Accounting 7 07 Cost Acctg Cost Management
Accounting 7 07 Cost Acctg Cost Management
Accounting 7 07 Cost Acctg Cost Management
Cubao-Fairview-Taytay
FIRST SEMESTER SY 2015-2016
FINAL DEPARTMENTAL EXAMINATIONS 3 HRS
ACCOUNTING 7 – 07 COST ACCOUNTING & COST MANAGEMENT
INSTRUCTIONS: Select the correct answer for each of the following questions. Mark only one answer for each
item by shading the corresponding letter of your choice on the answer sheet provided. STRICTLY NO
ERASURES ALLOWED. Use Pencil No. 2 only.
4. Conventional and just-in-time manufactures differ in that the conventional manufacturer is likely to
A. be a new entrant into its industry.
B. need less storage space than its JIT competitors.
C. give less credibility to management accounting reports.
D. have a longer production cycle than its JIT competitors.
6. How many units are in ending work in process inventory in the first processing department at the end of
the month?
A) 7,600 B) 900 C) 1,700 D) 900
ACCOUNTING 7 – 07 COST ACCOUNTING & COST MANAGEMENT
7. What are the equivalent units for conversion costs for the month in the first processing department?
A) 9,200 B) 8,520 C) 7,500 D) 1,020
8. The cost per equivalent unit for materials for the month in the first processing department is closest to:
A) P21.44 B) P21.96 C) P20.25 D) P23.25
9. The cost per equivalent unit for conversion costs for the first department for the month is closest to:
A) P41.59 B) P38.71 C) P39.61 D) P36.68
10. The cost per equivalent whole unit for the month in the first processing department is closest to:
A) P71.93 B) P62.86 C) P58.64 D) P66.63
11. The total cost transferred from the first processing department to the next processing department during
the month is closest to:
A) P516,100 B) P471,435 C) P539,500 D) P578,294
12. The cost of ending work in process inventory in the first processing department according to the
company's cost system is closest to:
A) P68,067 B) P64,115 C) P74,801 D) P106,859
13. The equivalent units for labor and overhead for June, using the FIFO method, were:
A) 46,000 units B) 49,800 units C) 43,200 units D) 52,600 units
14. The equivalent units for labor and overhead for June, using the weighted-average method, were:
A) 52,600 units B) 62,000 units C) 50,000 units D) 46,000 units
15. The equivalent units for materials for June, using the FIFO method, were:
A) 46,000 units B) 42,000 units C) 58,000 units D) 50,000 units
16. The equivalent units for materials for June, using the weighted-average method, were:
A) 58,000 units B) 52,600 units C) 46,000 units D) 60,000 units
17. The amount of direct material purchased during the year was:
A) P66,000 B) P70,000 C) P65,000 D) P74,000
Page 2 of 7
ACCOUNTING 7 – 07 COST ACCOUNTING & COST MANAGEMENT
18. The total costs added to Work in Process during the year were:
A) P206,000 B) P162,000 C) P176,000 D) P182,000
19. If Omar Company applies overhead to jobs on the basis of direct labor hours and Job 3 took 120 hours,
how much overhead should be applied to that job?
A) P960 B) P360 C) P528 D) P288
20. The cost of goods manufactured for the year was:
A) P190,000 B) P162,000 C) P168,000 D) P135,000
21. If the company bases its predetermined overhead rate on estimated machine-hours, then its
predetermined overhead rate would have been:
A) P6.27 B) P7.00 C) P5.00 D) P6.33
22. If the company bases its predetermined overhead rate on estimated machine-hours, then its overhead
for the year would have been:
A) P12,800 overapplied C) P7,400 overapplied
B) P12,800 underapplied D) P7,400 underapplied
23. If the company bases its predetermined overhead rate on machine-hours at capacity, then its
predetermined overhead rate would have been:
A) P6.33 B) P6.27 C) P5.00 D) P7.00
24. If the company bases its predetermined overhead rate on machine-hours at capacity, then the cost of
unused capacity reported on the income statement would have been:
A) P700 B) P7,400 C) P6,700 D) P12,800
26. The applied manufacturing overhead for the year is closest to:
A) P136,269 B) P138,348 C) P136,987 D) P137,630
28. The predetermined overhead rate for the year was closest to:
A) P34.95 B) P34.83 C) P34.98 D) P35.10
Page 3 of 7
ACCOUNTING 7 – 07 COST ACCOUNTING & COST MANAGEMENT
29. The applied manufacturing overhead for the year was closest to:
A) P208,283 B) P209,001 C) P209,898 D) P209,180
37. What is Kapanga's work in process inventory balance at the end of October?
A) P23,000 B) P30,500 C) P32,000 D) P43,000
Page 4 of 7
ACCOUNTING 7 – 07 COST ACCOUNTING & COST MANAGEMENT
The General Factory activity cost pool's costs are allocated on the basis of direct labor hours.
38. The predetermined overhead rate under the traditional costing system is closest to:
A. P 21.00 B. P14.21 C. P111.09 D. P50.51
39. The overhead cost per unit of Product A under the traditional costing system is closest to:
A. P10.50 B. P55.55 C. P25.26 D. P7.11
40. The predetermined overhead rate (i.e., activity rate) for Activity 1 under the activity based costing
system is closest to:
A. P27.00 B. P94.50 C. P21.00 D. P70.36
41. The overhead cost per unit of Product A under the activity-based costing system is closest to:
A. P25.26 B. P73.44 C. P42.21 D. P55.55
The following information pertains to the three product lines for next year:
Economy Standard Deluxe
Units produced 10,000 5,000 2,000
Orders Shipped 1,000 500 200
Number of parts per unit 10 15 25
Machine Hours per unit 1 3 5
Labor hours per unit 2 2 2
43. What is HiTech's pool rate for the automated machinery activity?
A. P24.00/machine hour C. P49.42/unit
B. P24.50/labor hour D. P50.00/machine hour.
46. Under an activity-based costing system, what is the per-unit overhead cost of Economy?
A. P141 B. P164 C. P225 D. P228
47. Under an activity-based costing system, what is the per-unit overhead cost of Standard?
A. P164 B. P228 C. P272 D. P282.
48. Under an activity-based costing system, what is the per-unit overhead cost of Deluxe?
A. P272 B. P282 C. P320 D. P440
49. Assume that HiTech is using a volume-based costing system, and the preceding overhead costs are
applied to all products on the basis of direct labor hours. The overhead cost that would be assigned to
the Deluxe product line is closest to:
A. P 456,471 B. P 646,471 C. P 961,176 D. P 1,141,176
50. Assume that HiTech is using a volume-based costing system, and the preceding overhead costs are
applied to all products on the basis of direct labor hours. The overhead cost that would be assigned to
the Standard product line is closest to:
A. P 456,471 B. P 646,471 C. P 961,176 D. P 1,141,176
If X and Z are processed further, no disposal costs will be incurred or such costs will be borne by the
buyer.
51. Refer to Ratcliff Company. Using a physical measure, what amount of joint processing cost is allocated
to X (round to the nearest dollar)?
A. P4,000
B. P4,757
C. P5,500
D. P3,243
52. Refer to Ratcliff Company. Using a physical measure, what amount of joint processing cost is allocated
to Z (round to the nearest dollar)?
A. P4,000
B. P3,243
C. P5,500
D. P4,757
53. Refer to Ratcliff Company. Using sales value at split-off, what amount of joint processing cost is
allocated to X (round to the nearest dollar)?
A. P5,500
B. P2,500
C. P4,000
D. P3,243
54. Refer to Ratcliff Company. Using sales value at split-off, what amount of joint processing cost is
allocated to Z (round to the nearest dollar)?
A. P5,500
B. P4,000
C. P2,500
D. P4,757
Page 6 of 7
ACCOUNTING 7 – 07 COST ACCOUNTING & COST MANAGEMENT
55. Refer to Ratcliff Company. Using net realizable value at split-off, what amount of joint processing cost is
allocated to X (round to the nearest dollar)?
A. P4,000
B. P5,610
C. P2,390
D. P5,500
56. Refer to Ratcliff Company. Using net realizable value at split-off, what amount of joint processing cost is
allocated to Z (round to the nearest dollar)?
A. P5,500
B. P4,000
C. P2,390
D. P5,610
57. Refer to Ratcliff Company. Using approximated net realizable value at split-off, what amount of joint
processing cost is allocated to X (round to the nearest dollar)?
A. P3,090
B. P5,204
C. P4,000
D. P2,390
Actual:
Production 2,750 units produced during the month
Material 8,700 feet used; 9,000 feet purchased @ P4.50 per foot
Labor 7,000 direct labor hours @ P7.90 per hour
58. Refer to Marley Company. What is the material price variance (calculated at point of purchase)?
A. P2,700 U
B. P2,700 F
C. P2,610 F
D. P2,610 U
Page 7 of 7