Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Izenbridge - Project Management Professionals (PMP) ® Exam Prep Course Based On Pmbok Ver. 6

Download as pdf or txt
Download as pdf or txt
You are on page 1of 71

iZenBridge -

Project Management
Professionals (PMP ) ®
Exam Prep Course
Based on PMBOK Ver. 6

PMP is a registered trademark of the


Project Management Institute, Inc.
@2017|http://izenbridge.com/|CONFIDENTIAL
1
PMBOK 6:

@2017|http://izenbridge.com/|CONFIDENTIAL 2
Agenda : Lessons – PMBOK
Ver. 6

Disclaimer : All references , Definitions and figures have been taken from
PMBOK Guide Version 6, by PMI 2017

@2017|http://izenbridge.com/|CONFIDENTIAL 3
Lessons – PMBOK Ver. 6
 Part 1 : Project Management Body of knowledge
(PMBOK) Ver. 6
1. Introduction
2. The Environment in which projects operate
3. The Role of the Project Manager
4. Project Integration Management
5. Project Scope Management
6. Project Schedule Management
7. Project Cost Management
8. Project Quality Management
9. Project Resource Management
10. Project Communication Management
11. Project Risk Management
12. Project Procurement Management
13. Project Stakeholder Management

@2017|http://izenbridge.com/|CONFIDENTIAL 4
Lesson 1: Introduction

@2017|http://izenbridge.com/|CONFIDENTIAL 5
Lesson 1: Introduction – Ageda

1 1.1 Overview and Purpose of this guide

1.2 Foundational Elements :


2 a. Projects, Programs, Portfolio,
b. Organizational Project Management ,
c. Components of Guide,
d. Tailoring & Business Documents

@2017|http://izenbridge.com/|CONFIDENTIAL 6
1.1 Overview and Purpose of PMBOK Guide Ver 6 :

Review “The Guide to the Project Management Body of Knowledge –

PMBOK Ver. 6”

◦ Understand key defnitions and terminology and concepts

◦ Review of the commonly accepted Project Management

functions / Knowledge Areas

◦ Analyze important topics from examination perspective

◦ Tips and Tricks , Exercise of sample test questions

@2017|http://izenbridge.com/|CONFIDENTIAL 7
PMBOK® Guide Ver. 6

• Foundational reference for the Project


Management Professional Programs
• Identifed subset of the project management
body of knowledge
• Includes generally recognized good practices
applicable to most projects most of the time
• Provides and promotes a common vocabulary
within the project management profession

@2017|http://izenbridge.com/|CONFIDENTIAL 8
Generally Recognized Good
Practice
Generally recognized means the knowledge and practices
described are applicable to most of the projects most of the
time , and there is consensus abut their value and usefulness.

 Good Practice means there is general agreement that the


application of knowledge ,skills, tools and techniques to Project
Management processes can enhance the chance of success
over many projects in delivering the expected business values
and results.

 The PMBOK Guide is diferent from a methodology. A


Methodology is a system of practices ,techniques , procedures
and rules used by those who work in a discipline. PMBOK Guide
is a foundation upon which organizations can build
methodologies ,tools and techniques, policies , procedures ,
rules and life cycle phases needed to practice Project
Management.

@2017|http://izenbridge.com/|CONFIDENTIAL 9
The Standard for Project Management
 The PMBOK Guide is based on the Standard for Project
Management which is included as a Part II of PMBOK Guide
Ver. 6.
 The Standard for Project Management is ;

1. Foundational reference for project management


Professional programs and practice of Project
Management.
2. Standard and PMBOK guide both are based on descriptive
practices rather than prescriptive practices to be tailored
to ft to needs of projects.
3. Standards identify the inputs and outputs associated with
the processes.
4. PMBOK Guide gives more details about key concepts ,
Emerging trends and tailoring considerations for
processes and information on how tools and techniques
are applied on the projects. @2017|http://izenbridge.com/|CONFIDENTIAL 10
Code of Ethics and Professional conduct :
 PMI Publishes the code of ethics and professional conduct to ;
1. To instill confdence in project management profession ,

2. To help individuals make wise decisions especially when


faced with difcult situations where they are asked to
compromise his/her integrity or values.

3. The Most important values that global project management


community defne are ; Responsibility , Respect , Fairness
and Honesty.

@2017|http://izenbridge.com/|CONFIDENTIAL 11
1.2 Foundational Elements : a: project, Programs , Portfolio
1. Projects : What is a Project?

*Project – “A temporary endeavor undertaken to create a unique product, service, or result.”
The project can create
•Component or end item itself
•Capability to perform a service
•A result such as outcome or document

2. Characteristics of Project :
It has starting and ending points
It is performed by one or many number of people
It has constraints of time , money and other resources

It is progressively planned , controlled and executed


It results in a unique product , service or result of the enterprise

Projects drive Change


Projects Enable business Value Creation

3. Project Initiation Context :


Meet Regulatory or Social Requirements
Satisfy stakeholder request or needs
Create or improve/fx products or services

Implement or change business or technological strategies

• * Defnitions taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.

@2017|http://izenbridge.com/|CONFIDENTIAL 12
Factors that lead to Creation of Project

Market
demand

Need
Business met
Need

Customer
Request Project Need
Start cannot Stop
be met

Technology

Need no
Legal longer
exists

Ecologica
l

@2017|http://izenbridge.com/|CONFIDENTIAL 13
Examples of Projects..
 Development of New Software to track workforce using GPS
 Implementation of new Business Process
 Implementation of ERP system
 Reduce the call centre response time by 20%
 Conduct a survey to fnd out trend in customer preferences

MANUFACTURING PROJECTS

 Engineering Applications for the Plastics Industry

 Performance Improvement in the Prefabrication Industry

 Production Planning Methodology for the Automotive Industry

 Finish Systems for Housing Construction

 Engineering Design Capabilities in the Sugar Industry.

@2017|http://izenbridge.com/|CONFIDENTIAL 14
Projects Drive Change, moving an organization from one
state to another state to achieve organizational objectives.

@2017|http://izenbridge.com/|CONFIDENTIAL
15
Projects Enable business Value Creation :

 PMI defnes business value as the net quantifable beneft


derived from a business endeavor. Benefts from the
projects may be tangible , intangible or both.
Examples of Tangible benefts include ;
 Monetary Assets, Stock holder equity , Utility, Fixtures ,

Tools and market share.


Examples of Intangible benefts include ;
 Goodwill, Brand Recognition, Public beneft, Trademarks

,Strategic alignment & Reputation

@2017|http://izenbridge.com/|CONFIDENTIAL 16
Project and Project Management

@2017|http://izenbridge.com/|CONFIDENTIAL 17
Portfolio , Program, Projects and
Operations

@2017|http://izenbridge.com/|CONFIDENTIAL 18
Relationship of Project, Program & Portfolio Management and Operations Management

 Program : A group of related projects, subprograms, and


program activities managed in a coordinated way to obtain
benefts not available from managing them individually
 It focuses on Project Interdependencies Management
• Resolving Resource Constraints / Conficts
• Aligning with Organization strategic directions
• Resolving issues within a shared governing structure
 The program is not a collection of unrelated Projects

 Examples :
 Pulse Polio Immunization Program
 Operational Cost reduction program, reduce operational cost
by 10%
 A university wanted to build admissions web sites for all of
their departments

@2017|http://izenbridge.com/|CONFIDENTIAL 19
Portfolio Management

 *Portfolio: Projects, programs, sub portfolios, and


operations managed as a group to achieve strategic
objectives.
 Project or Program of Portfolio may not necessarily to be
interrelated
 Portfolio Management focuses on identifying , prioritizing ,
authorizing , managing and controlling project, program
and other related work to achieve strategic business goals
 Program and Project management focus on doing the
things “Right Way” , while Portfolio management Focuses
on doing “Right” programs and projects.
 Aim of portfolio Management:

1. Guide Organizational Investment decisions and


increase the likelihood of achieving planned ROI.
2. Select optimal mix of projects and programs to
meet strategic objectives.
3. Centralized management of overall risk profle.
@2017|http://izenbridge.com/|CONFIDENTIAL 20
What is Project Management and it’s importance?

• Application of
Knowledge (e.g. Domain areas – IT, Pharmaceutical, Construction, etc.)
Skills (Managing)
Tools & Techniques (Software)
Project activities (e.g Time Management, Cost Management, etc.)
To achieve
Project objectives.

Project Management helps organizations to manage projects


efectively and efciently.

• PM is accomplished though processes:


Initiating, Planning, Executing, Controlling, and Closing

• Project work typically involves (Why Project Management ?);


1. Identifying requirements
2. Addressing stakeholders needs and expectations for meeting project
objectives.
3. Carrying out communications amongst stakeholders
4. Balancing constraints including but not limited to Scope, Quality,
Schedule, Budget, Resources and Risk
5. Achieving Financial efciency & Manage risks efectively
@2017|http://izenbridge.com/|CONFIDENTIAL 21
Project / Operations

 Operations management is an area that is


defned as outside the formal Project
Management as per PMBOK Guide.
 It is concerned with the ongoing production of

goods and/or services by managing processes


that transform inputs (material, labor..) into
outputs (products, goods, services).
 Project / Operations Intersects at ;
 At each closeout phase or at the end of

product development Life cycle.


 When developing a new product, upgrading a

product , or expanding outputs


 When Improving operations or the product

development process
@2017|http://izenbridge.com/|CONFIDENTIAL 22
Project Vs Operations

Project Operations

Temporary On Going

Business Process /
Project Management Operational
Management

Produces the Unique Produces the same


Product / Output Product Repetitively

@2017|http://izenbridge.com/|CONFIDENTIAL 23
1.2.b Organizational Project Management and Strategy :

OPM is a strategy execution framework utilizing project, program, and


portfolio management as well as organizational enabling practices
(enablers) to consistently and predictably deliver organizational strategy
producing better performance, better results, and a sustainable
competitive advantage.
Purpose :
1. Is to ensure that organization undertakes right projects and manages
critical resources appropriately.
2. Helps to ensure that all levels in the organization understand the
strategic vision, the initiatives that support that vision , the objectives
and deliverables.

@2017|http://izenbridge.com/|CONFIDENTIAL 24
Organizational Project Management :

@2017|http://izenbridge.com/|CONFIDENTIAL 25
1.2.C : Components of PMBOK Guide Ver 6 :

26
@2017|http://izenbridge.com/|CONFIDENTIAL
Description of Key Components :

@2017|http://izenbridge.com/|CONFIDENTIAL 27
Project and Development Life
Cycle

*The series of phases that a project


passes through from its initiation to
its closure.

@2017|http://izenbridge.com/|CONFIDENTIAL 28
Development Life Cycles

Project Life Cycle Product Life Cycle

@2017|http://izenbridge.com/|CONFIDENTIAL 29
Project Life Cycle

 Project Life Cycle is a :


 Collection of Project Phases

 Life cycle provides the basic framework for managing the project

 Characteristics of Project Life Cycle :


1. Starting the project

2. Organizing and Preparing

3. Carrying out the project work

4. Closing the project

@2017|http://izenbridge.com/|CONFIDENTIAL 30
Project Phase

 A collection of logically related project activities that


culminates in the completion of one or more deliverables
• The work has a distinct focus
• Closure of phase results in some form of phase deliverable
 Project Phases are determined by
• Management and Control need of the organization
• Nature of the Project
• Unique aspects of Organization, industry and technology
• Project Elements including technology, Engineering,
Business, Process or legal
• Decision Points (No/No-Go, Funding , Milestone Review)

@2017|http://izenbridge.com/|CONFIDENTIAL 31
Phase to Phase Relationships :
 A sequential relationship :
◦ In a sequential relationship, a phase starts only when the previous
phase is complete.
 An Overlapping Relationship :
◦ In an overlapping relationship, a phase starts prior to completion of the previous one.
 A Parallel Relationship :
o In this type of relationship, both the phases can be
started of together / in parallel.

Phase Gate : Phase Gate is held at end of each phase, and


here the Project performance and progress are compared
against project and business documents and decision is made
whether to :
 Continue / End / Repeat the Phase/Project

@2017|http://izenbridge.com/|CONFIDENTIAL 32
Types of Project and Development Life
Cycles
 Project Life Cycles can be Adaptive or Predictive.
Development Life cycles are associated with project
phases , are ; Predictive, Iterative ,Incremental ,Adaptive
,or hybrid types.

1 Predictive Life Cycle :


 Predictive life cycles (also known as fully plan-driven) are ones in

which the project scope, and the time and


cost required to deliver that scope, are determined as early in
the project life cycle as practically possible
 Predictive life cycles are generally preferred when the product to

be delivered is well understood, there is


a substantial base of industry practice, or where a product is
required to be delivered in full to have value to stakeholder
groups.

@2017|http://izenbridge.com/|CONFIDENTIAL 33
Life Cycles…

2 Iterative Life Cycle :


 Iterative and incremental life cycles are ones in which project phases (also

called iterations) intentionally repeat


one or more project activities as the project team’s understanding of the
product increases.

Iterative and incremental life cycles are generally preferred when an


organization needs to manage changing
objectives and scope, to reduce the complexity of a project, or when the
partial delivery of a product is benefcial and provides value for one or more
stakeholder groups without impact to the fnal deliverable or set of
deliverables.
3 Incremental Life Cycle : The deliverable is produced through a series of
iterations that successively add functionality within a predefned time frame.
4 Adaptive Life cycles are Iterative, Incremental or agile. The detailed SOW is
defned and approved before the start of the iteration.

@2017|http://izenbridge.com/|CONFIDENTIAL 34
Life Cycles…Contd…
 Adaptive life cycles (also known as change-driven or
agile methods) are intended to respond to high levels
of change and ongoing stakeholder involvement.
 Adaptive methods are also iterative and incremental,

but difer in that iterations are very rapid (usually with


a duration of 2 to 4 weeks) and are fxed in time and
cost.
5 Hybrid Life Cycle :
It is a combination of adaptive and predictive types of life
cycles ; Some Elements of project with fxed requirements
follow Predictive development life cycle and other elements
which are still evolving follow adaptive development life cycle.

@2017|http://izenbridge.com/|CONFIDENTIAL 35
Predictiv
Predictiv
Adaptive
Adaptive Iterative
Iterative ee

Plan Iteration Plan


Iteration Analysis
Plan

Iteration
Design

Test
Code
Iteration

Design
1 -4 Week
Analysis
Code
Iteration
Deploy
1 to 3 Months

Iteration Test
Iteration
Deploy
Iteration
Plan
Analysis

Iteration
Analysis
Iteration
Iteration Design

Iteration Code
Iteration
Test
1 to 3 Months
Design

Iteration
Iteration Deploy

Iteration Plan
Iteration Analysis
3 to 24 Months

Iteration
Design
Iteration
Code

Iteration Code
Iteration
Test
1 to 3 Months

Iteration
Deploy
Iteration
Iteration Plan
Test

Iteration Analysis
Iteration Design
@2017|http://izenbridge.com/|CONFIDENTIAL

Iteration
Iteration Code

Test
1 to 3 Months

Iteration
Deploy

Iteration Deploy
A Sample Software Development Life Cycle

36
Product vs. Project Lifecycle

Project Product
Development of New The Typical Product Life
Product has been usually cycle starts with the
project of its own conception till obsolete.

Project life cycle may A product may span


occur in one or many across many projects
phases of production during its life cycle

@2017|http://izenbridge.com/|CONFIDENTIAL 37
Project and Product lifecycle Relationships

Upgrade
Product Lifecycle

Divestment
Business
Plan
Operations
Idea

Produ
ct
Project Initial Intermediate Final
Lifecycle

@2017|http://izenbridge.com/|CONFIDENTIAL 38
Project Management Processes :
 A systematic series of activities directed towards causing an end result
such that one or more inputs will be acted upon to create one or more
outputs.

 Project Management is accomplished through the appropriate application


and integration of logically grouped Project Management Processes.

 Project management processes are grouped into fve groups :


• Initiating Process Group
• Planning Process Group
• Executing Process Group
• Monitoring & Controlling Process Group
• Closing Process Group

@2017|http://izenbridge.com/|CONFIDENTIAL 39
A Process :

Tools and
Input Technique Output
s

@2017|http://izenbridge.com/|CONFIDENTIAL 40
A Project Team Must
•Select appropriate processes
•Use a defned approach
•Comply with requirements to meet stakeholder needs
•Balance the competing demands of scope, time , cost, quality ,
resource and risk
 Which Processes are applicable?
• For any given project, the project manager and team should
determine appropriate processes and the appropriate degree of rigor.

• There are 49 Processes spread across


5 Process groups and 10 Knowledge
Areas.

@2017|http://izenbridge.com/|CONFIDENTIAL 41
Process Categories :
1. Processes used once or at predefned points in the project ,
e.g DEVELOP PROJECT CHARTER

2. Processes that are performed periodically as needed, e.g.


CONDUCT PROCUREMENTS

3. Processes that are performed continuously throughout the


project , e.g DEFINE ACTIVITIES, many Monitoring &
Controlling processes.

@2017|http://izenbridge.com/|CONFIDENTIAL 42
Process Categories:
 Project Management Processes, these are the one
covered in PMBOK® Guide ;
1. Processes used once or at predefned points in
the project. Examples; Processes Develop
project Charter or Close project/phase
2. Processes that are performed periodically as
needed ; Acquire Resources or Conduct
Procurements
3. Processes that are performed continuously
throughout the project. Defne Activities Or
Many of Monitoring and Controlling
processes.

 Product Oriented Processes, they vary by


application area.
 Following Slide mentions all Process Groups

@2017|http://izenbridge.com/|CONFIDENTIAL 43
Project Management Process Groups – Initiating

Monitorin
Initiatin Planning Executin g and
Closing
g g Controllin
g

 Formally Authorizes the new project


 It also occurs during transition from one phase to
another
 Activities like, High Level Business Need Analysis,
Project Selection
 Stakeholder Identifcation and Stakeholder
Management Strategy

@2017|http://izenbridge.com/|CONFIDENTIAL 44
Project Management Process Groups – Planning
Monitorin
Initiatin Executin g and
Planning Closing
g g Controllin
g

 It's all about Information gathering and Project


Planning
 It covers all areas of Project- scope , budget ,
schedule , risk, quality , communication ,
procurement and human resource
 It's not a one time process, needs to be progressively
elaborated
 All planning activities ultimately lead to
comprehensive Project Management Plan
 The Project Management Plan is not a static
document
 It is Plan component of Plan-Do-Check-Act cycle
@2017|http://izenbridge.com/|CONFIDENTIAL 45
Project Management Process Groups – Executing

Monitoring
Initiatin Executin
Planning and Closing
g g
Controlling

 It’s a Process Group where the bulk of project time


and budget will be spent
 It includes processes that are related to development
of delivery , team development , procurement
activities, verifying deliverables and distributing
project information
 Its a Do component of Plan-Do-Check-Act cycle

@2017|http://izenbridge.com/|CONFIDENTIAL 46
Project Management Process Groups – Monitoring & Controlling
Monitorin
Initiatin Executin g and
Planning Closing
g g Controllin
g

 Ensures that plan is followed


 Watch for variance and problems
 Management of team and stakeholders
 Managing Procurement Contracts
 Ensure the Project Changes are properly
managed
 Monitoring and Reporting on risks, scope , cost ,
schedule , quality , team performance
 Monitoring & Controlling Process group is “check
& act” component of Plan-Do-Check-Act cycle.
@2017|http://izenbridge.com/|CONFIDENTIAL 47
Project Management Process Groups – Closing

Monitoring
Initiatin Executin
Planning and Closing
g g
Controlling

 Formally end the project, phase or procurement


contract
 Deliverable Handof to Customer
 Archiving Project Documents
 Settling Contracts
 Provide Final Performance Information
 Closing Process always occurs even if the project is
cancelled or terminated.

@2017|http://izenbridge.com/|CONFIDENTIAL 48
Project Management Knowledge Areas :

Project Project Project


Project Cost
Integration Scope Schedule
Managemen
Managemen Managemen Managemen
t
t t t

Project Project
Project Project Risk
Quality Resource
Communication Managemen
Managemen Managemen
s Management t
t t
Project
Project
Procuremen
Stakeholder
t
Managemen
Managemen
t
t

@2017|http://izenbridge.com/|CONFIDENTIAL 49
Project Information
 Work performance data. The raw observations and
measurements identifed during activities performed to carry out
the project work.
 Examples include reported percent of work physically completed,
quality
and technical performance measures, start and fnish dates of
schedule activities, number of change requests, number of
defects, actual costs, actual durations, etc.
 Work performance information. The performance data
collected from various controlling processes, analyzed in context
and integrated based on relationships across areas.
 Examples of performance information are status of deliverables,
implementation status for change requests, and forecasted
estimates to complete.
 Work performance reports. The physical or electronic
representation of work performance information compiled in
project documents, intended to generate decisions or raise issues,
actions, or awareness.
 Examples include status reports, memos, justifcations,
information notes, electronic dashboards, recommendations, and
updates. @2017|http://izenbridge.com/|CONFIDENTIAL 50
Project Information :

@2017|http://izenbridge.com/|CONFIDENTIAL 51
d. Methodology, Tailoring & Business
Documents:
Methodology :
A methodology is a system of practices , techniques, Procedures
and rules used by those who work in a discipline.

It clearly means that PMBOK GUIDE is not a methodology.

Tailoring :
For Each project being unique , appropriate project
management processes ,inputs ,tools & techniques , outputs ,
Life cycle approach to be selected to manage the project.

This selection is called “Tailoring Project Management”


to the project.
@2017|http://izenbridge.com/|CONFIDENTIAL 52
About Tailoring :
 PM Collaborates with Team ,sponsor ,Organizational
management

 Tailoring addresses competing demands of constraints;


scope ,time ,cost ,resources , quality and risk.

 Level of governance required and culture of the project with


all other important environmental factors.

 May require some specifc PM methodology to be used.

@2017|http://izenbridge.com/|CONFIDENTIAL 53
Project Management Business
Documents :
Its imperative that Project Management approach captures the
essence and intent of project management business
documents.

@2017|http://izenbridge.com/|CONFIDENTIAL 54
Project Management Business Documents - Facts:

 The Project Sponsor is accountable for development,


Maintenance.
 PM Is responsible for providing recommendations, an

oversight to keep all documents in alignment Organizational


goal and objectives.

 Business case and Benefts management plan are


maintained at program level.

 PM should work with concerned Program Managers to


ensure consistency and alignment.

@2017|http://izenbridge.com/|CONFIDENTIAL 55
Interrelationships between Project Documents:

@2017|http://izenbridge.com/|CONFIDENTIAL 56
Project Business case :
 Project Business Case is a documented economic feasibility study used to
establish the benefts of the components and that used as the basis for the
authorization of further project management activities like authorizing
Project Manager to use organizational resources.

 Lists the objectives and the reasons of the project initiation, may be used
before initiation and may result in go/no-go decision based on feasibility
factors.

 Helps measures the project success at the end of the project against project
objectives defned.

 Used throughout the Project Life Cycle, A needs assessment often precedes
the business case.

@2017|http://izenbridge.com/|CONFIDENTIAL 57
Business Case Document - Contents :
1. Business Needs
2. Analysis of Situation
3. Recommendation
4. Evaluation

@2017|http://izenbridge.com/|CONFIDENTIAL 58
Project Benefts Management Plan :
 The Projects Benefts Management plan is the document that
describes how and when the benefts of the projects will be delivered
and describes the mechanisms to measure those benefts. It’s an
Iterative Process ensuring the alignment throughout with all other
critical documents.
 KEY ELEMENTS :

1. Target Benefts

2. Strategic Alignment

3. Time Frame for realizing benefts

4. Benefts Owner

5. Metrics

6. Assumptions

7. Risks

@2017|http://izenbridge.com/|CONFIDENTIAL 59
Project Success Measures :
 Project objectives that are measurable :
1. Completing Project Benefts Management Plan
2. Meeting Agreed upon fnancial Measures documented in Business
case document
3. Meeting Business Case fnancial documents
4. Completing the movement of an organization from its current
state to the desired future state
5. Completing Contracts
6. Achieving Stakeholders expectation and satisfaction
7. Customer acceptance
8. Meeting Governance
9. Achieving Other agreed upon success measures (e.g. Process
throughout)

@2017|http://izenbridge.com/|CONFIDENTIAL 60
Questions?

@2017|http://izenbridge.com/|CONFIDENTIAL 61
Lesson 2: The Environments in
which projects operate

@2017|http://izenbridge.com/|CONFIDENTIAL 62
Lesson 2: The Environments in which Projects Operate –
Agenda

1 2.1 Overview

2 2.2 Enterprise Environmental Factors

3 2.3 Organizational Process Assets

4 2.4 Organizational Systems

@2017|http://izenbridge.com/|CONFIDENTIAL 63
2.1 Overview :
 All The projects exist and operate in the environments
that infuence with favorable and/or unfavorable
impact on them.
 There are two main Categories of these infuences ;

1 Enterprise Environmental Factors (EEFs) ; which does


originate from the environment outside of the project
but internal to enterprise and often from outside the
enterprise as well.
2 Organizational Process Assets (OPAs) ; Which are
internal to organization , and originates from
organization, portfolio, program or project itself.

3. Additionally, Organizational Systems also plays a


greater role on the life cycle of the project.
@2017|http://izenbridge.com/|CONFIDENTIAL 64
Project Infuences :

@2017|http://izenbridge.com/|CONFIDENTIAL 65
2.2 Enterprise Environmental Factors
 Conditions not in Control of Project team but
Infuence , Enhance, Constraint and direct the project
work
 EEFs can be Internal as well as external also
 EEFs are input to many planning g processes and

sometime they are updated as outputs also.


 Both Internal and external EEFs to be duly considered

for the project to efective.

 e.g. Enterprise level HR Management Framework,


Strategic practices, Financial policies etc.

@2017|http://izenbridge.com/|CONFIDENTIAL 66
Enterprise Environmental Factors

External Environment

Organization Environment

Project

@2017|http://izenbridge.com/|CONFIDENTIAL 67
Enterprise Environmental Factors

A. Internal EEFs :
 Organization Environment
• System / Work Authorization System
• Information System Software for Projects and data management
• Style ,Structure and Governance
• Skills / People Capability
• Geographic Distribution of facilities and resources
• Infrastructure and Resource availability
B. External EEFs:
 External Environment

 Market Conditions , demand , resource availability , financial indicators


 Political Climate
 Government and Industry standards
 Commercial database
 Geo Political, Social and cultural influences and issues
 Legal restrictions, Academic Research
@2017|http://izenbridge.com/|CONFIDENTIAL 68
2.3 Organizational Process Assets :
 OPAs Infuence the management of the
• Plans
project.
• Processes
• Policies, Procedures based on process groups
• Basis of Estimates, Measurements
• Knowledge Base , Specifc to the organization
• Standards
• Corporate Knowledge Base
• Various project documents like registers
• Project Closure documents ; lessons learnt,
• Archived records including knowledge repositories

All are generic in nature , & they are applied based on


the context.

@2017|http://izenbridge.com/|CONFIDENTIAL 69
Corporate Knowledge Base

• Confguration Management Knowledge base ,


current baselines
• Financial Database , labor rates
• Historical Information and Lesson Learned
• Process Measurement Database
• Project fles

@2017|http://izenbridge.com/|CONFIDENTIAL 70
Processes and Procedures :
 Initiating & Planning
• Guideline and criteria for tailoring
• Organization Standards and Policies
• Product and Project Lifecycle
• Templates
 Executing , Monitoring and Controlling
• Change Control
• Financial Control
• Issues and defects Procedures
• Communication Requirement
• Risk Control Procedure
• Guidelines , Work Instructions and Performance
Evaluations

@2017|http://izenbridge.com/|CONFIDENTIAL 71

You might also like