Stone Columns
Stone Columns
3
Applicability of Deep Vibro Techniques
Transition
Clay Silt Sand Zone Gravel Stones
100 100
80 80
Percentage Passing
60 60
40 40
20 20
4
Grain Size [mm]
Concept of Vibro Techniques
Before
h After
6
Construction Sequence – Dry Bottom Feed Method
7
Construction Sequence – Wet Top Feed Method
8
Design Methodology (Priebe’s)
9
Area Replacement Ratio (ARR) - Typical
• Key index for effectiveness of improvement
• Area Replacement Ratio (ARR) = Area of column, Ac/Area of grid, A
Example: For 2.2m x 2.2m typical grid (Area of grid, A = 4.84 m2),
• Area of 1.0m diameter column, Ac = 0.785 m2 ARR ~ 16%
10
Effects of Ground Improvement
“Islands” of densified soil surrounding the probe
Stiff columns
11
Advantages of Vibro Sand/Stone Columns
Robust – Large column of compacted stone/sand
12
QA/QC
Before stone column work
• Pre-treatment test
• Existing soil strength
• Treatment depth
During stone column work
• Real-time monitoring
• Stone Consumption
• Daily check of column quality
After stone column work
• Check Installation records
• Expose column head
• Load Test
13
Real Time Quality Record
14