PMP Sample Questions
PMP Sample Questions
PMP Sample Questions
C.Defect repair
D.Risk mitigation
6) You are managing a project in a foreign country. In this country there is a
normalpractice for business people to exchange gifts when very large
contracts, such as the one you are working on, are signed. The gift is of a
greater value than your companys policy for gift exchange will allow. You
have given a gift of similar value to the customers representative already.
What should you do?
a. Take the gift
b. Contact your companys management and seek for assistance
c. Refuse the gift graciously, explaining your companys policy
d. Ask the customers representative to give the gift to your manager.
7) You recently are being replaced by an existing project manager in a new
organization, observed a certain cost had been calculated twice by mistake,
due to which now the original budget figure is in excess of $10500.
You know that revealing this information will affect previous project
managers credit in the organization.What should you do as a PMP certified
manager?
A. Keep silence on this matter
B. Keep silence but dont spend additional fund available without taking
approval from your manager
C. You must bring this to the notice of the top management
immediately
D. Use the additional funding for other projects
8) In your project, there have been several changes in the cost and schedule
estimates, and the original estimating assumptions are no longer valid.
Calculate the estimate at completion (EAC) for your project based on the
following data? BAC = $ 300,000, AC = $ 100,000, EV = $ 150,000, ETC = $
120,000, ETC = $ 120,000
A. $ 250,000
B. $ 220,000
C. $ 280,000
D.$ 300,000
9) The project manager develops a process improvement plan to encourage
continuous process improvement during the life of the project. Which of the
following is a valid tool or technique to assist the project manager to assure
the success of the process improvement plan?
A. Change control system
B. Process analysis
C. Benchmarking
D. Configuration management system
10)