Finalized Geo Report
Finalized Geo Report
Finalized Geo Report
GEOT4002
GEOTECHNICAL DESIGN AND MODELLING
ASSIGNMENT 2
GROUP 1
DATE OF SUBMISSION
2nd June 2019
Table of Contents
List of Tables...........................................................................................................................................i
List of Figures.........................................................................................................................................ii
1.0 Introduction...............................................................................................................................1
1.1 Engineering context................................................................................................................2
1.2 Scope......................................................................................................................................2
2.0 FEA modelling approach............................................................................................................3
2.1 Geometry Input.....................................................................................................................3
2.1.1 Existing structures..........................................................................................................3
2.1.2 Borehole..........................................................................................................................5
2.1.3 Structures........................................................................................................................7
2.2 Mesh Generation...................................................................................................................11
2.3 Performing Calculations.........................................................................................................12
2.4 Output....................................................................................................................................13
3.0 Design.........................................................................................................................................23
4.0 Discussions..................................................................................................................................24
5.0 Conclusions.................................................................................................................................25
6.0 References..................................................................................................................................26
Appendix A1........................................................................................................................................27
List of Tables
Table 1: Existing Structure Loadings.......................................................................................................5
Figure 6: Safety factor, ΣMsf against displacement, lul of Section A-A’ Hardening Soil Model..............14
Figure 7: Safety factor, ΣMsf against displacement, lul of Section A-A’ Mohr Coulomb Model............14
Figure 8: Safety factor, ΣMsf against displacement, lul of Section B-B’ Hardening Soil Model.............14
Figure 9: Safety factor, ΣMsf against displacement, lul of Section B-B’ Mohr Colomb Model..............15
Figure 12: Axial Force Diagram of Section A-A’ Mohr Coulomb Model................................................16
Figure 13: Axial Force Diagram of Section B-B’ Mohr Coulomb Model................................................16
Figure 14: Axial Force Diagram of Section A-A’ Hardening Soil Model.................................................16
Figure 15: Axial Force Diagram of Section B-B’ Hardening Soil Model.................................................17
Figure 16: Shear Force Diagram of Section A-A’ Mohr Coulomb Model..............................................17
Figure 17: Shear Force Diagram of Section B-B’ Mohr Coulomb Model..............................................17
Figure 18: Shear Force Diagram of Section A-A’ Hardening Soil Model...............................................18
Figure 19: Shear Force Diagram of Section B-B’ Hardening Soil Model................................................18
Figure 20: Bending Moment Diagram of Section A-A’ Mohr Coulomb Model.....................................18
Figure 21: Bending Moment Diagram of Section B-B’ Mohr Coulomb Model.....................................19
Figure 22: Bending Moment Diagram of Section A-A’ Hardening Soil Model......................................19
Figure 23: Bending Moment Diagram of Section B-B’ Hardening Soil Model......................................19
North of the proposed site is a historical heritage listed Church while a street to the east has
an underground utility tunnel at 10m depth from ground level. The tunnel was built using
cut and cover method using concrete elements of 40mm thick. At south of proposed site,
there is a park while a 8-storey residential building can be found at west. The site plan of the
proposed building and surrounding structures can be further illustrated in Figure 1.
1.2 Scope
2. Evaluation of soil behaviour during excavation with diaphragm walls and anchors
At the beginning of modelling, the model tab sheet is set as default options. The default
options for model is plane strain and for elements is 15-Node as the 6-node triangle gives
good result in standard deformation analyses but is not recommended in problems where
failure plays an important role (Mardia 2014).
The park is considered a live load which is 5kPa from AS1170 <Table 3.1 (C4)>.
The 8-storey residential building was located at west beside to the underground excavation
construction. The foundation of the resident building was approximated 2.8m to the
underground excavation. Therefore, the loading of the residential building must be
considered in the PLAXIS 2D analysis design which is going to affect the deformation of the
diaphragm wall. The dimension of the building can be determined for calculate area.
Whereas, there are some assumption need to be considered in order to calculate structure
loading. For instance, the height of the building is assumed 3m each floor and the 8-storey
building super structure are included shear wall and slab.
The concrete tunnel is 40 mm thick built through cut and cover method. The tunnel
properties are calculated as shown in Appendix A: A3.
The figure below shows the building structure layout, Figure 2: Elevation view and Figure 3:
Plan view. Table 1 shows the assumed dimensions while Table 2 summarized the loadings to
be input into PLAXIS.
2.1.2 Borehole
Soil consists of four layers. The top layer is 5m fill layer followed by 15m clay underneath it.
The next layer consists of 11m depth silty sand. The underlying layer is bedrock and lies to a
large depth of 15m in the FEA model. The water table is 7.5m from the top layer. Only one
borehole will be created since there is no slope needed in this model. Three data sets of soil
and a set of bedrock are defined with soil properties as tabulated in Table 3.
γ unsat = γt - 4
γ t = γsat
kx = ky
Rinter of the soils are assumed according to data provided by Tjie (2014)
For fill and silty sand layer, Drained is selected as the material behaviour. From soil mechanic
perspective, soil in a drained condition means the pore water pressure has been removed
because the loading rate is low enough for the water have enough time to dissipate. In this
condition, no excess pore water pressure is considered which mean the soil skeleton will
take the loading by itself.
For bedrock layer, Non-Porous behaviour is selected in PLAXIS. This setting does not take
initial or excess pore pressure into considerations for non-porous materials or rock. This
setting is often combined with linear elastic model (Mardia 2014).
2.1.3 Structures
The excavation consists of three structural element which are diaphragm walls, anchors and
grouts. As the proposed site is isolated from the existing buildings, the diaphragm slurry
concrete wall will be supported by 3 to 6 prestressed rock anchors as shown in Figure 4 and
5.
Diaphragm walls are modelled as plates passing through (53,46)-(53,14) and (93,46)-
(93,14) for Section A-A and (43,46)-(43,14) and (73,46)-(73,14) for Section B-B. Summarized
properties of diaphragm wall are listed in Table 4. The slurry wall will be constructed in a
series of 6 metres long panels each extending a minimum of 0.6 metres into the underlying
bedrock. Calculation of properties can be found in Appendix A: A2.
Table 4: Properties of Diaphragm Walls
2.1.3.2 Anchors
In PLAXIS, the anchor is modelled by node-to-node anchor as it simulates the free length.
Failure plane is taken from the lowest point of the silty sand layer align with the diaphragm
2.1.3.3 Grout
In PLAXIS, the grout is modelled by an embedded beam as it simulates grouted part of the
anchor. Table 8 shows the properties of the grout body while Table 9 and 10 shows the
input for Section A-A and Section B-B respectively in PLAXIS. Calculation for skin resistance
can be found in Appendix A: A5. The bore diameter (d b) is calculated by db = 1.4dc in cohesive
soil (Kokona and Kokona 2016). The length of grout is fixed at 8m with reference to the case
study from (Jasmine Nisha and Muttharam 2017)
After geometry is complete, the finite element mesh is generated where geometry is
classified into volume elements and suitable structure elements based on robust
triangulation principle. It automatically transforms geometry input data to the finite element
mesh where element are nodes are made. This is part of an important role in dynamic
analysis to obtain realistic result. A coarse mesh fails to capture subtle stress changes at
points where stress concentrations are expected while a fine mesh has a longer execution
time resulting in less economical (Dey 2011). The mesh selected for this design report is
medium mesh to obtain an accurate solution.
2.3 Performing Calculations
Once the mesh has been generated, the finite element model is complete and calculation
stages begin to be defined. The first calculation phase will be automatically created as initial
phase and all structural elements and loads presented in the geometry are automatically
switched off. After initial conditions are defined, the stages of excavation can be modelled as
shown.
Initial Phase
First row of ground anchors are installed into the diaphragm wall.
Second row of ground anchors are installed into the diaphragm wall.
4.5m depth of clay layer is excavated and the water table lowers down to the same level.
Third row of ground anchors are installed into the diaphragm wall.
4m depth of clay layer is excavated and the water table lowers down to the same level.
Fourth row of ground anchors are installed into the diaphragm wall.
2m depth of clay layer is excavated and the water table lowers down to the same level.
Fifth row of ground anchors are installed into the diaphragm wall.
2m depth of clay layer is excavated and the water table lowers down to the same level.
Sixth row of ground anchors are installed into the diaphragm wall.
Last 4m depth of clay layer is excavated and the water table lowers down to the same level.
Two types of finite-element calculations were used which are plastic calculation for elastic-
plastic deformation analysis and safety analysis. Elastic-plastic deformation analysis includes
the vertical and horizontal displacements of soil during excavation while safety analysis
includes the phi-c reduction to calculate safety factor (Mardia, 2014). After defining the
phases, calculation begins for each phase which takes several minutes to perform.
2.4 Output
Once the calculation is completed, the results are extracted to PLAXIS Output Program
where displacement and stresses are shown. The output generated for the excavation of the
proposed are shown in the following pages.
Figure 6: Safety factor, ΣMsf against displacement, lul of Section A-A’ Hardening Soil Model
Figure 8: Safety factor, ΣMsf against displacement, lul of Section B-B’ Hardening Soil Model
Figure 9: Safety factor, ΣMsf against displacement, lul of Section B-B’ Mohr Colomb Model
Figure 12: Axial Force Diagram of Section A-A’ Mohr Coulomb Model
Figure 14: Axial Force Diagram of Section A-A’ Hardening Soil Model
Figure 15: Axial Force Diagram of Section B-B’ Hardening Soil Model
Figure 17: Shear Force Diagram of Section B-B’ Mohr Coulomb Model
Figure 18: Shear Force Diagram of Section A-A’ Hardening Soil Model
Figure 20: Bending Moment Diagram of Section A-A’ Mohr Coulomb Model
Figure 21: Bending Moment Diagram of Section B-B’ Mohr Coulomb Model
Figure 23: Bending Moment Diagram of Section B-B’ Hardening Soil Model