Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

SAIC-L-2084 Material Storage and Preservation (EE) PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Storage and Preservation of Materials of Well Head Piping SAIS-L-2084 25-May-05 PIPING -
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A. Pipe Storage, Handling and Preservation

Pipe handling procedure and equipment is approved by the Saudi SAES-L-450,


A1
Aramco PMT, and is available. Para. 8.1
End bevel protectors shall remain on pipes and fittings while in storage, SAES-L-450,
A2
protectors shall not damage internal or external coating. Para. 8.4
Slings for lifting pipe shall be nylon or similar material to prevent damage SAES-L-450,
A3
to the pipe surface. Wire rope slings shall not be used. Para. 8.5
SAES-L-450,
A4 Pipe shall not be rolled or dropped off trucks.
Para. 8.6
Pipe stacking shall be made in a manner which will not damage the pipe SAES-L-450,
A5
or the coating. Para. 8.3
Internally coated pipe shall be handled from the outside diameter (O.D.), SAES-L-450,
A6
only. Para. 8.7
When a length of pipe is cut from a longer joint of pipe, all vendor
SAES-L-450,
A7 markings and other identifying information shall be transferred to each
Para. 8.8
length of pipe.

B. Storage, Handling and Preservation of fittings & Flanges

Fittings and Flanges must be packaged in steel-banded wooden crates 02-SAMSS-011,


B1
or secured to skids. Para. 10
Fittings and Flanges must be protected from mechanical damage.
02-SAMSS-011,
B2 Welding ends must be protected with suitable wood, plastic, or metal
Para. 10
covers, (see Attachment 1).

C. Storage, Handling and Preservation of Valves

Valve end flanges shall be fitted with plywood covers. The cover
diameter shall be the same as the outside diameter of the flange and 04-SAMSS-035
C1
shall be at least 10 mm thick for valves up to NPS 10 inch and 12 mm Para. 12.2
thick for valves NPS 12 inch and larger.
The cover shall be attached by machine bolts with a nut and washer
fitted on the inside of the flange. There shall be four (4) bolts on valves
04-SAMSS-035
C2 up to NPS 10 inch nominal size and eight (8) bolts on valves NPS 12
Para. 12.2
inch and larger. The bolts diameter shall not be less than ½ the size of
the flange bolt hole.
The raised face portion of the flange and the ring joint groove shall be 04-SAMSS-035
C3
covered with a heavy grease, (see Attachment 1). Para. 12.2
A heavy duty moisture-proof disc shall be fitted between the greased
04-SAMSS-035
C4 flange face and the cover. The disc shall have a diameter equivalent to
Para. 12.2
the inside diameter of the bolt holes.
The ends of threaded and socket weld end valves shall be protected with 04-SAMSS-035
C5
tight fitting plastic caps. Para. 12.3

Page 1 of 3
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Storage and Preservation of Materials of Well Head Piping SAIS-L-2084 25-May-05 PIPING -
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

REMARKS:

REFERENCE DOCUMENTS:
1. SAES-L-450, Construction of On-Land and Near-Shore Pipelines, 30 September, 2003
3. 02-SAMSS-011, Forged Steel Weld Neck Flanges for Low and Intermediate Temperature Service, 28 January, 2004
3. 04-SAMSS-035, General Requirements for Valves, 31 July, 2001

ATTACHMENTS:
1. FIGURE 1 - Flanged Valves; FIGURE 2 - Weld End Valves

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 2 of 3
SAUDI ARAMCO ID/PID - 2/19/05 - REV A (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Storage and Preservation of Materials of Well Head Piping SAIS-L-2084 25-May-05 PIPING -

Attachment 1

Page 3 of 3

You might also like