India Balco 4X300 MW TPP: LV Wei Liu Ping Zhou Shengzhang
India Balco 4X300 MW TPP: LV Wei Liu Ping Zhou Shengzhang
India Balco 4X300 MW TPP: LV Wei Liu Ping Zhou Shengzhang
60 250 - 290
70 120 - 150
80 80 - 120
90 50 - 80
98.9 30 - 50
100 30 - 50
110 20 - 30
120 10 – 20
1.4 Technical data of main pressure parts and heating surface tube
Attached table 1-9
No. Name Unit Value
1 Steam drum
Design pressure MPa.g 19.82
Max operating pressure MPa.g 18.873
Steam drum internal diameter mm 1,778
Steam drum external diameter mm 2,158
Length of steam drum straight section mm 18,000
Total length of steam drum mm ~20,134
Steam drum center elevation m 64.09
Steam drum material SA-299
Allowable stress of steam drum steel plate MPa 132.57
FATT of steam drum steel plate ℃ -20
Axial-flow cyclone separator +
Steam purifier type
vertical louver
Cyclone separator diameter mm Ф254
Evaporation and maximum evaporation of one
t/h, t/h 12.2,13.6
cyclone separator
Cyclone separator quantity set 84
Steam drum water capacity kg 48,000
Total weight of steam drum (including steam
t ~175
drum interior fittings)
Steam drum weight t ~179
Steam drum dimension (L×W×H) mm 20,200x3,300x2,500
Combustion chamber, water-cooled wall and
2
combustion equipment
Furnace type Membrane wall
Furnace dimension (W×D×H) mm 14,048×12,468×53,380
Furnace volume m3 7,754.1
Total heating area of furnace m3 4,514
Furnace radiation heating area m3 4,514
Furnace refractory belt area m3 /
Furnace cross-section heating load (BMCR) Mw/m2 4.398
Furnace volume heating load (BMCR) Mw/m2 99.34
Heating load of furnace effective projected
Mw/m2 170.6
radiant surface (EPRS) (BMCR)
Burner area heating load (BMCR) Mw/m2 1.513
Furnace outlet temperature (BMCR) ℃ 1023
Furnace design pressure ± KPa ± 5.8
Load carrying capacity for short-time non-
± KPa ± 9.8
deformation
Water-cooled wall design pressure Mpa.g 19.82
Water-cooled wall circulating mode Natural circulation
Water-cooled wall mass velocity (BMCR) kg/s 1,000~1,200
Quantity of water-cooled wall circulation
28
circuits
Water-cooled wall tube type Rifled tube + light pipe
Water-cooled wall tube external diameter φmm 63.5
Water-cooled wall tube internal diameter φmm 49.5
Water-cooled wall tube pitch mm 76.2
Water-cooled wall quantity Piece 668
Water-cooled wall tube material SA-210C
Arrangement height of water-cooled wall rifled
tube:
Front wall m ~28
Rear wall m ~31.5
Side walls m ~28
External diameter of water-cooled wall rifled
φmm 63.5
tube
Wall thickness of water-cooled wall rifled tube Mm 6.6 (MWT)
Water-cooled wall ribbed quantity Piece 668
Water-cooled wall rifled tube material SA-210C
Corner tube minimum circulation ratio (B- ~3.0
MCR)
Downcomer external diameter φmm Φ457
Downcomer internal diameter φmm Φ367
Downcomer wall thickness mm 45
Downcomer quantity Piece 4
Downcomer material SA-106C
External diameter of descending water
φmm 159
distribution pipe
Internal diameter of descending water
φmm 123
distribution pipe
Quantity of descending water distribution
Piece 74
pipes
Material of descending water distribution pipe / SA-106C
Cross-section ratio between downcomer and
/ 0.33
riser
Cross section ratio between riser and steam
/ 1.08
lead pipe entering steam drum
2
Heating surface area of water-cooled wall m 2838
Total water volume of boiler kg 125000
Ratio of critical heating load to design
maximum heating load in heat transfer ~1.45
deterioration of water-cooled wall
Direct-flow swing burner, angle
Burner type
arrangement
Total quantity of primary air nozzles of burner 20
Elevation of furnace hopper top m 15.166
Slag discharge hole elevation of slag pit m 6.720
Ignition and low load oil gun type (Quoters fill Heavy oil Light oil
it respectively) system system
Quantity of configured oil guns Set 8 4
Capacity of one oil gun kg/h 2200 1500
Atomization steam pressure MPa.g 0.88 0.686~0.784
Oil supply pressure (steam atomization) MPa.g 1.37 /
Oil supply pressure (mechanical atomization) MPa.g / 2.94
3 Superheater and reheater
Superheater design pressure MPa.g 19.82
Superheater spray design attemperating water
t/h 68.3, 34.2
amount (first and second stage)
Heating area of front platen superheater m2 663
Mass velocity of front platen superheater 2
kg/m .s 1,380
(BMCR)
Flue gas temperatures of rear platen
℃ 1,122 1,023
superheater forepart and afterpart (BMCR)
Flue gas temperature of rear platen superheater
℃ 1,307
bottom (BMCR)
Mass velocity of rear platen superheater
kg/m2.s 1,050
(BMCR)
2
Heating area of rear platen superheater m 1,054
Heating area of division wall superheater m2 663
Flue gas temperatures of division wall
℃ 1,307 1,122
superheater forepart and afterpart (BMCR)
2
Heating area of roof superheater m 269
Heating area of wall enclosure superheater m2 1,427
Flue gas temperatures of last stage superheater
℃ 813; 736
forepart and afterpart (BMCR)
2
Heating area of last stage superheater m 2,306
Total heating area of the superheater m2 16,747
Weight of austenite and martensite tube of
kg 13,400/23,600
superheater
Times of coordinated transposition of
Times 1
superheater left and right
Total pressure drop of superheater (BMCR) MPa 1.373
Steam temperatures at all superheater outlets
(BMCR)
Steam temperature at high temperature
℃ 541
superheater outlet
Steam temperature at rear platen superheater
℃ 504
outlet
Steam temperature at division wall outlet ℃ 446
Steam temperature at low temperature
℃ 408
superheater outlet
External, internal diameters and pitches of all See the data table of superheater
mm
superheater tubes (See Notes) tube stack
Average flue gas velocity of all superheaters See the data table of superheater
m/s
(corrected by altitude) tube stack
See the data table of superheater
Material of all superheaters
tube stack
Max. calculated steam temperature, calculated
metal wall temperature and wall temperature at See the data table of superheater
℃
max temperature point of all superheaters (See tube stack
Notes)
Data table of superheater tube stack
Item Unit Data
I. Low temperature superheater
Horizontal low Vertical low
temperature temperature
superheater superheater
Tube specification (external dia.× wall thickness) mm 516 516
Tube pitch (transverse/longitudinal) mm 136/102 136/102
Average flue gas velocity of tube stack (BMCR) m/s 11.2 10.6
SA-210C
Material SA-213T12 SA-213T22
SA-213T22
454
Allowable temperature for the material ℃ 540 580
580
Outlet steam temperature ℃ 397 408
Max. calculated steam temperature of superheater ℃ 405 413
Metal wall temperature at the outlet ℃ 440 458
Max. metal wall temperature (B-MCR) ℃ 445 460
Quantity of tubes connected in parallel 102/6 102/6
II. Division wall superheater
Tube specification (external dia.× wall thickness) mm 516,7
Tube pitch (transverse/longitudinal) mm 2,810/60.5
Average flue gas velocity of tube stack (BMCR) m/s /
SA-213T22
Material
TP-304H
580
Allowable temperature for the material ℃
704
Total weight of used austenite steel tube and martensite
t 2.0/0
steel tube
Outlet steam temperature ℃ 446
Max. calculated steam temperature of superheater ℃ 450
Metal wall temperature at the outlet ℃ 532
Max. metal wall temperature (B-MCR) ℃ 569
Quantity of tubes connected in parallel 4×6/8
III. Last stage superheater
Tube specification (external dia.× wall thickness) mm 518, 9
Tube pitch (transverse/longitudinal) mm 152.4/102
Average flue gas velocity of tube stack (BMCR) m/s 11.3
SA-213T22
Material
SA-213T23
Allowable temperature for the material ℃
Total weight of used austenite steel tube and martensite
t 0/0
steel tube
Outlet steam temperature ℃ 541
Max. calculated steam temperature of superheater ℃ 550
Metal wall temperature at the outlet ℃ 560
Max. metal wall temperature (B-MCR) ℃ 564
Quantity of tubes connected in parallel 90/4
Data table of reheater tube stack
Item Unit Data
I. Wall reheater
Tube specification (external dia.× wall thickness) mm 504
Tube pitch (transverse/longitudinal) mm 50.8
Average flue gas velocity of tube stack (BMCR) m/s /
Material / SA-213T12
Allowable temperature for the material ℃ 540
Outlet steam temperature ℃ 390
Max calculated steam temperature of superheater ℃ 396
Metal wall temperature at the outlet ℃ /
Max. metal wall temperature (B-MCR) ℃ 490
Front wall 234 pieces
Quantity of tubes connected in parallel
Sides wall 2×90 pieces
II. Division wall reheater
Tube specification (external dia.× wall thickness) mm 634,4.5,7
Tube pitch (transverse/longitudinal) mm 457.2/72.5
Average flue gas velocity of tube stack (BMCR) m/s 8.5
SA-213T22
Material T91
TP-304H
Total weight of austenite steel tube and martensite steel
t/t 6.2/3.7
tube of reheater
580
Allowable temperature for the material ℃ 635
704
Outlet steam temperature ℃ 484
Max. calculated steam temperature of superheater ℃ 549
Metal wall temperature at the outlet ℃ 622
Max. metal wall temperature (B-MCR) ℃ 622
Quantity of tubes connected in parallel 30/14
III. Last stage reheater
Tube specification (external dia.× wall thickness) mm 634; 4.5; 7
Tube pitch (transverse/longitudinal) mm 228.6/114
Average flue gas velocity of tube stack (BMCR) m/s 10.6
SA-213T22
Material T91
TP-304H
Total weight of used austenite steel tube and martensite
t 4.3/35.0
steel tube of reheater
580
Allowable temperature for the material ℃ 635
704
Outlet steam temperature ℃ 541
Max. calculated steam temperature of superheater ℃ 570
Metal wall temperature at the outlet ℃ 616
Max. metal wall temperature (B-MCR) ℃ 616
Quantity of tubes connected in parallel 60/7
Data table of economizer tube stack
Item Unit Data
4 Economizer
Design pressure (BMCR) MPa.g 20.22
Economizer inlet water temperature (BMCR) ℃ 280.4
Economizer outlet water temperature (BMCR) ℃ 314
Heating area (serpentine tube, pendant tube etc.) m2 9,055
Economizer pressure drop (BMCR) MPa 0.392
Flue gas velocity at economizer inlet and outlet
m/s 9.1; 7.9
(BMCR) (corrected by altitude)
Economizer tube arrangement In line arrangement
Economizer tube external diameter mm 51
Economizer tube internal diameter mm 39
Economizer tube wall thickness mm 6.0
Economizer tube pitch mm 127
Economizer tube material SA-210C
Quantity of economizer tubes in parallel 3×110
Wearing plate + spoiler + wearing
Anti-wear facilities of economizer
shield
5 Air preheater
Type 28.5-VI (T)-2133-SMR
Air preheater quantity set 2
Air inlet temperature (BMCR) (primary air) ℃ 40.5
Air inlet temperature (BMCR) (secondary air) ℃ 37.2
Air outlet temperature (BMCR) (primary air/
℃ 316/331
secondary air)
Flue gas temperature at the inlet (BMCR) ℃ 353
Flue gas temperature at the outlet (BMCR)
℃ 133
(before correction)
Flue gas temperature at the outlet (BMCR)(after
℃ 128
correction)
Air leakage ratios at put-in and after one-year’s
6, 8
operation
Whether there is a damper or actuator at the air
Closing damper
preheater outlet
Rotor diameter mm Ф 9970
Rotor height mm 2879
Total rotor weight t 250/set preheater
Rotor rotating speed r/min 1
Quantity of sootblowers per air preheater Set 1
Manufacturer of sootblowers per air preheater Set Clyde, Diamond
Bearing lubricating and cooling mode Oil bath and water cooling
Material of regenerative component on high
Q235-A
temperature section
Plate thickness of regenerative component on
mm 0.5
high temperature section
Area of regenerative component on high
m2 45,000
temperature section
Material of regenerative component on middle-
Q235-A
temperature section
Plate thickness of regenerative component on
mm 0.5
middle-temperature section
Area of regenerative component on middle-
m2 28,000
temperature section
Material of regenerative component on low
CORTEN steel
temperature section
Plate thickness of regenerative component on low
mm 0.8
temperature section
Area of regenerative component on low
m2 13,000
temperature section
Main drive motor type Y160M-6
Main drive motor rotating speed r/min 970
Main drive motor power kW 7.5
Main drive motor quantity set 1/each preheater
Auxiliary drive motor type Y160M-6
Auxiliary drive motor rotating speed r/min 970
Auxiliary drive motor power KW 7.5
Auxiliary drive motor quantity Set 1/preheater
Drive reducer type ZSY
6. Safety valve
Steam drum safety valve type Spring type
Steam drum safety valve quantity 3
Steam drum safety valve nominal diameter mm F75
Steam drum safety valve throat diameter mm /
Steam drum safety valve exhaust volume (each
kg/h 277,100/285,600/289,700
set)
Popping pressure of steam drum safety valve MPa.g 19.82/20.22/20.41
Reseating pressure of steam drum safety valve MPa.g 19.03
Steam drum safety valve manufacturer CROSBY/DRESSER
Technical standard for design and manufacturing
ASME
of steam drum safety valve
Superheater outlet safety valve type Spring type
Quantity of superheater outlet safety valve 2
Superheater outlet safety valve nominal diameter mm F65
Superheater outlet safety valve throat diameter mm /
Superheater outlet safety valve exhaust volume
kg/h 114,500/114,800
(each set)
Popping pressure of superheater outlet safety
MPa.g 18.31/18.34
valve
Reseating pressure of superheater outlet safety
MPa.g 17.58/17.61
valve
Superheater outlet safety valve manufacturer DRESSER, CROSBY
Technical standard for design and manufacturing
ASME
of superheater outlet safety valve
Silencer type of superheater outlet safety valve Provisional
Silencer quantity of superheater outlet safety
Set 2
valve
Silencer manufacturer of superheater outlet safety
Domestic
valve
Superheater outlet PCV type Pneumatic
Superheater outlet PCV quantity 1
Nominal diameter of superheater outlet PCV mm F65
Throat diameter of superheater outlet PCV mm /
Exhaust volume of superheater outlet PCV (each) kg/h 103,000
Popping pressure of superheater outlet PCV MPa.g 18.13
Reseating pressure of superheater outlet PCV MPa.g 17.77
Manufacturer of superheater outlet PCV DRESSER/CROSBY
Technical standard for manufacturing of
ASME
superheater outlet PCV
Silencer type of superheater outlet PCV To be confirmed
Silencer quantity of superheater outlet PCV set 1
Silencer manufacturer of superheater outlet PCV Domestic
Reheater inlet safety valve type Spring type
Reheater inlet safety valve quantity 3
Nominal diameter of reheater inlet safety valve mm F152
Throat diameter of reheater inlet safety valve mm F114
Exhaust volume of reheater inlet safety valve
kg/h 191,200/193,300/197,300
(each)
Popping pressure of reheater inlet safety valve MPa.g 4.384/4.428/4.516
Reseating pressure of reheater inlet safety valve MPa.g 4.209/4.251/4.335
Manufacturer of reheater inlet safety valve DRESSER, CROSBY
Technical standard for design and manufacturing
ASME
of reheater inlet safety valve
Type of reheater outlet safety valve Spring type
Quantity of reheater outlet safety valve set 2
Nominal diameter of reheater outlet safety valve mm F150
Throat diameter of reheater outlet safety valve mm /
Exhaust volume of reheater outlet safety valve
kg/h 148,000/155,000
(each)
Popping pressure of reheater outlet safety valve MPa.g 4.105/4.311
Reseating pressure of reheater outlet safety valve MPa.g 3.941/4.138
Manufacturer of reheater outlet safety valve DRESSER, CROSBY
Technical standard for design and manufacturing
ASME
of reheater outlet safety valve
7 Sootblower and flue gas temperature probe
Hubei Diamond
Sootblower manufacturer
Shanghai Clyde
Type of furnace sootblower Retractable
Length of furnace sootblower m 0.86
Quantity of furnace sootblowers set 80
Type of convection heating surface sootblower Long retractable
Length of convection heating surface sootblower m ~7.0
Quantity of convection heating surface
set 24
sootblower
Type of economizer area sootblower Semi-retractable
Length of economizer area sootblower m ~3.5
Quantity of economizer area sootblower set 6
Type of air preheater sootblower Retractable
Length of air preheater sootblower m 4
Quantity of air preheater sootblower set 2/each boiler
Quantity of each boiler’s sootblower set 112 (including air preheater)
Quantity of sootblower holes reserved for furnace
and convection heating surface on the furnace /
wall
Steam source of sootblower Boiler proper
Manufacturer of pressure relief valve of pressure
Import
relief station
Type of pressure relief valve of pressure relief
/
station
Nominal diameter of pressure relief valve of
mm DN125
pressure relief station
Steam pressure at the inlet of pressure relief valve
MPa.g 18.1
of pressure relief station
Steam pressure at the outlet of pressure relief
MPa.g 3.1
valve of pressure relief station
Air supply amount of pressure relief valve of
t/h 19
pressure relief station
Drainage type of pressure relief valve of pressure
Temperature controlled
relief station
Manufacturer of pressure relief valve of pressure
Inlet
relief station
Type of flue gas temperature probe Retractable
Hubei Diamond Shanghai
Manufacturer of flue gas temperature probe
Clyde
Quantity of flue gas temperature probe set 2
Primary element type of flue gas temperature
/
probe
Temperature range of flue gas temperature probe ℃ 0~570
1.5 Steam and water quality criteria
Attached table 1-10
Index Description
Item
Boiler water Steam
Phosphate radical 0.5~3mg/L
Chlorine ion 1mg/L
Total salt content 20mg/L
Conductivity (25℃) 50s/cm 0.3s/cm (after hydrogen exchange, 25℃)
Silicon dioxide 0.25mg/L 20g/kg
PH 9~9.5
Na 10g/kg
Silicon dioxide
Iron 20g/kg 20g/kg
Copper 5g/kg 5g/kg
1.6 Relative thermodynamic system
(1) Main steam and reheated steam system
Main steam and reheated steam systems are both unit systems. Cold reheated steam is also as the standby
steam source for steam-driven feed water pump during unit startup and under low load as well as one of
steam sources of auxiliary steam system. Turbine bypass adopts HP & LP second stage serial bypasses with
capacity of 60% BMCR, so that the boiler can automatically reduce load during load rejection under
BMCR operating condition.
(2)Regenerative steam extraction system
Turbine adopts eight-stage non-regulated steam extraction, in which the first three stages are used for three
HP heaters respectively, the fourth stage is used for feed water pump turbine, deaerator and auxiliary steam
and the last four stages are used for four LP heaters respectively.
(3) Feed water system
Feed water system is a unit system. One boiler has two steam feed water pumps of 50% BMCR which is
used for normal operation, and one motor-driven variable speed feed water pump of 50% BMC which is
used for startup and as a standby. Bypass of feed water operating floor is 30% BMCR. Feed water system
also supplies attemperating water to reheater, attemperator, attemperator of the superheater and high
pressure bypass system.
(4) Condensate system
Condensate system adopts medium pressure condensate polishing system and each set of unit is equipped
with two condensate pumps of 100%, in which one is for standby application. Condensate will enter
deaerator after pressure raise by condensate pump through polishing device, one shaft seal heater and four
LP heaters.
Each boiler has one condensate make-up water tank and make-up pump to provide make-up water and
startup water for condensate system, as well as make-up water and storing water for water level control of
condenser hot well water level. Make-up pump is also used as boiler feed water pump during unit startup.
(5) Cooling water system of auxiliary machinery
Cooling water system of auxiliary machinery in this project is composed of open circulating cooling water
system and closed circulating cooling water system. Closed circulating cooling water system adopts
demineralized water mainly for cooling parts with relatively higher requirements for water quality, such as
rotating mechanical bearing, motor and etc. While, open circulating cooling water system comes from
circulating water system, mainly cooling surface type heat exchanger and etc. In order to save water, all
cooling water is considered to be complete recovered. Preliminary design parameters of cooling water
system are as follows:
System Design Pressure (MPa) Design Temperature (℃) Water Quality Remarks
Open circulating ~0.41 36 Circulating water
cooling water
Closed circulating ~0.5 41 Demineralized
cooling water water
1.7 Meteorological and geographical conditions of the plant
The construction site of this project is in a climate of high temperature and humidity.
Plant location: Korba District of Chattisgarh, India.
Power plant altitude: 295-300m above MSL (mean sea level)
Atmospheric pressure: 101.3kPa (provisional) according to the altitude
Extreme maximum temperature: 49℃
Extreme minimum temperature: 8℃
Design temperature: 8~50℃
Design temperature of electrical equipment: 50℃
Relative humidity:
Max. 90%
Min. 49%
Design 60%
Mean annual precipitation: 1200mm
Basic wind speed: as per Indian standard (IS-875), 10m high above the ground, once 50 years and
maximum wind speed with 3s is 39m/s.
Earthquake intensity: VII
Earthquake acceleration: 0.15g (as per IS-1893: zone-II)
Site-soil type: Type II (provisional)
Drive device
The normal rotating speed of output shaft is 0.9 rpm
Reducer
Double shaft
Model Y160L-6 B5
extension
Voltage 415 V
Main motor Current 17 A
Power 11 kW
2
Rotating speed 970 r/min
Double shaft
Model Y160L-6 B5
extension
Voltage 415 V
Auxiliary Current 17 A
motor
Power 11 kW
Rotating speed 970 r/min
Normal rotating speed of rotor: 0.9RPM; rotor rotating speed at low gear, adopting inverter speed
regulation: 0.3RPM.
Supporting Type Roller radial-thrust bearing
bearing Model 294/500E
Water
5 cleaning Multi-nozzle fixed type purge pipe
device
6. Specification list for pulverizing system equipment
No. Name Specification Remarks
Model: CS2024HP
Delivery capacity: 18.42-91.62t/h
Coal feeding distance (center line distance of coal feeder inlet and
outlet): 3,050mm
Installation site: bunker bay, 17.0m layer
Elevation of interface between inlet coal gate and bunker outlet:
+21.5m
Bunker outlet dimension: φ1000×10mm (provision)
Elevation of interface between outlet coal gate and coal pulverizer
inlet: +11.025 (provision)
Electric
Dimension of coal chute interface in coal pulverizer: φ950×10mm 5 sets per
1 weighing coal
(provision) boiler
feeder
Calculating precision: ±0.25%
Control precision: ±0.5%
Output interface of instrument: RS232/485, 4~20mA, solid state relay
pulse output
Alarm contact: in case of coal interrupt, there will be 4~20mA current
output, temperature alarm, coal jamming delay, belt side skid and 220V
AC5A contact rating.
Motor model: GT9350907
Power supply: 415V, three phase 50Hz
Power: 3kW
Scavenging Motor model: GT9361507
2 machine of Power: 0.25kW 5 sets
coal feeder Voltage: 415V, three phase 50Hz
3 Coal Item Unit Coal 5 sets per
pulverizer & Design Worst furnace
speed reducer coal coal
Coal pulverizer Max output t/h 76.35 73.67
output power Calculated output (BMCR) t/h 54.55 60.65
Guaranteed output t/h 60.61 67.32
Min output t/h 19.09 18.42
No. Name Specification Remarks
Coal pulverizer Max air quantity t/h 105.2 106.95
air quantity Circulated ventilation t/h 91.2 98.14
quantity (BMCR)
Air quantity of guaranteed t/h 95.07 102.65
output situation
Min air quantity t/h 68.36 69.52
Coal pulverizer Max ventilation resistance Pa 7.35k
ventilation Ventilation resistance Pa 6.39k 6.95k
resistance (guarantee output)
Calculated ventilation Pa 6.02k 6.53k
resistance (BMCR)
Unit power Unit power consumption of Kw. 12.67 12.36
consumption of coal pulverizer (BMCR) h/t
coal pulverizer
Unit power consumption in Kw. 12.10 11.85
guaranteed output situation h/t
Coal pulverizer grinding pan speed: 22.3r/min
Coal pulverizer rotation direction: clockwise (top view)
Sealing air quantity: 81.52 Nm3/min
D-value between sealing air pressure and primary air pressure: 2000Pa
Rated air quantity of coal pulverizer: 18.80kg/s
Electric power consumption of coal pulverizer: 6~10kW·h/t
Motor rated power: 1000kW
Motor rated speed: 990r/min
Rated voltage: 6.6kV
Frequency: 50Hz
Lubrication cooling device (model): XYZ350-L
Oil pump flow: 350 l/min
Motor power: 7/11
Normal oil supply pressure: 0.13mpa
Name of lubricating oil: N320
Hydraulic loading device (model)
Oil pump flow: 15l/min
Motor power: 7.5kw
Normal oil supply pressure: 14MPa
High-energy igniter: model XDH-12, output 1 piece for the heavy and
4 Igniter
voltage: 2,500V and spark frequency: 9-15’/s light oil burner each.
Sectional area of nozzle:
Air ratio: 27.5%
5 Primary air
Air speed: 27m/s
Primary air temperature: 316℃
Sectional area of nozzle:
Air ratio: 67.5%
6 Secondary air
Air speed: 47m/s
Air temperature: 331℃
Total pressure: 5.0kPa
2 sets for each furnace, which
Output: 3,500m3/h
Flame test probe must operate when the
7 Voltage: 415V
cooling fan furnace temperature is higher
Speed: 2,900r/min
than 150℃.
Capacity: 11kW
8. Specification table for flue gas temperature probe
No. Equipment Item Specification Unit
Type TS-0 Flexible-type
Quantity 2 set/furnace
Flue gas temperature Advance speed 1.44 m/min
1
probe Travel 4,800 mm
Max measured temperature 570 ℃
Exit temperature 538 ℃
Flue gas temp. probe Voltage 380 V
2
motor Power 1.1 kW
Hydrous dirty
Medium LDO LDO HFO,55℃ HFO,55℃
oil: 55
Multi stage Volumetric oil Gear type oil Worm type oil Worm type oil
Type
centrifugal type pump pump pump pump
Set 3 2 1 3 2
Pressure head 4.3MPa 0.4MPa 0.5MPa 3.0MPa 1.0MPa
Output 11m3/h 24m3/h 2m3/h 35m3/h 40m3/h
Shaft output 32.2kW 5.1kW 1.1kW 35.2kW 16.4kW
Rotating
2,970r/min 2,900r/min 1,420r/min 1,450r/min 1,450r/min
speed
Motor type YB225M-2 YB160M1-2 YB100L1-4 YB225M-4 YB180L-4
Power 45kW 11kW 2.2kW 45kW 22kW
Voltage 415V 415V 415V 415V 415V
Rotating
2,970r/min 2,900r/min 1,420r/min 1,470r/min 1,470r/min
speed
11.3.2 Technical data table of oil filter for heavy oil pump
For Heavy Oil Feed For Heavy Oil
Content Unit For Sewage Pump
Pump Drain Pump
SDGLQ-35T-60 SDGLQ-40T-30
1 Model SDGLQ-13T-30 mesh
mesh mesh
Vertical single- Vertical single-
2 Type Vertical single- barrel
barrel barrel
3 Quantity Set 3 2 1
4 Working medium Heavy oil Heavy oil Sewage
Mesh
5 Filter fineness 60 30 30
/inch
6 Design pressure MPa 1.6 1.6 1.6
7 Design temperature ℃ 120 120 120
8 Design flow m3/h 35 40 12.5
Differential pressure of
9 inlet and outlet during MPa 0.02 0.02 0.02
normal operation
Size of inlet and outlet
10 mm φ133×4.0 φ133×4.0 φ76×5.5
connections
Material and service life 1Cr18Ni9Ti/12 1Cr18Ni9Ti/12
11 1Cr18Ni9Ti/12 years
of filter element years years
Casing & supporting
12 Q235A Q235A Q235A
material
13 Weight Kg 126 162 56
14 Dimension mm φ500×1,050 φ650×1,115 φ450×840
12. Air cannon specification
Cone part of single coal bunker is equipped with eight air cannons (the capacity of 150L); there are four air
cannons on the upper of the cone (the capacity of 220L), air cannon adopts local/remote control. Air cannon
should be controlled by hierarchy, group and bunker and etc.
12.1 Main technical specification
Main technical specification
Working pressure: 0.4~0.8MPa
Working medium: compressed air
Container class: First class
Design temperature: -20~50℃
Nominal volume: 150L/220L
Hydraulic test pressure: ≥1.1MPa
Impact force: 10000N/14080N
Explosion energy: 20400kgfm/35600 kgfm
Design service life: 30 years
PART 2 Boiler Unit Stadrtup
Chapter 1 Trial Operation & Test of Main Equipment of Boiler after
Inspection & Repair
1.1 Trial operation of auxiliary machinery after inspection and repair
1.1.1 Check before trial operation
1) The check before trial operation of auxiliary machinery shall be done according to the check
requirements before startup on each post.
2) Make sure the inspection and repair of both each auxiliary machinery and electric equipment thereof is
finished, work sheets have been recalled, each damper, baffle and rotating machinery of the air, flue gas
system and pulverizing system all have been calibrated and are in good condition; the main equipment and
related lubricating oil, hydraulic oil and cooling system, as well as each instrument all meet the
requirements for startup; the motor connections are in good condition.
3) After checking it is normal, switch on the motive power source and operating power source and air
source, and put each protection and related instrument and interlocker thereof into operation.
1.1.2 Requirements in trial operation
1) The motor shall be operated in trial operation at no load in correct direction of rotation with the no load
current of motor recorded before the trial operation of auxiliary machinery.
2) When the trial operation of auxiliary machinery is operated, monitor the startup current, the duration of
max startup current and the no load current after return, and keep a record of them.
3) Each set of auxiliary machinery shall be started at no load so as to guarantee the safety of equipment.
4) When the induced draft fan, forced draft fan and primary air fan are operated, the load adjustment test
and max load test under each operating condition shall be carried out and the current shall not exceed the
rating.
5) The continuous trial operation duration of the induced draft fan, forced draft fan and primary air fan shall
not be less than 4 hours; the continuous trial operation duration after replacing main parts shall not be less
than 8 hours (or fixed according to the requirements for inspection and repair, but the record must be kept).
6) When each set of auxiliary machinery of the pulverizing system is operated, make sure there is no
pulverized coal deposit and self-ignition phenomenon.
7) If any abnormal case is founded during trial operation, the running must be stopped immediately and can
be restarted after ascertaining the causes and removing the fault.
8) Each protection and related interlocking test of auxiliary machinery must be finished before trial
operation of the power equipment.
1.2 General rules for the interlocking test & protection test of boiler
1.2.1 The interlocking test and protection test must be performed to the boiler that went through overhaul
and minor repair.
1.2.2 Each interlocking and protection test can be done only as applied by the troubleshooter and approved
by the shift engineer. During the test, the unit supervisor and electric, thermodynamic engineers and related
personnel must be present, and any problem shall be removed in case of being found until passing the test.
1.2.3 The test method includes two types, static and dynamic. During dynamic test, the operating power
source and motive power source all are switched on, but during static test, operating power source is only
switched on for the 6.6kV motor and motive power source is only switched on for the 415V low-voltage
motor. The dynamic test can only be done after static test normal, but is not done generally (if necessary, it
shall be approved by the chief engineer).
1.2.4 The test can be done after the interlocker and protection switch of boiler are switched off.
1.2.5 The electric interlocking and heat engine protection test shall be operated accurately and reliably.
1.2.6 When the unit is operated normally, it is strictly forbidden to switch off the electric interlocking and
heat engine protection; if necessary, the switch off shall be approved by the shift engineer and restored
within a definite time.
1.3 Related thermodynamic and mechanical protection fixed values of boiler are as follows:
1) Steam drum water level:
High limit I +120mm Alarm
High limit II +240mm Boiler shutdown
Low limit I -180mm Alarm
Low limit II -330mm Boiler shutdown
Notes: when the steam drum water level is at +140mm, interlock to open emergency water discharge valve;
when the steam drum water level is at +50mm, interlock to close it.
2) Furnace pressure:
High limit I +980Pa
High limit II +3,240Pa Boiler shutdown
Low limit I -980Pa
Low limit II -2,490Pa Boiler shutdown
3) Fixed values of safety valve operating pressure are as follows:
Reseating Pressure
Name Operating Pressure (MPa)
(MPa)
Saturated I safety valve 19.82
Saturated II safety valve 20.22 19.03
Saturated III safety valve 20.41
Last stage superheater outlet I safety valve 18.31 17.58
Last stage superheater outlet II safety valve 18.34 17.61
Superheater outlet PCV valve 18.13 17.77
Reheater inlet I safety valve 4.384 4.209
Reheater inlet II safety valve 4.428 4.251
Reheater inlet III safety valve 4.516 4.335
Reheater outlet I safety valve 4.105 3.941
Reheater outlet II safety valve 4.311 4.138
4) Air quantity is low:
≤30% total air quantity of boiler rated load Boiler shutdown
5) Turbine trips and load is higher than 30% Boiler shutdown
6) Flame check cooling air pressure is low:
Difference between cooling air pressure and furnace pressure is ≤ 2kPa Boiler shutdown
1.4 Test of motor-operated valve, governing valve, damper and baffle
1.4.1 Contact the thermodynamic personnel to switch on the power source for each motor-operated valve,
governing valve, damper, flue gas damper and baffle servo, and the operators shall cooperate for test.
1.4.2 Check the position of changeover handles of each valve, damper, baffle servo; perform on-off tests to
all motor-operated valves and governing valves, the extent of opening indication shall conform to the actual
extent and direction, and the red and green indicator lamp shall indicate correctly; close control and manual
operation shall be on and off flexibly; remote control test and limit switch shall operate normally, for the
valve and damper with “OFF” button, their stop shall be normal by test; the pneumatically-operated device
shall operate flexibly, air inlet pressure be normal without any leak and abnormal phenomenon.
1.5 The interlocking protection tests of auxiliary machinery shall be done one by one according to the
requirements in the equipment interlocking test card.
1.6 Protection test of boiler FSSS (furnace safeguard supervisory system)
1.6.1 Oil leak test
The fuel oil piping leak test must be finished under the precondition of MFT (master fuel trip) resetting in
the process of boiler startup. The bypass oil leak test is strictly forbidden.
1.6.1.1 Oil leak test: the oil leak test can be done only when all the following conditions are met:
(1) Oil leak test failure signal has reset;
(2) Pressure of fuel oil mains is normal;
(3) No flame is detected;
(4) Trip valves of all oil burners have shut down;
(5) No condition existing for MFT trip.
When the above conditions are all met, the signal “Oil Leak Test 1 Start” will be made to start the leak test
process, the command for opening the fuel oil mains trip valve and oil return mains is made, start the 40S
timer, close oil return fast valve and close the fuel oil fast valve 10s later to fill the oil mains with oil and
raise its pressure, and provide a self-holding circuit so that even if the startup transient signal is lost, the
output signal will still continue. Make the pressure in the fuel oil mains up to the oil supply pressure within
40S (provided no leak). After 40S time out, if no signal of “Oil pressure is normal by the fuel oil leak test”
is made, then the signal of “Leak Test 1 Failure” is made and the test is cancelled; if the signal of “Oil
pressure is normal by the fuel oil leak test” is made, then the system is proved no leak, meanwhile, another
2-minute timer will be triggered. When this 2 minutes time out, if no signal of “Oil pressure is low by the
fuel oil leak test” is made, the system is proved no serious leak and the oil leak test 1 succeeds. Otherwise
there will be the signal of “Leak test 1 failure” and the test is cancelled.
1.6.1.2 Oil leak test 2
After the oil leak test 1 succeeds, if the conditions for oil mains leak test are met, the step 2 test may be
started. Open the oil return shut off valve of fuel oil mains to reduce the pressure of oil mains, when “Oil
pressure is low by oil mains leak test”, close the oil return shut off valve of fuel oil mains, trigger 2-minute
timer, the signal “Oil Leak Test 2 Start” is made after closing the oil return shut off valve of fuel oil mains.
If the signal of “Oil pressure is low by the fuel oil leak test” continues (not triggered) after time out, then
the signal of “Leak test 2 success” will be made. On the contrary, the signal of “Leak test 2 failure” will be
made and the test is cancelled.
The leak test 2 may be started and stopped individually on the basis of leak test 1 success.
1.6.2 Conditions for purging furnace:
The conditions for purging furnace that must be met are as follows:
Condition1:
(1) No flame is detected:
(2) Furnace pressure is normal;
(3) The safety fast valve of fuel oil mains has been closed;
(4) Trips of all oil burners have been closed;
(5) All coal pulverizers have been stopped;
(6) All primary air fans have been stopped;
(7) All precipitators have been stopped;
(8) No condition for MFT trip;
(9) Oil leak test succeeded;
(10) All coal feeders have been stopped;
(11) Flame test cooling air pressure is not low;
(12) At least one air preheater is operated;
(13) At least one induced draft fan is operated;
(14) At least one forced draft fan is operated;
(15) All outlet dampers of coal pulverizers have been closed;
(16) Steam drum level is normal;
(17) Boiler air quantity is not less than 30%
Condition 2:
(1) The swinging nozzle is horizontal;
(2) OFA damper baffle has been closed;
(3) Auxiliary air baffle is on Purge position.
When all conditions above are met, the signal of “Purge Permit” is met, here the button “Purge Start” may
be pressed, 5 minutes for purging boiler is started to be timed, if any condition for purge above is lost
during the 5 minutes, the purging shall be interrupted and the alarm shall be made, the boiler purging may
be restarted only when all conditions above are met with the 5 minutes retimed until time out.
When the 5 minutes for purging time out, a signal of “Purge Finish” shall be made which will reset the
memory signal of “MFT (master fuel trip)”
1.6.3 Related operating commands & condition description of furnace front oil system
1.6.3.1 Allowable conditions for oil burner ignition
(1) After the furnace purging succeeds and the MFT relay OFT reset, the operator makes the command of
“Opening the safety fast valve of fuel oil mains” and command of “Opening the oil return shut off valve of
fuel oil mains”.
(2) Ignition of igniter
When the allowable conditions for boil ignition preparation mode are met, the igniter may be permitted to
be put into operation. In addition, the equipment availability of ignition system and if system conditions are
met will be proved.
(3) Allowable conditions for oil gun to ignite:
1) Boiler air quantity reaches the valve for purging;
2) Flame detector cooling pressure is met;
3) Valves of all burners are closed;
4) Wind box/furnace differential pressure is met;
5) No trip signal of MFT or oil system;
6) Atomized steam pressure is normal;
7) Oil pressure met the requirement for ignition;
8) Ignition system has been ready;
9) Oil temperature is normal;
When all the conditions above are met, “Ignite Permit” will be displayed on the screen of LCD, and when
the ignition conditions for each oil gun are met, the oil gun may be put into operation.
1.6.3.2 Ignition procedure of oil burner (with the oil burner AA1 on layer AA as an example):
1): When the oil burner AA1 is in remote control mode, operate the Start button of oil burner AA1 on the
graphic display of CRT or accept the sequence control oil burner AA1 startup command from the layer
startup to start the ignition program formally;
2): The command for oil gun protruding into is made (3S pulse);
3): The oil gun is detected having been protruded into the designated position 10S after entering the
ignition program formally, and the purge valve of oil burner AA1 is closed, then make the command for
igniter extending (30S pulse);
4): If the igniter is detected having been protruded into the designated position 10S after the command for
igniter protruding into is made, then make the command for opening the oil filling valve of oil burner and
the igniter starts to strike fire at the same time (10S pulse) .
5): If the trip valve of oil burner is detected opening and having been fired after the above command is
made for 10S, then the oil burner AA1 ignites successfully and enters the state to be put into operation.
Once any condition 1) to 4) above for oil burner AA1 being ready is not met in the process of the procedure
above, then the ignition fails.
1.6.3.3 Conditions for oil burner AA1 shutdown (OR)
(1) Ignition failure: no flame is detected 10s after opening oil valve A1;
(2) Oil valve failure: the oil valve does not reach the full opening position 10s after the command for
opening oil valve is made;
(3) Conditions for burner ignition are not met (such as the fuel trip MFT or OFT, etc.);
(4) In remote control mode and the operator makes a shutdown command.
1.6.3.4 Shutdown sequence of oil burner AA1
1): Close the oil valve;
2): If there is no “Condition for disabling purging oil gun”, the oil gun shall be purged;
3): Disengage the oil gun after purging is finished.
1.6.3.5 Conditions for purging AA1 oil gun
In any case as follows, the oil gun shall not be purged:
(1) MFT operates;
(2) OFT operates;
(3) Oil gun is not protruded into;
(4) Purging steam pressure is low;
(5) The central air baffle of the layer where this burner is not in correct position;
(6) The safety fast valve of fuel oil mains is not opened.
1.6.3.6 Process of purging oil burner AA1
Step 1: Protrude the igniter into;
Step 2: If the igniter is detected having been protruded into the designated position 10s after making
protruding command, then make the command for opening the purge valve and the igniter strikes fire for
10s;
Step 3: If the purge valve is detected having been opened to the designated position 5s after the command
for opening purge valve is made, then purge the oil burner for 30s;
Step 4: Shut down the purge valve after purging for 30s, 2s later, disengage the igniter and oil gun.
1.6.4 Control of the safety fast valve of fuel oil mains:
When the conditions as follows are met, it is permitted to open the safety fast valve of fuel oil mains:
(1) Trip valves of all oil burners are closed;
(2) OFT has been reset;
(3) MFT has been reset;
(4) Pressure of fuel oil mains is normal and the safety fast valve of fuel oil mains has been closed;
When the conditions above exist, pressing the button OPEN of the safety fast valve of fuel oil main will
make the command for opening it. With the opening of valve, the oil mains pressure will rise to normal
value. It is designed that the safety fast valve of fuel oil mains shall be opened and the fuel oil mains
pressure shall be up to normal within 5s after it departs from the CLOSE position, and otherwise the
opening is considered failed.
In any case as follows, the safety fast valve of fuel oil mains will be interlocked and closed:
(1) MFT operates;
(2) OFT operates;
(3) Pressure of fuel oil mains is abnormal.
The safety fast valve of fuel oil mains may also be closed manually.
1.6.5 Control of oil return shut off valve of fuel oil mains:
The oil return shut off valve of fuel oil mains is a single-coil solenoid valve. It needs to open when oil
circulation is constituted or oil leak test is carried out and will be closed after the oil burner is put into
operation.
When the conditions as follows are met, it is permitted to open the oil return shut off valve of fuel oil
mains:
(1) OFT has been reset;
(2) MFT has been reset;
(3) Trip valves of all oil burners are closed;
When all conditions above are met, then pressing the button OPEN of oil return shut off valve of fuel oil
mains will open the valve.
In any case as follows, the oil return shut off valve of fuel oil mains will be interlocked and closed:
(1) OFT operates;
(2) MFT operates;
(3) 10s after the oil return shut off valve of fuel oil mains is opened in oil leak test.
The oil return shut off valve of fuel oil mains may be closed manually in any case.
1.6.6 Startup of boiler oil layer:
This boiler fires two fuel oils: light oil for layer AA and heavy oil for layer AB and CD, so atomization with
steam is necessary and it is required to ignite from the oil burner on layer AA on and from bottom up layer
by layer (that is the oil layer AA is started first and then the layer AB and CD). With regard to the control of
oil layer, the startup sequence of oil burner is “1-3-2-4” and shutdown sequence is “4-2-3-1”. When local
operation is required, it may switch to the mode of local control, the command of “Local operation permit”
is made to the local control cabinet. Here the indicator lamp of “Local operation permit” on the local
control cabinet lights, then each set of equipment of oil burner may be operated on the local control cabinet.
1.6.6.1 Layer startup (with the oil burner on layer AA as an example):
When all the oil burners on layer AA are in remote control mode, if any condition as follows is met, the
command for oil layer AA startup will be made:
(1) Oil layer AA is started by the operator;
(2) Oil layer AA is requested to be put into operation before the coal layer A is put into operation.
Layer startup sequence:
(1) Operator confirms all oil burners on this layer have been ready;
(2) Press corresponding layer startup button;
(3) Start the oil burners at intervals of 15S in order of “1-3-2-4”.
1.6.6.2 Layer shutdown sequence:
(1) Press corresponding layer shutdown button;
(2) Shut down the oil burners at intervals of 15S in order of “4-2-3-1”.
1.6.7 Coal layer startup:
The requirement and method for startup of all coal layers of a same boiler are the same, and they all can be
started automatically or manually.
1.6.7.1 Coal layer ignition permit:
Conditions as follows for ignition of coal layer A~D shall be met first:
(1) Conditions for furnace ignition are met;
(2) Primary air pressure is normal;
(3) Coal feeder on adjacent layer prove >50%;
(4) Corresponding oil layer is put into operation;
(5) Air quantity is >30% and <40%, or any coal layer is put into operation;
(6) Primary air temperature is normal;
Before any coal layer (mill) start, the boiler side must have enough energy to ignite the pulverized coal on
this layer and sustain stable combustion of this coal layer, that is the corresponding signal of “Coal layer
ignition permit” shall be constituted.
When any condition as follows is met, the signal of “Coal layer ignition permit” for this coal layer is
constituted:
A. The boiler oil layer adjacent to this coal layer has been put into operation;
B. The other coal layer adjacent to this coal layer has been put into operation and corresponding mill load is
>50%, and boiler load is >30%;
C. The other coal layer adjacent to this coal layer has been put into operation and corresponding mill load is
>50%, and the boiler oil layer adjacent to such a coal layer that has been put into operation also has been
put into operation.
1.6.7.2 Mill startup permit: the signal of “Coal pulverizer startup” also must be constituted before any coal
layer start, referring to the Coal Pulverizing System, Part 6 Auxiliary machinery Part for details.
1.6.8 Boiler trip:
1.6.8.1 In case of MFT, it will interlock the equipment as follows to operate:
(1) Close oil trip valve, oil angle valve, oil filling shut off valve and oil return shut off valve;
(2) All pulverizing systems trip;
(3) Turbine and electric generator trip and bypass shall be put into operation when it is in auto mode;
(4) All primary air fans and seal fans stop;
(5) Sootblower trips and exits automatically;
(6) Automatically close locking valve and governing valve for stage I & II attemperating water of
superheater, and reheater spray locking valve and governing valve;
(7) Automatically open fuel air baffle and auxiliary air baffle of all layers;
(8) Steam-driven feed water pump trips, electrically driven feed water pump automatically starts, adjust the
rotating speed of electrically driven feed pump to make feed pressure a little higher than steam drum
pressure and maintain normal steam drum water level;
(9) Forcefully turn down the opening of induced draft fan static blade to a certain value to maintain the
furnace negative pressure at about - 100Pa;
(10) Adjust the burner swinging angle to horizontal position;
(11) Turbine trips;
(12) Electric generator trips.
1.6.8.2 Causes for boiler trip and first out display system:
For the boiler in operation, if any condition as follows is met, then a command for boiler trip will be
constituted to make MFT operate:
(1) No ignition 60 minutes after purging is finished;
(2) All forced draft fans stopped;
(3) All induced draft fans stopped;
(4) Boiler e-stop button is pressed;
(5) Steam drum water level is high (signal is made with 20s delay after PCV operates);
(6) Steam drum water level is low (signal is made with 20s delay after PCV operates);
(7) Furnace pressure is high;
(8) Furnace pressure is low;
(9) Furnace air quantity is < 25% BMCR
(10) Turbine trips;
(11) Turbine trips when the load is >30%;
(12) Any coal layer has been put into operation, but two primary air fans all stopped;
(13) All air preheaters stopped;
(14) All flames are lost (3s pulse);
When 3/4 oil burners have no flame detected, it is considered that there is no oil flame detected;
When 3/4 coal burners have no flame detected, it is considered that there is no coal flame detected;
When there is no oil flame and no coal flame detected, it is considered that there is no flame detected;
When there is no flame detected but there is the memory of burners being put into operation, loss of all
flame appears. That is no loss of all flame is considered when boiler shutdown.
(15) In case of no coal burner being operated, OFT operates;
(16) Loss of all fuels (5s pulse)
Fuel oil valves of all oil burners or all safety fast vales of fuel oil mains are shut down and all coal
pulverizers stopped. When both coal fuel and oil fuel are lost, it is considered loss of all fuels. This
condition plus “there is the signal of memory of burners being put into operation” makes a complete
condition. This is no loss of all fuels is considered when boiler shutdown.
(17) Flame detection cooling air is lost with a time delay of 20S;
(18) Ignition fails for more than 5 times;
(19) Feed water pumps all trip with a time delay of 2S;
(20) FSSS power failure
There is a “MFT First Out Cause Display” system designed in FSSS that is convenient for the operator to
understand and judge the causes of MFT.
The first cause of MFT shall be displayed on FSSS device correspondingly and the display circuit
corresponding to any other sequent command for boiler trip shall be shut off. Therefore only the first cause
of boiler trip, that is “MFT First-out Cause” can be displayed and kept in memory.
1.6.8.3 Conditions for OFT trip
(1) MFT operates;
(2) OFT command is made on CRT by the operator;
(3) Any oil burner trip valve failed to close;
(4) Oil layer has no flame;
(5) Atomizing pressure is low;
(6) Pressure of oil mains is over low.
In case of the safety fast valve of fuel oil mains not being closed, for the pressure signal of three oil mains,
the logic operation will be made for two selected from three mains and last for 2s.
1.6.9 Interlock control of secondary air baffle:
At different stages of boiler operation, the interlock on-off of the secondary air baffle is controlled by
FSSS, and the analog quantity of baffle and on-off interlock control command of FSSS are controlled and
executed by CCS.
1.6.9.1Control of auxiliary air baffle
A. When the boil MFT, FSSS makes the command of “Open the auxiliary air baffles of all layers with the
max extent of opening in memory and switch to manual position”.
B. When the furnace is purged, the signals of putting all secondary air baffles on Purge position and putting
all over-fire air baffles on Purge position are made to MCS by FSS. MCS is in charge of opening the air
duct and making the air quantity in furnace moderate at 25%~40%BMCR;
C. Coal layer is put into operation and the corresponding air baffle is put into automatic governing
(governed by CCS on the basis of the functional relation between boiler load and wind box/furnace
differential pressure).
1.6.9.2 Control of fuel air baffle
A. When boiler MFT, the command for “Close the fuel air baffles of all layers” is made by FSSS.
B. When there is no MFT, the command for “Close the fuel air baffles of corresponding layer” is made by
FSSS to the corresponding fuel air baffles of tripped-layer thereto.
C. For the coal layer that has been put into operation, the corresponding fuel air baffles are governed by
CSS on the basis of coal feeder speed.
1.7 Hydraulic test of boiler
1.7.1 Pressure and specifications for hydraulic test:
a. After the mounting of all pressure parts of boiler is finished, the hydraulic test shall be done with the
pressure 1.25 times of steam drum designed pressure. Take steam & water system, superheater, economizer
and steam drum of boiler as a whole for hydraulic test, and perform hydraulic test to the reheater
individually with the pressure 1.5 times of the designed inlet pressure of reheated steam.
b. In any case as follows, the overpressure hydraulic test shall be done:
1) Before newly-installed or moved boiler is put into operation.
2) After each overhaul.
3) When the left-unused boiler for more than one year needs to operate again.
4) After the pressure parts of boiler going through heavy repair or replacement, if more than 50% water-
cooled wall pipe is replaced and 100% superheater tube or economizer tube is replaced.
The hydraulic test pressure is as shown in Table 2.1.
Working Pressure Of Hydraulic Test Overpressure Test
Name Unit
Steam drum Pressure Pressure
Primary air system MPa 18.873 18.873 23.59
Test procedures:
a. Inform turbine operator of closing intermediate pressure main steam valve, high-low pressure bypass
valve and high pressure cylinder exhaust check valve to prevent leakage:
b. Open reheater air valve and close all the water drain valves of reheater and reheated steam at turbine
side;
c. Perform water filling from reheater emergency spray type attemperator, after the air valve overflows
continuously, close air valve;
d. Slowly raise the pressure and control pressure raising rate at 0.294Mpa/min, when the pressure rises to
1.0MPa, stop raising pressure temporarily and inform maintenance personnel for check;
e. After completing check, raise pressure at the speed of 0.2Mpa/min to working pressure and inform
maintenance personnel for check;
f. If it needs overpressure test, raise pressure at the speed of 0.098Mpa/min to the overpressure pressure,
keep it for five minutes, and reduce it to the working pressure, maintain the pressure for check;
g. After completing check, open the water drain valve of the reheater to reduce pressure at the decreasing
rate not more than 0.294Mpa/min;
h. When the pressure is down to 0.2MPa, open all furnace roof air valves, when the pressure is zero, close
the air valves, and perform boiler maintenance depending on the actual situation;
i. After hydraulic test, restore all systems to the state before boiler startup, and record test results;
j. The acceptance standard of secondary steam hydraulic test is the same with that of primary steam;
Attentions for hydraulic test:
a. Before hydraulic test, take measures to prevent water from entering the turbine;
b. During primary steam overpressure test, steam drum water gauge shall be paralleled off;
c. During hydraulic test, there should be special-assigned person in charge of air valve and feed water
valve;
d. When the overpressure test pressure exceeds the working pressure, operators should not stay at the
flange, weld junction, valve of pressure parts, etc. places or check equipment, knock at pipes, etc.;
e. During overpressure test, make preparations for emergency pressure relief in advance, if the pressure is
out of limit, take the following measures orderly:
1) Close attemperating water motor-operated valve and governing valve and reduce the speed of feed water
pump scoop tube.
2) Open the continuous blowdown valve wide.
3) Open the water drain valve of superheater steam header.
4) Inform turbine operator of stopping the pump emergently.
f. Increase and decrease of the pressure in hydraulic test should be performed slowly and steadily;
g. Valve test should be performed first for secondary valves and then for primary valves;
h. Before test, motor-operated water drain valve should be in good condition;
1.7.6 Pressure release after hydraulic test:
1) Open the stage I attemperating water discharge valve to reduce pressure.
2) The pressure shall be reduced slowly and evenly at a speed of 0.294MPa/min.
3) When the pressure is reduced to 0.2Mpa, the air valve shall be opened to reduce the steam drum water
level to the lowest visible level, then the economizer recirculation valve shall be opened; each water drain
valve of superheater part shall be opened to try to discharge the water in superheater to the utmost.
4) If water drain is necessary for the water-cooled wall, then each periodic blowdown valve shall be opened
to drain water.
5) When the pressure is released to 0, all water drain valves shall be opened, if the water is tested qualified,
the water shall be discharged to the level for ignition.
6) Details of test results and problems found shall be recorded in the record book.
7) After the hydraulic test is finished, the thermodynamic engineer shall be informed of cleaning the meter
pipe and sampling pipe with chemicals.
1.7.7 Precautions for hydraulic test:
a. All operations during hydraulic test must be under unified command, pressure rise and release shall be
approved by the commander on site.
b. There shall be specially-assigned person in charge of raising pressure and strict precautions shall be
taken against over pressure. When pressure is raised, the indication of steam drum local pressure gauge
shall be taken as standard and there shall be specially-assigned person in charge of monitoring the pressure
indicated by the gauge in the control room. The pressure raising and pressure release operators shall contact
with each frequently, when the difference between raised pressure and released pressure is large, it shall be
checked and judged by the thermodynamic engineer.
c. The pressure raising rate shall be controlled strictly to prevent over pressure. If the pressure exceeds
limit, the following measures may be taken in order:
1) Close attemperating water motor-operated valve and governing valve and reduce the speed of feed water
pump scoop tube.
2) Open the continuous blowdown valve wide.
3) Open the water drain valve of superheater steam header.
4) Inform turbine operator of stopping the pump emergently.
d. The gauge pipe and sampling pipe shall not be cleaned in the process of pressure rise until the hydraulic
test is finished.
e. If only one or two valves are found leaking or not closed tightly in the process of pressure raising or after
up to the rated pressure, such a valve must be operated with the approval of the pressure raising operator in
control room.
f. In the process of pressure rise, the contact and cooperation with the turbine shall be enhanced.
g. For the hydraulic test of boiler proper, attention shall be paid to the pressure of reheater and the pressure
raising and over pressure of reheater shall be prevented.
h. All bulkheads and safety valve padding for hydraulic test shall be removed
i. Because there usually is a time delay between the boiler hydraulic test, the first boiling out and acid
cleaning, the boiler shall be maintained at the state being filled with water and air in shall be avoided
during this time.
j. If filling nitrogen gas, the nitrogen gas shall be drawn into through the exhaust port of steam drum to fill
the boiler to 0.034MPa (gauge pressure).
1.8 Setting of safety valve
a. The safety valve shall be calibrated after boiler installation and overhaul or safety valve inspection and
repair.
b. Safety valve calibration is generally performed in no-load condition, if it needs calibration with load,
sound safety technical measures should be established;
c. The sequence of calibration is first from high pressure to then low pressure, from main steam side and
then reheated steam side so as to calibrate the steam drum, superheater outlet, reheater inlet and outlet
safety valve one by one;
d. Before safety valve calibration, check and test the control loop of electromagnetic relief valve.
1.8.1 Calibrate safety valve with load:
1.8.1.1 Perform check, preparation, ignition, temperature and pressure increase before startup as per
relative specifications and control the furnace outlet flue gas temperature not over 538℃, or diminish the
combustion and reduce the temperature and pressure raising rate;
1.8.1.2 When the boiler pressure rises to 80% of rated pressure (primary steam is about 14.0MPa,
secondary steam is about 3.13MPa), keep the pressure steady, calibrate all the safety valves one by one
with hydraulic device;
1.8.1.3 Set the control switch of electromagnetic relief valve to auto exit state and attach compressing
apparatus to all safety valves except the ones to be calibrated;
1.8.1.4 Raise the pressure at rate of 0.196~0.245MPa per minute to the popping setting pressure of safety
valve, if the safety valve does not pop up, reduce the pressure to 65% of the rated pressure (primary steam
is about 11.31MPa, secondary steam is about 2.5MPa) to make adjustment;
1.8.1.5 When the safety valve operates, record operating pressure, and adjust the combustion to make the
safety valve reseated and record reseating pressure. At the same time strengthen the adjustment of steam
temperature and water level to prevent excessive fluctuation of steam drum water level;
1.8.1.6 After the pressure is down to 80% of boiler rated pressure, calibrate other safety valves with the
same method;
1.8.1.7 If the safety valve operating value is different from the setting value, adjust and calibrate it again till
up to standard;
1.8.1.8 After completing the calibration of the safety valves of steam drum and superheater, calibrate
electromagnetic relief valve;
1.8.1.9 When the steam drum pressure is down to 8~10MPa, calibrate the reheater safety valve through
turbine bypass system, at the same time prevent reheater from overtemperature; After calibrating, safety
valve popping pressure, reseating pressure and valve clack opening height should meet specifications and
be recorded in boiler technical files;
1.8.1.10 The operation of safety valve calibration without load is basically the same with that of safety
valve calibration with load, but the following points shall be paid attention to:
(1) Such measures as preventing steam and water from entering turbine shall be taken for the turbine.
(2) The temperature of superheater and reheater wall shall be monitored not to exceed limit and the flue gas
temperature of low temperature reheater inlet shall be controlled at ≯450℃ and the saturated steam
temperature shall be >≯60℃/h.
1.8.2 Related specifications for safety valve calibration
a. On steam drum and superheater, the total discharge amount of all safety valves should be larger than
boiler maximum continuous evaporation amount;
b. When all safety valves on the boiler are fully open, the boiler overpressure extent should not exceed 6%
of boiler design pressure at any case;
c. Total discharge amount of reheater inlet and outlet safety valve should be larger than the maximum
design flow of reheater;
Safety valve reseating differential pressure is generally 4%-7% of popping pressure, maximally not
exceeding 10% of popping pressure;
1.8.3 Test value of safety valve operating pressure
Name Operating pressure (MPa) Reseating pressure (MPa)
Saturated I safety valve 19.82
Saturated II safety valve 20.22
19.03
Saturated III safety valve 20.41
Last stage superheater outlet I safety valve 18.31 17.58
Last stage superheater outlet II safety valve 18.34 17.61
Superheater outlet PCV valve 18.13 17.77
Reheater inlet I safety valve 4.384 4.209
Reheater inlet II safety valve 4.428 4.251
Reheater inlet III safety valve 4.516 4.335
Reheater outlet I safety valve 4.105 3.941
Reheater outlet II safety valve 4.311 4.138
2.5.32 Contact turbine operator to start steam-driven feed water pump A or B, when one steam-driven feed
water pump is under boiler control, keep the feed water flows of two pumps (one electrically driven feed
pump and steam-driven feed water pump) are the same basically as far as possible and control the steam
drum water level within the normal range.
2.5.33 When the output of pulverizing system A and B both exceed 50%, the pulverizing system C can be
started, at the same time, inform electrostatic precipitation attendant of putting the fourth electric field into
operation. When the superheated steam temperature reaches 530℃,superheated steam temperature control
automation can be put into operation.
2.5.34 When the load rises to 50%, the main steam pressure should reach 12Mpa, the main steam
temperature reaches 538℃, reheated steam temperature reaches over 500℃, report it to shift engineer and
contact the chemical group to check that the silicon content of boiler water is within 0.8mg/L, or stop
pressure rise and run up to clean silicon.
2.5.35 Start the pulverizing system D as required by combustion and run up, withdraw the oil guns on layer
AB according to the needs, at the same time, contact electrostatic precipitation attendant to put
corresponding electric field into operation.
2.5.36 When the load reaches 60%, reheated steam temperature reaches 538℃, put the control for swinging
angle of burner nozzle into auto and the control for reheater emergency water spray into auto, if the second
heat pump is put into operation for the turbine, gradually switch the load of electrically driven feed water
pump to the second steam-driven feed water pump, and then inform turbine operator of make electrically
driven feed water pump no-load for standby and gradually withdraw oil guns.
2.5.37 When the coal amount of each coal feeder is equal, they can be put into auto.
2.5.38 When the load rises to 80%, the main steam pressure should be controlled within 16.6Mpa, the main
steam temperature and reheated steam temperature is the rated value 540℃, at the same time, make an
overall check on the boiler.
2.5.39 After it is checked to be normal and the combustion is steady, perform overall sootblowing for the
furnace and air preheater.
2.5.40 Contact thermodynamic operator to put the controls for boiler feed water, attemperating, air quantity,
pulverizing, furnace negative pressure into auto state, continue to raise load to 80%~100%, at the time , set
the upper limit of the load as 100% (300MW), the lower limit as 80% (240MW), load object instruction as
100% (300MW), rate of load change as 1.6MW/min and throttle pressure as 17.4Mpa, put the fuel main
controller and boiler main controller into auto, and select turbine follow mode on DCS menu.
2.5.41 Start pulverizing system E and F into operation according to load, when putting a coal feeder into
operation, reduce the coal feed amount of other coal feeders until the load and steam pressure rise at rise
rate uniformly, gradually increase the load to 300MW..
2.5.42 After the turbine follow mode is steady, the CC-TF or CC-BF mode can be selected.
Precautions for cold start process:
Monitor the steam drum water level changes closely, when the auto of water level get “Failure”, switch
it to “Manual” immediately, control the water level within ±50mm strictly;
Strictly control the temperature difference between steam drum upper wall and lower wall not over
40℃, if it tends to exceed, it shall reduce the pressure rise rate immediately, after the temperature
difference is up to standard, continue to increase temperature and pressure;
Make a periodic check and record the expansion indications of all parts, if abnormal, find out cause and
then continue to increase the pressure only after removal of the reason.;
Control temperature and pressure rise according to the unit startup curve strictly, saturation temperature
rise rate can not exceed 1.5 ℃/min, closely monitor the temperatures of superheater and reheater tube walls
to prevent overheat;
Strengthen the maintenance and adjustment of the oil gun, guarantee atomization combustion is good,
closely monitor the changes of air preheater outlet gas temperature and exhaust gas temperature to prevent
secondary combustion accident, when the steam temperature and gas temperature increases rapidly, take
corresponding measures immediately, continue to increase the pressure only after it is normal;
2.6 Boiler hot start
2.6.1 Preparations before start
2.6.1.1 Close 5% bypass.
2.6.1.2 If the steam drum pressure is higher than 0.2MPa, all air valves are kept closed.
2.6.1.3 Other preparations are the same with those for cold start.
2.6.2 Boiler ignition and pressure rise
2.6.2.1 The steps of boiler ignition for hot start are the same with those of cold start, take the boiler
minimum pressure after ignition as the starting point, raise temperature and pressure according to hot
startup curve.
2.6.2.2 Open 5% bypass for drainage according to circumstances.
2.6.2.3 After boiler ignition, put high/low pressure bypass into operation. Gradually close 5% bypass.
2.6.2.4 Put a certain quantity of oil guns into operation according to the turbine cylinder temperature,
control steam pressure to correspond to the temperature.
2.6.2.5 During turbine impulse starting, the main steam temperature should have at least 50℃ of superheat
degree, and the reheated steam temperature should approach the main steam temperature as far as possible.
2.6.2.6 During turbine impulse starting, warm up one coal pulverizer.
2.6.2.7 During turbine impulse starting and warming up, boiler should maintain steam pressure and
temperature steady as far as possible.
2.6.3 Boiler run up
2.6.3.1 After unit synchronization, the coal pulverizer should be put into operation, at the same time, one
coal pulverizer should be kept warmed up.
Unit run up should be performed according to boiler hot startup curves, which is similar with that of the
cold start.
2.7 Boiler startup state
1. Cold start (shutdown for over 36 hours): <8 hours;
2. Warm start (shutdown for 10~36 hours): <2.5 hours;
3. Hot start (shutdown for less than 10 hours): <0.75 hours;
4. Synchronize to operate at full load (during hot start): 45 minutes;
5. Control the time of loading down from full load to zero load to 45 minutes.
PART 3 Unit Operation
Chapter 1 Normal Operation Adjustment
1. Tasks of boiler operation adjustment
1.1 Make the boiler capacity meet the demand of unit load.
1.2 Maintain normal steam temperature and pressure.
1.3 Balance water supply to maintain normal steam drum water level.
1.4 Guarantee boiler water and steam quality are up to standard.
1.5 Maintain reasonable combustion, reduce heat loss and increase boiler efficiency.
1.6 Guarantee the safe operation of the unit.
2. Main parameters and limitations of boiler operation control
Attached table 4-1
MCR Rated Variation Alarm Value
No. Name Unit
Cond. Load Range High Low Trip
1 Superheated steam flow T/h 1025 951.8
Superheated steam
2 MPa 17.4 17.28 17.2±0.2
pressure
Superheated steam outlet
3 ℃ 541 541 541±5 546 536
temperature
4 Steam drum pressure MPa 18.75 18.46
5 Reheater inlet pressure MPa 3.917 3.625 4.28
6 Reheater outlet pressure MPa 3.737 3.458 4.5
Reheater inlet
7 ℃ 330.3 322.6 407
temperature
Reheater outlet
8 ℃ 541 541 546~531 546 531
temperature
9 Reheated steam flow t/h 846 785
Low-temperature
10 superheater tube wall ℃ 490
temperature
Division panel wall
11 ℃ 490
temperature
Rear platen tube wall
12 ℃ 575
temperature
Last stage superheater
13 ℃ 585
tube wall temperature
Tube wall temperature of
604
14 division wall reheater ℃
606
and last stage reheater
15 Feed water temperature ℃ 282.6 277.5
Radiant reheater outlet
16 steam temperature not ℃
more than
Rear platen reheater
17 outlet steam temperature ℃
not more than
18 Steam temperature after ℃ 335
left emergency water
spray
Steam temperature after
19 right emergency water ℃ 335
spray
Electric Electric
+240
20 Steam drum water level mm 0 0 ±50 contact contact
-330
I: +120 I:-180
Steam temperature before
21 one-stage attemperating ℃
water not more than
Steam temperature after
22 one-stage attemperating ℃
water not more than
Steam temperature before
second stage
23 ℃
attemperating water not
more than
Steam temperature after
second stage
24 ℃
attemperating water not
more than
+3,240
25 Furnace pressure Pa -100 -100 -100~-50 +980 -980
-2,490
Forced draft fan bearing
26 ℃ >85 100
temperature
Induced draft fan bearing
27 ℃ <60 <60 >85 95
temperature
Pressure difference
between upper bowl and
28 KPa >2.5
lower bowl of coal
pulverizer
Coal pulverizer SA &
29 KPa >2 >2 <2
mill bowl DP
Primary air piping
30 KPa 10 10 -7.472 4.98
pressure
Primary air fan bearing
31 ℃ <70 >85 95
temperature
32 Oxygen content % 4 4~5 3~8
Pressure difference
33 between secondary air Pa 1,000 1,000 380
and furnace
34 Purging air pressure MPa 0.6~0.7 > 0.50
Air pressure for
35 MPa 0.6~0.7 < 0.5
instrument control
Coal pulverizer outlet
36 ℃ 77 77 65~80 >80 93
temperature
3. Steam drum water level adjustment and water level gauge maintenance
3.1 Water level adjustment
3.1.1 Water level should be kept within ±20mm, and its adjustment range is within ±50mm, the upper limit
alarm value is +120mm, low limit alarm value is -180m, when the steam drum water level is higher than
+240 or lower than -330mm, boiler protection MFT operates. During boiler operation, the steam drum
water level should be subject to the display instrument with pressure & temperature compensation in DCS
as standard, check and calibrate the local water level gauge and gauge water level gauge every shift, if the
indications are out of line, check the correctness of the water level gauge, and inform the thermodynamic
operator of dealing with it immediately.
3.1.2 When the boiler load is below 30%, automatic feed water adjusting system is under single impulse
control, when the load is above 30%, it is under three-impulse control, when feed water is in auto state, pay
attention to monitoring the change of boiler water level, when auto fails, immediately switch it to manual
control to maintain the steam drum water level within normal range, attendant should report it to unit
supervisor and shift engineer and contact thermodynamic operator to deal with it immediately.
3.1.3 During switching of manual/auto for water level adjustment, adjust the steam drum water level to “0”
position manually, after it is steady, put feed water to auto to prevent automatic adjusting system from big
disturbance.
3.1.4 When the steam drum water level increases due to manual misadjustment, reduce the water level to
the normal value by opening continuous blowdown valve, periodic blowdown valve and emergency water
discharge valve, etc. wide.
3.1.5 During operation, keep all steam drum water level gauges complete, indication correct and clear,
illumination enough, clean water level gauges according to regular working system to guarantee the TV
monitor for water level in the control room is clear.
3.2 Water level gauge maintenance
3.2.1 Check of water level gauge
When checking the water level, slightly open the water discharge valve, when the water level reaches a
certain hole, immediately close it, the indication for discharged part turns red from green and then recovers
to green quickly after water discharge valve is closed, which can be used to determine the correct water
level. If the liquid level of local water level gauge is found to be stagnated or unclear, wash the water level
gauge.
3.2.2 Put-in of water level gauge in cold state
3.2.2.1 Make sure the water level gauge maintenance is completed and the illumination is complete;
3.2.2.2 Open the primary and secondary steam and water valves of water level gauge, close water discharge
valve;
3.2.2.3 Water level gauge temperature and pressure rise is in line with that of the boiler;
3.2.3 Put-in of water level gauge in hot state
3.2.3.1 Make sure the water level gauge maintenance is complete, and the illumination is complete, steam
and water side valve and water discharge valve are all closed;
3.2.3.2 Slightly open the water discharge valve and fully open primary steam and water valves;
3.2.3.3 Slightly open the secondary valve of steam side and preheat water level gauge for 30 minutes;
3.2.3.4 Close the secondary valve of steam side and water discharge valve;
3.2.3.5 Slightly open the secondary valve of water side and lead hot water to the water level gauge;
3.2.3.6 Open the secondary valve of steam side and lead steam to the water level gauge;
3.2.3.7 Fully open the secondary valves of steam and water sides;
3.2.3.8 Observe that the water level of the gauge should have fluctuation;
3.2.4 Washing of local water level gauge
3.2.4.1 During operation, if the water level gauge is found not clear or does not change, perform washing
work immediately.
3.2.4.2 Close the secondary valve of water side and slightly open the secondary valve of steam side;
3.2.4.3 Slightly open the water discharge valve for warming and close it after 3 minutes;
3.2.4.4 Close the secondary valve of steam side and slightly open the secondary vale of water side, and
close it after the water level increases;
3.2.4.5 Open the water discharge valve to wash for five minutes;
3.2.4.6 Slightly open the secondary valve of steam side to wash for 20 minutes;
3.2.4.7 Slowly close the secondary valve of steam side and water discharge valve;
3.2.4.8 Slightly open the secondary valve of water side and lead hot water to the water level gauge;
3.2.4.9 Slightly open the secondary valve of steam side and lead steam to the water level gauge;
3.2.4.10 Fully open the secondary valves of steam and water sides;
3.2.4.11 Before and after washing steam drum water level gauge, pay attention to the water level situation
in the gauge, the water surface has slight fluctuation, if the water level in the gauge increases slowly, it
indicates there is jam, so it shall be washed again.-
3.2.5 Parallel off of local water gauge
3.2.5.1 During operation, if water level gauge leaks or explode, or the water level gauge mica is not clear
even after being washed, stop the water level gauge immediately and hand it over to the maintenance
personnel for treatment.
3.2.5.1 Close the secondary valve of steam side;
3.2.5.2 Close the secondary valve of water side;
3.2.5.3 Close the primary isolation valves of steam and water sides;
3.2.5.4 Slowly open water discharge valve, and then the water level gauge releases pressure;
3.2.6 Precautions for water level gauge operation
3.2.6.1 Operate the water level gauge slowly and carefully during put-in to avoid excessive thermal shock;
3.2.6.2 During the operation of water level gauge, prevent the outside cold air and cold water from
contacting with glass;
3.2.6.3 When operating water level gauge, stand at the side of water level gauge and use safety appliance;
3.2.6.4 During acid cleaning and overpressure test for the boiler, the local water level gauge should be
paralleled off;
3.2.6.5 During normal operation, the primary and secondary valves of steam and water side of water level
gauge should be fully opened.
4. Combustion adjustment
4.1 Fuel oil adjustment
4.1.1 During boiler normal operation, put boiler-front fuel oil circulation system into operation and make
all oil guns ready for put-in at any time;
4.1.2 The pressure of standby fuel oil should be kept larger than 3.26Mpa;
4.1.3 When the boiler load is lower than 150MW or combustion is unsteady, two coal pulverizers operate
and the coal feed rate of one of them is lower than 50%, and combustion-supporting with oil is needed;
4.1.4 When oil layer starts other than coal layer, the auxiliary air of this layer should be turned down to
below 10%, after the ignition of the first oil gun, open the auxiliary air of this layer to a larger extent
immediately, with opening ≥ 50%, and the differential pressure between big wind box and furnace is > 0.38
kPa;
4.1.5 When the oil gun is put into operation, there should be someone to perform local inspection, if it is
found that atomization is poor, oil does not burn or the oil gun leaks oil (including leak oil into the furnace),
withdraw the oil gun immediately, find the cause and remove it;
4.1.6 After the oil gun is put into operation, the oil mains pressure should be kept above 2.8;
4.1.7 Put-in of electrostatic precipitator
a. When only oil or the mixture of oil and coal from single coal pulverizer is fired, don’t put electrostatic
precipitator into operation;
b. When two coal pulverizers operate and the mixture of oil and coal is used for combustion, put No.
4electric field of electrostatic precipitator into operation;
c. When over three coal pulverizers operate or only coal is used for combustion, put all electrostatic
precipitators into operation;
4.1.8 Put air preheater into operation for sootblowing as long as oil is used for combustion;
4.1.9 When the oil layer is below or in the middle of coal layers, the auxiliary air of this oil layer should be
not too big for easier burning of pulverized coal. When the oil layer is above the coal layer, the auxiliary air
of this oil layer should be increased for the complete combustion of this oil layer;
4.2 Coal adjustment
4.2.1 During normal combustion for boiler, the flame is golden yellow and does not deflect, the combustion
in the furnace is steady, the flame should not wash the water-cooled wall directly, the filling degree of
flame is good, the heat load of the furnace is uniform so that they reduce the heat loss due to incomplete
combustion and improve economical efficiency of the boiler and guarantee the heating surfaces at all levels
of the boiler don’t overheat;
4.2.2 Operators should often make overall checks on the operation situation of the combustion system and
adjust it in time if poor combustion is found. Observe the combustion situation in the furnace and the
ignition distance of pulverized coal through flame television and the flame in the furnace and adjust the fire
point of the fuel and the flame center appropriately;
4.2.3 Adjust forced draft quantity and induced draft quantity and keep the negative pressure between
-50Pa~-100Pa to prevent the upper combustion chamber from smoke and ash. When single side fan
operates, the load depends on air quantity and combustion with oxygen lack is strictly prohibited.
4.2.4 Keep the best proportion of primary air and secondary air to guarantee the oxygen content in the
range of 4%-6%, organize good combustion conditions in the furnace, control the deviations of the furnace
outlet temperature and the flue gas temperatures at both sides of each section of gas pass does not exceed
28℃. When the fuel ash fusion point is too low or the mixture of oil and coal is used for combustion,
increase the oxygen content properly to prevent formation of slag;
4.2.5 After the burner is put into operation, check if the ignition situation is good, adjust the air quantity in
time to prevent funnel from black smoke. During combustion adjustment, pay attention to the temperature
change of each section of working medium and prevent coking. If coking, remove it in time, and perform
sootblowing for the water-cooled wall regularly, when the combustion is not steady, it is prohibited to
perform sootblowing for the water-cooled wall and remove coke. When coking is serious, reduce boiler
load;
4.2.6 When the load changes, if the extent is not big, adjust it by changing the coal feeder rotating speed, if
the extent is big, adjust it by starting and stopping pulverizing system; when the load is increased, first
increase air quantity and then the coal feed amount, when the load is reduced, first reduce coal feed
amount, and then the air quantity to guarantee complete combustion;
4.2.7 Master the combustion characteristics of this boiler, set the preact of each coal feeder during load
adjustment to prevent steam temperature and steam pressure from large fluctuation, when the load is lower
than 150MW or combustion is unstable, the oil gun should be put into operation to make combustion
stable;
4.2.8 In order to make sure the economical operation of the boiler, keep fineness of pulverized coal
qualified and make sampling analysis for fly ash and the slag at furnace bottom, make comparison and
adjustment in time;
4.2.9 During boiler operation, know about the chemical analysis for the categories of coal and fuel oil,
and adjust operating conditions in time according to the characteristics of fuel;
4.2.10 In order to keep boiler combustion stable and increase combustion efficiency, reduce air leakage as
much as possible. All observation holes, coke removal gate and manhole, etc. should be tightly closed, if
there is air leakage, stop it in time;
4.2.11 Change the flame center position through swing burner or changing the opening of the secondary air
damper according to the steam temperature and steam pressure to guarantee stable combustion, steam
temperature and steam pressure;
4.2.12 When unstable combustion happens due to any reason, put oil gun into operation in time to make
combustion stable and find out the cause and eliminate the factors of unstable combustion. If fire extinction
happens, it is prohibited to supply fuel to the furnace to avoid boiler explosion;
4.3 Air quantity adjustment
4.3.1 During boiler operation, adjust the air quantity according to the change of fuel amount in time and
keep the oxygen content of economizer outlet flue gas is 3.3~4.2%.
4.3.2 Under high load, properly reduce excess air coefficient to keep the oxygen content of flue gas at the
lower limit of the specified value; under low load, properly increase excess air coefficient to keep the
oxygen content at the upper limit of the specified value;
4.3.3 Under the conditions of low load, unstable combustion or relatively high moisture in the coal,
properly reduce primary air speed and turn down fuel air to make fire point in advance, when the load is
≥250MW, the coal quality is good and the combustion is stable, increase primary air speed and turn up the
fuel air for convenience of complete combustion and preventing water-cooled wall from coking;
5. Adjustment of boiler load and steam pressure
5.1 When the main steam pressure changes, operators should judge the cause of change in time and change
fuel amount according to the speed of steam pressure change; adjust fuel amount, as well as the primary air
quantity and secondary air quantity to keep the combustion stable and complete.
5.2 During combustion adjustment, guarantee the main steam pressure of boiler side is ≤17.3Mpa, reheated
steam pressure is ≤3.23Mpa, and the pressures at velocity stage of turbine side, high pressure heater and
deaerator should not exceed their rated values.
5.3 When the main steam pressure is higher than 18.02Mpa and PCV fails to operate, immediately open
PCV manually, if the steam pressure falls slightly, close PCV.
5.4 When the steam pressure is very low and it fails to recover in a short time after intensified combustion,
contact turbine operator to reduce partial load, and then recover the load after the steam pressure increases,.
When the steam pressure is lower than 14.9Mpa (turbine side), reduce load rapidly to maintain the main
steam pressure more than 14.9Mpa. (except sliding pressure operation-
5.5When the boiler load is within 117~233MW, sliding pressure operation can be adopted. During sliding
pressure operation, the load variation speed can not exceed 10MW/min.
6. Steam temperature adjustment
During normal operation, the main steam and reheated steam temperature should be kept at 541±5℃, when
t combustion conditions change, the main steam and reheated steam temperature should be adjusted within
the allowable value, and the differences of the main steam temperatures and the reheated steam
temperatures at both side should be lower than 14℃.
6.1 Main steam temperature adjustment
6.1.1 During constant pressure operation above 200MW and sliding pressure operation above 166MW, the
main steam temperature should be kept at 541℃ with normal variation range of 541±5℃.
6.1.2 Boiler steam temperature is attempered at two stages. The first stage attemperator is used to adjust the
steam temperature at division wall inlet to keep it at 409℃; the second stage attemperator is used to adjust
the steam temperature at last stage superheater inlet to keep it at 505℃, the proportion of spray water
quantities of the first and second attemperating water is 70% and 30%.
6.1.3 When the coal pulverizer or coal feeder is started by ignition in hot start, the steam temperature
increases rapidly, when the load is lower than 45MW, the motor-operated valve of attemperating water will
automatically lock and can not be opened, which should be paid more attention. The second coal pulverizer
should start after the load is higher than 40MW.
6.1.4 During normal operation, after stopping the high pressure heater, the steam temperature drops first
and then rises rapidly, at the time, open attemperating water valve wide, put water-cooled wall sootblowing
into operation, when necessary, open wide turbine governing valve to reduce combustion.
6.1.5 If the attemperating water governing valve is almost fully open and the steam temperature is still
high, find the cause and remove it, at the same time, reduce the steam temperature with the following
methods:
6.1.5.1 Perform partial sootblowing for the water-cooled wall;
6.1.5.2 Adjust burner swinging angle downwards;
6.1.5.3 Turn down the auxiliary air of lowest layer and turn up the auxiliary air of the uppermost layer;
increase the burner load of lower layer, at the same time, reduce the burner load of the upper layer, and
lower flame center;
6.1.5.4 Turn down total air quantity and the air quantity for fuel;
6.1.5.5 Open the turbine high pressure governing valve wide;
6.1.6 When attemperators are all withdrawn and the steam temperature is still low, take the following
method:
6.1.6.1 Perform partial sootblowing for superheater;
6.1.6.2 Adjust f burner swinging angle upwards;
6.1.6.3 Turn up the auxiliary air of the lowest layer and turn down the auxiliary air of the uppermost layer;
reduce the burner load of the lower layer, at the same time, increase the burner load of the upper layer, and
upraise flame center;
6.1.6.4 Increase total air quantity and the air quantity for fuel;
6.1.6.5 Turn down the turbine high pressure governing valve;
6.2 Reheated steam temperature adjustment
6.2.1 During sliding pressure operation above166MW and constant pressure operation above 200MW, the
steam temperature should be kept at 540℃ with normal variation range of 530~545℃.
6.2.2 Reheated steam temperature adjustment adopts the mode of swinging nozzle angle up and down, and
it don’t use spray attemperating during normal operation. When the reheated steam temperature is out of
limit, and it is still very high after the nozzle is swung and water-cooled wall sootblowing is performed,
adopt spray attemperating, when the reheated steam temperature returns to normal, stop spray
attemperating.
6.2.3 Precautions for steam temperature adjustment:
6.2.3.1 The steam superheat degree should be guaranteed not lower than 50℃ after attemperating in any
case;
6.2.3.2 For reheated steam temperature adjustment, it shall guarantee the outlet temperature is not out of
limit, as well as the difference of the outlet steam temperatures at side A and B not more than 14℃;
6.2.3.3 Be careful about the adjustment with attemperating water adjustment under low load operation and
make sure the superheat degree of steam temperature after attemperating;
6.2.3.4 During boiler operation, the combustion adjustment, start/stop of the burner, start/stop of induced
draft fan and pulverizing system, sootblowing, slag & coke removal, etc., as well as start/stop of HP heater
will result in the changes of superheated steam temperature and reheated steam temperature, therefore,
operators should analyze the cause and direction of steam temperature change and make corresponding
adjustment in time.
7. Boiler sootblowing
7.1 Perform boiler sootblowing only after getting permission from the chief shift engineer, during boiler
sootblowing, increase the furnace negative pressure properly to keep combustion stable, at the same time
pay attention to the change of steam parameters.
7.2 Sootblowing steam parameters
Attached table 4-2
Item Pressure Temperature Steam Source
Name
Boiler proper 2.5MPa after pressure relief 334℃ after pressure relief Division wall superheater
sootblowing station station outlet
Boiler proper 1.0~1.5MPa < 250℃ Rear platen superheater
sootblower outlet (it is auxiliary steam
at startup )
Air preheater 2.5MPa after pressure relief 421℃ after pressure relief
sootblowing station station
Air preheater 1.0~1.5MPa < 350℃
sootblower
7.3 Conditions required for sootblowing
7.3.1 Boiler operation condition is normal, combustion is stable, and there is no other major operation.
7.3.2 The unit load is higher than 60%, and primary and secondary steam temperatures are stable.
7.3.3 Furnace negative pressure is normal, and the induced draft fan has adequate allowance.
7.3.4 Compressed air system is already normally put into operation.
7.3.5 The sootblowing pressure governing valve, program-controlled device signal and alarm device meet
put-in conditions.
7.4 Stop sootblowing immediately for any one of the following states:
7.4.1 The boiler operation condition is abnormal, combustion is unstable or the unit load is lower than 60%;
7.4.2 The unit and system have an accident;
7.4.3 Sootblowing system or sootblowing equipment goes wrong or is damaged;
7.4.4 Combustion chamber negative pressure can not be maintained or decoking can not be performed;
7.4.5 Steam (sootblowing) pressure is lower than 0.8Mpa or steam flow is lower than 91%.
7.5 Sootblowing procedure
7.5.1 Regardless of performing sootblowing manually or automatically, it shall be done for each part in
sequence as follows: air preheater, water-cooled wall (furnace chamber), flue gas pass, and then air
preheater again. (that is: air preheater → furnace chamber → flue gas pass →air preheater.)
7.5.2 For the sootblowing of furnace chamber sootblower, perform it from top to bottom to avoid cross ash
depositing of heating surface, that is: fifth layer →fourth layer→ third layer→ second layer→ first layer, on
each layer, blow the front and rear wall first and then blow the side walls A and B, use one sootblower for
front/rear wall or side wall A/B respectively to perform sootblowing in pairs.
7.5.3 During flue gas pass sootblowing, perform in pairs on side A/B according to the flue gas flow
direction, (the order is: division wall bottom at the furnace outlet, rear platen, platen reheater, last stage
reheater, last stage superheater, low temperature superheater, economizer).
7.6 Sootblowing period:
7.6.1 When the boiler operates normally, perform it every shift; (eight hours)
7.6.2 For the heating surface only which ash deposits easily, perform sootblowing according to its deposit
extent;
7.6.3 When boiler starts normally and before the boiler stops, perform an overall sootblowing for all
heating surfaces;
7.6.4 If the superheat and reheated steam temperatures are high, increase the sootblowing times for furnace;
7.6.5 If the superheat and reheated steam temperatures are low, increase the sootblowing times for
superheater and reheater furnace;
7.7 Precautions for sootblowing:
7.7.1 During the operation of sootblower, pay attention to protecting the furnace negative pressure and
sootblowing parameter to meet requirement, and do not perform sootblowing without steam;
7.7.2 When putting sootblower into operation, perform sootblowing according to the specified sootblowing
procedure, during manual sootblowing, the number of sootblowers can not exceed two sets in operation;
7.7.3 During sootblowing, don’t open the inspection hole to observe combustion and don’t remove coke or
manually remove ash;
7.7.4 When perform sootblowing, make an overall site check on the exit position of each sootblower;
7.7.5 In the process of sootblowing, in case of soot lance jam, overload, overcurrent trip, etc. malfunctions,
timely contact maintenance personnel to remove it, for the soot lance with the fault that can not be removed
timely, swing out it manually and timely contact for defects elimination;
8. Boiler blowdown
8.1 Continuous blowdown: according to chemical requirements, adjust the opening of continuous
blowdown adjusting valve opening in time, control blowdown rate to ensure the boiler water quality.
8.2 Periodic blowdown: the chief shift engineer shall perform program-controlled blowdown for the
downcomer periodically under the supervision of chemical operators according to chemical requirements,
when the boiler water quality worsens, perform manual blowdown for water-cooled wall lower header
when reducing the load to 150MW~180MW, and in normal operation, perform periodic blowdown
according to the normal regular work.
8.2.1 During blowdown, strength monitoring to the water level.
8.2.2 Fully open the primary blowdown valve of water-cooled wall lower header, slightly open the
secondary valve for warming.
8.2.3When there is no water shocking sound in blowdown pipe, fully open secondary blowdown valve, and
after blowdown for 30s, close the secondary valve and then primary valve.
8.2.4 Perform blowdown for the four blowdown loops successively.
8.3 Precautions for periodic blowdown:
8.3.1 Before blowdown, check the blowdown system; when the blowdown system is going through
inspection and repair, do not perform blowdown;
8.3.2 During blowdown, the pipe should not have violent vibration, strength warming work when the
vibration is big;
8.3.3 The blowdown should be performed in proper order, do not open two primary valves for blowdown at
the same time;
8.3.4 During blowdown, operators must wear protective appliance, when the blowdown device is defective
or work site and passage have no illumination, do not perform blowdown;
8.3.5 Open blowdown valve with special wrench, do not cover the wrench with bushing to help start
blowdown valve, during boiler operation, do not check the primary blowdown valve;
8.3.6 When finishing blowdown, fully check that the blowdown valve is in close position and there is no
leakage, report to the chief shift engineer after blowdown;
8.3.7 In the process of periodic blowdown, if the unit has abnormal situation or blowdown system goes
wrong, stop blowdown immediately;
PART 4 Boiler Shutdown
Speed reducer thrust pad is No alarm when oil supply is few Check the alarm device
12
damaged or interrupts; regularly;
Water mix into the oil of oil Replace with qualified oil and
cooler, lubricating oil is bearing bush.
unqualified and deteriorates due
to long time use.
2.5.6 Coal feeder trip
2.5.6.1 Phenomenon of coal feeder trip
1) Sound and light signal of coal feeder trip is made, state of control switch displayed on CRT picture is not
corresponding, and current turns to zero.
2) Coal feed of coal feeder displays zero.
3) Coal pulverizer outlet temperature rises and current decreases.
4) Boiler combustion is instable and steam pressure decreases (except in case of MFT and RB).
2.5.6.2 Causes for coal feeder trip
1) When MFT, MTR (coal pulverizer trips and relay operates) or RB occurs
2) Coal pulverizer is stopped.
3) No coal on belt.
4) Coal feeder is operating and the startup conditions of coal feeder are lost.
2.5.6.3 Handling of coal feeder trip
1) Find out the causes for trip, and put the coal feeder into operation soon after removing the fault.
2) Properly reduce the boiler load according to the steam pressure.
3) If it cannot recover in a short time, switch into standby coal pulverizer operating.
2.5.7 Primary air fan trip
2.5.7 Phenomenon of primary air fan trip
1) Current of primary air fan turns to zero, and air fan stops operation, the sound and light signal is made,
and the state displayed on CRT picture is not corresponding.
2) Primary air pressure decreases sharply, and the alarm of low primary air pressure is made.
3) It may result in coal pulverizer trip.
4) Boiler fire extinction (when two primary air fan trip and no oil for supporting combustion).
2.5.7.2 Causes for Primary air fan trip
1) MFT operates.
2) Primary air fan protection operates.
2.5.7.3 Handling of primary air fan trip
1) Turn the switch of tripped air fan to the stop position.
2) When one primary air fan trips, there will be 50%RB, some coal pulverizer trip and at the same time
some oil guns put into operation automatically, which may result in all operating coal pulverizers trip due
to low primary air pressure.
3) When two primary air fans trip at the same time, all coal pulverizers will trip, and boiler fire is
extinguished, and MFT operates, here such a case shall be handled as per the specification for MFT
operating.
4) After one primary air fan trips, it shall close its inlet damper immediately, then open wide the inlet
damper of the operating primary air fan, and find out causes quickly to conduct handling, and after fault is
removed, restart it immediately, resume normal operation of coal pulverizer, and purge the coal pulverizer
prepared for standby after trip in time.
2.5.8 Seal fan trip
2.5.8.1 Phenomenon of seal fan trip
1) The seal fan trips, the sound and light signal is made, the state displayed on CRT picture is not
corresponding.
2) Standby seal fan starts automatically.
3) Sealing air pressure decreases instantaneously.
2.5.8.2 Causes for seal fan trip
1) Fault in motor or lose of power supply
2) Fault in mechanical part resulting in overcurrent.
2.5.8.3 Handling of seal fan trip
1) Turn the switch of tripped fan to the stop position.
2) Contact maintenance personnel to find out causes and handle.
3) Check if the sealing air pressure of coal pulverizer is normal.
2.5.9 Common fault, causes and handling for thin oil station are as follows:
Fault Causes Handling
1. No cooling water 1. Supply cooling water
Lubricating 2. Cooling water is too little. 2. Increase cooling water quantity
oil 3. Cooler has air inside. 3. Cooler discharges air
temperature is 4. Cooler is too dirty 4. Replace cooler, and wash or replace the dirty
over high piping and parts
h. The rotation direction of motor is correct and the earth wire of motor casing is reliable.
i. Different auxiliary machinery shall be checked according to their specific requirements and shall not be
started until the conditions availability are confirmed; the standby auxiliary machinery shall be in the
condition of being ready to be started.
1.1.2 Auxiliary machinery startup
a. The auxiliary machinery shall be energized after all checks are finished.
b. When the auxiliary machinery start, the current return period and indicated current value shall be
monitored, the state on CRT corresponds and the red and green indicator lamp on backup panel indicate
correctly.
c. Two set of 6.6kV equipment shall not be started at the same time and the approval from shift engineer or
unit supervisor shall be obtained before startup. There shall be a specially-assigned person to monitor the
equipment locally, if any problem found, he shall stop the equipment by the E-stop button promptly.
d. Related auxiliary machinery are not allowed to be started with load.
e. When the auxiliary machinery start, in the case of fault trip, the auxiliary machinery shall not be restarted
until the causes are found and removed.
f. The auxiliary machinery can be hot started once and cold started continuously not over two times. In case
of trouble, the number of times of start can be once more (excluding winding type). If continuous startup is
necessary, the interval between each start shall not be less than 30minutes.
g. If the auxiliary machinery are started for emergency or thermodynamic and electric interlock operate to
put in automatically, their operation condition shall be checked on site after starting.
1.1.3 Operation maintenance of auxiliary machinery
a. The patrol and inspection system shall be executed strictly in operation, operation shall be inspected
conscientiously and overall, if any abnormal, it shall be handled in time.
b. The auxiliary machinery in operation shall meet the following requirements:
1) Auxiliary machinery and its motor operates stably, without abnormal sound, without leak and attrition
phenomenon.
2) Oil level, temperature, pressure and flow are normal, oil level indicator is clear and oil quality is good.
3) Each bearing is lubricated well and sealing of shaft seals is good.
4) Cooling water is sufficient and water drain is unobstructed.
5) All fasteners and connecting pieces of equipment are not lose and do not drop out. Monitoring and
protective devices operate normally.
6) The temperature, vibration and run-off displacement of each part of auxiliary machinery shall meet the
following requirements:
Bearing oil temperature of coal pulverizer gear box, induced draft fan, forced draft fan and air preheater
shall be ≯60℃-
Sliding bearing temperature shall be ≯70℃, and rolling bearing temperature shall be >≯80℃.
The vibration of rotary equipment shall not exceed the following specified value: as shown in Table 6.1
Table 6.1
Rotating Speed (r/min) 3,000 below 1,500 below 1,000 below 750 below
The max vibration of induced and forced draft fan does not exceed the numerical values as shown in Table
6.2
Table 6.2
Rotating Speed (r/min) 1,500 below 1,000 below
a. In case of any fault as follows, the auxiliary machinery shall be stopped for emergency:
1) When the motor or auxiliary machinery has violent vibration, run-off displacement exceeds specified
value and there is a danger of damaging equipment.
2) The bearing temperature rises abruptly and exceeds the specified value.
3) The motor temperature rises to over specified value or there is smoke belching or fire catching.
4) The rotor and casing of auxiliary machinery are attrited or impacted seriously.
5) The auxiliary machinery does not stop running when up to the protective fixed value and specified time
delay.
6) There are other faults that may endanger human body or damage equipment.
b. For important auxiliary machinery, besides that they shall be stopped immediately in case of fault that
may injure human body and damage equipment, generally the standby auxiliary machinery shall be started
before the faulted auxiliary machinery is stopped.
Attached table:
Motor power table
No. Name Model Voltage Rotating Power Current Torque Qty
V speed KW A N-M
RPM
1 Long retractable sootblower 380 1400 1.1 2.85 7.6 24
2 Semi-retractable sootblower 380 1400 1.1 2.85 7.6 6
3 Furnace sootblower 380 1400 0.18 0.65 1.24 80
4 Flue gas temperature probe 380 1400 1.1 15 7.6 2
5 Main motor of the air 380 970 7.5 17 2
preheater
6 Auxiliary motor of the air 380 970 7.5 17 2
preheater
7 Air preheater sootblower 380 1400 1.1 15 7.6 2
8 Electric fitting for closing 380 605/90° 1.1 5800 6
damper of flue gas pass at
preheater inlet
9 Governing valve for steam 380 0.75 3.5 1
drum’s continuous blowdown
10 First stage attemperating 380 1600 0.33 0.85 800 1
water electric stop valve of
superheater
11 Second stage attemperating 380 1600 0.22 0.59 500 2
water electric stop valve of
superheater
12 Attemperating water electric 380 1600 0.22 0.59 500 2
stop valve of reheater
13 Electric actuated emergency 380 1600 0.33 0.85 800 2
water discharge valve of
steam drum
14 Periodic blowdown electric 380 1600 0.22 0.59 500 8
stop valve of centralized
downcorner
15 Drain electric stop valve of 380 1600 0.22 0.59 500 4
tail ring header
16 Electric stop valve 380 20 1.1 3.4 300 3
DN40, PN32
17 Electric stop valve 380 20 1.5 4.1 450 2
DN65, PN32
18 Electric stop valve DN50, 380 20 1.1 3.4 300 4
PN32
19 Electric stop valve DN100, 380 20 7.5 17 1800 2
PN32
20 Electric stop valve DN125, 380 20 7.5 17 1800 1
PN32
21 Motor-operated gate valve 380 20 7.5 17 1800 1
DN300, PN32
22 First stage attemperating 380 22 0.23 1.5 170 1
water governing valve of
superheater
23 Second stage attemperating 380 22 0.10 1.5 75 2
water governing valve of
superheater
24 Spray water governing valve 380 22 0.10 1.5 75 2
of reheater
25 Governing vale of feed water 380 22 0.81 3.9 597 1
bypass
Equipment water consumption table