UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Cement and sand (1:3)) (masjid) PAGE NO: 1/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
1 Cement and sand (1:3)
as described 350m2 Spirit level 1 skilled labor workers output 3 days
20mm Thick cement and = 2.5m2/hr
sand (1:3) as described Roller 5 general labor
paving with a troweled 2.5m2 x 6
smooth finishes to floor Bucket =15m2/hr
level on concrete base.
Trowel (350m2/15m2/h
r)/8hr = 2.92
days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 2/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
2 Supply and lay 300mm x
300mm x 8.5 mm thick 550m2 Pencil 1 skilled labor workers output 3 days
approved homogeneous = 4.7m2/hr
tiles as described Measuring 5 general labor
bedded, jointed and tape 4.7m2/h x 6 =
pointed in cement mortar 28.2m2/hr
(1:3) on cement and sand Spirit level
screed. (550m2/28.2m2
Trowel /hr)/8hr = 2.43
days
bucket
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 3/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
3 Ditto, skirting.
50m Pencil 1 skilled labor workers output 1 day
= 4.7m/hr
Measuring 2 general labor
tape 4.7m/h x 3
=14.1m/hr
Spirit level
(50m/14.1m/hr
Trowel )/8hr = 0.44
day
Bucket
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 4/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
4 Supply and lay 300mm x
300mm x 8.5 mm thick 680m2 Pencil 1 skilled labor workers output 4 days
approved ceramic tiles as = 4.7m2/hr
described bedded, Measuring 4 general labor
jointed and pointed in tape 4.7m2/h x 5 =
cement mortar (1:3) on 23.5m2/hr
cement and sand screed. Spirit level
(680m2/23.5
Trowel m2/hr)/8hr =
3.62 days
Bucket
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 5/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
5 Ditto, skirting
200m Pencil 1 skilled labor workers output 2 days
= 4.7m/hr
Measuring 2 general labor
tape 4.7m/h x 3
=14.1m/hr
Spirit level
(200m/14.1m/h
Trowel r)/8hr = 1.77
days
Bucket
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 6/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
6 Supply and lay carpet
with Islamic pattern with 350m2 Measuring 1 skilled labor workers output 2 days
high quality including tape = 4.7m2/hr
cement rendering 4 general labor
troweled smooth to floor Spirit level 4.7m2/h x 5
complete with adhesive =23.5m2/hr
all as per S.O's approval cutter
(350m2/23.5m2
/hr)/8hr = 1.86
days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 7/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
7 Supply and fix timber
skirting to architect 60m Measuring 1 skilled labor workers output 1 day
approval. tape = 4.7m/hr
2 general labor
Spirit level 4.7m/h x 3
=14.1m/hr
cutter
(60m/14.1m/hr
)/8hr = 0.53
day
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 8/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
8 Supply and lay approved
pebble wash on top of 320m2 Measuring 1 skilled labor workers output 3 days
slab of accordance tape = 2.7m2/hr
manufacturer's 4 general labor
instruction. Spirit level 5x2.7m2/h =
13.5m2/hr
Trowel
(320m2/13.5m2
Buckets /hr)/8hr = 2.96
days
UNION SIX CONSTRUCTION SDN. BHD.

METHOD STATEMENT FORM


TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK
PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019
ELEMENT: INTERNAL FLOOR FINISHES (Waterproofing system) (masjid) PAGE NO: 9/9

NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION


TOOL LABOUR
9 Waterproofing system
type Brush bond 170m2 Spirit level 1 skilled labor workers output 2 days
Cementitious waterproof = 3.5m2/hr
slurry as specified and Roller 4 general labor
laying to floor and apply 2.5m2 x 5 =
strictly to the entire Bucket 12.5m2/hr
satisfaction of the
Superintending Officer (170m2/12.5m2
and manufacturers /hr)/8hr = 1.7
printed instruction to: days
Wudhuk area