ABSTRACT
With augmenting cognizance of environmental issues and growing concern over climate change,
sustainable construction is gradually put forth globally. However, construction of green buildings in
Singapore still encounters impediments as there is a lack of proper project management framework for
such projects. Based on the survey and interview results from 31 industry experts, this study aims to
identify common challenges encountered during management of green construction projects and their
impact on project performances, ultimately proposing some solutions to overcome the barriers.
Findings from this study are: (1) main dissimilarities between conventional and green construction
projects exist, especially in the level of details and communication required; (2) there is no paucity in
sustainable knowledge in the Singapore construction industry; however, challenges against
implementation of the knowledge exist, influencing project performances, and the lack of investment on
management of green building construction is the most paramount barrier; and finally (3) to overcome
the barriers, a project management framework for green building construction should be developed,
possibly promoting adoption of sustainable management approaches for future green building projects.
1. INTRODUCTION
In Singapore, buildings contribute 16% of the nation’s total energy consumption and the energy cost can
constitute about 20% to 40% of the total operating cost (IMCSD Committee, 2009). According to Perez-
Lombard et al., (2008), both commercial and residential buildings are responsible for 20% to 40% of the
world’s energy consumption. With the recent mounting global concern of the negative impacts of human
activities on the environment, almost all industries are steering towards sustainable development and
implementing green measures (Gunawansa and Kua, 2011; Kua, 2011). The building construction
industries from various countries have taken these ‘green measures’ in their strides, putting strong accent
on green building construction (Hwang and Tan, 2010). In line with this trend, Singapore has also shifted
its focus in making sustainable development a key national priority (Singapore Green Building Council,
2009; Lutchmeeduth et al., 2010).
According to the Building and Construction Authority of Singapore, since the launch of the Green Mark
Scheme in 2005, the number of green mark certified buildings in Singapore has increased to more than
750 from the mere 17 buildings in 2005 (BCA, 2011). To promote environmental sustainability in
buildings, the BCA had also formulated the 1st and 2nd Green Building Masterplan together with other
efforts to thrust forward in developing more green buildings in Singapore. By year 2030, through BCA’s
2nd Green Building Master Plan, the Inter-Ministerial Committee on Sustainable Development (IMCSD)
targets to have at least 80% of the buildings in Singapore to achieve the BCA Green Mark Certified rating
(BCA, 2009b).
Under this circumstances, the specific objectives of this study are: (1) To compare design, construction,
and commission stages between conventional and green building construction projects based on a
*
Corresponding Author: E-mail - bdghbg@nus.edu.sg
171
World Construction Conference 2012 – Global Challenges in Construction Industry
28 – 30 June 2012, Colombo, Sri Lanka
comprehensive literature review; (2) To investigate common challenges that project managers encounter
while managing green building construction projects; and lastly (3) To propose some plausible solutions
for improving the current green construction project management. The findings from this study will
contribute to more intensive and effective implementation of green building construction in Singapore.
2.1. DEFINITION
The construction of green building is part of sustainable construction. According to Kibert (2008),
sustainable construction addresses the ecological, social and economic issues of a building in the context
of its community. Sustainable construction is applied throughout the entire life cycle of construction, from
preconstruction to disposal of the building. Such construction aimed to reduce the impact of the
construction practice on the environment through its planning and managing of a construction project
complying with the contract document (Glavinich, 2008).
172
World Construction Conference 2012 – Global Challenges in Construction Industry
28 – 30 June 2012, Colombo, Sri Lanka
end users to maintain sustainability (CIRIA, 2001). In addition, ease of maintenance has to be ensured
(CIRIA, 2001).
3.4. LENGTHY APPROVAL PROCESS FOR NEW GREEN TECHNOLOGIES AND RECYCLED MATERIALS
The market environment suggests that the planning process can be protracted as the process of approving
the use of new green technologies and recycled materials can be lengthy (Tagaza and Wilson, 2004).
Similarly, surveys conducted by Zhang et al. (2011) and Eisenberg et al., (2002) show that additional time
is expected in order to gain approval. A lengthy approval process presents a challenge to project managers
as they must develop the schedule and approve progress payments to vendors and suppliers (Pettersen,
1999; Ling, 2003).
173
World Construction Conference 2012 – Global Challenges in Construction Industry
28 – 30 June 2012, Colombo, Sri Lanka
the project with the required performance specified by the client (Pettersen, 1999; Ling, 2003), and
unfamiliarity with the performance of green technologies may affect the performance outcome.
3.6. GREATER COMMUNICATION AND INTEREST REQUIRED AMONGST PROJECT TEAM MEMBERS
To be successful, the project manager must manage a large number of suppliers, subcontractors and team
members. Communication is especially critical for the green project in order to convey the sustainable
practices expected from the team members. Interest amongst team members is important, Tagaza and
Wilson (2004) found that the initial enthusiasm for separating waste materials amongst sub-contractors
dissipated as the projects progressed and the recycling skips were found to contain a mix of materials.
4. RESEARCH METHODOLOGY
To achieve the objectives of this study, a comprehensive literature review on green and sustainable
building construction was first carried out. The aim of the literature review was to find out what are the
essential differences between conventional and green construction projects in design, construction, and
commissioning phases and what are the challenges encountered in green building construction project
management. In addition, the objective behind the review was to explore some innovative management
skills applied in these projects that can be implemented in Singapore’s context. The examination and
analysis of past work related to green construction also provided a better understanding of green and
sustainable building construction and the project management processes involved.
Then, a survey questionnaire was developed to capture a specific set of challenges encountered in the
Singapore construction industry. The survey also captured a comprehensive and accurate outlook of
management culture adopted by local green construction industry. The survey questionnaire consisted of a
section that could capture the profile of respondents. The next section carried questions regarding the
profile of green building construction projects undertaken by the respondents. The third section asked the
respondents to rate challenges encountered during management of green construction, and the last section
required the respondents to pick out solutions to overcome those challenges. The questionnaires were sent
via email to 101 Green Mark Professionals (GMPs) and Green Mark Managers (GMMs) registered under
the BCA’s Green Certified GMP and GMM scheme.
174
World Construction Conference 2012 – Global Challenges in Construction Industry
28 – 30 June 2012, Colombo, Sri Lanka
Respondent
Challenges
(%)
100 Increase of Project Cost
83.9 Lack of Communication and Interest among Project Team Members
77.4 High Implementation Cost of Green Practices
67.7 Lack of Credible Research on Benefits of Green Buildings
51.6 Lack of Interest from Clients
The respondents reported that green construction projects would result in the increment of total project
costs as relatively new technologies and systems are required to fulfil expected performances of buildings
constructed. Also, consultants who are specialised in green technology need to be hired to assess and
validate systems to be used for green buildings. This increases not only project cost, but also complexity
of communication among project team members. The knowledge and critical information provided by
green consultants should be clearly delivered and communicated to project team members who may not be
familiar with specific knowledge areas required to construct green buildings. This may cause
miscommunication or disconnection of information flow.
Furthermore, with consideration of tight schedule of construction projects, project team members may not
take sufficient time to understand green requirements, negatively affecting their interests in green features.
Similarly, green practices may be costly to be implemented. When new technology and systems are
introduced, project team members need to be trained and until they exhibit a certain level of performance
on the newly adopted concept and practices, the investment in implementing green practices may not be
paid back. As a result, it is not surprising that a lack of expressed interest from clients becomes one of the
critical challenges in managing green construction projects. This challenge may be solved by promoting
various benefits and incentives from going green, but as indicated by the survey, the respondents felt a
lack of research on true benefits of green buildings, which discourage project owners to consider and
implement green measures to their projects.
175
World Construction Conference 2012 – Global Challenges in Construction Industry
28 – 30 June 2012, Colombo, Sri Lanka
Respondent
Solutions Challenges
(%)
Government to provide incentives to offset high premiums
67.7
of green building projects
48.4 Public and market demand for green buildings Increase of Project Cost
Subsidy from government for R&D in green building Lack of Credible Research on Benefits of
96.8
systems and management Green Buildings
Bonuses provided for staff if the building is green mark
87.1 Lack of Interest from Clients
certified or qualified for green mark awards
Both challenges involving “Increase of Project Cost” and “High Implementation Cost of Green Practices”
are cost related and considered to be the biggest challenges that a project management team has to
overcome. Considering that most projects performed in the Singapore construction industry are awarded
based on the lowest tender price, project cost related issues are very sensitive to all stakeholders in the
industry. Hence, a green building project will be pale in comparison to conventional building projects in
terms of cost. While there is BCA’s green mark incentive scheme which is capped at an exhaustive
amount of $20 million (BCA, 2009a), according to one of the survey respondents, the fund has been
running out very fast and with tighter budget, future projects may only aim to attain minimum green
requirements so as to comply with local regulations. To overcome the problem of high cost involved in
green building construction, all respondents felt that the government should provide a larger scale of
incentives. Also, about 65% of the respondents argued that educating clients on future benefits of going
green could be one of the workable solutions to the cost related challenges. With clients internalising the
potential benefits reaped from green buildings, high cost premium may have less deterrence from the
perspectives of clients. Furthermore, this will become a remedy for the identified challenge, “Lack of
Interest from Clients”.
Since green building construction is a fairly new concept in the Singapore construction industry, it is also
important to communicate the green goals and objectives to all stakeholders and project team members in
order to achieve successful project execution. For the lack of communication between project members as
a challenge in green building project management, 74.2% of the respondents agreed that regular tool box
meetings would work for ensuring that important information about the project is communicated. More
specifically, engaging green consultants was recommended by 45.2% of the respondents to overcome
communication problems among project team members.
176
World Construction Conference 2012 – Global Challenges in Construction Industry
28 – 30 June 2012, Colombo, Sri Lanka
The poor demand for green buildings could also be due to the lack of credible research on their benefits.
96.8% of the respondents felt that subsidy from government for research and development of green
building systems and management could essentially provide concrete evidence of how beneficial they are
to humans, society as well as the economy.
6.1. CONCLUSIONS
This study aimed: (1) To compare design, construction, and commission stages between conventional and
green building construction projects based on a comprehensive literature review; (2) To investigate
common challenges that project managers encounter while managing green building construction projects;
and lastly (3) To propose some plausible solutions for improving the current green construction project
management. The literature review carried out for this study revealed that the main dissimilarities between
conventional and green construction projects are the level of details and communication required. Succinct
schematic design is usually adequate at the planning stage of conventional projects while green projects
require superlative communication which can only be achieved through delivery systems like design-
build, where building design and construction is carried out as a single entity. Furthermore, detailed
integrated design process is employed at the start of the project as unlike conventional building design,
green design features are unique and requires deep integration with every building aspect.
Results from the survey revealed the top 5 challenges in managing green building construction projects
and there are: (1) Increase of Project Cost; (2) Lack of Communication and Interest among Project Team
Members; (3) High Implementation Cost of Green Practices; (4) Lack of Credible Research on Benefits of
Green Buildings; and (5) Lack of Interest from Clients. These challenges were found to be interrelated,
ultimately resulting in high cost premium of green buildings. The lack of R&D on benefits of green
buildings and green technologies is a main driver behind the lack of demand for green buildings to go
beyond legislative requirement. In addition, green building constructions requires collaborative effort and
communication between project team members. However, many local projects adopt conventional design-
bid-build form for management, causing the lack of communication. All of these factors make it more
difficult to manage green construction projects when compared to conventional projects, discouraging
owners to take up green building projects.
177
World Construction Conference 2012 – Global Challenges in Construction Industry
28 – 30 June 2012, Colombo, Sri Lanka
The next step of the planning stage is to set the desired level of environmental performance according to
Singapore’s environmental policies, which the clients or building owners wish to obtain. Therefore, the
project team should look into BCA Green Mark Assessment Criteria and Building Control Act (Chapter
29) Building Control (Environmental Sustainability) Regulation 2008 to determine how the building
should be built in order to comply with legislative requirement or to obtain certain level of awards.
The last step of the planning stage of a green construction project is to develop an organisational structure,
which determines the relationship between important personnel involved in the projects. Some examples
of these personnel are contractors, engineering consultants, environmental management team, client and
affected parties. In addition, modes of communication between each team member should be established
to facilitate great communication within the project team. The responsibilities and authorities of all
personnel should also be clearly listed and defined to prevent any finger-pointing and confusion during the
construction process.
During the construction of green buildings, environment management program based on Green Mark
requirements on sustainable construction should be adopted. These sustainable construction practices
includes efficient use of concrete for building elements, conservation of existing building structures and
use of sustainable materials and products (BCA, 2009a). Standard work procedures of various activities
should be communicated to all personnel involved in the project to have better control. Penalties and
incentives schemes can be implemented during construction stage and operation of green buildings to
ensure compliance with local environmental standards. The project should be monitored and documented
to enhance management of the whole construction process. Audits of environmental performance should
be carried out at fixed intervals internally by environmental managers or externally by consultants in
accordance to Building Control Regulation and Green Mark Assessment to ensure compliance.
Last but not least, professionals’ knowledge and experience on green building construction should be
enhanced and upgraded through regular upgrading courses to keep them updated with the evolving
information on technologies, products and materials relevant to green building construction.
7. REFERENCES
BCA (Building and Construction Authority). (2009a). BCA green mark assessment criteria. Retrieved from
http://bca.gov.sg/GreenMark/green_mark_criteria.html.
BCA (Building and Construction Authority). (2009b). Certified green mark manager / professional. Retrieved from
http://www.bca.gov.sg/GreenMark/gm_manager.html.
BCA (Building and Construction Authority). (2011). CDL elevated to BCA green mark platinum champion status.
Retrieved from http://www.bca.gov.sg/Newsroom/pr16052011_GMPC.html.
CIRIA. (2001). Sustainable construction procurement: A guide to delivering environmentally responsible projects.
London: CIRIA.
Eisenberg, D., Done, R., and Ishida, L. (2002). Breaking down the barriers: Challenges and solutions to code
approval of green building. Retrieved from http://www.mrsc.org/artdocmisc/breaking_down_barriers.pdf.
Glavinich, T.E.(2008). Contractor’s guide to green building construction. New Jersey: John Wiley & Sons.
Gunawansa, A., and Kua, H.W. (2011). A comparison of climate change mitigation and adaptation strategies for the
construction industries of three coastal territories. Sustainable Development. doi: 10.1002/sd.527.
Hill, R.C., and Bowen, P.A. (1997). Sustainable construction: principles and a framework for attainment.
Construction Management and Economics, 15, 223-239
Hwang, B.G., and Tan, J.S. (2010). Green building project management: obstacles and solutions for sustainable
development. Sustainable Development. doi: 10.1002/sd.492.
IMCSD (Inter-Ministerial Committee on Sustainable Development). (2009). Sustainable Singapore – A lively and
liveable city. Retrieved from http://app.mewr.gov.sg/web/contents/ContentsSSS.aspx?ContId=1034.
International Initiative for Sustainable Built Environment (iiSBE). (2005). The integrated design process. Retrieved
from http://www.iisbe.org/down/gbc2005/Other_presentations/IDP_overview.pdf.
Kibert, C.J.(2008). Sustainable construction: green building design and delivery. New Jersey: John Wiley & Sons.
178
World Construction Conference 2012 – Global Challenges in Construction Industry
28 – 30 June 2012, Colombo, Sri Lanka
Kua, H.W. (2011). Integrated sustainability policies for China’s cement industry – A case study approach, in
environmental change in asia: challenges and prospects. Singapore: Pearson.
Ling, J.U. (2003). The project manager’s personal characteristic, skills and roles in local construction industry (
Master’s dissertation). Faculty of Civil Engineering, University Technology Malaysia.
Lutchmeeduth, B., Kua, H.W., Gunawansa, A., and Piana, V. (2010). Approaches to climate change mitigation and
adaptation – the cases of Mauritius and Singapore. University of Mauritius Research Journal,17.
Perez-Lombard, L., Ortiz, J., and Pout, C. (2008). A review on buildings energy consumption information. Energy
and Buildings, 40, 394-398.
Pettersen, N. (1991). What do we know about the effective projectmanager?. International Journal of Project
Management, 9 (2), 99-104.
Singapore Green Building Council (SGBC). (2009). A strategic plan. Retrieved from
http://www.sgbc.sg/images/uploads/SGBC_Strategic_Plan_v5.pdf.
Tagaza, E., and Wilson, J. L. (2004). Green buildings: drivers and barriers e lessons learned from five melbourne
developments. Melbourne, Australia: University of Melbourne and Business Outlook and Evaluation.
Yudelson, J.(2008). The green building revolution. Washington: Island Press.
Zhang, X.L., Shen, L.Y., and Wu, Y.Z. (2011). Green strategy for gaining competitive advantage in housing
development: a China study. Journal of Cleaner Production, 19 (1), 157–167.
179