Pipa Jacking
Pipa Jacking
Pipa Jacking
This paper presents case studies of two major projects incorporating large diameter pipe jacking. The
paper includes all aspects of project delivery including planning, design, procurement and
construction from the unique perspective of the client, the designer, the contractor and the pipe
manufacturer. In detail the paper includes:
1. A description of the projects, the Perth Desalination – Water Supply Trunk Mains and Perth
Main Sewer, which included the installation of DN1500 & DN1800 concrete jacking pipes in
variable soil conditions including sections below the water table with drive lengths in excess
of 200 m.
2. Key risks and challenges of the projects including major road and rail crossings, a new outlet
pipeline into an existing reservoir and installing large diameter sewers in a congested urban
area. Any delays or errors would place other associated major projects at risk (valued at
hundreds of millions of dollars).
3. Risk mitigation incorporated into the design of the pipelines and specification of the jacking
pipe & pipe jacking methods, procurement and contractor selection.
4. The contracting strategy and contractor selection process including pipe jacking equipment,
design and location of shafts.
5. The design and manufacture of concrete jacking pipes and the pipe jacking construction
including challenges and achievements.
These projects by a major Australian water authority are an excellent model of how a cooperative
approach between the client, designer, constructor and supplier can provide a technical solution to
mitigate serious project risks associated with microtunnelling in a congested urban environment.
1 INTRODUCTION
In 2005 and early 2006, pipe jacking techniques were used in the delivery of two strategic projects of
the Water Corporation, namely the Perth Desalination – Water Supply Trunk Mains and the Perth
Main Sewer Section 5 Stage 2. Although the projects are quite different in nature, they both employed
pipe jacking methods using closed–face, remotely controlled laser guided steerable tunnelling
equipment, or to use the North American definition, microtunnelling (ASCE 36-01). This paper
describes how a cooperative approach between the client, designer, constructor and supplier can
provide a technical solution to mitigate serious project risks associated with pipeline construction in an
urban environment.
The DN1400 trunk main was 12km long and included an important crossing of the main Kwinana
Freeway where works were already underway for the construction of a major passenger rail line in the
Freeway median.
-1-
2.1.2 Thomson’s Reservoir
Storage at Thomsons Reservoir consists of a single concrete lined pond of 93ML capacity constructed
approximately 53 years ago as a local zone storage reservoir. However with higher inflows from the
Perth Desalination Plant, a larger inlet and outlet were required to increase the reservoir outflow
capacity to deliver bulk water into the integrated water supply scheme as well as the local zone.
All of the railway crossings required a sleeve to protect the railway embankment in the event of a
failure of the pressurised water main. Agreements were reached for tunnelling under these crossings
but tight constraints were imposed including fine tolerances on settlement and vibration.
Due to the length of the Rockingham Road crossing, and the nature of the rocky ground, it was
considered that construction of the water main inside a sleeve was justified in that this construction
method would provide the lowest risk to the corrosion protection on the outside of the water main.
Hence the four crossings were bundled into a single contract with a common requirement to install a
sleeve using microtunnelling and retrofit the welded MSCL water main inside the sleeve. This bundle
was tendered as a design and construct package with specific design issues to be addressed in the
tender. These included:
• Submission of computations for loading stresses on the sleeve pipe due to jacking loads and
surface loads;
-2-
• Tolerance on the constructed level of the sleeve pipe so that a minimum annulus around the
water pipe was maintained, and assuming that the water main is a rigid pipe, i.e., the steel
water main cannot be bent around bends in the product pipe due to construction tolerance;
• Specified closed face, pressure-balanced machines to minimise settlement, or voids on the
outside of the sleeve pipe. This was considered necessary to minimise the risk of any
settlement on voids threatening the operation of the railway, or the riding surface of the
freeway pavements;
• Minimise voids by limiting the size of the cutter head to be not more that 10 mm greater than
the sleeve pipe diameter;
• Installation of threaded ports in every 4th precast concrete sleeve pipe to allow lubrication and
later grouting;
• Detailed construction planning to be submitted in advance to ensure well thought out
procedures and contingency plans;
• Sleeve pipe joints to be water tight to control any lubrication and grouting fluids from entering
to the inside of the sleeve pipe;
• Tunnelling machine to be steerable to control tolerances;
• High electrical resistance of the sleeve to mitigate possible induced voltage differences
between the sleeve and the steel product pipe.
The annulus between the sleeve and the product pipes was grouted with low strength cementitious
grout as it was considered that this provided a conservative yet cost effective solution to prevent
possible corrosion of the inaccessible exterior of the product pipe.
It was planned that this particular section would be replaced using conventional open cut and plastic
lined reinforced concrete pipes. This planning work was done several years previously and it became
-3-
evident that significant traffic growth in the meantime would result in major impacts to both commuters
and the local business area if open cut methods were to be used.
The alignment of the sewer has a significant impact on road traffic, a busy high-speed bike path and
adjoining mature trees. In addition, as the level of the sewer is below the water table in free draining
soil, open cut construction would require significant well-point dewatering. Disposal of the groundwater
presented an undesirable environmental impact and temporary lowering of the groundwater table
presented a high potential risk for structural damage to nearby structures.
A review of the estimates taking into account current steel sheet piling costs revealed that trenchless
technology offered not only a significantly reduced construction impact, but also offered an
approximate 25% cost saving.
Significant risks were identified during the risk assessment process including selection of the right
contractors for tunnelling works. Any delays or errors would delay the delivery of water by October
2006, putting at jeopardy hundreds of millions of dollars worth of associated works for the whole of the
Perth Desalination project.
From the key project activities, a comprehensive contracting strategy was developed for the complete
suite of integration projects including details on the strategy for the microtunnelling contract.
Critical to the microtunnelling contract was a frank assessment of client knowledge and expertise in
tunnelling as well as a detailed assessment of industry capability and capacity, equipment availability
and personnel. The Water Corporation were fortunate to have two employees with extensive
tunnelling experience in Europe, Southeast Asia, the east coast of Australia and previous projects in
WA providing a wealth of knowledge in these areas.
The microtunnelling strategy included a “Registration of Interest” during the engineering design stage
followed by selective tendering from the pre-qualified tenderers near the end of detailed design. This
strategy ensured high quality contractors who could deliver on time whilst also providing a competitive
environment for pricing. This resulted in minimisation of risk to costs and schedules. Tenders received
were checked for completeness and conformity including a “Tender Response Schedule” against the
following components:
• Specific microtunnelling methodology;
• Proposed design details;
• Installation methodologies;
• Site layout including details of launch & retrieval pits;
• Equipment details;
• Sleeve pipe details;
• Grouting details;
• Key contract personnel.
Tenders were then assessed using a weighted points scoring system against the Selection Criteria of:
• Microtunnelling design and methodology;
• Capacity to undertake the contract (including equipment and expertise);
• Key personnel;
• Demonstrated ability to complete the contract in the timeframe;
• Cost; and
-4-
• Buy local policy considerations.
Assessment of tenders showed that capacity was a major factor with many interested contractors
unable to deliver the project as their tunnel boring machines were tied up in existing contracts either
on the eastern seaboard of Australia or overseas.
The contracting strategy proved very successful in contractor selection with assets delivered on time,
to a high standard and below budget.
-5-
• Four 20 mm internal diameter stainless steel threaded ports were cast into every fourth pipe
which included a threaded plug on the inside and a simple non-return valve on the outside
face. For the Thomsons Reservoir drive, all pipes supplied included these ports.
For the Desalination Plant pipelines jacking pipes were designed as sleeve pipes. The specification
required that pipe joints provide a “tight waterproof seal” and for all crossings the joint detail shown in
Figure 1 was supplied. The flexible joint of the jacking pipe was only required to have a limited life and
as such mild steel (uncoated) was selected as the pipe collar.
For the Perth Main Sewer the jacking pipe was the product pipe and to meet the design life
requirements for this project thermoplastic lining was cast into the inside surface and collars were
manufactured from Grade 316 stainless steel. The internal lining was a 1.5 mm thick plasticised PVC
cast into the top 350 degrees of the pipe with a cover strip welded across each pipe joint. Intermediate
jacking station pipes were designed in part based on the requirements of an existing Japanese
Specification (JSWAS-A2). The lead pipe (or can) was mild steel (epoxy coated) designed to joint into
the collar of a standard jacking pipe. The trail pipe was a modified precast concrete pipe that was also
lined with plastic. The internal diameter of the lead pipe was greater than the standard pipes allowing
for the installation of wider plastic strip welded across the closed joint maintaining the continuity of the
plastic lining along the full length of the completed pipeline.
(a) Joint External Hydrostatic Testing (b) PMS – Pipes in storage (c) Installation of Interjack Pipes
-6-
at the surface where the solids were separated and the water was recycled back into the system. For
the Perth Main Sewer project slurry pipelines were supported on specially designed frames that
resulted in zero damage to the plastic lining during both jacking and removal of slurry lines at the
completion of jacking operations (see photograph 2b).
The contractor employed only experienced crews on all stages of the microtunnelling operations. In
particular all tunnelling machine operators had installed many kilometres of pipe of this diameter using
the same equipment in similar soil conditions.
Table 3 - Summary of Drives for DN1500 & DN1800 Pipes
-7-
of interjack stations. As can be seen in Table 2 jacking forces were maintained well below the jacking
pipe capacity. Intermediate jacking stations were installed on two drives but were only used on the
longer one (drive #10).
a. Perth Main Sewer site b. Slurry pipes & lubrication lines c. Installation of MSCL Pipe
7 CONCLUSIONS
The success of the two pipe jacking projects is attributed to the following:
a) Carrying out detailed risk assessments at key stages in the projects;
b) Identifying and specifying project and design solutions that mitigate the identified risks. The
key risk mitigation measures included selection of appropriate pipe installation techniques,
specification of minimum tunnelling machine and jacking pipe requirements and required use
of caissons for entry and exit shafts for the Perth Main Sewer;
c) A tendering process that ensured only appropriately experienced contractors with the correct
equipment and personnel were selected; and
d) Close cooperation and interaction between the client, designer, pipe jacking contractor and
pipe manufacturer during key stages of the project from design through to commissioning.
REFERENCES
ASCE 36-01, Standard Construction Guidelines for Microtunneling, American Society of Civil
Engineers, Reston Virginia 20191-4400
Concrete Pipe Association of Australasia (CPAA), Concrete Pipe Jacking Technical Brief, from
http://www.concpipe.asn.au
Concrete Pipe Association of Australasia (CPAA-1990), Jacking Design Guidelines Design Manual,
from http://www.concpipe.asn.au
AS 3725-1989, Loads on buried concrete pipes, Standards Australia, NSW.
AS 4058-1992, Precast concrete pipes (pressure and non-pressure), Standards Australia, NSW.
AS 4799-2000, Installation of underground utility services and pipelines within railway boundaries,
Standards Australia, NSW.
JSWAS-A2-1991, Jacking Reinforced Concrete Pipes for Sewerage (Nominal Diameter 800 - 3000),
Japan Sewage Works Agency.
Infrastructure Design Branch, DS60 Water Supply Distribution Standard, Version 3 August 2004,
Water Corporation of Western Australia.
-8-