(NIT Prevails) : Addendum/Corrigendum / (Clarification)
(NIT Prevails) : Addendum/Corrigendum / (Clarification)
(NIT Prevails) : Addendum/Corrigendum / (Clarification)
1
3 Section 4 The amounts of the advance As per Clause No.32, Contract Data, Mobilization advance (NIT prevails)
Contract Data payment are and Equipment advance clauses are deleted. Please
Clause 32 Mobilization advance – consider payment of Mobilization Advance and Machinery
DELETED Advance as is the norm in other Government Organizations
and as per Government G.R. dated 12/04/2017.
4 Section 3 DLP and Maintenance: Conditions of Contract Page no.86 (Please Read Addendum and
Condition of The Defects Liability Period is and clause no.25 Page no.146 Please clarify this clause as Corrigendum attached )
Contract and 1 Year excluding Road work both are different provisions. The Defects Liability Period
Section 10 (For Road Work 3 Year) and is 1 Year excluding Road
Clause 25 Maintenance Period is 2 Years. work. (For Road Work and
Other Concrete work - 3 Year)
and After completing DLP
Period Maintenance Period is
2 Years for remaining other
work such as Landscape,
Electrical and etc
5 Section 1 The performance security shall Security Deposit: As per Clause No. 34.2, Instructions to (Please Read Addendum and
Clause be either in the form of a Bank Bidders, Page No.25, the performance security shall be Corrigendum attached)
34.2Instructions Guarantee of entire amount or either in the form of a Bank Guarantee of entire amount or
to Bidders Demand Draft of 2% of Demand Draft of 2% of contract price, in the name of the
contract price, in the name of Employer, from a Nationalised or Scheduled Bank payable
the Employer, from a in PCMC area as defined in Appendix to ITB. The Balance
Nationalised or Scheduled 3% amount of security deposit will be recovered from R.A.
Bank payable in PCMC area as Bills. Please accept 3 % Security can be paid in the form of
defined in Appendix to ITB. bank guarantee.
(Balance 3% amount of
security deposit will be
recovered from R.A. Bills
6 Section 1 Within 10 days / as mentioned Refund of Security Deposit/ Retention Money: As per Clause As per Clause 6.1 in Section
Clause in the letter of Acceptance of No. 34.1, Instructions to Bidders, Security Deposit will be IV - The security deposit shall
34.1Instructions receipt of the Letter of retained till 30 days after expiry of Defect Liability period and be returned to the contractor
to Bidders Acceptance, the successful maintenance period. Please confirm that the Security without any interest when the
Bidder shall deliver to the Deposit shall be refunded after completion of the project, as contractor ceases to be
Employer a Performance performance security is being retained till Defect Liability under any obligations under
Security in any of the forms period. the contract i.e. after
given below for an amount completion of
equivalent to 5% of the defect liability and
Contract price, 30 days after maintenance period + 30
the expiry of defect liability and days.
maintenance period of 36
months plus additional security
for unbalanced Bids in
accordance with Clause 29.5 of
2
ITB and Clause 52 of
Conditions of Contract: a bank
guarantee in the form given in
Section 8; or certified Cheque /
Bank Draft as indicated in
Appendix.
7 Section 3 Payments shall be adjusted for Delay in Payment: As per Clause No.43.1, Conditions of No Interest shall be paid for
Condition of deductions for advance Contract, Page No.97, the Employer shall pay the delayed payment
Contract Clause payments, retention, other Contractor the amounts certified by the Engineer within 28
43.1 recoveries in terms of the days of the date of each certificate. Please specify the rate
contract and taxes at source, of interest for delayed payments after 28 days of
as applicable under the law. certification.
The Engineer will scrutinize the
bill and after due verification
certify the bill for the payment.
The Employer may get the
work verified, through some
designated officer equivalent to
the rank of Executive Engineer.
Such designated officers shall
verify the work to the extent of
5% and recommend the bill for
payment. The Employer shall
pay the Contractor the
amounts certified by the
Engineer within 28 days of the
date of each certificate.
8 PMC : Please specity the scope of the PMC for the work PMC not appointed for this
project. Architect for this
PMC
project is Landmark Design
Group
9 Schedule B The Contractor shall carry out As per Clause No.9, Schedule B, Page No.8 of Vol.II, (NIT prevails)
Note 9 of laisioning work with PCMC,contractor shall carry out laisoning work with Local Bodies
Volume II MSEB, Local bodies Gov.
for various permissions. Please delete this responsibility
Maharashtra, Gov Of India ,HPCL from the contractor as it will be easy for PCNTDA to co-
and All authorities to get ordinate this activity.
permission required for completion
of the project including but not
limited to water connection,
drainage connection, permission
regarding Electrification ,Solar,
Fire fighting, Culvert work and all
3
other required permission.
10 Section 1 The Earnest Money shall be Earnest Money Deposit /(Bid security): Please accept the (NIT prevails)
Clause paid by net banking gateway Earnest Money Deposit /(Bid security) in the form of bank
16.2Instructions system by using digital guarantee also.
to Bidders registration key as stated in
Appendix to ITB.
11 Section 1 The Earnest Money of Refund of Earnest Money Deposit /(Bid security): Please (NIT prevails)
Clause unsuccessful bidders will be refund the Earnest Money Deposit /(Bid security) of other
16.4Instructions returned within 30 days of the than L1 &L2 within 30 days of opening of financial bid.
to Bidders end of the Bid validity period
specified in Sub-Clause 15.1.
12 Section 1 The Earnest Money shall be EARNEST MONEY DEPOSIT: ( NIT Page 4 Vol-I) (NIT prevails)
Clause paid by net banking gateway
16.2Instructions system by using digital We request you to accept the Bid security in the
to Bidders registration key as stated in form of Bank Guarantee instead of paying by
Appendix to ITB. Gateway system and issue a suitable Bank
Guarantee format with following para :
4
these details are submitted. Since “The Chief
Executive Officer PCNTDA Pimpri Chinchwad New
Town Development Authority, Near Akurdi Railway
Station, Pune - 411044.” is the beneficiary of Bank
Guarantee towards Bid security for the subject
tender, we request you to kindly share the relevant
details The Chief Executive Officer PCNTDA Pimpri
Chinchwad New Town Development Authority Pune
44.
13 Appendix to ITB List of Key Plant &Equipment Plant &Equipment : ( Annexure –I on pg. 33-36 VOL- I) (Please Read Addendum and
Annexure-I to be deployed on Contract Corrigendum attached )
Work. We have noticed that the number of plant & equipment
specified vide Annexure are very much on higher side with
respect to the scope & quantum of work in the scope of
present tender.
5
Clause 12.1 (vi) on the rolls of the tenderer Vol-I )
giving details of experience
and qualification of each of
them and details of technical We presume that only Bio-data, Qualification and signed
personnel to be appointed for undertaking from bidder Authorized signatory minimum
this project along with bio-data required of technical personnel to be deployed for this
duly signed by the person to be project can be submitted along with tender for compliance &
appointed on the Bidders following details may be submitted by the successful bidder
letterhead. after award of work.
Undertaking signed by respective Technical personnel
Experience Certificates Kindly confirm.
15 Section 4 The amounts of the advance MOBILISATION ADVANCE: Vol. I, Contract Data Pg.109, (NIT prevails)
Contract Data payment are Cl. 32
Clause 32 Mobilization advance – We request you to pay 10% interest free mobilization
DELETED advance against submission of bank guarantee and shall be
recovered from 3rd RA Bill on prorata basis.
16 Section 4 The amounts of the advance MACHINERY ADVANCE: Vol. I, Contract Data Pg.109, Cl. (NIT prevails)
Contract Data payment are 32
Clause 32 Equipment advance – You are well aware that the sophisticated machineries are
DELETED required to be deployed to complete the project within the
stipulated period. We therefore request you to pay 5%
interest free Machinery advance against submission of Bank
Guarantee.
17 Section 4 The amounts of the advance SECURED ADVANCE: Vol. I, Contract Data,Pg.109, Cl.32, (NIT prevails)
Contract Data payment are We request you to pay 75% secured advance on material
Clause 32 Secured advance for in non brought to site.
Perishable materials brought to
site– DELETED
18 Section 4 The proportion of payments RETENTION MONEY: Vol. I, Contract Data,Cl.27, Pg 112 (NIT prevails)
Contract Data retained (retention money) and Vol. II,Pg.3
Clause 27 shall be 6 % [Cl. 48] from It is mentioned in Vol.I, Pg 109 that retention shall be 6 %
and Vol II each bill subject to a maximum from each bill subject to a maximum 5% of final contract
of 5% of final contract price. price. However it is mentioned in Vol. II, Pg 3 that Security
deposit / Retention to be paid in following manner.
.
Security Deposit 2% of Contract sum in the form of FDR. (Addendum and
(i) In the form of FDR Rs 3% of Contract sum To be deducted from Running bills at Corrigendum attached)
2% of Contract sum the rate of 6%.
(ii) To be deducted from
Running bills (6%) Rs Further it is mentioned in Vol. II, Pg 3 that “Alternatively
6
3% of Contract sum bidder can pay performance security / security deposit in the
TOTAL Rs 5% of form of bank guarantee as stated in the bid document
Contract sum
We presume that retention / security deposit shall be
accepted in the form of BG initially instead of FDR and cash
retention from RA bill
21 Section 4 The Intended Completion Date MILE STONES: Vol. I, Contract Data, Sr. No.6,Pg.108 (NIT prevails)
Contract Data for the whole of the Works is 15 The details for mile stone 1,2, &3 i.e. physical work to be
Cluase 6 (Fifteen) months after completed are not provided. Kindly provide the same.
start of work with the
following milestones:
[Cl.1.1, 17&28]
Milestone dates : Physical
works to be completed Period
from the start date [Cl.2.2
&49.1]
Milestone 1 i.e.._. 5 months. 25
% work.
Milestone 2 1.e.:.,.. 10 months.
60 % work.
Milestone 3 i.e., 15 months.
100% work.
22 Section 4 Price Variation - Deleted Price Variation: Vol. I, Contract Data,Cl.26,Pg 97 (NIT prevails)
Clause 26 Price We are surprised to note that escalation clause is not
Variation included in the tender. You will kindly appreciate that this
is very voluminous work to be completed in a period of
15 months; facing one financial budget. Hence contracts
may get affected due to the reasons not attributable to
the contractor such as agitation by local villagers, labour
strikes, transportation strike, natural calamities etc. It is
also observed that there is substantial unpredictable
cost variation in labour, material &POL due to various
factors such as Govt. Policies, International Market
rates, currency fluctuations, inadequate availability of
raw materials, labour cess etc., which is very difficult to
assess and provide the cost for the same in the quoted
price. Bidder can only estimate and quote the prices
of items for which adequate details and sufficient
information is available. However, since the escalation
on material, POL, labour in future is dependent on
various factors as mentioned above, no one has control
8
over the same and therefore it is not possible to
estimate and quote the escalation for future years, which
results in speculation by the contractor about provision
for the same in quoted price. Hence the speculative
escalated cost provided by the contractor may lead to
higher cost resulting in direct loss to client and lower
escalated cost may lead to inferior quality, disputes etc.
due to unworkable quoted price. In view of this, it is
fairly reasonable and very logical to include
escalation clause as per standard formula of CPWD
for this voluminous long duration of tender ,which
certainly will form common platform to all bidders.
23 Submission -Your good self is well aware that voluminous (NIT prevails)
work is involved such as getting quotations for specialized
items, rate analysis, site investigation etc. We, therefore
request you to extend the date of submission by minimum 2
weeks after all the clarifications are given in writing, so that
we shall be in a position to submit most competitive tender.
This will be in the best interest of the project &client.
24 Section 4 The amounts of the advance It is request to you kindly give us 10% Interest free or (NIT prevails)
Contract Data payment are interest bearing mobilization advance against Bank
Clause 32 Mobilization advance – guarantee. As the job involves large fleet of machinery,
DELETED mobilization advance to the tune to 5% of contract amount.
This will eventually help to reduce rates for the department
(All MA to be recovered by the time 80% work value is
achieved)
25 Vol II Schedule Supply of Polygonal / Circular Kindly provide drawings & design for gantry structure which Drawing attached with this
B Item No. 33 hot dip galvanized cantilever not attached. CSD
structure for the overhang of
4.17m along with suitable
foundation bolt sets made up of
High Tensile sheet confirming
to BSEN 100025 or equivalent,
as per reference cantilever-
structure suitable for mounting
of single sided message board
of size 3660mm x 1830mm on
one side &logo board of size
3050mm x 915mm on the other
side. Galvanization thickness
for the cantilever structure
should be avg 85 microns.
9
26 Section 4 Price Variation - Deleted As per PWD GR dated 23/10/2017 Price variation is allowed (NIT prevails)
Clause 26 Price for those work for which period of completion is more than
Variation 12 months. But this contract period is 15 Months.
27 Section 3 There is a contradiction in two clauses. We consider the (Please Read Addendum and
The Defects Liability Period is meaning as, “ Defects Liability Period is 1 year and Corrigendum attached )
Condition of
1 Year excluding Road work Maintenance period for 1 more year thereafter The Defects Liability Period
Contract (For Road Work 3 Year) and
A. General & is 1 Year excluding Road
Maintenance Period is 2 Years.
Section 10 Cl- work. (For Road Work and
25 Other Concrete work - 3 Year)
For period specified as the and After completing DLP
“Defect Liability and Period Maintenance Period is
Maintenance Period of 3 years” 2 Years for remaining other
for the work
work such as Landscape,
starts from the date of issuance
Electrical and etc
of the completion certificate or
issuance of completion
certificate
for the project work whichever
is later in accordance with para
"Final Inspection and
Acceptance" contractor shall
remain liable for any of the
works or parts thereof or
equipment and fittings supplied
which in the opinion of the
ENGINEER fail to comply with
the requirements of the
contract or are in any way
unsatisfactory or defective..
28 Vol – II After completion of project In absence of any payment clause for electrical bulbs & (NIT prevails)
Street Lights Street light should be hand lights, How contractor is to replace fuse bulbs without any
over to Pimpri Chinchwad payment after completion?
Muncipal Corporationby
the contractor with the help
of client. Until hand over
process is in progress,
contractor is responsible to
maintain street light
operation like Replacement
of the lights should take
place as mentioned in the
LED light specification & as
per PWD Red Book.
10
Electricity bill for the period
between final bill and
handing over streetlight
shall be paid by PCNDTA.
29 Appendix to ITB List of Key Plant &Equipment Minimum ownership of desired machinery may prove as a (Please Read Addendum and
Annexure-I to be deployed on Contract constraint. As such hired machinery under contract Corrigendum attached)
Work. agreement may kindly be allowed.
30 Section 1 -ITB For work, the bidder should We request to accept the similar type of one work of 30% as (NIT prevails)
Cl-4.5 A (b) have also achieved following per the GR
work(technical) experience
prescribed below, for which bid
has been invited, in last 5
years ending last day of month
previous to the one in which
bids are invited, should be
either of the following
i) 3 similar type work (Road
Work, Road and
Infrastructure Development
Work) each having cost Rs
20 Cr. OR
31 Section 1 -ITB For work, the bidder should Request to consider Experience in Turnkey contract (NIT prevails)
Cl-4.5 A (b) have also achieved following infrastructure Project work includes (Earthwork land
work(technical) experience development, electrification, Civil, road, waterline, electrical
prescribed below, for which bid substation etc.) in single work.
has been invited, in last 5
years ending last day of month
11
previous to the one in which
bids are invited, should be
either of the following
i) 3 similar type work (Road
Work, Road and
Infrastructure Development
Work) each having cost Rs
20 Cr. OR
34 Please consider weightage of 10% per year for the cost of (NIT prevails)
work completed and turn over to update it up to 2018-19
price level
35 Please revise the quantity required as per 30% of Tender (NIT prevails)
Quantity and Machinery own and hired as per practice
accordingly
36 Section 1 -ITB i) 3 similar type work (Road We presume that term "Infrastructure Development" Experience of Flyover,
Cl-4.5 A Work, Road and includes flyover, Bridges as similar work please clarify. Bridges will be considered
Infrastructure Development provided quantity criteria is
Work) each having cost Rs satisfied as per ITB ,Clause
20 Cr. OR 4.5 A (c).
ii) 2 similar type work (Road
Work, Road and
Infrastructure Development
Work) projects each having
cost Rs 25 Cr OR
39 Section 4 The amounts of the advance Please allow Mobilization and Machinery (NIT prevails)
Contract Data payment are
Clause 32 Mobilization advance –
DELETED
40 Please allow all machinery Own/Hire basis (Please read Addendum and
Corrigendum attached )
13
41 Vol I ,Clause no The expenditure on this project Please clarify availability of fund Funds are available,
2,Pg no 8 will be PCNTDA 's own
42 Vol I ,Pg no 28 , HPCL pipeline What is the status of permission for HPCL Permission received from
HPCL
43 Please Provide the Soil investigation report (Please read Addendum and
Corrigendum attached ).
44 Vol I ,Pg no 29 , Internal Road work What about the payment of internal road please clarify (NIT prevails)
45 Vol I ,Pg no 31, Retaining Wall Can we suggest the alternative design for retaining wall (NIT prevails)
46 Vol I ,Pg no 31, Proof Checking Please allow other alternative option government and private (NIT prevails)
agency
47 Vol I ,Pg no 68 During the entire contract This is the overburden of construction cost we request you (NIT prevails)
duration, the contractor shall to please cancel this clause.
provide Two nos new brand
Tata Nexon / Maruti Suzuki
Swift or equivalent with diesel,
driver & maintenance for a
running of at least 3000 Kms
per month with in a fortnight
from the date of award of the
contract for the field
engineering staff of Employer,
In case of failure to provide the
vehicle, an amount of Rs.
2000/-(Rupees Two Thousand
Only) per day per vehicle shall
be recovered from the
contractor’s due payment. The
cost of these facilities is
incidental to work and deemed
to be included in the offer given
by contractor
48 Allow use of crushed sand and flyash (NIT prevails)
49 Please allow price variation (NIT prevails)
50 Vol I ,Pg no 98 Bonus- Deleted Please allow bonus (NIT prevails)
51 Please allow time limit 24 months instead of 15 months (NIT prevails)
52 Vol I ,Pg no 36 Project Manager/ Ammend experience of Civil Engineering work for 10 years (NIT prevails)
Resident Engineer out of which 5 years shall be in Road/Highway works
B.E. Civil + 20 Years Exp
(5 years as a Manager in
Road Construction)
53 Section 4 The proportion of payments Generally security deposit is 2% in other department also as (Please read Addendum and
Contract Data retained (retention money) per PWD GR it is now 1%. So we request you to amend this Corrigendum attached )
Clause 27 shall be 6 % [Cl. 48] from clause accordingly as SD = 1% of contract cost.
14
and Vol II each bill subject to a maximum
of 5% of final contract price.
Security Deposit
(i) In the form of FDR Rs
2% of Contract sum
(ii) To be deducted from
Running bills (6%) Rs
3% of Contract sum
TOTAL Rs 5% of
Contract sum
Notes –
1) Words in brackets (----) indicate clarifications
2) Corrigendum – Means tender provisions are changed/replaced
3) Addendum – Means additional conditions are specified.
4) All other issues not addressed stands as per provisions of tender.
15
PIMPRI CHINCHWAD NEW TOWN DEVELOPMENT AUTHORITY, AKURDI, PUNE- 411 044.
Common Set of Deviation
Name of Work : Development of Outdoor Exhibition and Park Land in Sector 5 & 8 at Moshi, Pune 412 105.
16
13 Tandem Roller 15 1 1 2 (Minimum 80-
14 Concrete Mixes 15 1 1 2 100 TPH
with Capacity)
Integral Weigh 1 Paver Finisher 15 1 1 2
Batching facility 0 with Electronic
15 Concrete Batching 15 1 0 1 Sensor
and Mixing Plant 1 Water Tanker 15 2 3 5
(Minimum 1
Capacity – 30 Cum 1 Bitumen 15 1 1 2
/ hour) 2 Sprayer
Total 35 44 79 1 Tandem Roller 15 1 1 2
3
1 Concrete 15 1 1 2
4 Mixes with
Integral Weigh
Batching
facility
1 Concrete 15 1 0 1
5 Batching and
Mixing Plant
(Minimum
Capacity – 30
Cum / hour)
Total 30 49 79
4 Affidavit ( on Rs.500/- Stamp Paper)
Affidavit
I ....................................................
age ......................................
address ........................................ (Authorized
signatory to sign the contract), hereby submit,
vide this affidavit in truth, that I am the owner of
the contracting firm ....................................
/authorized signatory and I am submitting the
documents in envelope no.1 for the purpose of
scrutiny of the contract. I hereby agree to the
conditions mentioned below :-
1. I am liable for action under Indian Penal Code
for submission of any false / fraudulent paper /
information submitted in envelope no.1.
2. I am liable for action under Indian Penal Code if
during contract period and defect liability period,
any false information, false bill of purchases
supporting proof of purchase, proof of testing
submitted by my staff, subletting company or by
myself, I will be liable for action under Indian
Penal Code.
3. I am liable for action under Indian Penal Code if
any paper are found false / fraudulent during
contract period and even after the completion of
17
contract ( finalisation of final bill ).
(Signature of contractor)
(seal of company)
(Contractor note that Affidavit Uploaded along
with CSD.Bidders have to fill up on Rs.500/ stamp
paper duly signed and shall be uploaded with
tender document)
(If it is observed that contractor have submitted
any false/fraudulent paper/information, after issue
of work order to the contractor, and if the work in
the contract are at initial stage then contract will
be terminated.
Contractor will be blacklisted in this case.)
(The contractor will be solely responsible, if any
false/fraduent paper/information, quality control
reports, test reports,any correspondence, bills
are found during finalisation of tender and
execution of work as well as Defect Liability and
Maintenance period.Any officer from PCNTDA will
not be held responsible for this activity.)
7 The soil investigation reports uploaded with CSD and
Soil Investigation Report they are for information purpose only.
The most responsive bidder will have to
conduct soil investigation (As directed by Engineer in
Charge) and prepare structural
design based on this investigation only.
8 Operation and Maintenance of Landscaping and all
Operation and Maintenance other works like Electrical, Fire Fighting etc shall be
done by the contractor at his own cost in Defect
Liability Period. The work includes necessary watering,
maintenance of trees, lawn providing necessary
labours and other allied works etc.
For remaining Operation and Maintenance period (2
years) payment shall be made as per NIT.
Engineer Contractor
GEOTECHNICAL REPORT FOR PROPOSED OUTDOOR EXHIBITION PARKLAND@ SECTOR-5 & SECTOR 8
PCNTDA, MOSHI
1.0 Introduction.
PIMPRI –CHINCHWAD NEW TOWN DEVELOPMENT AUTHORITY(PCNTDA) have proposed an Outdoor Exhibition
Parkland in Sector5 &Sector 8, PCNTDA ,Moshi
The Detailed Layout of this Park land can be seen in the Drawing as prepared by the Design /Landscape
Architects
M/s Landmark Design Group based in Pradhikaran, Nigdi are the Design Architects for the Project.
The Competent Authority @ M/s Landmark Design have appointed M/s Gensys Technologies P.Ltd , based in
Pune to be the Structural Designer’s for the RCC components in this Project.
SE
Further as required by PCNTDA, M/s Landmark Design Group assigned a Geotechnical Investigation to be carried
out at specific locations on the Plot, to assess the sub-stratum conditions , so the parameters of the same could
assist in Structural Design
PO
The Geotechnical Investigation work was executed in Late September to early October 2014.
This Report submitted describes the observations, results of Investigation with recommendations in relation to the
proposed structures in the project corresponding to the Bore hole data in the vicinity.
R
A Site Layout Plan is attached in the Annexure depicting the Bore Hole Location.
PU
2.0 Scope of Work:-
It was planned to conduct 4 bore holes at pre fixed locations to cater to the Structural Designer’s requirements.
The Investigation was thus scheduled as follows,
1.Trial Borings at 4 locations prefixed by the Architects/Consultants and as approved by the Competent Authority
at PCNTDA and are planned to collect representative sample of soil/rock. The Bore Holes to be marked out in
Y
such manner so as to analyze roughly properties of stratum within the vicinity of proposed structure
2.To carryout Standard Penetration test in overburden soils preferably at 1.00m depth interval for ‘N’ value and
D
when rock is encountered to drill in rock ,for good depths to ensure continuity of competent stratum.
3. To neatly label all samples from bore holes for classification and in case of rock to assess the same for REC
U
/RQD parameters. All samples shall be neatly stored in wooden core boxes and submitted to Client’s Engineer
for good storage, in case of ready reference in the future.
ST
4. To carryout relevant laboratory tests on soil, rock and sub-soil water samples as encountered & for suitable
and relevant parameters of substratum under consideration.
5. To note the Ground Water Level in each bore hole after completion of Bore Hole.
6. To Prepare a Recommendation Report on Field/Laboratory Data in regards to the proposed structure under
R
consideration.
FO
3.2 The drilling rig, Standard Rotary Type coupled with Diesel engine fitted to a Tripod Frame with all drilling
accessories and generally suitable for Geotechnical Investigation works wherein driving of casings, drilling in rock
and extraction of samples by core barrel arrangement conducting standard penetration tests was installed at the
specified bore hole locations The bore hole is commenced by driving suitable casings in overburden so as to prevent
the collapse of bore holes. When rock is encountered the driving of casings is stopped.
Wash/Disturbed sample as may be the case are collected from soil to classify the strata and neatly stored in
polythene bags.
3.4 Standard Penetration Test(SPT) is conducted in the bore hole preferably at 1.00m depth interval in the
Address:- Bldg No.A/49, Flat No.1363 , M.I.G Adarsh Nagar Worli, Mumbai:-400 030 contd……
Tel No:- 91-22-2422 92 96, 2431 86 20 Tel Fax No. 91-22-422 9296. E-mail:- shailesh_zantye@yahoo.com
Pg 2
overburden soil layers. SPT is conducted in accordance to IS:2131-1981. In this test a bevel edged cone
(SPT cone) connected to a split spoon sampler is driven in to the soil under the blows from a Monkey hammer
weighing 63.5 kg. The blows are hammered to the split spoon assembly under free fall from a height of 75cms
st
above a guide coupling. After the initial seating reading of 1 set of 15cms the no of Blows required to penetrate
nd rd
the 2 & 3 set of 15cms ie. 30 cm penetration is recorded as the ‘N’ value. The ‘N’ value is indicative of relative
density of cohesion less soil and consistency of cohesive soil. Samples collected from the split spoon assembly
are visually assessed for classification.
3.5The drilling in rock is done using “ NX” Diamond Bit and Core Barrel. The Diamond Bit facilitates the neat and
efficient cutting of rock. The rock sample retrieved are assessed for the Core Recovery Percentage and RQD(Rock
Quality Designation) defined as the sum of length of rock pieces each having length greater than 10cm/ total
length of core drilled. The rock samples are then labeled with all details such as BH No, Rock Core No, depth and
neatly stored in wooden core boxes handfed over to the Client’s/ Owners of Project for any future references.
SE
3.6 On completion of bore the G.W.L is observed and noted . Water samples are collected in plastic jars for
testing. Also representative, relevant soil (subject to minimum quantity and satisfactory quality ) / rock samples at
different depths in bores are selected for Laboratory testing.
PO
4.0 Local Geology.
As per IS1893-1984; the area of the site has been classified as Volcanic rocks and minor basic intrusive.
R
The general area of the project consists mostly of nearly horizontal dispersed lava flows of Deccan Trap Basaltic
Formation of Cretaceous to Eocene age.
PU
Layers of Parent Basalt formations are generally encountered in this area. The thickness of this Igneous Rock
in this area is anticipated to be more than 500m.
As the depth progresses the surfacial residual soils grade into original bed rock, generally with one or more
intermediate stages of decomposition or weathering. These Igneous rocks are generally of horizontal deposition.
Y
The rock encountered at the bore hole locations is High to Moderately Weathered but seen with very predominant
D
Joints and Fractures. As the depths progressed the rock encountered was a Fresh Basalt with the Jointing Pattern
improving considerably within such depths.
U
As per IS 1893 2002, the site falls under Seismic Zone III. No Fault lines are known to occur in close proximity of
the site.
ST
5.0 Sub-Surface Conditions on Site:- A total of 4 Bore Holes have been taken on site
5.1 LAYER I/IA :- Residual strata /CWR. The bore holes commenced with a Residual Disintegrated Stratum
comprising of In-situ Boulders with pockets of Sandy /Rock Gravels or Core stones to a Completely Weathered
R
Rock This Layer is a consequence of the complete in-situ disintegration of parent rock materials, due to hydro
thermal agencies and depending upon the degrees of weathering has got converted to the texture of Sand/Rock
FO
gravels wherein the mass structure and parent material fabric is seen to be totally destroyed OR as In-situ
Boulders/ CWR (core stones) wherein all the rock material though totally decomposed ,the original rock mass
structure is largely intact. The materials comprising this Layer are inter-trapped in the Boulder/ Gravels zone
whereas the CWR is largely a discontinuous framework of core stones. The lower boundaries of this Layer are
observed generally from 0.60-1.00m below respective G.L . However in BH3 depth of this stratum is observed to
be extended upto 5.00m below G.L. Wash / Disturbed samples are collected from this layer for representation.
Due to presence of Sandy/ Rock Gravels in significant proportions in Layer 1 with Boulders the Standard
Penetration test conducted in BH-2 shows a Refusal value i.e N>50.
Due to very insignificant presence of soil layer, the same inter trapped with Boulders no True soil or disturbed
Sample is available in this layer for Laboratory testing
5.2 LAYER II :- Highly Weathered Basalt with Close Joints :- A bedrock in a Highly Weathered state is
underlying the Boulder/CWR stratum. The Core Recovery in this Layer is varying from 13 % - 29% and RQD from
0-20%. The rock mass within this zone is in a poor state of Joints/Fractures.
Address Bldg No.A/49, Flat No.1363 , M.I.G Adarsh Nagar Worli, Mumbai:-400 030. contd…..
Tel No:- 91-22-2422 92 96, 2431 86 20 Tel Fax No. 91-22-422 9296. E-mail:- shailesh_zantye@yahoo.com
Pg 3
UCS values for representative rock samples tested within this zone are 204 -246kg/cm2 This indicates the Rock
Strength to be of above Average to near Strong.
The lower boundaries of Highly Weathered Basalt are observed generally upto1.00 - 4.00m (BH-2) under
respective G.L’s
5.3 Layer III :- BED ROCK:- Occasionally Moderate with Medium Joints to Fresh Basalt
Gray /Gray Black a massive Basalt Occasionally Moderate with Close Joints gradually progressing to a Fresh
Basalt is observed through this layer . The Core Recovery is varying from 50% to 93% and RQD from 42 -91%
The RQD values indicate the Rock mass within this zone to be Fair to Excellent
UCS values for representative rock samples tested within this zone are varying from287 -338kg/cm2 This indicates
the Rock Strength to be near Strong.
The Bore Holes BH-1 -2 -4 are terminated in this zone at 5.00m depth below respective G.L
SE
It should be understood in context to the above described in Para5.2 & 5.3 that all grade of weathering may not be
seen in a given rock mass and that in some case a particular grade may be present to a very small extent .
Distribution of various weathering grades of rock material in a rock mass may be related to the porosity of rock
material and the presence of open discontinuities of all types in a rock mass.
PO
5.4 GROUND WATER LEVELS.
Ground Water Levels are monitored on completion of Bore holes. The levels on site are found to vary b/w 3.25 -
R
4.35m depth in bore holes. During the period of Investigation which is Late September 2014, most of the monsoon
has been over, however during the Field work, some spells of withdrawal monsoon were experienced
PU
The Levels thus recorded at a specific time interval are subject to such Seasonal & Annular Fluctuations
5.5 The Layers as described above in Para 5.1 to 5.4 can be summarized as follows wr.t to corresponding location
and relevant R.L’s in Table’s Below. The depths to these layers may vary in b/w bore holes
TABLE 1- Depths to Layer as encountered in bore holes
Y
BH 1 +602.500 +601.700/ 0.80 +601.50 / 1.00 +597.50 / 5.00 +598.15 =4.35m Central Park
BH 2 +602.000 +601.00 / 1.00 +598.00/ 4.00 +597.00 / 5.00 +597.90 =4.10m RW near Sec F-F’
U
BH 3 +606.000 +601.00 / 5.00 N.E N.E +601.70= 4.30m RW near Sec H-H’
ST
BH 4 +604.000 +603.40 / 0.60 +603.00/ 1.00 +599.00 / 5.00 +600.75=3.25m Near Sec J-J’
N.B:- Ground Level’s as above in R.L.M are furnished by the Client’s / their Authorized Representative for the site.
Location as described is in the vicinity of actual spot for Bore Holes BH-2 -3-4. As such there may be a level
Difference b/w the Ground Level for two .
R
6.1 BH 1 is conducted in Open Central Parkland. This is proposed to be a Outdoor exhibition area. Here the Bore
Hole is commenced from R.L +602.500m and within 1.00m a Highly Weathered Basalt is encountered followed by
A Fresh Basalt. As seen from the layout Plan there is no structure planned in this area. However for academic
2
purpose and representation incase of any planning for the future a SBC of 200T/m can be utilized from 1.00m
below on Fresh Basalt. Settlement will be 6.00m (permissible =12mm)
It is to be understood that there is a substantial difference in G.L on Plot, and in the Open Central Ground too the
levels as seen from the layout Plan have a elevational difference of 2-3 m. So the SBC recommended above
shall be adopted in context of Fresh basalt , the level for which may vary as per Ground elevation.
6.2 BH2 is conducted b/w Sections E-E’ & Section F-F’ and the findings from this location are considered as
representative for recommendations on any structure within the said sections.
Along Section E-E’ there is no Major structure apart from the Toilet Blocks which are seen extending from R.L
+602.00m to 598.00m .At Section E-E’ the Ground R.L as seen from the Layout drawing is around +596.00m
so here there is requirement of Fill for around 2.00m to rest the Toilet Blocks @598.00
Address:- Bldg No.A/49, Flat No.1363 , M.I.G Adarsh Nagar Worli, Mumbai:-400 030 contd……
Tel No:- 91-22-2422 92 96, 2431 86 20 Tel Fax No. 91-22-422 9296. E-mail:- shailesh_zantye@yahoo.com
Pg 4
Along Section F-F’ a retaining wall is planned as seen from R.L Approx +603.00m to 598.00m. Relating to
the findings of BH-2 this will involve a vertical excavation of around 4,00m to reach R.L of +598.00m
A SBC of 100T/m2 can be utilized to support the Retaining Wall at R.L +598.00m on a Highly Weathered Basalt.
Settlement will be less than 12mm. Differential settlement shall be ½ of this value.
Minimum width at the bottom shall 1.00m
6.3 BH3 is taken along Section H-H’. Here a Retaining wall with steps is to be constructed from R.L +606.00m to
600.00m. The Bore Hole is taken from R.L +606.00m. This in all probability involves a vertical excavation in excess
of 6.00m to found the Retaining wall. The Bore Hole findings show a presence of completely Weathered Basalt
to be the influencing strata through excavation depths.
A SBC of 50T/m2 can be utilized to support the Retaining Wall at R.L +600.00m on a Completely Weathered
Basalt. Settlement will be less than 12mm. Differential settlement shall be ½ of this value.
Minimum width at the bottom shall 1.00m
SE
6.4 BH4 is taken along Section J-J’. There is no major structure planned here except for a 12m peripheral road
The Bore Hole is commenced from a R.L +604.00m. Through the bore hole findings a Highly weathered Basalt is
seen from 0.60 -1.00m underlying the Residual soil strata and followed by Fresh basalt from 1.00m
PO
For representation a SBC of 200T/m2 can be utilized from 1.00m below on Fresh Basalt.
The Ground Level is observed to varying in the range of 2-3 for the Bore Hole location and section J-J’. Hence in
future any construction is carried out in this area, the SBC shall govern for Fresh Basalt, the R.L for the same
R
may vary.
PU
6.5 Ground water Levels in general are below. At Sec F-F’ and Section H-H’ foundation excavations will be
carried out It is seen from Table-1 that the GWL @ BH-3 (influencing Sec-H- H’) is within the Foundation Level
as proposed. Further due to the Topography of the area , difference in elevations and more so the presence
of CWR with close Joints , a possibility of water collection in pits cannot be neglected /overlooked.
So adequate de-watering arrangement shall be maintained at such locations where the foundation excavations
Y
are to be carried out. Minimum costs for the same shall be provided in foundation estimates.
D
pass through Residual stratum /CWR, Highly Weathered Basalt & finally the Fresh Basalt as may be required.
The foundation excavations may be sloped 2:1 in overburden soils/ CWR (Rec < 15%) to avoid slippage during
ST
At Section F.F’ /Section H-H’ wherein Retaining walls are planned , the excavations are likely to pass through
HWR./ CWR. The excavations may be proceeded as described herein above . However a concern on slippage
R
of the CWR-HWR even after the excavations are completed cannot be ruled out .
At Section F-F’ the Retaining wall can be constructed touching the vertical rock surface . This itself will act as a
FO
However at Section H-H’ the Retaining wall will be constructed with steps. The steps in itself can be carved out of
Rock excavations thereby acting as a barrier along the section with step rise. The Balance area over the vertical
face of CWR/HWR can be treated by Guniting which will allow the binding of joints in rock surface, top of such
Gunited surface can then be provided a decorative pointing with a locally broken stones for Aesthetic effects.
This would be a economic way of treating such sections where required
*Other methods that could be engaged to provide slippage would be use of High to Medium strength Boulder Net
(HSBN/MSBN). Long term stabilization methods could include
1. Shortcreting and Rock Bolting
2. Toe wall and drainage improvement by providing catch water drains
3. Provision of Berm at rock –soil interface
The general site terrain is seen to be rocky with a minimal Residual cover comprising of Boulders /Granular
Address:- Bldg No.A/49, Flat No.1363 , M.I.G Adarsh Nagar Worli, Mumbai:-400 030. contd…
Tel No:- 91-22-2422 92 96, 2431 86 20 Tel Fax No. 91-22-422 9296. E-mail:- shailesh_zantye@yahoo.com
Pg 5
Fragments of rock,other Granular/ Gravelly materials
This is going to involve a significant , time consuming and costly exercise of rock breaking to achieve finished grad
levels for landscape design as well as the major excavations for founding Retaining walls
Heavy duty Rock breakers will have to be employed and the noise arising out of such huge rock excavations,
clearing of rock debris are some of the issues which will require adequate planning and costs in foundation
estimates.
Any undulations in rock surface at recommended footing depth shall be done good by laying PCC in such areas
where the difference in elevation is observed . After filling such areas and the difference in elevation is done good
a uniform 100 thk PCC Pad may be provided below foundations to achieve even ground and uniform load transfer
to bearing stratum below.
As a matter of prudent caution any Ground water/ flowing water from adjoining higher elevations should not be
allowed to collect in foundation excavations for Retaining Walls. This may cause a softening of bearing strata at
recommended F.L. As such the construction of foundations /Retaining walls shall be completed in good time once
SE
the excavations have reached recommended foundation levels.
PO
Sec F-F’ will have approximately 1.00m of Retained earth as seen from the Sectional Layout (from R.L 602.00 to
603.00m). At Sec H-H’ the Retaining wall is with steps . As earlier explained the steps may be carved out of rock
excavations and the balance area may be treated for possible slippage of loose rock .As such there is no retained
R
earth for this Section .
In case of any future development wherein construction of Retaining walls may involve the structure to be
PU
subjected to lateral pressures due to retained earth , the Lateral Earth pressure Parameters can then be
recommended for design of such Retaining walls.
chloride (As Per IS 456 :2000 and CIRIA SP Publication No 31). As such the chemical environment on the site
can be termed Non-aggressive. A “Mild” exposure condition is assigned to site.
D
Following general precautions may thus be followed to protect the Foundation steel and concrete.
TABLE 4
U
It is to be noted, the recommendations and description of strata is based on the findings from the bore holes at
specified locations. It is assumed that the Geological conditions will not deviate much however the depths of strata /
FO
GWL may vary in between the borings , over a larger Plan area under consideration
This Report is submitted to Competent Authority with the understanding that contents herein are brought to the
attention of Design Engineer/ Structural Consultant/Architect as guidelines to enable him/them to anticipate, initiate
and design better
The Report shall not hold good in case the Structures(Retaining walls) are located away from the scheduled/
proposed location at time of Investigation. If such case, do arise same shall be brought to the notice of the author
for alternate recommendations /Investigations to note the deviations if any, in strata.
Sincerely,
For Simple Drilling and Construction Co.
Shailesh.M.Zantye
B.E (Civil) ,M.I.G.S (Mum)
Chief Technical Head- Geotechnical Date:- 11-10-2014.
Address:- Bldg No.A/49, Flat No.1363 , M.I.G Adarsh Nagar Worli, Mumbai:-400 030. contd…
Tel No:- 91-22-2422 92 96, 2431 86 20 Tel Fax No. 91-22-422 9296. E-mail:- shailesh_zantye@yahoo.com
Pg 6
BH 1 from 1.00 m below G.L i.e From R.L + 601.500 m below on Fresh Basalt
SE
qs= 3238 x 0.1 = say 323.80 T/m 2
Referring to the Clause9.2.i(a) of the above IS Allowable Bearing Pressure with allowance for weathering,
PO
2
discontinuities in rock , & submerged water condition consider 323.8 x ¾ = 242.85 T/m
2
Restrict to 200 T/m
Alternately by RMR Method.
Ref:- Soil Mechanics and Foundation Engineering by K.R.Arora ,Page 825 ,
Table 31.8
R
PU
Unconfined crushing strength of rock cores tested = 323.38 kg/cm2 = 32.3Mpa , RMR increment = 4
Assuming Joint Spacing to be considered 0.30 -1.00, therefore RMR Increment = 14 (by Interpolation)
U
By the above Two Trials , but for all practical purposes , for design restricted to 200T/m2
Address:- Bldg No.A/49, Flat No.1363 , M.I.G Adarsh Nagar Worli, Mumbai:-400 030. contd…
Tel No:- 91-22-2422 92 96, 2431 86 20 Tel Fax No. 91-22-422 9296. E-mail:- shailesh_zantye@yahoo.com
Pg 7
2
B. SETTLEMENT OF FOOTINGS EXERTING PRESSURE OF 200 T/m
th
Ref:- Foundation Analysis and Design, J.E. Bowles, McGraw Hill Publication, 5 Edition, 1996.
SE
M=4 for center of footing
Is= Influence factor =0.53 and If= Footing depth factor = 1.0(from table 5.2 Ref 1)
PO
Thus S1= 200 x 2.5 x 1- 0.252 x 4 x0.53 x1.0= 0.00584m = 5.84mm = say 6 mm (permissible 12mm) Thus OK
1,70,000
So 200T/m2 is good for design from 1.00m (R.L +601.500m) near BH-1
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
R
BH 2 near to Section F-F’ SBC @ R.L +598.00 m interface of HWR- Fresh Basalt
PU
A. By Compressive strength of rock core sample:-
2 2
@ R.L + 600m UCS = 204 kg/cm and R.L :- +597.15m UCS =287 kg/cm
Refer IS 12070:-1987 Code of Practice for Design and Construction of Shallow Foundations on Rocks. Clause6.2
Y
where, qc= Uniaxial Compressive strength of rock core teste (avg) = 2400 T/m (@3.00m)
Nj= Emphirical co-efficient depending on the spacing of discontinuities, Ref (Table.4 and Fig 1)
U
Table 31.8
Unconfined crushing strength of rock cores tested = 240kg/cm2 = 24Mpa , RMR increment = 2
SE
But considering good Basalt will follow , and is a Hard Basalt , by marginal extrapolation , recommended SBC
=100T/m2 . Settlement will <5mm , so Okay to Adopt 100 T/m2
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
PO
BH 3 near to Section H-H’ SBC @ R.L +600.00m on a Completely Weathered Basalt
Through this Bore Hole CWR is observed . Upto R.L + 603.00m as Core stones below which upto R.L + 601.00m
R
Core Recovery 5-10%
@ +600.00 R.L assuming the Completely Weathered Basalt is still continuous , Using only 50% of lowest value
2
PU
of rock cores tested in HWR zones , as such 204 x 50% (0.50) = 102kg/cm
2
where, qc= Uniaxial Compressive strength of rock core tested (as above) = 1020T/m
Nj= Emphirical co-efficient depending on the spacing of discontinuities, Ref (Table.4 and Fig 1)
D
2
qs= 1020 x 0.1 = 102T/m
ST
Referring to the Clause9.2.i(b) of the above IS Allowable Bearing Pressure with allowance for weathering,
discontinuities in rock , consider 102 x ½ = 51T/m2
2
Unconfined crushing strength of rock (as above) = 102kg/cm = 10.2Mpa , RMR increment = 1
Considering the lower of 2 values , Recommended to use 50 T/m2 on Completely Weathered Rock
SE
2
B. SETTLEMENT OF FOOTINGS EXERTING PRESSURE OF 50 T/m
Ref:- Foundation Analysis and Design, J.E. Bowles, McGraw Hill Publication, 5th Edition, 1996.
PO
1− µ2
Settlement = S = q0 B' mI s I f
Es
R
2
where, q=Footing pressure =50T/m
PU
B’ =B/2 = 2.0/2 =1.0
u= Poisson’s ratio =0.2
Now, considering the Completely Weathered rock to be a Boulder type of strat , pockets packed with Sand /Rock
Gravels , akin to a over consolidated sand , with SPT N> 50
Y
E Value for Over Consolidated Sand = 4000 +105 (N) = 4000 + 105(50) = 9250T/m2
Now, m=4 for center of footing Is= Influence factor Conservative =0.53 and Footing Depth Factor=1.00
D
9250
Settlement < 12mm so Okay to Use 50T/m2 for design on a Completely Weathered Basalt @ R.L +600.00m
ST
In vicinity of BH-3
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
R
BH 4 from 1.00 m below G.L i.e From R.L + 603.00m below on Fresh Basalt
FO
Referring to the Clause9.2.i(a) of the above IS Allowable Bearing Pressure with allowance for weathering,
discontinuities in rock , consider 338 x ¾ = 253.5T/m2
B. Alternately, By RMR method:-
Ref:- Soil Mechanics and Foundation Engineering by K.R.Arora ,Page 825 ,
Address:- Bldg No.A/49, Flat No.1363 , M.I.G Adarsh Nagar Worli, Mumbai:-400 030 contd…..
Tel No:- 91-22-2422 92 96, 2431 86 20 Tel Fax No. 91-22-422 9296. E-mail:- shailesh_zantye@yahoo.com
Pg 10
Table 31.8
Unconfined crushing strength of rock cores tested = 338kg/cm2 = 33.3Mpa , RMR increment = 4
SE
Ref Table:- 31.12
Assuming Ground Water general condition At bore Hole Location GWL is 3.25m (R.L =+600.75m), as such
PO
considering a dry condition, So RMR = 10
R
PU
Ref IS 12070:1987 Table 3 (as described earlier)
Classification No I II III IV V
Description of rock: Very Good Good Fair Poor Very Poor
RMR 100-81 80-61 60-41 40-21 20-0
Y
2
Safe Bearing Pr(t/m ) 600-448 440-288 280-151 145-90-58 55-45-40
D
2
By the above Two Trials , but for all practical purposes , for design restricted to 200T/m
Settlement will be 6mm so 200T/m2 is OK for Design
U
++++++++++++++++++++++++++++++++++END OF REPORT++++++++++++++++++++++++++++++++++++
ST
REFERENCES:-
1. IS 12070:-1987 Code of Practice for Design and Construction of Shallow Foundations on Rocks.
R
2. Foundation Analysis and Design, J.E. Bowles, McGraw Hill Publication, 5th Edition, 1996
FO
Address:- Bldg No.A/49, Flat No.1363 , M.I.G Adarsh Nagar Worli, Mumbai:-400 030.
Tel No:- 91-22-2422 92 96, 2431 86 20 Tel Fax No. 91-22-422 9296. E-mail:- shailesh_zantye@yahoo.com
CLIENT:- M/s LANDMARK DESIGN GROUP, Nigdi PUNE:-411044. DATE:-07-10-2014.
PROJECT:- Geotechnical Investigation – For Prop Development of Outdoor Exhibition Parkland at Sector 5 & Sector 8 for PCNTDA @ Moshi
SE
SR BH SAMPLE DEPTH SULPHITE AS CHLORIDE AS ORGANIC
pH REMARKS
NO NO NO ‘m’ SO3 cl MATTER
PO
BH 01 W.S No 1 4.35 m BGL
1. 7.15 15 PPM 18 PPM --------
(R.L=+598.15)
2. BH 02 W.S No 1 4.10m BGL
(R.L= +597.90)
7.20 10 PPM 12 PPM -------
LIMITS AS PER I.S
R
3. BH 03 W.S No 1 4.30m BGL 456
7.05 15 PPM 12 PPM --------
(R.L= +601.70)
PU
PH 6.50-8.30
4. BH 04 W.S No 1 3.25m BGL
(R.L= +600.75)
7.10 18 PPM 16 PPM -------
SULPHITE AS SO3
5. BH 02 0.50m BGL 400 PPM
D.S No 1
(R.L= +601.50)
7.20 0.00224% 0.00186% -------
Y
6. BH 04 0.50m BGL CHLORIDE AS CL
D.S No 1 7.55 0.00148% 0.00166% -------
D
(R.L= +601.50) 500 PPM
----- ------------ -------------- ---------------- -------------
U--------------------------- ------------------------- ------- ORGANIC MATTER
50 PPM
ST
----- ------------ -------------- ---------------- ------------- --------------------------- ------------------------- -------
Notes:- The test results are valid only for the sample tested. No reproduction either in part or full shall be done for this test certificate.
Any Change in the above data invalidates this certificate.
FO
PROJECT:- Geotechnical Investigation – For Prop Development of Outdoor Exhibition Parkland at Sector 5 & Sector 8 for PCNTDA @ Moshi
SE
PAGE NO. 1 OF 1
PO
Location DIA IN CM 3 3 ABSORPTION SP.GR
NO NO ‘M’ ROCK T/m T/m % STRENGTH LAYER
% 2
CORE Kg/cm
Ref Loc 11.00 Gray/GB Fresh
01 02 1.00 - 1.17 + 601.50 2.740 2.752 0.404 0.779 2.760 323.80
Plan 5.40 Basalt L-III
R
Ref Loc 4.00 Gray/GB- HWR
02 02 2.00 - 2.06 + 600.00 2.660 2.673 0.594 1.070 2.690 204.50
PU
Plan 5.10 Frac Basalt L-II
Ref Loc 8.00 Gray Fresh Basalt
02 15(A) 4.85 - 4.95 +597.15 2.710 2.722 0.444 0.806 2.735 287.83
Plan 5.30 with Joints L- III
Ref Loc 4.00 Gray HWR Basalt
04 03 0.88 -0.93 +603.12 2.680 2.694 0.788 1.324 2.711 246.84**
Plan 5.10 with Joints L-II
Y
Ref Loc 11.00 Gray/GB Fresh
04 09 2.00 - 2.17 +602.00 2.760 2.770 0.354 0.668 2.780 338.18
D
Plan 5.40 U Basalt L-III
--- ------------ ------- --------------- ----------- ------------ ------------ ------------- ---------------- ------------ ---------- ----------------------- -----------------------
ST
--- ------------ ------- --------------- ----------- ------------ ------------ ------------- ---------------- ------------ ---------- ----------------------- -----------------------
--- ------------ ------- --------------- ----------- ------------ ------------ ------------- ---------------- ------------ ---------- ----------------------- -----------------------
R
Test on BH-3 samples could not be cared out as due to Disturbed samples recovered as Core stones no sample fit for testing due to insufficient length, undefined shape &
size as required minimum for testing procedures.
FO
Notes:- The test results are valid only for the sample tested. Water Absorption / Porosity are surface values. **denotes Point Load Test for UCS value
No reproduction either in part or full shall be done for this test certificate. Any Change in the above data invalidates this certificate.
Top R.L’s of Rock core are derived from the Ground R.L’s approximated from Contour Plan and are as furnished by the Site Engineer. BH Location to be referred to on Plan
BORELOG
∅ CORE DRILLING
THICKNESS
FIELD TEST
SAMPLE
CASING
WASH
LAYER
TYPE
PIECES
OF
OF
OF RECOVERY R.Q.D. WATER
CORE
(M) (M)
STRATA S. P. T. % % COLOUR
‘N’
15 15 15 15 123
25 50 75 100 12
0.00 +602.50
123
123
12
25 50 75 100
12
Casing LVL=1.00m
+ + + RESIDUAL SOILS/BOULDERS
XXXXX
12 Wash Water
123 12
12 Colour
I
+ + + Brownish Boulders with’
+ + + Pockes of Sandy/Rock Gravels
123
123
13 12
12
10 0.00 - 1.00m
SE
+601.70 0.80 123 12
12 Brownish
123456789
sp10123
+++ 1
+ + + Gray Brown/Gray Fine Grained 12
123456789
123
II C.P 12
12345678901 1.00 -5.00m
1.00 +601.50 0.20 + + + Highly Weathered BASALT with 12
12345678901
+ + + Close Joints 12345678912345678901 Grayish
+++ 123456789 12345678901
12345678901
PO
+++
+++ 123456789
123456789
82
12345678901
12345678901
12345678901
82
+++
+++ 123456789 12345678901
12345678912345678901
12345678901
2.00 +600.50 +++ C.P 2/5 123456789 12345678901
+++
+++
R 123456789
123456789
12345678901
12345678901
‘NX’ Rock Drilling from 1.00m
+++ 12345678912345678901
12345678901
123456789 12345678901
PU
+++ 12345678901
+++
+++ 123456789
85 82
12345678901
12345678912345678901
12345678901
+++ 6/10123456789 12345678901
3.00 +599.50 +++
C.P
123456789 12345678901
12345678912345678901
+++ 12345678901
123456789 12345678901
Y
+++ 12345678901
+++ 123456789
123456789
90 12345678901
12345678901
88
+++
123456789 12345678901
D
12345678901
11/14123456789
+++ 12345678901
4.00 +598.50 +++ C.P 123456789123456789
12345678901
123456789
12345678901
123456789
U
+++ 123456789
+++ 123456789
123456789
123456789
123456789
123456789
64.35 +598.15
ST
+++
+++ 123456789
90
123456789
123456789
79
123456789
123456789
III + + + Gray/GrayBlack Fine 123456789123456789
15/18123456789
123456789
5.00+597.50 4.00 + + + Grained Fresh BASALT C.P 123456789
NOTES:- Bore Hole is Terminated at 5.00m BGL as scheduled in the present scope of Investigation
R
The Strata described above is specific to the bore hole Location. GWL iis measured at a specific time interval on completion of
bore and is subject to annular, seasonal Fluctuations
FO
SCALE :- V :- 1 : 50
H :- N.T.S
D - DISTURBED SAMPLE S.P.T - STANDARD PENETRATION TEST
WS - WASH SAMPLE U - UNDISTURBED SAMPLE DATE :- 30-09-2014
WO - WATER SAMPLE C.P - CORE PIECES S.P - SMALL PIECES
DRN BY :- SUPY
CHKD BY :- SMZ
AGENCY : M/s SIMPLE DRILLING AND CONSTRUCTION CO. DRG. NO:-SDCC / LDG
(SURVEYORS, GEOTECHNICAL ENGINEERS, GROUTING & MICROPILLING CONTRACTORS) PCNTDA -Moshi
A / 49 / 1363 / M.I.G ADARSH NAGAR, WORLI, MUMBAI - 400 030. Soil Bore Log -01 /2014
TEL :- 2422 92 96 / 2431 86 20. TELEFAX :- 91 - 22 - 2422 92 96. Mobile: 9821140441 E-mail -shailesh_zantye@yahoo.com PG:- 1OF 1
CLIENT: LANDMARK DESIGN GROUP, Nigdi, Pune:-411044 LOCATION : Refer Location Plan
BORELOG
∅ CORE DRILLING
THICKNESS
FIELD TEST
SAMPLE
CASING
WASH
LAYER
TYPE
PIECES
OF
OF
OF RECOVERY R.Q.D. WATER
CORE
(M) (M)
STRATA S. P. T. % % COLOUR
‘N’
15 15 15 15
0.00 +602.00 25 50 75 100 25 50 75 100
+++ Wash Water
Casing LVL=2.00m
+++
Colour
+++ 0.00 - 1.00m
I RESIDUAL SOILS/BOULDERS
SE
Brownish Boulders with’ Brownish
WS 1
1.00 +601.00 1.00
1234
1234
Pockes of Sandy/Rock Gravels 123 D1
1.00 -5.00m
123
+++ 1234 123 Grayish
+++ 1234 123
123
PO
+++
+++
1234
1234
20
123
123
123
20
+++ 1234
1234
123
123
+++
C.P 1 1234 123
‘NX’ Rock Drilling from 1.00m
+++ 123
2.00 +600.00 +++
+++
1234
1234
R
+++ 1234
1234
PU
20 NIL
+++
1234
2/4 1234
+++
12345
C.P sp07 1234
+++
3.00 +599.00 +++
+++
12345
1234
12345
12345
Y
+++ 123456
6 4.10 +597.90 +++ 123456789123456
123456789123456
123456
ST
The Strata described above is specific to the bore hole Location. GWL iis measured at a specific time interval on completion of
bore and is subject to annular, seasonal Fluctuations
FO
SCALE :- V :- 1 : 50
H :- N.T.S
D - DISTURBED SAMPLE S.P.T - STANDARD PENETRATION TEST
WS - WASH SAMPLE U - UNDISTURBED SAMPLE DATE :- 25-09-2014
WO - WATER SAMPLE C.P - CORE PIECES S.P - SMALL PIECES
DRN BY :- SUPY
CHKD BY :- SMZ
AGENCY : M/s SIMPLE DRILLING AND CONSTRUCTION CO. DRG. NO:-SDCC / LDG
(SURVEYORS, GEOTECHNICAL ENGINEERS, GROUTING & MICROPILLING CONTRACTORS) PCNTDA -Moshi
A / 49 / 1363 / M.I.G ADARSH NAGAR, WORLI, MUMBAI - 400 030. Soil Bore Log - 02 /2014
TEL :- 2422 92 96 / 2431 86 20. TELEFAX :- 91 - 22 - 2422 92 96. Mobile: 9821140441 E-mail -shailesh_zantye@yahoo.com PG:- 1 OF 1
CLIENT: LANDMARK DESIGN GROUP, Nigdi, Pune:-411044 LOCATION : Refer Location Plan
BORELOG
∅ CORE DRILLING
THICKNESS
FIELD TEST
SAMPLE
CASING
WASH
LAYER
TYPE
PIECES
OF
OF
OF RECOVERY R.Q.D. WATER
CORE
(M) (M)
STRATA S. P. T. % % COLOUR
‘N’
15 15 15 15
0.00 +606.00 25 50 75 100 25 50 75 100
Wash Water
+++
Casing LVL0.80m
+++ Colour
+++ 0.00 - 5.00m
++ ++ ++
SE
+++ WS 1 Grayish/
+++ D1 Brownish
1.00 +605.00 +++
+++
PO
+++
+++
+++ WS 2
+++ D2
2.00 +604.00 +++ R
+++
‘NX’ Rock Drilling from 0.00m
+++
PU
+++
+++ WS 3
+++
+++ 1234
1234
D3
3.00 +603.00 +++ 1234
+++ 1234
Y
IA ++ ++ ++ 1234
1234
10
1/2 1234
NIL
D
+++
4.00 +602.00 +++ C.P sp 101234
1234
123
123
U
+++
+++ 123
123
6 4.30 +601.70 Pale Gray/Gray Completely
ST
The Strata described above is specific to the bore hole Location. GWL iis measured at a specific time interval on completion of
bore and is subject to annular, seasonal Fluctuations
FO
SCALE :- V :- 1 : 50
H :- N.T.S
D - DISTURBED SAMPLE S.P.T - STANDARD PENETRATION TEST
WS - WASH SAMPLE U - UNDISTURBED SAMPLE DATE :- 04-10-2014
WO - WATER SAMPLE C.P - CORE PIECES S.P - SMALL PIECES
DRN BY :- SUPY
CHKD BY :- SMZ
AGENCY : M/s SIMPLE DRILLING AND CONSTRUCTION CO. DRG. NO:-SDCC / LDG
(SURVEYORS, GEOTECHNICAL ENGINEERS, GROUTING & MICROPILLING CONTRACTORS) PCNTDA -Moshi
A / 49 / 1363 / M.I.G ADARSH NAGAR, WORLI, MUMBAI - 400 030. Soil Bore Log - 03 /2014
TEL :- 2422 92 96 / 2431 86 20. TELEFAX :- 91 - 22 - 2422 92 96. Mobile: 9821140441 E-mail -shailesh_zantye@yahoo.com PG:- 1 OF 1
CLIENT: LANDMARK DESIGN GROUP, Nigdi, Pune:-411044 LOCATION : Refer Location Plan
BORELOG
∅ CORE DRILLING
THICKNESS
FIELD TEST
SAMPLE
CASING
WASH
LAYER
TYPE
PIECES
OF
OF
OF RECOVERY R.Q.D. WATER
CORE
(M) (M)
STRATA S. P. T. % % COLOUR
‘N’
15 15 15 15
0.00 +604.00 25 50 75 100 25 50 75 100
Wash Water
I +++ RESIDUAL SOILS / BOULDERS
Casing LVL=080m
XXXXX
WS 1 Colour
1234
Brownish Boulders with’
0.60 + + + D1
Pockes of Sandy/Rock Gravels
1234 0.00- 8.00m
SE
+603.40
WS 2 1/4 1234
0.60 +++ Grayish
II + + + Gray Fine Grained Highly Weath-
+++
1.00 +603.00 0.40 + + +
ered BASALT with Close Joints C.P 123456
1234
25
123456
1234
NIL
12345
+++ & Fractures 123456 12345
12345
+++ 123456 12345
12345
PO
+++
+++ 123456
123456
12345
12345
42
50 12345
+++
+++ 123456
5/8 123456 12345
12345
‘NX’ Rock Drilling from 0.60m
+++
12345678912345678901
12345678901
+++
123456789
92 12345678901
90
+++
12345678912345678901
D
12345678901
C.P 16/19123456789
+++ 12345678901
4.00 +600.00 +++ 12345678912345678901
12345678901
123456789
U
+++ 12345678901
+++ 123456789
123456789
12345678901
12345678901
12345678901
ST
The Strata described above is specific to the bore hole Location. GWL iis measured at a specific time interval on completion of
bore and is subject to annular, seasonal Fluctuations
FO
SCALE :- V :- 1 : 50
H :- N.T.S
D - DISTURBED SAMPLE S.P.T - STANDARD PENETRATION TEST
WS - WASH SAMPLE U - UNDISTURBED SAMPLE DATE :- 09-10-2014
WO - WATER SAMPLE C.P - CORE PIECES S.P - SMALL PIECES
DRN BY :- SUPY
CHKD BY :- SMZ
AGENCY : M/s SIMPLE DRILLING AND CONSTRUCTION CO. DRG. NO:-SDCC / LDG
(SURVEYORS, GEOTECHNICAL ENGINEERS, GROUTING & MICROPILLING CONTRACTORS) PCNTDA -Moshi
A / 49 / 1363 / M.I.G ADARSH NAGAR, WORLI, MUMBAI - 400 030. Soil Bore Log - 04 /2014
TEL :- 2422 92 96 / 2431 86 20. TELEFAX :- 91 - 22 - 2422 92 96. Mobile: 9821140441 E-mail -shailesh_zantye@yahoo.com PG:- 1 OF 1
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 SUB-SURFACE PROFILE
`
B H 03
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
DEPTH OF BORE (in R.L Meters)
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+606.00
+606.00
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
Notes:- All the depths of Layers as indicated below are specific to B.H Location.
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
The depths of these strata may vary in b/w bore holes 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
++ ++ ++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
UCS values described are for the rock cores tested at specific depths . 1234567
++ ++ ++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
Rock is overall i s a Gray/ Gray Black Strong High to Moderate or Fresh 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
BASALT. 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+605.00 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
Layer I :- Residual Sandy Soils / Boulders 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
Layer IA :- Completetly Weathered Rock (CWR-Basalt) 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 B H 04
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
Layer II:- Bed Rock --- Highly Weathered BASALT 1234567
+ ++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 1234567
+604.00 N.G.L
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+604.00 1234567
+++ 1234567
SE
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+ + +
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
Layer III:- Ocasionally Moderate to Fresh BASALT 1234567 1234567
+ +
1234567
X X X X+X
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+++ LAYER I - Residual Soils / Boulders 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+++ 1234567
+++
1234567+603.40
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+ + + 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
LAYER I A - CWR 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+++ 1234567
2 1234567
+++
PO
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 UCS=246kg/cm 1234567
+++
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 1234567
+603.00
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 + + + +603.00
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 II 1234567
1234567
+ ++
B H 01 + + +
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+ + + YE
R
1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+602.50
1234567 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 LA 1234567
+++
1234567
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+ + + 1234567
+++
R
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
X+X +
X X+
1234567
X 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 CK 1234567
+++
1234567
B H 02 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 1234567
+++
N.G.L 12345678 +++
1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 RO 1234567
+++
PU
+602.00
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+602.00 12345678 1234567 1234567
+ + +
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
D 1234567
BEUCS=338kg/cm21234567+++
12345678
+++ 1234567
+++ 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++
12345678 +601.7001234567
+++
1234567 +601.70 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567
+ + + 1234567
+++
1234567
12345678 LAYER I +++
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
1234567 1234567
+++
+++ +++ q +++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567 1234567 1234567
+++
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 + + + 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 1234567
12345678 +601.5001234567
+ +
1234567 + 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567
+++ 1234567
+++
1234567
2 +++
+ + + UCS= 323 kg/cm
Y
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 1234567
+601.00 12345678
12345678
1234567
+ +
1234567 + 1234567
+ + +
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 1234567
+++
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+ + + +601.00 1234567
+++ +++
1234567
D
+601.00
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ 1234567
+++ 1234567
+ + + +600.75
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 1234567
+++
12345678
+++ 1234567
+ + +
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567 1234567
1234567
q
+++ +++
+ +
12345678 + 1234567
1234567
U
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ LAYER II - H.W Basalt 1234567
+++
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
1234567
1234567
+++
1234567
+++
1234567
ST
+ + + 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 +++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 1234567
+++
+600.00 12345678 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+ + + UCS= 204kg/cm2 1234567 1234567
+++
1234567
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 +++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 1234567
+ ++
12345678
+ +
12345678
+ 1234567
+++
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 1234567
1234567
+ ++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 1234567
12345678
+ + + BED ROCK 1234567
+ +
1234567 +
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567
+++
1234567
R
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ 1234567
+++ +++
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567 LAYER III- Fresh Basalt 1234567
+ ++
+++ 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 + + +
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+599.00 12345678 1234567
FO
+++ + +
1234567 +
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 +599.00
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ 1234567
+++ BED ROCK
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567
+++ +++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ 1234567
+ + + +598.15
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+598.00 12345678
12345678
+++ BED ROCK
1234567
+++ q
1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+ + + +598.00 LAYER III- Fresh Basalt 1234567
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+597.90 q 12345678
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ 1234567
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678
+++ +597.50
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 123456789012345678
12345678 2
+ + + UCS= 287kg/cm CLIENT:- LANDMARK DESIGN GROUP , Nigdi ,PUNE:- 411044
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 SCALE:- 1:50
123456789012345678
123456789012345678
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
12345678 DRN BY:-SUPS SIMPLE DRILLING &
123456789012345678
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
+597.00 12345678 DRG. NO
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123PCNTDA/ Moshi -Soil CHKD BY:- SMZ 123456789012345678
CONST CO, MUMBAI
+597.00 PROJECT:-Geotechnical Investigation - Proposed Outdoor Exhibition Parkland SDCC/LDG-
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123 123456789012345678
APPR BY :-SMZ 123456789012345678
L-section -F1 / 2014.
1234567890123456789012345678901212345678901234567890123456789012123456789012345678901234567890121234567890123456789012345678901212345678901234567890123
for PCNTDA @ Sector 5 & Sector 8 in Moshi PG 1 OF 1 DT:-10-10-2014 Since 1999
123456789012345678