0 - Simulator 2 - PM Questions - 1
0 - Simulator 2 - PM Questions - 1
0 - Simulator 2 - PM Questions - 1
A. Formal
B. Expert
C. Referent
D. Reward
Question 2:
A. Laissez-faire
B. Servant leader
C. Innovative
D. Interactional
Question 3:
A. Legitimate
B. Situational
C. Charismatic
D. Punitive
Question 8:
A. You must do what I say because I'm the project manager and
I'm accountable on project success
B. If you don't achieve your target, you will not get the annual
bonus
C. You must comply with HR rules and come to work on time
D. If you face this type of problems in your work, solve it like this,
I have been solving this type of problems the same way over
the last three years and never failed
Question 9:
A. Waterfall
B. Iterative
C. Incremental
D. Adaptive
Question 13:
A. A portfolio
B. A program
C. A project
D. An enterprise environmental factor
Question 14:
A. Business case
B. Benefits management plan
C. Project charter
D. Project management plan
Question 17:
A. Project C
B. Project B
C. Project D
D. Project A
Question 18:
A. Stage gate
B. Phase review
C. Kill point
D. Transition phase
Question 20:
A. Waterfall
B. Iterative
C. Incremental
D. Adaptive
Question 22:
A. Tom
B. Frank
C. Ronald
D. None of them
Question 27:
A. Unaware
B. Resistant
C. Neutral
D. Supportive
Question 32:
A. Show him the project charter so that he knows that you are
in charge of the project
B. Work with him to understand the current requirements and
determine if he has new ones to add to the project
C. Do nothing
D. Add him to the communications management plan
Question 34:
A. Power/interest grid
B. Power/influence grid
C. Power/interest and power/influence grids
D. Stakeholder cube
Question 35:
A. Upward
B. Downward
C. Outward
D. Sideward
Question 37:
A. Identify Stakeholders
B. Plan Stakeholder Engagement
C. Manage Stakeholders Engagement
D. Direct and Manage Project Work
Question 38:
A. Power/interest grid
B. Power/influence grid
C. Impact/influence grid
D. Salience model
Question 41:
A. AC
B. EV
C. CV
D. VAC
Question 44:
A. Exact 50 %
B. Less than 50%
C. Over 50%
D. There is not enough information
Question 48:
A. You should estimate the costs during project initiating and ask
customer to confirm these estimates
B. You should estimate the costs during project planning and re-
estimate before executing each activity
C. You should estimate the costs during project executing and
then check costs against the baseline
D. You should estimate the costs at the beginning of the project
and then check costs against the baseline
Question 49:
You are working for a major pipeline project. The project is very
important and highly visible for your organization. It is performed
using 32 human resources. As you review the project results,
you notice that the value of the work accomplished is $1,200,000
at the last reporting point. You know the schedule performance is
good, since your SPI is 1.2 while you have spent $1,050,000 to
this point, what are the CPI, and the schedule and cost
variances?
A. 1
B. 0
C. PV
D. EV
Question 51:
A. Parametric Estimating
B. Analogous Estimating
C. Triangular distribution
D. Bottom-up Estimating
Question 54:
A. Direct costs
B. Indirect costs
C. Fixed costs
D. Variable costs
Question 57:
A. What to purchase
B. Rough order of magnitude estimates
C. Constraints and assumptions
D. Initial project organization
Question 69:
A new team member asks the project manager about the correct
order of actions that will be taken during the Close Project or
Phase process. What would be his answer?
A. Facilitation
B. Brainstorming
C. Expert Judgment
D. Focus groups
Question 76:
A. Integration Management
B. Stakeholder Management
C. Risk Management
D. Scope Management
Question 79:
A. Corrective action
B. Preventive action
C. Defect repair
D. Updates
Question 80:
A. Risk register
B. Issue log
C. Change management plan
D. Change log
Question 82:
The hardware design phase has reached its end. This phase is a
part of a three-phase sequential project. All of the following
actions should be performed before announcing that the design
phase has been formally closed except:
C. Making sure that resources are available for the next phase
D. Finalizing all open claims with the contracted sellers in this
phase
Question 83:
You are a project manager for a new billing system project. Your
client is the finance manager in your organization. The client has
agreed on the project scope at the beginning of the project, but
when the client validates the deliverables during the Validate
Scope process, he comes up with features that he would like to
add into the product. You are working with the client to find the
missing requirements in the planning stages of the project and
how to plan better in the future. Which of the following
statements best describes the current situation?
A. Inspection
B. Scope creep
C. Alternatives analysis
D. Control Quality process
Question 90:
You have just started work on the project scope statement. You
are analyzing the expected deliverables when you discover that
one of them could be delivered in three different ways. You
select the best method for creating that deliverable. What is the
best way to describe what you are doing?
A. Alternatives analysis
B. Decomposition
C. Define Scope process
D. Validate Scope process
Question 95:
Which of the following is not true about project scope and project
life cycle?
A. Deliverable
B. Control Account
C. Product Backlog
D. Work Package
Question 97:
A. Sergio
B. Michael
C. Mario
D. Project team members
Question 98:
The project was reaching its completion phase, when the project
manager had a meeting with the customer to gain acceptance for
the final product of the project. The project manager is worried
that the customer may not be satisfied with the product of the
project and may request some modifications, these
modifications-if required- may affect one or more of the project
objectives. Which document should he consult to know the
project objectives that will be affected by the required
modifications by the customer?
A. Crash activity C
B. Move more resources to activity B.
C. Fast track activities E and F
D. Crash activity H.
Question 102:
A. Decomposition
B. Dependency Determination
C. Rolling Wave Planning
D. Precedence Diagramming Method
Question 115:
A. Parametric Estimating
B. Analogous Estimating
C. Expert Judgment
D. Three Points Estimating
Question 120:
A. Checklists
B. Check sheets
C. Work performance information
D. Work performance data
Question 129:
C. Prevention
D. Statistical sampling
Question 130:
A. Cost of conformance
B. Cost of non-conformance
C. Cost of prevention
D. Cost of inspection
Question 131:
A. Matrix diagrams
B. Cause- and- effect diagram
C. Scatter diagram
D. Histogram
Question 132:
A. Audits
B. Alternatives analysis
C. Root cause analysis (RCA)
D. Process analysis
Question 134:
A. Control Resources
B. Control Quality
C. Manage Quality
D. Control Scope
Question 144:
A. Resource Requirements
B. RACI chart
C. Responsibility Assignment Matrix
D. Resources Management Plan
Question 146:
Stephen and Ann are two stakeholders are discussing about the
impact of the project on their departments. They both were not
satisfied with the impacts. Stephen asked Ann if the project is on
budget. Ann informed him that CPI is 1.03. Stephen and Ann
agreed that they are not sure that the project manager knows
their concerns. The project manager heard this conversation
between them. What is the best thing he can do?
A. Send both stakeholders a copy of the issue log and ask for
additional comments.
B. Ask both stakeholders to direct any questions to the project
manager in writing.
C. Make a presentation to all the stakeholders regarding the
status of the project.
D. Arrange a meeting with both stakeholders to allow them to
voice any concerns they may have.
Question 154:
What is the best method to report to the project team the status
of the project schedule during project executing?
A.
Milestone chart
B.
Network diagram
C. Activity
list
D.
Bar chart
Question 155:
A risk has remained even after you implement all of your risk
response strategies. What kind of risk is this and what should
you do about it?
You are a project manager for a data center upgrade project. The
data center uses old systems and your project was to upgrade to
a new system. The project was planned to be in winter were
heavy rains are likely to happen. The heavy rains caused power
outages just when the project was near completion. When the
power was restored, all of the project customer’s data were lost
with no way of retrieving them. What should have been done to
prevent this problem?
A. Schedule the installation in summer.
B. Plan for a reserve fund.
C. Insure against this risk.
D. Monitor the weather and have a contingency plan.
Question 173:
You are the project manager for a software project. You created
a Risk Management Plan, identified number of risks with project
team and stakeholders. The following figure shows the
probability and impact matrix you created. If Risk C happens,
how much will be left in the contingency reserve?
Larger image
A.
125,950$
B.
156,750$
C. 288,000
$
D.
318,800$
Question 178:
You are the project manager for a software project. You created
a Risk Management Plan, identified number of risks with project
team and stakeholders. The following figure shows the
probability and impact matrix you created. If risk B occured, what
should the project manager do?
Larger image
A.
Monitor Risks
B.
Plan Risk Responses
C. Implement
Risk Responses
D.
Plan Risk Management
Question 181: What is the purpose of this chart?
A. Risks prioritization
B. Finding root causes of potential risks
C. Determining which individual project risks has the most
potential impact on project outcomes
D. Evaluating the overall project risk
Question 182: