The document is a method statement form outlining the internal floor finishing works for a proposed new mosque. It provides details of 6 tasks involving installing cement and sand screed, floor tiles, skirting, and carpet over 350 square meters in 3 sentences or less:
Task 1 involves laying a 20mm thick cement and sand screed over 350 square meters requiring 3 days to complete with 6 laborers. Task 2 is to install 550 square meters of floor tiles over 2 days with 6 laborers. Task 6 is installing 350 square meters of carpet with Islamic patterns over 2 days with 5 laborers.
The document is a method statement form outlining the internal floor finishing works for a proposed new mosque. It provides details of 6 tasks involving installing cement and sand screed, floor tiles, skirting, and carpet over 350 square meters in 3 sentences or less:
Task 1 involves laying a 20mm thick cement and sand screed over 350 square meters requiring 3 days to complete with 6 laborers. Task 2 is to install 550 square meters of floor tiles over 2 days with 6 laborers. Task 6 is installing 350 square meters of carpet with Islamic patterns over 2 days with 5 laborers.
The document is a method statement form outlining the internal floor finishing works for a proposed new mosque. It provides details of 6 tasks involving installing cement and sand screed, floor tiles, skirting, and carpet over 350 square meters in 3 sentences or less:
Task 1 involves laying a 20mm thick cement and sand screed over 350 square meters requiring 3 days to complete with 6 laborers. Task 2 is to install 550 square meters of floor tiles over 2 days with 6 laborers. Task 6 is installing 350 square meters of carpet with Islamic patterns over 2 days with 5 laborers.
The document is a method statement form outlining the internal floor finishing works for a proposed new mosque. It provides details of 6 tasks involving installing cement and sand screed, floor tiles, skirting, and carpet over 350 square meters in 3 sentences or less:
Task 1 involves laying a 20mm thick cement and sand screed over 350 square meters requiring 3 days to complete with 6 laborers. Task 2 is to install 550 square meters of floor tiles over 2 days with 6 laborers. Task 6 is installing 350 square meters of carpet with Islamic patterns over 2 days with 5 laborers.
Download as DOCX, PDF, TXT or read online from Scribd
Download as docx, pdf, or txt
You are on page 1of 9
UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Cement and sand (1:3)) (masjid) PAGE NO: 1/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 1 Cement and sand (1:3) as described 350m2 Spirit level 1 skilled labor workers output 3 days 20mm Thick cement and = 2.5m2/hr sand (1:3) as described Roller 5 general labor paving with a troweled 2.5m2 x 6 smooth finishes to floor Bucket =15m2/hr level on concrete base. Trowel (350m2/15m2/h r)/8hr = 2.92 days UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 2/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 2 Supply and lay 300mm x 300mm x 8.5 mm thick 550m2 Pencil 1 skilled labor workers output 3 days approved homogeneous = 4.7m2/hr tiles as described Measuring 5 general labor bedded, jointed and tape 4.7m2/h x 6 = pointed in cement mortar 28.2m2/hr (1:3) on cement and sand Spirit level screed. (550m2/28.2m2 Trowel /hr)/8hr = 2.43 days bucket UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 3/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 3 Ditto, skirting. 50m Pencil 1 skilled labor workers output 1 day = 4.7m/hr Measuring 2 general labor tape 4.7m/h x 3 =14.1m/hr Spirit level (50m/14.1m/hr Trowel )/8hr = 0.44 day Bucket UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 4/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 4 Supply and lay 300mm x 300mm x 8.5 mm thick 680m2 Pencil 1 skilled labor workers output 4 days approved ceramic tiles as = 4.7m2/hr described bedded, Measuring 4 general labor jointed and pointed in tape 4.7m2/h x 5 = cement mortar (1:3) on 23.5m2/hr cement and sand screed. Spirit level (680m2/23.5 Trowel m2/hr)/8hr = 3.62 days Bucket UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 5/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 5 Ditto, skirting 200m Pencil 1 skilled labor workers output 2 days = 4.7m/hr Measuring 2 general labor tape 4.7m/h x 3 =14.1m/hr Spirit level (200m/14.1m/h Trowel r)/8hr = 1.77 days Bucket UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 6/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 6 Supply and lay carpet with Islamic pattern with 350m2 Measuring 1 skilled labor workers output 2 days high quality including tape = 4.7m2/hr cement rendering 4 general labor troweled smooth to floor Spirit level 4.7m2/h x 5 complete with adhesive =23.5m2/hr all as per S.O's approval cutter (350m2/23.5m2 /hr)/8hr = 1.86 days UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 7/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 7 Supply and fix timber skirting to architect 60m Measuring 1 skilled labor workers output 1 day approval. tape = 4.7m/hr 2 general labor Spirit level 4.7m/h x 3 =14.1m/hr cutter (60m/14.1m/hr )/8hr = 0.53 day UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Floor Tiles) (masjid) PAGE NO: 8/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 8 Supply and lay approved pebble wash on top of 320m2 Measuring 1 skilled labor workers output 3 days slab of accordance tape = 2.7m2/hr manufacturer's 4 general labor instruction. Spirit level 5x2.7m2/h = 13.5m2/hr Trowel (320m2/13.5m2 Buckets /hr)/8hr = 2.96 days UNION SIX CONSTRUCTION SDN. BHD.
METHOD STATEMENT FORM
TITLE OF PROJECT: CADANGAN MEMBINA MASJID BARU DI BANDAR UNIVERSITI SERI ISKANDAR PERAK PREPARED BY: MUHAMMAD NUR IRZUAN BIN M SANI DATE:1/11/2019 ELEMENT: INTERNAL FLOOR FINISHES (Waterproofing system) (masjid) PAGE NO: 9/9
NO TASK QUANTITY SEQUENTIAL DIAGRAM MACHINERY/ MANPOWER/ OUTPUT DURATION
TOOL LABOUR 9 Waterproofing system type Brush bond 170m2 Spirit level 1 skilled labor workers output 2 days Cementitious waterproof = 3.5m2/hr slurry as specified and Roller 4 general labor laying to floor and apply 2.5m2 x 5 = strictly to the entire Bucket 12.5m2/hr satisfaction of the Superintending Officer (170m2/12.5m2 and manufacturers /hr)/8hr = 1.7 printed instruction to: days Wudhuk area