Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Project Engineer'S Report: Department of Public Works and Highways Regional Office No. Xii

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Republic of the Philippines

Department of Public Works and Highways


REGIONAL OFFICE NO. XII
Corner Alunan Avenue-Mabini St., Koronadal City

PROJECT ENGINEER’S REPORT


Project Name :Construction of River Bank Protection Along Ala-River, Sta.
1+104 – Sta.1+664
Location : Brgy. New Panay, Sto. Niño, South Cotabato

Original Contract Amount : Php 97,569,174.14

Revised Contract Amount : Php 100,643,137.47

Contractor : Abu Construction

Date Started : June 11, 2018

Original Contract Duration : 286 Calendar Days

Revised Contract Duration (If approved) : 376 Calendar Days

Original Completion Date : March 23, 2019

Revised Completion Date (If approved) : June 22, 2019

Time Extension No. 2 Recommended (If approved) : 15 Calendar Days

Previously Approved Time Extension No.1 : 45 Calendar Days

Previously Approved CTE Due to Variation/ Change Order : 30 Calendar Days

Physical Accomplishment (As of February 4, 2019) : 84.73%


Time Elapsed to Date, As of February 4, 2019 (If Approved) : 65.93%

The contractor’s request for Contract Time Extension No. 2 Due to Unfavorable Weather
Condition/ Unworkable Site Condition is recommended.

Prepared By:

ACOB P. MAROHOM
Engineer II/ Project Engineer I

Concurred by:

BASIR M. IBRAHIM
Regional Director

You might also like