Annex: SP Manweb Urban Network
Annex: SP Manweb Urban Network
Annex: SP Manweb Urban Network
2.10 Annex
SP Energy Networks 2015–2023 Business Plan
SP Energy Networks
June 2013
SP Manweb Urban Networks
Scope
This annex to the SP Energy Networks 2015-2023 Business Plan provides background information
specific to the SP Manweb licence area.
Here we outline the fundamental design differences between traditional electricity distribution
networks in the UK, and the Manweb urban network design. We discuss capital and operational
costs and compare and contrast performance. This annex also comments on previous operational
efficiency reviews, the implications of change and our current philosophy on continued operation of
the Manweb urban network design.
Comment is provided on the SP Manweb ED1 expenditure proposals in relation to the continued
stewardship of the urban network.
Introduction
SP Manweb provides electricity to 1.5 million customers across a diverse geographical foot print that
encompasses both large urbanised areas of Merseyside together with rural areas of Cheshire, North
& Mid Wales and Shropshire
Over 66% of our customers live in the major urbanised conurbations of Merseyside and the Wirral,
together with other large towns and cities across Cheshire, where the electricity network is primarily
constructed from underground cables. Our remaining customers across our semi urban and rural
networks are connected to our network which more generally comprises of a mix of overhead lines
and underground cables.
It is recognised that not all electricity networks are the same. At industry privatisation in 1989 our
shareholders inherited an electricity distribution network that is unique in the UK and overall
delivers the highest customer performance outside central London; it can be argued that the design
of the urbanised network delivers the best customer performance in Great Britain.
The SP Manweb urban network was designed and built throughout the 1950-1970s with a design
philosophy of high transformer utilisation to target lowest economic costs based on commodity
price forecasts at that time. Smaller transformers than industry standard are run constantly
interconnected at all voltages and standard cable sizes are used throughout.
To supply our customers over our geographical footprint around 55% of the SPM network is
designed and run as an “X-Type” network, solidly interconnected at 33kV, 11kV and LV. Of the
remaining, 23% of the network is designed as a “Y-type” network, solidly interconnected at 33kV and
11kV but less so at LV and 22% is designed as a radial network with single transformers feeding a
non-interconnected 11kV and LV.
This annex describes the electricity network that supplies the SP Manweb customers in the urban
areas (X Type Networks).
SP Manweb Urban Networks
The accepted industry wide design is based on duplicate radial transformer feeders, operated in
parallel as show below.
At 132 and 33kV, the transformers can be connected singularly or banked with multiple
transformers (at up to 3 substations) connected to the higher voltage or source circuit breaker.
132/33kV
60MVA
132/33kV
60MVA
33/11kV 33/11kV
33/11kV 12/24MVA 12/24MVA
12/24MVA
n.o.
33/ 11kV
12/ 24MVA
n.o.
CB type
RMU
33kV networks tend to radiate outwards from 132kV bulk supply points, similarly 11kv networks
tend to radiate outwards from primary substations. Historically companies will have tapered the
network cables, as the cable travels further form the supplying transformer, but more recently
uniform (standardised) cables have been employed.
11kV networks fed from primary substations can be constructed as radial ‘or looped’ circuits back to
the same substation, or can be built as an interconnector to an adjacent primary substation to
provide post fault support and resilience. In all cases the circuit must be run with a split or ‘normal
open point ‘at an electrically convenient point on the circuit.
The LV network whilst having the capability to offer interconnection will in all cases be run radially
with fuses or links removed at substations, LV surface mounted pillars or beneath ground link boxes.
The recognised benefits of this network philosophy are in its simple design, simple protection
arrangements, requiring less distributed switchgear and protection with consequential reduced
capital and operating costs.
Some of the pertinent limiting factors of this design are that of Fault Level management, transformer
utilisation factor is limited to 50%, triggering reinforcement and hence capital expenditure at earlier
point of overall load growth, and customer interruptions (CI’s) are increased over that of an
interconnected network design. It is recognised however that advances in network controllable
points and automation algorithms has improved the quality of supply performance on these
networks in recent years.
SP Manweb Urban Networks
Cables emanating from large substations are often non-uniform along their length, and are often
tapered as the distance from the substation increases. By nature these networks are not readily
extended without considerable effort and expenditure to develop a new substation, and laying more
cable to increase the circuit capacity, therefore they are not considered as “Smart ready” as
interconnected networks.
and expanded over the next 30 years and continues to be 33kV NETWORK
The design was developed by Peter d’E Stowell the former Manweb Chief Engineer, and whilst there
are elements of similar design in restricted parts of Edinburgh, and throughout the
Central London area, the SP Manweb urban network is considered unique in the UK.
The underlying principle of the Manweb urban network is to maximise the utilisation factor of high
voltage transformers supplying any given load group through the combination of 3 key features,
uniformity, interconnection and unit protection.
Uniformity
The uniformity of the Manweb network design takes two separate forms, uniformity of equipment
ratings and uniformity of application.
Although design and specifications of component parts of the Manweb network have evolved
throughout the last 50 years, the ratings of these component parts have remained extensively the
same.
At each voltage level therefore there is a standard rating for circuits, between each voltage level
there is a standard transformer rating, and at each voltage layer there is a standard design covering
switchgear, protection and relay settings.
This uniformity of equipment and ratings provides opportunity for expansion in line with network
growth and facilitates reinforcement by the addition of a new transformer with minimal cable laying
and no change to protection or settings. This was a key driver through the expansion period of the
electricity network in its early years and is equally pertinent today as it delivers a scalable solution to
meet the demands for the anticipated load growth on the distribution networks as we migrate to,
and accommodate Low Carbon technologies.
Interconnection
The benefits of uniformity can be applied to any
Existing Substations
network configuration however when a uniform
network is configured to operate in an
interconnected manner then the benefits can be
multiplied. Interconnection in this context means
New Substation
the circuits of each voltage layer run from one
added or
plugged into the infeeding substation to another substation and are
network
In an ideal network, utilisation factors of up to 85% are possible. However in order to operate the
equipment on the Manweb Network safely within its design fault level parameters then it is normal
to operate via interconnected cables up to 4* 60MVA Grid Transformers, or 5 * 7.5MVA primary
transformers. This still achieves utilisation factors of 75% and 80% respectively but maintains fault
level within the design criteria of 750MVA and 250MVA. It is equally permissible to interconnect
SP Manweb Urban Networks
secondary substations via the LV network, with the limiting factor that no lv circuit can be controlled
by more than 3 fuses from separate substations. Beneath ground LV link boxes are used extensively
on the LV network to split up the LV interconnected network to achieve this requirement.
33/11kV
7.5/10MVA
33/11kV 33/11kV
7.5/10MVA 7.5/10MVA
With higher utilisation factors incremental load growth can be absorbed more efficiently before
reinforcement is triggered. When the group load reaches its maximum then a further transformer
can be simply added or ‘plugged in’ to the network or the transformer group can be reconfigured by
the movement of network split points.
Ring Main Units (RMU’s) were originally installed at the primary substations and secondary
substations along the interconnectors between infeeding substations. These RMU’s comprise of 2
ring switches and a circuit breaker or fused switch in a single unit of switchgear.
In the Urban network design the RMU is configured as an ‘X-type’ and is illustrated above, with one
ring switch connected to local transformer, the other ring switch and the circuit breaker being
connected to the incoming and outgoing cables along the interconnector. At 33kV suitable RMU’s
are no longer manufactured therefore the design and application has evolved to comprise of a 3
panel switchboard again illustrated above.
Unit Protection
Unit protection in its simplest form utilises the Merz Price principle, which effectively checks that
load current entering a protected zone is equal to the load current leaving the protected zone. As
long as this is the case then the protection remains in balance and does not operate. Should a fault
develop in the protected zone then the current entering the protected zone will be the sum of the
load current plus the fault current, the current leaving the protected zone will be the load current
only, therefore the protection becomes out of balance and will operate a protection relay, which in
turn will operate the controlling circuit breakers for the protected zone, and the circuit will be safely
disconnected from service.
Unit protection as applied to the SP Manweb network interconnected distribution network, whilst
generally based on the basic principle above is more sophisticated and has been developed to
protect substation, transformers and its feeding cables. A simplified representation of unit or ‘zone’
of protection as applied to the SP Manweb Urban network is illustrated in the figures below.
SP Manweb Urban Networks
The summated output of the pair of CT’s at RMU A and the output of the CT’s at remote RMU B are
connected via communication cables commonly referred to as ‘Pilot Wires’ run alongside the main
distribution cable between substations - illustrated by the red section of the drawing above.
Under normal circumstances the load current entering the unit protected zone at RMU B will
balance with the load current of the local transformer at RMU-A together with the outgoing load
current along the remainder of the interconnector, and the protection relays connected to the pilot
wires will remain stable.
If a fault occurs within the unit protected zone on the distribution cable between the two RMU’s or
on locally connected transformer at RMU A, then the normal load current entering and leaving the
protected zone will be incremented by the fault current entering the protected Zones at RMU A and
RMU B, and will not balance. Therefore the protection relays connected to the pilot wires will
operate, and cause the controlling circuit breakers to operate and remove the faulted zone. The
protection relays connected into Pilot Wires are powered by DC battery systems.
Unit protected
zones
Unit protected
zones showing
SP Manweb
Symbols
SP Manweb Urban Networks
By overlapping unit protected zones along the interconnector, a fault or outage in any given unit
protected zone can be occur without disconnecting customers, as these supplies will be maintained
by the adjacent network via the interconnecting cables from neighbouring substations. In the more
traditional ‘Y’ type networks used elsewhere in SP Manweb on semi urban and rural networks and
the wider GB electricity network as a whole, a similar fault will result in loss of supplies to the entire
customer base connected to the interconnector, or radially operated circuit, with as a consequence
a poorer customer performance.
Performance
It has already been stated that the Customer Performance of the SP Manweb network as a whole is
second only to that of Central London. (UKPN LPN), with customers in SP Manweb likely to see a
power interruption once in every 2 years, lasting typically 63 minutes, and customers in Central
London once in every 3 years lasting a similar duration. It is also true that with an average of 53
customers interrupted per fault on SP Manweb network; this is the lowest number of customers
impacted by a fault (and therefore the best performance) on any electricity network in Great Britain
(Data taken from Ofgem - Electricity Distribution Annual Report for 2010-11)
2010/11 - CUSTOMER
2010/11 - CUSTOMER
INTERRUPTIONS PER 100
MINUTES LOST
CUSTOMERS:
The statistics above relate to total network performance for individual Distribution Network
Operators.
SP Manweb Urban Networks
Looking at the SP Manweb values in more detail it is clear that they are a combination of both our
urban and rural networks performance, which due to the prominence of the west coast weather
systems is exposed to extremes in weather conditions and consequently a greater fault rate than
that experienced by the relatively benign urban networks.
As described above the design of the SP Manweb urban network is such that for any 33 kV or HV
network fault the CI’s should be zero, as the faulted circuit is protected by unit protection and
customer supplies are maintained by the wider interconnected network. In reality there are
interruptions to customer’s supplies on these networks due to a combination factors, such as:-
• Second circuit faults occurring simultaneously with the first circuit fault leaving sections of
network stranded or islanded.
• Failures of unit protection systems to operate correctly due to faulty relays or
faulty/damaged pilot cables.
• Failures of circuit breakers to operate correctly
• ‘Designed in’ customer losses such as radially fed HV customers or IDNO’s, or elements of
radial networks embedded within the urban network
• Failures on the fringe of the urban areas where the overall circuit can be configured using a
mixture of Urban X-type and Semi Rural Y-Type network
• More recently developments in organised 3rd party interference/intervention – Metal theft
For faults on LV interconnected networks then for the majority of fault conditions only a small
percentage of the customers connected to the LV cable circuit will be interrupted as fuses at one
end of the circuit only will trip to remove the fault, with supplies to the remaining customers
connected to the LV circuit maintained from the remote ends of the 2 way or 3 way interconnected
circuit.
The Central London electricity system of LPN consists entirely of underground urban networks, and
is operated in an interconnected mode, therefore it is appropriate to compare the SPM urban
network directly with the performance of LPN as a whole, in order to demonstrate the performance
advantage of the SP Manweb urban network design.
By extracting the customer performance for the SP Manweb urban networks for the same reporting
year as shown above (2010/11), the CI per 100 customers is 13.22 and the CML per 100 customers is
performance is 22.0 minutes, this equates to customers connected to the SP Manweb urban
networks likely to see a power interruption once in every 8 years, some 2.5 times better
performance than that of LPN network, with the interruptions affecting less customers per fault and
lasting on average for shorter periods.
This SP Manweb urban network has demonstrated consistently over time its frontier network
performance in terms of CI and CML
industry that this network has greater complexity, involves more components and is more expensive
to construct and maintain than the recognised industry network design, (Y Type).
This is something that SP Energy Networks is continually aware of and has reviewed and evaluated
on a number of occasions both internally and externally by engaging independent consultants, in
order that we can consider if it remains viable to continue to propagate the SP Manweb urban
networks ‘X type’, and to consider alternative network designs and solutions.
External : -
Internal :
The engineering aspects of these reviews remain unchanged over time and common threads of
these reviews can be summarised as follows:
• Urban LV interconnected networks should if designed and operated correctly provide better
performance than traditional radial networks but are expensive as they are generally longer
networks
• Urban 11kV interconnected network design delivers frontier customer performance, but at a
cost premium over traditional radial networks with or without automation. However it’s not cost
effective/or desirable to convert wholesale to ‘Y-type’ networks
• It is considered that urban 33kV interconnected network provides little or no customer
performance benefit and is significantly more expensive than traditional dual radial transformers
operated in parallel configurations, due to additional switchgear requirements. (Author
Comment - whilst the benefits of a development of a dual radial transformer solution may be
true for green field developments, the various reports have failed to recommend substantial
proposals of how we would complete a migration from the existing interconnected network. Both
in terms of the additional network reinforcement, or the more onerous task of acquiring suitable
‘larger’ sites for the development of additional urban substations. Analysis of SP Manweb 33KV
customer performance indicates major contributors to CI/CML are from faults affecting rural
radial primary transformers or radial urban transformers. Occasional malfunctioning equipment
on the SP Manweb urban network does incur customer interruptions; however this is the
exception rather than the rule.)
• The SP Manweb urban 33kV and 11kV cable networks utilise standardised and uniform cable
sizes. Migration to industry designs would in many locations leave stranded assets as the cable
sizes and rating would be inadequate.
SP Manweb Urban Networks
• The SP Manweb urban networks utilisation factor is very much higher than for traditional
networks, implying that our network is working harder in our SP Manweb area, leaving less
spare capacity than on traditional networks. (Author comment - through the introduction of the
UK network Load Measure, we will reduce our trigger point for reinforcement by 20%. We will
also continue our programme to uprate our high voltage network from 6.6kV to 11Kv, releasing
latent capacity in our HV cable networks throughout ED1).
• The SP Manweb urban network represents the most cost effective network, both in cost per kVA
of capacity and maximum demand. However, the incremental cost of SP Manweb’s urban
network arrangement is approximately 30% more expensive in terms of total cost per unit of
network capacity.
• No reports deal adequately with the consequential reinforcement of Bulk Supply points as a
consequence of breaking up 33kV network, and reducing the currently high utilisation factor of
Grid transformers at Bulk Supply Points.
In summary the advantage of the SP Urban Network is confirmed as offering frontier CI performance
over that of traditional radial networks. The network design is also inherently “smart” as the
network is designed to accept power flowing in either direction, and alternative paths are available
when there is a fault. The network is more ready to facilitate customer uptake of low carbon
technologies and the associated costs are lower as reinforcement is facilitated in the main by ‘plug
in’ substations and minimal cable lying.
The disadvantage of the SPM Urban Network design is that it is more expensive to build, as it
requires more switchgear and unit protection which in turn requires a means of reliable
communication network between substation sites and a more robust building construction.
The design reviews have confirmed that the size and complexity of the existing network does not
allow wholesale change to the network design in urban areas, without a major impact on the
performance of the network to existing customers and significant capital spend.
Whilst savings could be made by developing less complicated ‘Y-Type’ networks these savings would
be offset by additional capital expenditure and future operating costs required to supplement the
existing transformer capacity within the network as a whole, as current high utilisation factors on
which the network was fundamentally designed over the last 60 years or so would be brought down
to the industry norm of 50%
Internal estimates based on the last five years of data supplied to Ofgem through the quality of
supply reporting scheme indicate that for the 11kV network alone should it be converted to ‘Y-Type’
network, the result would see an additional 104,000 or 7% of our customers experience a power cut
each year.
We believe that this would be unacceptable to our customers who, through stakeholder
engagement across the Manweb licence area (including an event held in Liverpool) have told us they
want to experience less power cuts.
We therefore have no feasible alternative when replacing existing assets in interconnected areas
other than to replace like for like, and to maintain the existing network arrangements.
SP Manweb Urban Networks
However we recognise that it is more cost effective to build new networks using a more traditional
design, and therefore when SPEN, or an Independent Connection provider (ICP) are designing new
networks or connections on our network , we will build a non-interconnected design where possible,
provided this will not impact or compromise on existing customer performance.
Specific details are contained in the relevant CV tables, however key activities and threads are
itemised below :-
A summary of our key costs and investments for the ED1 period can be found in our 2015-2023
Business Plan – Expenditure Chapter.