Specification
Specification
19102 - 2019
April 2019
Email: skylne90280@gmail.com
Tel: 04-2516182
Fax: 04-2516183
P.O. Box 90280
Dubai, UAE
THE CONTENTS OF VOLUMES ARE AS FOLLOWS :
Content
3- CONDITIONS OF CONTRACT
6- BILL OF QUANTITIES
1.4. Penalty for the delay of work. : Dhs.60,000 /- per month to the owner and
Dhs.15,000/- per month to the consultant.
1.5. Period of maintenance : 365 days from the preliminary handing over.
The certificate to this will be issued from the consultants.
1.9. Third party insurance : Shall be provided from the contractor for himself & for
the project as per Clause 23.1 of the FIDIC
1.10 Time required for certification : (i) 7 days for interim payment
of bills by the consultant (ii) 15 days for the final payment
1.11. Time within which payment : (i) 10 days for interim payment
To be made by the owner after (ii) 15 days for the final payment
Certification
1.14. Over-Time Fees upon Request : Dhs. 200/- per hour to be on normal working days
Dhs. 300/- per hour to be on Friday's, Saturdays &
Declared public holidays.
1.16. Performance Bond : the winner contractor to change the Tender Bond into
Performance Bond (0% of the contract value), for a period of
0 months.
1.18. Any tender not including the fully detailed pricing of the bill of quantities in addition to the
information mentioned in item 1.19. Page No. 5 will be rejected.
1.19. The several documents forming the contract are to be taken as mutually explanatory of one
another, but in case of ambiguities or discrepancies the same shall be explained and adjusted by the
engineer who shall thereupon issue to the contractor instructions thereon and in such event, unless
otherwise provided in the contract. The priority of the documents forming the contract shall be as
follows:
1. The contract agreement (if completed)
2. The letter of acceptance;
3. The tender;
4. Part II of these conditions ;
5. Part I of these conditions ; and
6. Any other document forming part of the contract
Proposed Villa
( B + G + 1)
To:
P. O. Box
………., U. A. E.
Sir,
Having examined the Tender and Contract Documents for the Construction of the above named
works, we, the undersigned hereby offer to construct, complete, maintain and deliver up the whole
of the said works, in strict conformity with the said Tender and Contract.
Only or such other sum as may be ascertained in accordance with the said Conditions.
We undertake in the event of this Tender being accepted, with the understanding that you are not
bound to accept any tender you may receive, to execute when called upon by you to do so, a
Contract for the works in the terms of the article of Agreement which my be altered and added to in
such a manner as you may require for the purpose of the adapting it to the circumstances of this
Tender.
We undertake to complete and deliver up the whole of the works within the period named in
Appendix “A” to the form of Tender from the date of receipt by us of order to Commence with the
works, and furthermore complete the different parts of the works define in our program of works
within the time limits therein guaranteed.
We enclosed our Tender guarantee m the name and qualifications of the Site Agent whom we
propose to put in charge of the works, and also specifications of constructional plant which we
undertake to provide for the execution of the works.
Unless and until a formal Agreement is prepared and executed this Tender, together with your
written acceptance thereof, shall constitute a binding Contract between us.
Signature ………………………………………………
Address ………………………………………………..
To:
Sirs,
Project :-------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
The guarantee shall remain valid and irrevocable for a period of ninety (90 days) starting at twelve
(12) O’ clock noon on the day for the receipt of the tenders.
Yours truly,
(Signature)
Dear Sirs,
As Messers--------------------------------------------------------------------------P.O. Box--------------------
-have been declared that, their Tender for the construction of the above named works has been
accepted, we hereby undertake to hold at your disposal the sum of U.A.E Dirhams.--------------------
------------------------------------------------------------------(Dhs. -------------------------------)
As Performance Bond or Surety which constitutes percent (10%) of the tender sum. This bond
shall be free of interest and payable to you in cash on your first demand without the right to object
or suspend payment thereto for any reason whatsoever.
This undertaking shall remain in force from ----------------------- until--------------------- and will be
automatically renewed before expiry for period of these months each if the original guarantee is not
returned to our bank.
Yours faithfully,
Authorized Signature
Between
Hereinafter called “the Employer” of the one part
And
Hereinafter called “the Contractor” of the other part
Whereas the Employer is desirous that the Works as described in the Contract Documents and
shown on the Drawings prepared by
Messrs ………………………
P. O. Box
……., U. A. E.
be carried out and has accepted a Tender by the Contractor to construct, complete, maintain and
deliver up such Works, during the Contract period, and in the manner mentioned.
And whereas the Contractor undertakes to complete, maintain and deliver up the whole of the said
works, within the Contract period.
1. In this Agreement wards and expressions shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents shall be deemed to form and be read and constructed as per of
this Agreement, viz:
a) Tendering Conditions.
b) Appendix ‘A’ and Forms.
c) Conditions of Contract.
d) Specifications.
e) Drawings.
f) Bills of Quantities.
g) Addenda and Circular Letters (if any).
h) Letter of acceptance.
4. The Employer hereby covenants to pay the Contractor in consideration of the construction,
completion, maintenance and delivering up the Works the Final Contract price at the times, and
in the manner described by the Contract Documents.
In Witness whereof the parties hereto have set their respective hands and seals the day and
year first above written.
Contract value Dhs.
Amount in words
Contract period
Liquidated Damages
Employer
Signature
Name
Address
Contractor
Signature
Name
Address
Witnessed by
Signature
Name
Address
Signature
Name
Address
(General Condition of contract shall be as per the conditions of contract laid by Federation
Internationale Des Ingenieurs Conseils (FIDIC) Fourth Edition 1987.)
General notes for the Tender & specifications of this mentioned edition is considered part of this
tender and contract:
2.1 General Condition of contract shall be read in conjunction with General notes for the
tender, specification & drawings.
2.2 Tender document along with BOQ to be filled properly without any conditions. In case of the
missing basic price, the bidder shall indicate the basic price of the material which is taken into
consideration while evaluating the item rate of the work to be executed; if the contractor
ignores the basic price the consultant has the right to choose any material.
All the items has to be filled even though it is not specified in the specification (rate wise)
2.3. The contract is a lump sum priced contract. No variation will be accepted unless it is an
additional item of work instructed by the consultant after the approval of the owner the
same shall be recorded prior to the commencement of work.
2.4 All the documents collected from the consultant office along with drawing and also the fax
messages (if any, which are sent across clarifying the queries of the contractors) becomes part
of the contract document and the same shall be stamped, signed and handed over to the
consultants while submitting the tender document.
2.5. Mobilization of the work at site shall be within 30 days from demarcation or as
instructed by the consultant, which shall include the following:
- Site offices
To be as follows:
One site office for the contractor.
One site office for the Consultant including meeting room (30sq.m), RE office (20 sq.m.) and bath
room.
The areas of the site offices to be up to the consultant approval.
The office shall be provided with all the equipment necessary for their efficient operation. The
equipment to be provide for the Engineer’s offices, shall include, but shall not be limited to the
following:
1executive desk with lockable drawers, executive swivel chair
1desks with lockable drawers upholstered swivel chair
6 chairs with upholster seat and back on steel frame
1 full size drawing board with stand, stool, parallel motion
1 layout table for drawings
1 Large steel cupboard
1 vertical hanging unit for drawings
3 correspondence trays with spacers
2 waste paper baskets
1 portable dry powder extinguisher
2.7 The contractor must adhere to the latest rules and regulations of S.E.D, water supply/drainage
Dept. Civil Defense and Etisalat or du etc. In connection with the above service the
contractor shall approach the necessary authorities at times of need.
2.8 Contractor shall submit their list of sub contractor to execute all the services connected with
the bldg. for the approval by the consultant.
2.9. Selected contractor shall submit the sample chart of all the materials including certification of
geniuses for the consultant's approval & the same shall be made available at the site for the
entire tenure of the contract.
2.10. The selected contractor shall submit the detailed CPM & time BAR CHART which shall also
indicate the clearances /details / drawings etc. which are required from the consultants for the
uninterrupted work at site. The above said charts shall be submitted to the consultant prior to
commencement of the work at site.
2.11. The selected contractor shall also submit the tentative CASH FLOW CHART required for the
uninterrupted work at site which is to be evaluated from the work progress chart.
2.12. Contractor shall depute for the full time engineer as per clase 2.30
2.13. For all site meeting the main contractor shall depute qualified engineers of various
disciplines. viz. electrical, plumbing, air conditioning etc.
*All the above persons mentioned in item no. 2.12 & 2.13 are subject to the final approval of
the consultant and subject to removal from site for any mistake as per the consultant opinion.
2.14. The contractor if asked by consultant shall produce shop drawing for electrical, plumbing,
fire fighting, Aluminum work and also any other drawing
2.17. Taking over certificate will be issued only after the execution of the entire job as per the
scope of work of the contract & to the satisfaction of the consultant & after getting clearance
from all the departments required for the municipality checking. This also includes testing,
commissioning and rectifying the defects if any.
2.18. Defects liability period (Maintenance Period) shall be for one year and the same shall
commence from taking over date. In this period contractor shall rectify all the defects within
15 days from date of receiving the defect note or informed by the Consultant failing which the
same will be executed by hiring out side agency and the cost will be reimbursed from the main
contractor.
2.19. No variation is allowed unless by written instruction from the consultant, the rate for the
same to be finalized from the consultant/ his representative along with the consent of the
owner when all the documents of the variation is completed as per consultant opinion. The
rate of an extra item shall be evaluated on a prorate basis from an identical item for which the
rate is already agreed in the contract document, and in case of a new item, the contractor shall
submit the detailed break up to evaluate the cost of the item. Work order for the execution of
an extra term shall be collected from the consultant’s office prior to the commencement of the
work at site.
The contractor has to check the approved drawing with the tender drawing & submit the
claims (if any) within 14 days from receiving the approved drawing. The claims after this
period regarding any matter will not be considered
2.20. All the jobs shall be executed in proper line level, plumb & to the consultant’s satisfaction.
2.21. The consultant reserves the right of shifting the location of service connection subject to the
site conditions and within the flat. viz. electrical points, distribution board, kitchen sink,
ceramic fixtures etc.
The location of the above shall be discussed with the consultant at the time of preparing the
shop drawing Contractor won't be paid any extra amount for doing the above unless it is an
additional item of work by numbers.
2.22. All the light fixtures supplied shall be installed and commissioned by the main contractor.
2.24. Contractor shall take up one number of Macks up office and the same shall be finished in all
respect including door, window, ceramic fixtures, filling etc. completely.
2.25-(i) Contractor shall include in his bid to execute all the civil works whatsoever and are related
to the jobs of the specialized agencies (Ref.: items excluded) and are not mentioned in the
B.O.Q. viz.
(1) P.C. foundation pad for A/c outdoor units.
(2) P.C. foundation for water tank. Etc.
(3) P.C. foundation for transformer
(4) Builders work for MEP subcontractor or any other subcontractor.
(5) Main contractor shall also coordinate with all the agencies involved in the execution of the
project.
2.27- As built and guarantee: Provide As built drawings and guarantees as indicate here below but not limited to the
following items:
Guarantee should be from the date of releasing the taking over certificate.
TENDER No. 19102 /2019 18/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
2.27. SIGN BOARD SKETCH: with total Number of 1 signboard.
one illuminated sign boards shall be provided in Arabic and English giving names of the “EMPLOYER”,
“ENGINEER”, and “MAIN CONTRACTOR” only, and strictly in accordance with the format shown here with. The
signboards shall be illuminated adequately and as indicated on Drawings. The perspective view will be as agreed by
the Engineer.
The signboard shall consist of a supporting structure securely anchored to the ground and with sign plates fitted on it.
All working details including sitting and positioning shall be submitted for approval and shall be approved before
fabrication or erection commences. The signboards shall be properly illuminated to the required illumination levels and
good Engineering Standards and to the approval of the Engineer.
The contractor shall comply with current regulations of the Municipality and obtain approval of the Municipality. The
Contractor shall keep clean and maintain the signboards and remove them and make good all woks disturbed upon
completion of the Contract. The Contractor shall provide space for signboards and pay all costs in connection with
them including Municipality.
Construction Progress – Activities performed and progress achieved. Actual versus Planned by subcontracts
and overall Construction.
Plans and Schedules including important activities in the immediate future, updates, and forecasts.
Site Materials delivery details and forecasts including specific information on late Materials deliveries likely
to affect progress.
Progress, productivity, and man-hour data to include planned, actual and forecast progress together with
trend identification and analysis, by each Sub-Contract.
Project Schedule Status, highlighting the status of Critical activities along with schedule trend analysis
indicating the actions proposed to be taken to ensure timely completion of the Project.
Project Milestone Status
Drawings and Materials hold-up analysis and report.
Productivity analysis for each Sub-Contractor.
Project Trends Summary.
The contractor has to provide high technical staff to execute the project and he has to get the
consultant approval first
The contractor shall nominate a site quality control manager for approval by the Engineer. The quality
control manager will be an employee of the contractor, reporting directly to the contractor’s main office,
and to the Engineer. Additionally, the Quality Manager will remain independent of the Contractor’s field
operations, and have the authority to accept or reject the Contractor’s work.
The contractor shall provide and maintain an effective quality control system, the contractor shall be
responsible for ensuring that his sub-contractors and suppliers conform to the quality requirements as
provided in the contract documents.
The contractor shall establish a “Quality Control” (QC) system to perform sufficient inspection and tests of
all items of work, including that of his sub-contractors and nominated sub contractors to ensure that all
aspect of supply, construction, finishes, technical and functional performance, and prescribed in the contract
except where the technical provisions of the contract provide for specific control by inspections, test or
other means. The contractor’s QC system shall specifically include the surveillance and tests required in the
technical provisions of the Specification.
The contractor’s QC system is the means by which the contractor assures himself that his construction
complies with the requirements of the contract documents. The controls shall include as a minimum at least
three phases of inspection for all definable phases of construction as follows :
a. Preparatory Inspection : Preparatory inspection shall be performed prior to beginning any work on
any definable phase of construction and as shown in the approved construction programme. It shall
include a review of contract requirements: a check to assure that all materials and / or equipment
have been tested, submitted and approved; a check to assure that provisions have been made to
provide required control testing ; and plan mock ups where appropriate and as required by the
Engineer; examination of work area to ascertain that all preliminary work has been completed; and
a physical examination of materials and equipment to assure that they conform to the approved shop
drawings or submittal data and that all materials and / or equipment area on hand. The Engineer
shall be notified at least twenty four (24) hours in advance of the preparatory inspections and such
inspections shall be recorded in the QC report as specified herein.
b. Initial Inspection: Initial inspection shall be performed as shown in the approved construction
programme and as soon as a representative portion of the particular phase of the construction has
been accomplished and shall establish the acceptable standard of workmanship, including a review
of control testing for compliance with contract requirements, review of mock up, identifying
defective or damaged materials used, omissions and dimensional requirements. The Engineer shall
be notified at least twelve (12) hours in advance of the initial inspection and such inspection shall be
recorded in the QC reports as specified herein.
The contractor and sub contractors shall operate a quality system in accordance with ISO 9001 or ISO 9002
and shall furnish to the Engineer for his review as soon as practicable and in no event later than thirty (30)
Construction operations will not commence until the contractor’s QC plan has been accepted by the
Engineer. However, the Engineer may permit at his direction to proceed on specific phases of construction
for which the plan has been submitted and accepted. Progress payments will not be processed for any
portion of work that has QC requirements until that portion of the QC plan has been submitted and accepted.
Prior to submittal of the Contractor QC plan for acceptance, the contractor shall meet with the engineer to
discuss the QC system. The meeting shall develop mutual understanding relative to details of the system,
including the forms to be used for recording the QC operations, inspections, administration of the system.
The contractor’s QC organization shall be sufficiently staffed to perform the following tasks :
a. Conduct phased inspection (preparatory, initial and follow-up) as described above.
b. Perform all testing required under the Contractor’s QC reports hereinafter.
c. Prepare daily QC reports in accordance with contractor’s QC reports hereinafter.
d. Review and approve all submittals including shop drawings.
e. Inspect materials as they are delivered on site to ensure compliance with approved shop
drawings and contract specification.
f. Conduct off-site inspections of supply items fabricated or assembled and services to be
incorporated into the works. Provide monthly report of off-site QC activities. The contractor’s
QC representative at the fabricating plat shall be responsible for the release of the fabricated
items for shipment to the site job.
g. Maintain record of all QC activities. These records shall be made available to the engineer.
The contractor shall, within ten (10) days of issue of the letter of acceptance, report to the Engineer, the
names and qualifications of personnel assigned full time to the QC function for approval of the Engineer.
The named personnel shall prepare the QC programme and remain as the basis of the QC staff until a QC
program has been submitted and accepted.
If at any time during the life of the contract the Engineer determines the QC staff is not capable of
performing all the tasks listed above, then the Engineer may direct the contractor to revise and/or
supplement the present organization structure at no additional cost to the Employer.
Contractor’s QC Reports : The contractor shall submit a daily QC report in triplicate not later than the end
of the next working day. The report shall contain a record of inspections and tests for all work accomplished
subsequent to the previous report and shall include the following information.
a. Trade(s) of construction underway during the time frame of the report (i.e. earth work,
concrete work, structural steel erection , etc)
a. Latest Document
The QC programme shall provide for procedures which will ensure that the applicable portions of the
contract (and any variations thereto made in accordance with clause 51 of the general conditions of
contract) and the latest approved shop drawings and samples are used for fabrication.
c. Test methods
The test shall include typical, routine and sample tests specified in British Standard or ASTM or
equivalent International standards relating thereto and those corresponding to any special requirements
or change contained in the specification. In addition, the Engineer may direct special tests to be made to
prove that the equipment and materials supplied comply with the specification. The methods of tests for
equipment and materials not covered by a recognized standard and for which tests have not been
specified shall be as directed by the Engineer.
Should the employer decide not to send an inspector the manufacturer’s works, the contractor shall
obtain from the manufacturer, certificates of test, etc.., showing that the materials have been tested in
accordance with the requirements of the specification, but the omission of the employer to send an
inspector no the submission or manufacturer’s certificates of test as aforesaid shall not relieve the
contractor from his contractual responsibilities and commitments or shall affect the right of the
Employer or the Engineer to reject after delivery materials found to be unsuitable in accordance with the
specification. The contractor shall meet all expenses in connection with the testing and inspection.
Which is Contain:
Description
01 – Tender Documents:
Complete tenders shall be submitted in a sealed envelope as described in the Letter of Invitation to
Tender.
03 – Validity of Tenders:
Tenders shall remain valid for ninety (90) days from the date fixed for submission of tenders.
04 - Tender Guarantee:
Each Tenderer shall submit with this tender a Tender Guarantee in a sum equal to three percent
tender sum issued by an approved local Bank in the form included herein. The tender shall be
retained by the Employer as a guarantee of a good faith of the Tenderer for the performance of the
obligations and commitment undertaken by the Tenderer.
In the case of unsuccessful Tenderers the tender guarantees will be retained until the end of the
period of validity of the tender or until such earlier time as a tender for the contract shall have been
definitely accepted where after unsuccessful Tenderers may withdraw their tender guarantee.
The Contractor whose tender is accepted, shall be requested to execute within fifteen (15) days
from the date of issuance of the Notice of Acceptance of his tender, a formal Contract in the Form
of Agreement annexed hereto and shall provide within the above mentioned period a “Performance
Bond” issued by a local Bank approved by the Employer to the value stated in the Appendix “A”
and as stipulated in the conditions of Contract.
The tender guarantee shall be released only at the date of signing the Contract and handing over the
performance bond to the Employer.
Should the Contractor, for any reason, fail to provide a performance bond or execute the Contract
Agreement within the above stated period and as stipulated in the conditions of the Contract, the
Employer has the full right to confiscate the tender guarantee and the Contractor shall have no right
to claim refund or compensation.
The performance bond shall be retained by the Employer during the period of the contract and shall
only be released when the works are satisfactorily completed in accordance with the conditions of
Contract.
Tenderers shall in addition to the requirements of clause 04 of the General obligations (Inspection
of Site), satisfy themselves as to the sources, sufficiency, availability, means of obtaining and
delivering materials, water, fuel, power, labour, transport, accommodations of personnel if
necessary and any other matters or things required for the construction and influence the pricing of
their tender.
Should the Tenderer fail to obtain information as to the nature of the site and of his various
obligations under the terms of the Contract, he (the Contractor) shall not be relived of any of his
responsibilities and liabilities.
All expenses incurred by Tenderers in the preparation of their tenders, and site visits connected
therewith shall be t the sole expense of the Tenderers. The Tenderers shall have no right to claim
for any expenses or charges incurred due to such visits or investigations
Neither the Engineer nor any Agent of the Employer shall have any authority to make
representation or explanation to tenderers as to the meaning of the Contract documents or as to
anything to be done or supplied by the Tenderer or to any other matter or thing so as to bind the
Employer or fetter the judgment or discretion of the Engineer in the exercise of his powers and
duties under the terms of the Contract.
08 – Prices to be Inclusive:
The rates and prices set down by the Tenderer against the items in the Bills of Quantities are to be
the full inclusive value of the finished work described there under and are to include for all
Contractor’s overheads, profit and all other obligations and liabilities which, under the Contract,
are to be borne by the Contractor.
Each item in the Bills of Quantities is to be priced or if any items are left unpriced the Tenderer
must indicate the value of the work described there under as being allowed for elsewhere.
Any Alteration in the prices of the Bills of Quantities shall be installed by the person signing the
Form of Tender; uninitialled corrections shall not be considered and shall subject the tender to
rejection.
The Contractor shall be responsible for errors which he may make in computing any quantities of
materials and labour required or costs involved or through any lack of knowledge of the site or
misunderstanding of anything shown or implied on the drawings or in the specifications and/ or the
Bills of Quantities.
The Contractor must refer any discrepancy in the drawings and/ or the specifications to the
Engineer before submitting his tender otherwise the decision of the Engineer as to the
interpretation of the discrepancy will be final.
Any item or items of work not specifically shown on the drawings or referred to in the
specifications, but which would be necessary for the proper construction of the works in
accordance with the best practice is implied and must be included for in the tender sum.
Any item for which the Contractor has not inserted a price in the Bills of Quantities shall be
deemed to be covered by other prices or rates therein.
The Tenderer may be asked for and should be prepared to furnish forthwith and when so requested
a price analysis for any item priced in the Bills of Quantities. Likewise during the Contract
(construction) period, the successful Tenderer shall furnish price analysis for any item when
requested to do so by the Engineer.
11 – Correction of Errors:
The rates and prices inserted in the tender documents will be examined prior to award of the
Contract in order to ensure that the items are extended correctly at the rates quoted. Generally,
should any errors be found, the rate will remain unaltered and the extended amount will be
corrected, unless there is and obvious typographical error, in which case the more realistic figure
shall be inserted. The total amount of the tender shall be amended accordingly. Any or all
corrections necessary may be made without reference to the Tenderer.
And the tender price shall be revised accordingly and shall be used for the purpose of comparison
with other Tenderers.
Failure of the Engineer to discover any error during the analysis of the tender shall not entitle the
successful Tenderer (or any other Tenderer) for any claim against the error if it is subsequently
discovered.
12 – Tenderer’s Address:
The successful Tenderer shall have an address in the country where the works are to be executed.
Each Tenderer shall give with his tender an address at which notices may be validly served on him.
All notices shall be deemed to be validly served which are left at such address or are sent there by
post and every letter sent by post shall be deemed to have arrived in due course of post unless the
contrary is shown.
Should there be any doubt or obscurity in the meaning of any of the tender documents or as to
anything to be done or not to be done or as to any other matter or thing, the Tenderer must set forth
such doubt or obscurity in writing and submit same to the Engineer not later than one week before
the date fixed for the delivery of tenders. The clarification in the form of an addendum or circular
letters will be distributed to all Tenderers to whom a set of tender documents has been issued.
14 – Construction Programme:
Tenderers shall submit together with their offer a tentative construction programme in the form of a
bas chart indicating the dated of commencement and completion of each operation and the date by
which the Tenderer shall complete the construction of the works.
15 – Acceptance:
The Employer has the right to accept or reject any offer or to cancel the Tender and stop the
bidding without giving any justification.
16 – Partnership of Contractors:
“Partnership of Contractors” as used in these instructions shall mean an actual partnership, merger
of companies, joint ventures or any combination of Contractors or Contracting Companies joined
together for the purpose of tendering for this Tender.
Where several Contractors (local or local with foreign) decide to tender in partnership, such
partnership will have to be registered in the country where the works shall be constructed. The
partnership shall be registered either before the submission of the Tender, or before signing of the
Contract, the latter case being where the partners would have decided to become associated only if
they were awarded the Contract.
The partnership of the Contractors shall be for the whole duration of the Contract, otherwise the
Employer shall entitled to cancel the Contract immediately without any formalities, and to apply
the procedures stipulated in clause 56 (1), (2), and (3) of the conditions of Contract concerning the
forfeiture of the Contract.
It is imperative that the partnership of Contractors shall present a copy of the registered partnership
agreement indicating the persons who have the right to enter into Contract in the name of the
partnership, the extent and limits of such rights, the responsible person who will execute this
Contract, provided that they have the right to give correct statements in the name of the
partnership. Samples of the signatures of the aforesaid persons are required. The Tenderers shall
also submit a copy of their commercial register as legally approved by the Government Authorities.
The “Partnership of Contractors” shall submit with the Tender:-
An affidavit, signed by the parties of the partnership, declaring that they may be had jointly
liable.
The Contract of partnership they intend to register or an affidavit signed by all parties of the
proposed partnership and the draft of the proposed Contract.
Specialized Sub-Contractors for all specialist/ major work shall be of a high standard to the
approval of the Engineer
The Contractor shall submit with his tender as least three of qualified and top quality Sub-
Contractors for any and all trades which he intends to sublet, which shall be subject to the approval
of the Engineer.
The Engineer shall have the right to approve any one of the proposed Sub-Contractors and reject
others, or to reject all of the proposed Sub-Contractors. The Contractor shall then response further
three names for the Engineer’s approval. The Engineer shall review the resubmission and shall
have the right to select any one of the re-proposed names or reject all. The Contractor shall re-
propose and repeat the process till final approval is accorded by the Engineer. The Contractor shall
not be entitled for any claims in terms of money or time due to any revised proposal or delays
caused due to the approval process.
19 – Alternative Tenders:
In the event that the Tenderer wishes to submit and alternative tender based on specifications other
than those in the Tender Documents, this alternative will only be considered provided that a Tender
fully complying with the conditions laid in the Tender Documents is also submitted. The Tenderer
shall give full details of such alternative specifications together with the effect, if any, on the
Tender Sum. The Employer shall be free to accept whichever Tender he may choose. Alternative
Tender must be submitted along with the main Tender and shall be endorsed “Alternative No. 1”
Contract documents
05. (1) Language/s and law 37
(2) Documents mutually explanatory 38
06. (1) Custody of drawings 38
(2) One copy of drawings to be kept on site 38
(3) Disruption of progress 38
(4) Delay and cost of delay of drawings 38
39
Further drawings and Instructions
General obligations
Sufficiency of Tender
Labour
34 Commencement of Works 56
35 (1) Possession of Site 56
(2) Way leaves …etc. 56
36 Time for Completion 56
37 Extension of Time for completion 57
38 (1) No Night o Days of Rest Work 57
(2) Engineer’s Overtime 57
39 Rate of Progress 57
40 (1) Penalty for Delay 58
(2) Reduction of Penalty for Delay 58
(3) Engineer’s Supervision 58
41 (1) Certification of Completion of Works 58
(2) Certification of Completion by Stages 59
TENDER No. 19102 /2019 34/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
(3) Criteria for Completion of Works 59
44 (1) Variations 61
(2) Orders for Variations to be in Writing 61
45 (1) Valuation of Variations 62
(2) Power of Engineer to Fix Rates 62
(3) Variations exceeding 25 percent 62
(4) Day work 63
(5) Claims 63
Measurement
48 Quantities 65
49 Works to be Measured 65
50 Method of Measurement 65
Nominated Sub-Contractors
Special Risks
Frustration
Settlement of Disputes
Notices
Default of Employer
62 Default of Employer 79
64 Currency Restrictions 80
65 Taxation 80
66 Boycotts 81
67 Bribery 81
Safety of Construction
68 Safety of Construction 81
1.1 Definitions:
(1) In the Contract (as hereinafter defined) the following words and expressions shall
have the meanings hereby assigned to them except where the context otherwise
requires:
(a) “Employer” means “Client”, who will employ the Contractor, and the legal
successors in title to the Employer, but not (except with the Consent of the
Contractor) any assignee of the Employer.
(b) “Contractor” means the person or persons, firm or company whose tender
has been accepted by the Employer, and includes the Contractors personal
representatives, successors and permitted assignees.
(c) “Engineer” means : Skyline International Consulting Engineers
P. O. Box 3436, Sharjah – U. A. E. Directly within the scope of the
particular duties assigned to him and the authority given to him by the
Employer for this Contract according to the context of the Contract
Documents.
(d) “Engineers Representative” means any resident engineer or assistant of the
Engineer or any clerk of works appointed from time by the Employer or the
Engineer to perform the duties set forth in clause 2 (Duties and Powers of the
Engineer and Engineer’s Representative) hereof whose authority shall be notified in
writing to the Contractor by the Engineer.
(2) “Works” means the works to be executed in accordance with the Contract and shall
include both Permanent works and Temporary Works.
(e) “Contract” means collectively the Contract Documents listed in the form of
agreement (including accompanying documents), and any letters exchanged which
letters both contracting parties agree shall be part of the Contract.
(f) “Contract Price” means the sum named in the Letter of Acceptance subject
to such additions thereto or deductions therefrom as may be made under the
provisions hereinafter contained.
(g) “Constructional Plant” means all appliances or things of whatsoever nature
required in or about execution, completion or maintenance of the Works, but does
not include materials or other things intended to form or forming part of the
Permanent Works.
(h) “Temporary Works” means all Temporary Works of every kind required in
or about the execution, completion or maintenance of the Works.
(i) “Permanent Works” means the permanent works to be executed and
maintained in accordance with the Contract.
(j) “Specifications” means the specifications referred to in the Tender and any
modification thereof or addition thereof as may from time to time be furnished or
approved in writing by the Engineer.
(k) “Drawings” means the drawings referred to in the Specifications and any
modification of such Drawings approved in writing by the Engineer and such other
drawings as may from time to time be furnished or approved in writing by the
Engineer.
(l) “Site” means the lands and other places on, under, in or through which the
Permanent Works or Temporary Works are to be executed or carried out and any
TENDER No. 19102 /2019 38/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
other lands or places provided by the Employer for working spaces or any other
purpose as may be specifically designated in the Contract as forming part of the
Site.
(m) Approved” means approved in writing by the Engineer including subsequent
written confirmation of previous verbal approval and “approval” means approval in
writing by the Engineer including as aforesaid.
(n) “Moth” means calendar month according to the Gregorian Calendar.
1.4 Cost:
The word “Cost” shall be deemed to include overhead costs whether on or off the Site.
1.5 Time:
Time is defined by reference to Gregorian Calendar.
(1) The Engineer shall carry out such duties in issuing decisions, certificates and
orders as are specified in the Contract
(2) The Engineer’s Representative shall be responsible to the Engineer and his
duties are to watch and supervise the Works and to test and examine any materials
to be used or workmanship employed in connection with the works. He shall have
no authority to relieve the Contractor of any of his duties or obligations under the
Contract no, except as expressly provided hereunder or elsewhere in the Contract, to
order any work involving delay or any extra payment by the Employer, nor to make
any variation of or in the Works.
The Engineer may from time to time in writing delegate to the Engineer’s
Representative any of the powers and authorities vested in the Engineer, and shall
furnish to the Contractor and to the Employer a copy of all such written delegations
of powers and authorities. Any written instructions or approval given by the
Engineer’s Representative to the Contractor within the Terms of such delegation
(but not otherwise) shall bind the Contractor and the Employer as through it had
been given by Engineer. Provided always as follows:
3. Assignment:
The Contractor shall not assign the Contract or any part thereof or any benefit or interest
therein or thereunder (otherwise than by a charge in favour of the Contractor’s Bankers of
any monies due or to become due under this Contract).
4. Sub-Letting:
The Contractor shall sub-let the whole of the Works. Except where otherwise provided by
the Contract, the Contractor shall not sub-let any part of the Works without the prior written
consent of the Engineer (which shall not be unreasonably withheld), and such consent, if
given, shall not relieve the Contractor from any liability or obligation under the Contract,
and he shall be responsible for the acts, defaults and neglects of any sub-contractor, is gents,
servants workmen as fully as if they were the acts, defaults or neglects of the Contractor, his
agents servants or workmen. Provided always that the provision of labour on a piecework
basis shall not be deemed to be a sub-letting under this Clause.
The Engineer shall have full power and authority to supply to the Contractor from
time to time during the progress of the Works such further drawings and instructions
as shall be necessary for the purpose of the proper and adequate execution and
maintenance of the Works, and the Contractor shall carry out and be bound by the
same.
General Obligations:
Contract Agreement:
2. The Contractor shall, when called upon so to do, enter into and execute a contract
agreement (to be prepared at the cost of the Employer) in the form annexed, with
such modification as may be necessary.
Performance Bond:
3. For the due performance of the Contract the Tender shall contain an undertaking by
the Contractor to obtain, when required, a bond or guarantee of an insurance
company or bank or other approved sureties to be severally bound with the
Contractor to the Employer, in a sum of 10% of the sum named in the Letter of
Acceptance. The said insurance company or bank or sureties, and the terms of said
bond or guarantee shall be such as shall be approved by the Employer. The
obtaining of such bond or guarantee or the provision of such sureties and the cost
of the bond or guarantee to be so entered into shall be at the expanse in all respects
of the Contractor.
Wording of the performance bond shall be as stipulated in the Form of Performance Bond
attached to the Instructions to Tenderer’s section. The Bond shall be presented to the
Engineer for his retention, immediately after the Contractor’s receipt of Letter of
Acceptance.
Inspection of Site:
4. The Employer shall have made available to the Contractor with the Tender
documents such data on hydrological and sub-surface conditions as shall have been
obtained by or on behalf of the Employer from investigations undertaken relevant
to the Works, and the Tender shall be deemed to have been based on such data, but
the Contractor shall be responsible for his own interpretation thereof.
Sufficiency of Tender:
Programme to be Furnished:
7. (1) The Contractor shall provide the Engineer with a program of his approval
within three weeks receipt of the Letter of Acceptance showing the order of
procedure in which he proposes to carry out the Works. The Contractor shall
whenever required by the Engineer or Engineer’s Representative, also provide in
writing for his information a general description of the arrangements and methods
which the Contractor proposes to adopt for the execution of the Works.
(2) If at any time it should appear to the Engineer that the actual progress of the
Works does not conform to the approved program referred to in sub-clause (1) of
this Clause, the Contractor shall produce, at the request of the Engineer, a revised
program showing the modifications to the approved program necessary to ensure
Contractor’s Superintendence:
8. The Contractor shall give or provide all necessary superintendence during the
execution of the Works and as long thereafter as the Engineer may consider
necessary for the proper fulfillment of the Contractors obligations under the
Contract. The Contractor or a competent and authorized English Speaking agent or
representative approved of in writing by the Engineer (which approval may at any
time be withdrawn) is to be constantly on the Works, and shall give his whole time
to the superintendence of the same. If such approval shall be withdrawn by the
Engineer the Contractor shall as soon as is practical (having regard to the
requirement of replacing his as hereinafter mentioned) after receiving written
notice of such withdrawal remove the agent from the Works and shall not
thereafter employ him again on the Works in any capacity and shall replace him by
another agent approved by the Engineer. Such authorized agent or representative
shall receive on behalf of the Contractor directions and instructions from the
Engineer or (subject to limitations of clause 2 “Duties and Powers of the Engineer
and Engineer’s Representative “ hereof) the Engineer’s Representative.
The Contractor’s authorized agent or representative shall be sufficiently fluent in
the Arabic and English languages to receive directions and instructions and
instructions, and to correspond with the Employer, the Engineer and the Engineer’s
Representative.
Contractor’s Employees:
9. (1) The Contractor shall provide and employ on the Site in connection with the
execution and maintenance of the Works.
(a) Only such technical assistants as are skilled and experienced in their
respective trades and such sub-agents foremen and leading hands as are
competent to give proper supervision to the work they are required to
supervise, and
(b) Such skilled, semi-skilled and unskilled labour as is necessary for the proper
and timely execution and maintenance of the Works.
(2) All Contractor's supervisory staff down to and including general foreman level
provided and employed by the Contractor shall have a reasonable command of the
English language.
At all times during normal working hours the Contractor shall have on site a
sufficient number of people provided by the Contractor sufficiently competent in
both English and Arabic to ensure transmission and comprehension of all
instructions".
Setting-Out:
10. The Contractor shall be responsible for the true and proper setting-out of the Works
in relation to original points, lines and levels of reference given by the Engineer in
writing and for the correctness (subject as above-mentioned) of the position, levels,
dimensions and alignment of all parts of the Works, and for the provision of all
necessary instruments, appliances and labour in connection therewith. If at any
time during the progress of the Works any error shall appear, or arise in the
position, levels, dimensions or alignment of any part of the Works, the Contractor
on being required so to do by the Engineer or Engineer’s Representative shall at his
own expense rectify such error to the satisfaction of the Engineer or Engineer’s
Representative. Unless such error is based on incorrect data supplied in writing by
the Engineer or the Engineer’s Representative in which case the expense of
rectifying the same shall be borne by the Employer, Provided that the expense of
rectifying any errors shall be borne by the Contractor if such error results from
incorrect data on the Drawings or in the Specifications which were used for Tender
purposes which Drawings and Specifications are deemed to have been carefully
studied by the Contractor and accepted by him as being correct unless he has
notified the Engineer in writing of such errors at the time of tendering. The
Checking of any setting-out or of any line or level by the Engineer or the
Engineer’s Representative shall not in any way relieve the Contractor of his
responsibility for the correctness thereof and the Contractor shall carefully protect
and preserve all benchmarks, sight-rails, pegs and other things used in setting out
the Works.
Care of Works:
13. (1) From the date of Commencement of the Works until the date stated in the
Certificate of Completion for the whole of the Works Pursuant to Clause 41 hereof
the Contractor shall take full responsibility for the care thereof. Provided that if the
Excepted Risks:
(2) The “excepted risks” are war, hostilities (whether war be declared or not) invasion, act
of foreign enemies, rebellion, revolution, insurrection or military or usurped power, civil
war, or unless solely restricted to employees of the Contractor or of his sub-contractors and
arising from the conduct of the Works, riot, commotion, or disorder or use or occupation by
the Employer of any part of the Permanent Works, or cause solely due to the Engineer’s
design of the Works, or ionizing radiation’s or contamination by radioactivity from any
nuclear fuel or from any nuclear waste from the combustion of nuclear fuel, radioactive
toxic explosive, or other hazardous properties of any explosive, nuclear assembly or
nuclear component thereof, pressure waves caused by aircraft or other aerial devices
traveling at sonic or super-sonic speeds, all of which are herein collectively referred to as
“the excepted risks”.
Indemnity by Employer:
(2) The Employer shall indemnify the Contractor against all claims, proceeding, damages,
costs, charges and expenses in respect of the matters referred to in the proviso to sub-clause
(1) of this Clause.
(3) The Contractor shall pay all fees arising from Clause 19 (1), (2) and shall be deemed to
have included any such fees in his Tender.
Fossils, …etc:
20. All fossils, coins, articles of value or quantity and structures and other remains or
things of geological or archaeological interest discovered on the Site of the Works
shall as between the Employer, and the Contractor be deemed to be the absolute
property of the Employer and the Contractor shall take reasonable precautions to
prevent his workmen or any other persons from removing or damaging any such
article or thing and shall immediately upon discovery thereof and before removal
acquaint the Engineer’s Representative of such discovery and carry out at the
expanse of the Employer, the Engineers Representative’s order as to the disposal of
the same.
Extraordinary Traffic:
23. (1) The Contractor shall use every reasonable means to prevent any of the
highways or bridges communicating with or on the routes to the Site from being
Special Loads:
(2) Should it be found necessary for the Contractor to move One or more loads of
constructional plant, machinery or pre-constructed units or parts of units of work over part
of a highway or bridge, the moving whereof is likely to damage any highway or bridge
unless special protection or strengthening is carried out, the Contractor shall before moving
the load on to such highway or bridge, give notice to the concerned owner or Government
Department. All costs, expenses, delays and the like arising therefrom shall be the entire
responsibility of the Contractor. No claim will be allowed by the Engineer for any such
costs, expenses, delays and the like.
Waterborne Traffic:
(4) Where the nature of the Works is such as to require the use by the Contractor of
waterborne transport the foregoing provisions of this Clause shall be construed as though
“highway” included a lock, dock, sea wall, or other structure related to a waterway and
“vehicle” included craft, and shall have effect accordingly.
Labour:-
Engagement of Labour
27. (1) The Contractor shall be responsible for arranging for a sufficient and suitable
supply at all times throughout the Contract of all labour and personnel and shall
make his own arrangement for their recruitment.
Recruitment of Labour
(2) The Contractor shall pay all costs and charges for and shall make all arrangements in
connection with the engagement, transport, accommodation and feeding during transport
guarantee and all other matters whatsoever in connection with the recruitment of labour all
of which arrangements shall be subject to the relevant laws, regulations and orders in force
from time to time during the continuance of the contract.
Expatriate Labour
(4) The Contractor shall be responsible for the engagement, importation and repatriation of
all expatriate labour required for the purposes of the contract and in respect of the
engagement, importation, repatriation, employment, transportation, payment, feeding,
housing, health welfare and working conditions or all matters connected therewith shall at
all times during the continuance of the contract conform in all respects with and carry out
all obligations imposed on him by the provision and requirements of any law, regulation or
order of the Government or any regulation or bye-law of any local or other duly constituted
authority which may be applicable including any such law, regulation, order or bye-law
passed or made or coming into force during the continuance of the contract.
Housing
(6) The Contractor shall make his own arrangements for providing the necessary housing
for labour employed on the Works in accordance with all local authority requirements. The
Engineer shall have the right to enter on and inspect and check that all local authority
requirements are being complied with.
Food
(7) The Contractor shall be responsible for making suitable arrangements for the provision
of food and cooking facilities for workmen and labourers employed on the Works.
Wage Record
(8) The Contractor shall keep proper wages books and time sheets together with such other
records as are required by labour laws and regulations and shall be bound whenever
required to produce such wages, time sheets and other records for the inspection of any
person authorized by the Engineer.
Repatriation
(9) The Contractor shall be responsible for the repatriation to those places where they are
recruited of such labour as be recruited and employed subsequently on or in connection
with the works and shall maintain such persons as are being repatriated in a suitable
manner until such time as they have left the district or country; in default the
Government may maintain and repatriate such persons and recover the costs from the
Contractor.
Returns of Employees
(10) At the commencement of each month the Contractor shall deliver to the Engineer's
representative's office a return showing the number, distribution and trades of all
employees (including staff) employed by him during the previous month at the site. On
daily basis the Contractor shall deliver to the Engineer's representative's office daily
manpower reports as well as details of equipment on site, or any other reports as instructed
by the Engineer.
Safety Precautions
(11) The Contractor and all persons employed by him on the site in or about the execution
of the Works shall conform in all respects with the provisions of all statutes, ordinances,
regulations, bye-laws made by a competent authority that shall be applicable to the Works
or any temporary Works and binding upon the Contractor or persons employed as aforesaid
and in particular but without prejudice to the generality of the foregoing such matters as
concern the safety, health or welfare of persons working on the site. The Engineer may
require the immediate removal from the site and the Works of any person who in the
Epidemics
(15) In the event of any outbreak of illness of any epidemic nature the Contractor shall
immediately inform, comply with and carry out such regulations, orders and requirements
as may be made by the Government or the local medical or sanitary authorities for the
purpose of dealing with and overcoming the same.
Disorderly Conduct
(16) The Contractor shall at all times take all reasonable precautions to prevent any
unlawful riotous or disorderly conduct by or amongst his employees and for the
preservation of peace and protection of persons and property in the neighborhood of the
Works against the same.
Accidents
(17) The Contractor shall within 24 hours of the occurrence of any accident at or about the
site or in connection with the execution of the Works report such accident to the Engineer's
representative. The Contractor shall also report such accident to the competent authority
whenever such report is required by law.
Observance by Sub-Contractors
(18)The Contractor shall be responsible for the observance by sub-contractors employed by
him or by the Employer (nominated sub-contractors), in the execution of this contract of
the provisions of this Clause.
Cost of Samples:
(2) All samples shall be supplied by the Contractor at his own cost, if the samples are
clearly provided for in the Contract.
Cost of Tests:
(3) The cost of making any test shall be borne by the Contractor if such test is clearly
intended by or provided for in the Contract and (in the cases only of a test under load or of
a test to ascertain whether the design of any finished or partially finished work is
appropriate for the purposes which is was intended to fulfil) is particularized in the
Contract in sufficient detail to enable the Contractor to price or allow for the same in his
Tender.
(3-1) The Contractor shall allow in his pricing for all tests as necessary to be carried out on
the materials due for incorporation into the works. The Contractor should note that it may
be required that the Engineer will have to visit the factories of various manufacturers in
order to establish and monitor testing procedures and the Contractor’s price is deemed to
have included for providing such provisions.
(3-2) The Contractor is to submit samples of all materials and / or catalogues requested by
the Engineer, and the cost for the same is deemed to be included in the Contract. Samples
of workmanship requested by the Engineer shall be provided by the Contractor and the cost
for the same is deemed to be included in the Contract.
(3-3) The Contractor is to carry out tests of materials as required by the Engineer and the
cost for the same is deemed to be included in the contract.
Inspection of Operations:
30. The Engineer and any person authorized by him shall at all times have access to the
Works and to the Site and to all workshops and places where work is being
prepared or from where materials, manufactured articles or machinery are being
TENDER No. 19102 /2019 54/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
obtained for the Works and the Contractor shall afford every facility for and every
assistance in or in obtaining the right to such access.
Suspension of Work:
33. (1) The Contractor shall on the written order of the Engineer, suspend the progress
of the Works or any part thereof for such time or times and in such manner as the
Engineer may consider necessary and shall during such suspension properly protect
and secure the work so far as is necessary in the opinion of the Engineer. The extra
Commencement of Works:
34. The Contractor shall commence the Works on Site within the period named in the
Appendix to the Tender after the receipt by him of an order in writing to this effect
from the Engineer and shall proceed with the same with due expedition and
without delay except as may be expressly sanctioned or ordered by the Engineer or
be wholly beyond the Contractors control.
Wayleaves …etc.:
(2) The Contractor shall bear all costs and charges for special or temporary wayleaves
required by him in connection with access to the Site. The Contractor shall also provide at
his own cost any additional accommodation outside the Site required by him for the
purposes of the Works.
Engineer’s Overtime:
(2) In the event that the Engineer is obliged to supervise the Contractor’s operations in
excess of 8 hours per working day, or on Fridays or declared Public Holidays, the cost to
the Engineer of such overtime shall be agreed between the Engineer and the Contractor,
and approved by the Employer, Payment will be made to the Engineer by the Employer
who shall deduct the agreed amount from monies due to the Contractor certified by the
Engineer in the payment certificates. Overtime rates will be as set out in the Appendix to
the Conditions of Contract.
Rate of Progress
39. If for any reason, which does not entitle the Contractor to an extension of time, the
rate of progress of the Works or any section is at any time, in the opinion of the
Engineer, too slow to ensure completion by the prescribed time or extended time
for completion, the Engineer shall so notify the Contractor in writing and the
Contractor shall thereupon take such steps as are necessary and the Engineer may
approve to expedite progress so as to complete the Works or such section by the
prescribed time or extended time. The Contractor shall not be entitled to any
additional payment for taking such steps. If, as a result of any notice given by the
Engineer under this Clause, the Contractor shall seek the Engineer’s permission to
do any work at night or on Fridays, if locally recognized as days of rest, or their
locally recognized equivalent, such permission shall not be unreasonable refused.
Engineer’s Supervision:
(3) In the event that the Engineer is obliged to supervise the Contractor’s operations after
the period named in the Contract for the completion of the Works, the cost to the Engineer
of such supervision shall be as set out in Appendix A to the Conditions of Contract.
Payment will be made to the Engineer by the Employer who shall deduct the agreed
amount from the monies due to the Contractor certified by the Engineer in the payment
certificates.
Contractor to Search:
43. The Contractor shall if required by the Engineer, in writing, search for the cause of
any defect, imperfection or fault under the direction of the Engineer and the cost of
the work carried out in searching for the aforesaid shall be borne by the Contractor
Variations
44. (1) The Engineer shall make any variation of the form, quality or quantity of the
Works or any part thereof that may in his opinion be necessary and for that purpose
or if for any other reason it shall in his opinion be desirable he shall have power to
order the Contractor to do and the Contractor shall do any of the following:-
(a) Increase or decrease the quantity of any work included in the Contract.
(b) Omit any such Work.
(c) Change the character or quality or kind of any such work.
(d) Change the levels, lines, position and dimensions of any part of the Works,
and
(e) Execute additional work of any kind necessary for the completion of the
Works.
And no such variation shall in any way vitiate or invalidate the Contract, but the value (if
any) of all such variations shall be taken into account in ascertaining the amount of the
Contract Price.
Valuation of Variations:
45. (1) All extra or additional work done or work omitted by order of the Engineer
shall be valued at the rates and prices set out in the Contract if, in the opinion of the
same shall be applicable, if the Contract does not contain any rates or prices
applicable to the extra or additional work, then suitable rates or prices shall be
agreed upon between the Engineer and the Contractor. In the event of disagreement
the Engineer shall fix such rates or prices as shall, in his opinion, be reasonable and
proper.
Day work:
(4)The Engineer may, if in his opinion it is necessary or desirable, order in writing that any
additional or substituted work shall be executed on a day work basis. The Contractor shall
then be paid or such work under the conditions set out in the Day Work Schedule included
in the Bills of Quantities and at the rates and prices affixed thereto by him in his Tender.
The Contractor shall furnish to the Engineer such receipts or other vouchers as may be
necessary to prove the amounts paid and, before ordering materials, shall submit to the
Engineer quotations for the same for his approval.
In respect of all work executed on a day work basis, the Contractor shall, during the
continuance of such work, deliver each day to the Engineer’s Representative an exact list in
duplicate of the names, occupation and time of all workmen employed on such work and a
statement, also in duplicate, showing the description and quantity of all materials and plant
used thereon and therefore (other than plant which is included in the percentage addition in
accordance with the Schedule herein before referred to). One copy of each list and
statement will, if correct, or when agreed, be signed by the Engineer’s Representative and
returned to the Contractor.
At the end of each month the Contractor shall deliver to the Engineer’s Representative, a
priced statement of the labour, material & plant, (except as aforesaid), used & the
Contractor shall not be entitled to any payment unless such lists and statements have been
fully and punctually rendered. Provided always that if the Engineer shall consider that for
any reason the sending of such list or statement by the Contractor, in accordance with the
foregoing provision, was impracticable he shall nevertheless be entitled to authorities
payment for such work, either as day work, on being satisfied as to the time employed and
plant and materials used on such work, or at such value thereof as shall in his opinion, be
fair and reasonable.
Claims:
(5) The Contractor shall send to the Engineer’s Representative once in every month an
account giving particulars (as full and detailed as possible) of all claims for any additional
payment to which the Contractor may consider himself entitled and of all extra or
additional work ordered by the Engineer which he has executed during the preceding
month. No final or interim claim for payment for any such work or expense will be
considered which has not been included in such particulars. Provided always that the
Engineer shall be entitled to authorize payment to be made for any such work or expense
notwithstanding the Contractor’s failure to comply with this condition if the Contractor has
Re-Export of Plant:
(4) The Contractor shall be solely responsible for the import and export of Constructional
Plant, Temporary Works and materials, and shall at his own cost obtain licenses for such
purposes if required.
Customs Clearance:
(5) The Contractor shall be deemed to have included in his tender for all Custom Duty,
Harbour and Port Fees, Wharfage, Landings, Pilotage and all other costs relating to the
import and export of Constructional Plant, Temporary Works and materials.
(6-a) The constructional plant, temporary works, materials, transport and things of
every kind necessary for the construction, completion and maintenance of the works shall
be erected in such positions and used or executed at such times and in such a manner as is
indicated in the programme to be provided by the Contractor under the terms of Clause 14
of these conditions of contract or any subsequent modifications to such programme agreed
by the Engineer and as are most efficient and suitable for the proper, timely and safe
execution of the Works to be undertaken under this contract.
(6-b) The Contractor shall be solely responsible for the provisions, sufficiency, safety and
all other risks and costs of all the aforesaid constructional plant, temporary works,
materials, transport and things of every kind and for the methods adopted by him for the
proper execution of the Works in accordance with the contract.
(6- c) The Contractor shall at his own expense, unless otherwise specified, make all his
own arrangements for the supply and the distribution of water (including adequate storage
facilities) fuel, light and power (including temporary facilities as required) to all points
where they are required for all the operations under the contract and for this purpose he
TENDER No. 19102 /2019 63/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
shall provide and use all the necessary constructional plant temporary works, transport,
materials and things of every kind necessary to supply and distribute the supplies to the
various parts of the Works including also for a satisfactory supply and adequate storage
facilities of water to the offices, camps, latrines and other temporary buildings requiring it
and a sufficient supply of drinking water of good quality for his employees. If the
Engineer considers the level of lighting is inadequate to ensure the level of workmanship
required by the contract, the Contractor shall provide additional lighting provisions at his
expense, all to the Engineer's satisfaction.
(6-d) The Contractor shall take all risks from water whatever the source of cause may be
and shall, at his own expense unless otherwise specified, properly deal with and dispose of
water by use of sufficient constructional plant, temporary works, materials, transport and
things of every kind as to ensure the whole of the Works being executed in a satisfactory
dry and safe manner in accordance with the requirements of the contract.
(6-e) The Contractor shall at his own expense unless otherwise specified provide and
maintain all necessary temporary bridging gangways, ladders, staging, railways, roads and
footpaths to and about the site of the Works as may be necessary for the construction and
completion of the Works or transport of labour, plant and materials.
(6-f) The Contractor shall obtain his own information with regard to the granting of import
and export licences. The Contractor shall bear the expense of obtaining all import and
export licences for constructional plant, materials, equipment and Other things required for
the completion and maintenance of the Works and shall be deemed to have satisfied
himself with regard to all his liabilities under the statutes, ordinances, laws, regulations and
bye-laws governing the granting of these licenses.
The Contractor shall ensure that applications for import and export licences are submitted
to the appropriate authorities in sufficient time to clear all formalities before the licences
are required.
(6-g) The Contractor shall make good at his own cost all diversions or damage to
telephone, telegraph and electric cables, wires, sewers, water mains or other pipes and all
other services encountered except where the authority or private party owning or
responsible for the same elects to take the responsibility. The cost incurred in so doing
shall be paid by the Contractor to the authority or private party on demand.
(6-h) All injury to the surface of the land where disturbed by the Works (other than where
specifically ordered by the Engineer) shall be repaired by the Contractor or the authorities
concerned at the Contractor's expense. All such making good shall be at the approval of
the Engineer and the authority or private party concerned.
Quantities:
Works to be Re-Measured:
49. The Contract is for a lump sum and is not subject to re-measurement. If the
Engineer requires any part or parts of the Works to be measured, he shall give
notice to the Contractor who shall forthwith send a qualified agent to carry out
such measurement. The Contractor shall furnish the Engineer with all particulars
and measurements he requires for checking and approval. Should the Contractor
not attend or neglect or omit to send such an agent then the measurement
Made by the Engineer or approved by him shall be taken to be correct measurement of the
work. Quantities of work omitted shall be re-measured from the original Contract drawings
and shall be agreed by the Engineer before the value of variation is calculated.
Method of Measurement:
50. The Works have been measured net, notwithstanding any general or local customs,
except where otherwise specifically described or prescribed in the Contract.
Nominated Sub-Contractors:
Nominated Sub-Contractors:
(2) The Contractor shall be required by the Employer or the Engineer or be deemed to be
under any obligation to employ any nominated Sub-Contractor:
(a) That in respect of the work, goods, materials or services the
subject in the sub-contract, the nominated Sub-Contractor will undertake
towards the Contractor the like obligations and liabilities as are imposed on
the Contractor towards the Employer by the terms of the Contract and will
TENDER No. 19102 /2019 66/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
save harmless and indemnify the Contractor from and against the same and
from all claims, proceedings, damages, costs, charges and expenses
whatsoever arising out or in connection therewith, or arising out of or in
connection with any failure to perform such obligations or to fulfill such
liabilities, and
(b) That the nominated Sub-Contractor will save harmless and
indemnify the Contractor from and against negligence by the nominated
Sub-Contractor, his agents, workmen and servants and from and against any
misuse by him or them of any Constructional Plant or Temporary Works
provided by the Contractor for the purpose of the Contract, and all claims as
aforesaid.
Design Requirements to be Expressly Stated:
(3) If in connection with any Provisional Sum the services to be provided include any
matter of design or specification of any part of the Permanent Works or for any
requirement or plant to be incorporated therein, such requirement shall be expressly stated
in the Contract and shall be included in any nominated Sub-Contractor. The nominated
Sub-Contractor shall specify that the nominated Sub-Contractor providing such services
will save harmless and indemnify the Contractor from and against the same and from all
claims, proceedings, damages, costs, charges and expenses whatsoever arising out of or in
connection with any failure to perform such obligations or to fulfill such liabilities.
(4) For all work executed or goods, materials or services supplied by any nominated Sub-
Contractor, there shall be included in the Contract Price:
(a) the actual price paid or due to be paid by the Contractor, on the direction of
the Engineer, and in accordance with the Sub-Contract,
(b) The sum, if any, entered in the Bill of Quantities for labour supplied by the
Contractor in connection therewith, or it ordered by the Engineer pursuant to
Clause 51 (2) (b) hereof, as may be determined in accordance with Clause
45 hereof,
(c) In respect of all other charges and profit, a sum being a percentage rate of
the actual price paid or due to be paid calculated, where provision has been
made in the Bills of Quantities for a rate to be set against the relevant
Provisional Sum, at the rate inserted by the Contractor against that item or,
where no such provision has been made, at the rate inserted by the
Contractor in the Appendix to the Tender and repeated where provision for
such is made in a special item provided in the Bills of Quantities for such
purpose.
(5) Before issuing, under Clause 53 hereof, any certificate, which included any payment in
respect of work done or goods, materials or services supplied by any nominated Sub-
Contractors the Engineer shall be entitled to demand from the Contractor reasonable proof
that all payments, less retention’s, included in previous certificates in respect of the work or
for goods, materials or services of such nominated Sub-Contractor have been paid or
discharged by the Contractor, in default whereof unless the Contractor shall:
The Engineer shall have powers to with-hold all further interim payments, till such period
the Contractor provides reasonable proof that all payments, less re-tensions, included in
previous certificates have been paid or discharged by the Contractor to his sub-contractors.
Alternatively the Engineer shall be entitled to pay to such nominated Sub-Contractor
direct, upon the certificate of the Engineer, all payments, less re-tensions, provided for in
the sub-Contract, which thr Contractor has failed to make to such nominated Sub-
Contractor and to deduct by way of set-off the amount so paid by the Employer from any
sums due or which may become due from the Employer to the Contractor.
Provided always that, where the Engineer has certified and the Employer has paid direct as
aforesaid, the Engineer shall in issuing any further certificate in favor of the Contractor
deduct from the amount thereof the amount so paid, direct as aforesaid, but shall not
withhold or delay the issue of the certificate itself when due to be issued under the terms of
the Contract.
Cash Discount:
(7) Any cash discount allowed by the Nominated Sub-Contractor shall be for the benefit of
the Employer.
(a) The value of the works executed up to the end of that month,
(b) Seventy five percent (75%) of the value of any goods or
materials delivered to the Site for, but not yet incorporated in the Works (if
mentioned in the form of tender).
(c) Other amounts to which the Contractor considers himself
entitled and for which provision is made in the Bills of Quantities.
Unless the total of such sums does not exceed the Minimum Amount of Monthly
Payments, as set down in the Appendix to the Tender, after the deduction of Retention,
previous payments and other sums as may be deductible under the Contract.
The statement shall list separately amounts due to nominated sub-contractors
(2) Upon receipt of the Contractor’s monthly statement, the Engineer shall issue an Interim
Payment Certificate to the Employer with a copy to the Contractor for the amount he
considers payable to the Contractor less:
Unless such amount is less than the Minimum Amount of Monthly Payments as set down in
the Appendix to the Tender.
Before issuing, any interim payment certificate, which includes any payment in respect of
work done or goods, materials or services supplied by any of the Sub-Contractors of the
Contractor, the Engineer shall be entitled to demand from the Contractor reasonable proof
that all payments, less retentions, included in previous certificates in respect of the work or
goods, materials or services of such Sub-Contractor have been paid or discharged by the
Contractor, in default whereof unless the Contractor shall:
The Engineer shall have powers to with-hold all further interim payments, till such period
the Contractor provides reasonable proof that all payments, less retention’s, included in
previous certificates have been paid or discharge by the Contractor to his sub-contractors.
Alternatively the Employer shall be entitled to pay to such Sub-Contractor direct, upon the
certificate of the Engineer, all payments, less retentions, provided for in Sub-Contract,
which the Contractor has failed to make to such Sub-Contractor, and to deduct by way of
set-off the amount so paid by the Employer from any sums due or which may become due
from the Employer to the Contractor.
Provided always that, where Engineer has certified and the Employer has paid direct as
aforesaid, the Engineer shall in issuing any further certificate in favor of the Contractor
deduct from the amount thereof the amount so paid, direct as aforesaid.
Retention:
(3) Retention shall be held on the amount payable to the Contractor in respect of items (a)
or (c) of sub-clause (1) of this Clause. The percentage of Retention is stated in the
Appendix to the Tender. Retention shall be held up to the limit stated in the Appendix to
the Tender.
Reduction of Retention:
(5) After the issue of the Certificate of Completion the Contractor shall submit a statement
of final account and supporting documentation showing in detail the value in accordance
with the Contract of work done together with all further sums which the Contractor
considers to be due to him under the Contract. After examining this statement the Engineer
shall issue a payment certificate for the amount he considers payable to the Contractor less:
Release of Retention:
(6) Upon the issue by the Engineer of the Maintenance Certificate the Employer shall pay
to the Contractor the remaining Retention money less any amounts due to the Employer
under the Contract.
Provided that if at such time there shall remain to be executed by the Contractor any work
ordered pursuant to Clause (42) and (43) hereof in respect of the whole or any part of the
Works, the Employer shall be entitled to withhold payment of the remaining retention
money or such portion thereof as shall, in the opinion of the Engineer, represent the cost of
work remaining to be executed unit the completion of such work.
Currency:
(9) All payments shall be in U. A. E. Dirhams.
Advance Payment:
(10) An Advance Payment of the amount stated in Appendix “A” to Form a Tender shall,
following the presentation of the Contractor to the Employer of an approved performance
Bond in accordance with Clause (3) hereof and a guarantee of one of the approved banks
on terms approved by the Employer for the full value of the Advance Payment, be certified
by the Engineer for Payment to the Contractor.
The Advance Payment shall not be subject to retention. The Advance Payment shall be
repaid in monthly installments at 10% of the value of the monthly Certificate commencing
from the second month of the Contract Period. Provided that upon the issue of a Certificate
for Substantial Completion for the whole of the Works under Clause (41) hereof, or
termination under Clause (56) or (58) (6) hereof, the whole of the balance then outstanding
shall immediately become due and payable by the Contractor to the Employer.
Maintenance Certificate:
55. (1) The Contract shall not be considered as completed until a Maintenance
Certificate shall have been signed by the Engineer and delivered to the Employer
stating that the Works have been completed and maintained to his satisfaction. The
Maintenance Certificate shall be given by the Engineer within Twenty eight 928)
days after the expiration of the Period of Maintenance, or, if different periods of
maintenance shall become applicable to different sections or parts of the Works,
the expiration of the latest such period, or as soon thereafter as any works ordered
during such period, pursuant to Clause (42) and (43) hereof, shall have been
completed to the satisfaction of the Engineer and full effect shall be given to this
Clause, notwithstanding any previous entry on the Works or the taking possession,
working or using thereof by the Employer. Provided always that the issue of the
Maintenance Certificate shall not be a condition precedent to payment to the
Contractor of the retention money in accordance with the conditions set out in
Clause (53).
Unfulfilled Obligations:
(3) Notwithstanding the issue of the Maintenance Certificate the Contractor and (subject to
sub-clause 2 of this Clause) the Employer shall remain liable for the fulfillment of any
obligation incurred under the provisions of the Contract prior to the issue of Maintenance
Certificate which remains unperformed at the time such certificate is issued and for the
purpose of determining the nature and extent of any such obligation the Contract shall be
deemed to remain in force between the parties hereto.
Default of Contractor
56. (1) If the Contractor shall become bankrupt of have a receiving order made against
him or shall present his petition in bankruptcy or shall make an arrangement with
or assignment in favor of his creditors or shall agree to carry out the Contract under
a committee of inspection of his creditors or (being a corporation) shall go into
TENDER No. 19102 /2019 71/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
liquidation (other than a voluntary liquidation for the Purposes of amalgamation or
reconstruction) or if the Contractor shall assign the Contract without the consent in
writing of the Employer first obtained or shall have an execution levied on his
goods or if the Engineer shall certify in writing to the Employer that in his opinion
the Contractor:
Urgent Repairs:
57. If by reason of any accident or other event occurring to in or in connection with
the Works or any part thereof either during the execution of the Works or during
the Period of Maintenance any remedial or other work or repair shall in the opinion
of the Engineer or the Engineer’s Representative be urgently necessary for the
safety of the Work and the Contractor is unable or unwilling at once to do such
work or repair the Employer may employ and pay other persons to carry out such
work or repair as the Engineer or the Engineer’s Representative may consider
necessary. If the Work or repair so done by the Employer is work which in he
opinion of the Engineer the Contractor was liable to do at his own expense, under
the Contract all expenses properly incurred by the Employer, or may be deducted
by the Employer in so doing shall be recoverable from the Contractor by the
Employer, or may be deducted by the Employer from any monies due or which
may become due to the Contractor. Provided always that the Engineer or the
Engineer’s Representative (as the case may be) shall as soon after the occurrence
of any such emergency as may be reasonably practicable notify the Contractor
thereof in writing.
Special Risks:
(a) Any permanent work and for any materials so destroyed or damaged.
And, so far as may be required by the Engineer, or as may be necessary for the
completion of the Works, on the basis of cost plus such profit as the Engineer may
certify to be reasonable.
(b)Replacing or making good any such destruction or damage to the Works.
(c) Replacing or making good such materials or other property of the Contractor
used or intended to be used for the purposes of Works.
Special Risks:
(5) The special risks are war, hostilities (whether war be declared or not), invasion, act of
foreign enemies, the nuclear and pressure waves risk described in Clause (13) (2) hereof, or
insofar as it relates to the country in which the Works are being or are to be executed or
maintained, rebellion, revolution, insurrection, military or usurped power, civil war, or
unless solely restricted to the employees of the Contractor of his Sub-Contractors and
arising from the conduct of the Works.
Outbreak of War:
(6) If during the currency of the Contract there shall be an outbreak of war (whether war is
declared or not) in any part of the world which whether financially or otherwise materially
affects the execution of the Works the Contractor shall unless and until the Contract is
terminated under the provisions of this Clause,
Continue to use his best endeavors to complete the execution of the Works. Provided
always that the Employer shall be entitled at any time after such outbreak of war to
terminate this Contract by giving notice in writing to the Contractor and upon such notice
being given this Contract shall (save as to the rights of the parties under this Clause and to
the operation of Clause 60 hereof) terminate but without prejudice to the rights of either
party in respect of any antecedent breach thereof.
(a) The amount payable in respect of any preliminary items so far as the work or service
comprised therein has been carried out or performed and a proper proportion as certified by
the Engineer of any such items the work or service comprised in which has been partially
carried out or performed.
(b) The cost of materials or goods reasonably ordered for the Works which shall have been
delivered to the Contractor or of which the Contractor is legally liable to accept delivery
(such materials or goods becoming the property of the Employer upon such payment being
made by him).
Frustration:
59. If war, or other circumstances outside the Control of both parties arises after
the Contract is made so that either party is prevented from fulfilling his
contractual obligations, or under the law governing the Contract, the parties
are released from further performance, then the sum payable be the
Employer to the Contractor in respect of the work executed shall be the same
as that which would have been payable under Clause (58) hereof if the
Contract had been terminated under the provision of Clause (58) hereof.
Settlement of Disputes:
Settlement of Disputes – Arbitration:
60. If any dispute or different of any kind whatsoever shall arise between the
Employer and the Contractor or the Engineer and the Contractor in
connection with, or arising out of the Contract, or the execution of the
Works, whether during the progress of the Works or after their completion
and whether before or after the termination, abandonment or breach of the
Contract, it shall, in the first place, be referred to and settled by the Engineer
who shall, within a period of 90 days after being requested by either part to
do so, give written notice of his decision to the Employer and the Contractor.
Subject to arbitration, as hereinafter provided, such decision in respect of
every matter so referred shall be final and binding upon the Employer and
the Contractor, and shall forthwith be given effect to by the Employer and
by the Contractor, who shall proceed with the execution of the Works with
all due diligence whether he or the Employer requires arbitration, as
hereinafter provided, or not. If the Engineer has given written notice of his
decision to the Employer and the Contractor and no claim to arbitration has
been communicated to him by either the Employer or the Contractor within
a period of 90 days from receipt of such notice, the said decision shall
remain final and binding upon the Employer and the Contractor. If the
TENDER No. 19102 /2019 75/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
Engineer shall fail to give notice of his decision, as aforesaid, within a
period of 90 days after being requested as aforesaid, or if either the
Employer or the Contractor be dissatisfied with any such decision, then and
in any such case either the Employer or the Contractor may within 90 days
after receiving notice of such decision, or within ninety days after the
expiration of the first-named period of 90 days, as the case may be, require
that the matter or matters in dispute be referred to arbitration as hereinafter
provided. All disputes or differences in respect of which the decision, if any,
of the Engineer has not become final and binding as aforesaid shall be
finally settled by a committee of three arbitrators. One arbitrator shall be
appointed by the Employer and one by the Contractor and these two
members shall appoint a third member to act as chairman. If agreement
between the two appointed members upon a third member cannot be reached
within 15 days from the last date of their appointment such third member
shall be appointed, on the application of either of the parties, by the
president for the time being of the Chamber of Commerce and Industry in
the Country where the Contract is being executed. The decisions of the
Arbitration Committee shall be final and binding on both parties. The said
arbitrator/ s shall have full power to open up, revise and review any decision,
opinion, direction, certificate or valuation of the Engineer. Neither party
shall be limited in proceedings before such arbitrator/ s to the evidence or
arguments put before the Engineer for the purpose of obtaining his said
decision. No decision given by the Engineer in accordance with the
foregoing provisions shall disqualify him from being called as witness and
giving evidence before the arbitrator/ s on any matter whatsoever
Relevant to the dispute or difference referred to the arbitrator/ s as aforesaid. The
reference to arbitration may proceed notwithstanding that the Works shall not then
be or be alleged to be complete, provided always that the obligations of the
Employer, The Engineer and the Contractor shall not be altered by reason of the
arbitration being conducted during the progress of the Works.
Notices:
Default of Employer:
(a) Failing to pay to the Contractor the amount due under any
certificate of the Engineer within the Time stated in Appendix “A” to the
Tender, after the same shall have become due under the terms of the
Contract, subject to any deduction that the Employer is entitled to make
under the Contract, or
(b) Interfering with or obstructing or refusing any required
approval to the issue of any such certificate, or
(c) Becoming bankrupt or (being a Company) going into
liquidation other than for the purposes of a scheme of reconstruction or
amalgamation, or
(d) Giving formal notice to the Contractor that for unforeseen
reasons, due to economic dislocations, it is impossible for him to continue to
meet his contractual obligations, the Contractor shall be entitled without
prejudice to any other rights or remedied to terminate his employment under
the Contract by giving 14 days prior notice in writing to the Employer, with
a copy to the Engineer.
(2) Upon the expiry of the 14 days notice referred to in Sub-Clause (1) of this Clause the
Contractor shall (notwithstanding the provisions of Clause 46 (1) hereof) with all
reasonable dispatch remove from the Site all Constructional Plant brought by him thereon.
(3) In the event of such termination the Employer shall be under the same obligations to the
Contractor in regard to payment as if the Contract had been terminated under the provisions
of Clause (58) hereof, but in addition to the payments specified in Clause (58) (8) hereof
the Employer shall pay to the Contractor the amount of any loss or damage to the
Contractor arising out of or in connection with or by consequence of such termination.
Currency Restrictions:
64. (N/A).
Taxation:
65. (1) The Contractor shall comply with the statutes, ordinances, laws,
regulations and bye-laws of Dubai and U.A.E. He shall be responsible for
ascertaining the extent and incidence of all taxes, customs, rates, dues and all
other charges payable in accordance with such statutes, ordinances, laws,
regulations and bye-laws.
(3) The rates in the Bill of Quantities will be held to have included for the cost not only of
all such taxes, customs, rates, dues and all other charges in Dubai / U.A.E. but also all
charges of whatever nature incurred outside Dubai / U.A.E. in connection with the
fulfillment of the contract and all such costs will not be considered as reimbursable by the
Employer in the interpretation of Clause 26 of the Conditions of Contract.
Boycotts:
66. The Contractor shall ascertain and comply with any Government regulations
concerning the boycott of other countries.
The Contractor shall indemnify the Employer against any penalty which may arise
as a result of breach of Boycott laws and regulations.
Bribery:
67. Any commission, advantage, gift, gratuity reward or bribe given, promised
or offered by or on behalf of the Contractor or his agent or servant or any
other person on his or their behalf to any officer servant representative or
agent of the Employer or the Engineer or the Engineer’s Representative or to
ny person on their behalf or on behalf of any of them in relation to the
obtaining or the execution of this or of any other contract with the Employer
shall, in addition to any criminal liability which may be thereby incurred,
subject the contractor to the cancellation of this and of all other contracts
which may have entered into with the Employer and also to the payment of
any loss or damage resulting from such cancellation. The Employer shall be
entitled upon a certificate in writing from the Engineer to deduct the
amounts so certified from any monies or otherwise due to the Contractor
under this or any other contract or to recover the said amounts as a debt due
or partly the one and partly the other as the Employer shall deem advisable.
Safety of Construction:
68. The Contractor shall be held responsible, for a period of (10) years after
issuance of Completion Certificate for the safety of construction and for any
defect in the Works resulting from the execution thereof for any loss or
damage that may result out of such lack of safety or defect.
Contract Confidentiality
69. The Contractor shall treat the Contract as confidential. In particular the
Contractor shall not publish any information, drawing or photograph
concerning the Works nor shall he use the works for the purpose of
advertisement without written consent of the Engineer and subject to such
conditions as the latter may prescribe.
Law to apply
70. The Contract shall in all respects be construed in accordance with the law of
Dubai, and the UAE and any difference that may arise between the
As built Drawings
71. During construction the Contractor shall keep an accurate record of all
variations between the work as shown on the drawings and which is actually
constructed. The Contractor shall obtain from the Engineer a complete
reproducible set of drawings, against the payment for the same to the
Engineer and shall in a neat and accurate manner note in ink on such
reproducibles a complete record of all changes and revisions which have
been incorporated in the works as and when they are completed.
CONTRACTOR'S DRAWINGS
General
72. (1) The Contractor shall be solely responsible for providing all sub-
contractors, whether nominated or otherwise, with sufficient copies of all
relevant drawings in order that they can complete their work within the
construction programme.
Co-ordination
(3) The Contractor shall be responsible for co-ordinating all drawings including those
produced by sub-contractors whether nominated or otherwise and submitting them well on
time for the Engineer to study / comment / approve.
Approval of Drawings
(4)All drawings shall be submitted to the Engineer by the Contractor at the appropriate
time. Should the Engineer instruct any alteration or amendment, the Contractor shall ensure
that it is done immediately in order to avoid any delay to the construction programme.
(5) The Contractor shall submit to the Engineer three prints of each drawing or document
Cleaning Up
73. (1) The Contractor shall keep the premises free from accumulation of waste
material and rubbish. At the completion of the work he shall remove from
the premises all rubbish, implements and surplus materials and leave the
building broom-clean. He shall employ a specialized cleaning company to
ensure that proper cleaning is carried out.
Cleaning
(2) Special cleaning : Besides the general broom cleaning, the Contractor shall do the
following special cleaning for all trades under this Contract Scope of Works at completion
of work;
a) Cleaning of Glass: Contractor shall remove putty stains and paint from all glass and
shall wash and polish same. Care shall be taken not to scratch glass.
b) Cleaning of all Painted, Decorated and Stained Work; Contractor shall remove all
marks, stains, fingerprints, and other soil or dirt from all painted, decorated, and
stained work.
c) Removing of all Temporary Protection: Contractor shall remove all temporary
protection and shall clean and polish all floors at completion.
d) Cleaning and Polishing of all Woodwork: Contractor shall clean and/or polish all
woodwork upon completion.
e) Cleaning and Polishing of all Hardware: Contractor shall clean and polish all
hardware for all trades; this shall include removal of all stains, dust, dirt, paint, etc.,
upon completion.
f) Removal of all Spots, Soil, and Paint from all tile work : Contractor shall remove all
spots, soil, and paint from all the work and shall wash same upon completion.
g) Cleaning of all Fixtures and Equipment: Contractor shall clean all fixtures and
equipment, removing all stains, paint, dirt and dust.
Content
1. General notes for the Civil And The MEP works
2. General & scope of work
3. List of Approved Materials, Manufacturers & Suppliers
4. Excavation and earth works
5. Soil investigation report, site plan
6. Concrete works
7. Pile Works.
8. Solid and Hollow blocks
9. Plaster Works
10. External works
11. External Finishes
12. Floor finishes
13. Skirting finishes
14. Wall finishes
15. Ceiling finishes
16. False Ceiling finishes
17. Wood and Carpentry works
18. Metal works
19. Glazing Works
20. Roofing and Water proofing
21. Garbage Chute
22. Lift Works
23. Fitting & fixtures
24. Provisional Sum
SITE WORK
6.1 All quantities for excavation have been measured net with no allowance for increase in bulk or
working space.
6.2 The Tenderer shall allow in his rates for excavation for excavating in any material including
running silt, running sand and rock, commencing excavation of any depth, excavating below the
normal water table, excavating around existing services and mains supporting the vertical sides of
excavations, working space and filling soft spots as described.
6.3 Rates for all excavation shall include for keeping excavations free from water by whatever means.
6.4 Rates for disposal of excavated material shall include for any necessary double handling and the
provision of a tip, if necessary, including any charges in connection herewith.
6.5 The rates for trenches for service pipes shall include for disposal and back filling.
6.6 The rates for drains, inspection chambers, etc. are to allow for testing.
6.7 Rates for drain pipes generally are to include for all short lengths, back stops, wooden plugs and
retaining and alignment pegs required in laying and for the extra involved over normal trench
excavating in hand packing and tamping selected fine material around the lower half of the pipes to
buttress them against the side of the trench. Rates are to include for leaving all pipes clean and
clear.
6.8 Pipes are measured net as laid and are to include for all cuttings, etc., for laying in trenches of any
depth and building in to sides of inspection chambers.
6.9 Rates for drain fittings on all types of drainpipes are to include for extra joints of all types and
cutting and waste on all pipes.
6.10 Rates for drain accessories shall include for concrete surrounds and any additional excavation and
disposal.
CONCRETE WORK
7.1 Construction joints have not been measured but are to be included in the rates for concrete slabs,
beams, columns and walls, etc. The position of all construction joints shall be agreed with the
Engineer.
The rates for blinding concrete shall include for formwork to edges.
7.3 The rates for concrete shall include for hosting to any heights, or lowering to any depth, compaction
by vibrators if required, curing, hacking surfaces for key, forming and grouting mortises, making
good concrete in connection with holes and mortises and all surface treatment to unset concrete.
7.4 The rates for concrete easing to stanchions shall include for expanded metal lathing and angle
beads.
7.5 The rates for concrete shall include for joint sealing between concrete and plaster.
7.6 The rates for rod reinforcement shall include for the fixing of rods of any diameter, extra material in
laps, for straightening as necessary, cutting to length, bending to the required shapes, tying wire,
distance pieces, chairs, block spacers and for welding of bars to form mesh reinforcement.
7.8 The rates for shuttering shall include for all props, struts, stays, wedges, bolts, all cutting labours at
the intersections, overlaps, passing at angles, cutting and fitting round projections and pipes,
grooves of any sectional area, all stops, chamfers, splaying angles, mould oil, strutting and
supporting shuttering to any height and for easing, striking and removal.
7.9 The rates for precast concrete shall include for all reinforcement and for all moulds, square, rounded
and mitred angles, holes or notching for pipes, etc., and hoisting, setting and bedding in position.
MASONRY
8.1 The rates for block work are to include for all cuttings, building to any height of slabs or beams,
raking out joints or hacking surfaces to form key, bedding and pointing frames, etc., building in
door and window frames and the like building in or cutting pinning in ends of lintels, steps, timbers,
steel sections, and the like, mortices and making good in connection with building in cutting and
pinning in holes and mortices.
8.2 The rates for blockwork shall include for all expansion joint with compressible filler and joint
sealant where shown on the drawings unless they are contained within the Bill of Quantities.
8.3 The rates for blockwork shall include for G.I anchor channels and masonry ties at horizontal
abutments of beams and vertical abutments of columns within the Bill of Quantities.
8.4 The rates for hollow block work shall include for filling blocks solid with in-sit concrete and steel
bar reinforcement if shown on the drawings and for providing solid course of block work at sill
level of all openings and bearings of all in-site concrete and at the top of all free-standing walls.
8.5 The rates for cavity walls shall include for G.I vertical twist ties as indicated on the drawings or in
the specification.
METAL WORK
9.1 The rates for all steel work and metalwork shall include for ends, angles, intersections, tamps on
frames, handrails, bearers, stays and the like: assembling and jointing together components, all
holes for pipes, tubes, bars, cables, conduits and the like and all other holes, countersunk holes,
tapped holes, slots and the like. The rates for steelwork shall include for all stanchion and rafter
restraints, gussets and end plates.
9.2 The rates for bolts and countersunk bolts shall include for holes and countersunk holes.
WOODWORK
10.1 The rates for all woodwork shall include for all raking, curved or splayed cutting, miters and ends to
all members, for all joints in members over 200 mm wide or for obtaining timbers in one width
notchings, sinkings, rounded curves, splayed edges, extra timber in joints, horns. Etc. all dowels and
cramps and holes for pipes, tubes, bars, cables, conduits, ducting, trunking and the like.
10.2 The rates for doors are to include for lifting and hanging any type.
10.3 The rates shall further include for rebates, chamfers, grooves, scribed edges, rounded edges and the
like labours, and shall include for all cross grain and stopped work and for all stops, ends, angles
and miters.
TENDER No. 19102 /2019 84/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
THERMAL AND MOISTURE PROTECTION
11.1 The rates for waterproof membranes and insulation slabs shall include for cutting, notching,
bending and lapping, holes for pipes, standards and the like, angles, ends, turning into grooves and
forming outlets, skirtings, upstands, aprons, gutters and channels and forming small openings.
11.2 The rates for gutters shall include for angles, ends, seams, passings at ends and outlets.
11.3 The rates for damp proof courses shall include for laps passing at angles and intersections and for
additional mortar in bedding.
FINISHES
12.1 The rates for all finishings shall include for preparing surfaces for finishings or backings, for
working at or up to any height, and all narrow widths, small areas and all cuttings.
12.2 The rates for all finishings shall include for all dubbing out to walls and columns necessary to
produce an even surface preparatory to the application of the finishing coat.
12.3 The rates for all finishings to soffits shall include for level and sloping soffits.
12.4 The rates for all finishings to block walls are to include for plasterwork to face of concrete columns,
lintels, etc.
12.5 The rates for in-situ plain sheet, tile, slab or block finishings shall include for fair edges, rebated
edges, splayed edges, rounded edges, arrises, quirks, grooves, flutes and the like; all ends and angles
or risers and edges of landing ends, angles, ramps to strings and ends of steps; all fair joints or fair
cutting, making good or cutting and fitting around pipes, bars, cables conduits, ducting, trunking,
sanitary fittings and the like; dishing to gullies and outlets, mortices, sinkings and ends, angles,
ramps, outlets and intersections to skirtings, flush, raised or sunk bands, sills, dividing strips,
control joints, channels, kerbs, and the like.
12.6 The rates for insitu finishings shall also include for all internal and external angles, fair, rounded
and chamfered edges, arrises, chamfered external angles and coved internal angles.
12.7 The rates for floor , wall and ceiling finishes shall include for expansion joints and control joints as
specified or as shown on drawings.
12.8 The rates for beds and backings shall include for preparing surfaces etc
12.9 The rates for plastering to vertical surfaces shall include for providing expanded metal lathing of the
required width wherever concrete and blockwork surfaces meet.
12.10 The rates for backings, plasterings, rendering, shall include for all metal plaster stops, angles and
beads and additional stops to form grooves in surfaces.
12.11 The rates for ceramic wall tilling shall include for a hollow rounded fillet at the junction with other
wall finishes.
12.12 The rates for painting shall include for working to or at any height: internal or external work; all
narrow widths; rubbing down between coats; work in multi-colours; cutting to line: opening edges
of doors and work on additional surfaces exposed by such opening edges; hooks, bolts and clips to
12.13 The rates for painting on wood shall include for work on hardwood or softwood and for knotting.
12.14 The rates for painting on manufactured boards and wood shall include for surface filling.
12.15 The rates for sprayed emulsion painting to horizontal soffits shall include for painting all pipes,
ducts, fittings, etc. as no allowance has been made in the measured items for this equipment.
13.1 The rates for pipework and ductwork shall include for, but not limited to the following:
All cuttings, short lengths and small quantities,
Made bends and proprietary fittings,
All jointings,
Fixing with approved holderbats or pipe clips cut and pinned, built in or plugged and screwed.
Sleeves through walls.
Bends and fittings on pipes whatever the diameter and valves and the like.
13.2 The rates for duct work shall include for, but not be limited to the following:
Cutting, short lengths and small quantities.
Couplers and or joints in the running lengths.
Bends, tees and other fittings.
Fixings with mild steel angles and threaded rod rawl plugged to the structure
And Testing and commissioning.
13.3 The rates for sanitary fittings and the like shall, unless otherwise described or implied, shall include
for, but not be limited to the following:
Assembling components parts including suitable bedding compounds.
All necessary plugging and screwing.
Joints to water services with straight or bent proprietary connectors.
Cleaning of all protective wrappers and leaving ready for use and
Leaving taps and valves greased, clean and in full working order.
13.4 The Contractor shall include for the supply of manufacturer’s recommended spares as required by the
Specifications for all mechanical engineering installations and shall submit details of spares to be
provided by him on a separate sheet accompanying his tender submission.
13.5 The rates for equipment shall include for, but not be limited to the following:
Assembling components parts including all supports,
Fixing including rawlbolts or the like,
Aligning,
Testing and pre-commissioning and
Spare parts. The rates for equipment shall include for the provision of commissioning spares,
consumables and operating spares during the one year maintenance warranty period.
13.6 The rates for testing and pre-commissioning for Mechanical Works shall include for, but not be
limited to the following:
Provision for permanent drains at all low points and vents at high points irrespective if shown on the
drawings.
Temporary supply lines, hoses, pumps, instruments, temporary blinds and gaskets.
Disconnection of piping systems and
13.7 The rates for commissioning shall include for vendor attendance at site.
Items that have been measured with imperial sizes shall require the Contractor to obtain that size
or the nearest metric equivalent to ensure a proper and component fit.
14.1 The rates in general shall include for , but not limited to the following:
All cutting short lengths and small quantities.
All joints in the running length and all connections.
All considerations arising from the Specifications.
Fixing conduits/cable trays, etc. by approved methods.
Pipe sleeves through walls.
Assembling components parts.
Cleaning off all protective wrappers and leaving ready for use.
Leaving all equipment etc. clean and in full working order.
Draw wires in empty conduits.
Rates for cable and duct trench excavation shall include for all excavation, bedding, backfill and
disposal as required by the Statutory Authority standard Specifications and
All pre-commissioning and commissioning works.
Main Circuits
Cabling and conducting within the buildings shall be described as an item, and be inclusive of all
sleeves, joints, etc. as required to connect the supply to the Main Distribution Board.
The Contractor shall include for the supply of manufacturer's recommended spares as required by
the Specifications for all electrical engineering installations and shall submit details of spares to be
provided by him on a separate sheet accompanying his tender submission. The rates for equipment
shall include for the provision of commissioning spares, consumables and operating spares during
the one year maintenance warranty period.
The cable lengths/routes are taken from point to point on the drawing, any cable required for
connections, loops, etc. at equipment, appliances, control gear or the like will be deemed to be
included. Internal cables are included with items.
The particular specification shall be read in conjunction with the General specification. Where
discrepancies occur between the conditions of the general and particular specification then the conditions of
the particular specification shall take precedence.
The contractor is responsible to execute any item mentioned in the particular specifications, drawings and
bill of quantities.
If any discrepancies occur between the above contracts documents, Consultant have the right to choose
any of the specified materials unless the contractor brought it to their notice while tendering.
SCOPE OF WORK
Material Procurement schedule to be submitted by all the sub contractors in line with the
approved time schedule.
Shop drawing tracking schedule to be submitted by all the sub contractors in line with the
approved time schedule.
Sub contractor-tracking schedule to be submitted for the consultant approval in line with the
approved time schedule.
1. Scope of work:
Includes all the required earth works for site preparation, excavation, backfilling, dewatering, shoring, anti
termite treatment deposal of surplus excavated materials or any other works according to the project
drawings.
2. Nature of soil:
The contractor to visit the site and clear for himself the actual average ground level compared to the road
level and the ground surface condition and to include in his bid any related works inside the plot limit to
have to zero level.
The Contractor shall judge for himself the nature of the ground and the possible occurrence of rock and
shall be fully responsible for ascertaining all necessary information concerning strain, permanent water
table, periods of rain fall, flooding of the site and all maters affecting the excavation and foundation work.
No extra will be allowed due to want of knowledge in this respect.
The methods of excavation, which the Contractor desires to use, shall be at the sole discretion of the
Contractor. The explosives may be used only with the Engineers written consent.
The Contractor shall report to the Engineer when excavation is ready to receive foundation concrete and
shall obtain consent before depositing concrete. Any concrete deposited before consent is given may, at the
Engineers request, be broken up and removed at the Contractors expense and the work re-executed at no
extra to the Employer.
In the event of excavation being made deeper than directed by the Engineer, the Contractor shall fill in the
excavated void to the correct profile with hard-core or with sulfate resistance mass concrete (Mix “D”) as
described in the Concrete Work Section herein after, at his own expense, and to the satisfaction of the
Engineer.
The final 6” depth of all excavations shall be taken out by hand unless allowed by the Engineer otherwise
and the bottom leveled and rammed immediately prior to placing Concrete.
3. Except where indicated on the drawings to remain undisturbed, the Contractor shall remove all
top soil, plants, roots vegetation, rubbish, rocks, etc. from areas lying within limits of structures and from
areas to receive fill, embankment, surfacing, road construction, concrete or other construction.
Foundations shall rest on firm undisturbed soil free from loose materials
4. The Engineer’s Representative may instruct the Contractor to test the bearing capacity of the
soil in the bottom of excavation. Upon receipt of such instruction, the contractor shall forthwith carry out
such tests at his expense.
Should the bottom of excavation if found to be unsuitable as bearing surfaces as a result of such tests or
inspection by the Engineer’s Representative, the Contractor shall excavate further as directed until a
satisfactory bearing surface is achieved.
5. Sheeting And Shoring: As per site coordination/soil report, the contractor has to submit the design
criteria for Consultant approval
6. Excavated materials
Excavated materials shall not be piled along sides of excavations in a manner that will overload or increase
danger of excavation side collapse.
Excavated materials shall be separated into those suitable for fill and those unsuitable for fill, materials
unsuitable for fill shall be removed as soon as possible from the site.
TENDER No. 19102 /2019 89/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
The excavated materials arising from all excavations declared by the engineer representative suitable for fill
to be used as filling, all other filling materials shall be imported.
Filling or backfilling shall be placed in layer not exceeding 15cm thickness after compaction, each layer
shall be spread and moistened or dried by aeration to ensure the OWC “optimum eater content” and shall be
compacted uniformly up to the specified density “98%”, the number of the density test per layer shall be as
instructed by the Engineer’s Representative.
When machine compacted, compaction shall be by means of a 6 ton smooth wheeled roller.
The Engineer's Representative shall have the right to disapprove any compacting device of inadequate
capacity or in his opinion, of type unsuited to the character of the material, being compacted/. Heavy
equipment for spreading and compacting fill and backfill shall not be operated closer to walls than a
distance to the difference in height between the opt of the footings and the layer being compacted
Testing to determine the density of enplane soil shall be by means of ASSHTO Standard
Method of Test T147 or in accordance with BS1377: 1975. The number of density tests per layer shall be as
instructed by the Engineer's Representative.
When backfilling behind the retaining walls or the basement walls, no compaction shall be carried out until
the wall concrete achieved its full strength.
Compact fill shall consist of approved materials obtained either from excavations or from other approved
sources. Compacted fill shall comprise suitable granular materials well graded and shall not include
perishable matter or an excess of fines and should give a dense fill layer. The material shall be free of
organic matter and have the following properties.
Minimum Soaked CBR of 15% when the material is compacted to 95% of the maximum dry density.
Insitu CBR of 10% when the compacted layer is field tested at site.
Liquid Limit not more that 35% and plasticity index not more than 60%
Linear Shrinkage not exceeding 3%
Water Soluble Salts not more than 5% by weight of dry material.
Organic Materials on organic material permissible
Maximum Particle Size not more than 75% mm: max passing seive No.200< 30%
Lab CBR Tests as determined by Test 16, BS 1377.
Field Density Test as determined by Test 15B of BS 1377.
Linear Shrinkage test as determined by AASHTO T92
Organic Matter Test as determined by BS 1377
Maximum Dry Density At Optimum Moisture Content as determined by Test 13,
BS 1377.
Liquid limit as determined by BS 1377;1975 : 2.2 (Test 2 A : Preferred method using the cone
penetrometer)
TENDER No. 19102 /2019 90/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
Plasticity Index as determined by BS 1377: 1975 2.4
Water Soluble Salt as determined by BS 812 Part 117.
Tests for Density and Compaction
The following gives the minimum testing required for fill. Additional or more frequent tests may be
required if materials vary or workmanship is consistent:
i) Laboratory tests for MDD, optimum moisture contents, for each layer.
ii) Field density and moisture contents, insitu CBR, for each layer as required by the Engineer.
The areas shall be rejected if the resulting test results do not satisfy specified requirements.
The Contractor shall alter, adopt and maintain all such works described above for the whole period of the
contract and shall finally clear away and make good all damages done.
The construction and efficiency of the shoring, underpinning, strutting and the like for the purpose for
which it is erected shall be the responsibility of the Contractor, should any subsidence or any other damage
occur due to the inefficiency of the shoring, underpinning, strutting and the like or any other support
provided, the damage shall be made good by the Contractor at his own expense and responsibility.
The shoring, strutting, piling and the like shall be executed in such a manner as to cause as little
inconvenience as possible to adjoining owners or the public and the Contractor shall be responsible for
negotiating with the adjoining owners the means to safeguard their property and for the use of any portion
of their land for the purpose of executing the excavations and no claims submitted on this ground will be
entertained.
The Contractor shall be held solely responsible for the safety of the adjoining existing buildings/structures
the sufficiency of all temporary or permanent shoring, underpinning, piling, and the like. The Contractor
shall keep the Engineer informed as to manner in which he intends to proceed with the execution of the
excavations and obtain his approval; such approval if given shall not absolve the Contractor of his
responsibility under this clause.
The Contractor shall save harmless and indemnify the Employer in respect of all claims, demands,
proceedings, damages, costs, charges and expenses whatsoever arising out of or in relation to any such
matters in so far as the Contractor is responsible under this Clause.
9. Dewatering:
Where the excavation level is under the water table level, it is necessary to install special form of
dewatering equipment around the perimeter of the excavated area, the Dewatering amount will be deducted
from the contract value if the same has not been executed
The excavations shall at all times be kept free from storm water, percolating water or subsoil water by any
means necessary. The contractor shall provide, maintain and clear away on completion any equipment
necessary together with temporary drains and the like. Under no circumstances shall concrete be poured, fill
placed, pipes laid or appurtenances installed in excavations containing water.
Where the excavation level is below the natural water table and it is necessary to pump continuously form
the excavation or to install a specialist form of dewatering equipment around the perimeter of the site or
excavation, the Contractor will be responsible for ensuring the safety and stability of all adjoining structures
TENDER No. 19102 /2019 91/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
and services or utilities above or below ground level. It will also be the responsibility of the Contractor the
equipment installed shall ensure the excavation and subsequent construction is carried out in dry
conditions.
Continuous or permanent dewatering of the excavation or site may not be undertaken without the written
approval of the Engineer to the work and the methods to be employed which shall also comply with Codes
of practice and local authority requirements.
The water pumped from the excavations or well points shall be pumped to disposal points or sumps as
approved by the Engineer and/ or Local Authority and if so required be passed through settling tanks before
disposal. Under no circumstances must water be disposed of the Municipality's sewer systems or as
instructed by them.
The de-watering system catering for de-watering upto about 50 cm below the final excavation level of the
bottom of the blinding concrete of the pile-cap/raft shall be handed over by the Piling Contractor at the
commencement of the project.
If the dewatering system does not maintain the groundwater level to obtain the specified sub grade
conditions, the Engineer shall be notified and the system shall be modified appropriately at no additional
cost to the Client.
If dewatering system causes sub grade soils to be unable to meet density requirements due to dewatering
interruptions or an inadequate system, notify the Engineer and modify the system to perform as specified at
no extra cost to the Client.
The Contractor shall submit the following for the approval of the Engineer.
Shop drawings to a scale agreed with the Engineer. Drawing shall indicate the locations and sizes of berms,
dikes, ditches, all deep wells, observation wells, sand and gravel filters, settlement points, well points,
sumps, recharge systems and discharge lines, including their relation to sedimentation ponds.
Capacitates of pumps, prime movers, and standby equipment.
Unless otherwise specified continue dewatering uninterrupted until the structures, pipes, and appurtenances
to be built there have been completed such that they will not be floated or otherwise damaged by an increase
in ground water elevation.
Dewatering Discharges.
Install sand and gravel filters in conjunction with well points and deep wells to prevent the migration of
fines from the existing soil during the dewatering operation.
Transport pumped or drained water without interference to the other work, damage to pavement, other
surfaces, or property. Discharge pumped water to a sedimentation pond or drainage system and as approved
by the local Municipality Authorities.
Do not discharge water into any storm or sanitary sewer system. Discharged water must be visible or
allowed to be observed to verify compliance with U.A.E Regulations.
Provide separately controllable pumping lines.
The Engineer reserves the right to sample discharged water at any time.
The soil investigation report enclosed herein is for reference and guidance only and it shall be
the responsibility of the Contractor to ensure that the minimum design soil strength is met with.
Any modification requires with the foundations or the soil strata under the foundations to satisfy
the design requirements shall be carried out at no extra cost and/or the time to the Contract.
The Contractor shall however submit all the necessary details of his findings and his proposed
modifications for the approval of the Engineer before commencing the work. However, any
such approval accorded shall not relieve the Contractor of any of his contractual obligations and
responsibilities.
The Contractor will follow up all recommendations and instructions given by the nominated
geotechnical engineer that appointed by Engineer. The scope of work of this nominated
geotechnical engineer will mainly pertain earthwork, site grading and all sub construction
works (including piles tests).
The cost of all tests in enclosed soil report or other required under this clause are to be paid by
the Contractor.
1. Codes of Practice:
Except where they are varied by the requirement of the this specification the provisions of the British
Standard codes of practice BS 8110-1985 the structure use of concrete in building be help to be incorporated
in the specification.
2. Materials
Except where otherwise specified all materials for which British Standard specifications exist shall conform
to the latest revised editions of such specifications as published at the date of tender.
a. Cement.
Except where otherwise required cement shall be locally manufactured controlled fineness ordinary
Portland cement complying with BS 12 or ASTM C 150 Type 1
The source of supply of cement shall be subject to the Engineer's approval and the Contractor shall at all
times furnish the manufacturer's certificates and proof that the required specification has been complied
with together with a note of the date of manufacturer, certified by an independent agency. The Engineer
shall have the power to reject a part of the whole of any consignment of cement if the considers it to be
unsuitable for use in the works.
The chemical composition of the cement shall comply with the standards as stipulated above an in addition
with the following requirements.
ii. The total lime (CaO) contents shall not exceed 70% unless agree otherwise by the engineer.
One brand as approved by the Engineer shall be used throughout the works unless otherwise authorized by
the Engineer in writing.
i General
Aggregates for concrete shall consist of naturally occurring materials complying with the requirements of
fine and coarse aggregates of BS 882 and as specified herein, except that for Class D concrete all in
aggregate within the grading limits of Table 3 of BS 882 may be used. Approval of aggregate will not
prevent subsequent rejection results of subsequent tests of not indicate compliance with the specified
requirements. The properties specified for aggregates in Sections 2,3 and 4 shall be for aggregates form
individual sources. The use of beach sand in mixes for reinforced concrete is prohibited. The frequency of
testing aggregates shall be one test each 50m3 or different batch of aggregates received at site.
The CI test shall be as per BS 812 (Part 117), S03 as per BS 812 (118) and water absorption test as per Bs
812.
The amount of deleterious material shall not exceed the following limits when determined by the ASTM
standard test stated below.
Fine aggregate shall satisfy the requirements of ASTM C33 with regard to organic impurities, when tested
in accordance with ASTM C 40 and C87. Local sands contain aggressive salts, and it is essential to test the
fine aggregate to ascertain that the maximum quantity of acid soluble chloride 4s shall not exceed 0.4% by
weight of fine aggregate. The fine aggregates shall be washed with fresh water complying with BS 3148
(1980)
unwashed sand shall not be allowed under any circumstances for any part of the works.
When fine aggregate is subjected to five cycles of the sodium Sulphate Soundness Test. ASTM C88 the
loss shall not exceed 10% of weight.
Fine aggregate shall be of such uniformity that the fineness modules as defined in AASHTO M6 shall not
vary more than 0.20 either way from fines modules of the representative samples used in the mix disign.
The sand equivalent for fine aggregate (AASHTO T176) shall be a minimum of 70%.
The water absorption of fine aggregate shall not exceed 2% (BS 812)
Coarse Aggregate shall be prepared as single size aggregate and blended to produce normal size grading.
The combined grading of coarse aggregate shall be with the limits given in Table 1 of BS 882 for nominal
size of graded aggregate 20mm to 5mm.
The proportion of soft and friable particles in coarse aggregate shall not exceed 1% when tested in
accordance with ASTM C 142. The maximum quantity of acid soluble chlorides
(C1) shall not exceed 0.03 % weight of coarse aggregate. The maximum quantity of acid soluble sulphate
(SO3) shall not exceed 0.4% by weight fo coarse aggregate. (BS 812 part (118). No organic matter of any
nature shall be permissible to be contained by the aggregates such as wood, paper, plastic, or any other
matter, The standard test method for organic maters shall be as per BS 1377 Test 8.
For the combined grading, the quantities of acid soluble salts shall not exceed the following in the concrete
mix.
Chlorides (C1)- Max 0.3% by weight of cement ( OPC ) and max 0.06% for SRC
Sulphates ( SO3) Max 4 % by weight of cement (including the sulphate in the cement)
If so directed by the Engineer, the contractor shall carry out petrographic analysis in accordance with ASTM
33 and C 295 on all aggregates proposed for use. Arising from such analysis the Engineer may require the
Contractor to perform further tests in accordance with ASMýTm C286 and BRE Digest No. 35; also in
accordance with ASTM C227 and C586 if the Engineer so decides after his examination the results of the
proceeding tests. In the event that tests in accordance with ASTM C227 are called for, the cement used in
the test shall have an alkali content (expressed as sodium oxide +0.658 potassium oxide)
greater than 0.8% by weight of 2.25 to 1.0 Depending on the results obtained the Engineer may decide to
limit the alkali content (Na 20 and K20) of the cement to 0.6%.
c) . Water.
Unless otherwise authorized in writing by the engineer only water form portable supply system may be used
for mixing concrete and other products containing cement. Similarly only portable water conforming to BS
3148 (1980) may be used for curing purposes. No other source of water shall be allowed to be used for any
of the above purposes.
i). hot rolled mild, high yield steel deformed bars complying with BS 4449 or similar approved standard.
ii) cold twisted bars complying with BS 4482 or similar approved standard.
iii) steel fabric reinforcement complying with BS 4482 or similar approved standard.
In case any other type of reinforcement is required, it shall comply with the requirements of the particular
specification .
All reinforcement shall be free of loose rust and mill scale and any coating such as oil, clay , paint etc.,
which might impair the bond with the concrete Steel reinforcement shall be stored in clean conditions and
shall be protected from damage at all times. It shall be clean and free of loose rust, dirt , mud, loose mill
scale, paint, oil or all other foreign substances at the time of fixing in position and subsequent concreting.
Manufacturer's test certificates for all classes fo reinforcement shall be supplied when required. Specimens
sufficient for three tensile tests and three supplied when required. Specimens sufficient for three tensile
tests and three cold bending tests per ten tones of bars or traction there of and for each different size of bar
shall be sampled under the supervision of the Architect. Testing shall be in accordance with BS 4449 or
other approved standard and batches shall be rejected if the average results for each batch are not in
accordance with the specification.
The Contractor shall cut and bend bars to Bs 4466 and to schedule, if provided or unless otherwise
instructed by the Architect, Straight sections of bars must be kept out of winding.
The internal radius of bands shall in no case be less than two times the diameter of the bar. Great care is to
be taken to be stirrups and blinders separately and to the sizes shown.
All bars will be bent cold on approved machines, and at temperatures in the range of
5 C to 100 C.
Lengthening of bars by welding, and rebinding of incorrectly bent bars will not be permitted, except where
requested by the Engineer.
Unless otherwise allowed for in the reinforcement except where described in the Contract or where
approved by the Engineer.
Reinforcement shall be placed and maintained in the position shown in the Contract. Unless otherwise
permitted by the Engineer, all bar intersections shall be tied together and the ends of the tying wire shall be
turned into the main body of the concrete. 1.2 mm diameter stainless steel wire shall be used throughout.
i) Concrete cover blocks required for ensuring that the reinforcement is correctly positioned, shall be as
small as possible consistent with their purpose, of a shape acceptable to the Engineer, and designed so that
TENDER No. 19102 /2019 97/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
they will not overturn when the concrete is placed. They shall be made of concrete with 10mm maximum
aggregate size to produce the same strength as the adjacent concrete. Tying wire complying with the
requirements of section e last paragraph shall be cast in the block for the purpose of tying it to the
reinforcement.
Concrete cover blocks required for ensuring that the reinforcement is correctly positioned, shall be as small
as possible consistent with their purpose, of a shape acceptable to the Engineer, and designed so that they
will not overturn when the concrete is placed. They shall be made of asbestos cement, factory produced and
of the same strength as the adjacent concrete. Tying wire complying with the requirements of section e last
paragraph shall be cast in the block for the purpose of tying it to the reinforcement.
3. Storage of Materials:
a. Cement
The cement shall be stored in a weather proof shed used exclusively for this purpose. The shed shall be
large enough to allow proper aeration and effectual separation of the various consignments, the old
consignments being used before the latter ones. Cement shall not be stored on site for more than 21 days;
after this it must be removed from the site a the Contractor's expense. Alternatively, the cement may be
stored in a silo the design of which has been approved by the Engineer.
b. Aggregates
The aggregates are to be stored on a concrete slab in such a way that contamination form other materials and
inter-mixing of the various grading will be prevented. The aggregate shall be deposited in a way that will
prevent segregation through dropping on to the peak of a high heap.
The Contractor's attention is drawn to the fact that for some of the design mixes specified it
may be necessary in order to obtain the required cube strength with minimum cement content to store the
aggregate in different sizes so that they can be combined in the correct proportion at the mixer.
Reinforcement
The reinforcement should be stored and properly covered clear to the ground and should be protected from
contamination by other materials.
4. Testing of Materials:
(All tests to be carried out by an independent approved Lab.)
The cost of all tests required under this clause are to be paid by the Contractor. whether the test results show
the materials to be satisfactory for the work or not.
The Contractor shall submit to the Engineer sufficient quantity of material proposed to be used for the
works, together with a list of suppliers to be employed. The Engineer's consent in wiring shall be obtained
to all such samples and source of supply before any concreting work is put in hand no change shall
subsequently be made without the Engineer's approval. The Engineer shall have access to all sources of
supply for the purpose of inspecting and taking samples of any materials which will be later delivered to the
site.
a) Cement
Cement will be tested at an approved testing station. Sample are to be taken from each delivery of cement as
directed and conveyed by the Contractor to a testing station to the approval of the Engineer, or as specified.
TENDER No. 19102 /2019 98/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
b) Aggregate
All aggregates shall be tested by an approved testing laboratory at the beginning of work and for every
50m3 of aggregate or before any change is made in the source of supply during the progress of the work and
the Engineer shall have approved the results of such tests before the preliminary test cubes are made.
The size of the sample shall be as required by the testing laboratory but in the absence of specific instruction
two sample of not less than 121/2kg. of fine aggregate and 50kg. of coarse aggregate shall be quartered
down from representative bulk samples for each test.
Each sample shall clearly and durably labeled to give the name of the supplier and of the pit of quarry and
one of each pair of samples shall be sent to the laboratory for testing and one retained on the site for
reference.
c) Water: water for the purpose of construction including all concrete works shall be clean potable water.
d) Reinforcement
Generally the manufacturer's test certification should be obtained with each delivery of reinforcement but
the Engineer reserves the right to request tests from an independent testing from time or from every batch of
steel delivered to site.
e) Testing Equipment
The Contractor shall provide:-
1. Sufficient 150mm. cast iron cube moulds to enable him to carry out the requirements of this
specification.
4. Suitable graduated measuring tubes for measuring the moisture content of fine aggregate.
Concrete for blinding and other uses as indicated on the Drawings shall be composed of sulphate resistant
cement and aggregates, complying with BS 882, including all-in aggregate within the grading limits of the
British Standard.
For pumped concrete, admixtures may be used in particular cases to increase the workability. As there is
likelihood of higher strengths due to their use, the requirements of average of four cubes and that of an
individual test result have to be correspondingly increased and those figures shall be agreed upon at the trial
mix stage.
Cement : B.S 12
Water : B.S 3148(Also as specified for concrete
works
Aggregates : B.S 882
Admixtures : B.S 5075 Part 1
All concrete mixes are to be designed according to requirements of the above table.
The concrete shall be mixed by machine to a uniform colour and consistency before placing./ The quantify
of water used shall not exceed that required to produce a concrete with sufficient workability to be placed
and compacted in the required location.
The concrete shall be compacted by mechanical vibration.
c. Trial Mixes
No structural concrete shall be placed in the works until the Engineer has approved the relevant mix.
The Contractor shall, at least 35 days before the commencement of concreting, have trial mixes prepared in
a laboratory to be approved by the Engineer. The concrete from each mix shall be tested in accordance with
clause 4.1.6 and must satisfy the strength requirements of Clause 4.1.5.
When the mix has been approved, no variations shall be made in the proportions the original source of the
cement and aggregates, or in the type size and grading zone of the latter without the consent of the Engineer
who may require further tests to be made.
The Engineer may also require practical tests to be made on the site by filling trial moulds to confirm the
suitability of the mix for the works. In these tests, the type of plant used for mixing, the method of
compaction used, and the form work face to the mould shall be similar in all respects to those intended for
used in the works.
When the Contractor intends to purchase factory-made precast concrete units the Engineer may dispense
with trial mixes and laboratory tests, provided that evidence is given which satisfies him that the factory
regularly produces concrete which complies with specification, The evidence shall include details of mix
proportions, water-cement ratio, workability and strengths obtained at 7 and 28 days.
d) Mixing Concrete
i) The weighing and water-dispensing mechanisms shall be maintained in good order. Their accuracy
shall be maintained within the tolerances described in BS 1305 and checked against accurate weights and
volumes when required by the Engineer.
iii) Unless otherwise agreed by the Engineer, concrete shall be mixed in a batch type mixer manufactured in
accordance with BS 1305 or in a batch type mixer, a specimen of which has been tested in accordance with
BS 3963 and having a mixing performance within the limits of table 6 of Bs 1305. Where appropriate the
batch capacity, conform to the detail furnished in accordance with the requirements of BS 3963 for the mix
which corresponds most closely to the mix proportions being used. The mixing blades of pan mixers shall
be maintained within the tolerances specified by
the manufacturer of the mixer and the blades shall be replaced when it is no longer possible to maintain the
tolerances by adjustment.
iv) Mixers which have been out of use for more than 30 minutes shall be thoroughly cleaned before any
fresh concrete is mixed, and unless otherwise agreed by the Engineer, the next batch of concrete through the
mixer shall contain only two-thirds of the normal quantity of coarse aggregate. Mixing plant shall be
thoroughly cleaned before changing from one type of cement to another.
v) The Contractor shall ensure that the constituent materials of the concrete are sufficiently cool to prevent
the concrete from stiffening in the interval between its discharge from the mixer and compaction in its final
position.
e) Ready-Mixed Concrete
i) Ready-mixed concrete as defined in BS 5238, batched off the site, may be used only with the agreement
of the Engineer and shall comply with all requirements of the Contract.
ii) The concrete shall be carried in purpose-made agitation's, operation continuously, or truck mixers. The
concrete shall be compacted and in its final position within 2 hours of the introduction of cement to the
aggregates, unless a longer time is agreed by the Engineer. The time of such introduction shall be recorded
on the delivery note together with the details of the constituents of each mix.
iii)When truck-mixed concrete is used, water shall be added under supervision, either at the site or at the
central batching plant as agreed by the Engineer but in no circumstances shall water be added in transit.
iv) Unless otherwise agreed by the /engineer, truck mixer units and their mixing and discharge performance
shall comply with the requirements of BS 4251. Mixing shall continue for the number and rate of
revolutions recommended in accordance with item 9
in Appendix B of Bs 4251 or, in the absence if the manufacturer's instructions, mixing shall continue for
not less than 100 revolutions at a rate of not less than 7 revolutions per minute.
When the rate of evaporation of surface moisture from concrete is expected to approach 1 kg/m2 per hour or
when the shade air temperature is 35C and rising, precautions shall be taken, including the following:
Fig.1108-effect of concrete and air temperature, relative humidity, and wind velocity on the rate of
evaporation of surface from concrete.
2. reducing the concrete temperature to the lowest practical level by procedures such as:
TENDER No. 19102 /2019 101/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
i. shading the aggregate
ii cooling the mixing water before use
iii screening the mixing plant and transporting vehicles from wind, rain and sun.
iv erecting wind breaks ad sunshades at the concrete placing location
v reducing the time between the placing of the concrete and the start of curing to the minimum possible
vi) minimizing evaporation (particularly during the first few hours subsequent to placing the
concrete) by suitable means such as applying moisture by fog spraying.
All precautions to be taken shall be subject to the Engineer's approval and the Contractor shall demonstrate
that all approved precautions are available for use prior to the Engineer granting approval to any concreting
operation.
The temperature of the concrete when placed shall not exceed 30 C or shall be concrete mixed or placed
when the shade air temperature is 35C or above, or is expected to reach such a level during concreting,
without special permission from the Engineer.
The Contractor is to employ a qualified competent person whose main duty is to supervise all stages in the
preparation and placing of the concrete work.
cement content shall not less than 420 Kg/m3 and fcu at 28 days should be not less than 40 N/mm2
and 80% of that strength should be provided after 7 days, with a slump not less than 200 mm using
superplasticiser rehobuild805 from BASF or equally approved, a transmit time of 60 minutes have
been allowed from mixing of concrete to placing of concrete
W/C ratio = 0.38.
Concrete placing temperature shall not be more than 32 degree Celsius.
Concrete water absorption shall be below 2% - when tested as per BS 1881 part 122.
Concrete water penetration shall be below 10mm -when tested as per Din 1048.
Concrete chloride permeability to be below 1500 coulombs - when tested as per AASHTO T277.
Concrete air content shall not be more than 2%.
Durable concrete using GGBS 50% or Fly Ash 30-40 % to be added, with a cement
content of 420 Kg/m3 and fcu should be not less than 50N/mm2 at 28 days 80% of that strength should
be provided after 7 days, with a slump not less than 150 mm.
Ipanex from Emirates specialist, Rheocrete 222+ from BASF construction chemicals or
equal to be added. W/C ratio = 0.38.
All columns will be with grade 40 N/mm2 with a cement content not less than 420 Kg/m3Concrete
placing temperature shall not be more than 32 degree Celsius and. W/C ratio = 0.38
Concrete water absorption shall be below 1.5% - when tested as per BS 1881 part 122.
Concrete water penetration shall be below 10mm -when tested as per Din 1048.
Concrete chloride permeability to be below 1500 coulombs - when tested as per AASHTO T277.
Concrete air content shall not be more than 2%.
4. Slabs: -
All slabs will be with grade of 40 N/mm2 with cement content not less than 420 Kg/m3
b. Sampling
Sampling shall be in accordance with the requirements of BS 1881(method of Testing Concrete) at a testing
station approved by the Engineer.
Concrete shall be sampled in two series as follows:
Series A- one batch shall be sampled at random from every 20 cubic.meter of concrete placed. For strength
tests one sample shall be taken from each batch samples, from which six test cubes shall be made, three of
which shall be tested at 7 days and three at 28 days.
Series B- batches shall be sampled at the direction of the Engineer. For strength test three independent
samples shall be taken from bath to be sampled, from each of which one test cube shall be made. Test cubes
shall tested at 7 days as directed.
The workability tests. one sample shall be taken at an early the discharge of each batch sampled at the
direction of the Engineer.
Testing
1. Test cubes shall be made, cured and tested in accordance with BS 1881 Parts 101,108,111 &116.
2. Where a batch been sampled for the purpose of determining the workability of the concrete, one test shall
be made on each sample using one of the following tests in accordance with AB 1881 (1983) and shall be
within the following limits of the values for the accepted trial mix:
d. Load Tests
lf any of the works tests are not up to standard, the Engineer shall be entitled t stop the work until the reason
has been investigated and steps taken to prevent further low results.
Any concrete carried out from a batch that afterward appears to be faulty will be liable to rejection and, if so
directed, the Contractor shall, at his own expense, cut and replace the defective work, or take such other
measure as may be allowed to prove by means of test loading, at his own expense, that the concrete is
capable of safely withstanding the prescribed stresses.
The control of concrete quality shall satisfy the requirements of Clause 4.1.5. (a to c)
b) Standard of Control
The Standard of control for structural concrete shall be such that not more than % of works concrete test
cubes shall have strengths which fall below the appropriate specified minimum strength. Compliance with
this standard of control shall be monitored by the methods described below.
As test results become available average values of test results and values of standard
deviation shall be determined on a continuing basis for Series a cubes taking 7 days & 28 days tests results
separately, but min. each calculating the Standard deviation.
Until the relationship between 7 days strength and 28 strength has been established to the satisfaction of the
Engineer, the assessment of control shall be based on the 28 days only. The required standard of control
shall be deemed to have been attained if the average value of the 28 days test results exceeds the specified
minimum strength.
When the Engineer is satisfied that sufficient cube test results from series a cubes are available to establish
the rates of 7days to 28 days strength the assessment of control as described in paragraph above shall also be
based on the 7 days cube tests.
The strength requirements of each set of three test cubes of Series B shall be deemed to be satisfied if none
of the test results for the three cubes is below the required minimum strength, or if the average value of test
results for the three cubes is not less than the required minimum strength and the difference between the
greatest and the lowest value is not greater than 20% of the average value. The required minimum strength
shall be the specified minimum strength at 28 days, as detailed on the drawing, multiplied by that ratio of 7
days and 28 days strength as determined.
In cases where the standard of control is being met but where any one cube tested has a strength less than 85
% of the required minimum strength, or where any set of three cubes in Series B fails to satisfy the strength
requirements as specified, the Contractor shall take such remedial action as the Engineer may direct. This
may require the -
cutting out of the concrete to which the cubes correspond together with any sound concrete as the Engineer
may consider necessary i n order to effect a satisfactory repair, the whole to be carried out at the
contractor's expense.
d. Additional Tests
Where a subsequent operation independent on the strength of the concrete in particular portions of the work,
for example if the Contractor wishes to remove form work in advance of the minimum periods stated or to
TENDER No. 19102 /2019 104/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
subject the concrete to early loading, the Engineer will require additional cubes to be made, stored, cured
and tested on the same basis as is specified for Series A&B in Clause 4.6 (b&c) to check the concrete has
attained sufficient strength for the subsequent operation to proceed until he is satisfied that the requisite
strength has been reached.
8. Concrete Placing
Before the concrete is actually placed in position the inside of the shuttering or moulds should be inspected
by the Engineer or the Engineer's representative to see that it has been properly assembled and fixed.
The Contractor shall submit to the Engineer a weekly and a monthly concreting program which shall be
approved before the concreting work is executed.
The Contractor shall be responsible for giving 24 hours notice in writing to enable the Engineer to have a
representative present during concreting. In the event of the contractor not giving such notice, the Engineer
reserves the right to cut away such concrete as he may require to expose the reinforcement and the cost of
such cutting away shall be borne by the Contractor, even is the position of the reinforcement is found to be
correct.
As soon as possible after the mixing and before the initial set has taken place, the concrete shall be
deposited directly in the work from barrows, etc. carefully trimmed into position in layers and well rammed
and vibrated. Concrete shall not be thrown or dropped form a height exceeding 2m without the written
authority of the Engineer.
The concrete shall be worked up against the face of the previously deposited concrete or against form work
or moulds with rods or long tampers. Very great impotence is attached to the depositing and through
consolidating of the concrete to ensure that it is homogenous and free from interstices and that it is in
contact throughout with the forms or moulds; all to the entire satisfaction of the Engineer.
Care shall be taken not to disturb setting concrete by shocks, loading or other wise before it has sufficiently
hardened, Any concrete that it not finally placed within half an hour of mixing shall be discarded. Any
concrete which shows signs of initial setting before it is deposited in the forms or moulds shall not be used
in the work and shall be removed from the site or otherwise disposed of to the satisfaction of the Engineer.
Care shall be taken that at no time segregation of the concrete takes place.
Where concrete is laid on hard-core or any absorbing material, the surface shall be thoroughly wetted before
the concrete is deposited.
Large areas of unsuspended floor construction shall be of alternate bay construction Each panel cast shall be
approximately square in plan and not exceeding an area of 20m2 for the un reinforced and 50m2 for the
reinforced slab.
For suspended floor construction generally the area may be increased to 100m2 and the sizes of bays to be
cast should be agreed with the Engineer. The sizes of bays may be increased at the discretion of the
Engineer depending on the conditions relating to each individual case.
The specifications for reinforced slabs may be consider to apply for reinforced wall construction generally,
but the length of panels to be cast may not exceed 8m.
All waterproof concrete below ground ( U.G. tanks and Swimming pool structure as well in addition to any
other specified element hereafter) and in direct contact with water shall include an admixture similar to "
Conplast WP400from Fosroc, Ipanex or equally approved " as directed by the Engineer.
b. Materials
Form work shall be constructed of timber , metal or other approved material shall be so constructed as to
prevent any loss of grout or fine materials during concreting. The materials used shall be adequate to
provide the required surface finish to the concrete after removal and be sufficiently rigid to produce
concrete surfaces true and plane as required within a tolerance of 6mm in 4 m.
c. Design
TENDER No. 19102 /2019 106/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
Form work shall be so designed and constructed that concrete can be properly placed and thoroughly
compacted.
Form work shall be firmly supported and adequately strutted, braced or tied. it shall be capable of
adjustment to the lines and dimensions of the finished concrete, and it shall be sufficiently strong to resist,
without excessive distortion, the pressure of concrete during its placing and compaction, and other loads to
which it may be subjected. It shall not be liable to suffer distortion under the influence of the weather.
When concrete is to be vibrated, special care shall be taken to ensure that the form work will remain stable
and the joints tight.
The Contractor shall., if required, supply to the Engineer drawings and calculation for the form work he
propose to use.
The Contractor shall make allowance for any settlement or deflection of form work that is likely to arise
during construction so that the hardened concrete conforms accurately to the specified line and level. The
Contractor shall also make allowance in the form work for any camber and deflection due to creep of the
concrete.
e. Supports
Form work shall be constructed so that the form work to the sides of members can be removed without
disturbing the soffit form work or its supports.
Props and supports shall be designed to allow the form work to be adjusted accurately to line and level to be
erected and removed in an approved sequence without injury to the concrete.
Supports shall be carried to construction, which is sufficiently strong to afford the necessary support
without injury to any portion of the structure. This may mean in some cases that it
be carried down to the foundations or other suitable base.
Props and bracing shall be provided for the temporary support of composite construction where separately
specified.
All joints in form work shall be close fitting to prevent leakage of grout from the concrete.
All construction joints form work shall be tightly secured against previously cast or hardened concrete to
prevent the formation of stepping or ridges in ht concrete.
Form work shall be constructed to provide straight and true angles, arises or edges. Where chamfers are
shown on the drawings, the fillets shall be accurately cut to size to provide a smooth and continuous
chamfer.
Form work panels shall have true edges to permit accurate alignment at sides and provide a clean line at
construction joints in the concrete.
Form work panels shall be fixed with their joints either vertical or horizontal, unless otherwise specified.
g. Ties
The material and position of any ties passing through the concrete shall be to the Engineer's approval.
Except where it shall be possible to remove a tie so that no part of it remaining imbedded in the concrete
shall be nearer to the finished surface of the concrete than the specified thickness of cover to the
reinforcement. Any holes left after the removal of ties shall be filled with concrete or mortar of approved
composition.
TENDER No. 19102 /2019 107/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
h Sundries
Form work shall be provided to the top surface of concrete where the slope or the nature of the work
requires it.
Provision shall be made for forming holes and chases for services and for building in pipes, conduits and
other fixings shown on the drawings.
All rubbish, chipping, shavings, sawdust and dirt shall be removed from the interior of the form work before
concrete is placed. The form work to be in contact with the concrete shall be cleaned and watered and
treated with suitable mould oil of approved composition. Care shall be taken that oil or composition is kept
from contact with the reinforcement or with concrete at any construction joints.
Retarding agents shall not be used except with the permission of the Engineer. Form work shall be
thoroughly cleaned after each use.
All formwork shall be removed without shock or vibration that might damage the concrete. Before the
soffit and props are removed the surface of the concrete shall be exposed where necessary in order to ensure
that the subjected at the time of striking.
The form work to vertical surfaces such as walls, columns and sides of beams may by removed after 12-24
hour in normal weather condition, although care must be taken to avoid damage to the concrete, especially
to arises and features. In cold weather a longer period may be necessary before striking and protection
against frost should be afforded to exposed surfaces.
Where the early concrete strengths are not accurately known the following minimum times (in days) shall
elapse before removal of form work.
Any days during which the average temperature is bellow 2oC must be completely disregarded in
calculating the minimum time which must elapse before form work is removed. The contractor must at
such time obtain the approval of the Engineer before striking any form work.
The times given for the removal of props are based on the assumption that the total live plus dead weight to
be supported at the time of removal is not more than one half the total design load.
For horizontal members where the loading is a higher proportion of the total design load these times may
need to be increased.
The Contractor shall be responsible for any injury to the concrete work and for any damage caused by or
arising from the removal and striking of the forms and supports. Any advise, permission approval given by
the Engineer relative to the removal and striking of forms and supports shall not relieve the Contractor from
responsibility.
Where concrete surfaces are to be plastered the Contractor shall ensure that the solution used on form work
will not in any way reduce the adhesion of the plaster to the concrete.
Before concreting is resumed, the surface of the concrete on the first side of the joint shall be thoroughly
cleaned, and the surface removed so as to expose the aggregate. The work required to achieve this will
depend on the age of the concrete, and may vary from hacking, if the concrete is thoroughly hard to mist
spry on horizontal surfaces which can be dealt with whilst the concrete is still green.
The new concrete shall be carefully worked up against the hardened surface of the joint. Where possible,
except in the case of exposed face work where colour is important, the proportions of cement and fine
aggregate to coarse aggregate shall be increased in the batches to be placed against the joint.
The Contractor must at all times ensure that the supply of concrete is adequate for pours up to a properly
constructed day work joint.
If for any reason this is not achieved the Engineer shall be entitled of stop the work and reject the
incomplete pour and the Contractor shall at his own expense remove that concrete either wholly or partly as
directed by the Engineer and re-concrete to a reply prepared day work joint.
While casting the retaining wall, the contractor shall not consider what mentioned above as no any
construction joint will be accepted while casting the retaining wall for the basements floors.
15. Remedial Treatment of Surfaces
Any remedial treatment of surfaces shall be approved from the Engineer following inspection immediately
after removing the form work and shall be carried out without delay. ''
Any concrete, the surface of which has been treated before being inspected by the engineer, shall be liable
to rejection.
No claim of any sort will be admissible for carrying out any such repair work.
16. Finishes
All concrete surfaces which are not exposed (sawn form work ) are to be left as struck from the mould,
except that any surfaces which are found to be honeycombed shall be made good as soon as they have been
inspected by the Engineer.
The making good shall be done with a mixture of fine aggregate and cement in similar proportions to the
concrete and as dry as possible .
All exposed concrete surfaces with wrought form work are to have a rubbed finish, which shall mean the
application of rubs. The first rub shall be made after the removal of the forms , the surface shall be wetted
and rubbed with a No. of 20 carborundum stone to remove all mould marks. The second rub shall be made
when finishing the concrete work when the surface shall again be wetted, and rubbed with a No of 24
carborundum stone, excess paste being removed with a we brush.
The final surface shall be free from all irregularities and discoloration and shall be an even level surface.
If any honeycombing is found on exposed faces, the Engineer's decision as to whether the concrete shall be
cut and replaced or made good shall be final.
17. Curing
a. General
The concrete shall be protected during the first stage of hardening from the harmful effects of sunshine,
drying winds, cold , rain or running water.
TENDER No. 19102 /2019 109/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
Unless the following procedures are followed to the satisfaction of the Engineer the concrete will be
considered defective and unacceptable.
All material needed for curing should be ready for use before concreting begins.
Contractor has to ensure attendance for the curing before proceeding with concreting.
b. Top Surface
Immediately upon finishing, the expose surface is to be covered by polythene sheeting, the sheeting to be in
direct contact with concrete and covered with hessian to prevent air circulation over the concrete.
As soon as the concrete has sufficiently the sheeting is to be removed and the surface covered with wet
hessian and polythene sheeting to reduce evaporation.
Addition water to be introduced frequently under the polythene sheeting to keep the hessain thoroughly and
permanently wet.
Alternatively and whenever possible ponding of the exposed concrete surface may be allowed, In such a
case care should be taken to reduce evaporation.
In areas where starter bars protrude and is not possible to pond, as much of the area as possible is to be
covered with hessian and kept continuously wet.
c. Vertical Surfaces
For the sides of columns beams and walls, form work kept in position and sprayed with water for at least 24
hours provides the initial protection needed against evaporation.
Immediately on removal of form work the concrete should be closely warped with wet hessian and enclosed
with polythene sheeting. The hessian should be kept wet by frequent additions of water. The process should
continue for not less than seven days.
Curing by using an approved curing membrane will be allowed on surfaces which are difficult to cure by
any other method.
Traffic or loading shall not be allowed on the concrete until the concrete is sufficiently matured and in no
case shall traffic or loading be of such magnitude as to cause deflection or other movement in the form work
or damage to the concrete members.
1. Scope of work:
The entire required block works Includes:
o Cement blocks “Hollow and solid”.
o Thermal Insulated block.
o The accessories and the other related items.
2. Cement Block:
Cement blocks shall be strictly as manufactured to B.S 6073 part II and I and shall be from
approved manufacturer.
Materials
Cement
The cement used in the manufacture of concrete masonry blocks shall comply with the requirements
of either BS 12, minimum cement content in mix is 200kg/m3.
Water
Water shall be conform to the requirements specified under “Concrete Works” with the beloq
requirements: -
The water shall be clean and free from any organic matter, having PH value in the basic range (7-9). The
inorganic impurities shall not exceed the following limits:
Aggregate
The aggregates shall consist of naturally occurring crushed. or uncrushed materials which shall fully comply
with BS882. The salt contents shall not exceed the following limits:
Coarse aggregates used for the manufacture of concrete blocks shall be 10mm nominal size aggregates for
standard blocks.
Additives
Additives to mixes for blocks and mortar shall be from approved manufacturers and shall be used
strictly in accordance with the manufacturers instructions. Additives shall only be used with
Engineer’s written instruction.
Mortar
Mortar for concrete block work shall be cement/sand mortar (1:3) composed of one part ordinary
Portland Cement to three parts of sand by volume for works above damp proof course level and
mortars for below damp proof course level shall be I part sulphate resisting cement to 3 parts sand.
Mortar shall be mixed in approved mechanical mixers. The mixers shall be kept clean at all the
times. The ingredients for mortar shall be measured in proper clean gauge boxes. Mortar shall be
prepared with the addition of the minimum quantity of clean water for workability. The sand used
shall be dry when proportioning. In case it is not possible to obtain dry sand, allowable shall be
made for bulking when gauging by volume. The mean compressive strength at 28 days for each
mortar shall conform to BS 5628: Par 1:1992.
Cement Block shall be manufactured of cement and sand 1:5 mix (300 kg cement to 1m3 sand)
made in vibrated pressure machine, they shall be hard sound square with maximum dimensional
tolerance of +-5mm.
The required bonding agent between blocks and plaster concrete and plaster shall be added as per
the manufacturer instructions.
Crushing strength: shall be comply with the following requirement:
Compressive strength at 28 days:
Hollow block>7.5n/mm2 average for 10 blocks (for non baring walls).
Solid block>12.5n/mm2 average for 10 blocks (for non baring walls).
Hollow block>6 n/mm2 minimum for any block.
Solid block>10.0 n/mm2 minimum for any block.
Water absorption: 20% or less of dry weight.
Dimension tolerance: +-5mm maximum.
When block works is constructed under ground level SRC shall be used.
Standard block sizes for walls shall be 40cm. long, 20cm width and 20cm height. Alternative sizes
are to be modular as specified in as 6073 Part 2. Load bearing blocks sizes are to have thickness not
less than 20cm. Hollow blocks must have voids between 25 and 50 percent with a minimum
external shell thickness' of 35mm or 1.75 times the nominal maximum size of aggregate, whichever
is greater.
Linear Shrinkage
When tested for shrinkage as per as 1881: Part 5: 1970, the values obtained must comply with BS
6073: Part 1 and in no case shall it be more than 0.05%.
Sampling
Ten blocks shall be drawn at random from every designated 1000 blocks section or part thereof in a
consignment. All samples shall be clearly marked at the time of sampling- in such, a way that the
designated section or part thereof and the consignment represented by the sample, are clearly
defined.
The sample specimen shall be tested in compression as specified in BS 6073: Part 1, Appendix “B”.
Strength
Concrete blocks when tested according to BS 6073: Part 2, shall have an average compressive
strength of 12.5 N/mm2 with a minimum individual strength of not less than 10 N/mm2 for load
bearing blocks and an average strength more than 7.5N/mm2 with a minimum individual strength
not less than 6 N/mm2 for non-loading blocks
This certificate is to be provided by the manufacturer at the time of sale as per item NO.12 .of BS
6073 where the independent-laboratory mentioned therein shall be the Dubai Municipality
Laboratory
Walls shall be carried up regularly without leaving any part more than one metre
lower than another unless the permission of the Engineer is first obtained. Work
which is left at different levels shall be hacked black. In the case of cavity walls,
both thicknesses shall not be carried up more than about 400mm.
The courses of blockwork shall be properly leveled. The perpendicular joints shall
be properly lined and quoins, jambs and other angles plumbed as the work proceeds.
All walls shall be thoroughly bonded in accordance with the best constructional
practice and as directed by the Engineer. Broken blocks shall not be used except
where required for bond.
Block walls are to be built in half bond. Where junctions are not wholly bonded, the
Contractor shall provide and build in 2 No. 6mm mild steel reinforcing bars to ever
other course at angles .and intersecting walls and partitions
All concrete blocks shall be soaked with water before being used and the tops of
walls left off shall be wetted before work is recommenced. The faces of walls shall
be kept clean and free from mortar droppings and splashes.
All blocks shall be properly spread with mortar before being used and the tops of
walls left off shall be wetted before work is recommenced. The faces of walls shall
be kept clean and free from mortar drained splashes.
Walls to be left un plastered shall have a fair face consisting of selected blocks
pointed with a neat weathered or flush joint as the work proceeds using the same
mortar mix as for the jointing and as per Local Order 44/90.
Blockwork described as 'fairface one side' shall be finished with all blocks laid in
one planed, smooth and level and presenting a uniform appearance. All vertical and
horizontal joints shall be bagged to eliminate joint lines and the outline of the
blocks.
Walls to be plastered shall have the horizontal joints raked out to a depth of 15mm
to form a key.
Fixing blocks, ends of brackets, bars, bolts, chases etc... are to be built into or
formed at the time of laying the blocks. No part of the blockwork shall be cut away
for any such item or for any other reason. without the Engineer's permission.
Blockwork shall be bonded to concrete columns and the like with 200mm x 6mm
galvanized metal ties cast in concrete and subsequently bent down ragged and built
TENDER No. 19102 /2019 113/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
into every alternative course of blockwork. . Shot-firing ties to .concrete will not be
permitted.
The ties shall be of the butterfly twist type of No. 10 SWG mild steel wire zinc
coated and similar to those described. in BS 1243. The length of the ties shall be
approximately 80mm less than the total thickness of the wall. . The cavity shall be
kept clean by lifting screeds or other means approved by the Engineer and shall be
left clean at completion.
Block wall should be kept for at least 7 days after being erected
Blocks should be damped before the mortar bed is applied on their surface
The following tests to be done on the consultant instruction for 12 blocks:
Tests:
1. Crushing strength:
2. Chemical analysis “chloride, and sulphate”.
3. Water absorption.
4. Dimension tolerance.
Workmanship:
1. Block workmanship shall be set out and built to the respective dimensions,
thickness, and height mentioned on the drawings.
2. First block line, doors jams, and windows opening to be solid block.
3. Windows sills should be made of concrete.
4. Mortar used in the block workmanship shall be of 10 mm average thickness
for the cement block, light weight block glow to be used as per the
manufacturer requirement “from Conmix or equally approved”.
5. Where blocks about against concrete each third course shall be tied together
by means of approved galvanized steel ties.
6. Horizontal joints shall be leveled and the vertical joints shall be lined.
7. Walls shall be carried out regularly without leaving any part more than 1 m
lower than another.
8. DPC comply with BS 6398type D to be used under the first line in the ground
floor and around the wet areas in the typical floors.
9. Block work partitions over 3 meter high shall be stabilized as following:
a. Providing continuous 20*20/10 cm reinforced concrete lintel at the door lintel
level.
10. Prefabricated lintels shall comply with the requirements of B>S 5977, Part 2
All lintels shall be bedded cement and and mortar and the Contractor shall allow
for a minimum bearing at each end of 150 mm.
11. Block work which exceeding 14m2 in area shall be stabilized as following:
a. Providing continuous 20*20/10 cm reinforced concrete lintel and 20*20cm
reinforced concrete columns.
12. All internal block work shall be extended up to the under side of the concrete
slab.
Sample Panel
The approved sample panel shall be deemed to represent the minimum acceptable
standard in the work.
Claustra Walls
Blocks for claustra walls shall be manufactured and built generally in accordance
with the preceding clauses for blockwork, except where otherwise noted below.
All blocks are to be finished with a fine finish to an approved ornamental pattern and shall be
100mm thick unless otherwise noted with slots in ends of blocks to receive reinforcement.
Claustra walls will normally be built with vertical straight joints reinforced with 12mm mild steel
reinforcing bars vertically at each straight joint pinned to structure at each end and surround solid
with mortar.
Blocks shall be bedded in a mixture of white cement and sand (1 :4) and struck pointed to approval.
Expansion Joints
Expansion joints shall be formed with straight vertical joints filled with 19mm impregnated
fibreboard and reinforced with two steel rods each side as described in Clause 11.01 .
Tops of non-load bearing walls are to be stopped 12mm short of structural concrete soffits
and pinned up with 12mm of soft board against the underside of the slab.
6. Plaster Works
Scope of work:
Including all the plastering works for the internal and external walls and ceiling.
Technical submittal:
Internal plastering is to comply with BS 5492.
The plaster for use internally is to be composed of one part cement and four parts of sand, and is to
be applied in two coats to a the finished stated thickness.
The render for use externally is to be composed of one part cement and four parts of sand, and is to
be applied to the finished stated thickness stated thickness externally.
Plaster or render is to be mixed in clean busckets and gauge boxes. All tools are to be kept clean
and not to be contaminated with plaster or render.
Preparation works as noted below to be completed well in advance of commencement of plastering
work.
a) All the service lines to be concealed in plastered area are to be completed and tested.
Cutting on plastered wall not be accepted.
b) Cutting made on block work for service lines in wider size shall be repaired by concrete.
c) Approved expanded metal mesh to be provided at all joints between block work / concrete
and on the repaired surface of cutting made for services viz. electrical, plumbing pipes etc..
d) Angle beads to be provided on all internal corners of walls & also in R.C. column
projection sample to be submitted for approval.
e) G.I. angle beads are to be provided on all corners for the door and window opening
wherever plastering will be done.
f) Key coat using cement slurry to be applied and cured properly on the surface to be plastered
and same shall be from approved supplier.
g) Necessary approved bonding agent to be added to the key coat mix applied on smooth
concrete surface.
h) Hacking to be done on concrete surface to roughen the area before the application of key
coat.
i) Plaster level pads to be provided to maintain the line, level and plumb.
j) Irregularities on the surface to be plastered shall be filled with mortar 24 hour before
plastering work
k) Joints in block etc. to be well raked out to form a good key.
l) All surfaces to be plastered shall be clean and free from dust, loose mortar and traces of
salt.
m) All The plaster accessories to be from approved manufacturer such as Expamet or emirates
specialties or equally approved.
The ingredients for the plaster or render are to be mixed three times dry and three times while water
is added. Alternatively mixing may be done by approved mechanical mixers, which are to be
cleaned before use.
The contractor is to ensure that before plastering or rendering commences the junctions between
differing base materials are reinforced with a strip of galvanized expanding metal lath secured at
both edges. All angle beads and the like shall also have been fixed.
All undercoats are to be scratched to form an adequate dry for the next coat. , The setting coat is
not to be applied until the floating coat has been left in a moist condition for at lest three days.
All Plastering shall be executed in a neat workmanlike manner and made good to wood frames,
skirting, pipes, fittings and the like.
Plasterwork is to be finished with as smooth, trawled face, free from blemished and fit to receive
decoration. Render is to be finished with a wood float. Any blown, cracked or otherwise damaged
plaster or render shall be condemned by the Engineer and is to be hacked off and made good with
quick setting plaster at the Contractor's expense.
Full use is to be made of grounds, rules and angle trowels to ensure that all wall faces finish plane
and true to line in all direction and that all angles are straight, true and plumb. Prices for plastering
and rendering are to ensure that work to walls and ceilings are effectively 'cut' at the joint so as to
minimize damage due to movement.
1. Scope of work:
Including all the external paving and car park as shown in the setting out plan and described herein.
i) Cement
The cement used in the manufacture of precast concrete paving blocks
Shall comply with the requirements of either BS 12, 4027 or BS 146
The cement content of compacted shall not be less then 400 kg/m3.
ii) Aggregates
The aggregates shall consist of naturally occurring crushed or uncrossed
Materials which apart from grading requirements comply with BS 882
The salt contents shall not exceed the following limits.
Acid soluble chlorides 0.06 % by wt. of Fine \aggregate
0.02 % by Wt of coarse Aggregate
Acid soluble sulphates 0.03 % by wt. by of coarse and fine aggregates
iii) Water
The water shall be clean and free and free from any deleterious matter having ph value n the basic
range(7-9) and shall conform to Bs 3148 (1990) and as specified for the concrete works.
iv) Pigments
Any pigment used shall comply with BS 10014.
3. Compressive Strength
The average compressive strength of the block on delivery when sampled and tested in the manner
described below shall not be less than 49 N/mm2
4. Sampling Block
Two blocks shall be drawn from each group of 1000 blocks for sampling , 10 blocks every designed
5000 block section or part there of in a consignment.
All samples shall be clearly marked at the time of sampling in such a way that the disignated section
or part thereof and the consignment represented by the sample, are clearly defined.
In case of chamfer or radius the width of chamfer or radius shall be measured and marked on the
cardboard shape. This shape shall then be cut out accurately and weighed for above calculation of
the wearing surface area.
Plywood nominally 4mm thick shall be sued as packing between the upper and lower faces of the
specimen and the machine platens, and these boards shall be larger than the specimen by a margin
of at least 5mm at all points. Fresh packing shall be used for each specimen tested.
The load shall be applied without shock and increased continuously at a rate of approximately 15
N/mm2 per minute until no greater load can be sustained. The maximum load applied to the
specimen shall be recorded. The strength shall be expressed to the nearest.
6. Certificate of Compliance
This certificate is to be provided by the manufacturer at the same time of sale as per item No. 12 of
BS 6717
4. Any units deviating more than 3mm in 3m from line or level shall be taken up and re-
laid
5. Where filling placed adjacent to the kerb is likely to have a harmful effect on the kerbs,
due to IRS aggressive chemical nature then the kerbs shall be protected from the fill
material by a method agreed with the Engineer or as shown on the Drawings.
6. Expansion joints will provided at 6m spacing along the kerb run. The Expansion joints
shall be formed of suitable flexible material to the approval of the Engineer.
TENDER No. 19102 /2019 119/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
7. For radius less than 12 m, radius curb should be used.
8. Heel curb to be provided in the shape and color as per the drawings
5. Curbstone marking:
- Curbstone marking: to be Durethane from Jotun or equal, and complying with the
following specification:
Technical Information:
Color :White
Finishing : Glossy.
Solid “by Volume” : 48 ± 2.
Flush Point : 31 C ± 2.
Gloss retention, Flexibility, Water & Chemical resistance, Abrasion resistance, UV
resistance : Very Good
For application, surface treatment and others to be as per the manufacturer
recommendation.
The External finishes shall be as descried herein and indicated in the elevation drawings but
not limited to the following:
-Granite cladding: 20 mm thick best quality Italian granite cut to size with basic cost of 400 DHS/Sq.m.
supply & installation rate, with edges and profiles as per the drawings & approved shop drawings.
Wall cladding to be by mechanical fix with stainless steel accessories.
Granite shall be obtained from a source that has the capacity to provide quantity, quality and sizes required
for the Works.
Samples of all granite to be used in the Work are to be submitted to the Engineer for approval prior to
commencement of it on site. Actual materials used in the works shall match the approved samples.
Granite shall be of the best quality, smooth, uniform in color and texture, free from voids, holes, vents,
cracks, earth veins, objectionable irregularities and laminations or structural weakness.
The Contractor is to ensure that all granite delivered to site is stored on a raised platform in a water free area
and is protected with suitable sheeting.
Any chipped or stained pieces are to be removed from site and replaced at the Contractor's expense.
The contractor to use acrylic modified protective coat to the back side of the marble and the granite as a
protective coat against moisture, similar to Brushbond from Fosroc or equally approved, in single coat.
For steps : use 20 mm thick best quality Granite from the same Granite type for the risers and use 30 mm
thick best quality Granite from the same Granite type for the Treads, skirting shall be in single unit and
having non- slip carborandum inserts and matching from the same Granite type.
Granite delivered at site should be presented to Engineer for selection before fixing.
For ramp use 30 mm thick best quality Granite from the same Granite type cut to size as per Consultant
approval with combination of polished and flamed granite finish (50/50)
Granite shall be obtained from a source that has the capacity to provide quantity, quality and sizes required
for the Works.
Samples of all granite to be used in the Work are to be submitted to the Engineer for approval prior to
commencement of it on site. Actual materials used in the works shall match the approved samples.
Granite shall be of the best quality, smooth, uniform in color and texture, free from voids, holes, vents,
cracks, earth veins, objectionable irregularities and laminations or structural weakness.
The Contractor is to ensure that all granite delivered to site is stored on a raised platform in a water free area
and is protected with suitable sheeting.
Any chipped or stained pieces are to be removed from site and replaced at the Contractor's expense.
The contractor to use acrylic modified protective coat to the back side of the marble and the granite as a
protective coat against moisture, similar to Brushbond from Fosroc or equally approved, in single coat.
-Grove in Plaster
As per the elevation drawings, shall be made by fixing Aluminum Channels, powder coated
from inside. These Aluminum Channels shall be fixed by stainless screws, and are to be
checked for plumb and alignment by the Engineer, prior to the plasterwork.
F. Floor Finish
(General specs for particular refer to the schedule of finishes mentioned in the drawings)
F-1 Granite: 20 mm thick best quality Italian granite cut to size with basic cost of 250 DHS/Sq.m. supply &
installation rate, with edges and profiles as per the drawings & approved shop drawings.
For steps : use 20 mm thick best quality Granite from the same Granite type for the risers and use 30 mm
thick best quality Granite from the same Granite type for the Treads, skirting shall be in single unit and
having non- slip carborandum inserts and matching from the same Granite type.
Granite delivered at site should be presented to Engineer for selection before fixing.
For ramp use 30 mm thick best quality Granite from the same Granite type cut to size as per Consultant
approval with combination of polished and flamed granite finish (50/50)
Granite shall be obtained from a source that has the capacity to provide quantity, quality and sizes required
for the Works.
Samples of all granite to be used in the Work are to be submitted to the Engineer for approval prior to
commencement of it on site. Actual materials used in the works shall match the approved samples.
Granite shall be of the best quality, smooth, uniform in color and texture, free from voids, holes, vents,
cracks, earth veins, objectionable irregularities and laminations or structural weakness.
The Contractor is to ensure that all granite delivered to site is stored on a raised platform in a water free area
and is protected with suitable sheeting.
Any chipped or stained pieces are to be removed from site and replaced at the Contractor's expense.
The contractor to use acrylic modified protective coat to the back side of the marble and the granite as a
protective coat against moisture, similar to Brushbond from Fosroc or equally approved, in single coat.
F-2 Granitee tiles, in two colors design, up to consultant approval with (supply by client ) for staircase as
indicated in the schedule of finishing with design as per the drawings and complying with the following
specs:
Test description USA (ASTM) / EUROPE International standard
Length and width (CEN)
C499 ± 0.5%
Thickness C499 ±5.0%
Rectangularity/ squareness C502 ±0.6%
Straightness of side EN 98 ±0.5%
Surface flatness C485 ±0.5%
Water absorption C373 <=0.5%
Module of rupture C674 >=27n/mm2
Impact resistance C368 No crack
Resistance to deep abrasion C501 <=205 mm3
Resistance to surface abrasion EN 154 Report abrasion class
Leaner thermal expansion C372 <=9*10-6/c
Resistance to thermal shock C484 No damage
Color Resistance to light DIN 51094 No change
Crazing Resistance C424 No Crazing
Frost Resistance C1026 No damage
Chemical Resistance C650 No damage
F-3 20 mm thick best quality marble approved as per Consultant approval laid in patterns & design as per
drawings and consultant's approval and including cement and sand bedding to give overall thickens to the
Engineers approval (not more 70 mm). Allow for three-color variations of marble “cut to size supply and
fix by client for supply & installation rate”.
The Contractor shall prepare and submit shop drawings for all marble laid in patterns or as directed by the
Engineer and he shall submit samples of material and workmanship on site for approval of the Engineer.
The contractor to use acrylic modified protective coat to the back side of the marble and the granite as a
protective coat against moisture, similar to Brushbond from Fosroc or equally approved, in single coat.
The hardened material after application shall achieve the following physical properties:
Density 1.53
Absorption (ASTM C413-80) 0.06%
Bond strength (DIN ISO 4624) 1.5N/mm² (concrete failure)
Abrasion resistance (DIN Taber 53754) 98mg
Modulus of elasticity (DIN 1048) 9000N/mm²
The product should be manufactured locally by a company certified to conform to the requirements of the
quality, environmental and occupational health & safety standards ISO 9001, ISO 14001 and OHSAS 18001
and applied a manufacturer endorsed and trained specialist applicator.
Mastertop 1210 CP –the contractor should provide at least 5 Years Warranty from the manufacturer.
Remark: -
All flooring marking should be phosphoric color.
F-9 Interlock & curbstone: Refer External works specs.
S-1 100x20mm granite skirting with profiled top and bottom edge set proud of the wall finish by 5mm, and
should be matching with the flooring type “refer floor finishes specs and schedule of finishes”
S-2 100x10mm thick Graniti tile skirting, up to consultant approval, and should be matching with the
flooring tile.
S-3 100x20mm marble skirting with profiled top and bottom edge set proud of the wall finish by 5mm, and
should be matching with the flooring type “refer floor finishes specs and schedule of finishes”
S-4 100x20mm thick polished Mosaic with profiled top edge, set inside the wall finish by 5mm.
To be 45 degree skirting for the staircase.
S-5 100x8mm thick ceramic skirting with round top edge and curved corners for all external and internal
angles. The skirting shall match in color and range to the floor tiles. The skirting shall be set 5mm inside the
wall, “refer floor finishes specs and schedule of finishes”
W-1 Granite cladding: 20 mm thick best quality Italian granite cut to size with basic cost of 350
DHS/Sq.m. supply & installation rate, with edges and profiles as per the drawings & approved shop
drawings.
Wall cladding to be by mechanical fix with stainless steel accessories.
Granite shall be obtained from a source that has the capacity to provide quantity, quality and sizes required
for the Works.
Samples of all granite to be used in the Work are to be submitted to the Engineer for approval prior to
commencement of it on site. Actual materials used in the works shall match the approved samples.
Granite shall be of the best quality, smooth, uniform in color and texture, free from voids, holes, vents,
cracks, earth veins, objectionable irregularities and laminations or structural weakness.
The Contractor is to ensure that all granite delivered to site is stored on a raised platform in a water free area
and is protected with suitable sheeting.
Any chipped or stained pieces are to be removed from site and replaced at the Contractor's expense.
The contractor to use acrylic modified protective coat to the back side of the marble and the granite as a
protective coat against moisture, similar to Brushbond from Fosroc or equally approved, in single coat.
as indicated in the schedule of finishes with the following specs:
Test description USA (ASTM) / EUROPE (CEN) International standard
Length and width C499 ± 0.5%
Thickness C499 ±5.0%
Rectangularity/ squareness C502 ±0.6%
Straightness of side EN 98 ±0.5%
Surface flatness C485 ±0.5%
Water absorption C373 <=0.5%
Module of rupture C674 >=27n/mm2
Impact resistance C368 No crack
Resistance to deep abrasion C501 <=205 mm3
Resistance to surface abrasion EN 154 Report abrasion class
Leaner thermal expansion C372 <=9*10-6/c
Resistance to thermal shock C484 No damage
Color Resistance to light DIN 51094 No change
Crazing Resistance C424 No Crazing
Frost Resistance C1026 No damage
Chemical Resistance C650 No damage
Light Reflectivity 88%
Anti-Carbonation Air Equivalent (R) >300m2
(Taywood Test Method)
Water Vapour Perms Dry (ASTM D1653) 2.1
The product should be supplied by a Dubai based company certified to conform to the requirements of the
quality, environmental and occupational health & safety standards ISO 9002, ISO 14001 and OHSAS 18001
and shall be applied by a manufacturer endorsed and trained specialist applicator who can demonstrate
experience in application of the specified system.
Sonoshield Parkcoat
W-5 Colored ceramic tiles size, color, pattern up to consultant approval with decorative boarder from
approved Manufacturer on plaster to full height of the wall. Allow for two-color variation (dark and light)
and or pattern and fixing of tiles in pattern of varying sizes to the approval of Engineer. Supply and fix by
client Tile grout and adhesive shall be waterproof type and grout shall be matching in color to the tiles.
Rounded edge tiles shall be used at all junctions including the junction at floor.
Contractor to include in his bid one or two décor pieces for each wall.
Ceramic wall tiles should be comply with the following specification:
Test description International standard Value
TENDER No. 19102 /2019 125/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
Length and width ISO – 10545-2 ±0.3%
Thickness ISO – 10545-2 ±5.0%
Rectangularity/ squareness ISO – 10545-2 ±0.4%
Straightness of side ISO – 10545-2 ±0.3%
Surface flatness ISO – 10545-2 ±0.3%
Water absorption ISO – 10545-3 7-12 %
Module of rupture ISO – 10545-4 >=20 n/mm2
Scratch hardness EN 101 2-4
Staining resistance ISO – 10545-14 Stains removed
Resistance to surface abrasion ISO – 10545-7 Class 1-3
Slip resistance ISO – 10545-17 -
Crazing Resistance ISO – 10545-14 No Crazing
Test description International standard Value
Chemical Resistance ISO – 10545-13 No damage
W-6 15mm thick sand cement plaster with sealer smoothed finish with three coats of washable emulsion
paint as specified in contract drawings with the following layers:
from Jotun Paints or equal.
W-7 magnum
Film thickness and spreading rate:
Physical prosperities
Surface preparation:
The substrate must be sound, clean, dry, free from dust, oil, grease and laitance etc. All traces of release
agents must be removed. On chalky and dusty surfaces, all loose material must be removed by stiff
bristle brushing.
The temperature of the substrate should be min. 10oC and min. 3oC above the dew point of the air,
temperature and relative humidity measured in the vicinity of the substrate.
Application methods:
C-1 15mm thick sand cement plaster with sealer smoothed finish with three coats of washable emulsion
paint as specified in contract drawings from, Jotun or equal
C-2 15mm thick sand cement plaster with Epoxy paint finish. And will be from Jotun paint or equal.
C-3 Magnum
Film thickness and spreading rate:
Physical prosperities
Surface preparation:
The substrate must be sound, clean, dry, free from dust, oil, grease and laitance etc. All traces of release
agents must be removed. On chalky and dusty surfaces, all loose material must be removed by stiff
bristle brushing.
The temperature of the substrate should be min. 10oC and min. 3oC above the dew point of the air,
temperature and relative humidity measured in the vicinity of the substrate.
Application methods:
C-3 Spray Plaster ceiling similar to Hytec, Terraco or equally approved with the following layers:
One Base Coat.
One Top coat or more (due to the surface situation).
Textured finish coat.
Contractor to submit reflected false ceiling shop-drawings showing all the access panel, openings, A/C
diffusers, Fire fighting sprinklers and smoke detectors & light fittings for consultant's approval
FC-1 12mm gypsum board ceiling/bulkhead on concealed metal proprietary suspension system with taped
and skimmed joints, fire rated with shadow line edge trim with three coats of acrylic emulsion textured
paint. Allow for all openings, proprietary lockable-framed access panels as required.
Design of ceiling to be as per the drawings.
Shallow domes to be done by Cast gypsum “refer to drawings”
FC-2 600x600x12mm thick PVC vinyl coated gypsum tiles with Aluminum foil backing rested on GI
metal suspension system with shadow line edge trim.
FC-3 Aluminum strips 2000x300 mm Aluminum Strips with thickness of 0.7 mm and to receive a super
durable powder coating (refer to Aluminum coating mentioned in the Aluminum section) and the color
choice will be according to the consultant choice.
FC-4 600x600mm Calcium Silicate suspended ceiling for swimming pool area and as per schedule of
finishes.
Note: the external sides of doors shall be 100% glossy and the internal sides shall be 70%
glossy.
WW-5 Solid Doors frame and fire rated doors frame to have 4*20 mm thick
intumescent strips.
All the doors to have rubber seal.
3. The Contractor is to take a site reading to determine the moisture content of all joinery by Moisture
Meter. Documentation is to accompany each batch shipped to verify the moisture content. Without
such documentation the whole batch will be rejected.
4. Soft wood timbers to be European redwood, Swedish or Russian, and to be comply with the BS
881/589 and 1186.
6. The preservative of timber shall comply with the BS 5268, the contractor shall provide certificate of
assurance that the treatment has been carried out as specified, and in no case wooden works to be
carried without the same to be coated with preservative and anti termite coats suitable for the
position in which the member is to be incorporated.
7. The timber shall be complying with the BS 476/5669 in respect of the fire resistance.
8. Plywood shall be comply with the BS 1455/6566, plywood bonding to be WBP comply with the
requirement of BS 1203, the surface grading to be grad 1 where to receive clear finish and grad 2
elsewhere, plywood shall be free from end joints, overlaps, dead knots, patches and plugs.
9. Veneer : shall be roll cut veneer with 0.06 mm min. thickness having class A facing in accordance
to the French standard FN B 53.504, only whole sheet shall be used.
The veneers shall be factory applied under pressure using urea-formol adhesive by manufacturer of
the various components, all veneers shall guaranteed by the manufacturer
10. Plastic lamination: : shall be comply with the BS 3794 class l, only whole sheet shall be used, and
should be of minimum thickness of 0.9 mm thick.
12. Nails and screws: Nails are to comply with BS 1201 and screws with BS 1210. They are to be of the
appropriate approved type for their intended use.
13. Adhesive are to be synthetic resin type complying with BS 1204 Part 1. and they are to be type
WBP.
14. Workmanship:
Joinery shall comply with BS 1186 Part 2 and CP 112 for structural carpentry, and where possible
shall be fabricated in a manufacturer's shop prior to delivery. It shall be accurately, properly and
soundly constructed with all moulds and arrises clean and sharp. Joinery shall be protected from
damage during storage at Site and throughout the construction period subsequent fixing.
The terms "frame" or "framed" or " framing" mean work put together by proper carpentry or
joinery, such as morticing and tenoning, dovetailing, dowelling, etc., and the joints are to be as
shown specified or directed. Butted and screwed or nailed joints or halved joints and the like will
not be deemed framed and will not be accepted for framed work.
Fixing of all joinery work, including fillets, architrave's, frames. glazing beads and the like shall be
by means of screws. Nailed work will not be permitted.
Screw heads in work to be painted shall be countersunk and stopped. Screw heads in wood to be
oiled, varnished or polished shall be pelted, with grain of the pellet in the same direction as the
grain of the member.
Unless otherwise described, work described as "plugged" shall be fixed by drilling holes in the wall
or floor, plugging with "Plastic Plugs" well rammed in and fixing the member with screws. Centers
of the fixings must not exceed those necessary to provide adequate support, and in any must not
exceed 600 mm,
15. Wood moisture content: Kiln–dried (KD) lumber with an average moisture content range of 6% to
11% shall be provided for their interior work. Temperature and relative humidity shall be
maintained so that moisture content values for woodwork at time of installation does not exceed
10%.
1 QUALITY ASSURANCE
1. Where possible, all hardware shall be the product of one manufacturer who maintains a
fully equipped plant with all necessary tools, fixtures, bonderizing and furnishing
equipment, engineering and installation organization to perform the requirements of this
specification in accordance with the highest standards and details of quality and
manufacturing skill.
2. All hardware shall be first class quality at least equal to the appropriate British Standards or
European Standards.
2 DESCRIPTION OF SYSTEM
1. Layout keying system for building in consultation with the Engineer. System includes
keying alike, keying in groups, submaster keying and grand master keying locks as
directed. Prepare and submit keying chart and related explanatory data for approval. Do
not commence lock work until written confirmation of keying arrangements is received.
2. Keying:
1. Keys alike: All lock within the building shall have the same key combination.
4. Forward grand-master and Submaster keys with a covering letter to the Engineer.
5. Unless otherwise specified or shown on the drawing, all locks shall have two keys with the
lock number stamped upon them, and the corresponding number stamped on the face of the
locks shall be master keyed as directed hereinafter and as approved by the Engineer.
6. Furnish three master keys. All keys shall have metal chain and metal tag on which shall be
stamped the room number. After all locks have been installed and upon completion of the
work, the keys shall in presence of the Engineer be shown to operate their respective locks
and shall be tagged and delivered to the Engineer.
3 SUBMITTALS
1. SAMPLES:
1. Submit one sample of each hardware item specified and manufacturer's catalogue
to the Engineer for approval prior to order. Fully label each sample as to
manufacture, type, size and location for use proposed.
2. Do not order hardware from manufacturers until samples have been approved.
Hardware and finishes supplied shall be identical with approved samples.
4. MISCELLANEOUS: Supply two complete sets of wrenches & fastening tools for lockset
and closers. Normally supplied from manufacturer. Submit template information for
distribution to related trades.
1. Pack hardware in suitable wrappings and containers to protect from injury during shipping
and storage. Enclose accessories, fastening devices and other loose items with each item.
Mark packages for each identification as indicated on approved delivery schedule.
Containers shall be clearly labeled as to content and door on which the hardware is to be
installed.
All hardware shall be carefully wrapped and protected until the completion of the work and
any items or part which are damaged or defaced shall be replaced by and at the Contractor's
expense before handling over the building to the Client.
5 WARRANTY
1. Warrant exit devices, locksets, latchsets and door closers to remain free from defects in
materials and workmanship for a period of one year from the date of issue of The Final
Completion Certificate. The warranty shall state expressly that all hardware shall be
replaced on the doors and frames at no cost to the Owner in the event of breakage or
manufacturing defect occurring, willful damage excluded.
6 MATERIALS
1. GENERAL: The type, quality, pattern and size of hardware items shall be as indicated on
schedules.
2. STRIKES: Standard template box strikes, extended lips to protect door frames and trim
from marking with bolts. Set flush in door frames. Supply blank standardized template
strikes for door frames as scheduled for such doors without locks.
3. DOOR CLOSERS: Door closers shall be with full cover, in stainless steel finish. Closers
shall have adjustable closing strength EN2-4, made of die cast aluminum bodies with
hardened rack and pinions. The door closers have to be per BS EN 1154 : 1997 for the
conformance to power rating and BS476: Part 22.187 for the fire resistance. Hold open
facility is not be used in fire rated doors. Closers should be not be used on the public side
of the doors. Install closers on the push side of doors opening from the public areas /
corridors (parallel arm type) and pull side on doors opening from the public areas /
corridors into rooms (regular arm type). The door closers should be installed on the push
side of doors opening to exterior.
Floor closers, where used, to be Dorma BTS80, depending on the weight and wind factors
of the location of the doors.
4. LEVER HANDLE SETS: Lever handle sets for wood and steel doors shall be with roses
and escutcheons, in stainless steel, 20mm diameter return to door lever handles with 8mm
spindle; secured by unique non reversible spring clips locating into serrations on spindle
and preventing lateral movement. Collared neck of levers push into sprung retaining clips,
TENDER No. 19102 /2019 135/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
providing a 3 point secure fixing, with all operating pressure transferred to the door leaf.
5. MORTISE LOCKS: Mortise locks for wood and steel doors to be Dorma Type 752, size
165 x 85 x 13 mm, 55mm backset, with stainless steel case and 8mm bronze bushed self
adjusting heavy sprung follower, 20 mm double throw nickel plated steel dead bolt and
11mm nickel plated reversible steel latch bolt, 24mm steel square forend in stainless steel
finish, suitable for europorfile cylinders at 72mm centers. Latch to have sound dampener.
Locks be supplied boxed with fixing screws and type 20 strike. Lock to have 3 separate
springs for follower, latch and dead bolt function.
For fire rated doors use Dorma Type 180, size 165 x 88 x 14mm, 55mm backset, 9mm
follower made as per DIN 18250 for fire and smoke check doors.
Bathroom locks shall be 790 Mortise lock, as per above description, but suitable for use
with thumbturn / indicator sets with 8mm spindle at 78mm centres. To be supplied with
fixing screws and type 20 strike
Narrow stile doors to have 852 locks, 30mm backset in stainless steeel finish.
Doors of the corridors to have 515 lockcase, latch lockcase sealed, zinc plated, latch nickel
plated 8mm follower without key operation. Double action doors to have 484 Roller lock,
55mm backset.
6. CYLINDERS: Cylinders to be euro profile double cylinder / cylinder with thumb turn,
matt nickel plated brass, under grand master key, complete with 3 keys.
The master key system should have change keys (3 keys per cylinder), master keys based
on the key schedule approved by the Consultant.
7. PULL HANDLE: Pull handle to be Dorma, in stainless steel, pull handle of size 350mm
between centers and 20mm diameter, with bolt through zinc plated, with M8 countersunk
steel bolts.
8. FLOOR STOP: Full dome satin stainless steel floor stop, with hard rubber stop, with
screws and dowel.
9. FASTENERS:
HINGES: All hinges shall be, ball bearing, five knuckle, stainless steel, brushed finish,
with size 100mm x 76mm x 3mm. Each door leaf shall have a minimum of 3 hinges -
doors 90cm wide and over to have a minimum of 4 hinges. Where aluminum doors are
used, and overhead closers are used, use aluminum hinges Type LM, B22, 22mm offset
two-part load bearing hinge.
3.1 PREPARATION
1. Before furnishing any hardware, carefully check all architectural drawings of work
requiring hardware; verify door swings, door and frame material and operating conditions.
Ensure hardware will fit work.
2. Check shop drawings and frame and doors lists affecting hardware type and installation.
Certify to correctness or advise Engineer in writing of required revisions.
3.2 PERFORMANCE
1. ADJUST AND CLEAN: Provide services of competent mechanic without additional cost.
Mechanic shall inspect installation of all hardware furnished under this section and
supervise all adjustments (by trades responsible for fixing) necessary to leave hardware in
perfect working order.
1. All hardware for fire rated openings shall comply with NFPA 80 or equivalent British
Standards and meet the standards by the local authority having jurisdiction and regulatory
agencies.
2. Hardware Installation
Distance from finish floor to center line of hardware unless instructed otherwise by the
Engineer.
Locksets / Latchsets -Centre Line of Strike - 1040mm
Deadlocks / Mortise Night Latch - 1200mm
Panic Device - Centre Line of Strike - 940mm
Push Plates & Door Pulls 1050mm Guard Bars - 1060mm
Blank Strikes & Blank Fronts - 1524mm
3. Provide hardware schedule as specified, for Engineer' s approval prior to placing finial
order.
Medium density fiber board (MDF): MDF shall be to BS 1142: 1989 of 750 Kg/m3 average density
with ash veneer 0.6-0.8 mm nominal thickness. Typical characteristic shall be as indicated
elsewhere in this section.
Carcasses: Carcasses shall be of 18 mm MDF white melamine faced factory applied and melamine
roll-on lipping on exposed edges.
All cabinet backs shall be of 3.2 mm thick white hardboard using a thermo set paint process.
Suitable supports at intervals shall be provided as required.
Drawers: Drawer shall be with all metal drawer runner system. Drawer box shall be solid, tested for
heavy loaded opening and closing.
Doors: Doors shall be of 18 mm thick MDF with white melamine finish from the inside and PVC
film faced on the outside with post formed vertical edges.
Hinges: Hinges shall provide 180 degree opening. Hinges shall be all heavy duty stainless steel,
having a self-closing action and permit adjustment in three planes. Hinges shall be concealed type.
Shelves: Shelves shall be MDF utilizing white plastic laminate on both sides, unless otherwise
indicated.
Shelves shall be adjustable or fixed type as indicated on Drawings. Shelves support shall be of
stainless steel and restrain shelves from movement/tilting in positive manner.
Hanger Rods: Hanger rods shall be chrome plated steel oval shape on approved supports.
Handles/Knobs: handles/knobs shall be as per the selection and approval of the Engineer.
Architraves: 18 mm thick MDF, PVC, finished on outside and white melamine finish from inside.
Locks: Suitable locks and bolts to the approval of the Engineer shall be provided. 3 keys shall be
provided for each lock.
AW-1 All the Aluminum sections for the sliding doors and windows are to be from approved
source and similar to series 105 sections for the sliding windows and 125 for the sliding
doors, from Gulf extrusion and the same shall be polyester powder coated 60-80 microns to
the approved color.
All the sliding windows & doors shall have fly shutter from outside
All the items must be strengthened, tapped and modified as necessary to receive
ironmongery. All ironmongery shall be of first quality with the sliding slashes fitted with
roller ball bearing type (Savio or equally approved).
AW-3 Staircases railing using Standard aluminum powder coated finished to the Engineer’s approval,
design to be up to the consultant approval.
Technical Submittal:
TENDER No. 19102 /2019 139/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
Any structure elements, the contractor is fully responsible for against the following:
ii) Contractor to submit method statement for the consultant approval, in no way
the contractor to start fixing without getting the same approval.
iii) 10 years guarantee letter to be submitted by the contractor.
Technical Properties:
All accessories and fixing items to be stainless steel.
All stainless steel works to be grad 316 L, 1.5 mm thickness with polishing No. 8
and backing with galvanized sheet 1.5mm.
Stainless steel tubes shall comply with BS3014, and plates shall comply with
BS1449 part 2
INSTALLATION GUIDES
1) All work shall be installed adjusted and glazed by experienced workmen all in
accordance with the manufacturer's installation instructions and in full conformity
with the approved shop drawings, samples and other submitted date. Under no
circumstances shall materials be installed on surfaces that contain condensation,
dirt, grease or other foreign encountered materials that would hinder or prevent
proper installation and functioning for the use intended.
2) All work shall be carefully and accurately assembled with proper and approved
provision for counteraction and expansion and set in correct locations as per
approved detailed shop drawings, all level, square,, plumb and aligned with
Other work all joints between framing and structural building shall be sealed in
order to be watertight and weatherproof and to satisfy all other requirements of the
Engineer.
4) All works are to be fully protected for the duration of the contract from damage
by other trades. The engineer shall approve the method of protection.
5) If for any reason final finishes become scratched, abraded or damaged during
transport, delivery, storage or erection, it shall be the Contractor's responsibility to
remove or repair those defective areas or components as directed and to the
complete satisfaction of the engineer.
Repair work shall be identical to the manufacturer's applied finish with regard to
gloss, finish and visual appearance. Field touch up of painted aluminum is
permitted only with written permission of the Engineer. Where touch up is no an
authorized means of repair the damaged material must be replaced by new.
6) Upon completion of work all protective coverings from all exposed surfaces
shall be removed. All surfaces shall be cleaned using soap or detergents as
recommended by the aluminum manufacturers to remove sealants, discoloration
and any other foreign material. Defection of any type determined by type
determined by the Engineer shall be repaired at the Contractor's expense.
7) Extreme care shall be taken when cleaning the exterior portion to protect all other
adjacent works.
1.1 MATERIALS
1.9.1 Materials: Inorganic, resistant to rodents, vermin, mildew,
fungus and algae, as necessary to obtain design and
performance requirements and as follows:
1.9.2 Framing, Trim and Flashings:
i. Aluminum:
1. Extrusions: Extrusions shall be from ally 6063 , T6
Temper with following chemical and mechanical
properties extruded to BS 1474.
Chemical Composition
Mg 0.45 – 0.60 %
Si 0.20 – 0.60 %
Cr 0.10 %
Zn 0.10 %
Fe 0.35 %
Cu 0.10 %
Mn 0.10 %
Other Impurities 0.05 %
Aluminium Remainder
Mechanical Properties
Tensile Strength Mpa 185
0.2% Proof Stress Mpa 160
Shear Strength Mpa 155
Hardness BHN 75
1.2 FINISHES
1.11.1 Steel at building interior and not exposed to exterior environmental
conditions shall be primed with primer.
1.11.2 Steel at building exterior or assemblies shall be galvanized.
1.11.3 Concealed surface of aluminum and galvanized steel which would
otherwise come in contact with structural steel, concrete, masonry or
plaster shall be given a heavy protective coating of alkaline resistant
bituminous paint or zinc chromate prior to installation.
1.11.4 Paint weld, galvanized items where galvanizing has been removed
for welding. Make good corrosion protection using two coats of
touch-up primer for galvanized steel. Make good corrosion
protection on prime painted steel using same premier.
1.11.5 All exposed aluminum shall have powder : refer powder coating
specs in the metal works Section (Section No.19).
1.11.6 Exposed fastenings if occurring: Finished and coloured to match the
finish and colour of the material in which they appear. The finish
provided shall be permanent and durable.
1.11.7 Stainless steel: all stainless steel products shall be made from 316L
Alloy in No. 8 mirror finish.
1.3 PREPERATION
1.12.1 Take field measurements from actual structure and verify prior to
commencement of fabrication.
1.12.2 Remove dust and other loose material from openings.
GLAZING WORKS:
1. SCOPE OF WORK:
Including Supply, Installation and guarantee for all the internal and external glazing works
as described here in and mentioned in the tender drawings.
2. GLAZING GENERAL:
All glazing work shall be installed by workmen experienced in this wok in accordance with
BS 6262.
The Contractor shall fix all glass with required gaskets, clips, beads, etc.
All glass panels shall have rounded edges to prevent any damage to gaskets.
The Contractor shall produce on request all invoices or advice notes from suppliers to
confirm that the glass is of the standard specified.
Any scratched, broker or otherwise defective glass is to be removed and replaced by the
Contractor at his cost during or on completion of the Works.
Glazing systems that are produced, fabricated, installed shall be provided to withstand
normal thermal movement, wind loading, and impact loading (where applicable), without
failure including loss or glass breakage attributable to the following: defective manufacture,
fabrication, and installation; failure of sealants or gaskets to remain watertight and airtight;
deterioration of glazing materials; and other defects in construction.
4. GLASS OPENINGS
The glass framing shall both structurally support and adequately cushion the glass. To
prevent mechanical and thermal stresses on the glass, the framing system shall provide
openings that are within the tolerances for spareness, corner offset and bow. The tolerances
are listed below.
If the variations from these tolerances are anticipated, details of same shall be advised to
engineer. If site conditions are found to be outside these tolerances corrections must be
made before the openings are glazed.
5. GLASS INSTALLATION:
6. CLEANING
All glass shall be thoroughly cleaned and polished on both sides and all paint spots and the
like completely removed to the satisfaction of the Engineer.
7. Materials:
1. Ground Floor
Shops elevation, Other External Windows and doors:
Outer lite: 6 mm Tented High performance heat-Strengthened.
Space: 12 mm air filling
Inner lite: 6 mm fully tempered clear glass.
2. Typical Floors
Outer lite: 6 mm Reflective High performance heat-Strengthened.
Space: 12 mm air filling
Inner lite: 6 mm fully tempered clear glass.
Spandrel area to be provided with insulation: 50 mm thick rigid rockwool
of density 50 kg/m3.
Balconies Handrail:
13.52 mm single laminated of the following make up:
6mm reflective high performance fully tempered
(4x0.38) mm clear pvb
6 mm clear fully tempered
Design to be up to the consultant approval.
8. Particular notes:
Obscured glass type and colour is to the architect’s approval.
Glasses shall conform to the requirements of ASTM C1036, quality Q3 unless otherwise
specified. Heat-treated glass shall conform to the requirements of ASTM C1048. Tempered
glass shall also conform to ANSI Z 97.1-984. All heat-treating shall be by the horizontal
process, and processed in such a manner as installed on the building.
Insulating glass shall comply with the following standards:
E773 test method for seal durability of sealed insulating glass units.
E774 specification for seal insulating glass units
E546 test method for frost point of sealed insulating glass units
E576 test method for dew / frost of sealed insulating glass units vertical position.
TENDER No. 19102 /2019 144/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
Laminated glass shall comply with ASTM C1172
10 years warranty on the double glazing units and 5 years on the laminated glass to be
submitted from the glass fabricators by the name of the project upon the completion.
Original glass certificate of origin and 10 years warranty on the reflective and low-E
coating from the glass agent should be submitted by the name of the project upon the
completion.
9. Approved Manufacturer:
VISTEON, (FORD GLASS) U.S.A.
PILKINGTON NORTH AMERICA (PNA), U.S.A.
Glaverbel from Gutal- Dubai or equally approved.
2) Supply and apply one coat of approved solvent base priming/ bonding course as per
manufacture instruction.
3) 1 layer of 4mm elastomeric special polyester tropical grade SBS non-woven modified
bituminous approved membrane, and complying with the following specs:
The waterproofing membrane for protection of concrete substructure shall be a SBS heavy
laminate bituminous felt of a type suitable for hot climates, reinforced with 200 gm/m2 of
non woven polyester inlay and modified bituminous compound presenting high thermal
stability, plasticity and flexibility characteristics as detailed on drawings and as specified in
this Section. The thickness of the membrane shall be 4 mm as specified and indicated on
drawings.
The typical characteristics of a 4 mm thick membrane shall be as follows:
T e s t s Un i t Value Tolerance Test Method
T h i c k n e s s M m 4 ± 5 % UEAtc
A e r i c Ma s s Kg/m 5.25 ± 1 0 % UEAtc
Tensile Strength at break Long N/5 cm 900 ± 2 0 % UEAtc
Tranv N/5 cm 800 ± 2 0 %
Elongation at break Long % 5 0 ± 1 5 % UEAtc
Tranv % 5 0 ± 1 5 %
Tear Strength Long N 170 ≥ 1 7 0 UEAtc
Tranv N 180 ≥ 1 8 0
C o l d B e n d i n g ° C -25°C ≤ - 2 5 UEAtc
Form Stability ° C 100 ≥ 1 0 0 UEAtc
Water pressure resistance Kpa 400 ≥ 4 0 0 DIN 16935
Soft en i ng Poi n t R& B ° C 115 ≥ 1 1 5 ASTM D36
Down Penetration 25 °C (77°F ) Dmm 3 2 ± 5 ASTM D5
4) The junction between the horizontal and vertical shall be covered with metal-faced water
proofing membrane as skirting with overlap of min. 300 mm.
5) 50mm thickness extruded Polystyrene (Rigid foam) SHD grad closed cell with 32 kg/m3 density,
and should comply with the following:
A. Material
The thermal insulation material shall be an inorganic plastic material and performed into
rigid foam slabs by pressure extrusion method. The foaming and extrusion process shall
ensure 100% closed cell formation and smooth hard unbroken skin on all external faces.
The insulation slabs shall be extruded polystyrene boards of 50 mm uniform thickness and
shall conform to BS 3837: Part 2: 1990 Extruded boards. It shall be type A, grade SHD
(extruded boars with skins) having a standard dimension of 1250 x 600 x 50 mm.
The material shall exhibit the following characteristics:
Five year aged average thermal conductivity of maximum 0.032 W/mk when tested at 24°C
in accordance with DIN –52612 or ASTM C-518-76, C-177-76.
Compressive strength of 43 psi or 300 kps average when tested in accordance with DIN-
53421 or ASTM D-1621.
Water absorption of maximum 1% average when tested in accordance with ASTM D-2842.
Water vapour permeability of 0.6 perm inch average when tested in accordance with ASTM
C-0355-64.
7) 600 * 600 Concrete panels to be provided with the necessary plastic support.
8) Gravel to be filled all around the roof at the skirting areas.
9) Roof membrane at the edges (skirting areas) to be mineral chips.
10) Zaid coat system from Al Zaid International and the coats will be as follow: -
1. RA 71.
2. Zaid Filler.
3. Zaid Coat.
4. Fiber Tex (Matrix)
WP-4 The Contractor is to allow in his rates for such areas to be flooded with water, and left for a minimum
of 48 hours.
Roof to be tested once again before the preliminary handing over of the project on the
written instruction by the engineer.
All the surfaces to be cleaned, dried and grinded in accordance to the manufacturer
instruction.
The contractor to protect any finished surfaces to ensure no damages will be occurred, and
in the case of the same it will be complexly the contractor responsibility to fix the same and
retested.
4. PREPARATION OF SURFACES
All surfaces shall be clear of all deleterious matter and dry all in accordance with the
manufactures written instructions. Prior to the application of any waterproofing/roofing
material or primer the Contractor shall grind the concrete surface using a mechanical
grinder to ensure al surface irregularities are removed. and gain the Engineer's written
approval that he may commence the said works, without same all works shall be rejected
and replaced at the Contractor's expense.
5. PROTECTION
Finished and part finished surfaces shall be suitably protected to ensure no damage by other
trades. Any roofing or waterproofing so damaged due to non-protection shall be remove an
replaced at the Contractor's expense. The contractor shall submit to the engineer his
proposed methods of protecting the various surfaces and locations prior to their completion
or application of finishing layers, i.e. tiling and the like.
7. WATER STOPS
TENDER No. 19102 /2019 149/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
Will be Galvanized metal strips, each is 2 cm long and 16.7 cm wide. Both sides are completely
covered with a special coating which guarantees a waterproof bonding to the fresh concrete.
The coating must be protected by a split protective film on both sides.
A concrete cover 3 cm should be sufficient to retain a water pressure of up to 6.0 bar. The
enormous elasticity of the coating in the area of the joint should prevent leaks that may arise
due to the concrete shrinkage.
Water stopper for construction joint shall be Pentaflex KB, Germany origin.
Approved supplier is Emirates Hickson or equally approved.
The contractor shall allow in his bid his price for fixing the Sanitary Ware and any related works for
the completion of this item.
-Items listed are from approved manufacturer, up to consultant approval. All colors to the
consultant selection.
6. All sanitary Accessories are from approved manufacturer, Position of accessories as directed
by Engineer wherever required.
Content
2- Generator Set
4- Light Fittings
5- CATV
8- D. DRAINAGE
9- Air Conditioning:
GENERAL
The Electrical Contractor shall include for the supply of the whole of the materials in accordance with the
specifications as per approved list of make and the whole of the work of fixing necessary for the complete
installations as set down in their specifications with accompanying drawings and schedules. Commencing
from supply authorities terminals
The work shall be carried out to the satisfaction of and in accordance with the rules, regulations and
requirements of the supply authority. Where none exist the work shall be carried out in accordance with the
"Current Regulation for the Electrical Equipment of Building " issued by the Institute of electrical Engineers
(United Kingdom).
The electrical contractor shall serve all notices on the supply authority for testing, pay all fees in connection
therewith, and should any additional charges be made for re-testing, they shall be paid by the electrical
Contractor.
Circuit list shall be provided inside all distribution board etc, clearly marked in Indian ink.
The consulting engineer shall have full power to require any material or work to be tested at the electrical
contractor's expenses in order to prove their soundness and efficiency.
The cable conduit and sheaths shall be tested for insulation and continuity as the work proceeds, before any
connections are made to the switch and distribution board terminals. In case any materials or work shall,
with or without being tested, be considered defective, such work shall forth with be amended in a proper
and satisfactory manner on being notified by the Consulting engineer. Where certificates are required from
manufactures of specialized equipment, before handing over the Electrical Contractor will pay all charges
incurred on obtaining these certificates.
The position of all points and equipment shown on the accompanying plans shall be assumed correct for the
purpose of tender but it is the Electrical Contractors responsibility to check the positions with the drawings
which will be available on site. Any variation of position or height may allow without extra charge, unless
such alterations are made after conduits, cables etc are fixed.
The Electrical Contractor shall submit shop drawings showing all details and samples of Electrical
Accessories as required by Consulting Engineer and shall be approved before starting work at site.
Surface/recessed mounted type switch gear and distribution board suitable for conduit or cable entry as
required and shall, where specified, be mounted on the building structure by means of suitable mild steel
straps or angle iron frames. In the case of distribution boards or switchgear required to be directly attached
to brickwork etc. the fixing shall be by means of grouted in bolts, or bolts of the expansion type.
Barriers of fireproof materials shall be fitted between all phases and neutral. Any live metal in the
distribution board shall be screened with the insulation material, so that circuit breakers can be withdrawn
and replaced without any danger to the operator.
Where single core cable enter or leave any item of metal clad switch gear, distribution gear, etc. the cable
core shall all pass through the same aperture in the enclosure or case of the unit concerned, to avoid the
setting up of eddy currents. Where separate holes are provided by the manufacturer for the slot, or
alternatively the holes shall be joined together with saw cuts through the solid metal sperating the holes. In
all cases the plates shall be of non-ferrous materials
The Contractor shall submit test certificates such as ASTA or as issued by any other independent testing
authority confirming the declared short circuit rating of switch board and circuit breakers.
Main L.V. distribution panel shall be of free standing cubicle multier type in cooperating 3 phase neutral
and earth high conductivity insulated copper bus bars with individual connection for every outgoing ACB'S
fuse switches, distribution units, metering panels, all necessary CT'S and the like as required. Each
compartment shall be equipped with thermostatic ally controlled heaters that shall be "on" all the time
Ventilation means and lights.
Main distribution panel (s) shall be equipped with all necessary circuit breaker and components with enough
spare outgoing for any future use as per drawing.
Switch distribution shall be designed to operate on a 415/240v 3 phase and neutral 50HZ supply and shall
have a minimum short circuit rating as specified in the approved drawing, for three seconds switchboard
shall be comply with BS. 5486 part - 1 malticubicle type FBA FROM-11
All ACB'S shall be tripe-pole withdraw able type. They shall have manually and electrically D.C. operated
spring charge closing mechanism and three duel- magnetic (low time delay) and instantaneous over current
trip devices unless specified otherwise (such as short time-delay for selective tripping)
Electrically operated-breakers shall have a push button on the escutcheon of the breaker. All the incoming
and outgoing circuit breaker shall have enough change over auxiliary contacts.
Each breaker of 630A or more shall be supported within its compartment by a roll-outer track that is part of
the withdrawable mechanism attached to the side of the compartment. All the ACB'S of the same type and
rating shall be entirely interchangeable.
All ACB'S shall be temperature Compensated at the manufacturers works to give the current rating
indicated on the drawings at 50 degree. C. Non-compensated breaker will not be approved. A formal
certificate will be required from the manufacturer confirming that the breakers have been suitably
temperature compensated.
The contractor will be responsible for the ensuring that any back up (current-limiting) fuse protection is
provided in circuit breaker switchboards as necessary. Any such current limiting fuses shall be
appropriately labeled to indicate their function.
The cubicle shall be front operated with a mechanical on/off position indicator and shall be designed and
tested in accordance with relevant standards. The cubicle shall be capable of being extended in either
direction for further MCCB'S as necessary.
The main incoming supply shall be complete with an ammeter, CTS, phase-to-phase voltmeter. Each meter
shall have phase selector switch and indication lamps and set for main incoming supply.
These shall be self contained, rust proof, durable stoves silver-gray hammered enameled, cubicle pattern
sheet steel units complete with circuit breakers of the size and rating required to meet the power demand (as
per approved drawing). All distribution boards shall contain an integral main isolator/MCCB appropriate
capacity. The short circuit capacity of the distribution boards shall be rated to withstand the short circuit
level of the position installed.
A sub-feed neutral assembly with a removable link for isolation shall have available as an integral part of
the distribution board. Earthing bar assembly shall also be available to felicitate the connection of earth
continuity conductors.
Door locks shall be fitted as standard to all distribution boards and all the locks shall be keyed alike. The
degree of protection of the switchboard shall comply with BS- 5490 and IP 31 OF ice 529 or upgraded to
meet the requirement of particular location
The MCB Distribution boards shall be flush-mounding type rust proof sheel units, complete with miniature
circuit breakers providing thermal over load and magnetic short circuit protection and ICB's as shown on the
drawings. The assembly shall comply with BS - 5486 part - 12
The MCB shall be mounted on either d phase or single phase or split busbars as appropriate. All MCB
distribution boards shall be provided with an integral main isolator/MCB with the capacity as shown on
drawings/schedules. All spaces that are not provided with breakers shall be covered with blank plates. As
standard items all MCB hoards shall be provided with permanent circuit identification chart to the approval
of the Engineer.
A final sub circuit neutral assembly and an earthing bar assembly shall be available to the felicitate the
connection of neutral conductors and protective conductors respectively.
All MCB's connected to incandescent and fluorescent lighting shall be protection type 3 and those
connected to general purpose socket and water heaters shall be protection Type- Final sub circuit for other
inductive loads to be provided with Type - 3 break. The three pole-circuit breaker shall be common trip with
individual spring pressure on each contact/ The minimum short circuit breaking capacity of MCB shall be
6K.A. All the circuit breakers shall comply to B.S.- 3871 Part -1, with amendments, and shall be
constructed and tested with the same. All CB's shall be factory calibrated to ambient temperature of 50
degree C
Earth leakage circuit breakers shall be provided as per the drawing/loading schedule.
NOTE:
DB colour to be submitted for the Architect’s approval before placing the order for the materials.
Note:
1) Electrical contractor has to put all the conduits
2) Consultants reserve the right to change the location of DB inside the building as per the site
condition. The electrical contractor has to do the same without cost variation.
3) Electrical contractor shall co-ordinate with A/c contractor for successful completion of A/c
works. The supply, installation, testing and commissioning of isolators, providing sleeves
and PVC pipes for A/c gas pipes, providing opening for fresh air supply wherever necessary
to be done by Elect. Contractor as instructed by consultants & A/C contractor.
4) Electrical contractor shall co-ordinate with Plumping contractor for successful completion
of Plumping works. The supply, installation, testing and commissioning of water heater,
water pump set, water booster pump set, , providing sleeves , wiring and PVC pipes for the
same, providing opening for the plumping sleeves wherever necessary to be done by Elect.
Contractor as instructed by consultants & Plumping contractor.
5) Electrical contractor shall co-ordinate with fire fighting contractor for successful
completion of fire fighting works. The supply, installation, testing and commissioning of
fire fighting pump set, providing sleeves and PVC pipes for the fire alarm cables, fire alarm
control panel.
6) The Electrical contractor has to do the testing and commissioning of the entire electrical
system as per DEWA rules and regulations and up to the satisfaction of the consultants'
engineer. Any item which is not mentioned in the specification / drawing and is necessary
for the successful operation of the electrical system, electrical contractor has to supply and
install the system without any extra cost.
7) Electrical contractor shall provide the power requirement for the window A/C that is
mentioned in the drawings.
8) Contractor has to provide cable tray for taking the cable from G.FL. Electrical room to
upper floors and horizontally at ground floor and first floor above false ceiling.
3 PHASE OUTPUTS
Generator Set 50 Hz
Model Rating
KVA KW
Standby 100 160
GEP 110
Rating Definitions
Standby Power
These ratings are applicable for supplying continuous electrical power (At variable load) in the event of a
utility power failure. No overload is permitted on these ratings. When used at standby rating the alternator
will be peak continuous rated (as defined in ISO8528-3) at 270C.
Prime Power :
These ratings are applicable for supplying continuous power (at variable load) in lieu of commercially
purchased power. There is no limitation to the annual hours of operation and this model can supply 10%
overload power for 1 hour in 12 hours.
The Generator should be provided with life time rechargeable battery.
A. General
The Contractor shall allow for the supply, Install, test and commission the Digital Audio vidio
Intercom system, as herein specified and shown on the drawings. The system shall consist of a master
intercom station at the main entrance and audio vidio intercom slave stations in all the apartments.
B. System Features
The basic function of the system shall be to facilitate communication between a visitor at the entrance
lobby and the occupants of the apartments. The visitor initiates a call by punching in the apartment
number to be visited, and pushing the call button in the digital keypad of the panel. A buzzer alerts the
occupant of a visitor. When the occupant picks the telephone handset, an audio communication link
shall be established between the entrance panel and the apartment.
The system shall be operated on 24VAC supplied by a 220V/24V transformer located at the ground
floor electrical room or above the false ceiling, to the approval of the Engineer. The main entrance panel
and apartment stations shall be installed as shown on the drawings, with all inter connection wiring,
conduits and accessories. The conduit system shall be segregated from all other systems.
The system shall be a programmable digital type permitting parallel connection (looping) of all flat
telephone units and shall not require individual radial connections. The program shall permit assignment
of suitable identification numbers to individual apartment stations.
The system shall allow privacy, i.e. conversation shall only be heard by the number called.
All apartment stations shall be complete with electronic call, conversation button on the base, door
opening button and supplementary button for additional services.
The handset shall be surface mounted type.
The main entrance unit station shall be flush mounted with an illuminated push button, microphone
speaker all as a built in unit. The face plate shall be of thick anodized aluminum, with aluminum push
buttons. It shall consist of a digital call module and electronic name directory module and speaker unit
with microphone. The digital call module shall have a four digit LCD display, 12 push button panel
illuminated form the rear, confirmation buzzer for push button pressed and shall act as electronic coded
key with 9 possible different control codes. The electronic name directory module shall have a 32-
character alphanumerical display. It shall memorize at least 400 user names. Name scrolling shall be
carried out using two search push buttons. Once the name of the desired person is displayed, the call
shall be imitated by simply pressing the call button.
The main contractor shall be responsible for the full coordination with the fittings supplier for incorporating
any arrangement required for good fixation such as appropriate hooks for pendant fittings, openings in the
false ceilings, special electricity power supply or any other requirement whatsoever. The contractor shall
show the dates of the light fittings delivery in the master programme of work after having the same
approved by the Client’s representative.
The main contractor shall show in his bid his price for fixing the light fittings.
All external; lights to be connected to timer.
The light fitting to be considered as LUPSUM contractor to include in his bid:
1. Lifting of materials, scaffolding, storage area.
2. Protection of stored materials will be the MEP Sub-contractor responsibility.
3. Fixing of light fittings.
4. Providing the light points.
The contractor shall allow in his bid his price for the infra-structure work required for the above work (
fixing the necessary manholes, pipes, cable trays, conduits, junction boxes, boxes and sockets with the
necessary pull ropes as per du requirement/ approval vide the approved drawing ), attendance/overhead &
profit.
The contractor to prepare separate CATV drawing and to submit the same for Etisalat approval.
System requirements
The IF system shall provide for the reception of a minimum of three satellite LNB (F) s. It shall also provide
for an RF signal input.
The IF system shall be future proof, so that any additional satellite packages can be added onto it.
Connectors
Only the correct connectors to suit the matching cable must be used. All connectors shall be crimp type only
and shall be waterproof type. All non-connected inputs or outputs hall be properly terminated with a 75
Ohm load.
Wall Outlets
- All wall outlets shall be capable of extracting the TV/FM & satellite frequencies
- Each wall outlet shall have direct IF connection, looping between wall outlets is not acceptable.
System shall have correct value of outlets and confirm to the signal level requirements.
Terrestrial antennas
Antennas should be constructed of light aluminum alloy and protected against corrosion by heavy anodic
coating.
Antennas should be fixed on a galvanized steel pipe 1.5” min. diameter, and the mast should be fixed on the
roof of the building with strong concrete base and secured by guy wires. The locations of the mast to be
agreed by the consulting engineer.
Channelized antennas shall be provided for VHF channels and channel-grouped antennas for UHF channels.
Number of elements and the gains of the antennas shall be selected according to the aerials signal level of
each channel.
Dish Antenna
All dish antenna shall be made by reputed international company and shall be made from non Ferron
material and coated if required by anti-corrosive paint.
Dishes shall have structural integrity to withstand the max expected wind forces in the area.
To support of all satellite dish antennas and terrestrial antennas on roof shall be to structure engineer
approval.
Following are the required satellite receptions :
A. MATV(Terrestrial) channels
1. Dubai Ch 33 & 41
2. Abu Dhabi Ch 43
3. Sharjah 22
4. Ajman Ch 26
TENDER No. 19102 /2019 170/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
5. FM Radio
WS-1 Scope of work include supply, installation, testing and commissioning of water supply and
drainage system as specified herein and as per drawing and up to the satisfaction and approval of
consultants. Any item of work which is not mentioned in the specification and drawing and is
necessary for the successful completion of the project, the contractor has to provide the same without
any extra cost.
WS-3 External water supply shall be using PPR pipes – Aluminum coated with UV protection layer, and
insulated with rubber insulation protected with canvas.
(i) From ground water tank up to the overhead water tank
(ii) Water outlet for external area (2 Nos)
(iii) From overhead water tank to individual location
WS-4 water transfer pump set to pump the ground water to the overhead tank placed at pump room in two
nos. ( one as stand by) - (GROUNDFOS OR BIRAL) and approved by consultants.
WS-5 booster pump sets to be provided on roof for the last two floors for each building with the
provision of a control panel and a pressure vessel having the proper capacity to BS standard,
(GROUNDFOS OR BIRAL) and approved by consultants.
WS-6 Water meters/ valves will be supplied and fixed by plumbing contractor. All laison work required
for water supply connection to be done by plumbing contractor.
WS-8 Angle valve shall be provided for all hot and cold water out let/ water heaters - Grohe - Germany or
equivalent
WS-9 All the water supply system shall be tested for 10 bar pressure for 24 hours in the presence of
consultants' engineer.
WS-10 All the water supply pipes at roof area to be identified in accordance with the colors and code
indication of BS. 1710.
The main contractor shall allow in his bid his price for attendance/overhead & profit.
Scope of work include supply, installation, testing, and commissioning of wet riser system “landing valve”
hose reel and sprinkler system as per Dubai Civil Defense requirements and as per the approved drawing
and up to the approval of the consultants. Civil Defense Department approval fees to be paid by the
contractor.
Where shown on the drawing, a wet riser two inlet breaching valve assembles shall be provided in a wet
riser inlet box.
The breaching shall be located in stainless steel cabinet and to be of 100mm two inlet type, horizontal
pattern with 65mm male instantiation inlets, caps and chains back pressure valves and 25mm drain valve all
as manufactured by Angus / Unitor / Sukar or as equal approved.
At each floor level wet riser landing valves shall be supplied and installed as shown on the approved
drawing. The valves shall be manufactured in gun metal and shall be of the gate pattern.
A. 01 GENERAL
(a) Wet pipe sprinkler system employ automatic sprinklers attached to a piping system
containing water and connected to a water supply, each line is fully pressurized, so that
water discharges immediately from sprinklers opened by a fire.
(b) The System shall be designed such that only those sprinklers, which have been
operated by heat only discharge water.
(c) The design of the sprinkler system indicated on the drawing will be fully developed by
the contractor strictly in accordance with the requirements of the local fire officer and
rules for automatic sprinkler installation as per NFPA 13. All material shall UL listed /
FM approved.
A. 04 Piping System:
As per Central Sprinkler System of Equal An Approved.
(a) Pipes:
Steel pipe shall be mutual systems ‘approved, exterior galvanized, ASTMA – 135 steel pipe
having and working pressure of 30 PSI. Coupling may be of the rolled grow type or the
mechanical locking type (push – on), and they shall be dimensionally compatible with the pipe.
Pipe and preparation accordance with the manufacturer's recommendation as of : LIGHT
WALL, SCH. 40 & SCH. 10.
(b) FITTINGS :
Mechanical grooved pipe coupling and fittings as manufactured by central shall be used for all
stand pipe systems. All material shall be underwriting laboratory listed factory mutual approved,
fitting 2 ½” below inclusive shall be threaded. 2 ½” above shall be mechanical grooved type.
b. 1) COUPLINGS :
All line and fitting joints shall be with grade ‘E’ gaskets with zinc and electroplated bolts and
nuts.
All reducing joints shall be reducing coupling with grade ‘E’ gaskets and zinc-electroplated
bolts and nuts.
` BRANCH CONNECTIONS :
Branches stub-in connection shall be made with clamp T and Clamp T cross with grade ‘E’
gaskets and zinc electroplated.
b.5) FITTING:
Shall be standard malleable iron, ductile iron, forged steel or segmentally welded steel
fittings with grooved or shouldered ends.
b.6) VALVES:
Shall be of wafer end design with encapsulated body and disc. Neck design shall
readily accommodate installation. Valves shall have pressure assisted double seal and be
capable of 175 PSI or 300 PSI bubble-tight shutoff. Butterfly valves shall be with gear
actuator.
(a) Support, hanger and guise are piping to preclude failure of deformation. Construction install
hangers, supports, hangers, guides and accessories to the approval of the engineer. Do not use
wire, tape of metal bands supports shall be designed to support weight of pipe, weight of fluid and
weight pipe insulation.
For internal Fire alarm system i.e. Fire alarm inside the building:
All the fire alarm works has to be executed by specialist fire alarm contractor approved by Dubai Civil
Defense / consultants.
The fire alarm contractor has to prepare and submit workshop drawing to Dubai Civil Defense / consultants
and has to get approval before commencing work at site.
The fire alarm system shall comprise of a multi zone control and indicator panel, smoke & heat detectors,
manual break glass units, alarm bells, batteries and chargers. All as indicated in the drawings, and shall be
complete with all necessary connections, accessories and wiring to give a completely reliable and
satisfactory system designed to operate on 24 volts DC.
The alarm system shall be designed to cover zones as detailed in the drawing. In any zone of the building,
the manual breaking of a break glass contact or automatic operation of heat or smoke shall give a visual and
audible alarm signal at the indicator panel, and shall simultaneously ring local alarm bells in the particular
zone.
All equipment and components of the alarm system shall be ordered from one approved manufacturer. The
supply, installation and commissioning of all fire alarm system shall be to the approval of the Civil Defense
Authority and consultant's Engineer.
The contractor shall provide the consultant's engineer with the schedules of equipment and comprehensive
wiring diagrams of the alarm system proposed and shall obtain his written approval before orders are
placed.
TENDER No. 19102 /2019 176/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
The following items to be connected to the fire alarm system of the building:
1. A/C system.
2. the lift.
The panel shall be of the illuminated lamp type designed for surface or flush mounting (to be approved by
the consultant) and shall be equipped with all necessary supervisory alarm, buzzers, indicators, pilot lamps,
switches, relays, push buttons, etc. The panel shall be arranged to indicate where the alarm initiated.
2.1 On receipt of manual or automatic fire signal in any zone the following shall occur:
(i) Visual and audible signal shall be given on the panel.
(ii) The appropriate zone indicators shall operate.
(iii) An "evacuate" signal shall sound in the particular zone.
(iv) An "alert" signal sound for 30 seconds in all other zones
All smoke detectors shall be complete with mounting junction boxes and red LEDS for indication. In
addition, in areas such as ceiling voids, Electrical and Lift Machine Rooms, each smoke detector shall be
connected to an LED, which shall be located outside each area.
All call points shall be finished stove enameled Red and shall be complete with an instruction plate lettered
" FIRE SMASH GLASS".
TENDER No. 19102 /2019 177/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
All call points shall be surface mounted at a height of 1.400 m above F.F.L. at approximate location
indicated in the approved drawing.
All bells shall be surface mounted at a minimum height of 2.30 m above F.F.L. at approximate locations as
indicated in the drawings.
8.0 WIRING
The whole of the wiring shall be carried out in flexible fire resistant cables of minimum cross-sectional area
1.5 mm2. The limit of voltage drop under full alarm load shall not exceed 1 volt.
All fire alarm wiring shall be completely segregated from all other wiring in the building.
D-1 All the manhole covers shall be heavy duty (double seal ) grade A for parking area and for non
parking area grade B (double seal) RSI-India or equal. For sizes refer drainage drawing.
D-2 Drainage shall be using UPVC pipes and fittings- Marly or Hyppworth for sizes . Ref. sanitary
drawing
D-3 Floor traps shall be UPVC with cover of approved make or as instructed by the consultant- Hyppworth
-UK.
D-4 All length of drains shall be tested for water tightness by means of water pressure and for the
straightness of possible blockages, to the satisfaction of consultant's Engineer. The tests shall be applied
before the drains are surrounded in concrete or aggregate protection and the satisfaction of the engineer
shall be confirmed in writing as a record. Prior to practical completion and with adequate notice to the
engineer the complete system will be proven by the contractor by testing in accordance with standard testing
procedure in the pressure of consulting engineer.
D-5 Roof water tank should be GRP hot pressed thermal panel type (Local Made) of capacity as per the
drawings, and to be heat insulated, of the following characteristics:
1. specific gravity of 1.8.
2. water absorption less than 0.2 %.
3. rubber gasket.
4. S.S bults and nuts.
5. GI frame angle and frame plate.
6. external ladder of hot deep galvanized steel.
7. internal ladder of rigid UPVC.
8. SS tie rods.
9. panel thickness of 12mm.
10. insulation of 25 mm.
11. glass tube level indicator.
D-6 Contractors shall submit shop drawings for the plumbing work before starting the work at site and all
the plumbing fixtures and accessories shall be approved by the consultant prior to the commencement of the
work at site.
D-7 floor drain shall have brass, chrome plated floor plates connected to the UPVC
D-8 As per drawings, the contractor has to provide for the 1st and 2nd basements fully shop drawing for the
drainage system including the sump pet with sand trap and submersible pumps up to consultant approval.
INDEX
1. Scope of works
2. Design Condition
3. Split Unit (Duct Type)
4. Duct Works
5. Installation
6. Pipe Works
7. Grilles and Diffusers
8. Commissioning
9. Guarantee
Civil work related to the Air conditioning & Mechanical Ventilation installation such as breaking,
cutting, foundation, carpentry work and finishing are excluded from the A/C works. All this items to
be carried out by the Main Contractor.
Electrical works and conduiting upto isolating switches are excluded from A/C Works. All this items
to be carried out by die Main Contractor.
Design Condition:
Outside Ambient Temperature : 115 deg. FDB/84 deg, FWB
Relative Humidity : 55 + 5%
Inside Room Temperature : 72 + 2 deg., FDB
Air Change (A/C areas) : 1 air change/hour.
Contractor should comply with internal design condition and it is his responsibility to do complete
testing in order to achieve this condition.
Contractor to submit copy of the heat load calculation and workshop drawings within 3 weeks after
signing the contract.
All ducts and fittings should be manufactured and installed as per the ASHRAE standard or
Equivalent standard as approved.
Sheet metal should be from excellent hot deep galvanised type. Fixing and installation way should be approved by the
Engineer before commencement of work at site.
Duct System should be provided with volume control dampers wherever necessary Steel supports should be
painted in anti-rust paint.
All ducts passing through the wall should be isolated and air-tight and installed as per the ASHRAE
Standard.
Duct should be designed on a low velocity basis in order not to exceed the specified noise level (N 35) and duct should
be designed on an equal friction method.
Exposed duct shall be of 2.0" thick and a density of not less than 16 Kg/M3 all duct internal and external to
be covered with canvas cloth (6 oz) and two coats of foster 30-36 and one coat of Foster 57-86 or
equivalent.
Sound Liner:
Accoustic insulation of fibre-glass W' thick shall be fixed to internal duct surface of each unit discharge duct of not
less than 10 ft., length.
Insulation shall be fixed as per the insulation manufacturer. The insulation shall not be split.
Pipe works:-
Refrigeration Pipe Works:-
All refrigeration shall be installed parallel to the building lines wherever possible. All pipe runs shall be straight and
parallel. All bends shall be made with a mechanical bending machine wherever possible. Brazed joints are to be kept to
a minimum hand bending of refrigeration pipes are not permitted.
Drain Pipes:
All drain pipes shall be of approved pipe and shall be fitted with a demountable trap
Commissioning
The Contractor shall allow for all R22 and air distribution services to be balanced and commissioned in accordance
with the relevant commissioning codes published by the Chartered Institution of the Building Services Engineers
The balancing and commissioning for all air-conditioning circuits shall be carried out by the manufacturer of the air
handling plants.
The Contractor shall supply & install on all air distribution system all test permits required in order to commission the
systems completely. Testing and commissioning results shall be submitted to the Engineer for approval.
The Contractor will be particularly required to show, in distribution systems, that the correct design static pressure will
be available at the most remove diffuser when operation with "wet cooling coils and dirty filters''.
The Contractor shall prepare a pre-commissioning programme for each system of every service included in the
development. The procedures to be adopted for commissioning shall be as laid down by the relevant commissioning
codes pulished by the Chartered Institute of Building Services Engineers.
All plant shall be Scheduled and recorded with its relevant duty and cross checked with the actual performance.
All main ducts and sub-distribution shall be checked for volume and pressure drop throughout its length and recorded in
schedule form.
The above procedure shall be carried out in stage & then checked and demonstrated to the Engineer. Should any of the
demonstrations show irregularities the Contractor shall repeat the procedure until the systems are provided against the
designs.
AIRCONDITIONING:
a) package system : REEM , DAIKEN , OGENERAL
b) Grills and Diffusers: TECHNALCO, Beta, B.C.I
c) A/C Control: HONEWELL, Siemens or equal with 3 Speed Digital type
d) Duct Insulation: ISOVER, KIMMCO, IZOCAM
e) G.I sheet Nippon – Japan, South Africa
TENDER No. 19102 /2019 185/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
f) Sound Liner: Manson, Kimmco
g) Copper Pipes: MULLER BRASS, Maksai
h) Copper Pipe Insulation: ARMOFLEX, GULFOFLEX
Note: All equipment and accessories shall be of the specified brands or equivalent.
Ventilating:/Supply Fans:
General
The contractor shall supply and. install where shown on the drawings, fans as described hereinafter and capacities
indicated in the capacity schedule on the drawings.
Fans shall have integral guide vane, inlet guard of stainless steel mesh and electric motor mounted on casing with belt
guard in case of belt driven.
Any other type as per description given in the drawings. For all fans the bearings shall be self-aligning, self grease
lubricated ball-bearing type, and shall be complete with grease fittings, extended for easy access where necessary. The
fan motors and starter shall be in accordance with local W.E.D. regulations and our electrical specifications. The sheets
shall be balanced statically and dynamically, after any coating is done o the wheel.
All required civil works, openings, Pedestals, Sleeves, loading & Unloading, Foundation for machines on the roof, sub-
Frame for ducting and electrical requirements for central Airconditioning shall be done by the main contractor. This
include panels, Isolators, Conduits Cables, Wiring & Control Wiring etc., complete as well as wiring and conduiting
between A/C machines & Thermostat, wiring and conduiting isolators and A/C Machines as per SEWA rules.
All pipes for drainage and all necessary drainage arrangements to the Main Drain Line etc., 3: dia., PVC Refrigeration
Sleeves for Refrigeration & 1" dia., PVC Sleeve for Thermostat Control Wire etc., shall be made by the Contractor to
the total approval of the Consultants. The Main Contractor shall co-ordinate all his works with the A/C Sub-
Contractors works. The Consultant has the right to accept or reject any of the Quotations submitted by the Sub-
Contractor. Note that, weatherproofed Isolators to be used on the Roof. FCU and Thermostat shall be fixed inside the
Room & Compressor (CU) shall be fixed outside on the Roof as shown in the Drawings
Sub-Contractor shall be approved by the Consultants
Any item of work not included in this B.O.Q which is essential for the satisfactory completion of the
project, the Contractor has to add the same in this list or to be considered elsewhere in their offer
SL Unit
DESCRIPTION OF WORK Unit QTY Total Price
No Price
A. Mobilization
Total of A.
1. Excavation m3
P.C.C for footings, Tie beams, Solid block
2. etc m3
3. Pilling Works
9. Polythene sheets m2
Total of B.
1. R.C. columns m3
2. R.C. beams m3
4. R.C.Lintels/Arches/Parapet etc. m3
5. R.C. Staircase m3
Total of C.
TENDER No. 19102 /2019 191/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
SL Unit
DESCRIPTION OF WORK Unit QTY Total Price
No Price
D. Block Work
Total of D.
TENDER No. 19102 /2019 192/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
SL Unit
DESCRIPTION OF WORK Unit QTY Total Price
No Price
E. Plaster works
Total of E.
F. External finishes
8.
ANY OTHER ITEM
The tenderer is to detail below any additional items
with quantities and rate not previously included to
complete the lump sum tender price for the above
section of works. Should the tenderer fail to insert
any items here, it will be deemed that his lump sum
price for the tender includes all items necessary to
make the various system outlined in the specification
and drawings, and no subsequent claim for any
additional item shall be entertained.
Total of F.
Total of G.
6. Terrazzo L.M
8. Threshold L.M
9. Vinyl
ANY OTHER ITEM
The tenderer is to detail below any
additional items with quantities and rate
not previously included to complete the
lump sum tender price for the above
section of works. Should the tenderer fail
to insert any items here, it will be deemed
that his lump sum price for the tender
includes all items necessary to make the
various system outlined in the
specification and drawings, and no
subsequent claim for any additional item
shall be entertained.
Total of H.
GROUND FLOOR
m2
J. Ceiling finishes
3. Spray Plaster m2
12 mm Gypsum board false ceiling as per
TENDER No. 19102 /2019 198/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
4. design m2
Total of J.
SL Unit
DESCRIPTION OF WORK Unit QTY Total Price
No Price
K. External works
3. Curbstone L.M
TENDER No. 19102 /2019 199/255
PROPOSED B +G+1 Private Villa
Owner: Mr. Kaleem Ullah Khan
4 Granite tile
ANY OTHER ITEM
5 The tenderer is to detail below any
additional items with quantities and rate
not previously included to complete the
lump sum tender price for the above
section of works. Should the tenderer fail
to insert any items here, it will be deemed
that his lump sum price for the tender
includes all items necessary to make the
various system outlined in the
specification and drawings, and no
subsequent claim for any additional item
shall be entertained.
Total of K.
SL Unit
DESCRIPTION OF WORK Unit QTY Total Price
No Price
4.
ANY OTHER ITEM
The tenderer is to detail below any
additional items with quantities and rate
not previously included to complete the
lump sum tender price for the above
section of works. Should the tenderer fail
to insert any items here, it will be deemed
that his lump sum price for the tender
includes all items necessary to make the
various system outlined in the
specification and drawings, and no
subsequent claim for any additional item
shall be entertained.
Total of K.
Total of M.
2. Roof tiles m2
Total of N.
1. Mirror L.S
2. Counters L.S
8.
ANY OTHER ITEM
The tenderer is to detail below any
additional items with quantities and rate
not previously included to complete the
lump sum tender price for the above
section of works. Should the tenderer fail
to insert any items here, it will be deemed
that his lump sum price for the tender
includes all items necessary to make the
various system outlined in the
specification and drawings, and no
subsequent claim for any additional item
shall be entertained.
Total of O.
1.
2.
3.
4.
5.
Total of W.
D. Piling Works
E. Block Work
F. Plaster works
G. External finishes
H. Floor finishes
I. Skirting
J. Wall finish
K. Ceiling finishes
L. External works
N. Aluminum works
P. Other works I
Landscape Hardscape:
-All external landscape and hardscape works including proposed Gasebo, Plants, Irrigation System
and Pump, nearby including finishes and MEP work also prepare shop dwg.
- Allow for any profit, Attendance. Builders work and other overhead %
- Allow for any profit, attendance, builders work and other overhead of this item %
Sanitary Ware :
- Supply of all sanitary ware and fitting by owner, fixing and installation by
main contractor PROVISIONAL Sum AED 150,000/-
- Allow for any profit, attendance, builders work and other overhead of this item %
- Allow for any profit, attendance, builders work and other overhead of this item %
supply and fix natural stone cladding dry fix PROVISIONAL Sum AED 850,000
Light Fitting:
- All light fitting including sockets and switches supply by owner
fixed and installed by main contractor
PROVISIONAL Sum AED 90,000/-
- Allow for any profit, attendance, builders work and other overhead of this item %
Villa Clean :
out internally and externally from dust and polish flooring fitting
BY SPECIALIST
PROVISIONAL Sum AED 15,000/-
- Allow for any profit, attendance, builders work and other overhead of this item %
Lift :
- allow provisional amount for lift
PROVISIONAL Sum AED 160,000
- Allow for any profit, Attendance. Builders work and other overhead %
LOW CURRENT :
- allow provisional amount for low current system by Smart Home
PROVISIONAL Sum AED 80,000
CCTV System
Access Point System
Telephone System
Intercom System
Satellite System
Structural Data Cabling
- Allow for any profit, Attendance. Builders work and other overhead %
HVAC :
- allow provisional amount for air conditioning and ventilation system
- Allow for any profit, Attendance. Builders work and other overhead %
- Allow for any profit, Attendance. Builders work and other overhead %
KITCHEN :
- Supply and installation Kitchen cabinet including sink and mixer
- Allow for any profit, Attendance. Builders work and other overhead %
- Allow for any profit, Attendance. Builders work and other overhead %
Notes:
2. Since the agreement is for the lump sum priced contract, the quantities mentioned in this BOQ
will be referred only for the purpose of tender analysis. No re measurement of work shall be made
at site.
3. Any future variation will be scrutinized based on the unit rates quoted in this BOQ and as per the
condition of contract.
4. The items mentioned in this BOQ is considered for the best quality of material - English make,
The make and choice is up to the consultant unless it is clearly mentioned by the contractor along
with the item or a list of proposed material is attached along with this BOQ. The unit rate quoted
will not be considered for the selection of material.
5. Contractor has to submit detailed breakdown for all the lump sum items mentioned in this BOQ.
6. Any item of work not included in this B.O.Q which is essential for the satisfactory completion
of the project, the contractor has to add the same in this list or to be considered elsewhere in their
offer.