Standard Commissioning Procedure For Evaporative Cooling Systems
Standard Commissioning Procedure For Evaporative Cooling Systems
Standard Commissioning Procedure For Evaporative Cooling Systems
General Notes:
1. This is a generic test procedure for evaporative cooling systems. If the complexity, configuration, or other
aspects of a specific project require substitute tests or additional tests, explain on the comments sheets, and
attach the additional test procedures and field data. Attach all relevant functional performance verification
sheets, and always attach the final signed and dated procedure certification page.
2. In all test sections, circle or otherwise highlight any responses that indicate deficiencies (i.e. responses that don’t
meet the criteria for acceptance). Acceptance requires correction and retest of all deficiencies, as defined in
each test section under “Criteria for Acceptance” or “Acceptance”. Attach all retest data sheets. Complete the
Deficiency Report Form for all deficiencies.
3. This Commissioning Procedure does not address fire and life safety or basic equipment safety controls.
4. To ensure that this Commissioning Procedure will not damage any equipment or affect any equipment
warranties, have the equipment manufacturer’s representative review all test procedures prior to execution.
INSTALLED CHARACTERISTICS:
Enter answers from field inspection. Note under response if the feature as installed differs in any way from the
design documents. If an item does not apply, write “NA” for not applicable.
Criteria for Acceptance: Installed characteristics must be in accordance with design intent documentation and
approved submittals.
DESCRIPTION RESPONSE
(add sheets as necessary to adequately describe)
1. Type of system (direct, indirect, indirect/direct, other . If
other, describe.)
SYSTEM COMPONENT NAMEPLATE DATA (From equipment nameplates, as recorded in field. Attach other
sheets as necessary. If the system is built-up of component equipment, enter the individual components in the
blank spaces.):
Criteria for Acceptance: Nameplate data must be in accordance with submittals as approved by Designer.
EQUIPMENT TYPE UNIT # MANUFACTURER MODEL # CFM/TOT.TONS COMMENTS
1. Packaged evaporative cooler /
BUILT-UP SYSTEMS:
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
COMMENTS ON INSTALLED CHARACTERISTICS & NAMEPLATE DATA ITEMS (item #, unit #, comment). Add
more sheets as needed:
INSTALLATION VERIFICATION:
Instructions: Under each unit write "Y" for yes, "N" for no, "NA" for not applicable, or a number to refer to any
needed comments. If other information is requested such as temperature, write the appropriate values. For fan
data, enter values for both supply and exhaust fans. Use additional sheets for additional fans.
Current and voltage imbalance is defined as the greatest difference between the measurement for any of the 3
phases and the average of the 3 phases, that quantity divided by the average of the 3 phases. As an example, if
the voltage measurements are 451, 461, and 463, then the average is 458.3 volts. The greatest difference between
any measurement and the average is 451-458.3, or 7.3 volts. Then, the voltage imbalance is 7.3 volts / 458.3 volts,
or 0.016. As a percentage, this is 1.6%, and would be acceptable by the criteria below.
Criteria for Acceptance: All items in this section require answers of “Y” (or “NA”, where relevant) except where
other criteria are noted.
INSPECTION ITEM UNIT # UNIT # UNIT #
1. Relevant sections of test & balance report reviewed?
22. Fan motor full speed Amps, measured at motor Supply: / / Supply: / / Supply: / /
(downstream of VFD) Exhaust: / / Exhaust: / / Exhaust: / /
23. Fan motor measured Amps < Rated FLA? / / /
24. Current imbalance at motor is < 2%? / / /
does not correspond to the intended design operation, also write a comment number that refers to an explanatory
comment in the comments section or on attached comments sheets. If a test does not apply, write "NA" for not
Controls calibration tests: Perform the following calibration verifications by slowly adjusting the setpoint of each
thermostat, humidistat, etc. until the controlled response begins. Note the setpoint when that occurs, and note the reading
on a calibrated thermometer (or other instrument as required) held in close proximity. If the units are controlled by a
building energy management system (EMS), compare the sensor input to the EMS to the simultaneous field measurement
made on a calibrated thermometer (or other instrument as required) held in close proximity. Use the blank lines for other
sensors and stats such as exhaust or return air thermostats, 2nd stage temperature differentials, etc.
If a single system serves multiple zones, select a sample of at least 10% of the zones, or 4 zones, whichever is greater, for
calibration checks of the room temperature and humidity sensors (or stats). If there is failure to meet acceptance criteria for
more than 10% of the sampled room sensors or stats, or 2, whichever is greater, then all such sensors and stats serving
that system shall be considered to be not in conformance.
Criteria for Acceptance: If sensor or stat is out of calibration by more than ± 3 degrees F or 5% relative humidity, note
that as a deficiency.
UNIT #
1. Outdoor air sensor or thermostat, computer input signal or setpoint
when control action occurs (°F). This is applicable only if the cooler is
equipped with an economizer or if OSAT is otherwise referenced in the
evaporative cooling control sequence.
9.
10.
11.
12.
13.
14.
Basic performance tests: With the system in the full outdoor air mode (i.e. no mixing of return air), and with mechanical
cooling locked out, record the following. The design line in each test set refers to the design condition as reflected in catalog
data, drawings, design intent document, etc. The measured line refers to your test results.
Test Conditions: The outdoor air temperature should be greater than 55°F during the testing period. The zones served
should be under a significant cooling load.
Criteria for Acceptance: Calculated efficiency (items #5 and 11) must be within ±15% of nominal efficiency.
Symbols: PEDB = primary air entering dry bulb temp.; PEWB = primary air entering wet bulb temp.; PLDB = primary air
leaving dry bulb temp.; PLWB = primary air leaving wet bulb temp; SEDB = secondary air entering dry bulb temp.; SEWB =
secondary air entering wet bulb temperature; DEDB = direct section entering dry bulb temp.; DEWB = direct section entering
wet bulb temp.; DLDB = direct section leaving dry bulb temp.; DLWB = direct section leaving wet bulb temp. Note that if
outdoor air is used for the secondary air stream, SEDB = PEDB, and SEWB = PEWB.
UNIT #
INDIRECT SECTION
6.
7.
DIRECT SECTION
12.
13.
Start/Stop Control (include interlocks, time-of-day control, outside temperature lockout, etc.):
Describe the control sequence:
Describe the tests that were done to verify the control sequence:
Conclusions:
Capacity Control (e.g. air bypass around evaporative section, valving off spray to media sections, mixing cooled
outside air with return air, staging of mechanical cooling, etc.):
Describe the control sequence:
Describe the tests that were done to verify the control sequence:
Describe the tests that were done to verify the control sequence:
Conclusions:
Other Control:
Describe the control sequence:
Describe the tests that were done to verify the control sequence:
Conclusions:
I certify that the data and test results as recorded herein are accurate.
Start/Stop Control (include interlocks, time-of-day control, outside temperature lockout, etc.):
Describe the control sequence:
Evaporative cooling packaged unit is enabled by a time-of-day signal from the building EMS. During
unoccupied mode, the outside air (OSA) damper is closed, the return air (RA) damper is open, both direct
and indirect section pumps are off, and the indirect secondary air fan is off. The supply fan may cycle on
by night low limit. For OSA temperature lockout, see “Capacity Control” below.
Describe the tests that were done to verify the control sequence:
We observed the units (dampers, fans, pumps) during the occupied and unoccupied modes. We also
adjusted the night low limit setpoint so we could observe what happens when the space temperature falls
below the low limit.
Conclusions:
When we raised the night low limit setpoint, we observed the supply fan to start, while no change occurred
to damper or pump status. The OSA damper was closed during the unoccupied mode and opened at the
start of occupancy. (RA damper did the reverse.) The secondary fan and all spray pumps were off during
the unoccupied mode. Field notes are attached.
Capacity Control (e.g. air bypass around evaporative section, valving off spray to media sections, mixing cooled
outside air with return air, staging of mechanical cooling, etc.):
Describe the control sequence:
Capacity control is by means of a mixed air section with dampers, and by staging the indirect and direct
sections. When there is no call for cooling, the return air (RA) damper is full open and the OSA damper is
closed. On a call for 1st stage cooling, the OSA damper is modulated open, subject to low limit thermostat
in the discharge duct. When the OSA temperature is above setpoint (60°F, adjustable), the indirect unit fan
and pump are started. On a call for 2nd stage cooling, the direct section pump is started. On a call
for 3rd stage cooling, the valve to the chilled water coil is modulated open.
Describe the tests that were done to verify the control sequence:
We very slowly lowered the space thermostat cooling setpoint to simulate an increasing cooling load, while
recording entering and leaving dry bulb temperatures for the direct and indirect sections, and the chilled
water coil. We also tested air-side economizer operation by varying the OSAT lockout setpoint between
60°F and 70°F, and observing secondary fan and pump operation. (The OSAT during testing was about 65°F.)
Conclusions:
When the OSAT was below the OSAT lockout setpoint, and there was a call for 1st or 2nd stage cooling, the
secondary fan and all pumps were off. When we set the OSAT setpoint back to 60°F, and simulated a call for
1st stage cooling, the secondary air fan and indirect section pump started. When we increased the load to
call for 2nd stage cooling, the direct section pump started. When we lowered the space cooling setpoint 6
degrees below actual space temperature, the chilled water valve modulated open. Field notes are attached.