Kind ATTN: Mr. .... : Indoors Yes Outdoors Yes Train No Train
Kind ATTN: Mr. .... : Indoors Yes Outdoors Yes Train No Train
Kind ATTN: Mr. .... : Indoors Yes Outdoors Yes Train No Train
At Station(s) / Train(s)
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………
Whether above proposed work will interface with existing S&TC equipment in operation: Yes/No
If yes, specify the list of S&TC equipment to remain suspended during the period of Work.
Note: (1) Functional tests are to be carried out by NMRC/DMRC before clearing the work permit.
(2) Work will be carried out in presence of authorized representative of Contractor.
Sign here
Forwarded:
Part II RECEIPT
(1) Track / Train Possession Required From / (for Train Set No.) ……………………… To ……………..
(2) Permit To Work Required: S&TC equipment as mentioned in Part I would remain suspended during the
period as mentioned above. Their suspension as above may be confirmed.
(3) Mr. ………………………………………Of NMRC/DMRC will be Engineer’s Possession in Charge (EPIC).
I hereby declare that work as mentioned above shall be carried out with the conditions of WORK PERMIT and the
requirements of safety rules of NMRC/DMRC.
Track is free from obstruction and available from train running. S&TC equipment as mentioned in Part I, suspended
during the period as mentioned above for carrying out modifications and alterations, are hereby reconnected.
Traction Power Shutdown taken as above is also withdrawn. Please Confirm.