Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

ITP - Civil Work

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5
At a glance
Powered by AI
The document outlines the various activities involved in a construction project from initial site work like piling and excavation to structural works and finishing works.

The main steps involve site preparation through piling, excavation and bracing, followed by structural works for the foundation, substructure and superstructure including works like concreting, formwork and reinforcement. Finishing activities include masonry, plastering, flooring, roof erection and other miscellaneous works.

Activities like concrete works, removal of formwork and electrical works need document reviews while concrete works and removal of formworks also need hold points.

Inspection & Test Plan

Activity Contractor Project


Manager
Construction of Pump House
Secant Pile Work
Guide Wall
Excavation H H
Screed H W
Setting Out H H
Reinforcement H W
Formwork H W
Concrete H W
Primary Pile
Boring H W
Concrete H W
Secondary Pile
Boring H W
Reinforcement H W
Concrete H W
Foundation Pile
Boring H H
Reinforcement H H
Concrete H DR
Pile Hacking H W
Capping Beam
Reinforcement H W
Formwork H W
Concrete H W
Excavation Work
1st Level Excavation H W
1st Level Bracing H W
2nd Level Excavation H W
2nd Level Bracing H W
Final Level Excavation H W
Final Level Bracing H W
Concrete Work- Substructure
Raft
Final Trimming H H
Screed H DR
Setting out H H
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Backfilling up to Raft top H H
Wall
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Water Tightness Test H H
Leakage Arresting H H
Backfilling H W
Intermediate Slab & Top Slab
Reinforcement H H
Formwork H H
Electrical Conduit Laying H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Pile Cap
Pile hacking up to cut off level H H
Screed H W
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Backfilling H W
Plinth Beam
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Backfilling H W
Concrete Work- Super Structure
Column
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Corbel
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Roof Beam
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Trenches / Chambers / Underground Tanks
Raft
Excavation H H
Screed H DR
Setting out H H
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Backfilling up to Raft top H W
Wall
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Water Tightness Test H H
Leakage Arresting H H
Backfilling H W
Top Slab
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Ancillary Buildings
Footing with Strap Beam
Excavation H H
Screed H DR
Setting out H H
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Backfilling up to Footing top H W
Ground Beam
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Backfilling H W
Plinth Beam
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Backfilling H W
Column
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Roof Beam & Slab
Reinforcement H H
Formwork H H
Electrical Conduit Laying H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Tie Rod removal H H
Closing tie rod hole H H
Pedestal or Foundation
Excavation H H
Screed H DR
Setting out H H
Reinforcement H H
Formwork H H
Concrete H DR
Removal of Formwork H W
Surface inspection H H
Rectification of identified defect H H
Backfilling H DR
Pipe Laying
Excavation H H
Bedding Preparation H W
Pipe Laying H H
Wrapping of Joints H H
300mm Backfilling H H
Warning Tape H W
Backfilling H DR
Finishing Work
Masonry Work
Block or Brick work H W
Plastering H W
Putty Application H H
Painting Work
Primer H W
1st Coat H W
Final Coat H DR & FI
Floor Finish
Surface Preparation H H
Concreting H DR & FI
Doors & Windows
Fabrication H H
Fixing of Door & Windows H DR & FI
Roof Erection
Fabrication of roof Truss H H
Sand Blasting H H
Painting H DR/FI
Drilling for Base plate at Column H H
Erection of Roof Truss H DR/FI
Erection of Purlin H DR/FI
Erection of PVC coated mesh H W
Erection of Thermal Insulation H W
Erection of Roof Sheet H DR/FI
Erection of Gutter H DR/FI
Erection of Gutter Pipe H DR/FI
Erection of Barge Board H DR/FI

H: Hold Point

DR: Document Review

FI: Final Inspection

You might also like