This document outlines the inspection and test plan for construction of a pump house and ancillary buildings. It lists each construction activity, such as excavation, concrete work, and inspections. For each activity, it identifies whether the contractor or project manager is responsible for holding (H) or witnessing (W) the inspection or test. The plan provides a detailed breakdown of responsibilities to ensure quality control throughout the construction process.
This document outlines the inspection and test plan for construction of a pump house and ancillary buildings. It lists each construction activity, such as excavation, concrete work, and inspections. For each activity, it identifies whether the contractor or project manager is responsible for holding (H) or witnessing (W) the inspection or test. The plan provides a detailed breakdown of responsibilities to ensure quality control throughout the construction process.
This document outlines the inspection and test plan for construction of a pump house and ancillary buildings. It lists each construction activity, such as excavation, concrete work, and inspections. For each activity, it identifies whether the contractor or project manager is responsible for holding (H) or witnessing (W) the inspection or test. The plan provides a detailed breakdown of responsibilities to ensure quality control throughout the construction process.
This document outlines the inspection and test plan for construction of a pump house and ancillary buildings. It lists each construction activity, such as excavation, concrete work, and inspections. For each activity, it identifies whether the contractor or project manager is responsible for holding (H) or witnessing (W) the inspection or test. The plan provides a detailed breakdown of responsibilities to ensure quality control throughout the construction process.
Download as DOCX, PDF, TXT or read online from Scribd
Download as docx, pdf, or txt
You are on page 1of 5
At a glance
Powered by AI
The document outlines the various activities involved in a construction project from initial site work like piling and excavation to structural works and finishing works.
The main steps involve site preparation through piling, excavation and bracing, followed by structural works for the foundation, substructure and superstructure including works like concreting, formwork and reinforcement. Finishing activities include masonry, plastering, flooring, roof erection and other miscellaneous works.
Activities like concrete works, removal of formwork and electrical works need document reviews while concrete works and removal of formworks also need hold points.
Inspection & Test Plan
Activity Contractor Project
Manager Construction of Pump House Secant Pile Work Guide Wall Excavation H H Screed H W Setting Out H H Reinforcement H W Formwork H W Concrete H W Primary Pile Boring H W Concrete H W Secondary Pile Boring H W Reinforcement H W Concrete H W Foundation Pile Boring H H Reinforcement H H Concrete H DR Pile Hacking H W Capping Beam Reinforcement H W Formwork H W Concrete H W Excavation Work 1st Level Excavation H W 1st Level Bracing H W 2nd Level Excavation H W 2nd Level Bracing H W Final Level Excavation H W Final Level Bracing H W Concrete Work- Substructure Raft Final Trimming H H Screed H DR Setting out H H Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Backfilling up to Raft top H H Wall Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Water Tightness Test H H Leakage Arresting H H Backfilling H W Intermediate Slab & Top Slab Reinforcement H H Formwork H H Electrical Conduit Laying H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Pile Cap Pile hacking up to cut off level H H Screed H W Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Backfilling H W Plinth Beam Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Backfilling H W Concrete Work- Super Structure Column Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Corbel Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Roof Beam Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Trenches / Chambers / Underground Tanks Raft Excavation H H Screed H DR Setting out H H Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Backfilling up to Raft top H W Wall Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Water Tightness Test H H Leakage Arresting H H Backfilling H W Top Slab Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Ancillary Buildings Footing with Strap Beam Excavation H H Screed H DR Setting out H H Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Backfilling up to Footing top H W Ground Beam Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Backfilling H W Plinth Beam Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Backfilling H W Column Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Roof Beam & Slab Reinforcement H H Formwork H H Electrical Conduit Laying H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Tie Rod removal H H Closing tie rod hole H H Pedestal or Foundation Excavation H H Screed H DR Setting out H H Reinforcement H H Formwork H H Concrete H DR Removal of Formwork H W Surface inspection H H Rectification of identified defect H H Backfilling H DR Pipe Laying Excavation H H Bedding Preparation H W Pipe Laying H H Wrapping of Joints H H 300mm Backfilling H H Warning Tape H W Backfilling H DR Finishing Work Masonry Work Block or Brick work H W Plastering H W Putty Application H H Painting Work Primer H W 1st Coat H W Final Coat H DR & FI Floor Finish Surface Preparation H H Concreting H DR & FI Doors & Windows Fabrication H H Fixing of Door & Windows H DR & FI Roof Erection Fabrication of roof Truss H H Sand Blasting H H Painting H DR/FI Drilling for Base plate at Column H H Erection of Roof Truss H DR/FI Erection of Purlin H DR/FI Erection of PVC coated mesh H W Erection of Thermal Insulation H W Erection of Roof Sheet H DR/FI Erection of Gutter H DR/FI Erection of Gutter Pipe H DR/FI Erection of Barge Board H DR/FI