Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Arbitration & Conciliation Amendment Act, 2015

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 10

SYMBIOSIS INTERNATIONAL UNIVERSITY

ARTICLE SUBMITTED AS A PART OF 4TH INTERNAL ASSESSMENT


FOR ALTERNATE DISPUTE RESOLUTION ON THE TOPIC ENTITLED

“AMENDMENT OF ARBITRATION AND CONCILIATION ACT IN 2015


AND ITS EFFECTS ”

SUBMITTED BY:
KRITIK AGRAWAL
PRN:- 15010324214
SEMESTER- IX

SUBMITTED ON:
7TH SEPTEMBER, 2019

UNDER THE GUIDANCE OF:


ASST. PROF. SANU RANI PAUL
SYMBIOSIS LAW SCHOOL, HYDERABAD
INTRODUCTION

Arbitration is a form of an alternate dispute resolution mechanism wherein disputes are


settled privately, by mutual agreement of parties instead of going to court or without
any judicial interference. International commercial arbitration has been the most sought
after and chosen method by transitional parties to settle business disputes as it offers
the benefit of not going through the hassles of court procedure. The main objective of
Arbitration and Conciliation Act, 1996 was to make the country’s dispute resolution
mechanism in conformity with that of international standards.

The principal act was hence brought in as a means to adhere to the UNICITRAL Model
Law on International Commercial Arbitration, 1985 and the UNICITRAL Arbitration
Rules, 1976. Clearly, the intention of the legislature was to establish an investor friendly
regime which would ensure settling of commercial disputes expeditiously and instill
confidence in foreign investors. As noted by the Law Commission in its report, although
the Principal Act had been in place for two decades and arbitration had emerged as a
frequently chosen alternative to litigation, it had become afflicted with various problems
including those of high costs and delays.

The law of arbitration in India has been evolving to complement the needs of India’s
globalizing economy. India’s intent to elevate arbitration as the preferred mode of
dispute resolution, for both international and domestic businesses operating in India,
has been well documented in the recent past. Over the past few years, there have been
catena of pro arbitration judgments passed by the various High Courts and the
Supreme Court of India, as well as legislative amendments to the Arbitration and
Conciliation Act, 1996 through the Arbitration and Conciliation (Amendment) Act, 2015.

The Amendment Act eventually received the President’s assent on December 31, 2015,
and the Amended Act retrospectively came into effect from October 31, 2015. After two
abandoned attempts to amend the law of arbitration in India – in 2001 and in 2002, the
Amended Act has been a remarkable step towards remedying the blemishes to the law
of arbitration in India. Previously, a brewing cause of concern for litigants was the surge
in court intervention in arbitration proceedings in India, particularly ad hoc arbitrations.

Over the last two years, the courts have made a conscious effort to follow the policy of
minimal intervention, portraying India as both an arbitration friendly jurisdiction and a
viable seat for arbitration proceedings. In its effort to increase the ease of conducting
arbitrations in India for foreign parties and to re-affirm India as a friendly jurisdiction
for parties seeking speedy resolution of disputes, the Amendment Act has expanded the
territorial applicability of the Act and done away with the role of lower judicial courts in
matters of international commercial arbitrations.
CHANGES UNDER SECTION 8

Section 8 of the Act provided that a judicial authority must compulsorily refer the
parties to arbitration in a matter which is the subject of an arbitration agreement, if the
party seeking reference makes an application “not later than when submitting his first
statement on the substance of the dispute.” However, the Act was not clear on the
scope of analysis required by the courts in deciding whether a valid arbitration
agreement existed between the parties. Under the 1996 Act regime, the judicial
authority before which an application under section 8 was preferred was mandated to
refer the parties to arbitration. The only requirement was to see whether there existed
an arbitration agreement. However, the Supreme Court’s decision in SBP & Co. v. Patel
Engg. Ltd.1, where it propounded that the courts were to decide certain jurisdictional
issues before appointing an tribunal in an application under section 11, extended this
requirement even to section 8. This paved the way for judicial intervention even in pre-
arbitration stage.

The amendment has approached a confined role of judiciary under section 8 by way of
substitution of sub- section (1). It now states that a judicial authority can refer any of
the contesting parties or any person claiming through or under him to arbitration
notwithstanding any judgment, decree or order of the Supreme Court or any Court,
unless it finds that prima facie no valid arbitration agreement exists. The crucial
changes contained herein are:

‘Prima facie’ review -


Firstly, the role of the judicial authority has been confined to a prima facie review of the
existence and validity of the arbitration agreement. The intention behind this seems to
have been to restrict any intervention on jurisdictional issues, as noted by the Supreme
Court in Sundaram Finance Ltd. v. T Thankam2. The non-obstante clause thereafter has

1 SBP & Co. v. Patel Engineering Ltd., (2005) 8 SCC 618


2 Sundaram Finance Ltd. v. T Thankam, (2015) 2 SCC 66
been added to override the effect of any past or pending cases affecting such
applications. This also means that the question of arbitrability of the matter has largely
been left to be decided by the arbitral tribunal, unless the parties contest the validity of
the agreement before the Court, or the Court finds fraud or such other elements that
vitiate the arbitration agreement.

‘Copy of the arbitration agreement’


The second major change in section 8 is with regard to production of the Arbitration
Agreement between the parties. It was previously contemplated that an application
under section 8, i.e., to refer the parties to arbitration was to be accompanied by the
original arbitration agreement or a duly certified copy thereof, failing which, such
application was liable to be rejected. In government contracts, or contracts between the
state/state agency/instrumentality where the State is employer and a private party
(being a concessionaires, contractor etc.) there is a general trend that the State doesn’t
provide a copy of the original agreement or a certified copy of the agreement. What is
provided is a photo-copy of the agreement. This proved to be a big hurdle where a
section 8 application was preferred by the private party.

However, a proviso has been now added to sub-section (2) of Section 8, which provides
that where the original arbitration agreement or a certified copy thereof is not available
with the party applying for reference to arbitration under sub-section (1), and the said
agreement or certified copy is retained by the other party to that agreement, then, the
party so applying shall file such application along with a copy of the arbitration
agreement and a petition praying the Court to call upon the other party to produce the
original arbitration agreement or its duly certified copy before that Court . Therefore,
now an application under section 8 will not be defeated on the mere technicality of non-
production of original agreement/certified copies.
CHANGES UNDER SECTION 9

Another important amendment is to section 9 of the Principal Act, where two new sub-
sections, viz. section 9(2) and 9(3) have been added with the objective of reducing the
role of Courts and empowering the arbitral tribunals.

‘Invoking arbitration within 90 days’


Section 9(2) prescribes that arbitration has to commence within a period of 90 days
from the date of passing of any interim order/ measure of protection under section
9(1). A lot of parties invoke arbitration by serving a notice to the other party merely in
order to approach a Court for interim protection under section 9, so as to portray their
‘manifest intention’ to arbitrate. Once such protection is granted, they are reluctant in
commencement of arbitration and enjoy the fruits of an interim order in an unfettered
manner. A large number of petitions are pending on account of this in various courts in
India, and it is about time this is changed.

Section 9(2) intends to change that in as much as it mandates a time frame for the
parties to commence arbitration post passing of an interim order. An extension to this
time period may be granted by the Court at its discretion upon examining the facts and
circumstance of a case, hence, the parties will remain under compulsion to commence
arbitration expeditiously. However, the amendment does not provide for an automatic
vacation of an interim protection if the parties fail to commence arbitration within 90
days.

‘Empowering the arbitral tribunal’


Another important aspect of this amendment is to reduce intervention by Courts where
the arbitral tribunal is empowered to grant interim relief. Following the Amendment, it is
now a general rule that the Courts are not to interfere in on-going arbitration
proceedings, or where the arbitral tribunal has been appointed, if a party tries to
circumvent the same by applying for interim relief under section 9(1). However, an
exception has been provided to this bar in cases where it appears to the Court that
resort to section 17 is likely to render the party remediless. The intention of the
legislature here is to have a check-and-balances mechanism while ensuring that Courts
come in to picture only in extreme circumstances. The purpose of this amendment is to
ensure that parties eventually resolve their disputes through a proper adjudication on
merits by an arbitral tribunal without resorting to or adopting means which render an
arbitration clause redundant.

CHANGES UNDER SECTION 11

In cases where parties are unable to appoint an arbitral tribunal consensually, the
Principal Act provided for filing an application under section 11 for the appointment. For
domestic arbitrations, this power had been vested with the High Courts, ‘the Chief
Justice or a person designated by him’ to be precise, while for international commercial
arbitrations, the same had been vested with the Supreme Court through ‘the Chief
Justice of India, or any persona designated by him’. With the passage of time, the
power of appointment of an arbitral tribunal assumed more of a judicial role than a
supplemental one. This broadened the scope for pre-arbitration judicial intervention to
such levels that Courts began delving into questions of accord and satisfaction of
contractual obligations3, which was intended to be the domain of the arbitral tribunal by
the Act. This gave rise to the debate whether this power is a judicial one or an
administrative one and became the subject of judicial interpretations. The Supreme
Court in Konkan Railway Corporation Ltd. v. Rani Construction4 held that power to
appoint arbitrator is an administrative power. However in SBP & Co. v. Patel
Engineering the Court took a contrary view and held that the power to appoint an
arbitrator by the Chief Justice of India or his designate is a ‘judicial power’.

3
National Insurance Co. Ltd. v. Boghara Polyfab Pvt. Ltd., (2009) 1 SCC 267
4
Konkan Railway Corporation Ltd. v. Rani Construction, AIR 2000 SC 2821
Section 11 of the Amendment Act however strives to confine this role only to a prima
facie test of determination of the existence of the arbitration agreement. The
amendment substitutes the expressions ‘Chief Justice or any person or institution
designated by him’ in subsections (4), (5) and (6) with ‘the Supreme Court or, as the
case may be, the High Court or any person or institution designated by such Court’
respectively. It also substitutes ‘Chief Justice of India or the person or institution
designated by him’ with the words, ‘the Supreme Court or the person or institution
designated by that Court’ under sub-section (9).

The amendment further makes it clear by amending sub-section (7) that the decision
made by the Supreme Court, or as the case may be, the High Court or the person or
institution designated by such Court shall be final and not amenable to appeal including
a Letters Patent Appeal. However, a Special Leave Petition (SLP) has not specifically
been barred from the purview of this section.

Another important feature of this amendment is fixing of a time-line for appointment of


arbitrator by the Supreme Courts and High Courts. A bare perusal of the sub-section
suggests that the period of 60 days for appointment of an arbitrator by the Supreme
Court or High Court (as the case may be) is only guiding in nature and not mandatory,
even so, the presence of a recommendatory time line will have a bearing on petitions
filed henceforth under this section.
CONCLUSION

The Amendment Act is indeed a welcome change for the dispute resolution canvas in
India, a lot will however depend on its implementation. One of the primary objectives of
the Amendment was to reduce judicial intervention and remove superfluous procedural
requirements such that choosing arbitration becomes an efficacious form of dispute
resolution. To expedite the arbitral process and help the government to achieve its goal
of making India a seat of International Commercial Arbitration, the act will also help in
regaining the confidence of investors in Indian judicial and arbitral system. Along with
this some changes can also be made in regards to lowering the involvement of lower
judiciary and dedicating separate benches specially for arbitral matters in High Court as
done by Delhi High Court.

Judicial intervention in arbitral proceedings has been reduced at all stages of


arbitration, beginning from pre-reference to enforcement of the award. For some
stages, the role of the Courts has been confined by prescribing the limits whereas at
some stages by providing a time frame for disposing of the matter before them. The
empowerment of the arbitral tribunal by enabling them to enforce their orders in the
same manner as the Courts for the purpose of the proceedings before it, is another
such step in the right direction albeit a departure from the Model Law.
REFERENCES

Acts & Reports


1. Arbitration and Conciliation Act, 1996
2. Arbitration and Conciliation Amendment Act, 2015
3. 246th Law Commission Report.

Articles

1. Shubham Kaushal & Vijay Purohit, Arbitration and Conciliation


(Amendment) Act, 2015: Making India an Arbitration Friendly Seat, Rajiv
Gandhi National Law University of Law, 3 RSRR 3 (2016)
2. Ms. Zabeen Motorwala, Arbitration and Conciliation (Amendment) Act,
2015 – Key Changes And Circumstances Leading to the Amendments,
Bharati Law Review, April – June, 2016.

You might also like