WED Manual
WED Manual
Experiment No.1
Well Planning
Introduction:
Well planning is the most demanding aspect of drilling engineering that requires the
integration of engineering principles, corporate or personnel or personal philosophies and
experience factors. The concept of well planning vary within drilling industry but the end result
should be a safely drilled minimum cost hole that satisfies the reservoir engineer’ s requirement
for production of fluids.
Objectives:
The objectives of well planning is to formulate a program from many variables foe
drilling a well that is safe, minimum cost and usable form.
Safety:
Safety should be the highest priority in well planning. Personal considerations must be
placed above all other aspects of the well plan. If required the plan must altered during the course
of drilling the well when unforeseen drilling problems endanger the crew, failure to stress crew
safety has resulted in loss of life etc.
The second priority should be safety of the well. The well planned must design to have
minimum risk of the well during drilling life of well.
Minimum cost:
A valid objective of the well planning to have minimum cost of the well without
jeopardizing the safety aspects. In most cases the effective cost can be drastically reduced with a
little effort of proper planning. It is not noble to build steel monuments in the name of safety. The
expenses should be incurred only when they are necessary.
Usable hole:
Drilling a hole to the target if the depth is not completely satisfactory if the final well
configuration is not usable the hole diameter is sufficiently large so an adequate completion can
be made and the hole or producing formation is not irreparably damaged.
1
Well Engineering and Design 2015course
Classification of wells
Exploratory wells: Site selection based on seismic data, satellite surveys etc; no known drilling
data in the prospective horizon.
Step out wells: Delineates the reservoir’s boundaries, drilled after a exploratory discovery; site
selection usually based on seismic data.
Infill wells: Drills the known productive portions of the reservoir site selection usually based on
patterns, drainage radius etc.
Re-entry wells: Existing wells reentered to deepen, side track, rework, or re-complete; various
amount of planning required on purpose of re-entry.
Formation pressure:
The formation or pore pressure encountered by the well significantly affects the well
plan. The pressure may be normal, abnormal (high), or sub-normal (low). Normal pressure wells
generally do not create planning problems. The mud weights are in the range of 8.5 – 9.5 ppg.
Kicks and blowout prevention problems should be minimized but not eliminated. Casing
requirement can be stringent even in normal pressure well deeper than 20,000 ft. due to tension/
collapse.
Subnormal pressure wells may require setting additional casing string to cover weak or
low pressured zones. The lower than normal pressure may result from geological or tectonic
factor or from pressure depletion in producing intervals.
Abnormal pressure affects the well plan in many ways including the following-
Casing and tubing design, mud weight and type selection, casing setting depth selection,
cement planning.
Kicks and blow outs, differential pipe sticking, lost circulation, heaving shales.
Planning cost:
The cost required to plan a well are insignificant in comparison to the actual drilling cost
in many cases, less than $ 1,000 is spent in planning a $ 1 million well. This represent 1/10 or 1
% of the well cost.
1
Well Engineering and Design 2015course
Well planning is an orderly process. It requires that some aspects of the plan be
developed before designing other items like-
The mud density can be done at any stage during the well planning. However the bit
program is usually based on drilling parameters from offset wells. This can be affected by the
mud plan i.e. the performance of PDC bits in oil muds. The bit sizing can be controlled by casing
program.
Casing and tubing should b considered as an integral design starting from the size of
production casing. The tubing design are drift diameter of the production casing that can be
effected by packer to tubing forces created by tubing tendencies for movement.
The completion plan must be visualized in advance. This affects the size of casing and tubing to
be used. In addition the plan can require the high strength tubing or usually long seal assemblies
in certain situations.
Data sources:
Source of the data should be available for the virtually every well drilled in the field. The
wildcats can be source of seismic data and pore pressure prediction. Common types of data
required by drilling engineers are –
2. Method of drilling: cable tool drilling, rotary drilling, drilling with downhole motors,
top drive drilling etc.
1
Well Engineering and Design 2015course
4. Formation characteristics:
5. Well lithology:
6. Mechanical planning:
a) conductor casing
b) surface casing
c) intermediate casing
1
Well Engineering and Design 2015course
d) production casing
e) liner casing
v) Casing design
8. Mud program:
1
Well Engineering and Design 2015course
i) Type of bit and its stability: drag bit, rotary roller bits, diamond bits, PDC bits,
core drilling bits, jet bits, mill bits.
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
Experiment No.2
Theory:
The various input data are thoroughly analyzed and the GTO prepared, which provides broad
guidelines for drilling of the well. GTO furnishes the following details:
a) General data like well name, well no, area, location, water depth elevation, well type,
category, objective of well etc.
b) Geology and the data consists of the following details like depth, age, formation,
lithology, interval of coring, electrologging, collection of cuttings, angle of dip, oil gas
zone, formation pressure, formation temperature, mud loss/ caving etc.
i) Type of mud
iii) Viscosity
iv) pH
v) % of sand
i) Casing policy
v) No of bits expected
vi) Meterage/bit
1
Well Engineering and Design 2015course
vii) WOB
x) Pump discharge
1
Well Engineering and Design 2015course
Experiment No.3
Drilling Cost Analysis
Objective:-
Theory:-
The drilling engineer is frequently called uponto predict the cost of a well at a given location.
These predictions are required so that sound economic decisions can be made.
Drilling cost depends primarily on well location and well depth. The location of well will govern
the cost of preparing the wellsite, moving the rig to the location, and the daily operating cost of
the drilling operation, e.g. rig rentals, crew boat & work boat rentals, helicopter rental, well
monitoring services, crew housing, drlling fluid treatment, rig supervision etc. The depth of the
well will govern lithology that must be penetrated and thus the time required to complete the
well.
Drilling costs tend to increase exponentially with depth. Thus, when curve fitting drilling cost
data, it is often convenient to assume the relationship between cost, C, and depth, D, given by,
----------(1)
where the constants a and b depend primarily on the well location. This can be drawn on semilog
or cartesian plots.
When more accurate drilling cost prediction is needed, a cost analysis is based on a detailed well
plan must be made. The cost of tangible well equipment and the cost of preparing the surface
location usually can be predicted accurately. The cost per day of the drilling operations can be
estimated from considerations of rig rental costs, other equipment rentals, transportation costs, rig
supervision costs, and others. The time required to drill and complete the well is estimated on the
basis of rig-up time, drilling time, trip time, casing placement time, formation evaluation and
borehole survey time, completion time and trouble time.
An estimate of drilling time can be based onhistorical penetration rate data from the area of
interest. The penetration rate in a given formation varies inversely with both compressive strength
& shear strength of the rock. Also, rock strength tends to increase with depth of burial because of
the higher confining pressure caused by the weight of the overburdon. When major
unconformities are not present in the subsurface lithology, the penetration rate usually decreases
exponentially with depth. Under these conditions, the penetration rate can be related to depth, D,
by
1
Well Engineering and Design 2015course
-----------(2)
where K and a2 are constants, the drilling time, td, required to drill to a given depth can be
obtained by separating variables and integrating.
-----------------(3)
As experience is gained in an area, more accurate predictions of drilling time can be obtainedby
plotting depth vs. drilling time from past drilling operations. Plots of this types also are used in
evaluating new drilling procedures designed to reduce drilling time to given depth.
Trip Time:
The time required for tripping operations depends primarily on the depth of the well, the rig being
used, and the drilling practices followed. The time required to change a bit and resume drilling
operations can be approximated using the relation-
------------(4)
where,
The above analysis shows that the time required per trip increases linearly with depth. In
addition, the footage drilled by a single bit tends to decrease with depth, causing the no. of trips
required to drill a given depth increment also to increase depth. So the depth of the next trip gives
the following equation,
---------(5)
1
Well Engineering and Design 2015course
The total bit rotating time, tb, will vary with depth as the bit size and bit type are changed.
Equations (4) & (5) can be used to estimate the total trip time required to drill a given depth using
ts, tb, K & a2.
Formation with high strength requires more no. of bits and to drill a given depth. The time
required per round trip per 1000ft intervals can be approximated from the concerned graph which
is normal cost for 1000ft intervals.
The no. of bits required per 1000ft, N’b, at a given depth can be approximated by deviding the
drilling time per 1000ft, t’d, by the average bit life for that interval:
---------------(6)
The drilling time required to drill from D to (D+1000) can be obtained as,
--------------------(7)
------------------(8)
where,
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
Example:-
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
Experiment No.4
Pore Pressure
Objective:-
Theory:
Mathematical expression:
d = D exponent
ROP= ft/hr
RPM=rotary speed
WOB= lb
B= Diameter of bit (in)
D' exponent basically attempts to correct ROP b changing RPM, WOB and hole size. D-
exponent is proportional to rock strength and normal pressure formation; it increases with depth
linearly as rock strength increases with depth. For abnormally Pressured shales, D' exponent
deviates from normal trend and actually decreases with depth. Further modification of D-
exponent considering effect of changes in mud wt is
dc=d (NPP/Ecd)
In overpressured zone indicates formation becomes less dense and will have higher porosity than
rock at same depth. The decrease in rock strength results in greater ROP and so reduction in D-
exponent.
1
Well Engineering and Design 2015course
2) Establish normal pressure trend line through dc values corresponding to normal pressure
shales which predict dc values corresponding to normal pressure shales which predict dc vales at
a depth in shale section which exhibits normal compaction and normal pore pressure. The trend
line should slope to right to indicate increase dc values
With depth. This slope indicates increasing density and decreasing porosity and reliability in
normally pressured shale.
3) Plot actual dc values alongside to trend line.
4) Calculate pore pressure
In Eton, record values of normal trend line dc (dcn) an observed dc (dco) at depth of interest.
Record overburden gradient
Ratio:-
It does not prefer overburden gradient to calculate pore pressure.
Sonic log:-
These are considered to provide most reliable values because they are unaffected by bore hole
size, formation temp and salinity. Sonic log measures transit time delta t For compression sonic
1
Well Engineering and Design 2015course
wave to travel through formation from transmitter to receiver. Time travelled through ft/in is
termed as interval transit time. In a shale showing normal compaction profile the transit time
should decrease with depth due to decrease in porosity and increase in density. Abnormally
pressured shales have higher porosity and lower density. Hence, delta t values will be higher.
Resistivity log:-
Shale resistivity increases with depth.
Resistivity of shale depends on following factors:
1.) Porosity
2.) Salinity of pore H2O
3.) Temperature
Porosity is major factor affecting resistivity values. In normal shale, resistivity increases with
depth as porosity decreases.
D – Exponent
Depth
2500 1.6 1.6 2 1.304
2900 1.3 1.8 2.3 1.464
3000 1.0 1.8 2.45 1.614
3200 1.1 2 2.55 1.884
3250 1 2.1 2.6 1.944
Pore pressure =
= 2 – (2 – 1.304)*(
1
Well Engineering and Design 2015course
Porosity is the major factor affecting resistivity values. In normal shale, resistivity increases with
depth as porosity decreases.
Sonic Log
Depth
2500 110 55 2 1.304
2900 110 35 2.3 1.464
3000 100 30 2.45 1.614
3200 100 25 2.55 1.884
3250 70 20 2.6 1.944
Pore pressure =
1
Well Engineering and Design 2015course
Experiment No.5
Drill String Design
Theory:
The drill string design involves the determination of length, weight and grades used for
drilling and other operation. It depends upon several factor including hole depth, size, mud
weight, desired safety factor, tension margin of overpull, length and weight of drill pipe and drill
collar.
Tension
Collapse
Shock loading
Torsion
1
Well Engineering and Design 2015course
Hence DP must be capable of withstanding all type of loading and must have a long service life.
1. 18 – 22 ft
2. 27 – 30 ft
3. 38 – 45 ft
The grade of DP available to suit different hole depth and loading requirement are P, E, X-95, G-
105, S-135. These grades are manufactured in different sizes of OD ranging from 2.375” to
6.625”. each grade and size is specified by,
Collapse strength:
The maximum internal pressure required to cause steel to yield is burst pressure.
It is the maximum value of force required for plastic deformation of the pipe.
The properties of drill pipe change with time due to stress acting on it which is because
of:
During drill pipe operation, stresses result in pipe wear and reduction in pipe strength of new DP,
hence API has classified DP’s according to wear as follows:
1
Well Engineering and Design 2015course
Design criteria:
= [L dp × W dp + Ldc × Wdc] × BF
Where, ρmud and ρsteel are densities of mud and steel respectively.
DS design is never based on the tabulated yield strength value but 90% of the yield strength to
provide an added safety in resulting design.
Therefore,
The difference between the above two equations 1 and 2 gives the Margin of Overpull (MOP)
Therefore,
MOP = Pa – P
The ratio of the equation 1 and 2 gives the actual safety factor as,
SF = Pa / P
On simplifying we get,
Or in terms of MOP as
Ldp may be expressed as Lmax that is maximum length of DP that can be selected for a given
loading situation.
1
Well Engineering and Design 2015course
Collapse:
Maximum differential pressure (∆P) across DP exists prior to the opening of the DST tool and is
got using
Where,
Shock loading:
It arises whenever slips are set on moving Dp and can contribute to parting of pipe in marginal
designs. Additional tensile force Fs generated by stock loading is calculated from,
Fs = 3200 Wdp
Torsion:
It can be shown that the DP torsional yield strength when subjected to pure tension is
given by,
Q = 0.096167 J Ym / D
Where DP is subjected to both tension and torsion, which is usually the case, the equation
becomes
Qt = 0.096167 J / D √ Ym2 – P2 / A2
Where,
1
Well Engineering and Design 2015course
Drill pipe stretches under the action of weight of DC and also its own weight.
Assume that changes in DP diameter are very small such that DP extension is only
significant in the axial direction.
E = (P/A) / (e1 / L)
Where,
e1 = extension of DP
We get
e1 = PL / AE = P L / [π / 4(D2 – d2)]E
Therefore
Weight 31.2 kg/m, class-II pipe with a tensile strength of 141.8 tonnes. The length upto which
this pipe can be used is calculated as follows.
1
Well Engineering and Design 2015course
4] length of second section of DP: next ,higher grade DP above E grade DP is to be calculated
Length up to which this grade of pipe can be used is calculated using the same formula and
combining the total wt of E grade pipe in the Wc Lc term
= 1186 m of G grade DP
Since this length is more than the required depth to reach top of the well, this grade is used up to
the top.
Stretch due to own wt : DP also stretches under its own wt when suspended in mud. This can be
calculated by, e2 = L^2/72 * 10^7 ( 489.5 – 1.44ρm1)
Problem:
Data given: Depth = 2700 m, hole size = 12 ¼ “, mud wt = 1.6 gm/cc (kb = 0.796)
1
Well Engineering and Design 2015course
1] total length of drill collar assembly: determine air wt of drill collars necessary to maintain a
WOB of 25 tonnes
Adjust this wt approx in 4 stands or 120m of 8^1/2 * 3’’ drill collars and 2 stands of 6^1/2’’ * 2
^13/16’’ drill collars.
2] Length of first section of DP above DC assembly: consider DP of lower grade 5’’, 19.5lb/ft E
grade (NC- 50) adjusted
iv) 5’’, 19.5 lb/ft (29 kg/m) E grade (N-50) = 1400 m class- II pipe
v) 5’’, 19.5 lb/ft (29 kg/m) G grade (N-50) = 1400 m class- II pipe
TOTAL = 2700 m
5] MOP calculation: margin of over pull that can be applied in case the string gets
1
Well Engineering and Design 2015course
= 0.9 * 197.6 – P
= 177.8 – P
DP + HWDP + DC
P = 95.8 tonnes
= 82 tonnes
So the excess pull to be applied should be based on ‘E’ grade tensile properties
Calculate the collapse pressure (pc) at 2460m (base of E grade Dp) due to a fluid column of
specific gravity of 1.6 gm/cc
Collapse resistance of E grade DP is 335 kg/sq cm. therefore, the pipe must be run empty and a
water cushion may be placed while conducting DST.
gravity of water.
1
Well Engineering and Design 2015course
Experiment No.6
Rig Hydraulics
Objective:-
Theory:-
Proper utilization of hydraulic energy at the drill bit and determination of pressure losses at
various part of drill string is discussed under heading of ‘Rig Hydraulics’. The sequence of fluid
mechanism is very important to Drilling Engineers.
1) Maximum impact force criteria: For max. I.F the pressure drop across bit is ,
1
Well Engineering and Design 2015course
P (bit) = (n/n+2) * Ps
IF = Q√ϼ * P bit / 58
Where,
ϼ → ppg
Q → gpm
The index ‘n’ can only be determined on site and in largely controlled by downhole
conditions. The steps involved are:
1) Prior to pulling bit out of hole for changing, run pump at 4 or 5 different speeds. Record
resulting stand pipe pressure.
2) From nozzle sizes, fluid pressure losses across the bit for each value of Q.
5) Using BHHP and IF criteria’ find nozzle sizes for next bit run.
The objective of any hydraulic program is to optimize pressure drop across bit such that max.
Cleaning of bottom hole is achieved. Pressure losses across bit are greatly influenced by nozzle
size. Smaller nozzle size , greater is pressure drop.
Annulus V = q/2.448(d2²-d1²)
τ= Ѳ300 - µp
NRe = 928* ρ* Δ* d/ µp
1
Well Engineering and Design 2015course
Annulus
Rig Hydraulics
Total surface pressure available is also called as pump pressure is equal to.
Pp = ΔPs + ΔPdp+ΔPdc+ΔPbit+ΔPdca+ΔPdpa
ΔPd = ΔPdp+ΔPdc+ΔPdca+ΔPdpa+ΔPs.
This is circulating pressure loss accept bit. This is also called as parasitic pressure loss that is
frictional pressure loss to and from the bit;
Pp = ΔPb + ΔPd.
ΔPd has to be minized and ΔPb is be optimized by calculating hydraulic level requirement at
every depth.
1) Max bit hydraulics Hp i.e. pressure loss across bit is simply the difference between pump
pressure (stand pipe pressure) and Δpd.
For optimum hydraulics, bit pr.drop must be a certain fraction of max available surface
pressure.
Pbit = n/n+1.Ps
1
Well Engineering and Design 2015course
Q : It is desired to estimate proper pump operating condition and bit nozzle sizes for max bit
horse power at 1000ft increments for an interval of the well between surface casing at 4000 ft.
and intermediate casing at 9000ft.The well plan falls for following condition:
Max Hp = 1600Hp
Efficiency = 0.85
600ft of 7.5 in 0.D 2.75 in 1.D drill collar surface equipement. Pr.loss = 340ft drill pipe
Mud program
5000 9.5 15 5
6000 9.5 15 5
7000 9.5 15 5
8000 12.0 25 9
9000 13.0 30 12
PH = Δ Pp q / 1714
qmax = 681gpm
For the given problem, since pump pressure Vs q is not available, n = 1.75 is assumed.
Now,
1
Well Engineering and Design 2015course
Δ Pd = 1 / 1.75+1 * 3423
= 3423 / 2.75
Δ Pd = 1245 paisa
= 395.36 gpm.
Although qmax and qmin is known for given condition and assumed ‘ή, we calculate further data
based on convenient flow rate value that lies in between qmax and qmin.
Vdp = 13.95 ft / s
= 37100*0.95*5*(3.826) ²/ 15²
= 114650.23
Ref. fig. 4.33 to get critical reynold no. Vs headstorm no. graph.
NRe = 7200
Now,
NRe = 928*ρ*V*d/ μ
1
Well Engineering and Design 2015course
= 31,370
= 490 psi
∆ Ps = 38 psi
˅ = q/ 2.448 d^2
= 37100*9.5*(2.75)^2
= 59231
= 928*9.5*27*2.75 / 15
= 43,640
؞Flow is turbulent
= 2.53 ft/sec
1
Well Engineering and Design 2015course
= 16,018
=757*9.5*2.53(10.05-4.5) /15
=6714
∆ Pdpa=25.23 psi
Using procedure similar as before, frictional Pressure losses in other sections are also completed
at diff. depths of 6000,7000, 8000 and 9000 ft.
The pressure losses expected at each depth assumed are plotted at assumed flow rate of 500 gpm.
We then draw a line of slope = 1.75 through computed points.
1
Well Engineering and Design 2015course
The above table gives nozzle sizes required for max bit hp for any interval.
Q 2.
Determine proper pump operating condition and bit nozzles for max jet impact force for next bit
run. The bit currently in use has 3 12/32” nozzles. The driller has recorded that when 9.6 ppg
mud is pumped at q = 485 gpm, a pump pressure of 2800 psig is observed and when pump is
slowed to a rate of 247 gpm, 900 psig is observed. The pump is rated at 1250 hp and has an ή of
0.91. the qmin to lift cuttings is 225 gpm. The max. allowable surface pressure is 3000psig. Mud
density will remain unchanged in next bit run.
Pump: 1250 HP rating, E = 0.91, qmin = 225 gpm, Pmax = 3000 psig
At = 3*π/4(12/32) ^2 = 0.3313sq in
1
Well Engineering and Design 2015course
Sub in formula,
If we plot a graph of ∆Pd vs Q on log-log paper, slope can be got , also by calculation ,
We get,
( ؞n) = 1.178
From yhe grap of ∆Pd vs Q, we get a Q value of 825 gpm. Corresponding to ∆Pdp optimum
value of 1888 psig.
Nozzle calculation,
At = 0.483 sq in.
D = √ [4At/3π]*32 = 14.48 in
Q 3.
1
Well Engineering and Design 2015course
Prior to changing of bit in a 12 ¼” hole, stand pipe pressure were recorded at different flowrates
with the present bit still on bottom. Present hole depth = 6528 ft and next bit is expected to drill
down to 8000 ft. other relevant data is given below.
Determine optimum hydraulic parameters for the next using BHHP and IF criteria.
m = 1.47
D = √4At/3π
D = 0.432
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
Experiment No.7
Bit Hydraulics
Objective:-
STUDY AND DESIGN OF ROTARY DRILLING BITS, BIT PLANNING, ROP AND DRILL
OFF TEST.
Theory:-
The rate of penetration is achieved with the bit as well as the rate of bit wear. The most important
variables affecting penetration rate are- 1) Bit Type 2) Formation characteristics 3) Drilling fluid
properties 4) Bit operating conditions 5) Bit tooth wear 6) Bit Hydraulics.
1.Bit Type:
For roller cone bits, initial ROP is often highest in a given formation when using bits with
long teeth anf large cone offset angle. However these bits are practical only in soft formations
because of rapid tooth destruction and decline in penetration rate hard formations.
The lowest cost per feet is the objective while achieving highest ROP. Drag bits are
designed to obtain given ROP in hard formations. Drag bits give a wedging type rock failure in
which bit ROP per revolution depends on the no of blades and bottom cutting angle.
Diamond and pcd bits are designed for a given penetration per revolution by the selection
of the size and no of diamond or pcd blanks. The width and no of cutters can be used to compute
the effective no of blades length of the projectors/cutters projecting from bit face, limit the depth
of cut.
2. Formation characteristics:
The elastic and ultimate strength of formation are the most important formation
properties affecting ROP. The shear strength predicted by Mohr failure criteria, sometimes it
gives or is used to characterize the strength of the formation mouter reported the crater volume
produced beneath a single tooth is inversely proportional to both that is compressive and shear
strength of the rock.
The permeability of the formation has a significant effect on ROP. The drilling fluid
filtrate can move into the rock ahead often bit and equalise the pressure differential acting on the
chips formed beneath each tooth. These would tend to promote more expensive elastic mode of
crater formation. The nature of fluids contained in the pore faces of the rock affects these
mechanism, since more filtrate volume would be required to equalise the pressure in rock
containing gas than in rock containing liquid.
1
Well Engineering and Design 2015course
Rocks containing hard abrasive minerals can cause rapid drilling of a bit. The gummy
clay cause mineral can cause the bit to ball up and drill in a very inefficient manner.
ROP tends to decrease with increase fluid density, viscosity andsolids content ROP
increase with increase in filtration. The fluid viscosity controls the circulatory losses or parasitic
frictional losses and thus the hydraulic energy available of the bit jets for clearing. The chemical
composition of the fluid has an effect by way of hydration rate and bit balling tendency of some
clays on ROP. The presence of colloid size particles less than 1 micron are an order of magnitude
more efficient at plugging of the filtration beneath the bit. The pressure differential has effect on
ROP and has been described for Berea sandstone for clay H2o mud using 1.25” drilling cutter bit
of the rolling type. This is based in the experiment, similarly a no of other graph indicate
decrease in ROP with higher overbalance.
The graphs have been described for drag as well as rolling bits.
4. Operational aspect:
These have been very well explained by the graphs of WOB vs RPM. To optimise the bit
weight exponent and rotary speed exponent, the defailed drill-off test has been described
separately.
5. Hydraulics:
These plays very important role in multilateral and horizontals . On must prefer to the
API manuals and IADC bit selection, once the set of fluid properties are ready. Depending upon
the formation characteristic, depth and drilling data pertaining the mud related difficulties, you
should choose the level of hydraulics. Significant improvement in ROP can be achieved simply
by way off improved jetting action that is for an additional input to drilling as well as more
downhole volumetric floe rate to promote the early life of cutting, hence the bottom hole clean
up must be proportional to ROP. These could be observed by surface observation. This level of
hydraulics achieved at bit is to be decided by way of flounder point. At low bit rate and ROP, the
level of hydraulics required is small.as more weight is applied and cutting generated faster
flouder point is reached eventually where the cutting are not removed as quickly as they are
generated. If the level of hydraulics is observed / increased, a higher bit weight and ROP will be
achieved before floundering occurs. Various graphs of ROP vs Reynolds number function and
hydraulics HP/IF with higher Reynolds no, HHP and jet impact force.
The tooth length of milled tooth of rolling cutter bit is reduced continuously by abrasion and
chopping. Similarly, you may need to dress up the tipped tooth bit or to carry off hard facing that
1
Well Engineering and Design 2015course
is the process to promote a self sharpening type of tooth wear. The teeth of tungsten carbide
insert type rolling cutter bit facility by breaking rather than abrasion hence the projection and
tooth geometry is an important criterion while selecting used bits. One must follow IADC
selection criteria for old bits.
The type of lubrication and bearing is to be followed as per the maintenance programme
of the bit. The instantaneous rate of bearing wear depend on the current condition of the bit,
proper attention to damage bearing will enhance the life of bearing. Usually a linear rate of
bearing wear is assumed for a given applied force; the bearing life can be expressed in term of
total revolution (RPM) under the applied force, as long as the surface rotary speed is Lough
enough the prevent and excessive rise in temperature. The bearing life is assumed to be linear
with the rotary speed. Price of bit is lowest for non-sealed roller bearing and highest for sealed
journal bearing.
Effect of WOB on bearing life depends on the number and type of bearing, whether or not the
bearing is sealed. Lubrication is accomplished with the drilling fluid for non-sealed bearings,
again the properties of mud also affect the bearing life, as Q increases the ability of mud / fluid to
cool the bearing also increases, however to lift the cutting will also be sufficient to prevent
excessive temperature build up in bearing. Bearing life is estimated by formula given by
t = time in hours
Question 1:
A 8.625” diamond bit containing 270 diamond stones each of 0.23 inch diameter stones of
1.00carat is designed to operate at a depth of penetration of 0.01”. Estimate the overall ROP that
could be obtained if an acceptable bit weight and torque could be maintained at rotary speed of
200 rpm
Answer:
1
Well Engineering and Design 2015course
= 3.59
R = 24 ft/hour
Question 2:
The approach usually taken is to be assume that the effect of WOB, RPM, Tooth wear, etc on
ROP are independent of one of another and that the composite effect can be computed by
following form of equation
R = F1 * F2 * F3 * F4 --------- Fn
Where,
F1, F2, F3 represent fractional relations between ROP and various drilling variable, These are
based on laboratory or field data.
Reference
F1 = e 2.303 a1 = K
F2 = e 2.303 a2 (10,000 - D)
F3 = e 2.303 a3 D^0.69(g p - g)
F6 = (N / 60)a6
1
Well Engineering and Design 2015course
F7 = e – a7 * h
F8 = (fj / 1000)a8
In these equation
D = true V D, ft (Tvd)
F1 represent formation strength snf bit type effect on ROP. F2 and F3 model the effect of
compaction on ROP. F4 models the effect of overbalance on ROP. F4 model the effect of
overbalance on ROP. F5 and F6 model the effect of WOB and rotary speed. F7 models the effect
of tooth wear on ROP. F8 models the effect of bit hydraulics on ROP.
Question 3:
A 9.875 inch milled tooth opearated at 40000 lbf per inch and 80 RPM is drilling in a shale
formation at a depth of 12000 feet at ROP of 15 feet/hour formation PPG is equivalent to 12 ppg
and ECD of mud at bottom is 12.5 ppg. The computed jet impact force beneath the bit is 1200 lbf
and the computed frictional tooth wear is 0.3 compute the apperent formation drillability ‘f
’using a threshold bit weight of zero and the values of constant for the drilling condition are
given below a2 = 0.00007, a3 = 0.000005, a4 = 0.000003, a5 = 1, a6 = 0.5, a7 = 0.5, a8 = 0.5
Answer:
F2 = e 2.303 * (1000 - D)
= 0.724
F1 = e 2.303 (D^0.69)(g p - q)
= 1.023
= 0.6606
1
Well Engineering and Design 2015course
F5 = [(40/9.875) / 4]
= 1.013
By formulae,
R = F1 * F2 * F3 * F4 * F5 * F6 * F7 * F8
1. Select a depth to run a drill off test where a section of uniform litho-logy is expected.
2. While drilling with WOB currently in use, lock the break and determine the time required
to drill off 10% of this weight currently in use.
3. Increase bit weight to initial value of drill off test, these initial values should be at least
20% increase in bit weight over the bit weight currently in use.
4. Drill at this bit weight long enough to establish new bottom hole pattern of bit. The time
allowed is usually one characteristic time per 10% increase on bit weight for example
time interval of twice the characteristic time would be used for 20% increase in bit
weight.
5. Lock brake and maintain constant rotary speed record time, each time the bit weight falls
off 4000 lbs force. If weight indicator is fluctuating, use midpoint of fluctuation as bit
weight continue test until at least 50% of initial bit weight has been drilled off.
6. Make plot of ∆t vs W and R vs W. Using log-log paper. Slope of graph is bit weight
exponent deviation from straight line graph may occur at higher bit weight if bit
floundering occurs or is impending.
Hooke,
∞حδ
For axial tension in drill string, the stress change is equal to change in bit weight/ cross section
area of drill pipe.
The change in strain is equal to drill pipe length change per unit length.
1
Well Engineering and Design 2015course
∆W / As = E ∆L / L
∆W L / E As = ∆L
Average penetration rate for change in bit weight (∆W ) can be obtained by dividing above
equation by time interval ∆t to drill off ∆W
R = ∆W L / E As ∆t = ∆L / ∆t
Range to drill pipe have joint about 5% of drill length that have grater cross section area area
than pipe body.
R = ∆W L / E As ∆t * 0.95
Length change of drill collar is small that can be ignored or taken into account.
Using the following data evaluate bit weight expressed and rotary speed exponent
The evaluation of slope of straight line portion yield value of 1.6 this is bit weight exponent
value below flounder region.
1
Well Engineering and Design 2015course
Procedure:
If ROP = 13.7 ft/hr for WOB = 58000 lbs and N = 150 rpm on graph.
Reduce N to 100 rpm for these point, we will get ROP = 10.7 ft/hr for some WOB.
R = K N a6
13.7 = K (150) a6
10.7 = K (100) a6
S, K = proportionality constant
1.280 = (150/100) a6
1.280 = (1.5) a6
a6 = ln 1.280/ ln 1.5
a6 = 0.6
Conclusion:
These value of bit weight exponent and rotary speed exponent below floundering region gives
optimum ROP and be used to determine highest WOB and RPM in standard equation for ROP.
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
Experiment No.8
Casing Shoe Depth Selection
Objective:-
Theory:-
In this experiment, we are solving the problem of depth selection of casing seat or shoe. The
requirements to approach the selection of depth are:
1. Target Depth
2. Poisson Ratio
3. Overburden Pressure or gradient
4. Formation Fracture Pressure
5. Formation Pressure against depth
Target depth is given to us. If Poisson ratio is not given then it is calculated on depth basis as
Where D=ft
f = porosity
From this given things we now start our calculation part by first calculating the Formation
Fracture Gradient. This is done by two methods:
1. Direct Method
2. Indirect Method
1
Well Engineering and Design 2015course
Theory:
Leak off test is to test the formation just below casing shoe to determine fracture gradient of
the formation by pressurizing fluid in casing in increments and recording the pressure when
initial leak-off starts. This is a field method of determining fracture strength of the formation
just below casing seat. This also tests the cement job of casing along with competency of
formation to withstand pressure without fracturing.
Necessity of LOT:
While drilling after intermediate casing, weakest formation is generally near the previous
casing shoe. This formation must stand maximum mud weight to be used to drill open hole,
to control kick and maximum allowable surface pressure to control kick without fracturing
formation at shoe.
In directional well, formation breakdown pressure can occur at values higher or lower than
fracture propagation depending on hole inclination & azimuth. In deviated well, σ3 is
considerably different from σ2.
=LOT pressure + ρ d / 10
Max allowable surface pressure= New mud weight- Old mud weight × d / 10
1
Well Engineering and Design 2015course
Eaton’s Formula:
This is indirect method and Eaton’s formula is derived by Hubbert and Willie method.σ1, σ2 and
σ3 are principal stresses. σ1 acts vertical, σ2 and σ3 are horizontal and directly influence
fracturing rock. So; hydrostatic head should be equal or greater; fracture occur when applied
fluid pressure exceed the sum of min effective stress. Effective stress is defined as difference
between total stress and pore pressure
σ1’= σ1-Pf
σ2’=σ2- Pf
σ3’=σ3-Pf
Now,
Also,
Therefore, ε2=ε3=0
0=
Fracture Pressure=σ3’+Pf
= +Pf
or dividing by depth D
1
Well Engineering and Design 2015course
Where,
µ=Poisson’s Ratio
σ1=overburden pressure
After calculating all these parameters we plot a graph of depth vs. pressure (MWE), Depth vs.
min mud weight required and depth vs. formation fracture gradient.
Draw a vertical line from point w.r.t. target depth and design formation fracture gradient in
MWE. The point at which the vertical line intersects the fracture pressure gradient is the tentative
casing seat for intermediate casing or liner.
Now we check the casing w.r.t. differential sticking point and kick tolerance aspect as we now
have the tentative depth for casing seat.
1
Well Engineering and Design 2015course
The pressure is MWE and from this we find another depth (D2) which is depth of casing
seat/shoe to avoid differential sticking point.
Where,
ρ1= min mud weight required at target depth
D1= Target Depth
D2=Depth from differential sticking point calculation
Now, difference between formation fracture gradient at tentative seat and kick impact tolerance
is between 0.2 to 0.4 ppg or 0.02 to 0.048 MWE
1
Well Engineering and Design 2015course
= (1.65-1.05) 1300/10
= 72.8 kg/cm^2
= 1033.76 psi
= 2.124
a = 2.1 – 2.124
1
Well Engineering and Design 2015course
Experiment No.9
Casing Grade Selection
Objective:-
Theory:-
One of the most important factor in casing design is casing material selection in this, we consider
two parameter of material that is,
1. Collapse
2. Burst
Collapse Pressure:
It is the net external pressure imposed on the pipe. The condition when maximum
collapse pressure is taken as basis of design. Maximum worst condition occurs when pipe is
empty and hydrostatic pressure is exerted to pipe from outside H.P increase with depth, hence we
should chose the material considering this also,
P = ρ * d / 10
Burst Pressure:
It is the net interval pressure that is difference between internal and external pressure
acting on pipe for maximum internal pressure. Casing is considered to be filled completely with
gas at B.H.P for minimum external pressure, the hydrostatic load/head of salt water is supposed
to act from outside.
Then, the casing is subjected to maximum burst pressure near the surface where external
pressure is minimum.
1
Well Engineering and Design 2015course
B.H.P = ρ * d / 10
I. Design factor for tension = Pipe body (yield strength) / Total weight in air.
and should be greater than 1.8 to 2.
II. Collapse = Collapse Resistance / Collapse Pressure {>1.25}
III. Burst = Internal yield pressure / Burst pressure at surface >{1.1 kg/cm2}
Problem:
9 5/8” 0 to 2940
Solution:
Collapse Pressure = ρ * d / 10
1
Well Engineering and Design 2015course
= 1.68 * 2940 / 10
= 493.2 kg/cm2
Burst Pressure = B.H.P = ρ * d / 10
= 2.1 * 4000 / 10
= 840 kg/cm2
1
Well Engineering and Design 2015course
= 624.85 kg/cm2
= 510.9 kg/cm2
At surface = 0
=14.58 kg/cm2
Net burst
= 558 / 493.5
= 716 / 510.9
1
Well Engineering and Design 2015course
III. Design factor for tension = pipe body yield strength / total weight in air
= 774 / 0.079 * 2940
= 3.3 Grater than 1.8 kg/cm2, hence safe.
D = 1962
= 61.3
= 0.079
= 363.67 Kg/cm2
D = 1912 m
Again calculate for 1912 biaxial effect weight of section = 1028 * 0.786 * 80 / 1000
= 64.64
1
Well Engineering and Design 2015course
= 0.0835
= 268 / 1.125
ρ * d / 10 = 238.22
1.691 * d / 10 = 238.22
D = 1409 m
= 92
X = 0.2, Y = 0.922
= 248.97
D = 1309 m = 1300 m
= 98.07
1
Well Engineering and Design 2015course
Y1 = 0.922
= 247.09
= 144.48 tonnes
= 214.48
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
Experiment No.10
Cement Slurry Calculation
Objectve:-
Theory:-
Cement:
Step 1:
Step 2:
Step 3:
Sack required in casing = number feet into f/s to f/s * casing capacity / (yield of ft3 / sack)
1
Well Engineering and Design 2015course
Calculation:
1
Well Engineering and Design 2015course
= 553 sacks
= 553 * 94
= 51986.08 lb
= 983 * 94
= 92402 lb
= 42 tonnes ------------- 2
30.72 * 94 = 2888 lb
Adding 1, 2 and 3
1
Well Engineering and Design 2015course
Experiment No.11
Well Control
Objective:-
Theory:-
4. Final circulating pressure with kill mud = slow pump rate pressure * (Kill mud
weight/O.M.W)
Drillers Method:
First circulation
a) Bring the pump to kill speed in steps of 5 spm, gradually opening the choke holding
the casing pressure constant.
b) When pump is up to kill speed, maintain drill pipe pressure constant.
c) Circulate out influx from the well maintaining drill pipe pressure constant.
d)When the influx is out, stop the pump reducing the pump speed in steps of 5spm,
gradually close the choke, maintain casing pressure constant. Record pressure, SIDPP
and SICP should be equal to original SIDPP.
Second circulation
a) Line up suction with kill mud.
b) Bring the pump up to kill speed in steps of 5spm,gradually opening the choke holding
casing pressure constant .
c) When pump is at kill speed , pump kill mud from surface to bit, maintaining casing
pressure constant.
d) Pump kill mud from bit to surface , maintaining drill pipe pressure constant equal to
FCP.
e) When the kill mud reaches the surface , stop the pump reducing the pump in steps of 5
spm, gradually closing the choke maintain the casing pressure constant. Record SIDPP,
SICP both should be equal to zero.
1
Well Engineering and Design 2015course
Procedure:-
a) Line up suction with kill mud.
b)Bring pump up to kill speed in steps of 5spm, gradually opening the choke, holding casing
pressure constant.
c) when the pump is at kill speed, pump kill mud from surface to bit , maintain drill pipe pressure
as per step down schedule ( during this step drill pipe pressure will fall from ICP to FCP ).
d) Pump kill mud from bit to surface, maintain drill pipe constant equal to FCP.
e) When kill mud reaches surface, stop the pump reducing the pump speed in steps of 5 spm,
gradually closing the choke maintaining casing pressure constant. Record SIDPP, SICP both
should be equal to zero
PROBLEM:
SIDP = 500 psi
SICP = 700 psi
Slow pump rate pressure (KRP ) = 550 psi at 30 SPM
Mud Pump Output = 0.107 bbl/Stroke
OMW = 12.8 ppg
Hole Depth = 14325/11520 ft
9 5/8 shoe depth = 12220/10175 ft
5” DP Capacity = 0.0178 bbl/ft
5” HWDP = 420 ft, capacity = 0.0088bbl/ft
DC, 6.25”, 800ft long, capacity = 0.006bbl/ft
Volume open hole / collar = 0.0322 bbl/ft
Volume open hole/ DP/HWDP = 0.0473 bbl/ft
Volume csg/ DP = 0.0493 bbl/ft
Prepare kill sheet
1
Well Engineering and Design 2015course
ρm
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
1
Well Engineering and Design 2015course
References
1. Gatlin C.; Petroleum Engineering, Drilling and Well Completions, Prentice Hall.
2. Rabia H.; Oil Well Drilling Engineering, Graham Trotman Ltd., London.
4. Drilling Mud and Cement Slurry Rheology Manual; Gulf Publishing Company.
1
Well Engineering and Design 2015course