PMO Handbook v1.5
PMO Handbook v1.5
PMO Handbook v1.5
HANDBOOK
REV 1.5
12th June 2015
PMO HANDBOOK
VERSION CONTROL
Revision History
Revision Date Description of Change
1.0 28/5/2014 Document Created
1.1 28/7/2014 Document Amended – reformatted / restructured for ease of
reading
1.2 01/8/2014 Document Amended
1.3 25/8/2014 Amendments to reflect minor formatting changes and inclusion of
latest Capital Project Governance process lifecycle
1.4 9/9/14 Formatting changes to Roles section
1.5 23/03/15 General format changes and update brand
1.5 12/06/2015 Update to Financial Management Process
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 2 of 85
PMO HANDBOOK
Table of Contents
1 Introduction ..................................................................................................... 6
1.1 Purpose of the College PMO Handbook ............................................................................... 6
1.2 Executive Summary .............................................................................................................. 6
1.3 Scope of the PMO ................................................................................................................. 7
1.4 Project Risk Indicator (PRI) ................................................................................................... 9
2 Capital Project Governance ...................................................................................... 10
2.1 Project Approval & Prioritisation ....................................................................................... 12
2.2 Initiation and Strategic Planning ........................................................................................ 13
2.3 Detailed Planning and High Level Design ........................................................................... 14
2.4 Detailed Design................................................................................................................... 15
2.5 Execution and Handover .................................................................................................... 16
2.6 Closeout .............................................................................................................................. 17
2.7 Post Project ........................................................................................................................ 18
3 Key Capital Project Governance Processes ................................................................ 19
3.1 Project ID Request process ................................................................................................. 19
3.2 Project Approval and Prioritisation process ....................................................................... 20
3.2.1 Business Case pack preparation.................................................................................... 21
3.2.2 PASS 1 – Filter and Create Potential Project Shortlist .................................................. 21
3.2.3 PASS 2 – Assess Business Case and Supporting Documents ......................................... 23
3.3 Project Portfolio Performance Reporting Process ............................................................. 25
3.3.1 Preparation of Status Report by Project Manager........................................................ 25
3.3.2 Collation of status information and issuance to CRG by PMO...................................... 25
3.3.3 CRG Project Portfolio Performance meeting ................................................................ 26
3.4 Project Stage Gate Approval Process ................................................................................. 27
3.4.1 Stage Gate Approval steps ............................................................................................ 27
3.5 Change Request (CR) management process ...................................................................... 29
3.5.1 Background ................................................................................................................... 29
3.5.2 Recording information about the requested change ................................................... 29
3.5.3 Authority to Initiate Change Request ........................................................................... 31
3.6 Project Financial and Resource Management Processes ................................................... 35
3.6.1 Project Financial Management process ........................................................................ 35
3.6.2 Project Resource Management process ....................................................................... 35
3.7 Risk, Assumption, Issue & Dependency (RAID) Review Management Process .................. 37
3.7.1 RAID Item Ranking (Heat Map) ..................................................................................... 38
3.8 RAID Definitions.................................................................................................................. 39
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 3 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 4 of 85
PMO HANDBOOK
FIGURES
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 5 of 85
PMO HANDBOOK
1 Introduction
1.1 Purpose of the College PMO Handbook
The purpose of the PMO Handbook is to record in one location the standards, processes and
controls relating to management of Capital Projects.
The Handbook introduces the College-wide PMO and presents the standard governance process, a
project lifecycle and related processes for Capital Project management, and clarifies how the
standards, processes and controls align the PMO with business roles, responsibilities and functions.
The PMO is currently implementing a College- wide project governance structure, a standard set of
project management processes (including approval and prioritisation and performance reporting)
and a common lifecycle for projects. It is coordinating the introduction of the Capital Project
Governance lifecycle and is planning provision of training in lifecycle and processes for Sponsors,
Governance groups and Project Managers.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 6 of 85
PMO HANDBOOK
The purpose of the PMO is to support College/senior management in a variety of ways which
include:
1. Provision of a consistent approach to project approval, prioritisation and delivery;
2. Developing and managing Capital Project processes and standards, including project
management templates and processes;
3. Establishing an organisational focus on improvements
4. Consolidating and co-ordinating regular standardised reporting of the project portfolio
to the Board, EOG and the CRG (Capital Review Group described in detail below);
5. Establishing and managing the College Project Portfolio;
6. Provision of portfolio level status and performance reporting;
7. Establishing an organisational focus on improvements in project management
competency.
In June 2013, Board approved that Capital Projects meeting certain criteria would report through the
College-wide PMO. Business Cases for proposed projects will be assessed on the basis of:
Severity of the problem and the impact of the project over the next 5-15 years;
Quality of project planning (including risk analysis);
Level of innovation and synergies in proposed solution;
Benefit of the proposed solution compared to alternatives;
Fit with current College strategic plans and initiatives;
Cost Benefit Analysis.
Two principle information flows operate within the PMO – Approval & Prioritisation and Reporting
as shown below. Detailed process descriptions are provided later in the Handbook.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 7 of 85
PMO HANDBOOK
There are a number of significant benefits anticipated from the PMO and the processes being
implemented:
Improved definition of project Business Cases so that College resources and funds are
committed to the areas of highest priority and return for the College and better alignment of
the Business Case with deliverables;
Assistance with identification of resource requirements, particularly in critical front end
project stages;
Clearer decision making processes and, consequently, timely decision making during the
lifecycle of each project leading to better control of timescale and budget;
Better identification of the necessary organisational change activities needed so that
projects provide the required return on effort and investment;
Improved management of risks associated with programmes and projects;
Improved verification of timelines and budget for planned projects through standard
reporting processes;
Development of an improved project management culture, formal change controls and risk
management strategies;
Standardised reporting and monitoring leading to improved management information and
support of College strategy;
Better coordination between projects;
Improved visibility of project performance, capital spend, project costs, benefits and key
resource impacts; greater control of costs and risks;
Improved project approval and prioritisation process;
Improved College project delivery, higher levels of skill among project managers from use of
a common approach and ongoing competency training;
Standardisation of the College Capital Project Governance .
Sponsors may request advisory support from the PMO in completing the documentation outlined
within the governance process, or to provide advice on how best to progress through the Capital
Project Governance Process.
In summary, the PMO has responsibility for establishing the management processes for projects
reporting through it and will incorporate a set of defined policies, procedures, templates,
management processes, tools, and services.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 8 of 85
PMO HANDBOOK
Dependency on external Long standing Reasonable Used before, but Used before, No previous
suppliers / organisations relationship relationship not regularly but not recently relationship
Risk to Reputation Reputational risk Reputational Reputational risks Reputational Reputational risks
unlikely to happen, risks are likely as not to risks are likely certain to occur,
with negligible occasionally occur, with to occur, with which threatens
impact occur, with notable impact to substantial reputation of
minor impact to reputation impact to project or TCD
reputation reputation if
they do
TCD Resource Impact In house skills In house skills In house skills Up skilling In house and
present and project present with present but the required, external
is easily absorbed some project will impact resources will resources
within current occasional current workloads have to be dedicated to
workload impact on and require dedicated to the project and from
current backfill project more than one
workloads department
Funding/Finance Funding exists with Most funding in Funding not in Funding Funding will be
current budgets place or place. sources not difficult, funding
requires minor clear, will complexity mix
budgetary Project will impact impact TCD high and possibly
allocation departmental budgets not attainable
budgets
Project Scoring:
Low < 19 Total:
Medium 19 – 31
High > 32
Fig 3. PROJECT RISK INDICATOR
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 9 of 85
PMO HANDBOOK
Each of the major Stages listed concludes with a Gate Review at which the project’s performance is
assessed against its Business Case. To be considered ready to move to the next lifecycle stage,
specific criteria within the Stage Gate Approval Pack and other key supporting documents must be
met. These provide control of milestone completion and confirm that required tasks and steps have
been satisfactorily completed, and that required deliverables have been completed, reviewed, and
have received signoff.
Throughout the lifecycle, if any changes are identified that will alter the Business Case (project
scope, timeline, resource effort or costs/benefits) previously approved, the Sponsor and Project
Manager will initiate a Change Request for submission into the Change Request process, for review
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 10 of 85
PMO HANDBOOK
by the appropriate governance level before being confirmed as accepted by the project for delivery
(see relevant section later in document for process details).
The rationale for the Capital Project Governance lifecycle and its context are summarised in the
Appendices.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 11 of 85
PMO HANDBOOK
At the end of this stage, the proposed project is submitted to CRG for review and recommendation
(see later section for Approval & Prioritisation process details.)
Principle deliverables
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 12 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 13 of 85
PMO HANDBOOK
Processes used
Project portfolio performance reporting process
RAID review management process
Recruitment, if required
Procurement, if required
Change Request management process, if required
Project Stage Gate approval process
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 14 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 15 of 85
PMO HANDBOOK
A Stage Gate review will be held at the end of the tendering sub-stage.
Reviews will be carried out by Steering at the end of the Execution and Testing sub-stages and a
Stage Gate review will be held at the end of the complete Stage (Gate Review 5).
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 16 of 85
PMO HANDBOOK
2.6 Closeout
The primary owner for the Stage deliverables is the Project Manager. In this Stage, a lessons learned
exercise is performed where all stakeholders are encouraged to provide constructive feedback on
how the project operated throughout its lifecycle – what worked well, and what might be done
differently if the project were to be executed again.
The project logistics initiated in the earlier stages of the project are shut down. The project team
ensures that all key project documents are available in the project folders, with unwanted versions
of deliverables removed or archived.
A Project Closure Report (TBC) is prepared by the Sponsor and Project Manager based on the
approved Business Case and any subsequent approved change requests. This summarises the state
of project delivery – what the project has delivered and what it has not. It highlights any key
deliverables not delivered and any key critical success factors not achieved. It details the project
performance against the approved baselines in the areas of scope, timeline, effort, financial, and
quality. Lessons learned are included in this document.
Project management documents are finalised including the Decision and RAID Logs. Team resources
are officially released from the project.
If a Post-implementation benefits review was agreed during earlier phases of the project, specific
requirements and the scope of this review are reconfirmed and a provisional timeline to execute it is
agreed. This will include details on when the review will be performed, who will own, deliver and
drive the review, and who the key resources will be to perform the review.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 17 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 18 of 85
PMO HANDBOOK
Step 2. PMO confirms that all information required to support the allocation of a new project ID to
the request is available on the email.
Step 3. PMO then updates the Project ID Request Register with the details provided, and allocates
the next sequential ID from the register to the project.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 19 of 85
PMO HANDBOOK
At the end of this stage, the proposed project is submitted to CRG for review and recommendation
(see later section for Approval & Prioritisation process details.)
Principle deliverables
Approval & Prioritisation Proposal pack
Business Case pack
o Business Case
o Financial Plan
o Change Request PRI Log
Processes used include
Approval & Prioritisation
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 20 of 85
PMO HANDBOOK
PMO follows the Project ID Request process and provides a unique project number to the Project
Sponsor. This unique ID will be included in the appropriate location in all project documents. Please
refer to the Project ID Request process in this document for further detail on the process.
The Project Sponsor submits the required documents (listed below) to PMO for inclusion in CRG
submissions via the Project Approval & Prioritisation process.
The Financial Plan template allows contingency for all budgeted project costs and resource man-
days. The % contingency allocated is variable and can be set to any % based on the perceived risk of
project estimates. This is agreed during the Pre-Project Approval stage, and monitored throughout
the project lifecycle.
PMO will collate the information provided with any other requests received, and submit to the CRG
for their review, consideration and decision.
The templates / documents to be used by the Project Sponsor for submission to the CRG are:-
Business Case Summary
Business Case
Financial Plan
Change Request PRI Log
Step 1. Annually, a communication will be issued by CRG indicating the timeline for
submissions.
Step 2. The Sponsor completes the required templates. In summary, the required process
information will include:
Background (problem to be resolved) and objectives
Scope (both in and out)
Constraints, assumptions, risks and dependencies, interfaces
Options (with pros and cons) and recommended programme/project option.
High level schedule
Estimated costs (project and ongoing operational)
Estimated benefits (both quantifiable and non-quantifiable)
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 21 of 85
PMO HANDBOOK
Step 3. If space allocation is a requirement of the project, the Sponsor will get approval on
space from the Space Allocation Sub-Committee (SASC) in advance of submission.
Step 4. Dean/Chief Officer signs off on Business Case Summary (the Proposal) before
submission to CRG via PMO.
Step 5. PMO receives a request from the Sponsor to include the Proposal in the schedule of
CRG Project Portfolio Approval and Prioritisation meeting and provides all required
documents.
Step 6. PMO confirms that the Proposal provided is complete. If further details are required,
these are requested and received from the Sponsor.
Step 7. PMO updates the Project Portfolio Summary Register Log with any previously
unavailable project information.
Step 11. CRG members review and consider the details of project proposals and raise any
queries or requests for additional information either directly to the Sponsor or via PMO
in advance of the meeting.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 22 of 85
PMO HANDBOOK
Step 16. PMO provides the updated Project Portfolio Roadmap and impacts of CRG decisions to
CRG.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 23 of 85
PMO HANDBOOK
Sponsor presents each project for approval/prioritisation and a decision is made for
each submission. All potential impacts are considered in this process. Potential CRG
decisions are:
Recommendation for approval (to EOG/Board)
Rejected (with reason)
Further Information requested (with specifics)
Project Put on Hold or Deferred (with reason)
Step 12. PMO provides an updated Project Portfolio Roadmap and impacts of CRG decisions to
CRG.
Step 13. CRG processes decisions/recommendations to EOG/Board as required via CRG minutes.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 24 of 85
PMO HANDBOOK
Additional templates / documents / processes used by PMO during this process are:
Project Portfolio Performance Reporting pack
Project Portfolio Summary Register Log
Step 1. PMO provides a reminder of the upcoming reporting due date at each calendar month
end.
Step 2. Project Manager completes the required Project Status Report pack and reviews with
Sponsor in advance of submitting to PMO.
Step 3. Project Status Report received by PMO from all Project Managers by due date.
Step 4. PMO crosschecks the Project Portfolio Summary Register Log, and confirm which, if
any, projects have not provided submissions.
Step 5. PMO contacts relevant Project Managers who have not delivered the pack, requesting
reason for delay and expected delivery date.
Step 7. Full Project Portfolio Performance Reporting pack issued by PMO to all CRG members
three working days in advance of the CRG meeting for review and consideration.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 25 of 85
PMO HANDBOOK
Step 8. CRG member reviews and considers / prepares for the Project Portfolio Performance
meeting. The CRG member raises any queries or requests for additional information
directly to the Sponsor or via PMO in advance of the meeting.
Step 9. Project Portfolio Summary Register Log is updated by PMO with the following
information received from the Project Manager:
Overall project status
Schedule current status
Financial current status
Effort current status
Step 10. CRG Project Portfolio Performance meeting is held. Status of each project is reviewed,
performance deviations highlighted, and required corrective actions challenged if
appropriate and/or required.
Step 11. Key project portfolio Risks, Assumptions, Issues and Dependencies and current impacts
are reviewed.
Step 12. Decisions on submitted Change Requests are sought and received from the CRG at this
meeting.
Step 13. CRG recommendations are communicated to EOG/Board and the wider community (as
appropriate) by the CRG Chair (supported by PMO).
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 26 of 85
PMO HANDBOOK
The Project Stage Gate Approval Process provides an opportunity for a formal review and decision
to point to:-
review actual project performance against plan
consider any changes to the environment in which the project is operating which may impact
the project delivery (positively or negatively)
review estimated benefits to confirm they are still on target to be delivered
review / challenge the project approach taken so far in the project
identify / agree any corrective action required to keep the project on track
review any changes (if any) to the approved project scope, timeline, financials and resourcing
…before making a decision if College will commit to closing the current stage and commencing the
next stage.
It ensures the agreed level of approval for the project, and is a checkpoint for the control of College
resources (€, resources, technology).
Step 1. Sponsor signs off project to request Stage Gate Approval and requests Project Manager to
collate all required documentation.
Step 2. Project Manager collates all required documentation for the Stage Gate Approval Pack.
Step 3. Steering is presented with the Stage Gate Approval pack and a decision whether to proceed
to Stage Gate Approval is made.
Step 4. If Steering decides to proceed to Stage Gate Approval, the Sponsor submits the Stage Gate
Approval request to CRG.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 27 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 28 of 85
PMO HANDBOOK
3.5.1 Background
The primary owner for the process is the Project Manager/Project Sponsor. Changes during the
course of a project are inevitable and can affect the project scope, cost, deliverables, delivery
timeline, and benefits. The Change Request (CR) management process is a systematic approach that
allows for change while minimising the negative consequences of those changes. The CR
management process is used when a change has been identified that requires approval to vary the
approved project baseline.
This is the only process for varying the project baseline and a CR Approval form is used to record the
change description, benefits, request options, costs and details of impact.
A CR may be initiated by anyone involved in the project. For example:
College may originate a CR because the environment, needs, or goals have changed since
the project started
The project team may identify issues during design/implementation. As knowledge of the
solution increases, aspects of the original design may no longer be suitable or optimal
A non-compliance issue may need corrective action.
After completion of the CR Approval form, the Project Sponsor must approve the request to proceed
for evaluation. If the impact of the change falls within the approved project baseline, accountability
for approving the CR will remain with the Sponsor. If the impact of the change falls outside of the
approved project baseline, then the CR and its impacts will be submitted by the Sponsor to the
Steering Committee for approval and then on to the Appropriate Authority based on the current
project approval levels (e.g. CRG/EOG/Board) using the Change Request presentation template.
Additional documents used by the Project Manager and Sponsor during the process include:
Change Request Log (see tab in Change Request PRI Log template)
Project Risk Indicator (PRI) Log (see tab in Change Request PRI Log template)
Business Case Pack (Business Case, Financial Plan, Project Delivery Plan and related trackers)
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 29 of 85
PMO HANDBOOK
Review CR &
consider for
evaluation
Approve No
evaluation Close CR
exercise?
Yes
Escalate CR to
Within approved No Project Steering
baseline? Committee for
decision
Approve CR No
Yes Close CR
evaluation?
Yes
Approve CR No
Evaluate CR Close CR
evaluation?
Request Approval
for Change
Yes
Approval for No
Close CR
change?
Yes
Escalate CR to
Within approved No Project Steering
baseline? Committee for
decision
Approve CR No
Yes Close CR
delivery?
Yes
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 30 of 85
PMO HANDBOOK
The Project Sponsor works with the Project Manager to ensure that appropriate
resources are assigned to evaluate the change request.
The Project Manager / Project Sponsor inform the Project Steering Committee of the
change request in the next status report / at the next Steering Committee meeting.
2. If it falls outside the approved baseline, then the Project Sponsor escalates the change
request to the project Steering Committee for review and decision at the next Steering
Committee meeting.
Reject the Change Request – the Steering Committee does not accept the impact of
evaluating the CR. The CR will not be evaluated.
Approve the Change Request - the Steering Committee accepts the impact of
evaluating the CR and approves its escalation to the CRG for a decision (as it is
outside of their approval authority).
If approved for escalation by the Steering Committee to the CRG, the Project Sponsor
prepares the required documentation and submits a request for approval by the CRG via
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 31 of 85
PMO HANDBOOK
the Approval & Prioritisation process. Please refer to the relevant section in this
document for full details on this process. .
If the CRG does not accept the impact of evaluating the change request, the change request
will not be evaluated.
If the outcome of the CRG is the approval of the evaluation, the Project Sponsor works with
the Project Manager to ensure that appropriate resources are assigned to evaluate the
change request, and continue to progresses through the Change Request process.
If the request has been escalated to the CRG, the Project Manager provides details of the
change request and its status to the PMO. PMO update the Project Portfolio Change
Request Log.
At each stage of the process, the Project Manager updates the Requestor of the status of the
change request, and updates the Change Request PRI Log.
Step 5. Evaluate Proposed Change
Assigned resources evaluate the change request to determine the potential impact (cost,
resource effort, schedule & quality), risk, and complexity of the request.
Evaluation of the proposed change may involve the following actions:
Evaluating the scope of the potential change to determine the project & business
impact
Determining the effects the change may have on completed and planned
deliverables
Identifying any modifications required to the project baseline and/or documents
Estimating the resource effort and costs associated with completing the change and
determine the costs of not addressing the change
Providing a recommendation on the priority of the change
Proposed change request may need to be communicated to the project team to determine
the full impact of the event. Depending on the urgency of the request, the changes may be
discussed during the regular weekly project team status meetings or at a special meeting.
Assigned resources complete the project change request impact details with their evaluation
findings and provide the completed information to the Project Manager.
If the request has been escalated to the CRG, the Project Manager provides details of the
change request and its status to the PMO. PMO update the Project Portfolio Change
Request Log.
At each stage of the process, the Project Manager updates the Requestor of the status of the
change request, and updates the Change Request PRI Log.
Step 6. Request Approval for Change
The Project Manager reviews findings and presents recommendations for dealing with the
CR to the Project Sponsor.
The Project Sponsor makes a decision on the change request, which could be-
Approved
Rejected
Further Information Requested
On Hold / Deferred
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 32 of 85
PMO HANDBOOK
If the Project Sponsor does not accept the impact of implementing the change request, the
change request will not be implemented.
If the Project Sponsor accepts the impact of implementing the change request (potential
cost, resource, time slippage or change in quality of deliverables), they will do one of two
things:-
1. If the impact of the change falls within that approved project baseline for resource
effort, cost, benefit, and delivery schedule which was approved by the CRG when
the project was approved and prioritised, the accountability for approving the
change request implementation will remain with the Project Sponsor.
The Project Sponsor works with the Project Manager to ensure that appropriate
resources are assigned to deliver the change request.
2. If it falls outside the approved baseline, then the Project Sponsor escalates the
change request to the Project Steering Committee for review and decision at the
next Project Steering Committee meeting.
The Steering Committee can make one of the following decisions:
Reject the Change Request – the Steering Committee does not accept the impact of
implementing the CR. The CR will not be implemented.
Approve the Change Request – the Steering Committee accepts the impact of
implementing the CR and approves its escalation to the CRG for a decision (as it is
outside of their approval authority).
If approved for escalation by the Steering Committee to the CRG, the Project Sponsor /
Project Manager prepares the required documentation and submits a request for approval
by the CRG via the Approval & Prioritisation process. Please refer to the relevant section in
this document for full details on this process.
If the request has been escalated to the CRG, the Project Manager provides details of the
change request and its status to the PMO. PMO update the Project Portfolio Change
Request Log.
If the CRG does not approve the impact of implementing the change request, the change
request will not be implemented.
If the CRG approves the impact of implementing the change request, the Project Sponsor
works with the Project Manager to ensure that appropriate resources are assigned to deliver
the change request.
At each stage of the process, the Project Manager updates the Requestor of the status of the
change request, and updates the Change Request PRI Log.
Step 7. Incorporate Change, Update Project Plans and documentation
If approval obtained, the Project Manager updates all impacted project management
documentation, including –
Business Case Pack
Business Case
Financial Plan
Change Request PRI Log
Step 8. Project Manager ensures updated documents are stored in the project directory.
Step 9. Project Manager schedules the change request requirements for delivery.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 33 of 85
PMO HANDBOOK
Step 10. Project Manager updates the Change Request PRI Log with status as the change request
progresses to completion. This is to provide a permanent record of the change request
history.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 34 of 85
PMO HANDBOOK
The templates / documents to be used by the Project Manager include the following:-
Project Status Report
Financial Plan
Oracle Financial reports, e.g., Capital Summary Report
Project Manager resolves, where possible, any differences or anomalies that are identified.
Project Manager reports any unresolved differences or anomalies to the Project Sponsor.
Project Manager updates the monthly Project Status Report with the month end
actual/committed financials for Current Stage and Overall to Date highlighting deviations
from the approved budget and any corrective actions agreed. This is submitted per
governance to the PMO (or local PO for projects less than €500K) via the Project Portfolio
Performance Reporting process.
If deviation from baseline continues, or corrective action is not sufficient, Project Manager
and Project Sponsor agree if a Change Request to alter the approved project budget is to be
submitted for consideration and approval by the Project Steering Committee(if appropriate)
and Trinity Governance (CRG/EOG/Board).
If a Change Request is required, Project Manager and Project Sponsor create a Change
Request Pack and submit for approval via the Change Request process.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 35 of 85
PMO HANDBOOK
Project Manager resolves, where possible, any differences or anomalies that are identified.
Project Manager reports any unresolved differences or anomalies to the Project Sponsor.
Project Manager updates the monthly Project Status Report with the month end
actual/committed resource effort (Man-days) for Current Stage and Overall to Date
highlighting deviations from the approved budget and any corrective actions agreed. This is
submitted per governance to the PMO (or local PO for projects less than €500K) via the
Project Portfolio Performance Reporting process.
If deviation from baseline continues, or corrective action is not sufficient, Project Manager
and Project Sponsor agree if a Change Request to alter the approved project budget is to
be submitted for consideration and approval by the Project Steering Committee (if
appropriate) and Trinity Governance (CRG/EOG/Board).
If a change request is required, Project Manager and Project Sponsor create a Change
Request pack and submit for approval via the Change Request process.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 36 of 85
PMO HANDBOOK
3.7 Risk, Assumption, Issue & Dependency (RAID) Review Management Process
The primary owner for the process is the Project Manager.
Anybody (or another project) directly or indirectly related with the delivery of the project may
identify / raise a risk, assumption, issue or dependency (RAID) item.
The Project Manager can either create the RAID item in the RAID Log, or delegate the creation of the
RAID item in the RAID Log to the individual who identified it or to one of the project team members.
Resolution of all items should be attempted by the individual / project that identified the item
before discussing with the relevant Project Manager.
The ownership of the RAID item remains with the person / project that identified it until that item
has been closed. The ownership is held, regardless of which individual or actions are involved in the
resolution or closure of the item.
The following section describes how the management of project RAID items will be implemented on
all TCD projects.
The management of RAID items is a key element of the project governance. Any deviations from
these governance requirements should be clearly documented and justified in the individual Project
Initiation Document.
The purpose of the RAID review management process is to identify, quantify and manage effectively
the risks, assumptions, issues & dependencies that could potentially have an adverse effect on the
project scope, timeline, cost, resourcing, quality or deliverables. The process entails completing a
number of actions to reduce the probability of occurrence and the potential impact on the project of
the item.
RAID review management takes into account all potential sources such as:
Scope
Timeline
Cost
Resource
Quality
Operational
Business
Technical
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 37 of 85
PMO HANDBOOK
To confirm if project assumptions made are true or false. If false, to minimise the risk to the
project by initiating appropriate mitigating actions to minimise the impact on the project
delivery
The templates / documents to be used by the Project Manager include the following:-
RAID Log
Change Request PRI log, if appropriate
Change Request Approval, if appropriate
Additional templates / documents / processes used by PMO during this process are:-
Project Portfolio RAID Log
Moderate -medium
impact to project time
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 38 of 85
PMO HANDBOOK
Red status indicates there is a live risk or issue on the project where remedial action is required to bring the
Red project back on track within the parameters set as the baseline. The remedial action has not yet been identified
and/or is not yet in progress. The risk or issue is not being addressed.
Amber status indicates there is a live risk or issue on the project; however remedial action(s) have been identified
Amber and/or are in progress to bring the project back on track within the parameters set as the baseline. The risk or
issue is being addressed.
Green Green status indicates there is no risk or issue and no action is required at this time. The project is on track to
deliver within the parameters set as the baseline.
3.8.1 Risk
A Risk is a prediction of a significant negative event that might occur in the future, and which is likely
to adversely affect the ability of the project to achieve the defined objectives.
3.8.2 Assumption
An Assumption is a statement that is assumed to be true and from which a conclusion can be drawn.
Assumptions are made about the project variables e.g. timeline, scope, cost, resourcing, quality,
business / 3rd party support and interfaces, organisational delivery capability, etc., and form part of
the basis for the project delivery. Where an assumption turns out to be false, a CR may need to be
raised to control the impact to the project delivery.
3.8.3 Issue
An Issue is a matter that is currently impeding (or will impede) the progress of the project and about
which no agreement has yet been reached. The impact of an issue may cause delay, change the
direction, impair the solution, hinder the quality, alter the deliverable content or increase the cost.
3.8.4 Dependency
A Dependency is any event or deliverable that is required before a project activity can commence or
complete. There can be internal dependencies i.e. dependencies that are being managed /
controlled within the project, and external dependencies i.e. dependencies that require interaction
between other projects / business areas / organisations that do not form part of the project e.g.
External Architects’ availability.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 39 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 40 of 85
PMO HANDBOOK
The Risk Review Management process is an iterative process and includes the following steps:
Step 1. Identification of project risks and logging to the project RAID Log
Risk Originator (Project Manager / project team member / other project or organisation
resource) identifies a risk applicable to the project.
Risk Originator attempts to resolve the risk. If this is successful, the risk is not logged and
the process completes.
If the risk cannot be resolved, Risk Originator discusses the risk with the relevant Project
Manager.
Risk Originator and Project Manager consider the risk and determine whether the risk is
applicable to the project.
Project Manager may need to seek additional information from Risk Originator / project
team / others to verify the validity of the risk.
If the risk is considered by the Project Manager to be relevant to the project, then a
formal risk is created in the project RAID Log. This may be created by the Project
Manager / Risk Originator / project team member as directed by the Project Manager.
Project Manager assigns an initial priority to the item.
Based on the initial priority assigned, the following steps will be scheduled and executed.
Step 2. Assessment of the probability of occurrence and potential impact on the project timeline,
scope, cost, resourcing, quality, etc.
Project Manager assigns a project team member to analyse the risk, and consider the
level of probability and impact to the project.
Project team member performs analysis and discusses findings with the Project
Manager.
Project Manager decides on the level of probability and impact based upon the risk’s
severity. The decision may be facilitated through discussions with the Risk Originator /
project team members / others, as appropriate to the specific risk.
Project Manager updates / confirms the priority of the item on the project RAID Log.
Step 3. Development of risk mitigation strategies to minimise impact on the project if the risk
occurs
Project Manager / project team member develop risk mitigation strategies to minimise
the impact on the project in the case of the risk occurring.
Step 4. Logging and tracking the risk details in the project RAID Log
Project Manager, project team member, or delegated resource updates the project RAID
Log with details of the risk. Any updates to the details of the risk will be captured in the
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 41 of 85
PMO HANDBOOK
log, with actions being tracked on a regular basis. This is to ensure that the latest status
of the item is always maintained in the log.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 42 of 85
PMO HANDBOOK
Based on the initial priority assigned, the following steps will be scheduled and executed.
Step 2. Assessment of the probability that the assumption is true or false and potential impact on
the project (timeline, scope, cost, resourcing, quality, etc.) if proven to be false
Project Manager assigns a project team member to analyse the assumption, and
consider the level of probability and impact to the project if the assumption is proven to
be false.
Project team member performs analysis and discusses findings with the Project
Manager.
Project Manager decides on the level of probability and impact based upon the
assumption’s severity. The decision may be facilitated through discussions with the
Assumption Originator / project team members / other, as appropriate to the specific
assumption.
Project Manager updates / confirms the priority of the item on the project RAID Log.
Step 4. Logging and tracking the assumption details in the project RAID Log
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 43 of 85
PMO HANDBOOK
Project Manager, project team member, or delegated resource updates the project RAID
Log with details of the assumption. Any updates to the details of the assumption will be
captured in the log, with actions being tracked on a regular basis. This is to ensure that
the latest status of the assumption is always maintained in the log.
Step 5. Monitoring of assumptions and invoking the assumption action plan for assumptions
proven to be false
Project Manager and Assumption Owner monitor the assumption to see if the
probability or impact has changed since last reviewed. Action plans are invoked as
required.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 44 of 85
PMO HANDBOOK
Step 1. Identification of the project issues and logging to project RAID Log
Issue Originator (Project Manager / project team member / other project or organisation
resource) identifies an issue applicable to a project.
Issue Originator discusses the issue with the relevant Project Manager.
Issue Originator and Project Manager consider the issue and determine whether the
issue is applicable to the project.
Project Manager may need to seek additional information from the Issue Originator /
project team / other, to verify the validity of the issue.
If the issue is considered by the Project Manager to be relevant to the project, then a
formal issue is created in the project RAID Log. This may be created by the Project
Manager / Issue Originator / project team member as directed by the Project Manager.
Project Manager assigns an initial priority to the item.
Based on the initial priority assigned, the following steps will be scheduled and executed.
Step 2. Assessment / Estimation of the impact of the issue on the project (timeline, scope, cost,
resourcing, quality, etc.)
Project Manager assigns a project team member to assess the issue, and define /
estimate the impact to the project.
Project team member performs assessment and discusses findings with the Project
Manager.
Project Manager decides on the priority of the issue based on the upon the issue’s
severity. The decision may be facilitated through discussions with the Issue Originator /
project team members / other, as appropriate to the specific issue.
Project Manager confirms and updates the priority of the item on the project RAID Log.
Step 3. Development of issue corrective action plan to close / minimise the impact on the project
Project Manager / project team member develop corrective action plans to close out the
issue or, if that is not possible, to minimise its impact on the project.
Step 4. Logging and tracking the issue details in the project RAID Log
Project Manager, project team member, or delegated resource updates the project RAID
Log with details of the issue. Any updates to the details of the issue will be captured in
the log, with actions being tracked on a regular basis. This is to ensure that the latest
status of the item is always maintained in the log.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 45 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 46 of 85
PMO HANDBOOK
Based on the initial priority assigned, the following steps will be scheduled and executed.
Step 2. Assessment of the probability that the dependency is not met and potential impact on the
project (timeline, scope, cost, resourcing, quality, etc.) if not met,
Project Manager assigns a project team member to assess the dependency, and consider the
level of probability and impact to the project if the dependency is not met.
Project team member performs assessment and discusses findings with the Project
Manager.
Project Manager decides on the level of probability and impact based upon the
dependency’s severity. The decision may be facilitated through discussions with the
Dependency Originator / project team members / other, as appropriate to the specific
dependency.
Project Manager updates / confirms the priority of the item on the project RAID Log.
Step 3. Development of action plans / mitigation strategies to minimise impact on the project if
the dependency is not met
Project Manager / project team member develop dependency action plans / mitigation
strategies to minimise the potential impact on the project in the case of the dependency not
being met.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 47 of 85
PMO HANDBOOK
Step 4. Logging and tracking the dependency details in the project RAID Log
Project Manager, project team member, or delegated resource updates the project RAID Log
with details of the dependency. Any updates to the details of the dependency will be
captured in the log. The Project Manager must ensure that the latest status of the item is
always maintained in the log.
Step 5. Monitoring of dependency & invoking action plans / mitigation strategies as required
Project Manager and Dependency Owner monitor the dependency to see if the probability
or impact has changed since last reviewed. Action plans / mitigation strategies are invoked
as required.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 48 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 49 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 50 of 85
PMO HANDBOOK
3.12.2 Sponsor
The Sponsor has overall accountability for delivering the project within the agreed scope, timeline,
quality and budget and is accountable for gaining project financial approval and for demonstrating
project benefits in order to make the case for approval & prioritisation of the project. The Sponsor
develops the Business Case and approves/accepts key project deliverables.
Responsibilities include:
Financial Management
Accountable for ensuring financial approval for the project (project costs, on-going
operational costs and benefits realisation).
Accountable for ensuring approval to draw down on the project budget at each Stage Gate
or as agreed in the Business Case or at project approval.
Accountable for Financials Planning of project, and initiate corrective action where
necessary within the constraints lay down by the project.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 51 of 85
PMO HANDBOOK
Secure availability and timely assignment of the key resources required for successful
delivery.
Attend all Steering meetings or arrange appropriate delegate.
Communicating unforeseen issues (priority) to relevant stakeholders/committees.
Project Deliverables
Responsible for development and presentation of the Business Case and related ongoing
deliverables including financial model.
Proposing/approving/accepting overall project solution and key project deliverables.
Passing back to steering the key deliverables that have been completed and approved.
Accountable for producing required management (including financial) reporting.
Attending key project decision making meetings as required.
Maintaining project alignment with business and cultural goals.
Responsible for delivering the benefits that underpin the achievements of the programme’s
Business Case.
Building durability for the project’s outputs so that they will be sustained by the people and
processes in place once the project completes its handover.
Developing the facilities management plan (in Construction projects).
Accountable for occupation of the building (in Construction projects).
Review and close out of project Stage Gates
Conduct review of project once completed
Arrange audit by College internal auditor, external auditors, external auditors from State
Departments and other agencies.
Confirmation of project benefits on completion.
Post-project monitoring to ensure benefits achieved in successful handover to business as
usual.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 52 of 85
PMO HANDBOOK
The Programme/Project Steering Committee member’s role is to ensure that project priority and
resource commitment is achieved and maintained within their department/area and to
approve/accept key project deliverables as presented by the programme/project team.
Responsibilities include:
Ensuring compliance with Capital Project Governance under which the programme/project
operates.
Monitoring and controlling the project scope and containing it to what is formally defined
and approved in the Business Case.
Ensuring that all changes are formally approved via the Change Request process.
Reviewing and accepting key programme/project deliverables as required.
Ensuring project priority is achieved and maintained within their department / area.
Enabling appropriate resource commitment within their department / area.
Proactively and visibly sponsoring the project within their department / area.
Delivering key project messages to staff within their department / area.
Reviewing, approving or rejecting Change Requests falling within the approved project
baseline. Approving or rejecting Change Requests to project scope, timeline or budget.
Acting as the ultimate escalation point for issues that cannot be resolved by the
Sponsor/Programme/Project Manager.
Escalating Change Requests which fall outside of the project baseline through the required
approvals governance.
Making strategic decisions on items raised by the project, to support delivery of the project’s
overall objectives and purpose.
Resolving Risk, Issue and Dependency items escalated through the Risk and Issue Review
Management process.
Attending key project meetings as requested.
Challenging or testing that project benefits continue to be valid throughout the
programme/project lifecycle.
In the event of a conflict between the Chair and Sponsor which cannot be resolved at
Steering, Chair has the responsibility of escalating to EOG for resolution.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 53 of 85
PMO HANDBOOK
Ensuring that all Steering members engage to the appropriate level in the discussions and
decisions of the committee.
Ensuring the meetings are organised, managed and executed in an effective and efficient
manner to maximise the Steering Committee members’ investment of time and effort.
Steering may also include other specific roles including the following. Specific representatives –
dependent on project type who may not be in every Steering Committee – may include:
Dean of Research: ensuring alignment with College innovation and entrepreneurship
strategy.
Advisory Board Representative: manages the relationship with school or other advisory
boards.
Representative of Trinity Foundation: managing the relationship with the donor
community.
Advisor to Sponsor: for advice on specialist areas including architecture.
Finance representative: holds the Sponsor, Steering, Project team and key stakeholders to
account for financial decisions and project finances. Owns the financial model for the project
and is responsible for monitoring and reporting performance against it.
Estates and Facilities representative: ensures that building/construction fits with College
facilities management systems and processes and that there is a good fit with the overall
College amenities. Ensures timely and effective communications between the
programme/project and College infrastructure services.
External consultant such as Construction Project Manager: ensuring delivery of specific
services e.g. construction project management within approved scope, timeline, budget and
quality constraints.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 54 of 85
PMO HANDBOOK
Financial Management
Financials Planning of the programme (and all sub-projects), and initiating corrective action
where necessary within the constraints as laid down by the programme.
Monitoring and controlling all financial aspects of the programme, in compliance with the
financial governance processes.
Supporting the Sponsor in obtaining financial approval for the project (project costs, on-
going operational costs and benefits realisation).
Supporting the Sponsor in getting approval to draw down on the project budget at the end
of each Stage Gate.
Governance
Ensuring that the programme and all related project activities comply with best
practices/College policy and by those agreed to by the project.
Supporting the Sponsor and Steering Committee in the preparation and delivery of key
communication messages to internal and external resources, key stakeholders and College
committees to ensure delivery within scope, schedule, budget, and quality.
Producing required management reporting and presenting to Sponsor/Steering/other as
required.
Progressing the programme’s work and use of resources, and initiating corrective action
where necessary within the constraints as lay down by the programme.
Reporting to Sponsor on completion of Stage Gates.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 55 of 85
PMO HANDBOOK
Raising Risk, Assumption, Issue and Dependency (RAID) items and proactively managing
programme RAID Logs.
Escalating RAID items that cannot be resolved by the team to the Sponsor.
Advising the Sponsor of any deviations from schedule, recommending corrective action, and
helping prepare any appropriate execution plans.
Identifying and advising the Sponsor of any risks associated with a delivery / milestone.
Ensuring information being presented to the Sponsor and Steering Committee is complete
and accurate, and effectively represents the project’s delivery status.
Supporting and advising the Sponsor and Steering on project delivery matters throughout
delivery.
Holding Project Managers and the Project Team to account for decisions and project
delivery.
Ensuring that Project Managers act in the best interests of the overall project objectives,
goals and vision, and not just their own specific project area.
Ensuring the project and programme meetings are organised, managed and executed in an
effective and efficient manner to maximise project team members’ investment of time and
effort.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 56 of 85
PMO HANDBOOK
Financial Management
Financial Planning of the project within scope, and proposing and initiating corrective action
where necessary within the constraints laid down by project governance.
Providing regular updates on project financial performance.
Monitoring and controlling all financial and resourcing aspects of the project, in compliance
with governance processes.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 57 of 85
PMO HANDBOOK
Supporting the Sponsor/Programme Manager in obtaining financial approval for the project
(project and on-going operational costs and benefits realisation).
Supporting the Sponsor/Programme Manager in getting approval to draw down on the
project budget at the end of each stage (gate).
Resolving priority conflicts or other internal project related issues that may arise within the
project.
Governance
Applying PMO methodologies, processes, templates and standards.
Preparing and maintaining a comprehensive set of project procedures to be used as a
framework to establish common policy, procedures and standards across all parties on the
project.
Establishing and managing project documentation repository. Ensuring that proper and
accurate records are maintained including all instructions and information to all project
parties.
Acting as the agent of the Sponsor/Programme Manager within the remit of delegated
authority to achieve progress on project tasks.
Providing advice to College on project implementation.
Ensuring establishment of roles and responsibilities within the project and related lines of
communication.
Liaising with internal and external resources to ensure delivery within scope, schedule,
budget, quality.
Taking tactical decisions based on the direction of the Sponsor and Steering.
Ensuring compliance with the Governance (including the Stage Gate lifecycle) under which
the project operates.
Ensuring compliance with College procurement policies and procedures.
Establishing and coordinating control systems for cost, quality and timescale.
Coordinating approval of payments within agreed timelines.
Coordinate audits and reviews of the project including post-completion.
The additional responsibilities listed below are specifically for the Project Manager on Construction
projects.
Pre-Construction
Overseeing formalities relating to Professional Indemnity and warranties.
Evaluating all necessary insurances for both professionals and contractors.
Leading all contractor and sub-contractor negotiations.
Liaising with legal advisors on all contractual issues (contract compilation terms and
conditions).
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 58 of 85
PMO HANDBOOK
Proactively working with Quantity Surveyor to achieve any potential cost savings.
Establishing Health and Safety File (Design).
Addressing all environmental aspects of the project.
Coordinating local and statutory authorities.
Submitting recommendation of contractor for approval by Steering.
Ensuring all documents regarding tax clearance are in place for contractors/sub-contractors.
Construction
Confirming from Sponsor that all contracts are signed and sealed prior to commencement of
works.
Ensuring all collateral warranties and performance bonds are in place.
Confirming adequate insurance cover for works.
Establishing and maintain Health and Safety File (Construction Stage).
Responsible for contractor’s construction schedule and method statements.
Establishing and managing mechanisms for dealing with potential claims during the project.
Maintaining construction progress records, photo and video records from start to
completion of the project.
Coordinating local and statutory authorities to ensure that project time and cost schedule
are maintained.
Ensuring timely site inspections take place.
Ensuring design information required by contractor is supplied by design team in a timely
manner.
Ensuring contractors resources are adequate and suitable.
Proactively working with Quantity Surveyor to achieve any potential cost savings.
Assisting and liaise with Quantity Surveyor on Final Account negotiations.
Post-Construction
Responsible for all commissioning documentation, maintenance manuals, and all as-built
drawings.
Advising Programme Manager/Sponsor on insurance termination post contract.
Planning and reporting on with testing and commissioning documentation.
Ensuring all training regarding facilities is completed in a timely manner.
Confirming receipt completion certificates from design team.
Ensuring creation of snag lists by design team.
Responsible for closure of items on the design team snag lists.
Establishing the system of defects reporting post-construction.
Responsible for rectification works.
Assisting with handover of Health and Safety File (Post-Construction).
Procuring warranties and guarantees from suppliers.
Submitting final project close-out report for sign off at end of defects liability period.
Ensure publicity plaques are in place if required.
Review final Stage Gate.
Ensure audits are planned and carried out.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 59 of 85
PMO HANDBOOK
Pre-Construction
As client representative attending programme meetings/processes to observe, report and
act on the selection process of:
o Design Team members
o Design team appointment
o Contractor, subcontractor and supplier interviews, selection and appointments
Taking Client instructions and report back to Sponsor/Programme Manager/Project
Manager.
Making independent recommendations to Sponsor/Programme Manager/Project Manager.
Working with client legal advisors on design team appointments and liabilities.
Making independent recommendations to Sponsor/Programme Manager/Project Manager
following legal advice on various project issues.
Visiting consultant team members to query, interview and make suggestions and
recommendations to design team lead and Sponsor/Programme Manager/Project Manager.
Representing Sponsor/Programme Manager/Project Manager and have authority to issue
instructions at design team meetings.
Making independent recommendations on final approval and sign off at each stage of the
construction process.
Ratifying budgets and cost control procedures.
Working with Procurement on tender and reporting process.
Construction
As Client Representative attending where possible all construction and site meetings
o Verification of change order (Change Request) procedures. As changes occur, the
Validating Agent is the direct link between College and the team for verifying
reasons for change, to identify who is responsible for change and at what cost.
o Proactively pursuing design cost savings.
o Monitoring and independent reporting on design cost additions.
o Access to all quantities and costs before and during progress of works.
o Working with Client’s legal advisors on all contractual issues relating to the Business
School.
Access to monthly payment recommendations for certification in order to provide
independent, regular reports to Board.
Participation at any dispute negotiations during the progress of the works and reporting on
additional costs should they arise.
Reporting independently to Board on all progress in relation to cost reports and procedures
to highlight any deviations/variation from approved budget and agreed time schedule.
Reporting to Board on a regular basis on any delay or disruptions on site which may have a
cost implication.
Authority to visit team consultants during the progress of the works to assist with any
reporting issues to the board.
Attending with project team members on compilation of snag lists and verification of snag
solutions and liabilities etc.
Assist with audit and final sign-off at each Stage Gate of the project as Client’s
Representative.
Post Construction
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 60 of 85
PMO HANDBOOK
As Client’s Representative:
o Attendance and participation at final account agreement meetings.
o Ensure all “As built” drawings and O&M documentation etc. are compiled as works
progress.
Responsible for signing off final account cost report and agreement with Quantity Surveyor.
Liaising on behalf of the client with construction and decanting projects on handover and
occupation procedure. Support smooth handover and ensuring that proactive solutions are
considered as the work progresses.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 61 of 85
PMO HANDBOOK
Providing expert knowledge within their field and provide source information to the project
team.
Reviewing and confirming all major deliverables for the project relevant to the area with the
Project Manager, Business Analyst and Project Team Members.
Providing expert knowledge on information collected and used in performing work.
Providing expert knowledge on when, how and by whom information is used.
Identifying opportunities to improve effectiveness, efficiency and economy of processes.
Assisting in identifying and defining issues with existing processes.
Participating in defining new and amended functional requirements.
Developing test cases and perform/sign off on acceptance testing.
Participating as required in any testing activities.
Responsibilities include:
Providing expert legal knowledge within their field and provide source information to the
project team.
Evaluating and reporting on the impact of legislation on the project.
Drafting information for review by SMEs, Business Analysts and Project Governance and the
project team.
Ensuring compliance with legislation.
Coordinating all professional/employment contracts to ensure compliance with College
procurements policy and procedures.
Availability for
o Contractual advice before, during and after progress of works.
o For legal advice on delays and disruptions if and as these occur.
o For legal advice on warranties and maintenance issues should they arise.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 62 of 85
PMO HANDBOOK
Supports the business in the development of the financial model for the project.
3.12.11 Trainer
Responsibilities include:
Understanding in full the project’s business context, solution and deliverables.
Developing the project training strategy and detailed plan.
Developing training guides and content for courses and manuals.
Establishing and executing appropriate training sessions to support project strategy and
deliverables.
3.12.12 Architect
Responsibilities include:
Pre-Construction
Producing Client Brief.
Producing Initial Design.
Producing Developed Design.
Producing Detailed Design.
Producing Tender Documentation.
Construction
Carrying out Site Inspections and Visits.
Providing Contract Administration.
Providing Payment Certification.
Monitoring and signing-off scope change.
Monitoring extensions of time.
Attendance at all relevant meetings.
Compilation of snag lists.
Supervising completion of snag lists.
Dealing with disputes on site should they arise.
Post-Construction
Producing Certificate of practical completion
Producing Final Payment Certification
Providing opinion on compliances with planning and building regulations.
Providing as-built drawings.
Pre-Construction
Preparing a preliminary cost study based on the Concept Design.
Preparing and implementing cost estimating and control procedures for the Project, to be
approved by College.
Preparing and implementing change control procedures for the Project, to be approved by
College.
Reviewing of and input to, as appropriate, all Project reports and studies.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 63 of 85
PMO HANDBOOK
Preparing feasibility cost estimates for all alternative design solutions proposed by the
Design Team.
Attending all project and specific discipline meetings as required.
Preparing and establish a Definitive Estimate or Budget for the Project as part of the
completion of Preliminary Engineering.
Preparing a detailed cost plan for the Project and advising on financial effects of
construction phasing.
Completing Value Engineering reviews at all major stages of design development.
Providing full Quantity Surveying services to the Project including preparation of Bills of
Quantities for all Works Contracts (including any enabling works contracts required).
Providing Bills of Quantities for M&E elements of the work.
Regularly reviewing design development to ensure compliance with cost plan or
recommending action to mitigate impending overruns.
Consulting and liaising with all Project Parties in a supportive and co-operative manner to
ensure overall Project objectives are met.
Ensuring PM Team and College are advised of any circumstances arising that might cause
cost or schedule overrun.
Advising on tendering procedures and contract documents in respect of all construction
contracts, and prepare the appropriate documents as required.
Reviewing and analysing all construction bids, as appropriate and attending clarification and
negotiation meetings with Bidders.
Construction
Providing comprehensive cost and cash flow reports for the Project on a monthly basis.
Carry out all responsibilities and activities efficiently and in accordance with the programme.
Attending site meetings as necessary.
Monitoring actual cash flow against forecast.
Approving invoices for payment and ensure payment by College.
Ensuring contractor compliance with all insurance requirements. Secure certificates for
safekeeping.
Post-Construction
Negotiating and agreeing final account with main contractor and all sub-contractors.
Providing final cost report for College.
Pre-Construction
Liaising with design team on programme for completion of design.
Liaising with design team on programme for construction of works.
Development of design proposal for works.
Preparing representative sketches/drawings/specifications to assist with planning
permission/cost plan.
Consulting with local authorities.
Developing detailed design.
Preparing final calculations to comply with building regulations.
Assisting Quantity Surveyor with estimates of reinforcement, final specifications etc. for Bill
of Quantities.
Assisting Architect in communication to client over technical suitability of works.
Advising on the need for any special conditions of contract relevant to the works.
Advising the Client/Architect on the likely necessity for appointing supervisory site staff.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 64 of 85
PMO HANDBOOK
Construction
Advising on preparation of formal contract documents relating to accepted tenders for
carrying out the works or any part of them.
Advising the Client/Architect in relation to the need for special inspections or tests arising
during the construction of the Project.
Reporting to Architect on the necessity of appointment of supervisory site staff.
Assisting the Architect in examining the Contractors proposals where required by the
building contract documents.
Attending for duration of the structural works, all relevant site meetings.
Advising the Architect on certificates for payment to the contractor.
Performing any services which the Consulting Engineer may be required to carry out under
any contract for the execution of the works.
Assisting the Architect in settling any dispute or difference relating to the works.
Post-Construction
Delivering copies of the drawings supplied to the Contractor for the project upon completion
of the works.
Pre-Construction
Preparation of mechanical and electrical services drawings.
Preparation of mechanical and electrical services specifications.
Preparing budgets and obtaining costs from nominated contractors.
Negotiating Fixed Price on receipt of costs (if applicable).
Construction
Attending all site meetings.
Carrying out site inspections and oversee Mechanical and Electrical Contractor’s work.
Evaluating interim work in progress for Quantity Surveyor.
Making payment recommendations, MEP work for Quantity Surveyor.
Snagging building services and overseeing completion.
Post-Construction
Preparing final accounts.
Issuing opinion on compliance in relation to Building regulations.
Checking ‘as built’ drawings and documents/certified contained in the Mechanical and
Electrical operational and maintenance manuals.
Preparing Health & Safety statement as part of the design process in relation to the services
element of the project.
Pre-Construction
Participating in design team meetings
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 65 of 85
PMO HANDBOOK
Construction
Holding regular meetings with design team
Liaising with Fire Officer
Monitoring installation
Monitoring variations in specification with regard to fire implications.
Procurement of O&M and specification confirmations with regard to fireproof material.
Post-Construction
Providing certification and documentation for Fire Officer.
Pre-Construction
Holding regular meetings with design team.
Compiling and producing a Safe System of work plan (SSWP).
Appointing a Project Supervisor, Design Process (PSDP).
Appointing a Project Supervisor, Construction Stage (PSCS) (Pre-construction).
Developing the Health & Safety file for the project and make available to PSDP, PSCS and
Contractor.
Communicating and liaising with team as necessary.
Construction
Holding regular meetings with design team and contractor.
Monitoring continuous Health & Safety on site.
Updating and amending the Health & Safety file.
Liaising with team if necessary.
Conducting/supervising toolbox talks, safety talks.
Post-Construction
Making site Health & Safety file available for handover.
Compiling Health & Safety report post construction.
Pre-Construction
Compiling report on traffic implication for new construction.
Engaging with Health & Safety Consultant.
Construction
Monitoring traffic control including traffic light coordination, access and egress and liaising
with Dublin City Council, traffic department.
Liaising with An Garda Siochána, if required.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 66 of 85
PMO HANDBOOK
Pre-Construction
Holding regular meetings with design team.
Acquiring client brief.
Production of drawings and specification.
Compilation of budgets and costs for fit out.
Construction
Monitoring work in progress during fit out.
Working closely with design and management team on site.
Dealing with all insurances of fit out staff.
Engaging with Health & Safety Consultant.
Supervising installation.
Signing off of installation on completion.
Post-Construction
Dealing with all snags and maintenance issues with regard to fit out.
Acquisition of all O&M manuals.
Monitoring use of fit out installation until expiration of warrantees etc.
Pre-Construction
Holding regular meetings with design team.
Engaging with Health & Safety Consultant.
Compilation and production of report with regard to sustainable energy.
Signing off on accepted specification for sustainable energy within the design and contract
documents.
Construction
Monitoring sustainable energy materials and installation during the progress of the works.
Availability to amend design should variations occur.
Ensuring maintenance of sustainable energy components during the works.
Signing off of components and fittings upon completion of the works.
Post-Construction
Monitoring use of sustainable energy components until expiration of warrantees etc.
Compilation of report on sustainable energy at close-out of project.
3.12.21 Planner
Responsibilities include:
Pre-Construction
Holding regular meetings with design team.
Consultation with Dublin City Council planning department.
Production of planning report and recommendations.
Assisting design team with planning application lodgement.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 67 of 85
PMO HANDBOOK
3.12.22 Archaeologist
Responsibilities include:
Pre-Construction
Holding regular meetings with design team.
Liaising with Dublin City Council.
Compilation of report on archaeology aspects of project, if any.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 68 of 85
PMO HANDBOOK
CRG is not responsible for the execution of projects, but plays an oversight role on behalf of the EOG
and Board to monitor project performance against what was approved. It also monitors the overall
College project portfolio performance and may recommend reprioritising, placing on hold or halting
a project to support the success of the overall portfolio.
CRG does not have the authority to make decisions on behalf of the Project Steering or Sponsor, but
can raise concerns about a project and may escalate these concerns to the Project Sponsor or
Steering / EOG / Board for resolution. CRG reports decisions, recommendations and escalations to
EOG. CRG reports decisions affecting space allocation to the Space Allocation Sub-Committee (SASC).
CRG may approve projects with a capital spend up to €150k.
CRG comprises the following members:
Bursar (Chair).
Chief Operating Officer.
Chief Financial Officer.
Head of PMO.
PMO Admin (Secretary).
As the PMO does not have a responsibility for proposed or approved projects with a capital spend of
less than €500k, responsibility for receipt and recording of information for these projects (approval,
prioritisation, performance reporting etc.) lies with local project offices where these are in place,
and with PMO for support of the business areas otherwise.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 69 of 85
PMO HANDBOOK
To manage and report on Capital Project approval and prioritisation, and project portfolio
performance reporting processes in a timely and effective manner.
CRG can approve projects with an estimated / potential capital spend of up to €150k. CRG may
decide to escalate projects within their approval limit to EOG for approval if deemed appropriate
(e.g. project is of high risk).
All projects with an estimated / potential capital spend value of greater than €500k must have an
EOG Champion assigned.
EOG can approve projects with an estimated / potential capital spend of up to €3m. EOG may decide
to escalate projects within their approval limit to Board for approval if deemed appropriate (e.g.
project is high risk).
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 70 of 85
PMO HANDBOOK
Any project with an estimated / potential capital spend of more than €3m must be approved by
Board.
Deans and Chief Officers are responsible for sign-off of projects being proposed by their area in
advance of their submission via CRG into the project Approval & Prioritisation process.
When an annual prioritisation process is adopted submissions will follow a 2 pass review approach
through the CRG. The 1st pass will be used by CRG to review all project submissions at a high level
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 71 of 85
PMO HANDBOOK
and filter those that are not to be progressed further as they are not considered to be appropriate
for College to pursue at this time. Projects will be categorised into one of the following:
Rejected
Additional information required before being considered further
On hold
Progressed to the next pass of the CRG process.
These meetings will be scheduled to take place annually at the end February through end March.
The 2nd pass will be used by CRG to review those projects progressed from the 1st pass at a much
greater, granular level of detail. Detailed Business Cases will be developed by the Project Sponsor
and a standard summary template completed for submission to CRG. Submitted proposals will be
considered, Business Cases challenged, and decisions made on what projects are to be
recommended for:
Approval
Rejection
On hold
Further information required
This decision will be based on a number of criteria and will take into account the impact of a project
on the overall College project portfolio, and the appropriate use of College resources (money,
people, technology, etc.). These meetings will be scheduled to take place annually from May through
mid-June.
Projects being recommended for approval will be presented to EOG / Board for approval, as
appropriate.
For approved projects, the Head of PMO will provide timely collated and summarised project
performance information based on information received directly from the projects or via the local
Project Office, where one exists.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 72 of 85
PMO HANDBOOK
For proposed projects, the Head of PMO will provide the latest summary information made
available either directly from the projects or via the local Project Office, where one exists.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 73 of 85
PMO HANDBOOK
In summary, each project will use a shared project folder in which to maintain all project
management information. A document/file directory structure will be proposed by PMO (intended
as a guide). Project Managers may make changes to this as required by their own specific project.
The project folder will be used to facilitate sharing of information amongst the project team and
within the wider key stakeholder community as appropriate.
All working documents will be saved by project team members so that all have access to and are
working on the same version of deliverables.
Documents will include minutes of all meetings, presentations and communications.
All project resources will complete periodic timesheets and provide to the Project Manager. This
information will feed into the project financial processes, calculating actuals and budgets for the
project.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 74 of 85
PMO HANDBOOK
In the process of implementing the PMO, the full range of governance structures, roles and
responsibilities were proposed in detail and approved, as were the key project management
processes for approval, prioritisation, reporting, risk and issue management while other process
designs are being prepared with input and feedback from the key areas of College managing Capital
Projects.
As roles and responsibilities and project management processes have been developed further, the
PMO Design Team have reviewed each Stage in this model and introduced some modifications in
order to achieve the original objectives by expanding the model to encompass all Capital Project
types.
In doing this, the PMO Design Team continues to engage with the PMO Consultation Group. In
addition, the Team has used portfolio, programme/project management and construction best
practice with particular emphasis on the Irish Government’s Capital Works Management Framework
(CWMF – see below).
In summary, the PMO Design team have confirmed the following lifecycle for Capital Projects. The
modified lifecycle illustrated in the diagram below addresses several issues including the fit of the
model with several project types other than construction, staying in line with more recent
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 75 of 85
PMO HANDBOOK
developments including design of the approval and prioritisation process, and alignment in full with
the Government framework thus enhancing governance and control at all Stages in the lifecycle.
The original Stage Gate lifecycle has been reviewed against best practice and construction
frameworks and aligned to enhance Capital Projects Governance and control over all Stages of the
lifecycle.
The figure overleaf cross-references the original Stage Gate lifecycle proposed by PrimeCore with
the Capital Project Governance Process, aligned with CWMF and identifying the rationale and
benefits of the modification.
The over-arching project management methodology remains Stage Gate in its design as approved by
Board.
Additional mandatory Steering Reviews have been added and these align with the CWMF
framework. Deliverables from the construction lifecycle have been aligned with Stage Gate to ensure
that projects of all types will be managed using a standardised approach.
The following is the detailed Stage Gate Lifecycle model:
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 76 of 85
PMO HANDBOOK
DELIVERABLES
SPONSOR PROJECT MANAGER PROJECT MANAGER PROJECT MANAGER PROJECT MANAGER PROJECT MANAGER SPONSOR
OWNER*
HANDOVER &
Sub-Stage PASS 1 : FILTER PASS 2 : ASSESS TENDER EXECUTION TESTING
IMPLEMENTATION
BUSINESS CASE [PRODUCTS BENEFITS
BUSINESS CASE PROJECT INITIATION DOCUMENT DELIVERY PLAN (DETAILED) DELIVERY PLAN (DETAILED) WHOLE LIFE COST UPDATE TEST PLAN SCHEDULE LESSONS LEARNED
(APPROVED) DELIVERED] REVIEW
FINANCIAL, RESOURCE FINANCIAL, RESOURCE PLANS
PROJECT FINANCIAL PLAN DELIVERY PLAN (HIGH LEVEL) [TENDER DOCUMENTATION] [PRODUCTS TESTED]
PLANS (DETAILED) (DETAILED)
MANAGEMENT
RESOURCE PLAN FINANCIAL & RESOURCE PLANS [BUSINESS REQUIREMENTS] [CONTRACTOR LIST SELECTION]
DELIVERABLES
LIFECYCLE [APPOINT DESIGN TEAM] [HIGH LEVEL DESIGN] [FUNCTIONAL SPECIFICATION] [TENDER ASSESSMENT CRITERIA ]
[TECHNICAL
DELIVERABLES] [TENDER ANALYSIS & REPORT ]
[CONTRACTOR RECOMMENDATION]
PROCESS APPROVAL & PRIORITISATION STANDARD PROJECT MANAGEMENT PROCESSES incl. STAGE GATE, PERFORMANCE REPORTING, RAID, CHANGE CONTROL
GATES 0 1 2 3 3a 4 4a 4b 5 6
1 2 3 4 5 6 7
CAPITAL WORKS MANAGEMENT
Definitive Procurement Strategy Devd Cost Plan (rev) Tender Documentation Project
Preliminary Project Brief Contract Type Proposal Stat Approvals Sub'n Detailed Pre-tender Cost Check Outturn
FRAMEWORK (CWMF)
Preliminary Output Spec Project Team Selection Report* Devd Sketch Scheme Whole Life Cost Update Review
Feasib. Study, Cost Plan * if not appointed earlier Contractor List Selection
Design Brief Tender Assessment Criteria
Devd Cost Plan (rev) Final Output Spec
Stat Approvals Sub'n Definitive Project Brief Outline Sketch Scheme (Buildg) Developed Cost Plan Tender Analysis & Report
Devd Sketch Scheme Proj Execution Plan Preliminary Planning drawings Contractor Recomm
Risk Management Plan Outline Cost Plan
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 77 of 85
PMO HANDBOOK
PRIMECORE NEW STAGE FOLLOWED BY GATE REVIEW STEERING REVIEW RATIONALE AND BENEFITS
(0) Idea Screening, APPROVAL & 0: CRG recommends project, Improved governance/controls on filtering
Gate 0 PRIORITISATION submits it to EOG/Board to proposed projects.
approve funding for initiation
and strategic planning
(1) Project INITIATION & 1: CRG makes recommendation Aligns with Steering Review 1 Improved flow of project, allows advancement of
Initiation, Gate 1 STRATEGIC to EOG/Board re acceptance of project to high level design stage, aligns better
(2) Strategic PLANNING Stage with sequencing of variety of project types.
Planning, Gate 2
(3) Concept, Gate 3 DETAILED Midway in Stage: CWMF/Steering Review 2 for Aligns with CWMF Review 2.
(4) Basis of Design PLANNING AND construction projects: definitive procurement strategy,
Gate 4 HIGH LEVEL DESIGN contract type proposal, project team selection report.
2: CRG makes recommendation Aligns with Steering Review 3 for construction projects: Aligns with CWMF Review 3.
to EOG/Board for Stage Outline sketch scheme, preliminary planning drawings,
acceptance and outline cost plan.
(5) Detailed DETAILED DESIGN Midway in Stage: Aligns with Steering Review 4 for Aligns with CWMF Review 4.
Design, Gate 5 construction projects: detailed cost plan.
3: CRG makes recommendation Aligns with Steering Review 5 for construction projects:
to EOG/Board re acceptance of developed sketch scheme, developed cost plan, Aligns with CWMF Review 5.
Stage statutory approval submission.
(6) Execution & EXECUTION &
Handover, gate 6 HANDOVER:
Tender 4: Following Tender Steering Review 3a – all projects (following Tender). Aligns with CWMF Review 6.
Aligns with Steering Review 7 for construction projects: Aligns with CWMF Review 7 (LAST REVIEW).
tender analysis and report, contractor rec’n.
Execution Steering Review 4a – all projects (following Execution). Enhanced governance and control over the
Testing Steering Review 4b – all projects (following Testing). details of execution, testing and handover.
5: CRG makes recommendation Approval to move into Closeout Stage
Handover & to EOG/Board re Stage
Implementation acceptance
(7) Closeout CLOSEOUT 6: CRG makes recommendation Enhances governance over Closeout Stage and
(no Stage gate) to EOG/Board re final closeout reviews lessons learned from project; establishes
and agrees review period and timeline/expectations for Benefits Realisation
deadline for Benefits Review. review
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 78 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 79 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 80 of 85
PMO HANDBOOK
A 2. Definitions
A2.1 Projects and their classifications
A project is defined as a temporary activity designed to produce a unique product, service or result
with a defined beginning and end (usually time-constrained, and often constrained by funding or
deliverables), undertaken to meet unique goals and objectives, typically to bring about beneficial
change or added value. The temporary nature of projects stands in contrast with business as usual
(or operations), which are repetitive, permanent, or semi-permanent functional activities to produce
products or services.
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 81 of 85
PMO HANDBOOK
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 82 of 85
PMO HANDBOOK
A 3. Abbreviations used
The following table provides a list of abbreviations commonly used throughout the project
documentation.
Abbreviation Description
BA Business Analyst
CR Change Request
LIPC Library & Information Policy Committee
PM Project Manager
PMO College-wide Project Management Office
RAID Risks, Assumptions, Issues and Dependency logs
SAC Space Allocation Committee
SME Subject Matter Expert
TCD Trinity College, University of Dublin
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 83 of 85
PMO HANDBOOK
Capital Works Management The Capital Works Management Framework is a structure that has
Framework (CWMF) been developed to deliver the Irish Government’s objectives in
relation to public sector construction procurement reform. It
consists of a suite of best practice guidance, standard contracts
and generic template documents that form the four pillars that
support the Framework.
Change Request Presentation Template for presentation of Change Request. PowerPoint
presentation required to request Steering Committee / CRG (as
appropriate) approval for changes to the project performance
areas i.e. Schedule, Financials, Resources, Scope, Quality and Risk.
Project Closure Report The Project Closure Report is the final document produced for the
project and is used by senior management to assess the success of
the project, identify best practices for future projects, resolve all
open issues, and formally close the project.
Change Request PRI Log Change Request PRI Log Template contains an Excel worksheet
used to log details of the Project Change Requests received /
processed by the project including status, impact, actions and
decisions relating to each change request.
Financial Plan Project financial estimates of resources (people, technology,
miscellaneous) required to deliver the project, and to support post
implementation. It also includes details of the estimated benefits
to be delivered by the project.
Handover & Implementation Document outlining the approach to be taken to deliver the
Schedule (part of Delivery project deliverables to the business by detailing the related
Plan) activities and tasks, responsibilities and timelines involved.
Post Implementation Benefits Evaluation (post project) of the operational success of the project
Review Template and assessment of the actual costs, benefits and savings in
comparison with planned amounts.
Project Closure report Document outlining the status of what the project set out to
achieve as documented in the Business Case, against what it
actually achieved at project completion. It also identifies the
actions required to close down project activities and move to
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 84 of 85
PMO HANDBOOK
business as usual.
Project Delivery Plan Project Delivery Plan showing key deliverables, delivery dates, and
Template key dependencies
Project Portfolio Performance Pack for presentation to CRG of all projects each month. Will
include monthly update of all live projects, Change requests, and
Reporting Pack
new Business cases. It is produced and maintained by PMO.
Project Portfolio Summary This pack contains a summary of the status of all Capital Projects. It
is produced and maintained by PMO.
Register Log
Project Status Report pack Pack for regular project status reports
RAID Log RAID Log contains an Excel worksheet to hold details of project
Risks, Assumptions, Issues, and Dependencies.
Code of Practice for Project Management for Construction and Development (4th edition
2010, CIOB)
th
Issued: 12 June 2015 PMO Handbook V1.5 Page 85 of 85