
FIG U R E 12.1 I Timber connectors.
Split rings, in sizes with 2 \ in. and 4 in. diameters, are used with wood-to-
wood connections for heavy loads. It is necessary to drill a hole for the bolt and
a groove for the ring. A complete connector unit includes a split ring, bolt, and
two steel washers. Toothed rings in diameters of 2§ in. and 4 in. are used for
wood-to-wood connections in thin members with light loads. A complete unit
includes a toothed ring, bolt, and two steel washers.
Spike grids and flat clamping plates, made of malleable metal, are used to
joint two flat wood members, or connecting gusset plates for splicing the ends
of multiple members in roof trusses. Metal plate connectors are available as
hangers for connecting the end of joists to their supporting members. Toothed
ring, spiked grid, and flat clamping plate types of connectors are installed by
applying pressure against the assembly to force the connectors to penetrate the
wood members.
288 Estimating Construction Costs
Dimensions of
Shipping
metal, in. weight per
Timber connector Size, in. Depth Thickness 100, pound
Split rings 2| 0.75 0.163 28
4 1.00 0.193 70 ■
Toothed rings 2 0.94 0.061 9
2- 0.94 0.061 12
q3 0.94 0.061 15
4 0.94 0.061 18
Shear plates
Pressed steel p5 0.375 0.169 35
Malleable iron 4 0.62 0.20 90
Spike grids
Flat 4 b x 4g 1.00 — 48
Single curve 4 j x 4g 1.38 — 70
Circular 3g diam. — — 26
Clamping plates
Plain 5 j x 5} — 0.077 59
Flanged 5 x 8j 2.00 0.122 190
FABRICATING LUMBER
Fabricating lumber includes such operations as measuring, sawing, ripping,
chamfering edges, boring holes, etc. The rates at which these operations can be
performed will vary greatly with several factors, including:
1 . Amount of fabrication required
2 . Length of finished pieces
3. Size of pieces to be fabricated
4. Number of similar pieces fabricated with one machine setting
5. Care in sorting and storing lumber at the job
6 . Clarity and amount of details on the drawing
7. Skill of the carpenter and quality of supervision
Cutting multiple pieces of lumber with table saws and radial arm saws
requires considerably less time than when cutting individual members with hand
saws. It requires considerably more time to fabricate rafters and stair stringers
than it does to fabricate studs and joists.
Since a certain amount of time is required to handle and measure lumber,
more time is required to fabricate a given quantity of lumber consisting of short
lengths and small sections than when it consists of long lengths and large sec
tions. Time is required to set a machine for a given operation. If only a few
pieces are fabricated, after which the machine must be reset, the total time per
piece will be higher than when many similar pieces are fabricated.
Chapter 12 Carpentry 289
HOUSE FRAMING
Houses can be framed by several methods, as illustrated in Fig. 12.2. For the bal
loon frame, the studs for the outside walls of a two-story building extend from
Stud
p'T Partition wall—
I____ I U rn
13
Corner Partition Cross Double Joist
Stud details bridging under partition
Floor jo is t
the sill to the top plate on which the rafters rest. For the platform frame, the studs
for the external walls are limited to one story in length. The lengths of studs for
interior or partition walls for both types of frames are limited to one story.
SILLS
Sills are attached to grade beams, which are usually constructed of concrete or
masonry. The grade beams may rest directly on the ground, or they may be
placed on drilled concrete piers spaced at 4- to 6 -ft intervals. The sills may be
2 X 4, 2 X 6 , and 2 X 8 S4S lumber for light structures, or they can be 4 X 6
or larger members for heavy timber structures.
Anchor bolts are set in the grade beams at 6 - to 8 -ft intervals. The sills have
holes bored to permit the anchor bolts to pass through them. A nut and washer
secures the sill to the grade beam. Unless the top of a grade beam is smooth and
level, a layer of stiff mortar should be placed under each sill to ensure full bear
ing and uniform elevation. At the comers and at end joints, the sills should be
connected by half-lapped joints. It is common practice to place a strip of insula
tion material along the full length of sills to reduce air infiltration and provide
heat-loss protection to the interior of the structure.
Table 12.7 gives the labor-hours per 1,000 bf required to fabricate and
install sills, including boring the holes and tightening the nuts.
Labor-hours
Size sill, in. Carpenters Helper
2X 4 24-30 8-10
2 X6 18-22 6-8
2 X8 14-18 5-6
4X 6 15-20 5-7
4 X 10 14-19 5-7
FLOOR GIRDERS
Floor girders are installed under the first-floor joists to provide intermediate sup
port for the floor joists. The girders may consist of single pieces, or several
pieces of 2-in.-thick lumber that are nailed together. For heavy timber structures,
girders may be 4 X 6 or larger members. Piers, usually spaced from 8 to 10 ft,
support floor girders. End joints should be constructed with half-laps, located
above piers.
Table 12.8 gives the labor-hours required per 1,000 bf of floor girders.
Chapter 12 Carpentry 291
Labor-hours
Size joist, in. Carpenters Helper
2X4 13-16 4-5
2X6 11-13 4-5
2X8 9-12 4-5
2x10 8-11 4-5
2x12 7-10 4-5
Cross bridging per 100 sets
1x 3 5-6 1-2
2x3 5-6 1-2
292 Estimating Construction Costs
EXAMPLE 1 2 .1
Wood framing for a house requires 2 x 6 ceiling joists at 18 in. on centers. The struc
ture is 35 ft wide and 90 ft long. The joists will bear on the two exterior walls and an
interior wall that extends the full 90-ft length. A 1-ft overlap will be placed across the
interior wall. Two rows of 1 x 3 bridging will be installed the full 90-ft length of the
structure. Estimate the cost of material and labor for framing the joists, assuming
$0.55/bf for lumber, $21.56/hr for carpenters, and $15.56/hr for laborers.
Quantities of material:
Joists:
Joist spacing = 18 in./(12 in./ft) = 1.5 ft
Number of joists = [length of structure/spacing of joists] + 1
= [(90 ft)/( 1.5 ft/joist)] + 1 = 61 joists
Length of joists, assuming 18 ft/board: 61 joists x 2 boards x 18 ft = 2,196
lin ft
Board feet of joists: 2,196 lin ft x [(2 X 6)/(1 x 12)] = 2,196 bf
Bridging:
Number of sets of bridging: 61 rows x 2 sets/row = 122 sets
Length of 1 x 3 bridging: 1.5-ft boards x 2/set x 122 sets = 366 lin ft
Board feet of bridging: 366 lin ft x [(1 x 3)/(1 x 12)] = 91.5 bf
Labor-hours required:
From Table 12.9 for framing joists and bridging:
Carpenters framing joists: 2,196 bf x 12 hr/1,000 bf = 26.4 hr
Carpenters framing sets: 122 sets x 5.5 hr/100 sets = 6.7 hr
Total carpenter hours = 33.1 hr
Laborers framing joists: 2,196 bf x 4.5 hr/1,000 bf= 9.9 hr
Laborers framing bridging: 122 sets X 1.5 hr/100 sets = 1.8 hr
Total laborer hours = 11.7 hr
Cost of material and labor:
Joists: 2,196 bf @ $0.55/bf = $1,207.80
Bridging: 91.5 bf @ $0.55/bf = 50.33
Carpenters: 33.1 hr @ $21.56/hr = 713.64
Laborers: 11.7 hr @ $15.56/hr 182.05
Total cost = $2,153.82
Cost per board foot of lumber: $2,153.82/2,196 bf = $0.98/bf
Cost per linear foot of joist: $2,153,82/2,135 lin ft = $1.01/lin ft
In this example, the crew may consist of 3 carpenters and 1 laborer. The cost of
nails, tools, job supervision, overhead, and profit are excluded.
Chapter 12 Carpentry 293
Studs are generally purchased in standard 8 -ft lengths. If the wall is taller
than a standard 8 -ft height, then it is necessary to cut all the studs for a wall of
a room to the proper length. After the studs are cut to length, they are properly
spaced and nailed to a bottom and top plate on the subfloor, then tilted into posi
tion. A second top plate can then be installed to join the sections or to tie parti
tion walls to main walls. If 2 X 6 studs spaced at 24 in. on centers are used for
exterior walls and the roof trusses spaced at 24 in. on centers are set directly on
top of each stud, then the second top plate is sometimes omitted. Lateral rigid
ity for walls can be provided by plywood, diagonal steel tension straps, diago
nal sheathing, or cut-in braces installed at each comer of the building.
Table 12.10 gives labor-hours required per 1,000 bf for wall framing con
sisting of studs with one bottom and two top plates.
294 Estimating Construction Costs
Labor>hours
Size studs, Stud spacing,
in. in. C arpenters H elper
2X4 12 20-25 5-6
16 22-26 5-6
24 24-28 5-6
2X6 12 19-24 5-6
16 21-25 5-6
24 23-27 5-6
Note: These values apply to wall heights up to 10 ft. For walls over 10 ft high, increase
these values by 25 percent.
EXAM PLE 1 2 . 2
The total length of walls of a w ood-fram ed structure is 750 lin ft. The wall consists of
2 X 4 studs, 8 ft long, at 16 in. on centers with one bottom plate and two top plates.
An evaluation of the drawings shows there will be 42 corners. Estimate the cost of
material and labor, assuming lum ber is $0.55/bf and labor rates of $21.56/hr for ca r
penters and $15.56/hr for laborers.
Quantity of material:
Studs: [750 lin ft/(16/12)] = 562.5, or 563 studs X 8 ft = 4,504 lin ft
Bottom plates: 750 lin ft X 2 boards = 1,500 lin ft
Top plates: 750 lin ft x 1 board = 750 lin ft
Corners: 42 corners x 3 boards = 126boards x 8 ft = 1,008 lin ft
Total = 7,762 lin ft
Total board feet of lumber required: 7,762 lin ft x [(2 x 4)/(1 x 12)] = 5,175 bf
Labor-hours required:
From Table 12.10:
Carpenters: 5,175 bf X 24 hr/1,000 bf = 124.2 hr
Helpers: 5,175 bf x 5.5 hr/1,000 bf = 28.5 hr
Cost of material and labor:
Lumber: 5,175 bf @ $0.55/bf = $2,846.25
Carpenter: 124.2 hr @ $21.56/hr = 2,677.52
Laborers: 28.5 hr @ $15.56/hr = 443.46
Total = $5,967.23
For this example, the crew may consist of 4 carpenters and 1 laborer. The cost of
nails, tools, job supervision, overhead, and profit are excluded.
Chapter 12 Carpentry 295
framed above window openings. Each side of the window opening is framed with
a trim stud that is the same size as the wall studs and a horizontal board, called a
sill, which is framed along the bottom opening of the window. For windows
greater than 6 ft wide, two trim studs are installed in each side of the window.
The standard height of doors is 6 ft 8 in. Common widths of door openings
include 2 ft, 2 ft 8 in., 3 ft, 3 ft 6 in., and 4 ft. Larger heights and widths are
sometimes specified for a particular project. The size of a door is designated by
its width and height. For example, a door that is 3 ft 0 in. wide and 6 ft 8 in. high
is designated as a 3-0 6 - 8 door. The headers above doors may be 2 X 6 lumber
or larger. The vertical sides of door openings are called doorjambs.
The quantity of lumber required to frame window and door openings
depends on the width and height of the opening, which can be calculated from
the drawings for a particular project. To calculate the quantity, some estimators
do not deduct the size of the opening when calculating the lumber required to
frame the stud walls, assuming the quantity of lumber required to frame the
opening is approximately equal to the lumber that is required to frame the wall.
Table 12.11 gives the approximate labor-hours per 1,000 bf of lumber to
frame openings for doors and windows.
Labor-hours
Type and size
of opening Carpenters Helper
Windows:
Up to 5 ft wide 1.0-1.5 0.5-0.8
Over 5 ft wide 1.5-2.5 0.8-1.0
Doors
Up to 7 ft high 0.8-1.0 0.5-0.8
Over 7 ft high 1.0-1.2 0.8-1.0
RAFTERS
One method of roof construction is called joist and rafter framing, as illustrated
in Fig. 12.2. Rafters are the upper members of roofs. They are notched where
they rest on the wall plates and are held in place by nailing them to the wall
296 Estimating Construction Costs
plates or by use of metal framing anchors. The ridge board is placed at the top
and perpendicular to rafters. A horizontal collar beam is often placed below the
collar ridge beam to assist in resisting wind load on the roof. For long span
lengths, a diagonal knee brace is sometimes installed from the center of each
rafter down to the interior wall.
The labor required to frame and erect rafters will vary considerably with
the type of roof. The rise (vertical) over run (horizontal) dimension measures
the steepness of a roof. Typical rise over run for roofs includes 3:12, 4:12, 5:12,
and 6 :1 2 .
There are many configurations of roofs. Simple gable roofs are easier to
frame than hip roofs. Double-pitch or gable roofs, with no dormers or gables,
will require the least amount of labor, while hip roofs, with dormer or gables
framing into the main roof, will require the greatest amount of labor.
Table 12.12 gives labor-hours required per 1,000 bf for rafters.
EXAMPLE 1 2 . 3
Estimate the material and labor cost to frame rafters for a structure, 35 ft wide and
90 ft long. The slope (rise-over-run) of rafters is 5:12 and each rafter will extend 2 ft
outside of each exterior wall. The 2 x 6 rafter spacing will be spaced at 18 in. on
centers.
A 2 x 8 ridge board will extend the full 90 ft dimension of the roof. Horizontal
collar ties of 1 x 6 lumber will be placed across each rafter at a distance of 2 ft
below the peak of the rafters. Diagonal knee braces of 2 x 4 lumber will brace the
m idpoint of each rafter down to the center wall (see Fig. 12.4). Assume $0.55/bf for
lumber, $21.56/hr for carpenters, and $15.56/hr for laborers.
C hapter 12 Carpentry 297
Quantities of material:
Rafters:
Total width of structure: 35 ft + 2 overhangs @ 2 ft = 39 ft total width
Diagonal dimension for a 5:12 slope: V ( 5 ) i: + ( 1 2 )^ = 13 ft
Length of rafter: 39 ft x (13/12) = 42.3 ft, therefore need two 22-ft-long
boards
Number of rafters: [(length/spacing) + 1 ] = [90 ft/( 18/12) + 1] = 61 rafters
Linear feet of rafter: 61 rafters x 42.3 ft/rafter = 2,580 lin ft
Collar ties:
Horizontal length at 2 ft below peak of rafters with a 5:12 slope:
[2 ft x (12/5)] x 2 sides = 9.6 ft, therefore need 10-ft-long boards
Ridge board:
Total length = 90 ft
Number of boards required using 18-ft lengths: (90 ft)/( 18 ft/board) = 5
boards
Knee braces:
Total length: 17.5 ft x (13/12) = 18.96 ft, therefore, need two 10-ft-long
boards
Board feet of lumber:
Rafters: 61 rafters x 2 boards/rafter x 22 ft x [(2 x 6)/(1 x 1 2 )] = 2,684 bf
Collar ties: 61 ties x 10 ft/tie x [(1 x 6)/(1 x 12)] = 305 bf
Ridge board: 5 boards x 18 ft/board x [(2 x 8)/(1 x 12)] = 120 bf
Knee braces:
61 rafters x 2 braces/rafter x 10 ft x [(2 X 4)/(1 x 12)] = 813 bf
Total lumber = 3,922 bf
298 Estimating Construction Costs
Labor-hours required:
Using average values from Table 12.12:
Carpenters: 3,922 bf X (27 hr/1,000 bf) = 105.9 hr
Laborers: 3,922 bf X (7.5 hr/1,000 bf) = 29.4 hr
Cost of material and labor:
Lumber: 3,922 bf @ $0.55/bf = $ 2 ,1 5 7 .1 0
Carpenters: 105.9 hr @ $21.56/hr = 2,283.20
Laborers: 29.4 hr @ $15.56/hr = 457.46
Total cost = $4,897.76
Proper bracing of the first end truss is especially important to obtain the correct
alignment of the roof truss system.
The cost of prefabricated wood trusses is established by the supplier. Four
carpenters and a small lifting crane can erect trusses for about 2,000 to 3,000 sf
of floor area in one day.
ROOF DECKING
Roof deckings are usually constructed of §-, or f-in.-thick sheets of plywood
or wood fiber. The thickness of the sheets will vary, depending on the required
roof load and the spacing of the rafters. The decking is usually installed with a
pneumatic nail gun.
Roof decks can also be constructed with lumber. The lumber may be 1 X 6
or 1 X 8 S4S laid flat, fastened with at least two 8 d common nails per rafter. The
labor-hours will be slightly higher for a two-story building. Also, the labor-hours
will be higher for a steep roof than for a flat roof.
Table 12.13 gives the labor-hours required per 1,000 sf using plywood deck
ing. Table 12.14 gives the labor-hours required per 1,000 bf using 1 X 6 and
1 X 8 S4S lumber laid flat.
vLafc.bishoM.rSv'
Thickness of Rafter
plywood, in. spacing, in. Carpenters Helper
1
2 12 10-12 2-3
16 9-11 2-3
18 8-10 2-3
5
8 16 11-13 2-3
18 1 0 -1 2 2-3
20 9-11 2-3
3
4 16 12-14 2-3
18 11-13 2-3
24 10-12 2-3
Labor-hours
Decking size, Rafter spacing,
in. in. Carpenters Helper
1X 6 16 12-15 4-5
18 11-14 4-5
24 10-13 4-5
1X 8 16 11-14 4-5
18 10-13 4-5
24 9-12 4-5
300 Estimating Construction Costs
WOOD SHINGLES
There are two types of wood shingles, red cedar and shakes. Red cedar shingles
are available in lengths of 16 and 18 in., and in random widths. The shingles are
about | in. thick. These shingles are cut to relatively smooth surfaces and may
be installed with an exposure of 5 or l \ in. on the roof. Prior to placing red cedar
shingles, a 1 X 4 strip of lumber is nailed across the rafters of the roof. The spac
ing of the 1 X 4 lumber should correspond to the length of shingles exposed to
the weather. Each shingle should be fastened to the 1 X 4 strips with if- to 2-
in.-long nails. Each shingle should be fastened with two nails.
Hand-split red cedar shakes have irregular surfaces and are available in 18-
and 24-in. lengths with an 8 5 - or 10-in. exposure on the roof. Two types of wood
shakes are available, junior shakes and jumbo shakes. Junior shakes have thick
ness up to about | in., whereas jumbo shakes have random thickness greater than
| in. These shingles are installed on a 30-lb organic felt underlayment.
Wood shingles are measured by the square, which is 100 sf. They are pack
aged in bundles, which will cover about 20 to 25 sf of roof, depending on the
exposure. About 5 percent waste should be added for red cedar shingles and 10
percent waste for wood shakes.
In addition to using wood shingles on roofs, they are sometimes used for
exterior wall siding. To estimate wood shingles on walls, the openings for doors
and windows should be deducted from the total surface area of the walls.
Table 12.15 gives the labor-hours required to lay 100 sf of surface area for
wood shingles.
Note: Multiply the above values by 0.75 when pneumatic nail guns are used.
SUBFLOORS
Subfloors are usually constructed with plywood sheets. The thickness of the ply
wood will vary, depending on the required floor load and the spacing of the floor
Chapter 12 Carpentry 301
Labor-hours
Thickness of Joist spacing,
plywood, in. in. Carpenters Helper
5 10-11 2-3
8 12
16 9-10 2-3
18 8-9 2-3
3 11-12 2-3
4 16
18 10-11 2-3
24 9-10 2-3
T A B L E 1 2 .1 8 I Carpenter-hours
required per 100 lin ft of fascia, frieze,
and corner boards.
Item Carpenters
Fascia and frieze 4-5
Corner boards 3-4
SOFFITS
Soffits are measured by the square foot of area. Soffits may be or j-in. ply
wood, f-in. hardwood, or f-in.-thick wood fiber. The soffit is nailed to the ledger
and fascia header. Typically, the soffits are installed by carpenters, without the
help of laborers. It requires about 3.0 to 4.0 carpenter-hours to install 100 sf of
soffit.
WALL SHEATHING
Sheathing for exterior walls may consist of §-, or f-in.-thick sheets of ply
wood or insulating fiberboard. Plywood sheets are installed horizontally across
the vertical wood studs and fastened with 8 d common nails.
Table 12.19 gives the labor-hours required per 1,000 sf of exterior plywood
sheathing.
Labor-hours
Thickness of Stud spacing,
plywood, in. in. Carpenters Helper
1
2 12 13-15 2-3
16 11-13 2-3
18 10-11 2-3
5
8 16 14-16 2-3
18 12-14 2-3
20 11-13 2-3
3
4 16 15-17 2-3
18 13-14 2-3
24 12-14 2-3
occupies these structures, architects and engineers design them, unlike residen
tial wood structures that are designed by the builder who abides by local build
ing codes and inspectors.
Columns for heavy timber structures are usually square in sizes from 8 to
12 in. The sides are chamfered or rounded and the bottoms rest on and are
attached to the footings through fabricated metal column bases and bolts.
Column caps may be all wood, all metal, or a combination of wood and metal
with bolts and timber connectors to provide the transfer of loads and stresses
from girders, floor beams, or trusses.
Floor beams are usually 4 or 6 in. thick and 8 to 10 in. high, with span
lengths from 12 to 16 ft long. Girders are usually 8 to 12 in. thick and 12 to 24 in.
high, with span lengths up to 20 ft. Beams and girders are attached with timber
connectors or metal plates with bolts. Flooring for timber structures is usually
constructed of S4S tongue and groove lumber.
To estimate the cost of timber structures, the estimator must perform a
detailed material quantity takeoff, listing the number, size, and length of each
member in the structure.
Fabricating timber members for heavy timber structures involves starting
with commercial sizes of lumber and sawing them to the correct lengths and
shapes, boring holes, chamfering edges, etc. Table 12.21 gives the approximate
labor-hours per 1,000 board feet to fabricate and erect timbers. Because the
members are larger and heavier than wood framed structures, such as houses, a
small lifting crane is required to lift the members to the position for connecting.
After the timber members are cut to the proper length they are attached by tim
ber connectors, bolts, and plates.
PROBLEMS
12.1 Estimate the total direct cost and cost per 1,000 bf for furnishing and installing
96 floor joists size 2 X 8 lumber. The 17-ft-long joists will rest on wood sills at
each end of the joist and at the midpoint of the joist. Use average values from
Table 12.9, $21.56/hr for carpenters, $15.56/hr for laborers, and $0.55/bf for
lumber costs.
12.2 Estimate the total direct cost and cost per 1,000 bf for furnishing and installing
plywood subflooring for a floor area of 2,240 sf. The 4-ft by 8 -ft plywood, |-in .
306 Estimating Construction Costs
thick, will be placed on joists, spaced at 18 in. on centers. Use average values
from Table 12.13, $28.50/sheet for the 4-ft by 8 -ft plywood, $21.56/hr for car
penters, and $15.56/hr for helpers.
12.3 The total length of exterior walls of a residence is 464 lin ft. Studs, size 2 X 4 by
8 ft long, will be spaced not over 16 in. on centers. There will be 8 outside cor
ners and 12 inside comers, each requiring three studs. The studs will rest on
2 X 4 plates and will be capped at the tops with two 2 X 4 plates for the full
length of the walls.
Neglecting the door and window openings, prepare a list of materials for the
studs and the bottom and top plates, showing the number of pieces of each
length required. Estimate the total direct cost and cost per 1,000 bf for furnishing
and installing the studs and plates. Assume $0.55/bf for lumber, $21.56/hr for
carpenters, and $15.56/hr for laborers.
12.4 Estimate the total direct cost per 1,000 bf of lumber for furnishing and installing
2 X 8 rafters, spaced 24 in. on centers, for a rectangular building whose outside
dimensions are 42 ft wide and 135 ft long. The framing for rafters is the same as
shown in Example 12.3, using one set of knee braces, collar tie, and ridge board.
Use the same unit costs for material and labor as shown in Example 12.3.
12.5 The following is a list of windows and doors for a wood frame structure.
Estimate the cost of labor for framing the openings, assuming $21.56/hr for car
penters and $15.56/hr for laborers.
Size Number
Doors:
2 ft 8 in. x 6 ft 8 in. 5 each
3 ft 0 in. x 6 ft 8 in. 14 each
3 ft 6 in. x 6 ft 8 in. 2 each
Windows:
2 ft 0 in. x 4 ft 0 in. 4 each
2 ft 6 in. x 5 ft 0 in. 17 each
3 ft 0 in. x 5 ft 0 in. 8 each
4 ft 0 in. x 6 ft 0 in. 1 each
Interior Finish, Millwork,
and Wallboards
INTERIOR FINISH CARPENTRY
Examples of interior finish carpentry include moldings around ceilings, floors,
doors, and windows. Also included are hand railings, shelving, cabinets, vani
ties, fireplace mantels, louvers, shutters, etc. These items often are stained to
expose the natural grains in the wood, which requires skilled carpenters.
Moldings are estimated by the linear foot, whereas doors, windows, cabi
nets, etc., are usually estimated by the unit. The cost of these items will vary
considerably with the kind and grade of materials and the grade of workmanship
required. The most dependable method of estimating the cost of interior finish
and millwork is to list the quantity and cost of each item separately, together
with the quantity and cost of the labor required to install each item.
Many types and sizes of windows are available. They may be fabricated of
metal, wood, or vinyl. Prefabricated window frames are shipped from the sup
plier and installed in window openings that have been previously framed in the
stud walls. Windows may be single-hung or double-hung. For single-hung win
dows, only the bottom half of the window can be raised and lowered, whereas
both the top and bottom can be raised and lowered for double-hung windows.
Table 13.1 gives the carpenter-hours required to install various types of
doors and windows. Trim wood is installed around the top and both sides of the
door opening. Threshold is lumber placed between the bottom of the door and
the floor. After the windows are installed, trim wood is placed around them.
Table 13.2 gives the carpenter-hours to install trim around doors and windows.
GYPSUM WALLBOARDS
Gypsum wallboards, which are made by molding gypsum between two sheets of
paper, are used on walls and ceilings of buildings. Gypsum wallboard is some
times called sheetrock. They are manufactured in sheets, either \ or § in. thick,
4 ft wide, and lengths of 8 or 10 ft. Gypsum wallboards are fastened to furring
strips that are attached to concrete or masonry walls, or they may be installed
directly against wood studs and ceiling joists.
Where gypsum wallboards are installed on wood studs and ceiling joists, the
studs and joists should be placed at 12, 16, or 24 in. on centers because these
dimensions are divisible into the 4-ft width. For walls, the boards are usually
installed in vertical positions, with the length equal to the height of the wall. For
ceilings, they may be installed perpendicular to or parallel with the joists. Some
specifications require the use of nailing strips, such as 1 X 4 lumber, installed
perpendicular to the ceiling joists on 1 2 -in centers, to which the boards are fas
tened with nails.
Gypsum wallboards are fastened with sheetrock nails, size 5d or 6 d with f or
fg-in. heads, or by screws. Recommended spacing of fasteners are 8 in. for walls
and 7 in. for ceiling installation. For studs or joists spaced at 12 in. on centers, the
quantity of nails per 1,000 sf will be about 8 or 9 lb. For a 24-in. spacing, the
quantity will be about 4 or 5 lb per 1,000 sf.
The joints between adjacent gypsum boards are filled special cement, which
is spread with a putty knife to cover a strip about \ \ in. wide on each side of the
joint. After the cement is applied, the joint is covered with a perforated fiber tape
about 2 in. wide, and another layer of cement is applied and spread over the tape.
After the cement dries, it can be sanded to a uniformly smooth surface to elim
inate evidence of a joint for painting, or a textured surface can be spread over
the entire surface of the gypsum wallboard.
The labor-hours required to install gypsum wallboard will vary considerably
with the size and complexity of the area to be covered. For large wall or ceiling
areas, which require little or no cutting and fitting of the boards, two carpenters
should install a board 4 ft wide and 8 ft long in about 10 to 15 min. This is equiv
alent to 1 to 15 labor-hours per 100 sf. However, where an area contains numer
ous openings, it is necessary to mark the wallboards and cut them to fit the open
ings. For such areas, the labor-hours may be as high as 3 to 4 hr per 100 sf.
Cutting is done by scoring one side of the board with a curved knife, which is
drawn along a straightedge. A slight bending force will break the board along
the scored line. Table 13.4 gives representative labor-hours required to install
gypsum wallboard and perforated-tape joints.
WALL PANELING
Prefinished plywood panels are used as covering for walls, ceilings, and wain-
scotings in buildings. Panels \ to § in. thick, 4 ft wide, and 8 ft long are avail
able. Prefinished plywood panels are available in many species, including birch,
310 Estimating Construction Costs
Labor-hours
Spacing of studs
or joists, in.
Unit of
Operation measure 12 16 24
Install wallboard
Large areas 100 sf 1.7 1.5 1.2
Medium-size rooms 100 sf 2.8 2.5 2.0
Small rooms 100 sf 4.0 3.5 3.0
Install perforated tape and
sand the surface 100 lin ft 4.0 4.0 4.0
cherry, chestnut, mahogany, oak, pine, pecan, rosewood, and teak. Since the ply
wood is prefinished, special finishing nails are used to fasten panels to the
framed walls.
The cost of prefinished plywood panels depends on the size and species and
can be obtained from building suppliers. The cost of labor installing plywood
panels will vary considerably with the size, shape, and complexity of the area to
be covered. Where areas are large and plain, the waste of materials will be low,
and labor can install them rapidly. However, where areas are small or irregular,
with many openings, which require considerable cutting and fitting, the waste
can be large and the cost of labor will be higher. The area to be covered should
be carefully examined prior to preparing an estimate. Depending on the com
plexity of the area, it requires from 3 to 5 carpenter-hours per 100 sf to install
prefinished plywood panels.
T A B L E 1 3 .5 I Carpenter-hours
required per 100 lin ft of interior trim
moldings.
Item Carpenters
Base boards 3.5-4.0
Base board shoes 3.0-3.5
Cornice molding 2.5-3.0
Crown molding 3.0-4.0
"Generally all widths of softwood flooring are available in each listed thickness. In some locations
not all listed nominal widths of hardwood may be available. Also hardwood may be available in
other thicknesses.
The percentages of side waste listed in Table 13.6 are determined by divid
ing the reduction in width by the net width. For example, if the nominal width
is 4 in. and the face width is 3 \ in., then the loss in width is f or 0.75 in. For these
dimensions the table lists the percentage to be added for side waste. For exam
ple, (0.75 X 100)/3.25 = 23.1 percent. The reason for using this procedure is
that when the quantity of lumber required is determined, the area of the floor is
known. If the quantity of side waste listed in Table 13.6 is added to the area of
the floor for the particular nominal width of flooring selected, this allowance
will be sufficient for the side waster. An additional amount may be required for
end waste, resulting from sawing to shorter lengths.
Wood flooring is also available in prefinished strips, § in. thick and widths
of 2 \ and 2>\ in. These prefinished strips of tongue and groove wood are glued,
rather than nailed, to either concrete or wood floors.
Parquet patterns of wood are also used for finished wood floors. This type
of flooring is usually walnut, teak, or oak. Various patterns and sizes of blocks
are available, about ^ in. thick and in blocks of 9 or 12 in. square.
312 Estimating Construction Costs
Table 13.7 gives the approximate labor-hours per 100 sf to install wood
floors.
PROBLEMS
13.1 The following is a door and window schedule for a building. Use average values
from Table 13.1 and estimate the labor cost to set the doors and windows,
assuming carpenters cost $21.56/hr.
Doors:
2 ft 8 in. x 6 ft 8 in. 5 each Hollow core Interior
2 ft 8 in. X 6 ft 8 in. 12 each Hollow core Interior
3 ft 0 in. X 6 ft 8 in. 14 each Wood Interior
3 ft 6 in. x 6 ft 8 in. 2 each Wood Exterior
Windows:
2 ft 0 in. x 4 ft 0 in. 4 each Metal
2 ft 6 in. x 5 ft 0 in. 17 each Wood
3 ft 0 in. x 5 ft 0 in. 8 each Wood
4 ft 0 in. X 6 ft 0 in. 1 each Vinyl
13.2 Estimate the labor cost to install trim for the doors and windows in the following
schedule, assuming carpenters cost $21.56/hr. Include threshold only for exterior
doors.
Doors:
2 ft 8 in. x 6 ft 8 in. 12 each Hollow core Interior
3 ft 0 in. x 6 ft 8 in. 14 each Wood Interior
3 ft 6 in. x 6 ft 8 in. 2 each Wood Exterior
Windows:
2 ft 0 in. x 4 ft 0 in. 4 each Wood
3 ft 6 in. x 5 ft 0 in. 17 each Wood
4 ft 0 in. X 5 ft 0 in. 8 each Wood
5 ft 0 in. x 6 ft 0 in. 1 each Wood
13.3 Estimate the total cost and cost per square foot to furnish and install gypsum
wallboard on the walls of a wood frame building. The structure has 250 lin ft of
exterior walls and 480 lin ft of interior walls. A review of the construction draw
ings reveals that the structure has medium-size rooms and the stud spacing is
16 in. on centers. The gypsum board must be installed on one side of the exterior
Chapter 13 Interior Finish, Millwork, and Wallboards 313
wall and both sides of the interior walls. Neglect the cost of installing perforated
tape and sanding the surface. Assume that a 4-ft by 8-ft sheet of gypsum board
costs $6.20 each and carpenters cost $21.56/hr.
13.4 Estimate the labor cost for installing gypsum wallboard for the ceilings of a
structure consisting of 5,435 sf. A review of the drawings for the project shows
that 10 percent of the rooms are large, 70 percent of the rooms are medium size,
and 20 percent of the rooms are small size. Neglect the cost to install perforated
tape and sanding the surface. Assume carpenters cost $21.56/hr.
Roofing and Flashing
ROOFING MATERIALS
Roofing refers to the furnishing of materials and labor to install coverings for
roofs of buildings. Several kinds of materials are used, including but not lim
ited to:
1. Shingles
a. Wood
b. Asphalt
2. Slate
3. Clay tile
4. Built-up
5. Metal
a. Copper
b. Aluminum
c. Galvanized steel
d. Tin
AREA OF A ROOF
The unit of measure for roofing is the square, which is 100 sf. Roofing materi
als used to cover ridges and valleys are measured by linear feet, with the width
specified.
The area to be roofed is the full length and width, measured along the slope
of the roof, including eaves, overhangs, etc. Some estimators do not deduct for
the areas of openings containing less than 100 sf. A minimum of 5 percent waste
should be added to calculated quantities.
Chapter 14 Roofing and Flashing 315
STEEPNESS OF ROOFS
Some estimators define the steepness of a roof by its pitch. Others define steep
ness by the vertical rise over the horizontal run, measured in inches. These terms
and their values are
Rise
Pitch in./ft
1
8 3
1 6
4
1 8
3
1 12
2
2 16
3
ROOFING FELT
Most specifications require installation of an asphalt felt underlayment prior to
placing roofing shingles, such as asphalt, slate, shakes, and tile. Two weights of
asphalt felt are used, either 15 or 30 lb/square. This material is sold in rolls con
taining 108, 216, and 432 sf, which will cover 100, 200, and 400 sf, respectively,
with a 2-in. lap. Galvanized nails about § in. long, with ^-in. heads, spaced about
6 in. apart along the edges, are used to hold the felt in place.
_______________________________ROOFING SHINGLES
WOOD SHINGLES
Wood shingles, both red cedar and shakes, are discussed in Chapter 12 under
Carpentry.
316 Estimating Construction Costs
ASPHALT SHINGLES
Asphalt shingles are manufactured in several styles, colors, and sizes, including
organic asphalt, fiberglass asphalt, hexagon, etc. The shingles are fastened to
wood decking with galvanized roofing nails, 1 to l | in. long, starting at the
lower edge of the roof. Asphalt starting strips should be laid along the eaves of
a roof prior to laying the first row of shingles, or the first row can be doubled,
as illustrated in Fig. 14.1.
Shingles
overhang
roke ’A to
strip
Start 4th course or course o f shingles
with full strip_ , inverted
minus / tab
Start 3rd
course with
full strip"
minus B“— first course
/*■
Start 2nd course with with full strip
full strip minus 4
F IG U R E 14.1 I Three-tab strip asphalt shingles.
EXAMPLE 1 4 .1
Estimate the cost of material and labor for installing asphalt shingles for the struc
ture shown in the plan view in Fig. 14.2. As shown in the plan view there are three
gables with the same slope of 5:12, rise over run. The dimensions shown are for the
outside walls of the building. A 2-ft overhang is required, therefore the end of the roof
extends 2 ft on either side of the outside walls.
25 ft -15 ft - 50 ft
25 ft
5 ft
5 ft
_I_
A 15-lb felt underlaym ent will be installed prior to installing three-tab, 235-lb
asphalt shingles. Assume material costs of $2.50/square for the felt, $27.75/square
for shingles, and $0.49/lb for nails. The cost of labor includes $21.56/hr for carpen
ters and $15.56/hr for laborers.
Quantities of materials:
Slope lengths (see Fig. 14.3):
Section /A; 29 ft x (13/12) = 31.42 ft
Section B: 34 ft x (13/12) = 36.83 ft
Section C: 39 ft X (13/12) = 42.25 ft
25 ft + 4 ft = 29 ftN ‘
-2 9 ft-
SLATE ROOFING
Slate for roofing is made by splitting slate blocks into pieces having the desired
thicknesses, length, and width. The slate is usually ^ or \ in. thick and up to
16 in. in widths and lengths. Colors include black, green, gray, red, and purple.
Slate is heavy material, weighing from 170 to 180 lb/cf. For a 3-in. head lap,
]|-in.-thick slate will weigh 700 lb/square and |-in.-thick slate will weigh about
900 lb/square.
Slate is priced by the square, with sufficient pieces furnished to cover a
square with a 3-in. head lap over the second course under the given course. Thus,
for slates 16 in. long, the length exposed to weather will be (16 — 3)/2 = 6.5 in.
This same calculation will apply to any length for which the head lap is 3 in. If
the slates are 8 -in. wide, the area covered will be 8 X 6.5 = 52 sq. in. The num
ber of slates required to cover a square will be (100 X 144)/52 = 277. For other
sizes the number required to cover a square can be determined in the same man
ner. An area should be increased 10 to 25 percent to allow for waste.
S la te s iz e , in . S la te r H e lp e r
12 x 8 5.0-7.0 2.5-3.5
16 x 8 4.0-6.0 2.0-3.0
16 x 12 3.5-5.2 1.8-2.7
16 X 16 3.2-5.0 1.6-2.5
nailed to the roof decking with galvanized nails. The clay tiles are more uniform
in shape than slates and therefore are easier to install. However, the tiles are brit
tle and are subject to breakage, which can reduce the production rate.
The rate of placing the tiles will depend on the steepness and complexity of
the roof. The labor-hours required to lay clay tile roofing should be about 4.5 to
7.0 labor-hours per square for the roofer and 2.0 to 3.5 labor-hours per square
for the helpers.
BUILT-UP ROOFING
Building up roofing consists of applying alternate layers of roofing felt and hot
pitch or asphalt over the area to be covered, with gravel, crushed stone, or slag
applied uniformly over the top layer of pitch or asphalt. This type of roofing may
be applied to wood sheathing, concrete, poured gypsum, precast concrete tiles,
precast gypsum blocks, book tile, and approved insulation.
The quality of built-up roofing is designated by specifying the weight and
number of plies of felt, the weight and number of applications of pitch or
asphalt, and the weight of gravel or slag used. The unit of area is a square.
Not less than these quantities of materials should be used for each 100 sf of
roof area:
Weight, lb
Material Gravel Slag
Four plies of 15-lb asphalt felt 60 60
Roofing asphalt 100 100
Gravel or slag 400 300
Total weight 560 460
three, four, or five plies of asphalt felt, lapping each sheet enough to give the
required number of plies. Roll each sheet immediately behind the mop to ensure
a uniform coating of hot asphalt, so that in no place shall felt touch felt. Over the
entire area spread a uniform coating of hot asphalt into which, while hot, embed
not less than 400 lb of dry gravel or 300 lb of dry slag per square.
For a three-ply roofing the quantities of materials given in this table might
be used per square.
Weight, lb
Material Gravel Slag
Concrete primer 10 10
Three plies of 15-lb asphalt felt 45 45
Roofing asphalt 125 125
Gravel or slag 400 300
Total weight 580 480
A typical crew for laying roofing on buildings up to three stories high would
include one person each tending the kettle, handling hot asphalt or pitch, laying
felt, rolling felt, and mopping, with a foreman supervising all operations. On some
jobs one person may be able to tend the kettle and handle the asphalt or pitch.
Table 14.4 gives the labor-hours per square required to perform each oper
ation and to complete all operations for various types of built-up roofing. Use
the lower values for large plain roofs and the higher values for roofs with irreg
ular areas.
Operation Labor-hours*
Apply sheathing paper on wood deck 0.10-0.15
Apply primer on concrete 0.10-0.15
Lay 1 ply of roofing felt 0.10-0.15
Apply asphalt with mop 0.10-0.15
Apply asphalt and gravel 0.50-0.75
Apply 2-ply roofing on wood deck 1.3-2.0
Apply 3-ply roofing on wood deck 1.5-2.2
Apply 4-ply roofing on wood deck 1.7-2.5
Apply 5-ply roofing on wood deck 1.8-2.7
Apply 3-ply roofing on concrete 1.6-2.3
Apply 4-ply roofing on concrete 1.8-2.6
Apply 5-ply roofing on concrete 1.9-2.8
*The labor-hours for the last eight applications include three workers on the
roof and two workers heating and supplying hot asphalt.
FLASHING
Flashing is installed to prevent water from passing into or through areas such as
valleys and hips on roofs, where roofs meet walls, or where openings are cut
through roofs such as the chimney shown in Fig. 14.5. Materials used for flash
ing include sheets of copper, tin, galvanized steel, aluminum, lead, and some
times mopped layers of roofing felt.
Flashing is usually measured by the linear foot for widths up to 12 in. and
by the square foot for widths greater than 1 2 in.
METAL FLASHING
When metal flashing requires nails or other metal devices to hold it in place, it
is essential that the fastener and the flashing be of the same metal; otherwise,
galvanic action will soon destroy one of the metals.
324 Estimating Construction Costs
PROBLEMS
14.1 Estimate the total cost and the cost per square for furnishing and laying three-tab
asphalt shingles on a wood roof decking whose area is 3,436 sf. The roof will
have numerous valleys, hips, and dormers. Use the unit cost of materials and
labor as shown in Example 14.1.
14.2 Estimate the labor cost for installing flashing for a building, assuming $19.04/hr
for roofers. Quantity takeoffs from the plans reveal
Metal base around parapet wall: 870 lin ft
Metal counter flashing around walls: 870 lin ft
Metal shingles along chimney: 2 each
Masonry
MASONRY UNITS
Masonry units that are commonly used for construction include brick, concrete
masonry units, and stone, either natural or artificial. They are bonded by suitable
mortar. Masonry units are available in several sizes, grades, and textures. Plans
and specifications for a particular job designate the type of masonry unit, includ
ing its size, grade, and texture. The specifications also define the kind of mortar
and thickness of joints.
Members of the construction craft that installs masonry units are called
masons or bricklayers. Sometimes bricklayers are called brick masons. A helper
usually assists masons or bricklayers. Masonry construction is labor intensive.
Although the masonry units may be placed beside the masons, they must pick up
each individual unit, properly spread the mortar, and fit the unit in place one at
a time.
327
328 Estimating Construction Costs
MORTAR
Mortar for masonry units is made by mixing portland cement with lime or
masonry cement, and sand. The quantity of each ingredient may vary to produce
a mortar suitable for a particular job.
Mortar is designated as ASTM types M, S, N, O, PM, and PL. The M type
is high-strength, suitable for masonry subjected to high compressive loads,
severe frost action, high lateral loads from earth pressures, and structures below
grade. The S type is used for structures requiring high flexural bond strength, but
subject only to normal compressive loads. The N type mortar is used in medium-
strength mortar for general use above grade, specifically for exterior walls such
as masonry veneers applied to frame construction. Type O is used in low-strength
mortar for interior non-load-bearing partitions and for fireproofing.
The lime used for making masonry mortar is hydrated lime, which is cal
cium hydroxide. Lime, which sets only on contact with air, gives the mortar
workability, water retentivity, and elasticity. Hydrated lime can be purchased in
paper bags weighing 50 lb and containing 1 cf, or it can be purchased in bulk
quantities.
Sand acts as a filler and also contributes to the strength of the mix. If fine
sand is used, the workability of the mortar will be much better than if coarse
sand is used. The sand should be screened and washed at the rock quarry pit. The
price of sand may be quoted by cubic yard or ton.
Colored mortar is often required. The desired color is obtained by adding a
color pigment to the mortar mix. The cost of the color pigment is usually minimal,
but adding color to the mortar does require additional labor-hours to ensure con
sistency of the color during multiple mixing operations during a particular job.
Mortar properties may be specified by strength or by proportions. Table 15.1
gives the quantities of materials for 1 cy of various types of masonry mortar.
Cementitious materials
Sand, Portland Masonry Hydrated
Mortar dry, loose, cement, cement, lime,
type cy bag or cf bag or cf bag or cf
M 1.0 cy 4.5 4.5 None
1.0 cy 7.5 None 2.0
S 1.0 cy 3.0 6.0 None
1.0 cy 6.0 None 3.0
N 1.0 cy None 9.0 None
1.0 cy 4.5 None 4.5
0 1.0 cy None 9.0 None
1.0 cy 3.0 None 6.0
BRICKS
PATTERN BONDS
Masonry units may be oriented in various positions for construction of walls.
Bricks laid with the long dimension placed in the horizontal direction are called
stretchers. When the bricks are laid with the long dimension placed in the verti
cal direction, they are called soldiers. Bricks laid with their ends (height and
depth dimensions) exposed to the exterior are called headers.
330 Estimating Construction Costs
The arrangement of masonry units is call pattern bond. The common pattern
bonds are running bond, common bond, English bond, Flemish bond, basket pat
tern, and stack bond. Figure 15.1 illustrates these pattern bonds.
Stretcher Soldier
— n— ii ii ii
ir ii ii " ii hi n~~ii ii ii ii
ii ii ii ii ii ii
.. .... II ii ll ll ll
ii ii ii ii ii ll
ii ii ii ii ii
ii ii ll ll ll ll
ii ii ii II ' II II II II II «!|l
ir ii II II II II
English Flemish
1 1
1 1 1
1 1 1
1 1
1 1 I
1 1 1 1
Basket pattern Stack bond
FIG U R E 15.1 I Brick patterns for masonry units.
Running bond uses only stretcher courses with head joints centered over
stretches in the course below. Common bond is similar to the running bond,
except that a header course is repeated about every sixth course. English bond is
made up of alternated courses of headers and stretchers, with headers centered
on stretchers. Flemish bond alternates stretchers and headers in each course with
headers centered over stretchers in the course below. Stack bond provides no
Chapter 15 Masonry 331
interlocking between adjacent masonry units and is used for its architectural
effect. Horizontal reinforcement should be used with stack bond to provide lat
eral bonding.
Concave Raked
Flush-cut joints are made by passing the trowel across the surface of the
bricks and removing any excess mortar. This operation requires very little time.
Struck and weathered joints are made with a trowel after the mortar has
gained some stiffness. This operation requires more time than flush-cut joints.
Concave joints are made by tooling the mortar with a wood or nonstaining
metal rod before the mortar gains final set.
Convex joints are made by compressing the mortar during the process of
laying the brick.
Raked joints are made by removing the mortar to a depth of \ to | in., by
using a special tool.
modular bricks are given in Table 15.2. The actual manufactured sizes of these
bricks will be less than the nominal dimensions given in the table. For example,
the Norman brick may be manufactured with the dimensions of 2 \ by 3§ by 1 if
for use with f-in. mortar, or with the dimensions of 2 \ by 3 5 by 11\ for use with
j-in. mortar.
The quantity of mortar required for a single brick can be calculated with the
following equation.
Volume per brick = (L + H + t ) X t X D [15.1]
where t = thickness of mortar
L = length of brick
H = height of brick
D = depth of brick
EXAMPLE 1 5 . 1
Calculate the quantity of mortar per 1,000 bricks for Roman type modular brick for
construction of a brick veneer wall using running bond and |-in . thick mortar. Table
15.2 gives the nominal dimensions of this modular brick as 2 in. X 4 in. x 12 in. for
the height (H), depth (D), and length (/_), respectively. When this brick is purchased
from the manufacturer for |-in. mortar, the actual size will be 1 § in. x 3 | in. x 1 1 | in.
to accurately estimate the quantity of mortar that will be wasted in laying bricks.
Most estimators add 20 to 25 percent for mortar waste.
Table 15.3 gives the approximate cubic yards of mortar per 1,000 bricks. No
waste factor is given for the amounts shown.
T A B L E 1 5 .3 I Approximate cubic
yards of mortar per 1,000 bricks.
Thickness of
mortar
Name 1 in. \ in.
Standard 0.300 0.382
Engineer 0.319 0.404
Economy 0.341 0.433
Roman 0.397 0.506
Norman 0.419 0.533
Norwegian 0.433 0.552
SCR 0.648 0.837
Nominal
Thickness of horizontal mortar joint, in.
thickness
of wall, in. 1 3 1 5 3
4 8 2 8 .4
TABLE 15.5 I Cubic yards of mortar required per 1,000 standard-size (2|-in. by
3|-in. by 8-in.) bricks for full joints, using common bond (no allowance included
for waste).
are simple cut flush with a trowel. For some jobs, more than one bond pattern is
used, which increases the labor required to lay bricks.
Table 15.6 gives the approximate labor-hours to lay 1,000 bricks for modu
lar brick veneer walls and for nonmodular solid brick walls. The indicated time
includes mixing the mortar and laying the bricks.
TABLE 15.6 I Approximate labor-hours to lay 1,000 bricks for modular brick
veneer walls and solid brick walls.
Note: (1) For other than running bond pattern brick veneer increase by 7 percent; (2) for cavity walls,
the labor-hours should be increased by 15 percent; and (3) for curved walls, the labor-hours should
be increased by 30 percent.
EXAMPLE 1 5 .2
Estimate the total direct cost of material, labor, and equipm ent for constructing the
walls of a rectangular building 116 ft long, 68 ft wide, with brick veneer walls 10 ft
high. The total area of openings for doors and windows will be 468 sf.
The walls will be 4 in. thick, using Roman type bricks laid in common bond with
|-in . mortar joints on all sides. A header course will be placed every sixth course
between the stretcher courses. Wall ties will be placed every 16 in. in the horizontal
direction and every 24 in. in the vertical direction.
Material costs will be $615/1,000 bricks, $83/cy for mortar, and $4.25/100 wall
ties. Labor costs include $20.95/hr for bricklayers and $15.56/hr for helpers. The
mixer for mortar will cost $9.50/hr. Scaffolding rental will be $1,800 for the job.
Quantity of materials:
Gross outside area:
[(116 ft x 10 ft) x 2 walls] + [(68 ft X10 ft) x 2 walls] = 3,680 sf
D educt for four corners: [(4 in.)/(12 in./ft)] x 10 ft x 4 corners = - 1 3 sf
D educt for doors and windows = - 4 6 8 sf
Net area = 3,199 sf
Bricks required:
From Table 15.2 for Roman type modular brick
Stretcher bricks: [(1 brick)/(2 in. x 12 in.)] x 144 sq. in./sf = 6.0 bricks/sf
H eader bricks: [(1 brick)/(2 in. x 4 in.)] x 144 sq. in./sf = 18 bricks/sf
For comm on bond, every sixth course of bricks will be headers and the other
courses of bricks will be stretchers. Therefore, the num ber of bricks can be ca lcu
lated as:
Chapter 15 Masonry 337
Mortar required:
From Table 15.3 for Roman brick with j-in . mortar joints = 0.506 cy /1 ,000
brick
Quantity of mortar required: 26,872 bricks x 0.506 cy/1,000 bricks = 13.6 cy
Add 25% waste = 3.4 cy
Total mortar = 17.0 cy
Labor-hours required:
From Table 15.6 using average values for brick veneer walls with common bond:
Bricklayers: 26,872 bricks x 16 h r/ 1,000 bricks x 1.07 for comm on bond =
460 hr
Helpers: 26,872 bricks x 10.5 h r/ 1,000 bricks x 1.07 for comm on bond =
302 hr
Equipment required:
Time for mortar mixer assuming 3 bricklayers: 460 hr/3 = 153 hr
Rental cost of scaffolding = $1,800
Cost of material, labor, and equipment:
Materials:
Bricks: 26,872 bricks @ $615/1,000 bricks = $16,526.28
Mortar: 17.0 cy @ $83/cy = 1,411.00
Wall ties: 1,200 ties @ $4.25/100 ties = 51.00
Labor:
Bricklayers: 460 hr @ $ 20 .95/hr = 9,637.00
Helpers: 302 hr @ $15.56/hr = 4,699.12
Equipment:
Mortar mixer: 153 hr @ $9.50/hr = 1,453.60
Scaffolding rental = 1,800.00
Total cost = $35,578.00
338 Estimating Construction Costs
This cost does not include indirect costs of taxes, insurance, contingency, or profit.
TABLE 15.7 I Sizes, weights, and quantities of mortar for concrete blocks, using f-in.
joints.*
Approximate weight Quantities per 100 sf
per block, lb of wall area
Actual size:
thickness, height, Light Number Mortar,
length, in. Standard weight of blocks cy
3 {j ^ 4g X 1 1 Q 1 1 -1 3 8 -1 0 240 0 .1 5
X 4 | X 11 § 1 7 -1 9 1 2 -1 4 240 0 .1 6
7 | x 4 | X 11§ 2 2 -2 4 1 4 -1 6 240 0 .1 7
*00°
IOIOD
X
1 7 -1 9 1 2 -1 4 150 0.11
5 | x 7 | x 11| 2 6 -2 8 1 7 -1 9 150 0 .1 2
7 | x 7§ x 1 1 | 3 3 -3 5 2 1 -2 3 150 0 .1 3
5 | X 3 | x 15| 1 7 -1 9 1 1 -1 3 225 0 .1 8
7 | X 3 | X 15| 2 2 -2 4 1 4 -1 6 225 0 .1 9
3 § x 7§ X 15§ 2 3 -2 5 1 6 -1 8 113 0 .1 0
5 | X 7 | x 15| 3 5 -3 7 2 4 -2 7 113 0.11
OBii
ow.
cn
4 5 —47 2 8 -3 2 0 .1 2
X
113
X
‘ These quantities do not include any allowance for waste. Add 2 to 5 percent for blocks and 20 to 50 percent for
mortar.
Chapter 15 Masonry 339
not include any allowance for waste, which frequently will amount from 2 0 to
50 percent of the net amount required.
EXAMPLE 1 5 . 3
Estimate the total direct cost and cost per 1,000 CMUs for furnishing and laying
standard-weight concrete masonry units for a rectangular building 120 ft long, 80 ft
wide, and 14 ft high. The total area of the openings will be 516 sf.
The CMUs will be 8 in. by 8 in. by 16 in. and mortar joints will be §-in. thick. Three
rows of bond beams are required, reinforced with two no. 5 reinforcing steel bars.
The manufacturer's literature shows 0.22 cf of concrete is required to fill each linear
foot of the U -shaped CMUs that will be used for the bond beams.
Material costs will be $1.86/CMU and $83/cy for mortar. Material costs for the
bond beam will be $0.30/lb for reinforcing steel and $79/cy for the concrete. Labor
costs include $20.95/hr for masons, $15.56/hr for helpers, and $18.67/hr for the
mixer operator. Equipm ent for mixing the mortar will cost $9.50/hr. Scaffolding rental
will be $2,500 for the job.
340 Estimating Construction Costs
Quantity of materials:
Outside perimeter of wall: (120 ft + 80 ft) x 2 walls = 400 lin ft
Gross outside area:
[(120 ft x 14 ft) X 2 walls] + [(80 ft x 14 ft) x 2 walls] = 5,600 sf
D educt for four corners: [(8 in.)/(12 in./ft)] x 14 ft x 4 corners = - 3 7 sf
Deduct for doors and windows = - 5 1 6 sf
Net area = 5,047 sf
CMUs required:
From Table 15.7, num ber of concrete masonry units = 113 CMUs/100 sf
Num ber of CMUs required: 5,047 sf x (113 CMUs/100 sf) = 5,703 CMUs
Add 5% waste = + 2 8 5 CMUs
Total = 5,988 CMUs
Chapter 15 Masonry 341
Mortar required:
From Table 15.7 for 8-in. by 8-in. by 16-in. CMUs = 0.1? cy/100 sf
Quantity of mortar required: 5,047 sf x (0.12 cy /100 sf) = 6.1 cy
Add 30% waste = 1.8 cy
Total mortar = 7.9 cy
W eight of no. 5 bars: 3 rows x 400 lin ft x 2 bars x 1.043 lb/ft = 2,503 lb
A dd for lap splicing:
3 rows X [(400 lin ft)/(20 lin ft/lap)] x 1 ft/lap x 1.043 lb/ft = 63 lb
Total = 2,566 lb
Labor-hours required:
Labor installing CMUs in wall:
Table 15.8 using average values for 8-in. by 8-in, by 16-in. CMUs:
Masons installing CMUs: 5,988 CMUs x 54.5 hr/1,000 CMUs = 326 hr
Masons installing bond beams: (400 lin ft/15 lin ft/hr) x 3 rows = 80 hr
Total = 406 hr
Equipment required:
Time for mortar mixer assuming 3 masons: 406 hr/3 = 135 hr
Rental cost of scaffolding = $2,500
Equipment:
Mortar mixer: 135 hr @ $9.50/hr = 1,282.50
Scaffolding rental = 2,500.00
Total cost = $34,161.72
This cost does not include lifting equipm ent if required or the indirect costs of taxes,
insurance, contingency, or profit.
STONE MASONRY
Several kinds of stone, both natural and artificial, are used in structures such as
buildings, walls, piers, etc. Natural stones used for construction include sand
stone, limestone, dolomite, slate, granite, marble, etc. Artificial limestone is
available in many areas.
Each kind of stone and work should be estimated separately. The cost of
stone in place can be estimated by the cubic yard, ton, cubic foot, square foot, or
linear foot. Because of the various methods of pricing stonework, an estimator
should be very careful to use the correct method in preparing the estimate.
WEIGHTS OF STONE
Table 15.10 gives the ranges in weights of stones commonly used for masonry.
The given weights are expressed in pounds per net cubic foot of volume.
Chapter 15 Masonry 343
COST OF STONE
The cost of stone varies so much with the kind of stone, extent of cutting done
at the quarry, and location of use that no estimate that requires accurate pricing
should be made without obtaining current prices for the particular stone. The
cost of freight to the destination must be added to the cost at the source to deter
mine the cost at the job.
Stones suitable for rubble masonry may be priced by the ton for the speci
fied kind of stone and sizes of pieces.
344 Estimating Construction Costs
Labor-hours required
Per cy Per cf
Operation Skilled Helper Skilled Helper
Unloading stones from truck 0 .2 - 0 .4 0 .8 - 1.6 0 .0 1 - 0 .0 2 0.03-0.06
Rough squaring 4.0-10.0 — 0.15-0.37
Smoothing beds 6 .0 - 12.0 0.22-0.45
Setting stone by hand
Rubble 2.0-4.0 3.0-6.0 0.08-0.15 0 . 11 - 0 .2 2
Rough squared 3.0-6.0 4.0-9.0 0 . 11 - 0 .2 2 0.15-0.33
Ashlar, 4- to 6 -in. veneer 10.0-15.0 10.0-15.0 0.37-0.55 0.37-0.55
Setting stones by using a hand derrick
Heavy cut stone, ashlar, cornices,
copings, etc. 2.0-3.0 12.0-18.0 0.08-0.11 0.45-0.67
Light cut stone, ashlar, sills, lintels,
cornices, etc. 2.5-4.0 12.5-20.0 0.09-0.15 0.46-0.75
Setting stones by using a power crane
Heavy cut stone
Crane operator 1 .0 - 2 .0 — 0.04-0.08
Stone setter 1 .0 - 2 .0 — 0.04-0.08
Helpers — 7.0-14.0 — 0.26-0.52
Medium cut stone
Crane operator 1.5-3.0 — 0.06-0.11
Stone setter 1.5-3.0 — 0.06-0.11
Helpers — 9.0-18.0 — 0.33-0.67
Pointing cut stone
Heavy stone 0.5 -0 .8 0 .2 - 0 .4 0.02-0.03 0 .0 1 - 0 .0 2
Veneer, 4 to 6 in. thick 1.0-1.5 0 .2 - 0 .8 0.04-0.06 0.02-0.03
Cleaning stone
Stone setter, 1.5 hr/100 sf
Helper, 0.75 hr/100 sf
Chapter 15 Masonry 345
EXAMPLE 1 5 . 4
Estimate the cost per 100 sf for furnishing and setting stone in random ashlar bond
for a building. The stone will be sawed on the top and bottom beds and on the front
and back faces. It will be furnished in random lengths to be sawed to the desired
lengths at the job. The thickness will be 4 in. The stone will be set with 3-in. mortar
joints. The stone will be hoisted with a hand derrick.
The stone, w hich will w eigh 150 Ib/cf, will be delivered to the job at a cost of
$326.00/T. Allow 10 percent for waste.
The quantity of stone required for 100 sf will be
100 x 4 x 1.1_ _ 36 7 cf
12
PROBLEMS
15.1 Estimate the total direct cost and cost per 1,000 bricks for construction of walls
of a rectangular building, 56 ft 6 in. wide and 108 ft 0 in. long, with brick veneer
346 Estimating Construction Costs
walls 8 ft 9 in. high. The total area of openings for doors and windows will be
324 sf. The walls will be 4 in. thick, using Norman type bricks laid in running
bond with j-in. mortar joints on all sides. Wall ties will be placed every 16 in. in
the horizontal direction and every 24 in. in the vertical direction.
Material cost will be $586/1,000 bricks, $83/cy for mortar, and $4.25/100
wall ties. Labor costs include $20.95/hr for bricklayers and $15.56/hr for
helpers. The mixer for mortar will cost $9.50/hr. Scaffolding rental will be
$1,800 for the job.
15.2 Estimate the total direct cost and cost per 1,000 bricks for construction of walls
of a rectangular building, 75 ft 6 in. wide and 340 ft 0 in. long, with brick veneer
walls 10 ft high. The total area of openings for doors and windows will be 560
sf. The walls will be 4 in. thick, using Norwegian type bricks laid in common
bond with \ -in. mortar joints on all sides. A header course will be placed every
fifth course between the stretcher courses. Wall ties will be placed every 16 in.
in the horizontal direction and every 24 in. in the vertical direction.
Material cost will be $612/1,000 bricks, $83/cy for mortar, and $4.25/100
wall ties. Labor costs include $20.95/hr for bricklayers and $15.56/hr for
helpers. The mixer for mortar will cost $9.50/hr. Scaffolding rental will be
$1,800 for the job.
15.3 Estimate the total direct cost and cost per 1,000 CMUs for furnishing and laying
standard-weight concrete masonry units for a rectangular building 185 ft long,
95 ft wide, and 12 ft high. The total area of the openings will be 725 sf.
The CMUs will be 8 in. by 8 in. by 16 in. and mortar joints will be f in.
thick. Two rows of bond beams are required, reinforced with two no. 5 reinforc
ing steel bars. The manufacturer’s literature shows 0.33 cf of concrete is required
to fill each linear foot of the U-shaped CMUs that will be used for the bond
beams.
Use the unit costs for material, labor, and equipment shown in Example 15.3.
Floor Systems
This chapter describes several types of floor systems that can be used as substi
tutes for concrete-beam-and-slab, concrete slab only, or pan-and-joist concrete
floors. An examination of the cost developed for each of the floor systems and
a comparison with the cost of an all-concrete floor will reveal that reductions in
the cost frequently can be effected through the choice of the floor system.
Although these analyses are made for floor systems only, the results should
demonstrate that similar analyses for other parts of structures may also permit
the selection of methods and materials that will produce reductions in the costs.
STEEL-JOIST SYSTEM
GENERAL DESCRIPTION
Open-web steel joists (Fig. 16.1) are fabricated in the shop into the form of a
Warren truss by an arc-welding process. The chord members consist of T sec
tions, angles, or bars. The web is made of a single round bar, or angle, that is
welded to the top and bottom chord members. A steel bearing seat is welded to
each end of a joist to provide proper bearing area. The bearing seats are designed
to permit the ends of the joist to rest on masonry walls or structural-steel beams.
347
348 Estimating Construction Costs
bridging
C eiling
extension
BRIDGING
Typical bridging for steel joists includes horizontal angle struts that are welded
between adjacent joists. If cross bridging is required, angle struts are fabricated
that are bolted or welded to the top chord of one joist and the bottom chord of
an adjacent joist. Two struts are installed for each line of bridging to give a
cross-bridging effect.
Cross bridging should be installed in accordance with the specifications of
the designer or the manufacturer of the joists, which will be approximately as
shown in Table 16.1. These are common bridging requirements for light joists.
Longer spans can be obtained with heavier chord sizes with the above lines of
bridging.
Span, ft
Lines of bridging K series joists LH series joists
Row near center Up to 16 Up to 22
Rows at 5 points 16-24 22-33
Rows at I points 24-28 33-44
Chapter 16 Floor Systems 349
METAL DECKING
To support the concrete floor or roof, a continuous layer of ribbed metal deck
ing is installed over the joists, with ribs perpendicular to the joists. The decking
is fastened to the top chords of the joists by welding or screw fasteners, spaced
not over 15 in. apart along the joists. Metal decking is fabricated under various
trade names by several manufacturers. It is designated by shape, size, and gauge.
Table 16.2 provides a representative example of metal decking.
Floor decking should be lapped at least 2 in. beyond the center of support
ing joists at the end of sheets and should be securely fastened to the next sheet.
CEILING EXTENSIONS
Ceiling extensions are provided at the same elevation as the bottom chord when
a ceiling is to be attached. These extensions support the ceiling hanger wire
along the bearing wall or supporting beam.
A pproxim ate
Depth, Sp an length, w eig h t,
Type in. ft Ib/lin ft
K series
12K3 12 12-24 5.0
14K3 14 14-28 6.0
16K4 16 16-32 7.0
18K6 18 18-36 8.5
20K6 20 ' 20-40 9.0
22K7 22 22-44 10,0
24K8 24 24-48 11.5
26K8 26 26-52 12.0
28K9 28 28-56 13.0
30K10 30 30-60 15.0
LH series
18LH04 18 25-36 12.0
20LH06 20 25-40 15.0
24LH08 24 33-48 18.0
28LH09 28 41-56 21.0
32LH11 32 49-64 24.0
36LH12 36 57-72 25.0
44LH13 44 73-88 30.0
48LH15 48 81-96 36.0
DLH series
52DLH13 52 89-104 34.0
56DLH14 56 97-112 39.0
60DLH14 60 105-120 40.0
64DLH16 64 113-128 46.0
68DLH16 68 121-136 49.0
72DLH17 72 129-144 56.0
probable rate at which the joists will be erected. The rate will vary with the size
and length of the joists, method of supporting them, type of end connections,
type of bridging, height that they must be lifted, and complexity of the floor area.
In some locations, union regulations require that all labor erecting steel
joists must be performed by union mechanics, while in other locations helpers
are permitted to assist in the erection.
Table 16.4 gives the approximate labor-hours required to erect 1 T of steel
joists, including the installation of bridging and accessories. If helpers are not
permitted to assist the ironworkers, the time shown for helpers should be added
to that shown for the ironworkers.
hr/T
Length of span, ft Ironworker Helper*
Irregular construction, small areas
6-10 6.5 3.25
10-16 6.0 3.0
16-24 5.5 2.75
24-30 5.0 2.5
Regular construction, large areas
16-24 4.5 2.25
24-32 4.0 2.00
*For each floor above the first floor, add 1.5 helper-hours if the joists are
carried up by hand.
EXAMPLE 1 6 .1
Estimate the total direct cost of steel joists, metal decking, and a 2 J-in.-thick light
w eight concrete slab for a floor area 48 ft w ide and 72 ft long. The floor will be
divided into four bays, each 18 ft wide and 48 ft long as shown in Fig. 16.2. The floor
is one story above the ground level.
■Joists @ 2 ft on centers
Bridging
__ " 4 g - T — jL i - T i = j
:= = c zze ==;
iz z tz z tz z : iz z iz z iz z
: z z |z z ? z z :
iz z iz z z iiz z :
iz ^ fc z z c z z : ir z iz z iz z : 48 ft
i z z i — iz z :
:z z ± z z jz z :
:zz+ zz+ zz:
:— + — + — :
-----1----- j------ — +— +—
) ■"■■■■ r i 5---- i----- = — H S----T ~ ~ T i5— = — = — H
18ft- 18 ft- 18 ft- -*++ 18 ft-
72 ft
The steel joist will be type 16K4, 18 ft long, spaced 2 ft on centers, with two rows
of bridging per joist. The joist will be w elded to the supporting steel mem bers by two
1 -in.-long w elds at each end of each joist.
The joists will be covered with ^ -in . 28-gauge corrugated-m etal decking w eigh
ing 0.86 psf. The decking will be fastened to the joist with g-in. welds spaced not
over 15 in. apart.
C hapter 16 Floor Systems 353
The concrete will be reinforced with a 6 x 6-10/10 welded-w ire fabric. The top
surface of the concrete will be screeded to the required thickness, but will not be fin
ished under this estimate.
Quantities of materials:
Floor area: 48 ft X 72 ft = 3,456 sf
Concrete:
C ubic feetof concrete: 3,456 sf X [2.5 in./(12 in./ft)] = 720 cf
C ubic yards of concrete: 720 cf/(27 cf/cy) = 26.7 cy
A dd 10% waste, 10% x 26.7 cy = 2.7 cy
Total = 29.4 cy
Reinforcing steel:
Square feet of welded-w ire fabric = 3,456 sf
A dd 5% waste, 5% X 3,456 sf = 173 sf
Total area = 3,629 sf
Metal decking:
W eight of decking: 3,456 sf x 0.86 Ib/sf = 2,972 lb
A dd 2% waste, 2% X 2,972 lb = 59 lb
Total w eight = 3,031 lb
Joists:
Number of joists per bay: 48 ft/2 ft/joist - 2 = 22 joists/bay
Total num ber of joists: 22 joists/bay x 4 bays = 88 joists total
Total linear feet of joists: 88 joists x 18 ft/joist = 1,584 lin ft
W eight of 16K4 joists: 88 joists x 18 ft @ 7 lb/ft = 11,088 lb
Converting to tons: 11,088 lb/(2,000 Ib/T) = 5.5 T
Bridging:
Linear feet of struts: 48 ft/row x 2 rows/bay x 4 bays = 384 lin ft
Metal decking:
Metal decking: 3,031 lb @ $0.32/lb = $969.92
Ironworkers: 3,456 sf X (9 hr/1,000 sf) = 31.1 hr @ $20.97/hr = 652.17
Small truck-m ounted crane: 31.1 hr @ $48.50/hr = 1,510.35
Crane operator: 31.1 hr @ $21.67/hr = 673.94
Portable w elding machine: 31.1 hr @ $5.75/hr = 178.83
Electrodes: 12 lb @ $0.57 = 6.84
Welder: 31.1 hr @ $20.97/hr = 652.17
Total for decking = $4,644.22
Reinforcing Steel:
W elded-wire fabric: 3,629 sf @ $7.10/100 sf = $257.66
Tie wire: 4 lb @ $0.98/lb = 3.92
Ironworkers: 3,629 sf X 1.0 hr/400 sf = 9.1 hr @ $20.97/hr = 190.83
Small truck-m ounted crane: 9.1 hr @ $48.50/hr = 441.35
Crane operator: 9.1 hr @ $21.97/hr = 199.93
Total for w elded-w ire fabric = $1,093.69
C oncrete slab:
Concrete: ready-mix delivered to job, 29.4 cy @ $75/cy = $2,205.00
Concrete pum p truck and operator: 1 day @ $975/day = 975.00
Laborers: 8 hr x 4 laborers @ $15.56/hr = 497.92
Total for concrete = $3,677.92
Summary of costs:
Joists = $9,744.89
Metal decking = 4,644.20
Reinforcing steel = 1,093.69
Concrete = 3,677.75
Total cost = $19,160.53
Labor-hours
Operation per 1,000 sf
Sorting and arranging sheets 2.5
Laying and fastening decking 5.0
Installing welded-wire fabric 3.0
Installing negative reinforcing bars 8.0
Installing and removing temporary supports 11.0
Estimate the total direct cost and cost per square foot for materials and labor for a
bay 18 ft w ide and 24 ft long using corrugated forms and reinforcement and a con
crete slab.
The corrugated sheets will be 22 gauge with 1.5-in.-deep corrugations, with 6
x 6-10/10 welded-w ire fabric for shrinkage steel. The perm anent supporting mem
bers will be steel beams, spaced at 8 ft on centers, parallel to the 18-ft side of the
bay, as shown in Fig. 16.3.
The concrete will have a maximum depth of 3.5 in. Negative reinforcing,
installed over each perm anent beam, will consist of no. 4 bars, 4 ft long, spaced at
6 in. on centers.
Tem porary intermediate support for the corrugated sheets will consist of one 2
x 8 w ood stringer and adjustable shores, spaced 4 ft 6 in. apart. The stringers will
be installed parallel with the 18-ft sides of the bay.
Quantities of materials:
Floor area: 18 ft x 24 ft = 432 sf
Corrugated sheets:
Square feet of surface area = 432.0 sf
A dd 1% waste, 432 sf x 1 % = 4.3 sf
Total = 436.3 sf
Reinforcing steel:
Negative steel: [18 ft/(0.5 ft/bar) + 1 ] x 2 rows = 74 pieces 4 ft long
W eight of negative rebar: 74 pieces x 4 ft x 0.668 lb/ft= 197.8 lb
Square feet of negative reinforcing: 18 ft x 4 ft x 2 rows = 144 sf
W elded-wire fabric: 432 sf + 5% waste = 454 sf
Concrete:
From Table 16.5, volume of concrete = 0.210 cf/sf x 432 sf = 90.7 cf
Converting to cu b ic yards of concrete: 90.7 cf/(27 cf/cy) = 3.4 cy
A dd 10% waste: 10% X 3.4 cy = 0.3 cy
Total = 3.7 cy
Labor:
Sorting and arranging sheets: 3.2 hr @ $15.56/hr = $49.79
Steel setters installing welded-w ire fabric: 1.4 hr @ $20.67/hr = 28.94
Ironworker placing no. 4 negative rebar: 1.2 hr @ $20.67/hr = 24.80
Laborers placing concrete: 6 laborers 0.4 hr @ $15.56/hr = 37.34
Laborers installing/removing supports: 4.8 hr @ $15.56/hr = 74.69
Crane operator: 11.0 hr @ $21.67/hr = 238.37
Foreman: 11.0 hr @ $28.00/hr = 308.00
Total labor cost = $761.93
Equipment:
Small hydraulic crane: 11.0 hr @ $48.50/hr = $533.50
Concrete pum p truck: 1/2 day @ $950/day = 475.00
Total equipm ent cost = $1,008.50
Summary of costs:
Materials = $864.78
Labor = 761.93
Equipm ent = 1,008.50
Total cost = $2,635.21
CONCRETE-FLOOR FINISHES
MONOLITHIC TOPPING
One of the best and most economical finishes for concrete floors is monolithic
topping. After the concrete for the floor has been screeded to the desired level
and has set sufficiently, it is floated with a wood float or a power-floating
machine until all visible water disappears. Then the surface of the concrete is
dusted with dry cement or a mixture of cement and sand, in approximately equal
quantities. After the concrete or mixture is applied to the floor, it is lightly
floated with a wood float and then finished with a steel trowel.
359
360 Estimating Construction Costs
js in., fine sand may be added to the cement. Table 17.1 gives the quantities of
materials required for finishing 1 0 0 sf of concrete floor by using various pro
portions and thicknesses.
Proportion
Thickness, Cement, '.'Send,
in. Cement Sand sacks cf
1
64 1 0 0.125 0
1
32 1 0 0.25 0
1
16 1 1 0.25 0.25
1
8 1 1 0.50 0.50
Conditions
Classification Favorable Average Unfavorable
Cement finisher 0.75 1.25 1.75
Helper 0.75 1.25 1.75
considered as satisfactory as the first. The surface of the subfloor should be left
rough to ensure a bond with the topping. The topping may vary from \ to 1 in.
thick. Concrete for the topping is usually mixed in the proportions 1 part cement,
1 part fine aggregate, and I 5 to 2 parts coarse aggregate, up to f-in. maximum
Labor-hours*
Thickness, Finishers
in. per crew Finisher Helper Laborer Foreman
1
2 1 1.25 1.25 1.25 0
2 1.25 1.25 1.25 0.63
3 1.25 1.25 0.80 0.42
3
4 1 1.25 1.25 1.25 0
2 1.25 1.25 1,25 0.63
3 1.25 1.25 0.80 0.42
1 1 1.25 1.25 1.25 0
2 1.25 1.25 1.25 0.63
3 1.25 1.25 1.25 0.42
4 1.25 1.25 1.00 0.31
Company, makes two sizes, 46- and 35-in. ring diameter. Each machine is sup
plied with three trowels, one set for floating and one for finishing the surface.
The trowels are easily interchanged. The machines rotate at 75 to 100 rpm.
On an average job the 46-in.-diameter machine should cover 3,000 to 4,000
sf/hr one time over, including time for delays. The 35-in.-diameter machine
should cover 2,400 to 3,000 sf/hr. For most jobs it is necessary to go over the
surface three to four times during the floating and the same during the finishing
operation.
In operating a power machine, a crew of two to three will be required—one
operator and one or two finishers—to hand-finish inaccessible areas.
Table 17.5 gives approximate labor-hours required to finish 100 sf of sur
face area, based on going over the surface four times during each operation.
Estimate the cost of materials and labor required to hand-finish 5,000 sf of floor area
with a 35-in.-thick monolithic topping. Assume that the weather will be clear, with an
average tem perature of 70°F, which is an average condition. The placing of the con
crete will start at 8:00 a.m. and will be com pleted at 4:00 p.m. One cem ent finisher
will report at 8:00 a.m. to direct the screeding of the slab, and the rest of the finish
ers will report at 9:00 a.m. and will remain on the job until the finishing is com pleted.
Assume that the finishing will be com pleted around 7:00 p.m. It will be necessary to
pay overtime wages to the finishers and helpers, at 1 | times the regular wage rates,
for all time in excess of 8 hr.
The number of finishers may be determ ined as
TERRAZZO FLOORS
A terrazzo floor is obtained by applying a mixture of marble chips or granules,
Portland cement, and water laid on an existing concrete or wood floor. White
364 Estimating Construction Costs
cement is frequently used. The thickness of the terrazzo topping usually varies
from 5 to | in. Several methods are used to install the topping on an existing floor.
Operation Labor-hours
Cleaning concrete floor, per 100 sf 0.75-1.25
Placing roofing felt on wood floors, per 100 sf 0.3-0.5
Placing netting on wood floor, per 100 sf 0.5-0.7
Mixing and placing 1^-in.-thick underbed, per 100 sf:
Mechanic 1.0-1.5
Helper 2.5-3.5
Mixing and placing f-in.-thick terrazzo topping and metal strips, per 100 sf:*
Mechanic 2.0-3.0
Helper 2.5-3.0
Finishing terrazzo topping, per 100 sf 7.0-8.0
Mixing and placing 100 lin ft of 6-in. terrazzo cove base:
Mechanic 14.0-18.0
Helper 14.0-18.0
Finishing 100 lin ft of 6-in. terrazzo cove base 8.0-10.0
'These rates are for metal strips placed to form 5-ft 0-in, squares. For other size squares, apply the following
factors: 4 ft 0 in., 1.10; 3 ft 0 in., 1.20; 2 ft 0 in., 1.30.
E X A M P L E 1 7 .2
Estimate the cost of 100 sf of terrazzo floor placed on a concrete slab, with a l]- in .-
concrete underbed, f-in .-th ic k terrazzo topping, and brass strips to form 4-ft 0-in.
squares. Use white cem ent for the topping.
VINYL TILE
Vinyl tiles are available in sizes 6 by 6 in., 9 by 9 in., and 12 by 12 in., and in
thicknesses of ^ and | in. The cost of tile will vary with the thickness, color, and
quality.
When the quantity of tile required for a given floor area is estimated, an
allowance should be included for waste due to cutting at the edges of the floor
and to irregularities in the locations of the walls around the floor. Wastage may
amount to 2 to 15 percent of the net area of a floor.
EXAMPLE 1 7 . 3
Estimate the cost of materials and labor required to lay 100 sf of vinyl tile § in. thick,
using 1 2 - x 1 2 -in. squares, on a concrete floor.
The cost will be:
PROBLEMS
17.1 A concrete slab for the second-story floor of a building will be 58 ft 6 in. wide,
136 ft 0 in. long, and 6 in. thick. The concrete will be delivered at a rate of 15
cy/hr, starting at 7:00 a .m ., and continued until all concrete has been placed.
The slab will be finished with a monolithic topping ^ in. thick, using hand
finishers.
The finishers will report at 9:00 a .m . and will remain until the job is
finished, estimated to be 3 hr after the last concrete is placed. Overtime wages
must be paid at l j times the regular wage rates for all time in excess of 8 hr. The
cost of a foreman will be charged to finishing for only the time after the last
concrete is placed in the slab.
Assume average working conditions.
Estimate the total cost and the cost per square foot for the materials and the
labor for the topping. Assume that the unit costs for materials and labor will be
the same as those used in Example 17.1.
17.2 Estimate the cost of finishing the floor in Prob. 17.1 using one or more, as
needed, 35-in.-diameter gasoline-engine-powered floor trowels. Use the costs
from Prob. 17.1 in preparing your estimate.
17.3 Estimate the total direct cost and the cost per square foot for furnishing the
materials and labor required for a 4,480 sf terrazzo floor placed on a concrete
slab, with a 1j-in.-thick underbed, f-in.-thick terrazzo topping, and brass strips
to form 4-ft 0-in. squares. Use gray cement and marble chips for the topping.
The floor consists of large rooms and corridors at approximately
ground level.
Use the unit costs for materials and labor from Example 17.2.
17.4 Estimate the total direct cost and the cost per square foot for furnishing and
laying ^-in.-thick vinyl tile, size 12- by 12-in. squares, on a concrete floor whose
area is 2,360 sf.
Use the unit costs for materials and labor from Example 17.3.
Glass and Glazing
It is common practice to furnish wood sash with the glass already installed by
the manufacturer. Steel and aluminum sash may be furnished with the glass
installed for use in residences, but when such sash are furnished for industrial
and commercial buildings, it is common practice to install the glass after the
sash are set in the walls, usually just before completing a building, to reduce the
danger of breakage.
The installation of glass is called glazing, and the individuals who install it
are glaziers.
An estimate covering the cost of furnishing and installing glass should
include a detailed list of the quantity for each size, kind, and grade of glass
required and for each the cost of the glass, putty, and glaziers.
GLASS
There are many kinds and grades of glass, not all of which will be covered in
this book. Glass used for glazing purposes is called window glass, and it can be
divided into sheet glass and plate glass.
Sheet glass. The thicknesses of ordinary window glass are single
strength and double-strength.
Plate glass. Plate glass used for glazing purposes is available in two
grades: second silvering and glazing quality.
Figured sheet glass. Many kinds of figured sheet glass are available,
with various patterns or figures rolled or otherwise produced on them.
The thicknesses and weights of clear sheet glass are given in Table 18.1.
Window glass is designated by size and grade, such as 20- by 36-in. B
double-strength. The first number represents the width and the second number
the height of the sheet.
Glass is sold by the square foot in sheets whose dimensions vary in steps
of 2 in. Fractional dimensions are figured for the next standard dimensions.
C hapter 18 Glass and Glazing 369
Thus a sheet whose actual size is 17§ by 14§ in. is classified for cost purposes
as 18 by 16 in.
Costs and certain operations related to glass are frequently based on the united
inches of a sheet of glass, which is the sum of the width and height of a sheet.
than when glazing is done during warm weather. If glazing is done from the out
side of a building, it will require about 2 0 percent more time than when it is done
from inside a building.
E X A M P L E 1 8 .1
Estimate the direct cost of double-strength glass, glazing com pound, and labor
required to glaze 240 lights in aluminum sash. The actual sizes of the lights will be
15§ by 31 § in. This will require lights whose standard sizes are 16 by 32 in. which
will require two cuttings per light.
The costs will be
PROBLEMS
18.1 Estimate the direct cost for furnishing and installing double-strength glass in 160
aluminum sash. Each sash will require two sheets of glass size 15 j by 31§ in.
Use glazing compound to set the glass. The installation will be done from out
side the building in good weather.
18.2 Estimate the cost of furnishing and installing the glass of Prob. 18.1 when the
glazing is done from the inside of the building during cold weather.
18.3 Estimate the cost of furnishing and installing 56 plate-glass lights 36 by 42 in. in
wood frames using wood stops. The glass, which is | in. thick, will cost $4.75/sf.
18.4 Estimate the total cost of furnishing and installing 280 single-strength l l | - by
231-in. lights in aluminum sash, using glazing compound. The glazing will be
done from inside the building during the summer. Use the material prices given
in this book.
18.5 Estimate the total direct cost for furnishing and installing double-strength glass
in 96 aluminum sash. Each sash will require two sheets of glass 151 by 231 in.
Use glazing compound to set the glass. The installation will be done from out
side the building during the summer.
18.6 Estimate the cost of furnishing and installing 76 plate-glass lights in 30- by 36-
in. aluminum sash. The glass, which is \ in. thick, will cost $4.35/sf.
18.7 Estimate the cost of furnishing and installing 196 double-strength 1 5 |- by 171-
in. lights in steel sash, using glazing compound. The glazing will be done from
outside the building during the summer.
Painting
Painting is the covering of surfaces of wood, plaster, masonry, metal, and other
materials with a compound for protection or for the improvement of the appear
ance of the surface painted. Many kinds of paint are used, some of which will be
described briefly.
Since various practices are used in determining the area of the surfaces to be
painted, it is desirable to state what methods are used. Some estimators make no
deductions for the areas of openings except those that are quite large, whereas
other estimators deduct all areas that are not painted. The latter method seems to
be more accurate. Practices vary in estimating the areas for trim, windows,
doors, metal specialties, masonry, etc.
Paints may be acrylic latex or enamel. Acrylic latex paint is considered a
waterbase and is often preferred because the paintbrushes and rollers can be
cleaned with water. Enamel paint is an oil base and the paintbrushes and rollers
must be cleaned with a petroleum product, such as turpentine. Enamel paint is
considered more durable than acrylic latex.
Paints can be applied in one, two, three, or more coats, with sufficient time
allowed between successive coats to permit the prior coat to dry thoroughly.
Paint can be applied with a brush, roller, or spray gun. The first coat, which is
usually called the prime coat, should fill the pores of the surface, if such exist,
and bond securely to the surface to serve as a base for the other coats.
The cost of painting includes materials, labor, and sometimes equipment,
especially when the paint is applied with a spray gun. Because the cost of the
paint is relatively small compared with the other costs, it is not good economy
to purchase cheap paint.
MATERIALS
It is beyond the scope of this book to discuss all the materials used for paints,
but those most commonly used will be discussed briefly.
Chapter 19 Painting 373
Table 19.1 gives representative values for the covering capacities of various
paints, varnishes, and stains when applied to different surfaces.
374 Estimating Construction Costs
COST OF PAINTING
Example 19.1 illustrates a method of determining the cost of furnishing materi
als and labor in painting a surface.
376 Estimating Construction Costs
Hours
Operation Unit per unit
Exterior work
Oil paint on wall siding and trim 100 sf 0.60-1.00
Oil paint on wood-shingle siding 100 sf 0.65-0.90
Stain on wood-shingle roofs 100 sf 0.60-0.75
Oil paint on wood floors 100 sf 0.30-0.40
Painting doors, windows, and blinds Each 0.50-0.75
Oil paint on stucco 100 sf 0.60-1.00
Oil paint on steel roofing and siding 100 sf 0.50-0.60
Oil paint on brick walls 100 sf 0.60-0.90
Interior work
Size or seal plaster and wallboard 100 sf 0.40-0.50
Calcimine on plaster and wallboard 100 sf 0.30-0.40
Casein paint on plaster and wallboard 100 sf 0.20-0.30
Trim, mold, base, chair rail
Sanding 100 lin ft 0.80-1.00
Varnishing 100 lin ft 0.50-0.75
Enameling 100 lin ft 0.50-0.75
Flat painting 100 lin ft 0.50-0.75
Staining 100 lin ft 0.40-0.60
Painting doors and windows Each 0.50-0.75
Floors
Sanding with power sander 100 sf 0.75-1.00
Filling and wiping 100 sf 0.50-0.60
Shellacking 100 sf 0.25-0.30
Varnishing 100 sf 0.40-0.50
Waxing 100 sf 0.40-0.50
Polishing with power polisher 100 sf 0.30-0.40
Structural steel
Brush painting
Beams and girders, 150 to 250 sf/T T 0.80-1.00
Columns, 200 to 250 sf/T T 0.90-1.00
Roof trusses, 275 to 350 sf/T T 1.25-1.75
Bridge trusses, 200 to 250 sf/T T 1.00-1.25
Spray painting
Beams and girders T 0.20-0.25
Columns T 0.20-0.25
Roof trusses T 0.25-0.35
Bridge trusses T 0.20-0.30
Chapter 19 Painting 377
EXAMPLE 1 9 .1
Estimate the cost of furnishing and applying paint for a three-coat application on
100 sf of exterior new wood wall for a residence, using ordinary workmanship. The
top of the wall will be 12 ft above the ground. The tem perature of the air will be about
70°F. Ready-mixed oil paint will be used.
The cost of the three coats will be:
Priming coat:
Paint: 100 sf/500 sf/gal = 0.2 gal @ $24.50 $4.90
Painter: 100 sf @ 0.9 hr/100 sf x $19.01 = 17.11
Second coat:
Paint: 100 sf/500 sf/gal = 0.2 gal @ $18.75 = 3.75
Painter: 100 sf @ 0.8 hr/100 sf x $19,01 = 15.21
Third coat:
Paint: 100 sf/550 sf/gal = 0.18 gal @ $18.75 = 3.38
Painter: 100 sf @ 0.8 hr/100 sf x $19,01 = 15.21
Painter mixing and stirring paint: 0.2 hr @ $19.01 = 3.80
Ladders, brushes, etc., 2.5 hr @ $1.50 = 3.75
Total cost = $67.11
Cost per sf, $67.11 - 100 sf $0.67/sf
PROBLEMS
For these problems use the national average wage rates given in this book.
19.1 Estimate the total cost of furnishing and applying a prime coat and two finish
coats of oil-base paint using brushes, on 3,380 sf of exterior wood surface, for a
one-story house. The cost of paint will be:
Prime coat: $18.75 per gal
Finish paint: $22.50 per gal
19.2 Estimate the total direct cost of furnishing and applying one sealing coat and two
coats of flat wall paint on 3,680 sf of smooth plaster walls and ceilings. The cost
of materials will be:
Sealer: $14.30 per gal
Paint: $24.50 per gal
19.3 Estimate the total direct cost of sanding, filling, wiping, applying four coats of
varnish, waxing, and polishing 3,640 sf of oak flooring, using first-grade work
manship.
Power sander: $4.20 per hr
Polisher: $1.20 per hr
Filler: $20.50 per hr
Varnish: $28.75 per gal
Wax: $14.50 per gal
Plumbing
Although general contractors usually subcontract the furnishing of materials and
the installation of plumbing in a building, they should have a reasonably good
knowledge of the costs of plumbing. The fact that general contractors do not pre
pare detailed estimates for plumbing does not eliminate the need for estimating;
it simply transfers the preparation to another party.
Plumbing involves the furnishing of materials, equipment, and labor to
bring gas and water to a building; the furnishing and installation of fixtures; and
the removal of the water and waste from the building. Water usually is obtained
from a water main, and the waste is discharged into a sanitary sewer line.
Materials include various types of pipe, fittings, valves, and fixtures, which will
be more fully described later. Consumable supplies, such as lead, oakum, gaso
line, etc., must be included in an estimate.
PLUMBING REQUIREMENTS
Some plans and specifications clearly define the types, grades, sizes, and quan
tities and furnish other information required for a complete plumbing installa
tion, while other plans and specifications furnish limited information and place
on the plumbing contractor the responsibility for determining what is needed to
satisfy the owner and the local plumbing ordinance.
All cities have ordinances that require that plumbing installations conform
with the plumbing code for the city in which the project will be constructed. A
contractor must obtain a plumbing permit prior to starting an installation, and
the work is checked by a plumbing inspector for compliance with the code.
Although plumbing codes in different localities are similar, there will be varia
tions that make it necessary for a plumbing contractor to be fully cognizant of
the requirements of the code that will apply to a given project.
378
Chapter 20 Plumbing 379
PLUMBING CODE
Some of but not all the requirements of the plumbing code for a major city are
given here. The information is intended to serve as a guide in demonstrating the
requirements of city codes for plumbing. When preparing an estimate of the cost
of furnishing and installing items for plumbing services, the estimator should
use the appropriate code for the area in which the project will be constructed.
Permit fee A fee, which is generally paid by the plumbing contractors
and included in their estimate, is charged by a city for issuing a plumbing
permit. This fee may vary with the type and size of the project and with
the location.
Plumbing-fixture facilities Table 20.1 lists the minimum requirements
for plumbing-fixture facilities for a representative city. The requirements
may differ in other cities.
T A B L E 20.1 I Minimum requirement for plumbing-fixture facilities (one fixture for each designated group).
Minimum-size trap and outlet Table 20.2 gives the minimum-size trap and
outlet permitted for the indicated fixture.
Fixture-unit values Table 20.2 gives the value of each fixture unit for
determining the relative load factors of different kinds of plumbing fixtures
and estimating the total load carried by soil and waste pipe.
Estimating Construction Costs
STEEL PIPE
Black and galvanized steel pipes are available in standard, extra-strong, and
double-extra-strong weights, with standard weights most commonly used for
Chapter 20 Plumbing 381
2?
_ 2 24 31
3 -- 20* 27+ 36t
4 -- 180 216 250
5 -- 390 480 575
6 -- 700 840 1,000
8 1,400 1,600 1,920 2,300
10 2,500 2,900 3,500 4,200
12 3,900 4,800 5,600 6,700
plumbing purposes. Table 20.4 gives the dimensions and weights of standard
steel pipe.
and number of threads per inch are the same as for steel pipe. Table20.5 gives
the dimensions of brass and copper pipe.
COPPER TUBING
Copper tubing is frequently used instead of steel pipes for water. It is furnished
in both hard and soft tempers. Both tempers are available in straight 20-ft
lengths, and the soft temper is furnished in 30-, 45-, and 60-ft coils in sizes to 11-
in. diameter. The tubes are joined by sweating the ends into special fittings,
using a solder or brazing alloy, which is heated with a blowtorch. Because of the
flexibility, the tubing can be bent easily to change directions, thus reducing the
number of fittings and the amount of labor required. This tubing is frequently
used instead of lead pipe for connections from water mains into buildings.
Table 20.6 gives the dimensions and weights of soft- and hard-temper cop
per tubing.
T y p e K soft T y p e M hard
N o m in a l O u ts id e W all W all
size , d ia m e te r, th ic k n e s s , W eig h t, th ick n e s s , W eigh t,
in. in. in. Ib/lin ft in. Ib/lin ft
1 3 0 .0 3 2 0 .1 3 3 0 .0 2 5 0 .1 0 6
4 8
3 1 0 .0 4 9 0 .2 6 9 0 .0 2 5 0 .1 4 4
8 2
1 5 0 .0 4 9 0 .3 4 4 0 .0 2 8 0 .2 0 3
2 8
5 3 0 .0 4 9 0 .4 1 8
8 4
3 7 0 .0 6 5 0 .6 4 1 0 .0 3 2 0 .3 2 8
4 8
0 .0 6 5 0 .8 3 9 0 .0 3 5 0 .4 6 4
1 1b
0 .0 6 5 1 .0 4 0 .0 4 2 0 .6 8 1
1? 1§
0 .0 7 2 1 .3 6 0 .0 4 9 0 .9 4 0
1s 18
2 pi 0.0 8 3 2 .0 6 0 .0 5 8 1 .4 6
‘-8
Ol p5 0.0 9 5 2 .9 2 0 .0 6 5 2 .0 3
^8
Ql 0.1 0 9 4 .0 0 0 .0 7 2 2 .6 8
3 J8
q! 0 .1 2 0 5 .1 2 0 .0 8 3 3 .5 8
°2 3§
4 0 .1 3 4 6 .5 1 0 .0 9 5 4 .6 6
0.1 6 0 9 .6 7 0 .1 0 9 6 .6 6
5 5i
6 0.1 9 2 1 3 .8 7 0 .1 2 2 8 .9 1
0.271 2 5 .9 0 0 .1 7 0 1 6 .4 6
8
0 .3 8 8 4 0 .2 6 0 .2 1 2 2 5 .5 7
10 10g
12 0 .4 0 5 5 7 .7 6 0 .2 5 4 3 6 .6 9
12i
and highly resistant to corrosion, has low resistance to the flow of water, and can
be installed rapidly and economically.
Joints between the pipe and fittings are made by applying a coating of sol
vent cement around the end of the pipe and then inserting it into the fitting.
This pipe is not suitable for use with hot water.
Table 20.7 lists representative sizes of PVC pipe and costs. Table 20.8 lists
representative PVC fittings for use with the pipe, with current costs.
T A B L E 2 0 .7 1
Representative costs
of PVC plastic water T A B L E 2 0 .8 I Representative costs of fittings for PVC plastic
water pipe.
Pipe Cost
P ric e e a c h b y size , in.
size, per
i 3 1
in. lin ft F ittin g 2 4 11 1i
1 SO 18 SO 19 $ 0 24 $0 46 $ 0 .6 5
$ 0 .1 5 9 0 ° e lb o w
3 0 .2 3 0 .3 7 0 .4 4 0 .6 3 0 .8 8
0 .1 6 4 5 ° e lb o w
0 .1 8 0 .2 4 0 .4 2 0 .5 8 0 .7 4
1 0 .1 7 Tee
0 .1 9 C o u p lin g 0 .1 0 0 .1 2 0 .2 2 0 .2 6 0 .4 3
1?
0 .2 3 M a le a d a p t e r 0 .1 3 0 .1 5 0 .2 5 0 .3 0 0 .4 3
1z
0 .2 7 F e m a le a d a p t e r 0 .1 5 0 .2 0 0 .2 4 0 .3 6 0 .4 1
2
384 Estimating Construction Costs
*This is the time required for making a joint. A coupling and an elbow require two joints, and a tee requires three
joints.
Extra heavy
Standard,
Size, single Single Double
in. hub hub hub
2 3.6 5,0 5.2
3 5.2 9.0 9.4
4 7.0 12.0 12.6
5 9.0 15.0 15.6
6 11.0 19.0 20.0
8 17.0 30.0 31.4
10 23.0 43.0 45.0
12 33.0 54.0 57.0
in one operation. After the lead solidifies, the runner is removed, and the lead is
heavily caulked.
Table 20.11 gives the approximate quantity of lead and oakum required for
a joint in cast-iron soil pipe.
T A B L E 2 0 .1 1 I Approximate
quantities of lead and oakum required
for cast-iron soil pipe.
FITTINGS
Fittings for black and galvanized-steel pipe should be malleable iron. Fittings for
copper and brass pipe and tubing should be copper and brass, respectively,
386 Estimating Construction Costs
threaded or sweat type. Fittings for plastic pipe should be of the same material as
the pipe. If different types of plastic are used, the solvent cement will not be
effective on both types of materials. Fittings for cast-iron pipe should be cast iron.
Adapters are available that can be used in joining one type of pipe or fitting
to another type.
VALVES
Valves are installed to shut off the flow of water. Several types arc used, includ
ing globe, gate, check, sill cocks, drain, etc. They are usually made from bronze
and brass.
TRAPS
Traps are installed below the outlets from fixtures to retain water as a seal to pre
vent sewer gases from entering a building. Vent pipes installed into the drain
pipes below the traps prevent the water in the traps from being siphoned out.
ROUGHING IN PLUMBING
Roughing in includes the installation of all water pipes from the meter into and
through a building, soil pipe, waste pipe, drains, vents, traps, plugs, cleanouts,
etc., but does not include the installation of plumbing fixtures, which is called
finish plumbing.
a guide in preparing an approximate estimate. The actual costs that will apply
should be determined and used in preparing an estimate for bid purposes.
Size, Unit
Number Item in. Unit cost
1 PVC pipe ii Lin ft $0.29
PVC pipe 2 Lin ft 0.37
2 PVC pipe 3 Lin ft 0.89
3 Roof flashing, neoprene H Each 3.75
2 Each 3.90
3 Each 3.90
4 Coupling 13 Each 0.17
2 Each 0.21
3 Each 0.55
5 Sanitary tee 1J Each 0.42
2 Each 0.65
3 Each 1.54
6 90° elbow 1j Each 0.27
2 Each 0.37
7 90° elbow 3 Each 1.16
8 Sanitary tee with two 1g-in. side outlets 3 Each 1.98
9 Slip plug 1J Each 0.35
10 Reducing closet flange 4X3 Each 3.00
11 45° elbow 1? Each 0.24
2 Each 0.34
3 Each 0.98
12 P trap with union ii Each 0.90
2 Each 1.75
13 Trap adapter, 1J-in. pipe to 1g-in. waste 1? Each 0.48
14 Trap adapter, 1J-in. pipe to l|- in . waste 1J Each 0.45
15 Wye branch ii Each 0.72
2 Each 0.92
3 Each 1.65
16 Cleanout adapter 1* Each 0.35
2 Each 0.59
3 Each 1.10
17 Threaded cleanout plug 1J Each 0.25
2 Each 0.27
3 Each 0.47
18 Combination Y and § bend 3 Each 2.82
19 Male iron pipe adapter 11 Each 0.26
2 Each 0.45
20 Adapter, plastic to iron hub 1J X 2 Each 0.90
2X2 Each 0.90
Adapter, plastic to plastic hub 3X4 Each 1.85
Cast-iron soil, waste, and vent pipes are joined with molten lead and oakum
joints. Many of these joints can be made with the pipe or fittings standing in an
upright position, which will reduce the time required. Line joints are made by
pouring the lead with the pipe in place, using a runner to hold the lead in the
joint. After the lead has solidified, it must be caulked. Time should be estimated
by the number of joints.
Vitrified-clay sewer pipe is manufactured in lengths varying from 2 \ to
4 ft. Joints are made with oakum and cement mortar or a heated asphaltic joint
compound.
Many plumbing contractors add a percentage of the cost of materials to
cover the cost of labor required to rough in plumbing. The rates used vary from
40 to 80 percent of the cost of materials. Although this is a simple operation, it
does not necessarily produce an accurate estimate.
Tables 20.14 through 20.22 provide representative costs of the various types
of pipes and fittings that are commonly used to rough in plumbing.
T A B L E 2 0 .1 4 I Representative cost of
standard-weight steel pipe.
Size, in.
3
Fitting 1
2 4 1 ij 1? 2
Black
Couplings $1.30 $1.45 $2.20 $2.75 $3.45 $4.95
Elbows 0.80 1.00 1.85 3.05 4.00 5.90
Reducers 1.35 1.45 2.20 3.15 3.65 4.95
Tees 1.10 1.60 2.90 4.75 5.85 13.50
Unions 3.60 3.70 5.40 7.50 9.10 11.50
Galvanized
Couplings $1.30 $1.50 $2.40 $3.10 $3.50 $5.30
Elbows 0.85 0.75 2.10 3.20 4.25 6.13
Reducers 1.25 1.50 2.40 3.10 3.70 5.35
Tees 1.10 1.85 3.10 4.90 6.00 8.75
Unions 3.80 3.90 5.75 7.85 7.55 11.90
Chapter 20 Plumbing 391
Valves I 3
4 1
1 2
Globe and angle $30.00 S40.00 $65 00 $100 00 $125.00 $185.00
Gale and check 22.00 30.00 45.00 60.00 70.00 105.00
Ball 6.50 11.00 13.00 23.00 29.00 36.00
TABLE 2 0 . 2 0 I Cost of single-hub fittings for cast-iron soil pipe, per fitting.
Size, in.
Fitting 2 3 4 6 8
Quarter-bend, standard $6.25 $1160 $17 20 $29.75 $91.30
Extra heavy 7.10 14.65 21.90 36.60 90.30
Eight-bend, standard 4.90 11.60 17.20 24.70 65.85
Extra heavy 6.15 11.90 17.25 27.95 71.95
T and Y branch, standard 15.25 22.83 31.65 73.10 178.43
Extra heavy 19.10 31.85 41.50 80.25 180.45
Cross, standard 14.75 26.10 34.85 75.50 161.35
Extra heavy 24.10 35.45 41.90 81.75 193.20
Running trap, with hub vent 49,75 69.25 97.35 291.75
Extra heavy
Plain trap, S and P, standard 20.59 32.31 66.25 150.69
392 Estimating Construction Costs
ASTM
Pipe size, ASTM C-425-71,
in.. C-700-71 rubber seal
4 $1.80 $1.70
6 2.90 2.35
8 4.50 4.15
10 6.80 6.65
12 9.20 9.10
15 16.50 14.95
18 24.50 24.05
Pipe
1 1 1
size, Wyes and 8 > 4 i 2 Cleanout
in. te e s bends wyes Stoppers
4 $6.75 $6.45 $1.75
6 15.45 11.10 17.75 2.35
8 19.80 17.70 26.35 3.40
10 29.42 44.23 4.50
12 47.50 44.10 6.25
FINISH PLUMBING
Finish plumbing includes fixtures such as lavatories, bathtubs, shower stalls,
water closets, sinks, urinals, water heaters, etc., and the accessories that usually
are supplied with the fixtures. The prices of finish plumbing vary a great deal
with the type, size, and quality specified. No book of this kind can give a com
plete listing of fixtures and prices. An estimator should list each item required
for a building and then refer to a current catalog for prices.
Table 20.24 gives representative prices for plumbing fixtures in the medium
grade range; these should be used as a guide only.
Chapter 2 0 Plumbing 393
PROBLEMS
For these problems use the national average wage rates and the costs of materials given
in this book. Use a plumber and a helper as a team to perform the work.
C hapter 20 Plumbing 395
Fixtures Labor-hours
Bathtub, leg type 10-16
Bathtub, flat bottom, no shower 14-20
Bathtub, flat bottom, with shower 18-26
Kitchen sink, enamel, single 6-10
Kitchen sink, enamel, double 8-12
Laundry tub, double 10-14
Lavatory, wall type 5-8
Lavatory, pedestal type 6-9
Urinal, wall type 8-12
Urinal, pedestal type 9-13
Urinal with stall 16-20
Water closet 6-9
Garbage disposal unit 6-8
Drinking fountain 5-8
20.1 Estimate the direct cost of furnishing and installing 286 lin ft of 1-in. galvanized
steel pipe, whose average length per joint prior to cutting will be 20 ft 0 in. It
will be necessary to cut and thread the pipe for installing eight galvanized tees,
six galvanized elbows, four galvanized unions, and three brass gate valves. The
pipe will be cut and threaded by hand.
20.2 Estimate the direct cost of furnishing and installing the pipe, fittings, and valves
of Prob. 20.1 when the pipe is cut and threaded by machines.
20.3 Estimate the cost of furnishing and installing 468 lin ft of f-in. type-K soft-
copper tube, including 14 couplings, 26 tees, 16 elbows, and 4 unions, using
sweated joints.
20.4 Estimate the cost of furnishing and installing 426 lin ft of 1^-in. type-L copper
pipe, including 16 couplings, 12 tees, and 6 ells, using sweated joints.
20.5 Estimate the cost of furnishing and installing 256 lin ft of 4-in. single-hub stan
dard cast-iron pipe, including six wyes, eight standard quarter bends, and three
P traps, all standard fittings, under average conditions. All joints will be made
with oakum and lead.
20.6 Estimate the cost of furnishing and installing 280 lin ft of 1j-in.-diameter ABS
drain pipe supplied in 20-ft lengths. The following fittings will be required, with
each requiring that the pipe be cut: six sanitary tees and five 90° elbows. The
cost of a 1-pt can of solvent cement will be $4.20. This is enough cement to
make 50 joints with lj-in . pipe.
Electric Wiring
Electric w iring is generally installed by a subcontractor w ho specializes in this
type o f work, w ith all m aterials and labor furnished under the contract. This pro
cedure does not elim inate the need for estim ating a job; it sim ply transfers the
operation from the general to the electrical contractor.
A pproxim ate estim ates, and som etim es estim ates for bid purposes, are pre
pared by counting the num ber o f outlets required for a jo b and then applying a
unit price to each outlet to arrive at the total cost. W hile this m ethod w ill perm it
estim ates to be prepared quickly, it will not always give an accurate cost for a
jo b , because conditions m ay vary a great deal betw een tw o jobs. W hen this
m ethod is used, each sw itch, plug, and fixture served w ill count as an outlet.
ity, and cost. When you are working from plans, it is good practice to indicate
on the plans, using a colored pencil, each item as it is transferred to the material
list. This procedure will reduce the danger of omitting items or counting them
more than once. The application of appropriate costs for materials and labor to
these items will give a dependable estimate.
TYPES OF WIRING
The types of wiring used in buildings may be governed by the National
Electrical Code (N EC), published by the National Board of Fire Underwriters,
or in some locations by state or municipal codes, which specify minimum
requirements for materials and workmanship. Codes require that electrical
wiring be protected against physical damage and possible short circuits by one
or more methods such as installing them in conduit or by the use of wires that
are furnished with factory-wrapper coverings.
39 8 Estim ating C onstruction Costs
RIGID CONDUIT
Rigid conduit is made of light galvanized pipe. Heavy conduit, which can be
used for outside or inside installations, is threaded at each end. Since the walls
of light conduit are too thin for threads, it is necessary to use special clamping
fittings for making joints or entering boxes. The conduit extends into outlet or
other boxes, where it is securely fastened with locknuts and bushings or with
clamps. The conduit must be adequately supported and fastened in position
along its run. The electric wires are pulled through the conduit at any desirable
time after the conduit is installed.
Table 21.1 gives the sizes of conduit required for the indicated sizes and
numbers of wires, as specified by the NEC.
ARMORED CABLE
Armored cables or conductors are made with or without a lead sheath under the
armor. Special fittings are required to connect this cable into boxes, outlets, etc.
Chapter 21 Electric Wiring 399
NONMETALLIC CABLE
The wires of this cable are covered with a flexible insulated braiding impreg
nated with a moisture-resisting compound. It is furnished in wire sizes 14 to 4
gauge. It is very popular for use in residences.
ELECTRIC WIRE
Electric wires are usually made of copper, either solid or standard. The wires may
be plastic-covered for use indoors or weatherproof for use outdoors. The size of
a wire is designated by specifying the Brown and Sharpe (B & S) gauge number,
or for sizes larger than B & S gauge no. 0000, by the number of circular mils.
Table 21.2 gives the resistance in ohms per 1,000 feet and the electric cur
rent capacity in amperes, as specified by the NEC, for copper wire.
Capacity, A
B& S /..’'-Resistance,;.-'. Plastic- Weather-
.’’.'gauge:'' ohms/1,000 ft covered proof
18 6.374 3 5
16 4.009 6 10
14 2.527 15 20
12 1.586 20 25
10 0.997 25 30
8 0.627 35 50
6 0.394 50 70
5 0.313 55 80
4 0.248 70 90
3 0.197 80 100
2 0.156 90 125
1 0.124 100 150
0 0.098 125 200
00 0.078 150 225
000 0.062 175 275
0000 0.049 225 325
ACCESSORIES
In addition to the conduit and wire, numerous accessories will be needed to
install wiring. Among the items needed will be:
1. M eter box
2. Entrance cap and conduit
3. Entrance box with switch and fuses or circuit breaker
4. Couplings, elbows, locknuts, bushings, and straps for conduit
400 Estimating Construction Costs
COST OF MATERIALS
The cost of materials for electric wiring will vary with the location, quality,
quantities purchased, and time. Representative costs are given in Tables 21.3 to
21.8. The costs given in the tables should be used as a guide only. W hen esti
mating the cost of a project for contract purposes, the estimator should obtain
current prices applicable to the particular project.
If the estimate is started with the service wires that enter a building, the
estimate should include any work required to bring the wires to the building.
Frequently the utility company will bring the service wires to a building, and the
contractor will install an entrance cap, a conduit, and wires to the meter box,
then install conduit and wires from the meter to a service fuse panel, with the
main switch located within the building. From this panel, as many separate cir
cuits as are necessary are installed throughout the building. Frequently a single
conduit may be used for several circuits for at least a portion of the building,
with individual circuits coming out of junction boxes installed in the main con
duit line.
Wires must be installed from a circuit to each outlet, switch, and plug.
Heavy rigid conduit is installed with threaded couplings, elbows, and lock-
nuts and bushings where it enters boxes. It should be supported with pipe straps
or in some other approved manner, depending on the type of construction used
for the building. This conduit is furnished in 10-ft lengths.
Lightweight rigid conduit is installed with special couplings and connectors.
Flexible conduit, armored, and nonmetallic cable can be bent easily as it is
installed. Usually only end connectors are required where it enters boxes. It can
be installed more rapidly than rigid conduit.
W here conduit, boxes, and accessories are installed in a building under con
struction, especially a concrete building, it may be necessary to keep one or
more electricians on the job most of the time, even though they are unable to
work continuously. This possibility should be considered by an estimator.
W hen 100 ft of straight rigid conduit is installed, the operations will include
connecting 10 joints into couplings, plus the installation of any outlet boxes
required. The installation of an outlet box requires the setting of a locknut and a
bushing for each conduit connected to the box. M ore time will be required for
large than for small conduit. Table 21.9 gives the labor-hours required for
installing conduit.
The installation of a switch, fixture outlet, or plug requires a two-wire cir
cuit from the main circuit to the outlet. The time required will vary with the
length of the run and the type of building. For a frame building, it may be nec
essary to drill one or more holes through lumber, whereas for a masonry build
ing it may be necessary to install the conduit through cells in concrete blocks,
then chip through the wall of a block to install the outlet box.
The wires usually are pulled through the conduit just before the building is
completed.
TABLE 2 1.9 I Labor-hours required to install electric wiring per 100 lin ft.
*T h e u n it in th is c a s e is " e a c h . ”
tT h e n u m b e rs 8 /2 d e s ig n a te tw o w ire s , e a c h n o. 8 g a u g e in a c a b le .
are installed. The costs of fixtures vary so much that a list of prices in this book
would be of little value to an estimator. The costs should be obtained from a cur
rent catalog or jobber.
PROBLEMS
For these problems use the representative wage rates and the costs of materials listed in
this book. Use an electrician and a helper to do the work.
21.1 Estimate the cost of furnishingand installing 420 lin ft of lj-in. heavy-duty con
duit, including 36 couplings, 12 elbows, and 18 Condulets under average condi
tions.
21.2 Estimate the cost of furnishing and installing 680 lin ft of 1-in. heavy rigid conduit,
including 38 couplings, 20 elbows, and 14 Condulets, when the installation is
made in a concrete building under construction. The conditions are such that the
electrician and the helper can work at only about 75 percent of normal efficiency.
21.3 Estimate the cost of furnishing and installing the following items in a frame
residence:
1 service fuse panel with switch for six branches
180 lin ft of f-in. light conduit
130 lin ft of ^-in. light conduit
23 junction boxes
28 switch boxes
12 single-pole toggle switches
16 flush receptacles
8§-in. elbows
1 2 f-in. couplings
2 4 1 -in. connectors
18 ^-in. couplings
1 2 j-in. elbows
18 j -in. couplings
48 \ -in. connectors
28 wall plates
320 lin ft of no. 10 gauge plastic-covered copper wire, two wires per circuit
280 lin ft of no. 1 2 plastic-covered copper wire, two wires per circuit
Chapter 21 Electric Wiring 405
21.4 Estimate the cost of furnishing and installing the wiring for a residence, includ
ing the following items:
20 lin ft of 1 ^-in. heavy rigid conduit
4 l|- in . elbows
2 1 ^ -in. couplings
4 1 5 -in. locknuts and bushings
1 main breaker load center, 150 amps
980 lin ft of no. 12 gauge two-wire nonmetallic cable with ground wire
320 lin ft of no. 14 gauge two-wire nonmetallic cable with ground wire
26 junction boxes, 4 in.
36 switch boxes
36 wall plates
20 flush receptacles, wall plugs
16 single-pole switches
Sewerage Systems
ITEMS INCLUDED IN SEWERAGE SYSTEMS
Sewerage systems include one or more types of pipes and other appurtenances
necessary to permit the system to collect waste water and sewage and transmit
them to a suitable location where they can be disposed of in a satisfactory manner.
A sewerage system can be classified as one of two or more types depending
on its primary function:
1. Sanitary sewer
2. Storm sewer
3. Other
This chapter is devoted to the construction of sanitary sewerage systems.
Among the items included in this system are the following:
1. Sewer pipe and fittings
2. Manholes
3. Service connections
4. Cleanout services
SEWER PIPES
Sewer pipes can be made of one of the following materials:
1. Vitrified clay
2. Ductile iron
3. PVC (polyvinyl chloride)
The properties and other qualities of these pipes may be designated by such
agencies as the American Society for Testing Materials (A STM ), the American
W ater Works Association (AW W A), or another appropriate agency.
406
Chapter 2 2 Sewerage Systems 407
CONSTRUCTION OPERATIONS
When a sewerage system is constructed, the operations will include, but may not
be limited to, these:
1. Clearing the right-of-way, if necessary
2. Excavating the trench for the pipe
3. Laying the pipe
4. Excavating the hole for the manhole
5. Placing the manhole in the hole
6. Installing service lines
7. Installing cleanout boots, if required
8. Backfilling with earth over the pipe and manhole
9. Removing surplus earth, if necessary
Equipment Required
The equipment required to install a sewerage system will include, but is not lim
ited to, these items:
1. Trenching machines
a. Wheel-type trencher
b. Ladder-type trencher
c. Backhoe
d. Dragline
408 Estimating Construction Costs
Manholes
Manholes are installed along sewer lines, usually 300 to 4 0 0 ft apart, to enable
access to the lines for inspection and cleaning. Also, manholes should be
installed at intersections with laterals, at changes in the grade or directions, and
for changes in the size of the pipe.
At one time manholes were constructed with bricks laid in place. But brick
manholes have largely been replaced with precast (Fig. 22 .1 ) or cast-in-place
concrete manholes. When precast manholes are used, the base may be cast at the
bottom of the hole first; then the remainder of the precast manhole will be set on
the base to complete the installation. Another method of constructing a manhole
is to cast the concrete base monolithically with a lower section of the manhole.
This section of the manhole is set in place; then one or more sections are added
to produce the desired depth. At the time the manholes are cast, holes are cast
through the walls to permit pipes of the sewer line to enter or leave the manhole.
Cast-in-place rubberized gaskets are installed to produce watertight seals for the
pipes. The manhole may be cast with an invert at the bottom to permit the
sewage to flow more effectively (see Fig. 22.2).
Chapter 22 Sewerage Systems 409
PVC wye
Cleanout Boots
Cleanout boots are frequently installed at the upper end of sewer lines to enable
easy access to the lines for cleaning and flushing purposes. The boots are made
of cast iron, with a base, throat, and cover, usually set in concrete for stability.
To provide this installation, the last joint of the sewer line ends with a wye,
pointing upward. Sewer pipe of the desired size is extended upward to the boot.
Figure 22.3 illustrates a cleanout boot installation.
Service Branches
When the main pipeline is installed, it may be desirable to provide access to the
pipe for future connections from users of the facility. This provision can be made
by installing wye branches in the main line at the time it is installed. Pipes of
desired sizes can be extended from the wye branch to locations near the surface
of the ground. The ends of the pipe are closed with stoppers, which permits easy
access to the services. Figure 22.4 illustrates representative service line installa
tion. Tables 22.1 through 22.5 give the approximate labor-hours of construction
operations to install sewer lines.
Labor-hours per
100 lin ft
Size pipe, Pipe laid,
in. lin ft/hr Pipe layers Laborers
4 70 1.5 1.5
6 60 1.7 1.7
8 60 1.7 1.7
10 40 2.5 2,5
12 40 2.5 5.0
15 40 2.5 7.5
Chapter 22 Sewerage Systems 4 11
Labor-hours
Size of Length of Pipe Backhoe
inlet, in. inlet, ft layers Helper operator
4 10-15 1.00 1.00 0.50
4 15-20 1.50 1.50 0.75
4 20-30 2.00 2.00 1.00
6 10-15 2.25 2.00 0.50
6 15-20 2.75 2.75 0.75
6 20-30 3.25 3.25 1.00
Labor-hours
Backhoe
Depth of
trench, ft Pipe layers Helpers Operator Helper
4-6 1.00 1.00 0.50 0.50
6-8 1.50 1.50 0,75 0.75
8-12 2.00 2.00 1.00 1.00
12-15 2.75 2.75 1.25 1.25
EXAMPLE 22.1
Estimate the direct cost of installing a sewerage system requiring the laying of PVC
pipe, fittings, manholes, service connections, and cleanout boots for the given con
ditions.
The project will be constructed in an open and clear area with no obstructions,
land clearing, utility lines, or other items to delay progress. Surplus earth will be
hauled to a disposal site approxim ately 2 mi distant.
The soil will be dense clay, with no groundwater. The trenches will be excavated
with a f-c y backhoe, which will enable the trench walls to assume normal slopes,
with no shoring required. After the pipe is laid, the backfill will be select earth from
along the trench. The backfill around the pipe will be hand-tam ped to a depth of
Chapter 22 Sewerage Systems 413
12 in. above the top of the pipe. The balance of the backfill will be placed by a
bulldozer-loader in 1 2 -in. layers and com pacted with a power-operated tamper.
The manholes will be precast concrete of a type illustrated in Fig. 22.1.
Service inlets will be spaced at 40-ft intervals along the pipeline. Each inlet will
require a wye fitting.
Four cleanout boots will be required.
The quantities of pipe, fittings, manholes, service connections, and cleanout
boots will be as follows:
Service lines:
Total no. of service lines: 4,290 lin ft/40 lin ft/line = 107
Average cost per service:
20 ft of 4-in. pipe @ $1.34 per lin ft $26.80
4 in. x I bend @ $6.45 25.80
4-in. stopper @ $7.56 7.56
Backhoe excavating trench: \ hr @ $64.85 32.43
Backhoe operator: \ hr @ $21.67 10.84
Pipe layer: \ hr @ $21.97 10.99
Laborer: \ hr @ $15.56 7.78
Total cost per service line $ 122.20
Total cost for 107 service lines: 107 X $122.20 $13,075.40
C leanout boots:
Total number, 14
Average cost per boot:
8 lin ft of 6-in. pipe @ $2.92 per lin ft $23.36
6 in. X ^ bend @ $12.41 12.41
Cleanout casting 11.14
6-in. plug 3.40
I cy concrete @ $75.00 cy 18.75
Pipe layer: 1 hr @ $21.97 21.97
Labor placing pipe and casting: 2 hr @ $15.56 31.12
Chapter 22 Sewerage Systems 415
TRENCHLESS TECHNOLOGY
W hen it is necessary to install new underground utility systems that are located
in congested areas near existing utility lines, it may be desirable to use one of
the modem methods of trenchless technology, rather than the open cut trench
method of utility construction. Trenchless technology includes all the methods
of underground pipeline and conduit installation with minimum or no surface or
subsurface disruption. It includes new installations and pipeline renewal.
Trenchless technology has been developed to address social costs, new safety
regulations, and difficult underground job conditions such as deep ditches, high
water tables, and the existence of natural or artificial obstructions. Social costs are
the costs incurred to the general public: safety hazards and damage to the envi
ronment and public assets such as road pavements. Examples of social costs are
loss of business activity due to road closings, reduced life of pavements due to
trenching, cutting trees and damage to green areas, increased possibility of acci
dents due to trenching and trench cave ins, and noise and air pollution. Safety is
also achieved because the workers remain above ground during the construction
process, rather than entering an open trench or a pipe below grade.
There are several methods of trenchless technology, including horizontal
directional drilling and microtunneling, which are presented in this book.
Horizontal directional drilling is used primarily for installation of underground
cables, gas and water lines, and sewer laterals (see Chapter 23). Microtunneling
is ideally suited for installation of gravity sewer lines where a high degree of
accuracy is required.
MICROTUNNELING
Microtunneling machines are laser-guided, remotely controlled, and have the
capability to install pipeline on precise lines and grades. Microtunneling can be
416 Estimating Construction Costs
used to install pipes into almost any type of ground condition up to 150 ft below
the ground surface and up to 1,000 ft in length from the entry drive shaft to the
reception shaft. By definition, microtunneling is a remote-controlled pipe-jacking
operation, and there is no maximum size diameter specified for microtunneling
machines, although most jobs apply to pipe diameters from 24 to 60 in.
Microtunneling is a method of installing pipe below ground, by jacking the
pipe behind a remotely controlled and steerable articulated microtunnel boring
machine (M TBM ). The MTBM, which is connected to and followed by the pipe
that is being installed, bores through the ground as the excavated soil is trans
ported out at the same rate as the boring operation. The minimum depth of cover
above the pipe is generally greater than 6 ft, or 1.5 times the outer diameter of
the pipe being installed. The overcut of the MTBM is usually 1 in. beyond the
outside radius of the pipe. Based on the mode of operation, microtunneling meth
ods can be subdivided into two major groups: slurry method and auger method.
Both microtunneling methods consist of these major components:
1. Microtunnel boring machine
2. Remote control system
3. Active direction control
4. Automated spoil transportation and rate of excavation controls
5. Pipe-jacking equipment suitable for direct installation of the pipe
6. Jacking pipe
/—Crane or other
Jf lifting device
Pipe!
Sending shaft - Receiving shaft Depth
.r-Pipe
N 6 to 150 ft
Concrete backing -
/ \ Microtunneling boring
for jacking thrust
machine (MTBM)
Laser —/
W m
Hydraulic jacking frame -Usually 100 to 1,000 ft-
F IG U R E 2 2 .5 I Microtunneling operation.
Chapter 2 2 Sewerage Systems 417
is constructed at the end of the boring operation. Figure 22.6 is a view looking
down an entry shaft that shows positioning of the MTBM for the boring opera
tion. A view of the MTBM boring the tunnel is shown in Fig. 22.7. A concrete
thrust block on the back side of the sending shaft provides resistance to the thrust
during the pipe-jacking operation. A hydraulic jacking frame at the bottom of
the sending shaft provides the mechanism to push the pipe. As the MTBM bores
through the soil, additional pipe sections are added. Lowering of an additional
pipe section into the entry shaft is shown in Fig. 22.8.
A laser system provides accurate guidance for the line and grade of the
MTBM. In the slurry microtunneling, a hydraulic pumping system provides
removal of the cuttings of the soil material. The solid soil material is separated
and removed by trucks. In auger microtunneling, the spoil is transported by
rotating augers to the sending shaft.
The MTBM is capable of controlling rotation and roll by means of either a
bidirectional drive on the cutter head or the use of fins or grippers. Electric or
hydraulic motors power the MTBM cutter head. The MTBM is articulated to
enable remote steering of the system.
A display showing the position of the shield in relation to a target is avail
able to the operator on an operation console, together with other information
such as face pressure, roll, pitch, steering attitude, and valve positions. The
MTBM has a closed face system capable of supporting the full excavated area
at all times.
418 Estimating Construction Costs
isSs
F IG U R E 2 2 .7 i MTBM boring tunnel for sewer pipe.
Courtesy: Luckinbill, Inc.
JACKING PIPE
In general, pipe used for jacking is round, with a smooth uniform outer surface
and with watertight joints that also enable easy connections between joints. Pipe
420 Estimating Construction Costs
lengths m ust be within specified tolerances and pipe ends must be square and
smooth so the jacking loads will be evenly distributed around the entire pipe
joint such that point loads will not occur when the pipe is jacked in a reasonably
straight alignment.
Pipe used for pipe jacking must be capable of withstanding all forces that
will be imposed by the installation process, as well as the loading conditions that
will be applied to the pipe after final installation. The pipe manufacturer speci
fies the required protection against damage to the ends of the pipe and interme
diate joints during the jacking process. The detailed method proposed to cush
ion and distribute the jacking forces is specified for each particular pipe
material.
If a pipe shows signs o f failure, it may be necessary to jack it through to the
reception shaft and remove it. The pipe manufacturer’s design jacking loads
should not be exceeded during the installation process. In general, the ultimate
axial compressive strength of the pipe must be a minimum of 2.5 times the
design jacking loads of the pipe. The pipe materials specially manufactured for
microtunneling operations include vitrified clay pipe, glassfiber reinforced poly
ester (G R P) pipe, reinforced concrete pipe, steel pipe, resin concrete pipe, and
ductile iron pipe.
Pipe-Jacking Equipment
The main jacks are mounted in a jacking frame that is located in the drive (start
ing) shaft. The jacking frame successively pushes the MTBM, along with a
string of connected pipes, toward a receiving shaft. The jacking capacity of the
system must be sufficient to push the MTBM and the string of pipes through the
ground. Calculations are made in advance of the boring operation to determine
the excavation forces, frictional forces, and the weight of the MTBM and pipes.
For larger pipe, it may be necessary to use intermediate jacking stations.
Spreader rings and packing are used to provide a uniform distribution of the
jacking forces on the end of the pipe. A lubricant may be injected at the rear of
the MTBM and through the pipe walls to lower the friction developed on the sur
face of the pipe during the jacking operation.
axial load capacity can be jacked directly in place without the need of a separate
casing pipe.
One of the major disadvantages of microtunneling methods has been the
inability to utilize flexible or low-strength pipes, such as PVC pipe. Other dis
advantages include high capital cost necessary to purchase the microtunneling
equipment and the problems caused by obstructions, such as large boulders,
roots, or old manmade structures.
MICROTUNNELING PROCESS
A breakdown of the procedures for microtunneling include:
1.Mobilization, soil investigation, and setup of equipment
2. Design and construction of entrance and exit shafts
3. Equipment setup
4. Delivery and preparation of pipe section
5. Tunneling operation
6. Retrieving the MTBM
7. Pipe inspection, testing, and demobilization
Prior to any tunneling project, a soil investigation is conducted to determine
the type of soil and the extent of water. The amount and mix of clays, sands,
silts, or clayey gravel must be known to determine the average time for pushing
the pipe. The presence of water determines the amount of water control that will
be necessary for preparation of the entrance and exit shafts. Mobilization
includes transportation of equipment to the jobsite, site preparation, temporary
facilities, and setup of the equipment.
The contractor is responsible for the design and construction of the
entrance and exit shafts. W here water is present, it may be necessary to install
sheet piling, cofferdams, pumping facilities, or other methods of dewatering the
shaft for the microtunneling operation. A shaft-sinking m ethod may be desir
able in areas with high water table and to eliminate the dewatering process. A
hollow, bottomless structure (reinforced concrete) is built on top of the ground
and is lowered into position by excavating material from within and below to
enable the structure to settle by force of gravity. Once the desired depth is
reached, a tremie seal is placed, the shaft is pumped free of water, and a struc
tural bottom is constructed.
After mobilization and construction of the entrance and exit shafts, the
micotunneling equipment is set up, pipe sections are prepared, and the tunneling
operation can be started. A typical crew consists of the microtunneling machine
operator, crane operator, technician, two laborers, and supervisor. Table 22.6
gives the equipment required for a microtunneling project.
Since speed of installation in a microtunneling project is critical, everything
required for the successful installation should be available when needed.
Consideration must be given to alternative or corrective procedures that might
422 Estimating Construction Costs
Tunnel-boring machine
Control room with operator station and control cables
Laser guidance equipment
Pipe-jacking frame and hydraulic pump equipment
Water and slurry tanks for solids separation
Pumps, hoses, and flow meters for slurry and lubricants
Portable compressor, generator, and welding machine
Backhoe for excavating entrance and exit shafts and spoil removal
Crane for hoisting jacking frame and pipe sections into entrance shaft
be required if conditions at the site are different than anticipated. Table 22.7 pro
vides an example of the time and production rates for a microtunneling opera
tion. The actual production rates are dependent on the experience and skills of
the contractor and the operator, and on the project-specific job conditions, such
as surface and subsurface conditions, type of pipe and equipment used, and
degree of planning and preplanning for the project.
PIPELINES
The following types of pipes are used for water systems:
1. Cast iron
a. Bell and spigot
b. Mechanical j oint
c. Push-on joint, or gasket-seal joint
d. Threaded
e. Cement-lined
423
424 Estimating Construction Costs
2. Steel
a. Threaded, black or galvanized
b. Welded, plain or cement-lined
3. Reinforced concrete
a. Prestressed
b. Nonprestressed
4. Brass and copper
5. Lead
6. Plastic
T A B L E 23.1 I Weight of bell-and-spigot and push-on joint cast-iron centrifugally cast in metal molds, AWWA
C106-70 or ANSI A21.6-1970, Ib/lin ft.
T A B L E 2 3 .2 I Approximate weights of lead and jute required per joint for cast-iron
pipe and fittings.
T A B L E 2 3 .3 I Weights of mechanicai-joint cast-iron pipe centrifugally cast in metal molds, AWWA C106-70 or
ABSI A21.6-1970. Ib/lin ft.
VALVES
Valves for cast-iron water pipes are usually cast-iron body, bronze-mounted,
bell or hub type. Gate valves should be used. A cast-iron adjustable-length valve
box should be installed over each wrench-operated valve to permit easy access
when it is necessary to operate the valve.
SERVICE LINES
Service lines are installed from the water pipes to furnish water to the customers.
These lines usually include a bronze corporation cock, which is tapped into the
water pipe, copper pipe extending to the property line or meter, a bronze curb
cock, and a meter set in a box. Customers install the service pipe from the meter
to their house or business.
Chapter 23 Water Distribution Systems 427
FIRE HYDRANTS
Fire hydrants are specified by the type of construction, size of valve, sizes and
number of hose connections, size of hub for connection to the water pipe, and
depth of bury. It is good practice to install a gate valve between each hydrant
and the main water pipe, so that the water can be shut off in the event repairs
to the hydrant are necessary.
Hand cutting
Size
With chisel With chain cutter Power cutting, hr
pipe,
in. Skilled Laborer Skilled Laborer Skilled Laborer
4 0 .3 0 0 .3 0 0 .2 5 0.2 5
6 0 .4 5 0 .4 5 0 .4 0 0.4 0
8 0 .6 0 0 .6 0 0 .5 5 0 .5 5
10 0 .9 0 0 .9 0 0 .8 0 0 .8 0 0 .6 0 0 .6 0
12 0 .9 5 1.90 0.8 5 1.70 0 .6 3 1.26
14 1.10 2.20 — — 0.66 1.32
16 1.25 2.5 0 — — 0 .7 0 1.40
18 1.40 2 .8 0 — — 0 .7 5 1.50
20 1.50 4 .5 0 — — 0 .8 0 2 .4 0
24 1.65 6 .6 0 — — 0 .8 5 3 .4 0
3 0* 1.25 3 .7 5 — — 0 .9 5 2 .85
36* 1.50 4 .5 0 — — 1.00 3 .0 0
42* 2.00 6.00 — — 1.10 3 .3 0
48* 2 .4 0 7 .20 — — 1.20 3 .6 0
54* 2 .8 0 8 .4 0 — — 1.30 3 .9 0
60* 3 .2 0 9 .6 0 — — 1.50 4 .5 0
*For pipes larger than 24 in. diameter, include the cost of a crane and an operator to handle the pipe.
the approximate time in hours required to cut various sizes of cast-iron pipe. The
time given includes measuring, setting up, and cutting for average conditions.
pipe, the runner is removed and the lead is caulked by hand or with a pneumatic
caulking hammer.
The size of crew required to lay the pipe and the rate of laying will vary con
siderably with the following factors:
1. Class of soil
2. Extent of groundwater present
3. Depth of trench
4. Extent of shoring required
5. Extent of obstruction such as utilities, sidewalks, pavement
6. Size of pipe
7. Method of lowering pipe into trench
8. Extent of cutting required for fittings and valves
Often, water lines are installed above sewer lines. The depth of water lines
are placed below the frost line. Since water lines are under pressure, they can be
routed up or down, rather than following grade to ensure gravity flow like sewer
lines.
The crew required to dig the trenches, lay the pipe, and backfill the trenches
for 12-in. pipe furnished in 18-ft lengths, using a tractor-mounted side boom to
lower the pipe into the trench, in trenches 3 to 6 ft deep in firm earth, with no
groundwater and no shoring needed, might include:
1 trenching machine operator
2 laborers on bell holes
1 tractor operator
2 laborers on pipe
2 workers centering pipe and installing yarning
1 person melting and supplying lead
1 person installing runners and pouring lead
2 workers caulking lead joints by hand*
1driver for utility truck
1bulldozer operator backfilling trench
1foreman
A crew should install four to six joints per hour, either pipe or fittings. The
length of pipe laid will vary from 72 to 108 ft/hr, with 90 ft/hr a fair average for
the conditions specified.
Table 23.5 gives representative labor-hours required to lay cast-iron pipe in
trenches 3 to 6 ft deep in firm soil with little or no shoring required, and no
groundwater, using caulked lead joints. For pipe laid under other conditions, the
*If the joints are caulked with a pneumatic hammer, use only one person. It will be necessary to
include the cost of an air compressor, hose, and hammer.
430 Estimating Construction Costs
T A B L E 2 3 .5 I Labor-hours required to lay 100 lin ft of cast-iron pipe with lead joints.
Labor-hours
Size Pipe Trenching
pipe, laid, machine Tractor Truck Kettle Pipe
in. ft/hr operator operators driver operator layers* Laborers* Foreman
4 120 0.83 0.83 0.83 0.83 1.66 4.15 0.83
6 110 0.91 1.82 0.91 0.91 2.73 4.55 0.91
8 100 1.00 2.00 1.00 1.00 3.00 6.00 1.00
10 95 1.05 2.10 1.05 1.05 3.15 6.30 1.05
12 90 1.10 2.20 1.10 1.10 4.40 6.60 1.10
14 85 1.17 2.34 1.17 1.17 4.68 7.02 1.17
16 80 1.25 2.50 1.25 1.25 6.25 7.50 1.25
18 70 1.43 2.86 1.43 1.43 7.15 8.58 1.43
20 60 1.67 3.34 1.67 1.67 8.35 10.02 1.67
24 50 2.00 4.00 2.00 2.00 10.00 12.00 2.00
•Includes workers pouring lead and caulking joints by hand. If the joints are caulked with a pneumatic hammer, reduce the time by one-third.
+lncludes the workers digging bell holes and handling and centering the pipe. Five workers are used for the 4- and 6-in. pipe and six for the other
sizes.
labor-hours should be altered to fit the conditions for the particular project. If a
crane is used to lower the pipe, replace the tractor operator with a crane operator.
A crew should lay five to seven joints per hour, either pipe or fittings. The
length of pipe laid will vary from 90 to 136 ft/hr, with 100 ft/hr a fair average.
Table 23.6 gives representative labor-hours required to lay cast-iron pipe
with mechanical joints in trenches 3 to 6 ft deep in firm soil with little or no
shoring required and no groundwater. For pipe laid under other conditions, the
labor-hours should be altered to fit the conditions of the particular job. If a crane
is used to lower the pipe, replace the tractor operator with a crane operator.
T A B L E 2 3 .6 I Labor-hours required to lay 100 lin ft of cast-iron pipe with mechanical joints.
Labor-hours
Size Pipe Trenching
pipe, laid, machine Tractor Truck Pipe
in. ft/hr operator operators driver layers Laborers Foreman
4 140 0.72 1.44 0.72 1.44 3.60 0.72
6 130 0.77 1.54 0.77 1.54 3.85 0.77
8 120 0.83 1.66 0.83 1.66 4.15 0.83
10 110 0.91 1.82 0.91 1.82 4.55 0.91
12 100 1.00 2.00 1.00 2.00 5.00 1.00
14 90 1.11 2.22 1.11 2.22 5.55 1.11
16 85 1.18 2.36 1.18 2.36 5.90 1.18
18 80 1.25 2.50 1.25 2.50 6.25 1.25
20 75 1.33 2.66 1.33 2.66 6.65 1.33
24 65 1.54 3.08 1.54 3.08 7.70 1.54
30 55 1.82 3.64 1.82 3.64 9.10 1.82
the pipe. The rest of the backfill may be placed with a bulldozer and compacted
by running the bulldozer along the trench over the backfill, requiring an esti
mated three or four passes of the bulldozer.
The compaction around and 6 in. over the top of the pipe will be obtained
from using a hand-operated gasoline-engine type of self-contained tamper.
The pipe will be lowered into the trench with a tractor-mounted side boom.
The pipe will be laid along one side of the trench prior to digging the trench.
The crew should lay four to seven joints per hour, for either pipe or fittings.
For pipes furnished in 18-ft lengths, the total length laid should vary from 72 to
136 ft/hr with 100 ft/hr representing a reasonable average rate.
The crew might include:
1 trenching machine operator
2 laborers cleaning trench and digging bell holes
1 tractor operator lowering pipe into trench
1 laborer assisting tractor operator
2 laborers in trench handling pipe
1 pipe layer with pipe and fittings
2 laborers backfilling trench
1 laborer operating tamper
1 bulldozer operator backfilling trench
1 foreman
Table 23.7 gives representative labor-hours required to lay push-on joint
cast-iron pipe in trenches whose depths average around 6 ft, in firm soil with lit
tle or no shoring required, with no groundwater, and no major obstacles to delay
the progress.
T A B L E 2 3 .7 I Representative labor-hours required to lay 100 lin ft of push-on joint cast-iron pipe.*
Labor-hours
Sne Pipe Trenching
pipe, laid, machine Tractor Truck Pipe
in. ft/hr operator operators driver layers Laborers Foreman
4 140 0.72 1.44 0.72 0.72 5.70 0.72
6 130 0.77 1.54 0.77 0.77 6.15 0.77
8 120 0.83 1.66 0.83 0.83 6.65 0.83
10 110 0.91 1.82 0.91 0.91 7.25 0.91
12 100 1.00 2.00 1.00 1.00 8.00 1.00
14 90 1.11 2.22 1.11 1.11 8.88 1.11
16 85 1.18 2.36 1.18 1.18 9.44 1.18
18 80 1.25 2.50 1.25 1.25 10.00 1.25
20 75 1.33 2.67 1.33 1.33 10.64 1.33
24 65 1.54 3.08 1.54 1.54 12.32 1.54
*lf for a given job the estimated number of feet of pipe laid per hour differs from the values given in this table, the information in the table can be
used. If the estimated rate of laying 8-in. pipe is 100 ft/hr, the labor-hours for a rate of 100 ft/hr should be used.
Chapter 23 Water Distribution Systems 433
EXAMPLE 2 3 .1
Estimate the cost per unit in place for a cast-iron pipe water distribution system con
sisting of the indicated quantities for each item.
The cast-iron pipe will be AWWA push-on joint for 150-lb/sq. in. water pressure,
in 18-ft lengths. The fittings will be push-on joint AWWA class D.
The quantities will be:
The trenches for the pipe will be dug to an average depth of 3 ft 6 in. and 30 in.
wide, by using a w heel-type trenching machine. The soil is firm, sandy clay that will
not require shores or trench supports. In backfilling the trench around and over the
pipe, the earth will be placed by hand and com pacted to a depth of 6 in. above the
top of the pipe, by using a self-contained gasoline-engine-operated tamper.
The pipe and fittings will be distributed along the trenches prior to digging the
trenches. The cost of the pipe and fittings includes furnishing and delivering the
materials along the trenches. Assume that the job conditions will perm it the pipe to
be laid at a rate of 80 lin ft/hr.
Use Table 23.7 to estimate the cost of labor.
The cost per unit will be:
firm, and suitable for movement of the HDD machine. At the receiving end, suf
ficient room is required so the complete string of pipeline can be fitted together
and aligned with the proposed borehole.
Classifications of HDD
The HDD methods can be divided into four categories: micro-HDD, mini-HDD,
medium- or midi-HDD, and large- or maxi-HDD (usually called HDD). For
comparison, micro-HDD applies to drive lengths less than 150 ft and pipe diam
eters up to 6 in. Mini-HDD is typically restricted to drive lengths less than 600 ft
and pipe diameters less than 10 in. Micro- and mini-HDD are used primarily in
the telecommunication industry for shallow-depth installation of underground
cables and gas lines. Due to limitations of tracking systems of micro- and mini-
HDD, the depths for these installations are limited to around 15 ft. In contrast,
the maxi-HDD systems have elaborate guidance systems that can install pipes to
depths such as 200 ft. The mini-HDD systems can be launched from a curb,
whereas the maxi-HDD systems require substantial space, 150 by 2 5 0 ft. Table
23.8 provides a comparison of the different HDD systems.
Wash
Wash Pipe Bit Riot string Bit
. Siiiycy Tool [ ___ -r
Drill Proffia:
Pilot String
I.D.2. Preream
l.D.3. Pullback
As the pilot hole is being drilled, bentonite drilling mud is pumped down the
center of the drill rods. The drill head usually consists of a jetting head and/or a
drill bit. In both cases, the soil is usually cut by the rotating pilot string. In the
jetting head, small-diameter high-pressure jets of bentonite slurry actually cut
the soil and facilitate spoil removal by washing the cuttings to the surface where
they settle out in a pit. When a drill bit is used for rock-boring operations or
maxi-HDD rigs, the bit can be driven by a down-hole mud motor located just
Chapter 23 Water Distribution Systems 439
behind the drill bit from energy derived from the pumped drilling fluid. The ben
tonite also functions as a coolant and facilitates spoil removal. In addition to the
drill head, for large-diameter crossings such as maxi-HDD rigs, the drill string
consists of a slightly bent section (typically between 0.5 degrees and 1.5
degrees) of a drill rod, called a bent housing, positioned close behind the drill
head. Rotating and positioning the bent housing affect the steering operation.
The progress of the pilot hole is monitored by a specially designed survey
system. One part of the system (usually for maxi-HDD operations is located
behind the bent housing) records the exact position, inclination, and orientation
of the drill head. This information is transmitted by magnetic fields, or for larger
HDD operations a wireline system, to the other part of the system, which is
located at the ground surface where a computer is used to interpret and plot this
data. The actual position of the drill head is then compared to the required posi
tion on the design path and deviations, if any, are corrected by moving the bent
housing and steering the drill head to the desired location. For mini-HDD and
most midi-HDD systems, a walkover system is used where the drill head is
located through magentic signals by a transmitter, located behind the drill head.
These signals are identified and interpreted on the surface by a receiving instru
ment, which is actually “walked over” the drill head location.
For larger diameters, the operator may make several passes to achieve the
final diameter of the borehole. For each pass, a larger diameter reamer tool, a
“step reamer,” is used. Alternatively, reaming devices can be directly attached
to the drill pipe and pulled back through the pilot hole, enlarging it to the desired
diameter suitable to accept the designed pipeline.
For diameters less than 20 in., the pipeline can be attached directly behind
the reamer using a swivel device so that the total assembly can be pulled back
in one pass. However, even for diameters less than 20 in., many contractors
choose to preream the borehole. Prereaming widens the pilot hole to a diameter
slightly greater than the utility diameter. A circular cutting tool, attached to the
drill pipe end, is then rotated by the drilling rig simultaneously pulling it back
along the drilled pilot hole. Bentonite is pumped down the drill pipe to carry the
soil cuttings to the surface.
Prior to the pipeline pullback operation, the pipeline has to be made up in
one full length. For steel pipe, which is usually used for larger diameters, it is
welded, X-rayed, coated, tested, etc. before installation. It is positioned on rollers
in line with the drilled hole to minimize any axial loads that will be imposed on
the line as it is being pulled, and to protect the product line from excessive
stresses. The pipeline is then attached to the drill pipe with special adapters. A
fly cutter, or other type reamer, and swivel are installed between the drill pipe
and the pipeline to increase the borehole to the desired diameter, to smooth the
hole, and to ensure that the rotating action of the drill pipe is not transmitted to
the pipeline. The pipeline is then pulled along the drilled path and installed in
position. When polyethylene pipe is used, it is butt-fused using fusion devices.
Usually steel pipe is used for large diameters, whereas, for small diameters,
PVC and most frequently polyethylene pipe is used for horizontal directional
440 Estimating Construction Costs
PRODUCTION RATES
M ost mini-HDD jobs are usually completed in a day or even a few hours. It is
common to complete a 200-ft job in a few hours. For midi-HDD projects, and
for lengths of 1,000 ft or longer, the job may take 10 or 15 days, including mobi
lization and setup of the rig and preparation of the product pipe. For major river
crossings using maxi-HDD, the project may take several months to complete.
. It should be noted that the duration of an HDD project is site-specific, and
it is dependent on many factors, such as experience of the operator and the con
tractor, project surface and subsurface conditions, equipment used, type of appli
cation, and the degree of planning and preplanning for the project.
Total Cost of
Engineering Projects
The previous chapters of this book have discussed methods of estimating the
costs of constructing engineering projects. However, the cost of construction is
not the only cost that the owner of the project must pay. The total cost to the
owner may include, but is not necessarily limited to, these items:
actually purchasing it. This right may be defined as an easement, for which the
owner of the project may pay the owner of the land.
LEGAL EXPENSES
The construction of a project frequently involves actions and services that
require the employment or use of an attorney. The actions requiring an attorney
may be the acquisition of land and easements, holding a bond election for a gov
ernment agency, printing and obtaining approval of bonds to be sold for provid
ing the money to finance the project, or assistance to a private corporation. The
legal fees paid for these services should be included in the cost of the project.
BOND EXPENSE
Before a project can be constructed by a government agency, it is usually nec
essary to hold a bond election for the purpose of permitting qualified voters to
approve or reject the project. In the event voters approve the project, it is neces
sary to print, register, and sell the bonds, usually through a qualified underwrit
ing broker, who charges a fee for these services. Private corporations frequently
sell bonds to finance new construction. In any event, it is correct to charge to the
project the costs of these services.
COST OF CONSTRUCTION
The cost of constructing a project is usually an estimate only, made in advance
of receiving bids from contractors, prepared by an engineer or an architect. It is
the amount that she or he believes the owner will have to pay for the construc
tion of the project.
The estimate may be a lump-sum cost, such as for a building, or it may be
a unit-price estimate, for a project that requires the construction of various items
whose exact quantities are not exactly known in advance of construction. For
example, the contract for constructing a highway may specify a given payment
to the contractor for each ton of asphaltic material placed in the pavement.
For a project that involves the construction of units of work, the bid form
will provide for the bidders to state the amounts that they will charge for con
structing each specified unit.
ENGINEERING EXPENSE
Prior to construction, the owner engages an engineer or an architect to make nec
essary surveys and studies, prepare the plans and specifications, assist in secur
ing bids for the construction, and act as the owner’s representative during con
struction. The cost of engineering services is by one of the following methods:
lump-sum, salary cost times a multiplier, cost plus a fixed payment, or percent
age of construction.
Chapter 24 Total Cost of Engineering Projects 443
For simple or small projects, the cost of engineering design may be based
on a single lump-sum payment. This method applies only when the work to be
performed is well defined and the project has no unusual requirements.
The salary times a multiplier method is used for complex projects or for
projects that do not have a well-defined scope of work. The designer provides a
fee schedule to the owner that lists the classification and salary cost of all per
sonnel, and a rate schedule for all other costs that will be directly charged for
engineering services. A multiplier, usually within a range from 2.0 to 3.0, is
applied to direct salary costs to compensate the design organization for over
head, plus a reasonable margin for contingencies and profit.
The cost plus a fixed payment method is often used when an engineering
design is required to start before the cost and scope of the project can be accu
rately determined. Such indeterminate projects generally result when the owner
wants to accelerate the design process, analyze special problems that require
studies, or prepare estimates for alternate types of construction. The fixed fee
usually varies from 10 percent for large projects to 25 percent for small projects
that are short in duration.
The percentage of construction cost method may be used for certain types of
engineering design, where design procedures, methods of construction, and types
of material are well known and relatively standard. This method applies only
where engineering experience has established a correlation between engineering
costs and construction costs. Generally the percentage is on a sliding scale that
decreases as the construction cost increases. The percentage also varies depend
ing on the level of design services that are provided, such as design only; design
and preparation of drawings; or full design services that include design, prepara
tion of drawings, and observation during construction. The percentage generally
will range from 5 to 12 percent of the anticipated construction cost.
CONTINGENCIES
If the exact cost of the project is not known in advance of raising funds to
finance it, as is frequently the case, it is good practice to provide funds to cover
any additional costs that may occur during construction. An estimator should
rely on personal judgment to determine the amount of contingencies desirable.
Computer Estimating
INTRODUCTION
The preceding chapters of this book presented the principles and concepts of esti
mating construction costs. Emphasis was placed on the thought process that is
required of the estimator to analyze job conditions and assess the required labor,
equipment, and method of construction that will be necessary to perform the
work. These are functions that can only be performed by the estimator because
experience and good judgment are required to prepare reliable estimates.
To assemble a complete estimate for bid purposes, the estimator must com
bine knowledge of construction methods and techniques into an orderly process
of calculating and summarizing the cost of a project. This process requires
assembly of large amounts of information in an organized manner, and numer
ous calculations must be performed. The computer is an effective tool to facili
tate this process by decreasing the time and increasing the accuracy of cost esti
mating. The computer can retrieve data and perform calculations in seconds,
enabling the estimator to give more attention to alternative construction meth
ods, assess labor and equipment productivity, obtain prices from subcontractor
and material suppliers, and focus on bidding strategies.
Preparing a detailed estimate is an ideal task for the computer. Estimates
consist of dozens, hundreds, or thousands of cost elements that must be summa
rized into various levels of subtotals and totals for intelligent review. The com
puter can perform the calculations rapidly and accurately, thus relieving the esti
mator from tedious and repetitious arithmetic.
Although the computer has dramatically improved the process of preparing
estimates, the estimator should never accept everything that comes out of the
computer as being totally correct. Estimators must use common sense and judg
ment and use the computer as a tool to assist the estimating process, and not
depend solely on the computer.
This chapter introduces computer methods for estimating construction costs.
Many commercial software programs are available. In this book, reference is
445
446 Estimating Construction Costs
ELECTRONIC MEDIA
Today, many companies operate in a paperless environment by using electronic
media and the Internet. Engineers produce drawings and specifications using
CAD and word processing software. Thus, full sets of bid documents are some
times supplied entirely in the electronic media.
E-mail is often used for communications both inside and outside a com
pany’s office. It enables users to send written messages with optional attach
ments to anyone and everywhere at no cost. Attachments can include drawing
files, word processing documents, spreadsheets, photos, multimedia clips, and
web pages. Faxes can also be sent over the Internet instead of over regular voice
lines. A request for information (RFI), request for quote (R FQ ), request for pro
posal (R FP), letter of intent, transmittal, and similar type correspondence are
often via the electronic media. Many state Departments of Transportation
(D OTs) provide pay quantities for bidding on their websites for access to
prospective bidders. This information can be downloaded into the estimator’s
computer.
Security of information is always a concern of businesses. Security issues
must be addressed with Intranets and Extranets. An Intranet is an Internet site set
up for private use of a company that might include certain corporate financial
data or other confidential information. The Intranet controls access of informa
tion. An Extranet is an Internet site set up by a company for shared use with oth
ers. It might contain a variety of information with limited or full access to its
employees, subcontractors, suppliers, or the general public.
FUNDAMENTALS OF SPREADSHEETS
Essentially, a spreadsheet is an electronic file that consists of hundreds of
columns and thousands of rows. The intersection of a row and column is called
a cell. Text and numerical data can be entered into cells and formulas can be
written by the user to program any desired calculation. Figure 25.1 is a simpli
fied spreadsheet of a bid summary for an estimate.
Spreadsheets have capabilities beyond simple calculations. Most have pow
erful graphic packages that enable the estimator to provide meaningful reports
to management. The user has considerable flexibility in formatting the input and
output.
A B c D E
1
2 Summary o f Costs fo r Bid
3
4 Item Labor Material Equipment Total
5 Install foundations $2,000 $0 $3,000 $5,000
6 Build Structure $4,000 $7,000 $2,000 $13,000
7 Finish work $3,000 $4,000 $1,000 $8,000
8 Clean up and move o ff $1,000 $1,000 $2,000 $4,000
9 Direct cost totals $10,000 $12,000 $8,000 $30,000
10 Overhead $2,400
11 Contingency 500
12 Profit $3,290
13 Total bid $36,190
F IG U R E 25.1 I Simple spreadsheet of bid summary.
450 Estimating Construction Costs
A B C D E F
1
2 Excavate
3 900 CY
4 Price Extensions
5
6 Item Hours Rate Cost
7 Foreman 24 $20 $480
8 Backhoe 24 $50 $1,200
9 Operator 24 $20 $480
10 3 Laborers 72 $10 $720
11 Total $ 2 ,8 8 0 / 900 CY = $3.20/CY
F IG U R E 2 5 .2 I Spreadsheets are a duplication of the paper and calculator process.
Chapter 2 5 Computer Estimating 451
Disadvantages of Spreadsheets
When estimators create programs and systems of programs, they are rarely cre
ating professional commercial software products. While this may not be a prob
lem in a company with one estimator who is doing all of the work, it can become
a problem in a larger company where many estimators use the same spread
sheets. Typically, someone in the office writes a spreadsheet at a particular time
for a specific purpose, and only the developer of the spreadsheet knows all the
features that are in the spreadsheet. If the spreadsheet proves useful in the office,
it is common practice to share it among other estimators. However, spreadsheets
may have errors in the logic that no one discovers because it does not occur to
anyone to check the programming. Thus, estimators may be using a spreadsheet
without knowing the results are correct.
As spreadsheets are developed, they are rarely documented, particularly if
they are sophisticated or elaborate. The developer of a complex spreadsheet is
often the only person who can use it as it was originally intended. The newer
users may not grasp the features easily, fully understand the formulas, or verify
the accuracy of the intended results. If the writer of the spreadsheet leaves the
company, often nobody knows how to change it. Thus, there may be a tendency
to continue using the spreadsheet as it was originally written, or one estimator
may make changes in the software without the knowledge of other estimators.
A common error in spreadsheets is to add a line and then forget to adjust the
sum formula to include the added line in the total cost, which results in a bid that
has some of the cost items missing. Too often, errors of this type are not detected
until the bid is submitted. It is then too late to correct the problem.
It is usually better for an estimator to devote time to estimating, rather than
developing elaborate systems of spreadsheets. Some people become intrigued
with computers, and if they are not careful, they spend more time playing with
the computer than doing the job they are supposed to be doing.
Many offices work in a multiuser environment, where several people work
on the same estimate at the same time. Spreadsheets are not conducive to this type
of work environment because they are intended for only one person at a time.
COMMERCIALLY AVAILABLE
ESTIMATING SOFTWARE
In the United States, computer estimating software is very specialized. The
process of preparing a fixed-price estimate for a high-rise building is quite dif
ferent than preparing a unit-price bid for a highway project. Thus, specialized
estimating software is written for different sectors of the construction industry
to reflect those differences.
The companies tend to specialize in these areas:
1. Residential construction
2, Building construction
452 Estimating Construction Costs
HeavyBid/Express R evision 1 0
£Be Edit Setup Estimate Queij' Repeats Sjjmmaty Tsois Window Help
ta d T ffin tg r
type process industry projects. Generally these types of projects involve large
capital investments and the engineering and construction are more integrated
than building or infrastructure projects. Cost estimating often overlaps the engi
neering design phase. The ICARUS software package is commonly used for
process industry type projects.
databases of vendors, multiple labor rate tables, etc. These databases can contain
thousands or hundreds of thousands of items.
Unlike spreadsheets, commercial estimating software is designed for multi
ple users. Most of these systems allow many estimators or managers to be in the
same estimate at the same time. This feature is valuable for estimating large
projects when numerous estimators are involved in putting a bid together.
Commercial software companies validate and document their product before
it is released for sale. Writing software requires extensive testing and retesting
to validate the results. Validation of their software is a continuous process, based
on feedback from users. Documentation of software packages is extremely
important because inevitable questions will arise by users during actual use and
operation of the software. The systems are well documented and usually contain
instructions and tutorials to assist the users.
To become proficient at any task, training is needed. Investment of a small
amount of training will greatly enhance the proficiency and efficiency of com
puter utilization. Many companies offer on-site training, training at the vendor’s
office, Internet training, and other training materials and opportunities to help
keep estimators up-to-date with the technology. Since estimators often work
long hours, many software companies offer 24-hr support, which is essential
when critical problems arise while using the software.
MANAGEMENT OF DATA
Vast amounts of data may be used in computer estimating. The data must be cre
ated, stored, retrieved, and continually updated. Most data is stored on spinning
disks called hard disks (see Fig. 25.4). Read/write heads move over the disks on
a radius from inside to outside and stop on concentric tracks and wait for the data
on the spinning disks to reach them. Although the heads move very fast and the
disks spin very fast, these are still mechanical devices that store and retrieve that
data. However, the data remains on the disks even when the power is turned off.
Data that is being temporarily worked on is stored in the computer’s mem
ory. These are electrical circuits that maintain their information only while power
is being supplied to them. This data is processed at electrical speeds several
orders of magnitude faster than data from the hard disks. Typically data is read
from hard disks into memory, processed, and then written back to the hard disks.
Spreadsheet programs load an entire spreadsheet, such as an entire estimate,
into memory where it can then be manipulated. Any new information added to
the spreadsheet is kept in the temporary memory and therefore can be lost until
the spreadsheet is saved again. If power is lost to the computer, any unsaved data
will be lost. Therefore, the estimator should periodically save the spreadsheet to
the hard drive, or have a default set in the spreadsheet program to automatically
save the data every few minutes.
Database systems read only small amounts of data from the hard disk into
memory and then write back to the hard disk when it is saved. For example, if the
user calls up a material item, changes the price, and presses a Save or OK key,
then immediately the data would be written back and safely saved to hard disk.
Although hard disks are usually safe from power failure, they do occasion
ally wear out or crash for various reasons, including malicious pranks such as
computer viruses. There is a substantial chance that one day in 2 or 3 years of
use a hard drive will fail and the data on it will not be recoverable, and estima
tors should plan for this possibility. Therefore, the active estimate on a hard
drive must be copied to a separate physical device as a backup copy.
Many companies have a nightly backup performed by their computer
department. Although this is a good practice, it is usually not sufficient to ensure
against the loss of an estimate. Many estimators work late at night, after normal
work hours. Therefore, substantial work may be performed on an estimate after
the nightly backup, so the work they have done may not get backed up. Also, a
team of estimators can do an extensive amount of work on an estimate during
the day prior to the nightly backup. Thus, active estimates should be backed up
several times during the day, especially the day before, and the day an estimate
must be submitted for an important bid.
For stand-alone personal computers, a backup to a floppy disk is common.
For an important bid, the estimator should use three or four floppy disks for
backups. The estimator should not keep backing up, or overwriting, on the last
backup disk because a serious error may not be discovered until after a backup.
Figure 25.5 shows the backup screen from HeavyBid/Express.
If the estimator’s personal computer is connected to a main computer net
work that contains the estimate, the estimate can be backed up to the hard disk
of the personal computer. For example, an estimator may be working on an esti
mate that is storing data on drive “F” of the central computer. The estimator can
store the estimate on drive “C” of the personal computer as the backup device.
Since the hard drive on the estimator’s personal computer is a separate physical
device from the drive on the main network computer, this constitutes a valid
456 Estimating Construction Costs
Backup Estimates
Type the location of the estimate to be backed up- To select
another estimate, click the prompt button,
LastChanae:
STARTING AN ESTIMATE
The enclosed estimating program (HeavyBid/Express) contains a tutorial to
guide the user through the keystrokes of preparing an estimate. The best way to
learn a software package is to explore features and try various scenarios to become
familiar with its capabilities. This chapter is more concerned with presenting the
concepts of computer estimating rather than attempting to teach the reader how
Chapter 2 5 Computer Estimating 457
Backup Estimate
Restore Estimate
1 C:\HBXPRESSSEST\OVERVIEW
2 C:\HBXPRESS\EST\AGENDA
3 C:\HBXPRESS\EST\ESTMAST
to use a specific software package. Most of the illustrations for this chapter are
from HeavyBid/Express, although some are from the more advanced versions of
HeavyBid.
Most programs start a new estimate by selecting something like the “New”
option in the “File” menu in the top left as in the illustration of Fig. 25.6,
although many may have shortcuts such as the HeavyBid/Express screen of
Fig. 25.3. This particular program walks the user through the steps to start an
estimate consisting of giving the estimate a number, name, and then specifying
where to copy from to create this estimate. The normal source for the estimate
in HeavyBid is the “Master,” but an estimate can be created from any prior esti
mate as well, for example, to make an alternate estimate or evaluate “what i f ’
scenarios while still keeping the original estimate.
The “Master” is a template estimate and contains data that is typically used
in every estimate. Most software vendors use this technique and most people set
up their spreadsheet programs the same way. Very few estimators start an esti
mate from scratch. Typically the Master contains a company’s resources such as
458 Estimating Construction Costs
labor, equipment, materials, subcontractors, and crews. It may also contain stan
dard overhead items and markups with or without costs. These are then copied
to be the starting point for a new estimate. The “Master” does not contain any
thing specific to a particular estimate such as biditems, activities, or cost detail.
The concept of copying data to start a completely new estimate makes each
estimate totally independent of each other. Thus, any changes made to one esti
mate have no effect on any other estimate. For example, changing a labor rate in
one estimate would not change other estimates that are in progress. If it is desir
able to change the labor rate everywhere, the new rate would be made in the
“Master” and in every estimate that had already been started. Future estimates
that started from the “Master” would then have the new rate.
After creating a new estimate, the estimator should look for one or more
screens that ask about information that applies to this estimate such as bid date,
sales tax rates, overtime rules, etc., and fill out any that is relevant to this new
estimate.
BIDITEMS
After a new estimate is started, the structure of the estimate can be set up. Most
infrastructure bids are unit-price bids in which the contractor is given a list of
biditems with quantities and the estimator furnishes the unit price of each item.
Since the owner provides the biditems and quantities, it is logical to enter them
into the system all at once. The estimator should find a screen similar to that
shown in Fig. 25.7 and then type or import the biditems into the estimate.
Many commercial software systems have the ability to import biditems and
quantities from major organizations such as state DOTs. These are often available
on the Internet or furnished on floppy disks. The HeavyBid/Express software in
this book does not have import capability, so the biditems must be typed in.
At the end of the estimating and bidding process, the amount of the bid is
simply the summation of all items, where each item is the product of the owner’s
quantity multiplied by the estimator’s unit price. Entry of accurate unit costs is
more important than the total cost because the owner recalculates the individual
cost items in unit-price bids. However, it is embarrassing on bid day if a contrac
tor’s bid total is read in public at the bid opening, and then the next day it has to
be corrected after being recalculated. Although this happens periodically with
spreadsheets or hand-calculated bids, it rarely happens with commercial software.
Sometimes the contractor may not agree with the quantity that is specified
in the owner’s bid documents. For example, the bid document may show
10,500 cy of excavation, but the contractors’ takeoff may show only 10,100 cy.
Thus, the contractor would expect to be paid for 10,100 cy. The 10,100 quantity
is referred to as the “takeoff” quantity, whereas the 10,500 quantity is referred
to as the “bid” quantity. The bid quantity is what the contractor must bid and
what the owner expects to pay. The takeoff quantity used in this context is the
quantity that the contractor expects to actually be measured during construction
and on which payment will be made upon completion.
Chapter 25 Computer Estimating 459
H eav y B id /E x p ress R ev isio n 1 0 OVERVIEW T utorial O verv iew E stim ate Hflil P |
£8e £dii je t# Esjmate: fluerji Bepoits Stjrnmaty T;fi6ls Window Help
1 h T *B I€ ^ 0 j : E i l l : <3l H i ► M fX
S e tu p - Biditem s
Description
Mobfcatwi
2 Clearing !< Grubbing 35.500 ACRE
3 Demolition & Removals
4 Sulk Excavation
5 Embankment
6 Fine Grading 190,556.000 SY
67,530.000 TON
8 2.5" A/C Binder Course ■Type D 25,010.000 TON
3 1.5" A/C Surface Course • Type F 15,010.000 TON
10 Striping - 4" Yellow 85.750.000 LF
11 Striping • 4" White 57,170.000 LF
1,245.000LF
Biditems
Umnteiral code lor Diditern v/e recon-mend the -eauentia! item r n te i time: )<1-a 100—
Although contractors must still bid the quantity that is given to them, they
must take into account the financial consequences if the takeoff quantity turns
out to be the actual quantity. If the takeoff quantity is less than the bid quantity,
the final revenue for that item will be less than that shown on the bid form.
More sophisticated systems, but not the shareware program in this book,
allow entering both bid quantities and takeoff quantities, and then provide some
analysis about the effect that differing quantities have on the bid. These features
should be tested thoroughly! This is a very complicated subject, and even
knowledgeable estimators do not agree on even the theoretical aspects. Once
agreed on how the program should work, the estimator then needs to verify how
it does work to avoid any surprise bidding errors.
If the bid is not a unit-price bid, but rather is a lump-sum bid in which the
owner only expects a single total price, the contractor could have only one
biditem with a unit of “lump sum” (Is). However, it is better to use the biditem
level to structure the estimate into major categories. For example, biditems might
460 Estimating Construction Costs
QUANTITY TAKEOFF
The term quantity takeoff is sometimes called material quantity takeoff, or sim
ply takeoff. Takeoff is the process of reading the plans and determining the quan
tities of work required to build the project. It is the estimator’s interpretation of
the designer’s intent. Takeoff can be performed by hand calculations or by using
the computer. Area and volume calculations, such as earthwork and paving, are
usually more efficiently done with the computer. Structure takeoffs, such as con
crete and reinforcing steel, are usually performed by hand calculations or with
spreadsheets because the details are often spread over multiple drawings.
Although some vendors have software for both takeoff and estimating/bidding,
most construction software vendors specialize in one or the other.
The process of performing a takeoff is the estimator’s opportunity to fully
understand the work that must be estimated. An estimator who has not per
formed or thoroughly reviewed the takeoff may not have an accurate under
standing of what is to be estimated. Items missed in the takeoff will obviously
not be included in the bid price, but will still be costs that will be incurred dur
ing construction of the project.
For unit-price estimates, the takeoff quantity may verify the bid quantity,
but not include all of the work for which a takeoff is required. For example, an
item to install 18-in. PVC pipe will state the length of pipe to be installed, but
does not address the quantity of excavated earth or the stone pipe bedding that
is required to complete this item. These takeoff quantities are ancillary to the
length of pipe, on which payment is calculated, and can only be determined from
the drawings.
RESOURCE TYPES
Resources for construction projects include labor, material, equipment, and sub
contractors. For infrastructure type projects, contractors typically categorize
costs by the following cost categories:
1. Labor
2. Material (or permanent material and construction material)
Chapter 25 Computer Estimating 461
d\
HCSS Pag*
6
OVERVIEW/ Tutorial Gvexvfcw 02/12/200 i 22:38
Mike Rydin. DIRECT COST REPORT
BIB ITEM * 12
Description * Install 18" RCP Unit = LF Quantity: 1,245.000
± u ►R
5 3 ! Finished
The eauinment code must start with 'S'. Last Chanae: ..... ... :..! .
FIG U R E 2 5 .8 I Cost categories in columns.
Thus the first letter, or number, of a cost category designates the type of
resource. For example, CF (carpenter foreman) is a labor code because it starts
462 Estimating Construction Costs
with a “C,” and 4ELEC is an electrical subcontractor because it starts with the
number 4.
The designation used for resources will vary, depending on the software.
For example, some software packages use the following designations:
L = Labor
M = Material
E = Equipment
S = Subcontractors
Using these designations, LCF (carpenter foreman) is a labor code because it
starts with an “L,” and “SELEC” is an electrical subcontractor because it starts
with an “S.”
Some software hides the cost category in an attempt to make the software
appear easier to use. Thus, the estimator doesn’t need to use a number or letter
to identify the resource type. However, the advantage of not having to know is
also the disadvantage of not knowing which cost category has been specified. If
the entry technique is such that the estimator can immediately identify a cost in
the wrong category, this technique is as good as the ones discussed earlier; oth
erwise, the only way to detect an error is to spot a resource in the wrong column
on a display or report.
RESOURCES
Identifying and selecting resources is crucial in estimating infrastructure proj
ects. For example, knowing the quantity of earth to be excavated is not enough
information to estimate the cost of excavation. The cost will depend on the size
of crew and the type of equipment that will be used for excavation. Therefore,
the estimator must select the crew mix and type of equipment to be used before
the cost can be estimated.
Resources, particularly types of equipment, are much more important when
estimating infrastructure projects compared to building type projects. Much of
the work involved in building construction is independent of the number of
workers or type of equipment. For example, knowing the square feet of painting
is normally sufficient information to determine the cost of painting. The estima
tor can simply multiply the square feet of painting by the painter production and
wage rate to determine the total cost.
A major feature of computer estimating software for infrastructure projects
is the ability to set up resources in more detail than building construction soft
ware. Not only do they contain resources such as labor, equipment, material,
subcontractors, and crews, but also the treatment of each of these resources is
more elaborate. Typically labor calculations take into account such details as
taxes, union fringes, and overtime. Equipment can include such details as rental
costs and components of operating costs.
Most contractors pick from the same pool of resources for every job. Thus,
there should be a place in the software to set up company resources that can be
Chapter 2 5 Computer Estimating 463
used for every job. In HeavyBid/Express, all resources are entered into the
“Master” estimate and then are copied to start each new job.
LABOR RESOURCES
Labor is typically estimated by craft rather than by individual people because
most contractors bid much more work than they expect to win. Thus, contractors
do not know how many jobs they will need to staff and with whom until after a
bid letting.
In computer estimating, labor crafts are usually selected from selection lists
that pop up on the screen. These codes should appear in a manner that enables
the estimator to quickly find them. For example, if all operator codes start with
the letter “O,” then the estimator is able to pick all of the operators without scan
ning through possibly dozens of unrelated labor codes.
Estimates of labor cost can vary from fairly simple for nonunion 40-hr/week
jobs, to extremely complex union jobs with various combinations of union wage
scales, overtime rules, taxes, and fringe benefit rules.
Regardless of the simplicity or complexity of the actual labor calculations, the
computer system must account for all of the labor costs with a consistent method.
Three typical methods for costing labor resources on infrastructure jobs are
Method 1: Enter all of the burden factors into the estimating software and
let the system compute labor rates.
Method 2: List all possible labor combinations in detailed spreadsheets
and then use the average rates that apply for a particular
estimate.
Method 3: Simply add an historical percentage to the labor base rate to
account for taxes, overtime, and other labor burdens.
The method used will depend on the complexity of the labor conditions, the
capabilities of the estimating software, the level of accuracy desired by the esti
mator, and the flexibility desired while estimating.
For example, HeavyBid/Express, shown in Fig. 25.9, has a base rate, a total
tax rate, a total fringe rate, and an overtime technique (not shown). For contrac
tors with simple labor computations, this software is accurate for method 1. It is
also accurate for any contractor using methods 2 and 3. However, a contractor
with complex labor conditions who wishes to use method 1 must upgrade to a
more sophisticated software package. Method 1 is particularly desirable on a
large, complicated, union job with many unusual conditions such as evening and
weekend work while traffic is shut down.
Regardless of the method used, if possible, the labor codes in the system
should remain consistent across estimates. It is much easier to establish estimating
standards when the codes remain the same and only the rates change when bid
ding in different union areas or different states. If the codes don’t change, then
the crews don’t necessarily have to change, nor anything else in the system that
is set up with labor craft codes.
464 Estimating Construction Costs
f j 2 «t i a IH 4 ► ►! X
EQUIPMENT RESOURCES
Setting up equipment has many of the same considerations as labor. Equipment
is usually generic as opposed to any specific piece of equipment because the
estimator typically does not know exactly which machine will be used, only the
required size and capacity. Equipment should be coded in like groups. For exam
ple, all dozers should appear together in selection lists. If specific pieces of
equipment are used in estimating jobs, they should be coded such that they
appear near generic equipment of the same type. The equipment codes kept by
the accounting department are often inappropriate to use in an estimating system
because they were often coded in historical sequence, rather than with quick
lookups in mind. Like labor, the equipment can be fairly complex, although the
HeavyBid/Express software (see Fig. 25.10) has one simple all-inclusive equip
ment rate.
The ability to fine-tune an estimate based on job conditions can be accom
plished more accurately when the equipment rates can be broken down into two
components: ownership costs and operating expenses. Operating expenses of
equipment are relatively straightforward costs, but ownership costs are more
complicated.
Equipment purchased by a contractor requires cost recovery calculations
that include purchase price, interest, insurance, repairs, etc., which are indepen
dent of the utilization of the machine. These costs must be recovered through the
estimates in which the equipment is used.
The contractor may be making installment payments on some equipment, so
it is obvious that the equipment is not free; however, other purchased equipment
may be owned with no debts, and thus the lack of payments may make the equip
ment appear to be free. However, all equipment must be charged a rent to cover
the cost of ownership or replacement, and ideally should bear some relationship
to the cost of ownership and the competitive rates other contractors are using.
From a cash flow perspective, equipment totally paid for requires no cash out
lay on a particular job, and if the ownership costs are broken down in an esti
mate, the contractor can determine how much of the equipment ownership cost
is not an immediate cash outlay.
Another issue related to construction equipment is whether to charge for
days the equipment is on the job, but not used. If operating expenses are broken
out separately from ownership costs, the estimator has the ability to ensure that
468 Estimating Construction Costs
! s si i fl l< < ► ►! I X
Setup Equipment
Arrow Board
Asphalt Paver {LG} 119.60-
Asphalt Paver (SM) 51.42
Asphalt Reclaimer 215.00
Roadway Saw (w/Blade)
8BH416 CAT 41SBaekhoe
8BH426 CAT 426 Backhoe
8BH510
8BH710 JD 710 Backhoe
8BH71C J D 710 Backhoe w/c
8BH71D JD 710 Backhoe w/hoe ram
Trench Box
.P.eieie Row
‘Equipment
F IG U R E 2 5 .1 0 I Equipment setup.
operating costs are incurred only when the equipment is actually operating
regardless of how the rent is charged.
Some software systems allow entering many equipment operating compo
nents, such as fuel consumption, lube consumption, GEC (ground engaging
components, or tires and treads), mechanic time, minor repairs, major repairs,
etc. Each of these factors can be individually adjusted for the particular job,
including fuel rates and mechanic rates. These cost components can be obtained
from actual job records, or from equipment manufacturer’s literature such as the
Caterpillar Performance Handbook, or from rental rate sources such as the
Dataquest Blue Book.
For company-owned equipment, the contractor may charge it by the hour,
day, week, or month. Some contractors do not charge the equipment to the job
when it is idle because they feel it makes no difference whether it sits on the job
site or in the equipment yard. Since it is a company policy issue, the method of
preparing the estimate should reflect the company’s method of charging equip
ment to the job.
Chapter 25 Computer Estimating 469
If the company policy is to charge for idle time, the idle time must be
reflected in the estimate, either as more hours for that equipment or as a higher
rate. For example, working 30 hr but paying rent for 40 equipment hours creates
a factor of 40/30 = 1.33. Thus, the equipment cost would be increased by the
1.33 multiplier factor. It is much clearer if the computer software allows the user
to enter the 1.33 factor rather than change the base rental rate. For example, if
the equipment is entered into the estimate as used 40 hr (instead of 30 hr), there
would be another 1 0 -hr increase in the operating costs, which would make the
estimate artificially high and thereby increase the risk of losing the bid. This
could be adjusted by reducing the operating expense by 30/40 = 75%, a feature
actually possible in advanced versions of HeavyBid.
MATERIAL
Some companies lump all material together, while others break material down
into permanent materials that are incorporated into the work and other materials,
often called construction materials.
A significant problem with automating materials is the large number of
materials that may be used. It is not uncommon for a company to have from
1,000 to 5,000 materials that are consistently used. One technique for entering
material is simply to create a code and description only for the material that is
used in the estimate. However, it is more common to have a database setup from
which to choose material. It is also common to have “plug” prices for many of
those items. For example, “Class A Concrete” could be set up with a unit of cy
and a price of $55.00.
This is an example of how a material database might be coded and structured:
Code Description
2 Material
2C Concrete
2CR Reinforcement
2CRS Reinforcing Steel
2CRS60 Grade 60 Rebar
CREWS
Most systems use the concept of a crew to link together labor, equipment, and
optionally material. Figure 25.11 shows the crew setup in HeavyBid/Express.
Using crews is a very fast way to enter labor and equipment into an estimate.
When the estimator selects one of these crews and enters a production rate, the
computer can pull in many laborers and pieces of equipment and compute their
hours and total costs. The estimator can do in 5 sec what takes 2 or 3 min on
handwritten estimates, and there are no arithmetic errors.
Most companies should set up anywhere from a few to 20 or 30 standard
crews that can then be used over and over in future estimates. However, some
software does not allow modification of a crew, which might require the esti
mator to have hundreds of crews to account for every possible variation in the
crew. HeavyBid/Express allows the estimator to modify the crew where it is
used in the estimate; therefore, the same crew can be used in many places with
minor variations.
8RPF F -Set
CoayCtew |
8RSW S ee ' • Rotter
8TWT3 Water Truck 3000 G
lab o r Foreman
(laborer
0RGLL BoSet Operator
feasible.Codes; CQNC05 IS man core' crewt: R4VE08 f8 man paving c m /i' La$tChangg-...i
F IG U R E 25.11 I Setup for crews.
Chapter 25 Computer Estimating 471
The “pieces” field simply tells how many members are in the crew and thus
the number of hours per crew-hour. For example, 3 carpenters means that if the
crew is entered for 40 hr, there will be 120 hr of carpenter. The “pieces” field
should not require just whole numbers. For example, a foreman running two
crews could be put into each as 0.5 pieces. If one operator takes turns driving a
backhoe and dozer, the backhoe and dozer might be entered as 0.5 each, depend
ing on how equipment rent is being charged. Also, the equipment does not have
to have the same number of hours as the operators. For example, if there are 4
dozers and 1 is standby, there could be 4 dozers but only 3 operators.
Level 1—Biditem
Level 2—Activities
Level 3—Resources (Detail)
H e a v y B id /E x p r e s s R e v is io n 1 .0 - O V E R V IE W T u to ria l O v e r v ie w E s tim a te
E n te r E s tim a te M a in E n try
yiewot Estimate:
*A= Tutorial Overview Estimate T (Mobifeafen ------------------- I---------- raff fcs—
0 S3 ^: Mobilization__________ Cost | 3:25.625.42 L|. Cost: I S 5 3 5 5 ^2 0
Last Ch a w
F IG U R E 2 5 .1 2 i Mobilization biditem.
The code 55150 would typically be stored with a description, a unit of mea
sure, and possibly a crew code and production rate. Some systems also allow
linking materials to the activity code. For example, specifying activity 55405
might automatically pull into the estimate, the description, unit, 5 labor crafts, 2
pieces of equipment, pipe, and use the production rates to compute all quantities
and totals.
Most companies initially think these codes should come from the job cost
accounting system. This may not be a good choice, especially if nonestimators
established the job cost codes. The main objective of the estimator is to bid fast
and accurately, and to win profitable work. Typically only 10 percent of jobs
estimated are going to be won, therefore, the structure of an estimate or database
of activity codes should be developed to help the estimator, not necessarily the
project manager or accountant. When an estimator has 5,000 codes to choose
from, it is essential to be able to find one quickly.
For the jobs that are won, most companies do not have a one-to-one corre
spondence with cost codes on the job. For example, an estimate with 200 activ
ities might result in a job with only 100 cost codes. This has to do with the
impracticality of getting information correctly recorded on vague or minor items
compared to the ease with which an estimator can theoretically figure a cost for
anything.
Nevertheless, coordination between estimate and job cost code is desirable
so estimators can benefit from feedback on the job to improve their estimating
accuracy. It is also expected that the estimate can be translated into the starting
budget if the bid is successful and that process should be automated between the
estimating software and the job-costing software.
H e a y y B id /F ; x p ie s s R e v is io n 1 .0 O VKRVU W T u to n a ! O v e m e w K s tim a te
Eite £d» Setup Estimate Queiy Reports Summary loot: Vtfndow H -’Cl
Q <9 x
Tutorial Overview
:Actwiy In fa ;
456.00
juDC ~ ] |OrainageDew
90.0000
UH vnits/Ht
HU Hr/Unit
SU Shifts/Unit
i . .
Exc 40.53 HR
When using the calculator to make calculations for the estimate, it is a good
idea to put the factors of the calculation in the notes with unit labels because it
is difficult to check a total with no backup factors. HeavyBid/Express includes
three simple calculation routines (on the + /— icon) and writes the entire calcu
lation into the notes. More advanced software packages usually have interfaces
to Excel spreadsheets to document calculations and they work with varying
degrees of integration.
For each activity, there should be a way to select resources. In HeavyBid/
Express, it is the three icons at the bottom right represented by the worker, the
dozer, and the pipe. Crews are a shortcut to enter labor and equipment into the
activity. But in HeavyBid/Express those resources could also be entered the long
way by selecting from labor and equipment resources.
Most companies include the material in the activity where it is used, for
example:
Place pipe 500 lin f t
Pipelayer 80 mh
Laborer 40 mh
Operator 40 mh
Backhoe 40 hr
Pipe 500 lin ft <—
Some companies separate material activities from those containing labor
and equipment. This is an example:
Buy pipe 500 lin f t
Pipe 500 lin ft <—
Place Pipe 500 lin f t
Pipelayer 80 mh
Laborer 40 mh
Operator 40 mh
Backhoe 40 hr
The latter technique may be used because there are years of historical data
on unit costs that do not include material, or simply because the company wishes
to isolate high-risk labor items from low-risk material ones.
■■
—-
Last Change:
F IG U R E 2 5 .1 4 I Copy screen.
narios to see what happens. It is the responsibility of the estimator to know how
the tools being used work.
Another real time-saver in computer estimating is to set up a library estimate
containing fully worked-up biditems of work that an estimator typically uses,
and then copy them into future estimates. These biditems could have many
activities and thus not need to be looked up one-at-a-time from a database for
every new estimate.
A library can be built gradually over time. For example, an estimator may
wish to save 1 1 biditems out of 60 from the first computer estimate and copy
them into a library estimate. A library estimate is an estimate just like any other
except that it is used to collect parts of previous estimates. Any software program
that allows copying from other estimates can make use of this concept. If 8
biditems were saved after the second computer estimate, and 13 biditems from
the third computer estimate, there would then be 32 items from which an estima
tor could select for future estimates. In this manner, a contractor can quickly and
easily acquire an extensive library of items from which to build new estimates.
Another way in which a library of biditems can be used is to develop a pick
list of all possible activities within a biditem, even those that may be mutually
exclusive. This requires software that allows selecting from the activities with
out necessarily selecting the entire biditem, although software without this fea
ture can be used in this manner by copying too many activities and then delet
ing those that do not apply. The pick-list concept serves as a reminder of options
so something is not overlooked.
When anticipating a library that may have hundreds of items, there should
be a coding structure so estimators can quickly find the desired item. Also, sig
nificant figures must be considered because huge rounding errors can occur. For
example, an item with a unit of 1 cy might have a mathematical computation of
0.000449 units/hr and be rounded by the computer to 0.0004. This innocent-
looking rounding represents an 1 1 percent error, which results in a huge error
when copied into an estimate with 500,000 cy. The estimator might never know
this has happened because no one knew about the initial 0.000049 that the com
puter discarded. Normally the quantity in the library should be greater than 100
except items that are typically bid in low quantities.
CHECKING ESTIMATES
FOR REASONABLENESS
Some software systems may have a screen or report to assist in finding unusual
things about the estimate that could be an error. For example, Fig. 25.15 shows
a screen from HeavyBid/Express that shows some information about biditems.
Options like “Bid Price < Cost” help an estimator to quickly identify situations
that may be an oversight or mistake.
In addition to features provided specifically to highlight potential mistakes,
the estimator should cross-reference the totals in various places. For example,
the cost total on a cost report should equal the cost total on summary screens
and the bid total should be significantly more than the cost total. Some of these
478 Estimating Construction Costs
-Biditems--------- ;—
No. of Biditems:
f tL ^ L I Qi j
checks may appear trivial, but the better an estimator is at correlating numbers,
the more he or she is likely to eventually spot something that is wrong. Although
computers may seem infallible, the human factor must always be considered and
a careful check of the numbers is prudent.
INQUIRIES
In addition to speeding up estimating and reducing errors, a computerized esti
mating system should provide the estimator with quick answers to questions
about the estimate. These features will likely be quite different in software from
different vendors. Figure 25.16 shows an inquiry from HeavyBid/Express that
enables the estimator to study activities. The tabs at the top allow selecting the
productivity that is most meaningful to the person reviewing the estimate. As
well as displaying in biditem order, the display can be changed to activity order,
Chapter 2 5 Computer Estimating 479
which, if standard activity codes have been used, would result in like activities
being displayed together. This can be helpful to ensure that similar activities
have similar crews and production rates.
Inquiries are very easy to try because they require no entry and therefore
no chance of harming the estimate. Therefore the estimator should try all of the
tabs and buttons to see what information is available that may prove useful in
the future.
S a l f l ’ H 4 ► >! I X
— - --------------------- - Z J P j T - T
Bid Summary
Run Spread
BID PRICING
The end result of the estimate is a bid. Figure 25.18 shows a sample of a pricing
screen used to arrive at the final bid. Most unit price estimating systems will
have a screen very similar to this one, the main difference being the number of
features and amount of information available. HeavyBid/Express has a very sim
ple screen with the most basic information.
The “Balanced Price” column is the computer-generated price. The “Bid
Price” column is for any override price the contractor wishes to use. There are
at least five reasons contractors override the price:
1. The item finishes early and the contractor wants the cash flow.
2. The item quantity is expected to overrun or underrun and the contractor
will gain or lose indirect costs, addons, and markup depending on how the
item is priced.
Bid Pricing
Gal Total
----------
LastChanoe:
If the software system has a feature for both bid quantities and takeoff quan
tities, there will probably be two markup percents; one based on bid quantities,
and one based on takeoff quantities. For example, if the Bid% is 8.5 percent and
the Takeoff% is 4.2 percent, this indicates that if the contractor is paid the
owner’s quantities, the job will produce 8.5 percent markup. However, if the
takeoff quantities turn out to be correct, and payments are made on that basis,
the job will only produce 4.2 percent markup. Reality is usually somewhere in
between. The computer analysis is giving the estimator some assistance to help
in exercising judgment. In these situations, experience counts, and bidding truly
becomes an art.
Most unit-price estimating systems have a “cut and add” sheet for accu
mulating last-minute changes that are not to be entered directly into the cost
estimate, but rather to be added at the end as an adjustment to the total bid.
This was more valuable in the past when it might take hours to recompute an
estimate from new cost information. Since computers now allow estimators to
summarize bids in less than a minute, it is more common to make the changes
in the estimate and rerun the bid summary. However, there are still contrac
tors whose policy is to “freeze” the estimate several hours before the bid and
make all last-minute changes as cuts and adds. They do this to control the
changes that are occurring in an attempt to reduce mistakes in the confusion
of bid day.
For the person in charge of the bidding, it is extremely important to
experiment with the bid summary and pricing features of the computer soft
ware. Simple test estimates can be set up with two or three biditems with only
a few costs of different types, such as one laborer, one piece of equipment,
one material, etc. Simple numbers should be used that are easy to work with
mentally, such as 1, 10, 50, 100, etc. These numbers should be followed all
the way through the summary, testing the various spreading techniques that
seem applicable, and making several rounds of changes to see how the num
bers flow through the system. This should give the chief estimator confidence
in understanding what is happening without being confused by too many
numbers.
QUOTE SOLICITATION
More advanced estimating systems may have a feature to help the estimator to
solicit bids from subcontractors and suppliers. Figure 25.19 is an example from
Heavy Bid/Advanced showing a screen that assists in selecting the suppliers
for each type of work, for example, striping subcontractors, and then faxing or
e-mailing them invitations to bid on the job.
This particular screen also has a place to indicate whether each contacted
company plans to bid. It is important to determine in advance the companies that
are expected to provide quotes as bid day approaches. If the estimator is not sure
that several quotes will be received for every class of work, then additional com
panies must be solicited for bids.
Chapter 25 Computer Estimating 485
H e a v y B id S ta n d a lo n e - S O U T H W A Y - S o u th la n d F r e e w a y
r^i^i i r«
Fite £dit Setup Estimate Query Reports Summary Subsystems
Addendum Letter
liJ________ _________________________________
on popupsand reports.
TAKING QUOTES
Most unit price bids are for state, city, and county projects that have a definite
time the bid must be submitted, and in state bids, there may be dozens of projects
whose bids are due at the same time. Traditionally, subcontractors and some sup
pliers wait until the last few minutes to supply their best prices to the contractors
486 Estimating Construction Costs
to prevent the contractors from having enough time to call other subcontractors
for better prices.
To process many quotes in a short period of time, a good procedure and
computer system for handling the quotes is essential to ensure the best prices
make it into the system and are reflected in the bid. Taking quotes from sub
contractors and suppliers is complicated by these factors:
1. Quotes are coming in via phone, fax, and e-mail, and possibly for many
jobs at once.
2. The fax machine or machines may be constantly busy and suppliers keep
getting a busy signal.
3. The e-mail coming in may get delayed because of traffic on the Internet.
4. Some suppliers do not quote all of the items and the missing items must
be obtained from someone else in order to be able to make useful
comparisons.
5. Some suppliers quote several classes of items, such as electrical,
mechanical, guardrail, and signage. Often they are low on one category,
and not low on the total, but will not do the one category of work without
the others. This complicates figuring out what combination is both low,
and will be agreed to by the suppliers.
6 . The contractor may be forced to select suppliers that are not low to meet
minority requirements.
7. Sometimes all of the quotes seem too high and the estimator has to make
an estimate at the last minute of what it would cost to do the work
themselves.
Figure 25.20 shows a screen from HeavyBid/Advanced that gives an
overview of the quote status in several quote classes at once. An overview such
as this is helpful to quickly see if a new quote coming in should be considered,
or quickly set aside to go onto the next quote.
As the estimator decides on suppliers to use, there should be a mechanism
to indicate to the system that they have been selected, and if minority goals are
applicable, there should be a way to instantly see the status of the bid with
respect to that goal. For suppliers with incomplete quotes, there must be a way
to supply a “plug” price for missing items so that their quotes can be compared
with those of the other suppliers.
Q u o te Sum m ary (P a g e 1 )
Steel Fab Co. $553,494 T j (South East Cutting $12,779 Triple A Sign D
Rebar Install Inc. $572,478 | Mid State Saw Cut $15,294 J.S. & Sons Signs $3,510
Iron ManRebar $591,646 — I SawCutTechnolo $16,467
Steelerslnc. $532,527 »|
mm.
i
Page Qrjer | More M o
Regardless of the method used for submitting bids, the estimator should test
the bidding procedure fo r each particular bid at least a day prior to bid day. The
estimator should print out the bid, even if the prices are still zero, and then com
pare the computer printout to the official bid document to see that the bid that
will be submitted looks exactly like the bid in the owner’s specifications. If there
is anything unusual, it is possible to investigate as long as there are several days
left prior to the bid. If the second-place bidder wants the job after seeing every
one else’s bid, they usually study the winning bid for irregularities in the hope
of getting the winning bid disqualified.
If the bid is submitted in electronic form on disk, a copy of the disk should
be made and used to run through the procedure to ensure it works. It may be
more difficult to test an electronic bid on the Internet, but if the bid can be sub
mitted and then revised later, the early bid should be submitted as early as pos
sible to constitute a test of the procedure.
Estimating Construction Costs
If not, select “Start,” “Run Program,” and for program type “D:Setup” and OK
assuming that the CD drive is drive “D.” Then select the “Install HeavyBid”
option, as shown in Fig. 25.22, and follow the remaining installation directions.
HeavyBid/Express will not conflict with any other versions of HeavyBid
that may already be on the computer and is actually used by contractors owning
full HeavyBid systems as a training device for new estimators.
PROBLEMS
Before attempting the following problems, the reader should become familiar with
HeavyBid/Express by going through the tutorial that is on the CD that accompanies
this book. The example problem on the disk will assist the user with the features of the
software and assist in performing the following problems.
490 Estimating Construction Costs
Table 25.1 provides historical production rates for various types of work for
use in Prob. 25.2 and 25.3. The reader should use LF in lieu of lin ft and all capi
tal letters, such as CY and SY, when entering data into the software. The pro
duction rates given as quantities per hour refer to the crew-hours of the standard
crews of Prob. 25.1.
Concrete— structural
Formwork—walls 4.50 sf/mh
Formwork— slabs 8.25 sf/mh
Formwork—footings 12.00 sf/mh
Formwork— chamfer strip 50.00 lin ft/mh
Install embedded misc. metal 1.00 hr/piece
Reinforcing steel—walls 125.00 Ib/mh
Reinforcing steel— slabs 190.00 Ib/mh
Reinforcing steel—footings 175.00 Ib/mh
Place concrete—walls 30 cy/hr
Place concrete— slabs 45 cy/hr
Place concrete—footings 15 cy/hr
Concrete paving
Set and strip 6-in. forms 120 lin ft/hr
Set and strip 9-in. forms 110 lin ft/hr
Reinforcing mesh 50 sy/mh
Slip formed curb—9 in. x 18 in. 300 lin ft/sh
Place stone base 80 ton/hr
Place and finish 6-in. concrete paving 130 sy/hr
Place and finish 9-in. concrete paving 120 sy/hr
Clean const, jt. (laborer only) 10.00 sf/mh
Spray cure surface 100.00 sf/mh
Rub and finish walls 0.02 mh/sf
Earthwork
Site clearing 1 50 ac/sh
Bulk excav.—over 100,000 cy 175.00 cy/hr
Bulk excav.— under 100,000 cy 140.00 cy/hr
Structural excavation 80.00 cy/hr
Place and compact fill (bulk) 125.00 cy/hr
Place and compact fill (structures) 50.00 cy/hr
Hand place and compact fill 10.00 cy/hr
Fine grade for paving 300.00 sy/hr
Rip rap— hand placed 1.25 mh/ton
Drainage (includes average trenching and backfill)
Install 12-in. RCP orCMP 200 lin ft/sh
Install 15-in. RCP orCMP 180 lin ft/sh
Install 18-in. RCP orCMP 170 lin ft/sh
Install 24-in. RCP orCMP 150 lin ft/sh
Install 36-in. RCP orCMP 120 lin ft/sh
Install 48-in. RCP orCMP 100 lin ft/sh
Install precast inlet 2 hr/piece
Perforated drains (install pipe only) 50 lin ft/hr
You must also set up the standard summary instructions in the SUMMARY SUMMARIZE section.
Chapter 25 Computer Estimating 491
Labor Resources:
Note: The payroll burden is 23.55 percent inclusive of workmen’s compensation and there is a health insurance
cost of $1.95 per man-hour (except for the foremen and superintendents who have expanded coverage costing
$2.75 per man-hour). Overtime, if required, is costed at 15 times the base rate for hours worked over 40 hr/week.
Equipment Resources:
(Continued)
Standard Crews:
Crew members may be selected from the appropriate list by entering the number of
pieces required. (All equipment and trucks must have appropriate operator or driver
included in crew.)
(Continued)
(Continued)
( Continued)
Markup Instructions:
Item Markup
Labor 25%
Materials 5%
Equipment 10%
Subcontracts 5%
25.2 Millenium Developers is adding an additional access road between two sections
of their Shady Acres Project. The road will join existing pavements at both ends.
Excavation and preparation of the subgrade have been performed by others.
Prepare a computer estimate for the project. Use the resources and crews
from ESTMAST in Prob. 25.1. Use the labor and equipment resources, crews,
material and subcontract prices, standard markup percentages, and follow the
Company Bidding Rules that were established in the setup of ESTMAST in
Prob. 25.1. Also use the historical production rates in Table 25.1. Assume a
7-week duration for the job. The project owner is a private client and does not
require a Payment and Performance Bond. Project information and the scope of
work to be estimated are detailed next.
Project Information:
Estimate No.: E-001
Estimate Name: New road and drainage—Shady Acres Phase II
Owner: Millenium Developers, Inc.
Engineer: Lanevco Partners, Inc.
Bid Date: 2 weeks from today
Scope of Work:
Paving dimensions 2,560 ft long X 27 ft wide (exclusive of curb) x 9 in. thick
Road details Reinforcing mesh (6 x 6, W2.9) and 3500 psi concrete
Surface to be sprayed with concrete curing compound
Contraction joints Saw cut across width at 15 ft center-to-center along the entire length
Curb 9 in. wide x 18 in. high along both edges, nonreinforced
Base course 6 in. crushed stone
Drainage under road Corrugated metal pipe - 2 each x 18-in. dia. and 3 each x 24-in. dia.
All culverts are 32 lin ft long with flared end sections at each end
Landscaping Grassing to be included along 30 ft on both sides for the entire length
Grass to be watered for 2 months after installation
Biditems:
Code D escription Q uantity Unit
10 Mobilization 1 Is
20 Furnish and place aggregate base course ?? cy
30 Furnish and place 9-in. reinforced concrete paving ?? sy
40 Saw cut construction joints ?? lin ft
50 Concrete curb ?? lin ft
60 Drainage culverts under roadway 1 Is
70 Landscaping (grassing) ?? sy
25.3 Radio station WARP is adding a new transmitter tower and has asked your Tri-
State Constructors to build the concrete base and anchor blocks. Prepare a com
puter estimate for the project. Use the labor and equipment resources, crews,
material and subcontract prices, standard markup percentages, and follow the
Company Bidding Rules that were established in the setup of ESTMAST in
Prob. 25.1. Also use the historical production rates in Table 25.1. Assume a
3-week duration for the job. The project owner is a private client and does not
require a payment and performance bond. Project information and the scope of
work to be estimated are detailed next.
Project Information:
Scope of Work:
All footings are concrete cast directly on the excavated subgrade. To allow for formwork, the
excavations need to be 5 ft larger than the dimensions of the concrete blocks. The top of concrete
is even with the surrounding ground level. Each footing is cast monolithically and receives a spray-
on curing compound on the upper surface and on all four sides. Granular backfill is placed around
the footings.
Tower footing— 1 each at 24 ft wide x 24 ft long x 6 ft deep with 16 steel embeds at 125 lb each
with an average of 100 Ib/cy of grade 60 reinforcing steel.
Anchor blocks— 4 each at 18 ft wide x 18 ft long x 5 ft deep with 4 steel embeds at 175 lb each
with an average of 95 Ib/cy of grade 60 reinforcing steel.
Biditems:
10 Mobilization 1 Is
20 Site clearing 3 ac
30 Excavate for anchor blocks and footing ?? cy
40 Concrete anchor blocks and footing ?? cy
50 Furnish and install steel embeds ?? lb
60 Hand place granular fill and compact ?? cy
498
MAINTENANCE FACILITY PROJECT
PROJECT OWNER'S NAME
CITY, STATE
ARCHITECT-ENGINEER
INDEX of SHEETS
AB C D E S IG N FIRM
A RCHITECTURE - ENGINEERING SERVICES
3456 S TR E E T COVER
C ITY, STATE ZIP
CIVIL C1 SITE PLAN
CONTACT: A rch ite c t / Engineer Name
PHONE NUMBER
ARCHITECTURAL A1 INTERIOR ELEVATION
A2 INTERIOR ELEVATION
A3 EXTERIOR ELEVATION
A4 SECTIONS
BUILDING CODES A5 SECTIONS
A6 FOUNDATION PLAN
T h i s p r o j e c t h a s b e e n d e s i g n e d in
a c c o r d a n c e with:
MECHANICAL M1 HVAC FLOOR PLAN
19 96 BO CA N a t io n a l B u i l d i n g Co de, PLUMBING P1 PLUMBING PLAN
1995 I n t e r n a t i o n a l P l u m b i n g Co de ELECTRICAL E1 ELECTRICAL POWER
w i t h 19 96 S u p p l e m e n t ,
1 996 In te r n a tio n a l M e cha n ica l Code,
E2 ELECTRICAL LIGHTING
1 996 N a t i o n a l E l e c t r i c a l Co de,
1994 Li fe Safety Code.
All w o r k s h a ll b e p e r f o r m e d in
a c c o r d a n c e w ith these codes.
500
PROJECT
O W N E R ’S
N A ME
STREET ADDRESS
LOCATIONS *5HOWN.
COMCRC'E
----- ADi) fi 701F ± . 2 "c SC H .80, PERIMETER P i PE FENCING
tV 2x4 w w r s h e e p f e n c e , to m a t c h e x is t in g f e n c in g
THAT RUNS ALONG SOUTH EDGE OF PROPERTY.
TOP R A O -4 |4 8 " ABOVE CROUND, WITH 6 ’ POSTS. l O '- O " O.C .
luesroNE b ^TULCOW
ITH‘C'U
'NCW
LTT
E A C H 'P ^S X TO BE SET IN 8 "e H 0 l£ ._ 2 -^ ’ DE-E-FH-----------
PROVIDE ALUMINUM CHANNEL DOUBLE GATES AT BOTH ENTRANCE
sr»eiii2£o
UNOl^T'JRB £D
1.^:% 'Z'-l ALTERNATE PRICING
BASE BID - 6" DEEP - 1 - 1 / 2 " CRL
EXISTING GASVlNE
ALTERNATE #1 - i" ASPHALT OVER 6" DEEP 1 'SHER
ALTERNATE #2 - 6’ CONCRETE OVER 5" OE£P
WATER LINE
6" THICK CONCRETE APRON
GATE W/ 6x6 !.4»i 4 WWF
(TYPICAL 4 L0^5±93?=?T
.0. C u lv ert
; xp an SiO JOINT
REFER D
Sh a p e g r a d e toy
PROVIDE POSITIVE D
AWAY FROM CULVER'
!VI«EEW 6 SANIT>
SEWER -EXISTINI
POWER POLE
NEW 10 "0 .D . CULVERT
B ENC
IRGINIAAVENUE BUILDING
as*winc
1" Away
Overhead Door Slope Grade Away From From All Doors
/ f v \ WEST ELEVATION Building at Minimum of ‘NEAST ELEVATION
IJL f) SCALE: 3/32 5 l'-0" ) SCALE: 3/32 = r-0"
6" in 10'-0"
San. Vent
(Typical)
H
W
1 co
>1
Motorized Dampers
w/ Metal Louvers Overhead Door
jft h
hQ <
QQh
NORTH ELEVATION
\f* 7 SCALE: 3/32 = l'-O"
A/A-4 Motorized Dampers
IS
iI s<
PROJECT
O W N E R ’S
NAME
STREET ADDRESS
PHONE NUMBER
SET T OP OF F L O O R D R A I N S
IN A N I M A L R O O M # 101A,
AT 9 1 6 . 2 5 E L E V AT I ON
( 15 DRAI NS )
C O N C . SLAB ( M I N I MU M )
W / # 3 B AR S @ 1 8 ” O. C.
/T \F O U N DATI ON PLAN B O T H W A Y S ON 4 " S A N D
\ / "V / s C A L E : 3 / 3 2 " « r - 0 '
\PROJECT3\BUILDINC\e3r\0RAWINGS\BASCPKN OWG
A-6
APPENDIX FIGURE 7 I Foundation Plan (Architectural Drawing A-6)
APPENDIX FIGURE 8 I HVAC Plan (Mechanical Drawing M -1)
507
508
0MPW1R-EL-
1
U1
«
Ip
Saf e
E-2
BID DOCUMENTS
FOR:
MAINTENANCE FACILITY PROJECT
1234 STREET
CITY, STATE
SET NUMBER
512 Estimating Construction Costs
INDEX
DIVISION 2—SITEWORK
SECTION 02200—EARTHWORK 1-4
SECTION 02282—TERMITE CONTROL 1-2
SECTION 02511—HOT-MIXED ASPHALT PAVING 1-4
DIVISION 3—CONCRETE
SECTION 03300—CAST-IN-PLACE CONCRETE 1-6
DIVISION 4—MASONRY
SECTION 04200—UNIT MASONRY 1-9
DIVISION 9—FINISHES
SECTION 09250—GYPSUM BOARD ASSEMBLIES 1-2
SECTION 09650—RESILIENT FLOORING 1-2
SECTION 09678—RESILIENT WALL BASE 1
SECTION 09900—PAINTING 1-2
DIVISION 10—SPECIALTIES
SECTION 10155—TOILET COMPARTMENTS 1
SECTION 10500—METAL LOCKERS 1
SECTION 10522—FIRE EXTINGUISHERS AND
WALL BRACKETS 1
SECTION 10800—TOILET AND BATH ACCESSORIES 1-2
DIVISION 12—FURNISHINGS
SECTION 12346—WOOD LABORATORY CASEWORK
AND FIXTURES 1-10
DIVISION 15—MECHANICAL
SECTION 15100—PLUMBING 1-3
SECTION 15500—HEATING, VENTILATING, AND
AIR CONDITIONING 1-2
DIVISION 16—ELECTRICAL
SECTION 16100—ELECTRICAL 1-4
* * * * * * END OF IN D E X ******
514 Estimating Construction Costs
OWNER
By _________Chairman’s Name__________
Chairman
1st Publication: January 29, 20XX
2nd Publication: February 5, 20XX
The OWNER invites bids on the referenced project on the Bid Form included in
the Contract Documents, all blanks of which must be appropriately filled in. Bids
will be received by the Owner at the time and place set forth in the Advertisement
for Bids and then at said place be publicly opened and read aloud.
The Owner may reject any bid not prepared and submitted in accordance
with the provisions hereof and may reject any and all bids or may waive any
minor informalities or irregularities in the bidding.
Bids received prior to the time of opening will be kept unopened in a secure
place. The officer whose duty it is to open them will decide when the specified
time has arrived, and no bid received thereafter will be considered. No respon
sibility will attach to an officer for the premature opening of a bid not properly
addressed and identified. Unless specifically authorized, telegraphic, oral, fa c
simile or telephonic bids will not be considered, but modifications by telegraph
or facsimile of bids already submitted will be considered if received prior to the
hour set for opening.
BID SUBMISSION:
Each bid must be submitted in a sealed envelope bearing on the outside the
name of the bidder, his address, and the name of the project for which the
bid is submitted, and addressed as specified in the Bid Form.
If forwarded by mail, the sealed envelope containing the bid must be
enclosed in another envelope addressed as specified in the Bid Form.
The Owner shall not be responsible for failure by the postal service to
timely deliver any bid.
SUBCONTRACT:
Any person, firm, or other party to whom it is proposed to award a subcontract
under this contract must be acceptable to the Owner.
TELEGRAPHIC MODIFICATION:
Any bidder may modify his bid by telegraphic or facsimile communication at
any time prior to the scheduled closing time for receipt of Bids, provided such
516 Estimating Construction Costs
WITHDRAWAL OF BIDS:
Bids may be withdrawn on written or telegraphic or facsimile request received
from bidders prior to the time fixed for opening. Negligence on the part of the
bidder in preparing the bid confers no right for the withdrawal of the bid after it
has been opened.
BASIS OF BID:
The bidder must include all unit cost items and all alternatives shown on the Bid
Forms; failure to comply may be cause for rejection. No segregated bids or
assignments will be considered.
QUALIFICATION OF BIDDER:
The Owner may make such investigation as he deems necessary to determine the
ability of the bidder to perform the work, and the bidder shall furnish to the
Owner all such information and data for this purpose as the Owner may request.
The Owner reserves the right to reject any bid if the evidence submitted by, or
investigation of, such bidder fails to satisfy the Owner that such bidder is prop
erly qualified to carry out the obligations of the contract and to complete the
work contemplated therein. Conditional bids will not be accepted.
BID SECURITY:
Each bid must be accompanied by a certified check made payable to the Owner
in the sum of not less than five percent (5% ) of the base bid, plus add alternates,
if any, or a bond with sufficient sureties, to be approved by Owner, in a penal
sum equal to five percent (5% ) of the base bid, plus add alternates, if any, and
naming the Owner as obligee, or for any bid of $2,000,000 or less an irrevoca
ble letter of credit containing such terms as may be prescribed by the Owner and
issued by a financial institution insured by the Federal Deposit Insurance
Corporation or the Federal Savings and Loan Insurance Corporation for the ben
efit of the state, on behalf of the Owner in an amount equal to five percent (5% )
of the bid. Such security shall be returned to all except the three (3) lowest
responsible bidders within three (3) days after the opening of the bids, and the
remaining security within three (3) days after the Owner and the bidder to whom
the contract is awarded have executed the contract.
Appendix Example Bid Documents 517
BID DEFAULT:
If the successful bidder fails or refuses to enter into a contract as required by the
Owner or fails to provide the required bonds and insurance to the Owner, within
the time limited, said bidder shall forfeit to the Owner the difference between the
low bid of said defaulting bidder and the amount of the bid of the bidder to
whom the contract is subsequently awarded and the cost, if any, of republication
of Notice to Bidders and all actual expenses incurred by reason of the bidder’s
default. The amount of said forfeiture shall not exceed the total amount
deposited as security and shall be forfeited to the Owner as liquidated damages
and not as a penalty.
Negligence on the part of the bidder in preparing or submitting the bid con
fers no right for the withdrawal of the bid after it has been opened and shall not
constitute a defense to or excuse from the requirements of this provision.
TIME OF COMPLETION:
Bidder must agree to commence work on or before a date to be specified in a
written “Notice to Proceed” of the Owner and to substantially complete the proj
ect within 180 consecutive calendar days thereafter.
POWER-OF-ATTORNEY:
The Attomey-in-Fact who signs bid bonds or contract bonds must file with each
bond a certified and effectively dated copy of the Power-of-Attomey.
METHOD OF AWARD:
If the order of acceptance of alternates is not a factor in determining the low bid
der, the Owner may accept any or all alternates in any order of preference. If the
acceptance or rejection of alternates or the order of acceptance of alternates is a
factor the low bidder will be determined by the application of alternates in the
order listed on the proposal form, at the time bids are opened, to the extent that
the amount of budgeted funds will permit. After the low bidder has been so
established, the Owner may elect to revise the extent or order of acceptance of
alternates or may adjust the amount of budgeted funds so long as the selection
of the low bidder is not affected.
The Owner reserves the right to reject any and all bids.
OBLIGATION OF BIDDER:
At the time of the opening of bids, each bidder will be presumed to have
inspected the site and to have read and to be thoroughly familiar with the plans
and contract documents (including all addenda). The failure or omission of any
bidder to examine any form instrument or document shall in no way relieve any
bidder from any obligation in respect of his bid.
Bidders shall carefully examine the documents and the construction site to
obtain first-hand knowledge of the existing conditions, make actual examination
of site, existing construction, and construction conditions prior to submission of
bids. Examination of conditions includes sizes, quantities, functions, etc.
Examination prior to bidding is the Contractor’s responsibility.
Coordinate requests for examination through: Tim Mitchel, Ph. AC &
Number
on behalf of the Owner in an amount equal to the full contract amount. Letters
of credit may not be substituted for bonds required by contracts in excess of
$ 100,000.
SURETY:
The Surety Company required to execute all bonds shall be authorized to trans
act business in the State in accordance with Title XX, State Statutes, Sections
481 et. seq.
MINORITY STATUS:
The contractor shall indicate on the bid form if a claim is being made for minor
ity bid preference in accordance with the State Minority Business Enterprise
Assistance Act (Title XX, Section YY of the State Statutes). Such a claim, if
desired, must be indicated on the bid form at the time of receipt of bids. Claims
for preference after receipt of bids will not be allowed.
OWNER
1234 Street, Suite 200
City, State Zip Code
4. Failure of the bidder to execute and submit the following forms with his
proposal will result in disqualification of his bid:
a. Affidavit of Nondiscrimination, Nonsegregated Facilities,
Noncollusion, and Business Relationships.
b. Bid Security.
c. Power of Attorney (with Surety Bonds).
522 Estimating Construction Costs
Place:
Date:
PROPOSAL OF
Gentlemen:
The bidder, in compliance with your invitation for Bids for the:
MAINTENANCE FACILITY PROJECT
1234 STREET
CITY, STATE
having examined the plans and specifications with related documents and the
site of the proposed work, and being familiar with all of the conditions sur
rounding the work, including the availability of materials and labor, hereby
agree to furnish all labor, materials, equipment and supplies, and to perform the
work required by the project in accordance with the contract documents, within
the time set forth in Instructions to Bidders, and at the prices stated below. These
prices are to cover all expenses incurred in performing the work required by the
contract documents, of which this bid is a part.
Bidder acknowledges receipt of the following addenda:_______________ .
All Bid amounts shall be shown in both WORDS and FIGURES. In case of
discrepancy, the amount shown in words will govern.
BASE BID:
Bidder agrees to perform all of the work described in the plans and specifica
tions as being in the Base Bid for the sum of:______________ Dollars.
$______________________
The Bidder agrees to perform all of the work described in the Drawings and
Specifications, which has been designated as Alternate Bids. Alternate Bids
shall be add amounts to the Base Bid. Changes shall include any modifications
of the work or additional work that the Bidder may require to perform by reason
of Owner’s acceptance of any or all Alternate Bids.
Appendix Example Bid Documents 523
ALTERNATE NO. 1 :
Add 3" thick Type “C” asphalt paving to compacted crushed limestone as shown
on Sheet C-l.
ADD: $______________________ .
________________________ Dollars.
ALTERNATE NO. 2:
Added cost difference to provide 6 " thick reinforced concrete paving in lieu of
asphalt paving as shown on Sheet C-l.
ADD: $_______________________.
________________________ Dollars.
The Bidder hereby agrees to commence work under this contract on or before a
date to be specified in a written “Notice to Proceed” by the Owner and to sub
stantially complete the project within 180 consecutive calendar days there
after.
The Owner reserves the right to reject any and all bids.
Bidder agrees that this bid shall be good and shall not be withdrawn for a
period of sixty (60) calendar days after the opening thereof.
In the event a contract is awarded by the Owner to the Successful Bidder, it
shall be executed within thirty (30) days. TheBidder shall return with his exe
cuted contract the Performance Payment Bond, Statutory Bond and Warranty
Bond as required by the Supplementary Conditions.
If the successful bidder fails or refuses to enter into a contract as required by
the Owner or fails to provide the required bonds and insurance to the Owner,
within the time limited, said bidder shall forfeit to the Owner the difference
between the low bid of said defaulting bidder and the amount of the bid of the
bidder to whom the contract is subsequently awarded and, the cost, if any, of re
publication of notice to bidders and all actual expenses incurred by reason of the
bidder’s default. The amount of said forfeiture shall not exceed the total amount
deposited as security and shall be forfeited to the Owner as liquidated damages
and not as a penalty. Negligence on the part of bidder in preparing or submitting
the bid confers no right for the withdrawal of the bid after it has been opened and
shall not constitute a defense to or excuse from the requirements of this provision.
(SEAL) if bid
is by Corporation Respectfully submitted,
By: __________________
Title
FEI/SS Number____________________
524 Estimating Construction Costs
STATE OF ______________________ )
COUNTY OF ______________________ )
The undersigned, of lawful age, being first duly sworn upon oath, deposes and
states that I am the duly authorized agent of the bidder submitting the attached
bid and am authorized by said bidder to execute the within affidavit.
I further swear that if said bidder is successful on this project, it will not dis
criminate against anyone in employment or employment practice because of
race, color, religion, sex, ornational origin. The undersignedfurther statesthat
said bidder will comply with all federal and state lawsand executive orders con
cerning the subject of nondiscrimination.
The undersigned further states that said bidder does not and will not main
tain or provide for its employees any segregated facilities as defined in the
instructions to bidders for this project at any of its establishments, nor permit its
employees to perform their services at any location under its control, where seg
regated facilities are maintained. The bidder further agrees that a violation of
this certification is a breach of the equal opportunity clause of this bid and any
contract awarded pursuant thereto. Said bidder further agrees that (except where
it has obtained identical certification from proposed subcontractors for specific
time periods), it will obtain identical certifications from proposed subcontractors
prior to the award of subcontracts exceeding Ten Thousand Dollars ($10,000)
which are not exempt from the provisions of the equal opportunity laws, and that
said bidder will retain such certifications in its files.
The undersigned further states that, for the purpose of certifying the facts
pertaining to the existence of collusion among bidders and between bidders and
state officials or employees, as well as facts pertaining to the giving or offering
of things of value to government personnel in return for special consideration in
the letting of any contract pursuant to the bid to which this statement is attached;
that I am fully aware of the facts and circumstances surrounding the making of
the bid to which this statement is attached and have been personally and directly
involved in the proceedings leading to the submission of such bid; and that nei
ther the bidder nor anyone subject to the bidder’s direction or control has been
a party: (a) to any collusion among bidders in restraint of freedom of competi
tion by agreement to bid at a fixed price or to refrain from bidding; nor (b) to
any collusion with any state official or employee as to quantity, quality or price
in the prospective contract, or as to any other terms of such prospective con
tractor; (c) in any discussions between bidders and any state official concerning
exchange of money or other thing of value for special consideration in the let
ting of a contract.
526 Estimating Construction Costs
The undersigned further states that any partnerships, joint ventures, or other
business relationships that are not in effect, or existed within one ( 1 ) year prior
to this statement, with the architect, engineer or other party to this project; or any
such business relationships between any officer or director of the bidder and any
officer or director of the architectural or engineering firm or other party to the
project are described as follows:
NAME OF BIDDER:
BY: _____________
Affiant
as Principal, an d _____________________________________________________
as Surety, authorized to transact business in the State, are hereby held and firmly
bound unto Owner, in the penal sum o f_______________________________ for
the payment of which, well and truly to be made, we hereby jointly and sever
ally bind ourselves, our heirs, executors, administrators, successors and assigns.
Principal
Surety
SEAL B Y __________________________________
Attomey-in-Fact
Dollars (. .)
as stated in the Contractor’s base proposal as attached hereto and made a part of
these contract documents and all extra work in connection therewith, under the
terms as stated in the General and Supplementary Conditions of the Contract,
and at his (its or their) own proper cost and expense to furnish all the materials,
machinery, tools, superintendence, labor, insurance, and other accessories and
services necessary to complete the said project in accordance with the conditions
and prices stated in the Bid Form, the General Conditions, and Supplementary
Conditions of the Contract, the plans which include all maps, plats, blueprints,
and other drawings and printed or written explanatory matter thereof, the speci
fications and contract documents for:
as prepared by ABC Design Firm of 3456 Street, City, State, Zip, herein enti
tled the Architect, and as enumerated in Para. 4.1 of the Supplementary
Conditions, all of which are made a part hereof and collectively evidence and
constitute the contract.
TIME OF COMPLETION
The Contractor hereby agrees to commence work under this Contract on or
before a date to be specified in a written “Notice to Proceed” of the Owner, and
to substantially complete the project within 180 consecutive calendar days
thereafter.
Appendix Example Bid Documents 529
PAYMENTS
The Owner agrees to pay the Contractor from current funds for the performance
of the Contract, subject to the additions and deductions, as provided in the
General Conditions of the Contract and to make payments on account thereof as
provided in the General Conditions.
IN WITNESS WHEREOF, the parties to these presents have executed this
Contract in eight ( 8 ) counterparts, each of which shall be deemed as original, in
the day and year first above mentioned.
ATTEST:
By:_____________________________ B y:_____________________________
S E A L : _________________________________________
Contractor
ATTEST:
By:_____________________________ By:_____________________________
Corporate Secretary
FEI/SS Number________________________
SECTION 00007—AFFIDAVIT
(The successful bidder must submit this affidavit with the contract)
STATE O F ______________________)
COUNTY O F ____________________ )
The undersigned, of lawful age, being first duly sworn upon oath, deposes and
states that I am the duly authorized agent of the contractor under the contract
which is attached to this statement, for the purpose of certifying the facts per
taining to the giving of things of value to government personnel in order to pro
cure said contract; that I am fully aware of the facts and circumstances sur
rounding the making of the contract to which this statement is attached and have
been personally and directly involved in the proceedings leading to the procure
ment of said contract; and that neither the contractor nor anyone subject to the
contractor’s direction or control has paid, given or donated or agreed to pay, give
or donate to any officer or employee of this State any money or other thing of
value, either directly or indirectly, in the procuring of the contract to which this
statement is attached.
Contract and any amendments thereto, less the amount properly paid by Owner
to Contractor.
Any suit under this Bond must be instituted before the expiration of three
(3) years from the date on which final payment under the contract falls due.
No right of action shall accrue on this Bond to or for the use of any person
or corporation other than the Owner named therein or the heirs, executors,
administrators or successors of Owner.
{SEAL:} ___________________________________________
Name of Principal
ATTEST:
By:_____________________________ By:______________________________
Title:____________________________Title:____________________________
****************************************************************
{SEAL:}
Name of Surety
ATTEST
B y:____ By:----
Attomey-in-Fact
Title:__ Title:____________________
Address
Telephone:
(To be used this State as required by Title 61, State Statutes, Sections 1 and 2 as
amended.)
(1 )_______________________________________________________________
(2 ) _________________________________________________ , as principal, and
(3 ) ______________________________________ ___________ , a Corporation,
organized under the laws of the State of _________________________and
authorized to transact business in this State, as Surety, are held firmly bound
unto the OWNER in the penal sum o f ______________ Dollars ($___________)
lawful money of the United States, for the payment of which sum well and truly
be made, said Principals and Surety bind themselves, their heirs, administrators,
executors, successors and assigns, jointly and severally, by these presents.
{SEAL:} ___________________________________________
Name of Principal
ATTEST:
B y:_____________________________ B y:_____________________________
Title:____________________________Title:____________________________
****************************************************************
{SEAL:} ___________________________________________
Name of Surety
ATTEST:
By:_____________________________ By:____________________________
Attomey-in-Fact
Title:____________________________ _____________________________
Address
Name:_________________________
Address:_______________________
Telephone:____________________
WHEREAS, the conditions of this obligation are such that said principal
has, by a certain contract between ____________________________ and the
OWNER, dated th e ______ day o f ____________________ , A.D., 20_____
agreed to construct MAINTENANCE FACILITY PROJECT, located at
1234 Street, City, State.
AND WHEREAS, Principal and Surety agree to correct any defects in
workmanship or materials appearing during a period of one ( 1 ) year from
the date of acceptance of the project as complete by the OWNER.
NOW THEREFORE, said ______________________________________,
Principal, agrees for a period of one (1 ) calendar year from and after com
pletion of said project and acceptance by OWNER to perform all acts nec
essary to correct any and all defects appearing in workmanship and materi
als and to bear the costs of all labor and materials, including the prime
contractor and all subcontractors, which may develop during the term of this
bond.
SIGNED, SEALED AND DELIVERED the day and year first above written.
{SEAL:} __________________________________________
Name of Principal
ATTEST:
By:_____________________________ By:________________
Title:____________________________Title:.
{SEAL:}
Name of Surety
ATTEST:
By:____________________________ _ By:___
Attomey-in-Fact
Title:____________________________ ______________________
Address
Address:_______________________
Telephone:
STATE OF _____________________ )
COUNTY OF _____________________ )
Affiant
Surety Company
Attomey-in-Fact
(SEAL)
The following supplements modify the “General Conditions of the Contract for
Construction,” AIA Document A201, Fourteenth Edition, 1987. Where a portion
of the General Conditions is modified or deleted by these Supplementary
Conditions, the unaltered portions of the General Conditions shall remain in effect.
REFER ARTICLE 1:
Add the following to subparagraph 1.1.1:
ENUMERATION OF DRAWINGS, SPECIFICATIONS AND ADDENDA
Following are the Drawings and Specifications, which form a part of this con
tract:
Drawings:
Cover
C l Site Plan
A1 Floor Plan
A2 Interior Elevations
A3 Exterior Elevations
A4 Building Sections
A5 Building Sections
A 6 Foundation Plan
PI Plumbing Plan
M l HVAC Plan
E l Electrical Power Plan
E2 Electrical Lighting Plan
Contract Documents:
Index to Specifications
Advertisement for Bids
Instructions to Bidders
Bid Form
Affidavit of Nondiscrimination, Nonsegregated Facilities, Noncollusion, and
Business Relationships
Bid Bond
Contract
Affidavit
Performance Payment Bond
Statutory Bond
Warranty Bond
Release of Liens Affidavit
Certificate of Approval
AIA General Conditions
Supplementary Conditions (where applicable)
Appendix Example Bid Documents 541
Specifications:
Divisions 1-16, Sections as indicated on the Index.
Addenda:
All Addenda issued before Bid Opening also form a part of the contract.
Add the following sub-subparagraph 1.2.3.1:
In the event of conflicts or discrepancies among the Contract Documents, inter
pretations will be based on the following priorities:
1. The Agreement.
2. Addenda, with those of later date having precedence over those of earlier
date.
3. The Supplementary Conditions.
4. The General Conditions of the Contract for Construction.
5. Drawings and Specifications.
In the case of an inconsistency between Drawings and Specifications or within
either Document not clarified by addendum, the better quality of greater quan
tity of Work shall be provided in accordance with the Architect’s interpretation.
REFER ARTICLE 2:
Add the following to subparagraph 2.1.1:
The term Owner as used in the following specifications and the contract docu
ments shall be construed to mean OWNER.
Omit subparagraphs 2.1.2 and 2.2.1 in their entireties.
Subparagraph 2.2.5 is hereby modified as follows:
The Contractor will be furnished, free of charge, 10 copies of the drawings and
specifications for the execution of the work.
REFER ARTICLE 3:
Add the following to subparagraph 3.3.1:
No work shall be done for any trade during “off hours,” weekends, or any other
time aside from the Owner’s normal working hours, unless the Contractor’s
Superintendent is present, and unless express permission is obtained from the
Owner for accomplishing such work.
Add the following to subparagraph 3.6.1:
TAXES:
All sales taxes and any other Municipal, State and Federal taxes applicable to
this work shall be paid by the Contractor. An exemption may be obtained from
542 Estimating Construction Costs
state and municipal sales tax on purchases of tangible personal property which
is incorporated into and becomes a part of the project and where title thereto
passes directly from the vendor to the Owner. If a Contractor desires to endeavor
to take advantage of this sales tax relief, the Owner will designate the Contractor
as an agent of the Owner for the purpose of purchasing tangible personal prop
erty. This agency will be created for the sole and exclusive purpose of avoiding
sales tax and will contain a provision stating that it is so limited and that the
Owner is not responsible to the vendor or any other person dealing with the des
ignated agent for the payment of the purchase price. Furthermore, said agency
shall not be deemed to apply to minor isolated sales, purchases of small or ran
dom items, or to property used only incidentally in connection with the project.
REFER ARTICLE 4:
Add the following to subparagraph 4.1.1:
The term Architect, as used on the contract documents, shall be construed to be
ABC Design Firm, who have prepared the plans and specifications and who will
review the work.
Omit subparagraph 4.1.4 in its entirety.
Subparagraphs 4.3.2, 4.3.4, 4.4.4 are hereby modified as follows:
Omit “arbitration” from these subparagraphs.
Subparagraph 4.3.7 is hereby modified as follows:
Omit “(2) an order by the Owner to stop the Work where the Contractor was not
at fault,” “(4 ) failure of payment by the Owner, (5) termination of the Contract
by the Owner, ( 6 ) Owner’s suspension,” from this subparagraph and add “as
determined by the Owner” after “reasonable grounds.”
Subparagraph 4.3.8.1 is hereby modified as follows:
Omit “of cost and” from this subparagraph and add the following:
“Requests for time extensions shall be submitted with each request for progress
payment and shall cover the same time period as the Application for Payment.
A ppendix Example Bid Documents 543
Failure to submit such request waives Contractor’s right to claim time exten
sions for that designated period.
It is agreed that the Owner’s liability for delay or any cost incurred there
from is limited to granting a time extension to the Contractor, and there is no
other obligation expressed or implied on the part of the Owner to the Contractor
for the delay or any cost incurred therefrom.
Time extension requests may not be acted upon until substantial completion
of the project has been reached as defined in Article 9.8 of the General
Conditions.
The maximum extension of time granted will not exceed the total requested.
The Owner reserves the right to approve or disapprove with cause such
requested extensions.”
Omit subparagraph 4.3.8.2 and replace with the following:
No extension of time for completion of the work will be granted on account of
weather during the contract time.
Omit Paragraph 4.5 in its entirety.
REFER ARTICLE 7:
Delete subparagraph 7.2.2 and replace with the following:
7.2.2 When the need for a change order has been justified, the Architect will
send the Contractor drawings, descriptions, and specifications which will define
the proposed changes. The Contractor shall then establish a cost for accom
plishing the changes and shall notify the Architect in writing of the amount on
forms furnished by the Architect. The amount shall then be reviewed. If a deci
sion is reached agreeing to pursue the changes for the established amount, then
the Architect will request approval from the Owner. Upon approval of the
changes by the Owner a Formal Change Order will be prepared and issued to the
Contractor for the stated amount. Processing time for change orders normally
requires several weeks from the time the Contractor’s estimate is received by the
Architect until issuance of formal change order. Processing change orders of a
critical nature may be expedited with permission of the Owner. Section 121 of
the STATE Public Competitive Bidding Act of 1974, as amended provides that
all change orders shall contain a unit price and total for each of the following
items:
a. All material with cost per item.
b. Itemization of all labor with number of hours per operation and cost per hour.
c. Itemization of all equipment with the type of equipment, number of each
type, cost per hour for each type, and number of hours of actual operation
for each type.
d. Itemization of insurance cost, bond cost, social security, taxes, workers
compensation, and overhead cost.
e. Profit for the contractor.
544 Estimating Construction Costs
Individual Change Orders less than $10,000 may be based on an acceptable unit
price basis in lieu of the itemization as listed above.
Accordingly, we must request that the foregoing information be provided as
an attachment to the change order proposal request.
REFER ARTICLE 8:
Subparagraph 8.3.1 is hereby modified as follows:
Omit “or by delay authorized by the Owner pending arbitration,” from this sub-
paragraph.
REFER ARTICLE 9:
Subparagraph 9.2.1 is hereby modified as follows:
Delete “Before the first application for payment” and replace with “Immediately
after formal award of Contract.”
or delivery to the Owner of (1) United States Treasury bonds, United States
Treasury notes, United States Treasury bills, or (2) general obligation bonds of
this State, or (3) certificates of deposit from a state or national bank having its
principal office in this State. The withdrawal of such retainage shall be accom
plished in accordance with procedures established by the business office of the
Owner and Section 113.2 of this State’s Competitive Bidding Act of 19XX, as
amended.
Add the following to subparagraph 9.9.1:
If such use prior to the Contract time for completion increases the cost of the
work or delays its completion, the contractor shall be entitled to extra compen
sation or extension of time, or both provided that the contractor shall notify the
Owner of the potential for extra cost and time extension upon giving written
consent for such use.
The Contractor’s claim for such extra compensation shall be in writing, with
vouchers and other supporting data attached.
After the Contract time for completion has expired, the Contractor shall not
be entitled to extra compensation or extension of time due to such use, neither
shall the amount of the liquidated damages, if required by these documents, be
reduced because of partial use or occupancy.
Add the following to subparagraph 9.10.1:
The following items must be received before final payment will be processed:
a. Monthly Progress Payment Application,
b. Affidavit (Release of Liens, Judgements, Etc.),
c. Certificate of Approval (Surety),
d. As-Builts,
e. Operating, Maintenance, and Instruction Manuals,
f. Warranties, Bond, and Guarantees.
that is authorized to do business in this State, and shall be subject to the approval
of the Owner.
The Contractor does hereby warrant and/or guarantee against and shall rem
edy any defect due to faulty materials or workmanship and shall pay for any
damages to other work resulting therefrom, which may appear within a period
of one (1) year from the date of Substantial Completion of the project.
Supplemental, special and extended warranties or guarantees which are also
required are indicated in the various Sections of the Specifications.
i
INDEX
549
550 Index
The fifth edition of Estimating Construction Costs retains the fundamental concepts of
estimating that have made this bock so successf~: Numerous example problems have bee'
added to illustrate new construction methods and various techniques of preparing cost
estimates. The example problems are presented in a consistent format throughout the text,
from quantities of materials and production rates through pricing of labor, material, and
equipment.
Many chapters have been extensively revised. The Conceptual Cost Estimating chapter has
been expanded to include additional emphasis on preparing early estimates. The Highways and
Pavements chapter has been rewritten to include modern equipment and illustrative examples
of preparing cost estimates for asphalt and concrete pavements. Particular emphasis is placed
on infrastructure-type projects.
The fifth edition has three new chapters: Bid Documents, Estimating Process, and Computer
Estimating. Bid Documents introduces the reader to aspects of the contract document that
specifically apply to preparing estimates. Estimating Process presents the total estimating
process, including development of cost databases, establishment of estimating procet.'e:
and retrieval of costs from completed projects for use in preparing future estimates. Computer
Estimating gives helpful insights on the use of computers for preparing cost est ~ate: ” ~e
accompanying CD-ROM, the HeavyBid/Express tutorial, assists the reader ' r e r : : e s ;
computer estimating.
Me
Graw
Hill
Higher Education
Some ancillaries, including electronic and print components, 9 780071 239455
m ay not be available to customers outside the United States. www-mhhe-coi