Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

NCR - BAM - 008 - 001 (Reply For Response)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Greater Colombo Wastewater Management Project

ADB Loan No: 2557(OCR)/2558(SF)-SRI


SECTION III - FOLLOW UP VERIFICATION
1) The Proposed Action(s) mentioned in Section NCR RESPONSE NO. BAM/008/001
III of the NCR is in conjunction with the
contractual requirements and obligations Proposal Accepted: YES / NO
Follow-up Comments / Remarks:
Non-Compliance 1(Crack propagation on wall):
• If root cause of the crack propagation may be due thermal effect what will be your preventive
mechanism on it for future pumping station since it was observed in other pumping stations as
well.
• Proposed Corrective action is acceptable and Contractor executed as approved method at site.
However, it reappears. It would be better investigating further.
Non-Compliance 2 (Identification Board):
• Root Cause is not acceptable. Please identify the root cause for the following.
1. What makes printing agency to make such a mistake?
2. How was this neglected through Quality Control Assurance process prior to delivery to
site?
3. Did identification approve by Project Manager?
• Proposal is accepted However Contractor has to get an approval for identification from Project
Manager, however Corrective action taken at site is not acceptable.
Non-Compliance 3 (DG Enclosure):
• The Contractor shall make his own arrangements for the unloading of the Plant supplied to site
or to a temporary store and be responsible for any damage occasioned. as per clause 2.1.11
Unloading, Storage and Erection of Plant in section 6A-2
• Proposal is acceptable. Please specify the requirement clearly prior to proceed the work.
Non-Compliance 4 (Chequered Plate):
• Root Cause for extra opening is acceptable. Please identify the root cause for all defect
mentioned in the NCR.
• Eventhough proposed action is not clear. Contractor executed the work in acceptable manner
at site.
Non-Compliance 5 (Wall Paint):
• Root Cause is not acceptable. Please identify the root cause for the following.
1. What makes painter to make such a mistake?
2. How was this neglected by supervision team & Quality Control Team in final inspection?
• Proposal is not mentioned however corrective action taken at site is acceptable.
Non-Compliance 6 (Cleanliness):
• Root Cause is not acceptable. Please identify the root cause for the following.
1. How was this neglected by supervision team & Quality Control Team in final inspection?
• Proposal is acceptable.
Non-Compliance 7 (Door):
• Root Cause is not acceptable. Please identify the root cause for the following.
1. What makes UTE to make such a mistake?
2. How was this neglected by supervision team & Quality Control Team in final inspection?
• Proposal is to be clearly mentioned since there is no approved paint and dry film thickness for
DG Room Door as of now.

Further to above it was noticed that Contractor is not keen on identifying the actual root cause of the
non-compliance issued by PM’s Staff. Therefore, proposed preventive action is also not acceptable.
Proposal Reviewed by (For Project Manager):
Name AJS.SHAARIM Designation Assistant Resident Engineer

Signature Date 01/11/2020

Page Revision No. 02 | Date 2017/10/24


Greater Colombo Wastewater Management Project
ADB Loan No: 2557(OCR)/2558(SF)-SRI
2) Corrective and/or Preventive Actions mentioned
in Section III of the NCR are carried out Corrective Action Implemented: YES / NO
satisfactorily and in compliance with the Contract
Follow-up Comments / Remarks:

Corrective Action Supervised by (For Project Manager):


Name Designation

Signature Date

NCR closed by:


Name Eng. (Mrs.) G. A. C. R. Ganepola Designation Project Manager

Signature Date

Page Revision No. 02 | Date 2017/10/24


Greater Colombo Wastewater Management Project
ADB Loan No: 2557(OCR)/2558(SF)-SRI
The Contractor shall fill the Section II and submit the original with two (2) copies verified/signed as “True
Copy” to the Project Manager (PM) within seven (7) days from the date of acknowledgement of the NCR.
The proposal of Section II will be reviewed and the status will be responded via Sub-section No. 01 of
Section III within seven (7) Working Days of Time. The Contractor shall resubmit Section II with
consecutive numbering in the column “NCR RESPONSE NO” till the Acceptance is granted.

The Contractor shall carry out the Action Plan subjected to the Acceptance of the Proposal and the
implementation of the Action Plan shall be notified initially to the Resident Engineer. Sub-section No. 02
of Section III will be filled by a supervision team member of PM / RE accordingly. Any major deviation(s)
at the implementation of the proposed Action Plan shall be subjected to correspondence.

The NCR will be closed by the Project Manager in collaboration with the Reviews and Follow-up
Comments mentioned in Section III and any other Correspondence formulated thereof.

SECTION II – ACTION PLAN

NCR RESPONSE NO. BAM/008/002


1) Reason / Root Cause(s):

2) Proposed Corrective Action:

3) Preventive Action:

For Contractor’s Representative:


Name Designation

Signature Date

Page Revision No. 02 | Date 2017/10/24

You might also like