Anao MPR 2016 17 Pdss4 Mrh90helicopters
Anao MPR 2016 17 Pdss4 Mrh90helicopters
Anao MPR 2016 17 Pdss4 Mrh90helicopters
On 28 November 2011, the Minister for Defence announced this project as a Project of Concern.
Cost Performance
In-year
The project has spent $104.4m against a budget of $175.5m to June 2017. The $71.1m underspend to June 2017 is primarily due
to net adjustments to payment phasings across the Prime Acquisition and delays in finalising Contract Change Proposals. This
is offset against a foreign currency loss.
Project Financial Assurance Statement
As at 30 June 2017, project AIR 9000 Phase 2, 4 & 6 has reviewed the approved scope and budget for those elements required to
be delivered by the project. Having reviewed the current financial and contractual obligations of the project, current known risks and
estimated future expenditure, Defence considers, as at the reporting date, there is sufficient budget remaining for the project to
complete against the agreed scope.
Contingency Statement
The project has applied contingency in the financial year primarily for the treatment of various supportability and performance risks
such as a replacement Mission Management System, Fast Roping, Rappelling and Extraction System, Eurogrid Tactical
Mission Computer, Multi Function Displays New Generation, and Landing Helicopter Dock supplies support.
Schedule Performance
As a result of the Deed 2 negotiations with the contractor, the final delivery of aircraft has been rescheduled to July 2017; this, and
ongoing technical deficiencies, have resulted in delays to the Final Materiel Release (FMR) and Final Operational Capability (FOC)
milestones. However, a number of capability milestones have been declared, including Army Initial Operational Capability (IOC) in
December 2014, Navy IOC in February 2015, first Operational Capability Land (OCL1) in September 2015, second and third
Operational Capability Amphibious (OCA2/3) in December 2015, and the second Operational Capability Land (OCL2) in March 2016.
The FMR and FOC dates are currently under review and are expected to be clarified in Quarter 4 2017 with the approval of a
revised Materiel Acquisition Agreement.
Forty six aircraft have been accepted into service with the final aircraft programmed for acceptance in July 2017. The first
Forecast dates and Sections: 1.2 (Materiel Capability Delivery Performance), 1.3 (Major Risks and Issues), 4.1 (Measures of Materiel Capability Delivery Performance), and 5
(Major Risks and Issues) are excluded from the scope of the ANAO’s review of this Project Data Summary Sheet. Information on the scope of the review is provided in the
Independent Assurance Report by the Auditor-General in Part 3 of this report.
Note
Forecast dates and capability assessments are excluded from the scope of the review.
Background
The Additional Troop Lift project was first foreshadowed in the Defence White Paper 2000.
The MRH Program consists of Phases 2, 4 & 6. Phase 2 was approved initially, providing 12 additional Troop Lift helicopters for
Army. Phases 4 & 6 were approved subsequently with Phase 4 which provided 28 helicopters as the replacement of the Australian
Army’s fleet of 34 S-70A-9 Black Hawk helicopters, again for troop lift capability, and Phase 6 provided 6 helicopters as the
replacement of the RAN’s fleet of six Sea King helicopters, providing maritime support capability for Navy. The delivery of a 47th
MRH90 was negotiated as part of Deed 2. This enables the use of one airframe as a Ground Training Device without impacting the
operational fleet.
In total, the AIR 9000 MRH Program will acquire 47 MRH90 aircraft and support systems. Support capabilities, such as Electronic
Warfare Self Protection Support System, MRH Software Support Centre, MRH Instrumentation System and a Ground Mission
Management System, will be acquired along with training systems and in-service support.
The Phase 2 Acquisition Contract was signed with Airbus Group Australia Pacific (Airbus Group AP) in June 2005 with the
subsequent Sustainment and Program Agreement contracts signed in July 2005.
In November 2005 the Defence Capability and Investment Committee agreed that the way forward was to seek a combined first and
second pass approval for both Phases 4 and 6 as part of a single approval process.
Cabinet endorsement was gained in April 2006 in a combined first and second pass process for Phase 4 and Phase 6. The agreed
method of procurement, a two stage Contract Change Proposal (CCP), resulted in the execution of options contained in the Program
Agreement for the procurement of additional aircraft approved under Phases 4 and 6. Initial CCPs for the Acquisition, Sustainment
and Program Agreement Contracts were signed in June 2006.
The three AIR 9000 Phase 2/4/6 contracts (Program Agreement Contract, Acquisition Contract and Sustainment Contract)
incorporate the above CCPs. On acceptance of two MRH90, appropriate training, maintenance and supply support, an In-Service
Date of December 2007 was achieved with aircraft operating under a Special Flight Permit granted by the Chief of Air Force. This
triggered the Sustainment Contract to come into effect and all three contracts are now currently active.
The Commonwealth suspended acceptance of aircraft from Airbus Group AP in November 2010; deliveries recommenced in
November 2011 after negotiations of a remediation plan (Deed of Agreement and CCPs) to address a number of engineering and
reliability issues. Concurrent with the recommencement of aircraft acceptance in November 2011, the Minister for Defence
announced that the project would be listed as a Project of Concern citing schedule, aircraft technical deficiencies and Airbus Group
AP’s performance.
The Commonwealth has conducted negotiations with the prime contractor to review and settle commercial, technical and schedule
issues resulting in a variation to the original contract signed on 9 May 2013, which has been termed ‘Deed 2’. Deed 2, which came
into effect on 1 July 2013 re-baselined the delivery schedule and addressed commercial and technical issues.
Uniqueness
The MRH90 aircraft is based upon the German Army variant of the NH90 Troop Transport Helicopter. The MRH90 design uses well
established aerospace technologies, but will introduce new technologies into Army and Navy, primarily in the areas of composite
structure, helmet mounted sight and display and fly-by-wire flight control systems.
The MRH Program is providing an MRH90 capability to two main users - Army and Navy. The capability delivery complexity this
introduces has been mitigated through an agreement between Chief of Army and Chief of Navy. This provides the project with a
single interface for introduction into service issues.
MRH90 Helicopters
The MRH Program Office Design Acceptance Strategy is dependent upon the French Military Airworthiness Authority’s (Direction
Générale de l’Armament (DGA)) prior acceptance of the NH90 variants and certification recommendation for the MRH90. The DGA
and other National Qualification Organisations’ prior acceptance of European NH90s provide confidence for the ADF to leverage off
Project Expenditure
Prior to Jul 16 Contract expenditure – Airbus Group AP (2,536.2)
Contract expenditure – CAE Australia (169.7)
Other Contract Payments / Internal Expenses (218.3)
(2,924.2)
3 The funding related to facilities elements of the project was managed by Defence Estate and Infrastructure Group (DE&IG).
4 Transfer to DE&IG for Facilities Infrastructure.
5 Real Cost Increase funding for Full Flight Mission Simulator.
Forty six MRH aircraft have been accepted to date. Both Full Flight Mission Simulators have been accepted by the Commonwealth.
Notes
1 The delivery of a 47th MRH90 was negotiated as part of Deed 2. This enables the use of one airframe as a Ground
Training Device without impacting the operational fleet.
Permit 1
Australian Military Type Certificate Dec 08 Dec 10 Apr 13 52 6
Full Flight and Mission Simulator #1 Jul 12 Aug 13 Aug 13 13 7
46.
2 The acceptance and test-readiness of the Ground Mission Management System (GMMS) was broken into six lots post
contract signature. The lots compose of GMMS deliverables that have been aligned to aircraft delivery – location and
baseline. The acceptance of GMMS lots are listed in the acceptance area of this table.
3 The 13 month delay to closure of Test Readiness Review was due to electronic compatibility test design issues not resolved
until November 2009. This delay was mitigated by the development of an interim MRH Instrumentation System capability
used for a test activity in October 2009.
4 Achieved through completion of Test Readiness Review for Contractor In-Plant Test and Evaluation in September 2011.
5 The first Airworthiness Board (for a Special Flight Permit (SFP)) was conducted in November 2007 and a SFP was granted
in December 2007. There have been a number of SFP extensions to allow flight trials of the aircraft as it further develops.
The most recent SFP was granted in December 2012 and expired in April 2013.
6 Achievement of the Australian Military Type Certificate proved problematic due to technical and reliability issues, leading to
insufficient levels of the Rate of Effort. Rate of Effort was required to validate that in-service support arrangements for the
fleet are sufficient to cope with current numbers of aircraft and are growing in maturity to meet fleet requirements. Australian
Military Type Certificate and Service Release was achieved 17 April 2013.
7 Refers to acceptance of Full Flight Mission Simulators in Oakey and Townsville. Delays have been incurred due to the late
delivery of facilities and an underestimation of the time required to implement the design.
8 Lot 1, 2 and 3 have been altered to accommodate the variation in aircraft delivery date and configuration.
9 The MRH instrumented system incurred delays due to technical and supportability issues that resulted in contractual non-
conformances. These non-conformances were rectified by September 2011.
10 The MRH90 program stopped accepting aircraft in November 2010 due to a number of technical and reliability issues. The
Commonwealth recommenced accepting aircraft in November 2011 after negotiating a remediation plan to address a
number of engineering and contractual issues; however acceptance of aircraft was again suspended in February 2012
pending resolution of another technical concern related to the aircraft’s cargo hook. In May 2012 the Commonwealth agreed
to accept a further four aircraft based on Airbus Group AP’s agreement to the commercial terms associated with the
rectification of the cargo hook issue. Scheduled aircraft acceptance recommenced in June 2012 with the most recent aircraft
(#46) accepted in June 2017.
Schedule Plan at
Approval
Government Approval
Jun-05
Jun-06
Jun-07
Jun-08
Jun-09
Jun-10
Jun-11
Jun-12
Jun-13
Jun-14
Jun-15
Jun-16
Jun-17
Jun-18
Jun-19
Jun-20
FOC
Note
Forecast dates in Section 3 are excluded from the scope of the review.
Amber:
MRHPO remains focused on the timely delivery of capabilities
to support operational capabilities. There continues to be a
number of capabilities that will need to be progressed and
released including the redesign of Cargo Hook, the Common
Mission Management System, and the improved Fast Roping,
50% Rappelling and Extraction System.
Red:
N/A
MRH90 Helicopters
Note
This Pie Chart does not necessarily represent capability achieved. The capability assessments and forecasts by the project are not
subject to the ANAO’s assurance review.
Note
Major risks and issues in Section 5 are excluded from the scope of the review.
MRH90 Helicopters
Operations and
Understanding
Requirement
Commercial
Maturity Score
Technical
Technical
Schedule
Difficulty
Support
Total
Cost
Project Stage Benchmark 10 8 8 8 9 8 9 60
Initial Materiel Project Status 7 7 9 9 8 7 9 56
Release Explanation • Schedule: The Final Materiel Release and Final Operational Capability dates are
currently under review and are expected to be clarified in late 2017 with the
approval of a revised Materiel Acquisition Agreement.
• Cost: Not all risks have been retired; however the estimate at completion to
mitigate remains within contingency guidance.
• Requirement: The MRH System design and acceptance testing phases are
essentially complete, with activities on-going for outstanding elements such as
cargo hook and mission troop seat. Additionally, the project office, with Navy and
Part 3. Project Data Summary Sheets
Army, is conducting validation trials to demonstrate that the system meets in-
service requirements.
• Technical Understanding: The knowledge necessary to operate and support the
platform is being transferred to the in-service providers.
• Technical Difficulty: Capability is still being tested fully due to the immaturity of
elements of the capability.
• Commercial: Deed 2 settled a number of long outstanding commercial issues
and has implemented sound management arrangements to provide confidence
that industry effort will be focused on capability realisation.
MRH90 Helicopters