Psslope Manual
Psslope Manual
Psslope Manual
Engineering Division
(304) 558-2885
[2]
DISCLAIMER
The West Virginia Division of Highways PSSLOPE MANUAL and the accompanying design
software were prepared for use by West Virginia Division of Highways technical staff. Neither the West
Virginia Division of Highways nor the Principal Investigator warrants the manual, the software and
results to be free of defects. All users are warned that they must have the technical training and
experience to apply the information to their needs, and they must be responsible for the outcomes of
such applications. Methods and techniques applicable to one locale or situation may not be suitable for
others, and users are responsible for recognizing such deviations and for making appropriate
adjustments. Some errors may exist in both the manual and the software that may affect the results
obtained. It is the user’s responsibility to check results and to assure correctness and suitability of those
results.
[3]
CHAPTER 1 - SLOPE STABILITY
A. PRELIMINARY STEPS
1. Prepare the Cross-section: Before the data can be entered into the program, a cross
section should be prepared. Use a reasonable number of straight line segments that will
represent the cross section. You can ignore some survey points if a single line segment is
very close to two or more surveyed line segments, but do not over simplify. Accurate
surveyed cross sections are important since the slope geometry is used to back calculate
the soil parameters on the failure plane.
Each location where your line segments intersect, or end, is called a point and each line
segment is called a line. Use lines to show the ground surface, different soil zones, and
water table surface. Plot the core boring soil and rock layers on the cross section and
determine the different soil boundaries. Number each line from left to right starting at the
top boundary (see Figure 1). Do not number water surface boundary at this time.
Determine and record on the cross section the coordinates x, y (offsets and elevations) for
the endpoints of all line segments, including those for the water surface, if any (Figure 1).
Notice all boundaries have the same beginning and ending edges. Extend the water
surface to the same beginning and ending edges. No vertical or overhanging boundaries
are allowed. The program always sets the starting point for the graph at x, y = 0, 0.
Consequently, when preparing the cross section, adjust the values of the coordinates so
that the lower left starting point is at least x, y = (10, 10) to allow room for the slip plane
below the lowest surface. Also, if the actual elevations are used, the program will plot
the actual distance from zero, producing an impracticably small graph (e.g., if the lower
left starting point on Figure 1 was imputed at the actual elevation 510-feet, the graph
would be scaled to fit the screen in such a manner that it would be hard to see the
geometry shown below).
[4]
Figure 1: Flagged Lines and Point Coordinates. Notice that the water surface is not
flagged.
2. Prepare the Soils Data: Number the soil (rock) zones on the cross section and record the
properties of the soil in each zone (Figure 2). The soil below each line is imputed into
the program as will be discussed later. The average Standard Penetration Test (SPT) N-
values can be used by the program to estimate the undisturbed soil parameters for each
layer. Unit weight, saturated unit weight, residual friction angle, peak friction angle,
disturbed cohesion, and undisturbed cohesion can be estimated based on the soil type or
from laboratory testing. The Rock Mass Rating (RMR) can be used to estimate rock
properties. Selecting soil parameters, using RMR and N-values will be discussed later.
100
192, 80
c = 100 psf
60
41, 22
Soil 2 γ = 120 pcf Φ = 30o Φr = 28o C=100
40 100, 20
Soil 3 γ = 150 pcf Φ = 45o c = 1000 psf
3. Select Coordinates for the Failure Surface: Use the scarp and toe plus any other
information, such as a boring, to determine or estimate the failure surface location. The
program uses a circular failure surface. Use a CAD program or a compass and graph
paper (this may require taping a piece of paper to your cross section) to find three points
of the arc that fits the predicted failure surface (see the three points on Figure 2).
Alternatively, if a range for the initiation point near the toe and ending point near the
scarp is entered, the program will search for the worst failure surface out of the ten worst
failure surfaces in the selected range. Make sure your circle does not intersect the ground
surface in more than two points or an error message will be generated. You may have to
slightly change some points, or lines, on the cross section to correct this problem.
[6]
B. INPUT
1. Enter a title.
2. Enter a number for Number of Soil Types; this must be greater than zero, except when
the Simple Wedge Analysis is used, then the number of soils should be 2 (See page 22).
3. Change the SPT Hammer Efficiency if the hammer used has a different efficiency than
the standard 60% for rope and cathead hammer. The program internally adjusts the SPT
blow-counts to the standard (N60) to determine the soil properties needed for soil-pile
analysis. If an Auto Hammer is used, input the efficiency to 80% (if the efficiency of the
Auto Hammer is unknown).
4. Click the Update Screen button to generate the required rows for the number soils
entered. After making changes to a table/section, and prior to selecting another
table/section, or running the analysis, the screen must be updated).
5. Select the Soil Type. There are four choices to choose from: three soils types and one
rock. When selecting Soil Type, it is important to understand how the program uses each
type of soil in the calculations.
a. Sand: This soil type has zero cohesion and has only friction; therefore the program
ignores any values entered input in the Cohesion Intercept undisturbed column. This
soil would be recognized as fairly clean sand with not enough binder soil to stick
together.
b. Clay: This soil type has zero friction and has only cohesion; therefore the program
ignores any values entered Friction Angle peak column. This soil would be classified
as clay with only a trace of sand of silt, and can be rolled into a thin thread between
the fingers.
c. C-Phi: This soil type is the typical soil found in West Virginia and contains both
friction and cohesion soil properties. This selection will use both soil properties in
the calculation. This soil should be selected unless it can be determined the soil is
either a pure sand, or pure clay.
d. Rock: Used for bedrock of all types, including an intermediate geomaterial (IGM) of
extremely weathered rock.
6. Input the disturbed cohesion intercept and friction angle. Cohesive Intercept Disturbed
and Friction Angle Residual represent the soil strength parameters along the failure
surface. These values are used in the slope stability analysis.
7. The last four columns of the soil properties, Blowcounts, RMR (rock mass rating),
Cohesion Intercept, Friction Angle, represent the data needed for the soil-pile analysis.
These represent the soil strength parameters above and below the failure surface and are
considered as undisturbed.
[7]
8. The program defaults to the columns labeled Blowcounts and RMR, when running the
soil-pile analysis. If values are entered into the Blowcounts (N Value), or RMR columns,
the program ignores any value entered in the last two columns, Cohesion Intercept and
Friction Angle.
9. Use the enter key, or the mouse, to move from one cell to the next, when entering data.
C. BOUNDARIES
1. There are three methods of analysis used in this program for analyzing the slope stability
as follows:
The input of the boundary layers is the same for the first two methods above. Before
inputting the soil layer boundaries and selecting a method for analysis it is important to
understand the difference in each method. The first two methods, Existing and Potential
Failure Surface, both require a detailed input of boundaries, soil profile, water surface
and slip plane. The third method, Simple Wedge Analysis, which will be discussed later
in detail, requires only the width of the wedge, height of wedge, depth of water table and
depth to bedrock. No surface, soil, or water boundaries are input into the boundary tables
for the simple wedge analysis (see page 22).
This section covers only the first of the three methods. When inputting the data into this
section, refer to Figure 4.
[8]
2. Input the Total number of boundaries and the Number of top boundaries and click Update
Screen. Referring to Figure 1, the number of top boundaries is 6 and the total number of
boundaries is 9.
3. Input the boundary line segments starting from the left and top most boundary and
working to the right and down through the layers. Input lines using the x and y
coordinate for the start and end of each line segment. Notice that the ending coordinates
are repeated as the starting coordinates for the next line segment.
4. When entering the line segments, it is required to define which soil type underlies which
line segment by giving the soil a number corresponding to the soil type. This Soil
Number is input in the same row as the line segment for which it underlies.
5. It is important to accurately estimate where the water surface was at the time of failure.
Enter the number of water surface points that make up the total number of line segments.
Do not forget the last ending point. For example, 9 line segments will require 10 points.
Enter the x and y coordinates that make up the line segments. The program only accepts
one water surface.
Figure 4: Input Table for Boundary Line and Water Surface Segments
6. It is possible to enter the data for either/both Existing Failure Surface or Potential Failure
Surface, on the same file and switch back and forth between the two methods. However,
if at any time the Simple Wedge Analysis button is selected all soil boundaries will be
deleted and lost from the program. Switching back to one of the other methods will
require that the boundary data be re-entered. Therefore, it is recommended that the user
save the file after inputting the boundary data and prior to switching methods of analysis.
It is a good practice to adopt a naming convention for naming files that identifies not only
the name of the slide, but also the analysis method used. For instance, if a file contains
information for a slide referred to as Pendleton slide and uses the existing failure surface
method of analysis, then a good name for the file is Pendleton_efs. Using such a naming
method will make it easier to differentiate among files that use different analysis methods
for the same slide.
[9]
D. RUNNING STABILITY ANALYSIS:
1. Existing Failure Surface: This method requires inputting the slip surface, utilizing a
three point method. The failure surface is determined from the slope geometry, by the
scarp, by the toe, and by the depth to slip plane as indicated from the borings. This
requires the x and y coordinates for the starting, ending, and middle points be entered in a
table (see Figure 5) that opens when the Existing Failure Surface button is selected. The
slope geometry and the failure surface can be viewed by selecting the Plot Failure
Surface button. This option is useful to determine if adjustments are needed to the failure
surface or boundaries.
If the table is closed without inputting data, the program will generate the warning box
shown in Figure 6. Ignore this warning; it is just indicating there is no data to plot.
2. Potential Failure Surface: This method requires entering the slip surface by inputting
the Leftmost Initiation Point, Rightmost Initiation Point, Left Termination Limit, Right
Termination Limit and the Min. Elevation of Surface Development (Figure 7). The table
will open when the 2nd button is selected (Figure 4). This method is used when the exact
failure surface is unknown or when searching for the most critical slip surface. It is also
used when just analyzing a slope for stability, which has not failed. It is common to
conduct a preliminary search for the critical slip surface first. It is usually found that
most of the slip surfaces occur within a defined range. It is possible after the first run to
more precisely define the search limits or force the critical surface to a predetermined
location.
[10]
Figure 7: Potential Failure Surface Input Box
3. Modified Bishop Method: The method used in the program is the Modified Bishop
Method, which is simulates a circular failure surfaces. When the factor of safety of a
slide is 0.99, or for practical purposes 1.0, failure has occurred. (It is commonly observed
that failures can occur with a factor of safety of 1.10 using this method – more on factors
of safety will be discussed later.) Other methods are available that simulate sliding block
failures which may be more accurate for the type of failure, but it is believed that the
Bishop method is within the accuracy of estimating soil parameters and provides
adequate results for pile wall design.
4. The Goal for the Initial Stability: The goal of the initial analysis is to establish the soil
parameters (strength parameters and water surface) to obtain a factor of safety of 1.0. In
this form of back-analysis, the soil parameter values do not have to be exact, just
reasonably correct. If you are running the program for an existing slide, the factor of
safety should be 1.0. If 1.0 factor of safety is not reached, adjust the strength parameters,
the water table data, or both until a 1.0 is reached. Do not waste time making the slide
factor of safety exactly 1.0, if the factor of safety rounds to 1.0 (i.e., is 0.96 to 1.04; use
two decimal places only). Use soil parameters and water surface in subsequent stability
analyses to evaluate the pile wall design (discussed later).
We seek the best method to correct the slide. The best method may be the least
expensive, the fastest, the easiest, or even the most aesthetic, depending on the
circumstances. Albeit the programs best attribute is that of a pile wall design, using the
stability analysis section of the program does allow for other designs, such as a buttress,
modifying the slope or relocating the road.
5. Run the Stability Analysis: At the top in the menu, select Run, Slope Stability. The
following note will appear if all inputs were input correctly (Figure 8).
[11]
Figure 8: Notification Message of Successful Stability Analysis
c. Total number of boundaries exceeds the actual boundaries in the table (Figure 13).
The program is expecting a value on the next line and to match the previous x value.
[12]
Figure 13: Error Message
d. Execution of program failure (Figure 14); This message can appear for a couple of
reasons:
i. Failure surface does not intersect the surface at two points or intersects in more
than two points, For example, the failure surface jumps across a ditch.
ii. A negative number(s) was input.
i. This is a common system error message that often results because the
programmer did not anticipate that the user would enter a value outside of the
expected range. In the PSSlope program, entering a value of zero for the slip
plane strength parameters is one way to generate this error. Because PSSlope
does not handle system error messages, generating one of these will cause the
program to crash.
ii. If this message is encountered please note the error message and contact the
central office. The file (.stm) will need to be saved and sent to the office to
correct the program.
f. PSSlope will display a warning or error message for the first input error it encounters
in the program. The error message most likely points directly to the problem or it can
[13]
indicate an error caused by an incorrect input in some other location. Check inputs
carefully before making corrections. It is important to remember that the program
will allow as many corrections to a section as needed, but the Update Screen must be
selected prior to selecting another section for corrections or running an analysis.
7. Viewing Results: The program offers two methods to view the profile of the input
parameters prior to running the stability analysis (this function is not available in the
Simple Wedge Analysis). This function can be used to check the soil, water table and
failure surfaces, and make adjustments prior to running the analysis (Figure 17).
a. In the Existing Failure Surface press the Plot Failure Surface button (Figure 16).
This button is not available in the Potential Failure Surface.
A small sketch of the surface, water and slip plane boundaries will be generated (Figure 17).
b. To view the preview sketch (Figure 17), select Profile on the main menu bar at the top of
the screen (Figure 18).
[14]
Figure 18: Profile on Main Menu Bar
c. Once the stability analysis has run successfully, the user has the option to view a
graph of the geometry and failure surface(s), Figure 19. The graph displays the
date and time, factor-of-safety (F.S.), water table, soil layers and slide name. If
the mouse pointer is moved over the graph the x and y coordinates are displayed
on the lower border of the graph. Please note that the order of the coordinates are
reversed, y and x.
iii. Print
1. Plot/Graph
a. Monochrome
b. Color (uses a lot of ink)
2. Output data
[15]
8. Including the Pile Wall: Once a F.S. of 1.0 has been reached by back calculating the soil
strength parameters and the user is confident in the modeling of the slip, it is
recommended to adjust the soil layers to include the pile wall and correction. Often the
installation of a pile wall requires rebuilding the road to include a 4 to 6-foot shoulder,
and possibly a guardrail. This added weight could result in a greater driving force on the
wall and should be modeled. When modeling the wall it is important to note that the
piling cannot be input as a vertical line. Offset the top by 0.1-feet, uphill (remember that
there must be soil under the line and not air, so don‟t offset in the wrong direction).
Remove any slide material below the piling that will be removed for construction and/or
road clearing. This will be dependent upon the situation. The main objective is to model
the correction geometry as accurate as possible, eliminating any resisting forces and
adding any additional driving forces. Run the analysis and ignore any change to the F.S.
as a result of these changes.
[16]
CHAPTER 2 – PILE SIZING AND ANALYSIS
A. Pile Data Input
1. Select from the drop down menu the appropriate pile (Figure 20), the most common
H and W sizes, for compact (Mp) and noncompact (My) piles are listed. Compact
piles utilize the plastic moment and noncompact piles use the yield moment.
Another option is to enter a custom pile size (Figure 21); some inputs can be obtained
directly from the “Manual of Steel Construction” or any other official source. Others
will have to be calculated as outlined below.
Note that this input window is not limited to just H-Pile sections, other shapes can be
used. Selection of the proper pile size will come with experience and will only need
minor adjustment to achieve the proper performance and deflection. A good practice
is to select a pile size a little larger than anticipated, and run the program to determine
the smallest size needed. Selecting a pile size that is too small results in an error
[17]
message (see Figure 22) that the pile failed under the moment and produces no
quantifying results in which to gauge how much larger the pile needs to be.
2. Enter the desired Lagging Depth; keep in mind that the slope on the downhill side
may continue to move. A good practice is to embed the lagging 2-feet into the
ground. The lagging cannot be extended beyond the failure surface.
3. Enter the estimated Total Length of the pile in feet. A good practice is to embed the
pile 10-feet into bedrock. Although this is not always possible or practical.
4. Enter the Pile Spacing, the standard spacing is 4-feet center-to-center of piles. This
can be adjusted as the situation dictates.
5. Enter the Pile Head x and y coordinate. This must be the same coordinates as the top
of the pile that was entered into the boundary input table.
6. Select the desired FS, for the initial analysis, use FS of 1.0.
1. It is important to remember that the Slope Stability must be run prior to running the Slope
with Piles, EVERY TIME a change is made. If a change is made to ANY input data, then
the slope stability must be run again. So it is recommended as a practice to run the Slope
Stability and then run the Slope with Piles, every time. To run the program, select Run
the Slope with Piles.
2. Once the program has successfully run, pile performance information will be displayed
on the main page, and the user has the option of viewing several files, and graphs. The
Factor of Safety and Pile Performance Ratio will be displayed at the far lower right of the
main page (Figure 23).
[18]
Figure 23: Pile Analysis Output
a. FS of the Unsupported Portion of Slope: This is the FS for the portion of the
slide that is downhill from the pile wall, which is not supported by the pile wall.
By stabilizing the upper portion of the slide, the driving force could be reduced or
even eliminated, thereby stabilizing the lower portion. This information is of
concern if there is something downhill of the slide that may be in jeopardy such as
structures, another road, railroad, and etcetera.
b. Pile Performance Ratio: This is a percent of the factored pile strength that is
being used. This information can be utilized several ways. When sizing the pile
up or down, this percent can help in determining how much to adjust the pile size.
It is important to remember that the final correction requires a factor of safety of
1.3 for general slides and 1.5 around structures (per AASHTO LRFD Bridge
Design Specifications). The higher FS will use a greater percent of the pile
strength. Also, if the pile is not long enough and rotates over (fence post), the
performance ratio will be low. This number should always be used in conjunction
with the deflection as discussed below.
3. Graphing Results: From the main menu select Graph, and then select Pile Response
from the drop-down menu. The pile response is analyzed utilizing four separate graphs:
Deflection, Moment, Shear Force and Line Load. On the graph there is a tab for Graphic
Control, this has no function with the program. Although it is still active and can be used
to modify the overall look of the graph, it will tend to produce a graph that is not as
usable. Once the graph has been manipulated with this function, it is not possible to
return to the original graph. Do not fear, closing the program and restarting the program
will restore the graph to the default.
a. Deflection: This graph displays the deflection of the pile, in feet, along the y axis.
Deflection is most critical when analyzed at a factor of safety of 1.0 (Figure 24).
The amount of deflection that is allowed is dependent on the situation. As a
practice 4 inches is the maximum deflection for rural roads, 2.0 for major roads.
Road type, slope steepness, shoulder width, and if a guardrail will be installed, all
have a major impact on the maximum allowable deflection. If the shoulder is
going to be paved up to the wall, less deflection is desirable. In addition to
deflection, this graph indicates if the length of the pile is adequate. It is important
[19]
to get two points crossing the zero line to get fixity, using the final factor of safety
of 1.3.
Two points
[20]
b. Bending Moment: The location and magnitude of the bending moment can be
visualized (Figure 25). As a check, the moment in the flexure formula
(moment/section modulus = fiber stress) can be used, to determine what section
modulus to use if a different shape is desired.
Maximum Moment
[21]
c. Shear Force: The shear is built up within the pile by the slipping mass then shed
into the more resistive layer below the slip surface. Shear is usually not a critical
design state for steel piles (Figure 26).
[22]
d. Line Load: The line load is the load per vertical inch of the pile that the soil or
rock sees. To convert this load to stress, divide the force by the flange width.
This is used to check the spike at the rock line to determine if the pressure
exceeds the unconfined compressive strength of the rock mass (Figure 27).
4. Pile Size: Once the required pile size has been determined by checking the pile
performance at a FS of 1.0 and 1.3, save the file, and print any files required.
[23]
5. In addition to graphs and plots the program generates two text files, Figure 28, 29 and 30.
These files are output files generated and used as input files to parts of the program. Care
should be taken when examining these files, as changes will corrupt the original results.
However, if needed the user can obtain the exact deflection, location, and depth of the
maximum moment from these files, although, as with most things in Geotechnical
Engineering, this level of accuracy is not really needed.
Figure 29: Profile Text File of data presented in the pile graphs
Figure 30: Output data indicating whether the pile is stiff, intermediate or flexible
[24]
C. SIMPLE WEDGE PROGRAM
1. Simple Wedge Analysis: This method of analysis is, as the name implies, a very
simple method to model the slip as a simple wedge of soil applying a driving force to
the pile. The program requires inputs as follows: the wedge geometry, depth to water
table, and depth to bedrock (Figure 45), as well as two soils types, lagging depth, pile
length, pile spacing and pile size. The second soil is assumed to be the bedrock,
regardless of the strength parameters entered.
a. Soil Input - Enter the two soils as follows: one soil for the slip surface and
surrounding area, and another to embed the pile into. Both soils can have the
[25]
exact undisturbed and disturbed strength parameters, or they can be two entirely
different soils/rock. The main point is the program requires two soils. The Total
number of boundaries, Number of top boundaries, boundary coordinates and
water table surface need not be entered.
b. Width of Wedge: Next select the Simple Wedge Analysis button and enter the
data the Width of the Wedge. This is the horizontal distance from the top of the
pile to the last break in the road. Adding extra width to the wedge will reduce the
driving force and is not advised. Caution is recommended when using this
analysis method and the results can readily be checked as discussed later.
c. Pile Height: Enter the Height of Wedge (ft); this is the vertical distance from the
top of the pile to the suspected slip surface.
d. Depth of Water Table: Input the estimated Depth of Water Table (Hw) (ft).
e. Depth of Bedrock: Enter the Depth of Bedrock (Hr) (ft), this is the second soil
listed in Figure 1. The second soil does not necessarily have to be Rock or even a
different soil type. If for example, the core borings show the same type of soil
deeper then the estimated pile length, enter the second soil having the same
strength properties as the first soil.
f. Pile Data: Enter the Pile size, Lagging Depth, Total Length and Pile Spacing.
g. FS: Enter the desired factor of safety. The program should be run with the FS of
1.0, and 1.3 or 1.5 as discussed on Page 17, “Running Pile Analysis”
2. Running the Program: On the main menu tool bar select run, then Slope with Piles.
It is the only option.
3. Viewing the Results: The program only allows for the viewing of the pile response.
4. Pile Performance: The pile performance is analyzed by viewing the available graphs
and the Pile Performance Ratio, see page 18.
[26]
CHAPTER 3 – EXAMPLE PROBLEMS
A. Learning By Example
1. The following example problem is provided to show the user how to design a pile
wall as a corrective measure. The user is encouraged to adjust the soil, rock, and
water table parameters (layering and soil properties) to produce a variety of results.
The user is also highly encouraged to experiment with the different slope stability
methods. An effort has been made to explain all steps in the analysis and design.
2. The program has been made as user friendly as practical; this includes trying to trap
common errors that the user may make. However, not all of these errors can be
anticipated, and error messages may arise that are incomprehensible to the average
user.
2. Strength Limit State: The factor of safety used by WVDOH for the design of
ordinary soil slopes (cuts and embankments) is 1.25 for Allowable Stress Design and
1.30 for Load Factor Design. Many designs have been developed by the WVDOH
Engineering Division in the last few years with factors of safety 1.25. The lowest FS
in the strength limit state is 1.1. This should only be used for extreme event limit
states, such as end of construction or rapid draw-down. A factor of safety of 1.1 is
considered at the edge of failure due to the accuracy of the method.
3. Factor of Safety: The use of reduced factors of safety for slide corrections requires
judgment based on experience. Sliding cause‟s a reduction of soil strength from peak
to residual, so strength can be lost between the times of design and construction.
Further, ground water conditions can become worse than those existing at the time of
original failure. Use good judgment or, if you lack experience, use a factor of safety
of 1.3. With experience, factors of safety of 1.25 can be used, based on local
experience.
1. Failure Circle: The failure circle must intersect the ground surface at two points (the
end points of the circular arc). Otherwise an error message will appear. If the slide
has a steep scarp or slope above the upper limit of the slip plane, the circle may
intersect the ground surface again (for the third time). Hence, some superfluous lines
above the slip plane must be eliminated. However, if a new circle is run to check the
corrective design, the eliminated lines may have to be added.
[27]
2. On rare occasions, a circle through the toe of the slope can intersect a line below (for
the third time) to give an error. It is good to check your circles before you run the
program.
3. The maximum vertical depth of a slide rarely exceeds ¼ of the slope length of the
slide; the maximum failure surface depth is always less than 0.3 times the length and
averages about 0.17 times the length. These criteria do not apply to new
embankments over soft, deep clay foundations.
1. Driving Forces: The driving force to be resisted depends on the location of corrective
measures within the slide and the slope configuration within the slide. For example, a
piling correction near the top of the slide may only have to hold the top of the slide,
not the entire slide. However, if we must fill on top of the slide (e.g., to rebuild the
road surface), we need a piling wall (with lagging) to hold the top of the slide PLUS
the new fill. We need to perform a new stability analysis on the slide and fill to
obtain the force the piling must resist. To accomplish this, the soil surface profile
will need to be modified to model the correction. So prior planning when selecting
and entering the x and y coordinates makes possible the remodeling of the correction,
much easier and becomes a simple matter of entering new line segments at the end of
the input table or change the value of a few points.
2. Resisting Forces:
a. Soil Strength: Soil strength is defined by the parameters of the internal friction
angle (phi ) and the cohesion intercept (c). Each type of soil will, in general,
have different values for and c. Furthermore, the same soil within and
surrounding a slide mass will typically have different strengths.
b. Where to use different strength parameters? Use r along the slip plane
(disturbed) during the original analysis. Within the slide mass and below the slip
plane (undisturbed), use peak values. Do not choose strength parameters over
conservatively; this will require the ground water to be modeled higher to get the
slide to fail.
c. Ground Water: The pore water force (U) values reduce the effective normal
forces, thereby reducing resisting forces. The exact U values are rarely known
since this requires extensive and usually long term piezometric water level
measurements. Even when such measurements are made, they may not reflect
values at the time of failure. One of following three ground water conditions is
normally encountered during corrective design.
[28]
water level at the time of failure will be at the ground surface for the full
length of the slide, even though there is no visual evidence. Borings above the
visible seepage may also show indications of the ground water level (when
practical, have observation well installed). These conditions allow an
approximate ground water level to be plotted on the design cross section. If
only partial information is available, i.e., only visible surface seepage or only
an indication of the water level in a boring, the water level must be estimated
from this information. The estimated water level may be adjusted later if
results of the stability analysis indicate that such adjustment is necessary.
3. Ground water and soil strength unknown: Emergency situations arise where
corrective measures must be based solely on site observations. Surface soils
are visible and surface indications of ground water may be visible, but
strength parameters and water levels are quite problematic. Guesstimate
strength parameters and water levels based on your observations, and run a
stability analysis. Adjust the assumed values to obtain a 1.0 factor of safety.
Design the correction using these values to estimate conditions outside the
slide area. For example, if the r is 23 degrees and use = 27 degrees and c =
100 psf for the soil under the slide. Adjust the embedment depth during piling
installation if the soil under the slide is significantly different or if bedrock is
encountered.
[29]
E. Example Problem
1. The number of soils used in the analysis will depend upon the information
available. It is often easy to determine the number of soil zones from boring logs.
For this example the soil parameters were derived from field observations and
core borings they are depicted in Figures 31 and 32. The core boring indicated
three main soil layers and a depth to water, at the time of coring.
2. Input the soil data in the program from Figure 31 and 32.
3. Determining the soil boundary coordinates is best accomplished through the use
of a CAD program. Often the coordinates are derived from a professional survey,
but if time is a limiting factor, the user can, with the aid of an assistant, produce a
simple plan view and cross section, by utilizing a surveyors tape and Abney
Level. In this example the soil boundaries and water surface coordinates have
been determined and plotted on Figure 33 and entered into the Figure 35.
[30]
4. The soil types and corresponding soil number have been annotated on Figure 34.
100
192, 80
Soil 1: Silty Clay
Φ = 31o Φr = 28o
80
7. Input the Existing Failure Surface from Figure 34, utilizing the 3 points.
8. Plot the failure surface; recall there are two methods for checking the failure
surface. Adjust inputs as required, correcting any errors.
9. After making any necessary adjustments, run the Slope Stability analysis.
[31]
10. View the Graph of the Slope Stability analysis and check the factor of safety. The
goal is to adjust the parameters to achieve a factor of safety of 1.0. At this point
the graph should look similar to Figure 36.
In this example the initial input of soil parameters were estimated low to produce
a F.S. of less than 1.0, for demonstration purposes.
11. Adjust the soil parameters as required to obtain a F.S. of 1.0, rounded. The
Cohesion Intercept and Friction Angle have the greatest effect. However,
disturbed soil has little to no cohesion, so it is highly recommended to input 0 for
cohesion. The friction angle is determined by the type of soil. Try adjusting the
friction angle and unit weight of the soil that is affected by the failure surface.
Adjust each item one at a time and check the graph, until proficiency is gained at
predicting the desired results.
12. The inputs in Figure 37 will give the desired results of a F.S. of 1.0, rounded.
Enter the inputs from the table below if a F.S. has not been achieved or the user
inputs differ greatly from those listed in the table. Having similar inputs will be
important to obtaining similar pile size for the rest of the exercise.
[32]
Soil Strength Properties
Cohesion Friction Cohesion Friction
Saturated
Soil # Soil Type Unit Weight Intercept Angle Intercept Angle
Unit Weight
Disturbed Residual Undisturbed Peak
1 C-Phi 126 128 0 24 50 31
2 C-Phi 124 126 0 28 100 28
3 Rock 145 146 10000 36 10000 36
Figure 37: Inputs that Produce 1.0 Factor of Safety in Example Problem.
The output graph should look similar to the graph in Figure 38.
13. Once the soil parameters have been adjusted to produce a factor of safety of 1.0
(rounded), input the soil boundary coordinates (Figure 39) to model the pile wall
correction. Only the cells highlighted in yellow have been changed. Do not make
adjustments to the disturbed soil strength parameters at this time. It is important
to remember that the pile wall head needs to be battered slightly, for modeling
purpose only. This adjustment will raise the soil boundary up, causing the slip
surface to terminate below the surface. Adjust the slip surface to account for the
extra soil (Figure 39).
[33]
SOIL SURFACE COORDINATES
Total Number of Boundaries = 9 Total of Top Boundaries = 6
14. Run the stability analysis for the slope and view the graph (Figure 40) for any
errors. Ignore the factor of safety.
16. Input the Pile analysis information from Figure 41 and run the Stability with Pile.
It is a good practice to size the pile larger than the anticipated size. However for
demonstration purpose the initial input will be smaller than the required size. The
initial analysis should be done with the Desired FS of the Supported Portion of the
Slope set to 1.0.
17. Because the pile is not long enough to penetrate beyond the failure surface, the
program displays the warning shown below in Figure 42.
After clicking OK, another message will be displayed that says to “check data for
a zero value” (Figure 43). Click the ok button; this is normal because the short
pile length caused a division by zero error.
[35]
18. Check the stability graph and note that the pile wall is now present on the graph,
but was not used in the calculations of the slope stability.
19. Now close the graph and adjust the pile length to 30 feet, and run the slope
stability and slope with piles programs again. This time a different warning
message is displayed as shown in Figure 44 below. This message indicates that
the pile penetrates the failure surface, but not deeply enough to be stable. This
can be seen by checking the slope stability graph and noticing that the pile just
barely penetrates the failure surface.
20. Now set the pile length to 40 feet and run the slope stability and slope with piles
programs again. This time, a warning will be displayed that the pile failed under
plastic moment (Figure 45). This warning indicates that the piles are too small
and that either larger sections should be used or the pile spacing should be
reduced.
21. Through trial and error, run the slope stability and slope with piles program using
increasing pile sizes until a size is found that does not fail. In this example, the
smallest pile size that does not fail should be HP 12x84. The Pile Performance
Ratio and FS of the Unsupported Portion of Slope are also now displayed to the
left of the input table.
[36]
22. Open the Graph drop-down menu and view the pile response graph (Figure 46).
23. Fence posting can indicate that the pile is too short. Enter a new pile length of 45
feet and re-run the program.
24. Open the pile response graph (Figure 47) and notice that the pile has two points
on the zero line (nodes); this indicates that under these conditions the pile has
[37]
fixity and that its length is long enough. The deflection is almost 13 inches; this
is excessive for a FS of 1.0.
[38]
25. A deflection of 13 inches is not acceptable, so the pile size must be increased so
that the deflection meets the specified standard. In this example, a pile size of W
14x176 meets the deflection criteria for rural roads of being less than 4 inches.
26. Notice that the graph shows that the pile is slightly fence posting again (Figure
48). Extend the length of the pile to 50 feet and run the analysis once more.
[39]
27. With a pile size of W 14x176, this example has the following results:
a. The deflection is less than 4 inches.
b. The performance ratio is 28%.
29. The FS of the Unsupported Portion of Slope is 1.03. With this FS, it is
anticipated the slope below the pile will continue to move. Therefore, place the
lagging deep enough to account for the loss of material. If structure and/or road
are below the slip, then the unsupported portion of the slope may need to be
addressed.
[40]
F. Error and Warning Messages
1. General input error (Figure 49): This could be caused by several reasons
a. Soil strength parameter missing: C-Phi requires both cohesion and a
friction angle. However the program will accept a zero for cohesion, but
not a zero friction angle.
b. Other inputs could cause this problem if a zero is placed in the cell.
2. Boundary Input Warning (Figure 50): This box is generated for a couple of errors.
a. A coordinate in a surface boundary does not correspond to a previously
entered coordinate (i.e. X-Left does not match X-Right of the previous
boundary) OR.
b. Total number of boundaries and top boundaries do not match the input of
boundary data: The number of top boundaries is too great.
3. Make sure that the total number of boundaries has been entered and is greater than
zero.
8. Surface Boundary Error (Figure 56): This message can occur for a couple of
reasons.
a. The right coordinate exceed the left coordinate.
b. The Total number of boundaries exceeds the actual coordinates.
c. The program is expecting coordinates on the last line.
[42]
Figure 56: Surface Boundary Error
9. General Stability Program Run Failure (Figure 57): This message can appear for a
couple of reasons:
a. Failure surface does not intersect the surface at two points or intersect in
more than two points.
b. A Negative number exist in the data.
i. Negative numbers are not allowed
10. This error is generated if the value entered for a Boundary‟s Soil Number is less
than or equal to zero.
11. Lagging Depth Warning (Figure 59): This message is self explanatory.
a. Lagging is set to deep, extends to or beyond the failure surface.
12. Pile Spacing Error (Figure 60): This message is self explanatory.
[43]
a. Enter a value for pile spacing (whole number).
13. Concave Failure Surface Warning (Figure 61): This message is self explanatory.
a. Check all three points for error
i. Error is most likely is with the middle point.
14. Slope Stability Warning (Figure 62): This message is self explanatory.
a. The pile location needs to be moved, or
b. The soil strength parameters need to be adjusted, or
c. Water surface needs to be adjusted, or
d. All of the above.
15. No Solution
a. A possible cause of this error can be a negative number in the Lagging
Depth column. Check all pile related inputs.
[44]
Figure 63: No solution warning
17. Pile to Soil Interaction Error (Figure 65): Soil strength is too low to accommodate
the forces applied by the pile wall. The soil is yielding and flowing around the
pile.
a. Check soil parameters and adjust as necessary OR
b. Adjust pile spacing to allow the soil wedge to interact with piles.
[45]
Figure 65: Pile to Soil Interaction
18. Pile Length Error (Figure 66): Tip of pile is not fixed in the soil below.
a. Check pile length or
b. Check failure surface.
19. Pile Failure (Figure 67): The pile has failed due to excessive forces for the
selected pile size.
a. Select a larger pile size OR
b. Reduce pile spacing OR
c. Recheck stability analysis and failure surface for errors.
[46]
Figure 67: Pile Failure
[47]