Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Bind PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 340

8.

0 ATTACHMENTS

8.1 Shop Drawings and Submittal Status


22 Dec.,2014

King Faisal Medical City(South) Phase 01 MAIN HOSPITAL


MASTER SHOP DRAWING SUBMISSION SUMMARY
TOTAL REVISED DWG
TOTAL NEW DWG
PLANNED TOTAL SUBMITTED TOTAL APPROVED APPROVED AS PER TOTAL UNDER TOTAL
S. N. DISCIPLINE SUB - DISCIPLINE DRAWINGS TOTAL APPROVED UNDER A B C D N
DRAWING AS PER PLANNED AS PER PLANNED SUBMITTED UNDER REVIEW REVIEW
SUBMITTED REVIEW
(%) (%) (%)

Architectural Architectural
01 744 302 40.59% 27.55% 67.88% 205 0 0 0 0 205 84 13 0
& Landscape & Landscape
Structural Structural
02 714 725 101.54% 84.87% 83.59% 606 0 0 0 6 600 101 2 16
& Civil & Civil
03 Mechanical 300 218 72.67% 61.33% 84.40% 184 0 0 0 0 184 33 1 0

04 Mechanical Plumbing 329 46 13.98% 12.46% 89.13% 41 0 0 0 0 41 5 0 0

05 Fire fighting 194 39 20.10% 12.89% 100.00% 25 0 0 0 0 39 0 0 0

06 Electrical-POWER 427 294 68.85% 63.47% 92.18% 271 0 0 0 0 271 22 0 1


Electrical
07 Electrical-LC 813 382 46.99% 44.03% 93.72% 358 0 0 0 0 358 24 0 0

TOTAL 3521 2006 56.97% 48.00% 84.95% 1690 0 0 0 6 1698 269 16 17 2006

A-APPROVED,B-APPROVED AS NOTED,C-NOT APPROVED REVISE & RESUBMIT,D-REJECTD,N-NOTED


8.0ATTACHMENTS
This Month Total Drawings was Submitted
22 Dec.,2014

King Faisal Medical City(South) Phase 01 MAIN HOSPITAL


SHOP DRAWING SUBMISSION SUMMARY (24 Nov. 2014 to 22 Dec.2014)
TOTAL REVISED DWG NEW DWG
TOTAL
APPROVED AS PER TOTAL TOTAL UNDER TOTAL
S. N. DISCIPLINE SUB - DISCIPLINE DRAWINGS UNDER A B C D N
SUBMITTED APPROVED UNDER REVIEW REVIEW
SUBMITTED REVIEW
(%)

01
Architectural Architectural
0 #DIV/0! 0 0 0 0 0 0 0 0 0
& Landscape & Landscape

02
Structural Structural
28 89.29% 25 0 0 0 0 25 3 0 0
& Civil & Civil
03 Mechanical 26 84.62% 22 0 0 0 0 22 4 0 0
04 Mechanical Plumbing 0 #DIV/0! 0 0 0 0 0 0 0 0 0
05 Fire fighting 0 #DIV/0! 25 0 0 0 0 0 0 0 0
06 Electrical-POWER 32 75.00% 24 0 0 0 0 24 8 0 0
Electrical
07 Electrical-LC 23 34.78% 8 0 0 0 0 8 15 0 0
TOTAL 109 72.48% 104 0 0 0 0 79 30 0 0 109

A-APPROVED,B-APPROVED AS NOTED,C-NOT APPROVED REVISE & RESUBMIT,D-REJECTD,N-NOTED


23 October,2014

KFMC - Phase 01 Advance IFC(Shop) Drawing Summary - Structural(24 Nov. 2014 to 22 Dec.2014)

Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

TOTAL RESUBMITTAL
00

01

02

03

04

05

06

07
ZFP Review

Received Date

Actual date
Dedline
Group
Trade

Level

DWG
Zone

DWG
Area
Sr.

RESUBMIT UR
Date

NEW DWG UR
N0.
Transmittal No.FTCO ZFP Transmittal Drawing Number Drawing name Package Remark
No.
Date Date Date Date Date Date Date
Status A B C D N
Status Status Status Status Status Status Status

FT-ZP-TRN-AA-0127 CALC RECEVIED ON


ZP-FT-TRN-MS-0001
FT-ZP-TRN-AA-0001 14\11\12 01\12\12 10\09\14 16\10\14 03\12\14 27\11\12 REVIEWED
ZP-FT-TRN-KH-0791
1 FT-ZP-TRN-AA-0835 892-1-KF01-FT-SH-T-GL-Z00-S-S02-2080 TOWER CRANE LOCATION & COORDINATE TOWER CRAN S T Z00 GL S02 2080 27\11\12 04\12\12 16\09\14 22\10\14 08\12\14 03\12\14 11\12\14 08\12\14 NOT APPROVED C ONLY DRAWING,
ZP-FT-TRN-KH-0825
FT-ZP-TRN-AA-0885 CODE B CODE B CODE C CODE C CODE C CALC RELESED ON
ZP-FT-TRN-RA-0893
FT-ZP-TRN-AA-0955 10\12\12 AS CODE B
FT-ZP-TRN-AA-0023 ZP-FT-TRN-MS-0023 20\02\13 29\09\13 14\12\14
1 FT-ZP-TRN-AA-0144 ZP-FT-TRN-AM-0122 892-1-KF01-FT-SH-H-PL-Z00-S-S04-2100 SOG PLAN PODIUM LEVEL PHASE -01 SOG PLAN S H Z00 PL S04 2100 24\02\13 07\10\13 17\12\14 14\12\14 22\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0953 ZP-FT-TRN-RA-0913 CODE C CODE B CODE B
FT-ZP-TRN-AA-0023 ZP-FT-TRN-MS-0023 20\02\13 29\09\13 14\12\14
1 FT-ZP-TRN-AA-0144 ZP-FT-TRN-AM-0122 892-1-KF01-FT-SH-H-PL-Z01-S-S04-2101 SOG PLAN PODIUM LEVEL PHASE -01 (PART 01) SOG PLAN S H Z01 PL S04 2101 24\02\13 07\10\13 17\12\14 14\12\14 22\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0953 ZP-FT-TRN-RA-0913 CODE C CODE B CODE B
FT-ZP-TRN-AA-0023 ZP-FT-TRN-MS-0023 20\02\13 29\09\13 14\12\14
1 FT-ZP-TRN-AA-0144 ZP-FT-TRN-AM-0122 892-1-KF01-FT-SH-H-PL-Z02-S-S04-2102 SOG PLAN PODIUM LEVEL PHASE -01 (PART 02) SOG PLAN S H Z02 PL S04 2102 24\02\13 07\10\13 17\12\14 14\12\14 22\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0953 ZP-FT-TRN-RA-0913 CODE C CODE B CODE B
FT-ZP-TRN-AA-0023 ZP-FT-TRN-MS-0023 20\02\13 29\09\13 14\12\14
1 FT-ZP-TRN-AA-0144 ZP-FT-TRN-AM-0122 892-1-KF01-FT-SH-H-PL-Z03-S-S04-2103 SOG PLAN PODIUM LEVEL PHASE -01 (PART 03) SOG PLAN S H Z03 PL S04 2103 24\02\13 07\10\13 17\12\14 14\12\14 22\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0953 ZP-FT-TRN-RA-0913 CODE C CODE B CODE B
FT-ZP-TRN-AA-0023 ZP-FT-TRN-MS-0023 20\02\13 29\09\13 14\12\14
1 FT-ZP-TRN-AA-0144 ZP-FT-TRN-AM-0122 892-1-KF01-FT-SH-H-PL-Z04-S-S04-2104 SOG PLAN PODIUM LEVEL PHASE -01 (PART 04) SOG PLAN S H Z04 PL S04 2104 24\02\13 07\10\13 17\12\14 14\12\14 22\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0953 ZP-FT-TRN-RA-0913 CODE C CODE B CODE B
FT-ZP-TRN-AA-0023 ZP-FT-TRN-MS-0023 20\02\13 29\09\13 14\12\14
1 FT-ZP-TRN-AA-0144 ZP-FT-TRN-AM-0122 892-1-KF01-FT-SH-H-PL-Z05-S-S04-2105 SOG PLAN PODIUM LEVEL PHASE -01 (PART 05) SOG PLAN S H Z05 PL S04 2105 24\02\13 07\10\13 17\12\14 14\12\14 22\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0953 ZP-FT-TRN-RA-0913 CODE C CODE B CODE B
FT-ZP-TRN-AA-0023 ZP-FT-TRN-MS-0023 20\02\13 29\09\13 14\12\14
1 FT-ZP-TRN-AA-0144 ZP-FT-TRN-AM-0122 892-1-KF01-FT-SH-H-PL-Z06-S-S04-2106 SOG PLAN PODIUM LEVEL PHASE -01 (PART 06) SOG PLAN S H Z06 PL S04 2106 24\02\13 07\10\13 17\12\14 14\12\14 22\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0953 ZP-FT-TRN-RA-0913 CODE C CODE B CODE B
FT-ZP-TRN-AA-0128 ZP-FT-TRN-EG-0150 TRANSVERSE BEAM ELEVATION REINFORCEMENT TRANSVERSE 24\09\13 06\08\14 10\12\14
1 FT-ZP-TRN-AA-0759 ZP-FT-TRN-ME-0700 892-1-KF01-FT-SH-H-03-Z00-S-S05-2234 DETAIL LEVEL-03 S H Z00 03 S05 2234 30\10\13 12\08\14 11\12\14 10\12\14 18\12\14 11\12\14 APPROVED AS NOTED B
BEAM
FT-ZP-TRN-HE-0974 ZP-FT-TRN-FL-0905 PHASE-1 (1 of 4) CODE B CODE B CODE B
FT-ZP-TRN-AA-0175 ZP-FT-TRN-AM-0137
FT-ZP-TRN-HE-0639 ZP-FT-TRN-FL-0581 09\10\13 25\05\14 05\06\14 06\07\14 30\11\14
FOUNDATION REBAR PLAN (TOP & BOTTOM STEEL FOUNDATION
1 FT-ZP-TRN-HE-0667 ZP-FT-TRN-FL-0610 892-1-KF01-FT-SH-H-GL-Z01-S-S11-2273 S H Z01 GL S11 2273 22\10\13 27\05\14 09\06\14 08\07\14 01\12\14 30\11\14 08\12\14 01\12\14 APPROVED AS NOTED B
GROUND FLOOR LEVEL PHASE -01 (PART -01) REBAR PLAN
FT-ZP-TRN-AA-0702 ZP-FT-TRN-RA-0643 CODE B CODE C CODE C CODE B CODE B
FT-ZP-TRN-HE-0943 ZP-FT-TRN-RA-0876
FT-ZP-TRN-AA-0175 ZP-FT-TRN-AM-0137
FT-ZP-TRN-HE-0639 ZP-FT-TRN-FL-0581 09\10\13 25\05\14 05\06\14 06\07\14 30\11\14
FOUNDATION REBAR PLAN (TOP & BOTTOM STEEL FOUNDATION
1 FT-ZP-TRN-HE-0667 ZP-FT-TRN-FL-0610 892-1-KF01-FT-SH-H-GL-Z01-S-S11-2274 S H Z02 GL S11 2274 22\10\13 27\05\14 09\06\14 08\07\14 01\12\14 30\11\14 08\12\14 01\12\14 APPROVED AS NOTED B
GROUND FLOOR LEVEL PHASE -01 (PART -02) REBAR PLAN
FT-ZP-TRN-AA-0702 ZP-FT-TRN-RA-0643 CODE B CODE C CODE C CODE B CODE B
FT-ZP-TRN-HE-0943 ZP-FT-TRN-RA-0876
FT-ZP-TRN-AA-0175 ZP-FT-TRN-AM-0137
FT-ZP-TRN-HE-0639 ZP-FT-TRN-FL-0581 09\10\13 25\05\14 05\06\14 06\07\14 30\11\14
FOUNDATION REBAR PLAN (TOP & BOTTOM STEEL FOUNDATION
1 FT-ZP-TRN-HE-0667 ZP-FT-TRN-FL-0610 892-1-KF01-FT-SH-H-GL-Z01-S-S11-2275 S H Z02 GL S11 2275 22\10\13 27\05\14 09\06\14 08\07\14 01\12\14 30\11\14 08\12\14 01\12\14 APPROVED AS NOTED B
GROUND FLOOR LEVEL PHASE -01 (PART -03) REBAR PLAN
FT-ZP-TRN-AA-0702 ZP-FT-TRN-RA-0643 CODE B CODE C CODE C CODE B CODE B
FT-ZP-TRN-HE-0943 ZP-FT-TRN-RA-0876
FT-ZP-TRN-AA-0692 ZP-FT-TRN-FL-0636
CORE 18-STAIR CASE PLAN AND SECTION 30\06\14 09\07\14 17\07\14 17\12\14
FT-ZP-TRN-AA-0713 ZP-FT-TRN-ME-0661
1 892-1-KF01 -FT-SH-H-ST -Z00-S-S15-2545 REINFORCEMENT DETAIL STAIRCASE S H Z00 ST S15 2545 02\07\14 10\07\14 23\07\14 17\12\14 17\12\14 25\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-AA-0742 ZP-FT-TRN-KH-0680
( 1ST FLOOR TO 3RD FLOOR) CODE C CODE C CODE B CODE B
FT-ZP-TRN-HE-0986 ZP-FT-TRN-RA-0916

FT-ZP-TRN-AA-0692 ZP-FT-TRN-FL-0636
CORE 19-STAIR CASE PLAN AND SECTION 30\06\14 09\07\14 17\07\14 17\12\14
FT-ZP-TRN-AA-0713 ZP-FT-TRN-ME-0661
1 892-1-KF01 -FT-SH-H-ST -Z00-S-S15-2546 REINFORCEMENT DETAIL STAIRCASE S H Z00 ST S15 2546 02\07\14 10\07\14 23\07\14 17\12\14 17\12\14 25\12\14 17\12\14 APPROVED AS NOTED B
FT-ZP-TRN-AA-0742 ZP-FT-TRN-KH-0680
( 1ST FLOOR TO 3RD FLOOR) CODE C CODE C CODE B CODE B
FT-ZP-TRN-HE-0986 ZP-FT-TRN-RA-0916
FT-ZP-TRN-AA-0699 ZP-FT-TRN-ME-0641
FT-ZP-TRN-AA-0738 'ZP-FT-TRN-ME-0671
FT-ZP-TRN-AA-0750 'ZP-FT-TRN-ME-0683 WAFFLE DOMES LAYOUT FOR 06\07\14 16\07\14 04\08\14 19\08\14 04\09\14 16\10\14 21\10\14 30\11\14
1 FT-ZP-TRN-AA-0784 'ZP-FT-TRN-RA-0722 892-1-KF01-FT-SH-H-03-Z00-S-S04-2939 LEVEL-03 PHASE-1 (1OF2) S H Z00 03 S04 2939 08\07\14 17\07\14 05\08\14 21\08\14 04\09\14 19\10\14 22\10\14 02\12\14 30\11\14 08\12\14 02\12\14 APPROVED AS NOTED B
FT-ZP-TRN-AA-0819 'ZP-FT-TRN-FL-0750 CODE C CODE B CODE B CODE C CODE B CODE B CODE B CODE B
FT-ZP-TRN-AA-0883 'ZP-FT-TRN-FL-0816
FT-ZP-TRN-AA-0895 'ZP-FT-TRN-FL-0824
FT-ZP-TRN-HE-0945 'ZP-FT-TRN-FL-0878
FT-ZP-TRN-AA-0699 ZP-FT-TRN-ME-0641
FT-ZP-TRN-AA-0738 'ZP-FT-TRN-ME-0671
FT-ZP-TRN-AA-0750 'ZP-FT-TRN-ME-0683 WAFFLE DOMES LAYOUT FOR 06\07\14 16\07\14 04\08\14 19\08\14 04\09\14 16\10\14 21\10\14 30\11\14
1 FT-ZP-TRN-AA-0784 'ZP-FT-TRN-RA-0722 892-1-KF01-FT-SH-H-03-Z00-S-S04-2940 LEVEL-03 PHASE-1 (2OF2) S H Z00 03 S04 2940 08\07\14 17\07\14 05\08\14 21\08\14 04\09\14 19\10\14 22\10\14 02\12\14 30\11\14 08\12\14 02\12\14 APPROVED AS NOTED B
FT-ZP-TRN-AA-0819 'ZP-FT-TRN-FL-0750 CODE C CODE B CODE B CODE C CODE B CODE B CODE B CODE B
FT-ZP-TRN-AA-0883 'ZP-FT-TRN-FL-0816
FT-ZP-TRN-AA-0895 'ZP-FT-TRN-FL-0824
FT-ZP-TRN-HE-0945 'ZP-FT-TRN-FL-0878
FT-ZP-TRN-AA-0740 ZP-FT-TRN-ME-0676
FT-ZP-TRN-AA-0871 'ZP-FT-TRN-KH-0804 17\07\14 24\09\14 30\09\14 17\11\14 01\12\14
CONSTRUCTION JOINT FOR LEVEL-03 FLOOR SLAB-
1 FT-ZP-TRN-AA-0875 'ZP-FT-TRN-ME-0813 892-1-KF01-FT-SH-H-03-Z00-S-S04-2969 S H Z00 03 S04 2969 20\07\14 25\09\14 02\10\14 18\11\14 02\12\14 01\12\14 09\12\14 02\12\14 APPROVED AS NOTED B
PHASE-1
FT-ZP-TRN-AA-0927 'ZP-FT-TRN-ME-0858 CODE B CODE C CODE B CODE B CODE B
FT-ZP-TRN-AA-0950 'ZP-FT-TRN-ME-0879
FT-ZP-TRN-AA-0760 ZP-FT-TRN-ME-0696 ADDITIONAL TRANSVERSE BEAM ELEVATION 06\08\14 10\12\14
1 892-1-KF01-FT-SH-H-03-Z00-S-S05-2980 S H Z00 03 S04 2980 10\08\14 15\12\14 10\12\14 18\12\14 15\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0975 'ZP-FT-TRN-RA-0909 REINFORCEMENT DETAIL LEVEL-03 PHASE-1(7of 7)
CODE B CODE B
CONSTRUCTION JOINT FOR LEVEL-04 FLOOR SLAB- 26\11\14
1 FT-ZP-TRN-HE-0942 ZP-FT-TRN-ME-0871 892-1-KF01-FT-SH-H-04-Z00-S-S04-3043 S H Z00 04 S04 3043 27\11\14 26\11\14 07\12\14 27\11\14 APPROVED AS NOTED B
PHASE-1
CODE B
FT-ZP-TRN-AA-0909 ZP-FT-TRN-FL-0842 ADDITIONAL TRANSVERSE BEAM ELEVATION 27\10\14 08\12\14
1 892-1-KF01-FT-SH-H-04-Z00-S-S05-3045 REINFORCEMENT DETAIL LEVEL-04 AND S H Z00 04 S05 3045 02\11\14 10\12\14 08\12\14 16\12\14 10\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0966 'ZP-FT-TRN-FL-0901
MEZZANINE LEVEL-04 PHASE-1 (1OF1) CODE C CODE B
FT-ZP-TRN-HE-0914 ZP-FT-TRN-RA-0853 05\11\14 24\11\14 03\12\14
WAFFLE DOMES LAYOUT FOR LEVEL-05 PHASE-1 (1
1 FT-ZP-TRN-HE-0938 'ZP-FT-TRN-RA-0870 892-1-KF01-FT-SH-H-05-Z00-S-S04-3050 S H Z00 05 S04 3050 09\11\14 26\11\14 07\12\14 03\12\14 11\12\14 07\12\14 NOT APPROVED C
OF 2)
FT-ZP-TRN-HE-0946 'ZP-FT-TRN-RA-0891 CODE C CODE C CODE C
FT-ZP-TRN-HE-0914 ZP-FT-TRN-RA-0853 05\11\14 24\11\14 03\12\14
WAFFLE DOMES LAYOUT FOR LEVEL-05 PHASE-1 (2
1 FT-ZP-TRN-HE-0938 'ZP-FT-TRN-RA-0870 892-1-KF01-FT-SH-H-04-Z00-S-S04-3051 S H Z00 05 S04 3051 09\11\14 26\11\14 07\12\14 03\12\14 11\12\14 07\12\14 NOT APPROVED C
OF 2)
FT-ZP-TRN-HE-0946 'ZP-FT-TRN-RA-0891 CODE C CODE C CODE C
LONGITUDINAL BEAMS AND RIBS ELEVATIONS AND 23\11\14 03\12\14
FT-ZP-TRN-HE-0937 ZP-FT-TRN-RA-0868
1 892-1-KF01-FT-SH-H03-Z00-S-S05-3092 REINFORCEMENT DETAILS LEVEL-03 PHASE-1 S H Z00 03 S05 3092 25\11\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0958 'ZP-FT-TRN-RA-0887
GRID LINE M CODE C CODE B
CORE-12 GROUND FLOOR TO LEVEL-3 WALLS 25\11\14
1 FT-ZP-TRN-HE-0940 ZP-FT-TRN-RA-0873 892-1-KF01-FT-SH-H-SE-Z00-S-S16-3095 S H Z00 SE S16 3095 27\11\14 25\11\14 04\12\14 27\11\14 APPROVED AS NOTED B
SECTION, ELEVATION & REINFORCEMENT DETAILS.
CODE B
CORE-13 GROUND FLOOR TO LEVEL-3 WALLS 25\11\14
1 FT-ZP-TRN-HE-0940 ZP-FT-TRN-RA-0873 892-1-KF01-FT-SH-H-SE-Z00-S-S16-3096 S H Z00 SE S16 3096 27\11\14 25\11\14 04\12\14 27\11\14 APPROVED AS NOTED B
SECTION, ELEVATION & REINFORCEMENT DETAILS.
CODE B
03\12\14 08\12\14
FT-ZP-TRN-HE-0957 ZP-FT-TRN-FL-0886
1 892-1-KF01-FT-SH-H-PL-Z00-S- S10-3097 CORE 1 VALVE BOX SECTION S H Z00 PL S10 3097 04\12\14 09\12\14 08\12\14 16\12\14 09\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0972 'ZP-FT-TRN-FL-0899
CODE C CODE B
03\12\14 08\12\14
FT-ZP-TRN-HE-0957 ZP-FT-TRN-FL-0886
1 892-1-KF01-FT-SH-H-PL-Z00-S- S10-3098 CORE 2 VALVE BOX SECTION S H Z00 PL S10 3098 04\12\14 09\12\14 08\12\14 16\12\14 09\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0972 'ZP-FT-TRN-FL-0899
CODE C CODE B
FT-ZP-TRN-HE-0957 ZP-FT-TRN-FL-0886 03\12\14 08\12\14
1 892-1-KF01-FT-SH-H-PL-Z00-S- S10-3099 CORE 3 VALVE BOX SECTION S H Z00 PL S10 3099 04\12\14 09\12\14 08\12\14 16\12\14 09\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0972 'ZP-FT-TRN-FL-0899
CODE C CODE B
23 October,2014

KFMC - Phase 01 Advance IFC(Shop) Drawing Summary - Electrical-LC(24 Nov. 2014 to 22 Dec.2014)

Actual Received Date

TOTAL RESUBMITTAL
Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

Actual Relase date


ZFP Review

00

01

02

03

04

05

06

Dedline
Group
Trade

Level

DWG

DWG
Zone
Sr.

Area

Date
N0.
Transmittal No.FTCO ZFP Transmittal Drawing Number Drawing name Package Remark

RESUBMIT
NEW DWG
No.
Date Date Date Date Date Date Date

UR

UR
Status A B C D N
Status Status Status Status Status Status Status

08\12\14
Level 04 – FIRE ALARM System Layout
1 FT-ZP-TRN-HE-0971 ZP-FT-TRN-RC-0903 892-1-KF01-FT-SH-H-04-Z00-E-L10-7358 L H Z00 04 L10 7358 10\12\14 08\12\14 16\12\14 10\12\14 NOT APPROVED C
(All Parts)
CODE C
08\12\14
Level 04 - FIRE ALARM System Layout
1 FT-ZP-TRN-HE-0971 ZP-FT-TRN-RC-0903 892-1-KF01-FT-SH-H-04-Z01-E-L10-7359 L H Z01 04 L10 7359 10\12\14 08\12\14 16\12\14 10\12\14 NOT APPROVED C
(Part-01)
CODE C
08\12\14
Level 04 - FIRE ALARM System Layout
1 FT-ZP-TRN-HE-0971 ZP-FT-TRN-RC-0903 892-1-KF01-FT-SH-H-04-Z02-E-L10-7360 L H Z02 04 L10 7360 10\12\14 08\12\14 16\12\14 10\12\14 NOT APPROVED C
(Part-02)
CODE C
08\12\14
Level 04 - FIRE ALARM System Layout
1 FT-ZP-TRN-HE-0971 ZP-FT-TRN-RC-0903 892-1-KF01-FT-SH-H-04-Z03-E-L10-7361 L H Z03 04 L10 7361 10\12\14 08\12\14 16\12\14 10\12\14 NOT APPROVED C
(Part-03)
CODE C
08\12\14
Level 04 (MEZZANINE)– FIRE ALARM
1 FT-ZP-TRN-HE-0970 ZP-FT-TRN-RO-0900 892-1-KF01-FT-SH-H-04-Z00-E-L10-7362 L H Z00 04 L10 7362 08\12\14 08\12\14 16\12\14 08\12\14 NOT APPROVED C
System Layout (All Parts)
CODE C
08\12\14
Level 04 (MEZZANINE)– FIRE ALARM
1 FT-ZP-TRN-HE-0970 ZP-FT-TRN-RO-0900 892-1-KF01-FT-SH-H-04-Z01-E-L10-7363 L H Z01 04 L10 7363 08\12\14 08\12\14 16\12\14 08\12\14 NOT APPROVED C
System Layout (Part-01)
CODE C
08\12\14
Level 04 (MEZZANINE)– FIRE ALARM
1 FT-ZP-TRN-HE-0970 ZP-FT-TRN-RO-0900 892-1-KF01-FT-SH-H-04-Z03-E-L10-7364 L H Z03 04 L10 7364 08\12\14 08\12\14 16\12\14 08\12\14 NOT APPROVED C
System Layout (Part-03)
CODE C
02\12\14 08\12\14
FT-ZP-TRN-HE-0949 ZP-FT-TRN-KS-0881 LEVEL 05 - AUDIO VISUAL SYSTEM
1 892-1-KF01-FT-SH-H-05-Z00-E-L04-7370 L H Z00 05 L04 7370 03\12\14 09\12\14 08\12\14 16\12\14 09\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0969 ZP-FT-TRN-KS-0898 LAYOUT (ALL PARTS)
CODE C CODE B
02\12\14 08\12\14
FT-ZP-TRN-HE-0949 ZP-FT-TRN-KS-0881 LEVEL 05 - AUDIO VISUAL SYSTEM
1 892-1-KF01-FT-SH-H-05-Z01-E- L04-7371 L H Z01 05 L04 7371 03\12\14 09\12\14 08\12\14 16\12\14 09\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0969 ZP-FT-TRN-KS-0898 LAYOUT (PART-01)
CODE C CODE B
02\12\14 08\12\14
FT-ZP-TRN-HE-0949 ZP-FT-TRN-KS-0881 LEVEL 05 - AUDIO VISUAL SYSTEM
1 892-1-KF01-FT-SH-H-05-Z02-E- L04-7372 L H Z02 05 L04 7372 03\12\14 09\12\14 08\12\14 16\12\14 09\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0969 ZP-FT-TRN-KS-0898 LAYOUT (PART-02)
CODE C CODE B
02\12\14 08\12\14
FT-ZP-TRN-HE-0949 ZP-FT-TRN-KS-0881 LEVEL 05 - AUDIO VISUAL SYSTEM
1 892-1-KF01-FT-SH-H-05-Z03-E- L04-7373 L H Z03 05 L04 7373 03\12\14 09\12\14 08\12\14 16\12\14 09\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0969 ZP-FT-TRN-KS-0898 LAYOUT (PART-03)
CODE C CODE B
16\12\14
LEVEL 05 - MATV SYSTEM LAYOUT (ALL
1 FT-ZP-TRN-HE-0982 ZP-FT-TRN-FN-0914 892-1-KF01-FT-SH-H-05-Z00-E-L04-7374 17\12\14 16\12\14 24\12\14 17\12\14 NOT APPROVED C
PARTS)
CODE C
16\12\14
LEVEL 05 - MATV SYSTEM LAYOUT
1 FT-ZP-TRN-HE-0982 ZP-FT-TRN-FN-0914 892-1-KF01-FT-SH-H-05-Z01-E- L04-7375 17\12\14 16\12\14 24\12\14 17\12\14 NOT APPROVED C
(PART-01)
CODE C
16\12\14
LEVEL 05 - MATV SYSTEM LAYOUT
1 FT-ZP-TRN-HE-0982 ZP-FT-TRN-FN-0914 892-1-KF01-FT-SH-H-05-Z02-E- L04-7376 17\12\14 16\12\14 24\12\14 17\12\14 NOT APPROVED C
(PART-02)
CODE C
16\12\14
LEVEL 05 - MATV SYSTEM LAYOUT
1 FT-ZP-TRN-HE-0982 ZP-FT-TRN-FN-0914 892-1-KF01-FT-SH-H-05-Z03-E- L04-7377 17\12\14 16\12\14 24\12\14 17\12\14 NOT APPROVED C
(PART-03)
CODE C
14\12\14
Level – 05 – Nurse Call System Layout
1 FT-ZP-TRN-HE-0978 ZP-FT-TRN-KS-0912 892-1-KF01-FT-SH-H-05-Z00-E-L03-7386 L H Z00 05 L03 7386 16\12\14 14\12\14 22\12\14 16\12\14 NOT APPROVED C
(All Parts)
CODE C
14\12\14
Level – 05 – Nurse Call System Layout
1 FT-ZP-TRN-HE-0978 ZP-FT-TRN-KS-0912 892-1-KF01-FT-SH-H-05-Z01-E-L03-7387 L H Z01 05 L03 7387 16\12\14 14\12\14 22\12\14 16\12\14 NOT APPROVED C
(Part-01)
CODE C
14\12\14
Level – 05 – Nurse Call System Layout
1 FT-ZP-TRN-HE-0978 ZP-FT-TRN-KS-0912 892-1-KF01-FT-SH-H-05-Z02-E-L03-7388 L H Z02 05 L03 7388 16\12\14 14\12\14 22\12\14 16\12\14 NOT APPROVED C
(Part-02)
CODE C
14\12\14
Level – 05 – Nurse Call System Layout
1 FT-ZP-TRN-HE-0978 ZP-FT-TRN-KS-0912 892-1-KF01-FT-SH-H-05-Z03-E-L03-7389 L H Z03 05 L03 7389 16\12\14 14\12\14 22\12\14 16\12\14 NOT APPROVED C
(Part-03)
CODE C
02\12\14 09\12\14
FT-ZP-TRN-HE-0948 ZP-FT-TRN-KS-0882 Level – 05 – Master Clock System Layout
1 892-1-KF01-FT-SH-H-05-Z00-E-L03-7394 L H Z00 05 L03 7394 03\12\14 10\12\14 09\12\14 17\12\14 10\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0973 ZP-FT-TRN-KS-0904 (All Parts)
CODE C CODE B
02\12\14 09\12\14
FT-ZP-TRN-HE-0948 ZP-FT-TRN-KS-0882 Level – 05 – Master Clock System Layout
1 892-1-KF01-FT-SH-H-05-Z01-E-L03-7395 L H Z01 05 L03 7395 03\12\14 10\12\14 09\12\14 17\12\14 10\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0973 ZP-FT-TRN-KS-0904 (Part-01)
CODE C CODE B
02\12\14 09\12\14
FT-ZP-TRN-HE-0948 ZP-FT-TRN-KS-0882 Level – 05 – Master Clock System Layout
1 892-1-KF01-FT-SH-H-05-Z02-E-L03-7396 L H Z02 05 L03 7396 03\12\14 10\12\14 09\12\14 17\12\14 10\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0973 ZP-FT-TRN-KS-0904 (Part-02)
CODE C CODE B
02\12\14 09\12\14
FT-ZP-TRN-HE-0948 ZP-FT-TRN-KS-0882 Level – 05 – Master Clock System Layout
1 892-1-KF01-FT-SH-H-05-Z03-E-L03-7397 L H Z03 05 L03 7397 03\12\14 10\12\14 09\12\14 17\12\14 10\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0973 ZP-FT-TRN-KS-0904 (Part-03)
CODE C CODE B
23 October,2014

KFMC - Phase 01 Advance IFC(Shop) Drawing Summary- Machinical(24 Nov. 2014 to 22 Dec.2014)

TOTAL RESUBMITTAL
Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

Revsion
00

01

02

03

04

05

06
ZFP Review

Received Date

Actual date
Dedline
Group
Trade

Level

DWG

DWG
Zone
Sr.

Area

Date
N0.
Transmittal No.FTCO ZFP Transmittal Drawing Number Drawing name Package Remark

RESUBMIT
NEW DWG
No.
Date Date Date Date Date Date Date

UR

UR
Status A B C D N
Status Status Status Status Status Status Status

FT-ZP-TRN-HE-0414 ZP-FT-TRN-SA-0371 24\02\14 27\03\14 11\12\14


ELECTROMECHANICAL BUILDER WORK
1 FT-ZP-TRN-HE-0484 ZP-FT-TRN-SA-0443 892-1-KF01-SH-H-GL-Z00-M-M08-5051 M H Z00 GL M08 5051 26\02\14 27\03\14 11\12\14 11\12\14 21\12\14 11\12\14 APPROVED AS NOTED B
GROUND SLAB(ALL PARTS)
FT-ZP-TRN-HE-0977 ZP-FT-TRN-SA-0907 CODE B CODE B CODE B
FT-ZP-TRN-HE-0414 ZP-FT-TRN-SA-0371 24\02\14 27\03\14 11\12\14
ELECTROMECHANICAL BUILDER WORK
1 FT-ZP-TRN-HE-0484 ZP-FT-TRN-SA-0443 892-1-KF01-SH-H-GL-Z02-M-M08-5053 M H Z02 GL M08 5053 26\02\14 27\03\14 11\12\14 11\12\14 21\12\14 11\12\14 APPROVED AS NOTED B
GROUND SLAB( PART 02)
FT-ZP-TRN-HE-0977 ZP-FT-TRN-SA-0907 CODE B CODE B CODE B
03\12\14
ELECTRO MECHANICAL BUILDER’S WORK
1 FT-ZP-TRN-HE-0959 ZP-FT-TRN-SA-0889 892-1-KF01-FT-SH-H-05-Z00-M-M08-5332 M H Z00 04 M08 5332 04\12\14 03\12\14 11\12\\14 04\12\14 NOT APPROVED C
LEVEL-05 SLAB (ALL PARTS)
CODE C
03\12\14
ELECTRO MECHANICAL BUILDER’S WORK
1 FT-ZP-TRN-HE-0959 ZP-FT-TRN-SA-0889 892-1-KF01-FT-SH-H-05-Z01-M-M08-5333 M H Z01 04 M08 5333 04\12\14 03\12\14 11\12\\14 04\12\14 NOT APPROVED C
LEVEL-05 SLAB (PART 1)
CODE C
03\12\14
ELECTRO MECHANICAL BUILDER’S WORK
1 FT-ZP-TRN-HE-0959 ZP-FT-TRN-SA-0889 892-1-KF01-FT-SH-H-05-Z02-M-M08-5334 M H Z02 04 M08 5334 04\12\14 03\12\14 11\12\\14 04\12\14 NOT APPROVED C
LEVEL-05 SLAB (PART 2)
CODE C
03\12\14
ELECTRO MECHANICAL BUILDER’S WORK
1 FT-ZP-TRN-HE-0959 ZP-FT-TRN-SA-0889 892-1-KF01-FT-SH-H-05-Z03-M-M08-5335 M H Z03 04 M08 5335 04\12\14 03\12\14 11\12\\14 04\12\14 NOT APPROVED C
LEVEL-05 SLAB (PART 3)
CODE C
FT-ZP-TRN-AA-0888 ZP-FT-TRN-RS-0823 BUILDER WORK ELECTROMECHANICAL 20\10\14 02\11\14 03\12\14
1 FT-ZP-TRN-HE-0912 ZP-FT-TRN-RS-0845 892-1-KF01-FT-SH-H-04-Z00-M-M08-5336 OPENING AND SLEEVE, LEVEL 04 (SW-01) M H Z00 04 M08 5336 21\10\14 03\11\14 04\12\14 03\12\14 11\12\\14 04\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0931 ZP-FT-TRN-SA-0885 TO (SW-04) CODE C CODE C CODE B
FT-ZP-TRN-AA-0888 ZP-FT-TRN-RS-0823 BUILDER WORK ELECTROMECHANICAL 20\10\14 02\11\14 03\12\14
1 FT-ZP-TRN-HE-0912 ZP-FT-TRN-RS-0845 892-1-KF01-FT-SH-H-04-Z00-M-M08-5337 OPENING AND SLEEVE, LEVEL 04 (SW-05) M H Z00 04 M08 5337 21\10\14 03\11\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0931 ZP-FT-TRN-SA-0885 TO (SW-08) CODE C CODE C CODE B
FT-ZP-TRN-AA-0903 ZP-FT-TRN-RS-0832 26\10\14 02\11\14 03\12\14
ELECTRO MECHANICAL BUILDER’S WORK
1 FT-ZP-TRN-AA-0911 ZP-FT-TRN-RS-0844 892-1-KF01-FT-SH-H-04-Z00-M-M08-5338 M H Z00 04 M08 5338 27\10\14 03\11\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
LEVEL-04 MEZZANINE SLAB (ALL PARTS)
FT-ZP-TRN-HE-0932 ZP-FT-TRN-SA-0884 CODE C CODE C CODE B
FT-ZP-TRN-AA-0903 ZP-FT-TRN-RS-0832 26\10\14 02\11\14 03\12\14
ELECTRO MECHANICAL BUILDER’S WORK
1 FT-ZP-TRN-AA-0911 ZP-FT-TRN-RS-0844 892-1-KF01-FT-SH-H-04-Z01-M-M08-5339 M H Z01 04 M08 5339 27\10\14 03\11\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
LEVEL-04 MEZZANINE SLAB (PART 1)
FT-ZP-TRN-HE-0932 ZP-FT-TRN-SA-0884 CODE C CODE C CODE B
FT-ZP-TRN-AA-0903 ZP-FT-TRN-RS-0832 26\10\14 02\11\14 03\12\14
ELECTRO MECHANICAL BUILDER’S WORK
1 FT-ZP-TRN-AA-0911 ZP-FT-TRN-RS-0844 892-1-KF01-FT-SH-H-04-Z02-M-M08-5340 M H Z02 04 M08 5340 27\10\14 03\11\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
LEVEL-04 MEZZANINE SLAB (PART 2)
FT-ZP-TRN-HE-0932 ZP-FT-TRN-SA-0884 CODE C CODE C CODE B
FT-ZP-TRN-AA-0903 ZP-FT-TRN-RS-0832 26\10\14 02\11\14 03\12\14
ELECTRO MECHANICAL BUILDER’S WORK
1 FT-ZP-TRN-AA-0911 ZP-FT-TRN-RS-0844 892-1-KF01-FT-SH-H-04-Z03-M-M08-5341 M H Z03 04 M08 5341 27\10\14 03\11\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
LEVEL-04 MEZZANINE SLAB (PART 3)
FT-ZP-TRN-HE-0932 ZP-FT-TRN-SA-0884 CODE C CODE C CODE B
BUILDER WORK ELECTROMECHANICAL 26\11\14
1 FT-ZP-TRN-HE-0941 ZP-FT-TRN-SA-0872 892-1-KF01-FT-SH-H-06-Z00-M-M08-5347 OPENING AND SLEEVE, LEVEL 06 (SW-01) M H Z00 06 M08 5347 27\11\14 26\11\14 07\12\14 27\11\14 APPROVED AS NOTED B
TO (SW-04) CODE B
BUILDER WORK ELECTROMECHANICAL 26\11\14
1 FT-ZP-TRN-HE-0941 ZP-FT-TRN-SA-0872 892-1-KF01-FT-SH-H-06-Z00-M-M08-5348 OPENING AND SLEEVE, LEVEL 06 (SW-05) M H Z00 06 M08 5348 27\11\14 26\11\14 07\12\14 27\11\14 APPROVED AS NOTED B
TO (SW-08) CODE B
BUILDER WORK ELECTROMECHANICAL 30\11\14
1 FT-ZP-TRN-HE-0870 ZP-FT-TRN-SA-0874 892-1-KF01-FT-SH-H-07-Z00-M-M08-5349 OPENING AND SLEEVE, LEVEL 07 (SW-01) M H Z00 07 M08 5349 30\11\14 30\11\14 08\12\14 30\11\14 APPROVED AS NOTED B
TO (SW-04) CODE B
BUILDER WORK ELECTROMECHANICAL 30\11\14
1 FT-ZP-TRN-HE-0870 ZP-FT-TRN-SA-0874 892-1-KF01-FT-SH-H-07-Z00-M-M08-5350 OPENING AND SLEEVE, LEVEL 07 (SW-05) M H Z00 07 M08 5350 30\11\14 30\11\14 08\12\14 30\11\14 APPROVED AS NOTED B
TO (SW-08) CODE B
BUILDER WORK ELECTROMECHANICAL 02\12\14
1 FT-ZP-TRN-HE-0954 ZP-FT-TRN-SA-0880 892-1-KF01-FT-SH-H-08-Z00-M-M08-5355 OPENING AND SLEEVE, LEVEL 08 (SW-01) M H Z00 08 M08 5355 03\1\214 02\12\14 10\12\14 02\12\14 APPROVED AS NOTED B
TO (SW-04) CODE B
BUILDER WORK ELECTROMECHANICAL 02\12\14
1 FT-ZP-TRN-HE-0954 ZP-FT-TRN-SA-0880 892-1-KF01-FT-SH-H-08-Z00-M-M08-5356 OPENING AND SLEEVE, LEVEL 08 (SW-05) M H Z00 08 M08 5356 03\1\214 02\12\14 10\12\14 02\12\14 APPROVED AS NOTED B
TO (SW-08) CODE B
BUILDER WORK ELECTROMECHANICAL 07\12\14
1 FT-ZP-TRN-HE-0960 ZP-FT-TRN-SA-0892 892-1-KF01-FT-SH-H-09-Z00-M-M08-5357 OPENING AND SLEEVE, LEVEL 09 (SW-01) M H Z00 09 M08 5357 08\12\14 07\12\14 15\12\14 08\12\14 APPROVED AS NOTED B
TO (SW-04) CODE B
BUILDER WORK ELECTROMECHANICAL 07\12\14
1 FT-ZP-TRN-HE-0960 ZP-FT-TRN-SA-0892 892-1-KF01-FT-SH-H-09-Z00-M-M08-5358 OPENING AND SLEEVE, LEVEL 09 (SW-05) M H Z00 09 M08 5358 08\12\14 07\12\14 15\12\14 08\12\14 APPROVED AS NOTED B
TO (SW-08) CODE B
BUILDER WORK ELECTROMECHANICAL 14\12\14
1 FT-ZP-TRN-HE-0976 ZP-FT-TRN-SA-0910 892-1-KF01-FT-SH-H-10-Z00-M-M08-5359 OPENING AND SLEEVE, LEVEL 10 (SW-01) M H Z00 10 M08 5359 16\12\14 14\12\14 22\12\14 16\12\14 APPROVED AS NOTED B
TO (SW-04) CODE B
BUILDER WORK ELECTROMECHANICAL 14\12\14
1 FT-ZP-TRN-HE-0976 ZP-FT-TRN-SA-0910 892-1-KF01-FT-SH-H-10-Z00-M-M08-5360 OPENING AND SLEEVE, LEVEL 10 (SW-05) M H Z00 10 M08 5360 16\12\14 14\12\14 22\12\14 16\12\14 APPROVED AS NOTED B
TO (SW-08) CODE B
BUILDER WORK ELECTROMECHANICAL 14\12\14
1 FT-ZP-TRN-HE-0981 ZP-FT-TRN-SA-0911 892-1-KF01-FT-SH-H-11-Z00-M-M08-5361 OPENING AND SLEEVE, LEVEL 11 (SW-01) M H Z00 11 M08 5361 16\12\14 14\12\14 22\12\14 16\12\14 APPROVED AS NOTED B
TO (SW-04) CODE B
BUILDER WORK ELECTROMECHANICAL 14\12\14
1 FT-ZP-TRN-HE-0981 ZP-FT-TRN-SA-0911 892-1-KF01-FT-SH-H-11-Z00-M-M08-5362 OPENING AND SLEEVE, LEVEL 11 (SW-05) M H Z00 11 M08 5362 16\12\14 14\12\14 22\12\14 16\12\14 APPROVED AS NOTED B
TO (SW-08) CODE B
BUILDER WORK ELECTROMECHANICAL 17\12\14
1 FT-ZP-TRN-HE-0984 ZP-FT-TRN-SA-0917 892-1-KF01-FT-SH-H-12-Z00-M-M08-5363 OPENING AND SLEEVE, LEVEL 12 (SW-01) M H Z00 12 M08 5363 18\12\14 17\12\14 25\12\14 18\12\14 APPROVED AS NOTED B
TO (SW-04) CODE B
BUILDER WORK ELECTROMECHANICAL 17\12\14
1 FT-ZP-TRN-HE-0984 ZP-FT-TRN-SA-0917 892-1-KF01-FT-SH-H-12-Z00-M-M08-5364 OPENING AND SLEEVE, LEVEL 12 (SW-05) M H Z00 12 M08 5364 18\12\14 17\12\14 25\12\14 18\12\14 APPROVED AS NOTED B
TO (SW-08) CODE B
23 October,2014

KFMC - Phase 01 Advance IFC(Shop) Drawing Summary -Electrical-POWER(24 Nov. 2014 to 22 Dec.2014)

TOTAL RESUBMITTAL
Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

Revsion

Revsion
00

01

02

03

04

05

06

07

08
ZFP Review

Received Date

Actual date
Dedline
Group
Trade

Level
Zone

DWG

DWG
Area
Sr.

Date
N0.
Transmittal No.FTCO ZFP Transmittal Drawing Number Drawing name Package Remark

RESUBMIT
NEW DWG
No.
Date Date Date Date Date Date Date Date Date

UR

UR
Status A B C D N
Status Status Status Status Status Status Status Status Status

FT-ZP-TRN-HE-0563 ZP-FT-TRN-KS-0532 LEVEL 02 LIGHTING SYSTEM LAYOUT (ALL 21\04\14 11\05\14 24\11\14
1 FT-ZP-TRN-HE-0604 ZP-FT-TRN-KS-0561 892-1-KF01-FT-SH-H-02-Z00-E-E04-4122 LIGHTING LAYOUT E H Z00 02 E04 4122 29\04\14 14\05\14 25\11\14 24\11\14 03\12\14 25\11\14 APPROVED AS NOTED B
PARTS)
FT-ZP-TRN-HE-0939 ZP-FT-TRN-RC-0869 CODE C CODE B CODE B
FT-ZP-TRN-HE-0563 ZP-FT-TRN-KS-0532 LEVEL 02 LIGHTING SYSTEM LAYOUT PART - 21\04\14 11\05\14 24\11\14
1 FT-ZP-TRN-HE-0604 ZP-FT-TRN-KS-0561 892-1-KF01-FT-SH-H-02-Z01-E-E04-4123 LIGHTING LAYOUT E H Z01 02 E04 4123 29\04\14 14\05\14 25\11\14 24\11\14 03\12\14 25\11\14 APPROVED AS NOTED B
01
FT-ZP-TRN-HE-0939 ZP-FT-TRN-RC-0869 CODE C CODE B CODE B
FT-ZP-TRN-HE-0563 ZP-FT-TRN-KS-0532 LEVEL 02 LIGHTING SYSTEM LAYOUT PART - 21\04\14 11\05\14 24\11\14
1 FT-ZP-TRN-HE-0604 ZP-FT-TRN-KS-0561 892-1-KF01-FT-SH-H-02-Z02-E-E04-4124 LIGHTING LAYOUT E H Z02 02 E04 4124 29\04\14 14\05\14 25\11\14 24\11\14 03\12\14 25\11\14 APPROVED AS NOTED B
02
FT-ZP-TRN-HE-0939 ZP-FT-TRN-RC-0869 CODE C CODE B CODE B
FT-ZP-TRN-HE-0563 ZP-FT-TRN-KS-0532 LEVEL 02 LIGHTING SYSTEM LAYOUT PART - 21\04\14 11\05\14 24\11\14
1 FT-ZP-TRN-HE-0604 ZP-FT-TRN-KS-0561 892-1-KF01-FT-SH-H-02-Z03-E-E04-4125 LIGHTING LAYOUT E H Z03 02 E04 4125 29\04\14 14\05\14 25\11\14 24\11\14 03\12\14 25\11\14 APPROVED AS NOTED B
03
FT-ZP-TRN-HE-0939 ZP-FT-TRN-RC-0869 CODE C CODE B CODE B
FT-ZP-TRN-HE-0563 ZP-FT-TRN-KS-0532 LEVEL 02 LIGHTING SYSTEM LAYOUT PART - 21\04\14 11\05\14 24\11\14
1 FT-ZP-TRN-HE-0604 ZP-FT-TRN-KS-0561 892-1-KF01-FT-SH-H-02-Z04-E-E04-4126 LIGHTING LAYOUT E H Z04 02 E04 4126 29\04\14 14\05\14 25\11\14 24\11\14 03\12\14 25\11\14 APPROVED AS NOTED B
04
FT-ZP-TRN-HE-0939 ZP-FT-TRN-RC-0869 CODE C CODE B CODE B
FT-ZP-TRN-HE-0563 ZP-FT-TRN-KS-0532 LEVEL 02 LIGHTING SYSTEM LAYOUT PART - 21\04\14 11\05\14 24\11\14
1 FT-ZP-TRN-HE-0604 ZP-FT-TRN-KS-0561 892-1-KF01-FT-SH-H-02-Z05-E-E04-4127 LIGHTING LAYOUT E H Z05 02 E04 4127 29\04\14 14\05\14 25\11\14 24\11\14 03\12\14 25\11\14 APPROVED AS NOTED B
05
FT-ZP-TRN-HE-0939 ZP-FT-TRN-RC-0869 CODE C CODE B CODE B
FT-ZP-TRN-HE-0563 ZP-FT-TRN-KS-0532 LEVEL 02 LIGHTING SYSTEM LAYOUT 21\04\14 11\05\14 24\11\14
1 FT-ZP-TRN-HE-0604 ZP-FT-TRN-KS-0561 892-1-KF01-FT-SH-H-02-Z06-E-E04-4128 LIGHTING LAYOUT E H Z06 02 E04 4128 29\04\14 14\05\14 25\11\14 24\11\14 03\12\14 25\11\14 APPROVED AS NOTED B
PART - 06
FT-ZP-TRN-HE-0939 ZP-FT-TRN-RC-0869 CODE C CODE B CODE B
FT-ZP-TRN-HE-0563 ZP-FT-TRN-KS-0532 LEVEL – 02 – LIGHTING SYSTEM LAYOUT 21\04\14 11\05\14 24\11\14
1 FT-ZP-TRN-HE-0604 ZP-FT-TRN-KS-0561 892-1-KF01-FT-SH-H-02-000-E-E04-4129 LIGHTING LAYOUT E H 00 02 E04 4129 29\04\14 14\05\14 25\11\14 24\11\14 03\12\14 25\11\14 APPROVED AS NOTED B
LEGEND AND DETAILS
FT-ZP-TRN-HE-0939 ZP-FT-TRN-RC-0869 CODE C CODE C CODE B
FT-ZP-TRN-AA-0861 ZP-FT-TRN-RO-0833 26\10\14 16\11\14 30\11\14
1 FT-ZP-TRN-HE-0922 'ZP-FT-TRN-RO-0857 892-1-KF01-FT-SH-H-04-Z00-E-E03-4235 LEVEL 04 GROUNDING LAYOUT (ALL PARTS) E H Z00 04 E03 4235 27\10\14 17\11\14 01\12\14 30\11\14 08\12\14 01\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0944 'ZP-FT-TRN-RO-0877 CODE C CODE C CODE B
FT-ZP-TRN-AA-0861 ZP-FT-TRN-RO-0833 26\10\14 16\11\14 30\11\14
1 FT-ZP-TRN-HE-0922 'ZP-FT-TRN-RO-0857 892-1-KF01-FT-SH-H-04-Z01-E-E03-4236 LEVEL 04 GROUNDING LAYOUT PART-01 E H Z01 04 E03 4236 27\10\14 17\11\14 01\12\14 30\11\14 08\12\14 01\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0944 'ZP-FT-TRN-RO-0877 CODE C CODE C CODE B
FT-ZP-TRN-AA-0861 ZP-FT-TRN-RO-0833 26\10\14 16\11\14 30\11\14
1 FT-ZP-TRN-HE-0922 'ZP-FT-TRN-RO-0857 892-1-KF01-FT-SH-H-04-Z02-E-E03-4237 LEVEL 04 GROUNDING LAYOUT PART-02 E H Z02 04 E03 4237 27\10\14 17\11\14 01\12\14 30\11\14 08\12\14 01\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0944 'ZP-FT-TRN-RO-0877 CODE C CODE C CODE B
FT-ZP-TRN-AA-0861 ZP-FT-TRN-RO-0833 26\10\14 16\11\14 30\11\14
1 FT-ZP-TRN-HE-0922 'ZP-FT-TRN-RO-0857 892-1-KF01-FT-SH-H-04-Z03-E-E03-4238 LEVEL 04 GROUNDING LAYOUT PART-03 E H Z03 04 E03 4238 27\10\14 17\11\14 01\12\14 30\11\14 08\12\14 01\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0944 'ZP-FT-TRN-RO-0877 CODE C CODE C CODE B
FT-ZP-TRN-HE-0916 ZP-FT-TRN-RC-0849
03\11\14 17\11\14 01\12\14 14\12\14
FT-ZP-TRN-HE-0926 'ZP-FT-TRN-RC-0863 LEVEL 4 - POWER DISTRIBUTION CABLE
1 892-1-KF01-FT-SH-H-04-Z00-E-E05-4251 E H Z00 04 E05 4251 05\11\14 20\11\14 03\12\14 15\12\14 14\12\14 22\12\14 15\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0952 'ZP-FT-TRN-RC-0883 TRAY & CABLE TRUNKING (ALL PARTS)
CODE C CODE C CODE C CODE B
FT-ZP-TRN-HE-0979 'ZP-FT-TRN-RC-0908
FT-ZP-TRN-HE-0916 ZP-FT-TRN-RC-0849
03\11\14 17\11\14 01\12\14 14\12\14
FT-ZP-TRN-HE-0926 'ZP-FT-TRN-RC-0863 LEVEL 4 - POWER DISTRIBUTION CABLE
1 892-1-KF01-FT-SH-H-04-Z01-E-E05-4252 E H Z01 04 E05 4252 05\11\14 20\11\14 03\12\14 15\12\14 14\12\14 22\12\14 15\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0952 'ZP-FT-TRN-RC-0883 TRAY & CABLE TRUNKING (PART-1)
CODE C CODE C CODE C CODE B
FT-ZP-TRN-HE-0979 'ZP-FT-TRN-RC-0908
FT-ZP-TRN-HE-0916 ZP-FT-TRN-RC-0849
03\11\14 17\11\14 01\12\14 14\12\14
FT-ZP-TRN-HE-0926 'ZP-FT-TRN-RC-0863 LEVEL 4 - POWER DISTRIBUTION CABLE
1 892-1-KF01-FT-SH-H-04-Z02-E-E05-4253 E H Z02 04 E05 4253 05\11\14 20\11\14 03\12\14 15\12\14 14\12\14 22\12\14 15\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0952 'ZP-FT-TRN-RC-0883 TRAY & CABLE TRUNKING (PART-2)
CODE C CODE C CODE C CODE B
FT-ZP-TRN-HE-0979 'ZP-FT-TRN-RC-0908
FT-ZP-TRN-HE-0916 ZP-FT-TRN-RC-0849
03\11\14 17\11\14 01\12\14 14\12\14
FT-ZP-TRN-HE-0926 'ZP-FT-TRN-RC-0863 LEVEL 4 - POWER DISTRIBUTION CABLE
1 892-1-KF01-FT-SH-H-04-Z03-E-E05-4254 E H Z03 04 E05 4254 05\11\14 20\11\14 03\12\14 15\12\14 14\12\14 22\12\14 15\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0952 'ZP-FT-TRN-RC-0883 TRAY & CABLE TRUNKING (PART-3)
CODE C CODE C CODE C CODE B
FT-ZP-TRN-HE-0979 'ZP-FT-TRN-RC-0908
FT-ZP-TRN-HE-0917 ZP-FT-TRN-RC-0850 LEVEL-4 (MEZZANINE) POWER DISTRIBUTION 03\11\14 17\11\14 01\12\14 16\12\14
1 FT-ZP-TRN-HE-0928 'ZP-FT-TRN-RC-0867 892-1-KF01-FT-SH-H-4M-Z00-E-E05-4319 CABLE TRAY & CABLE TRUNKING LAYOUT E H Z00 04 E05 4319 05\11\14 23\11\14 04\12\14 17\12\14 16\12\14 24\12\14 17\12\14 NOT APPROVED C
FT-ZP-TRN-HE-0951 'ZP-FT-TRN-RC-0888 (ALL PARTS) CODE C CODE C CODE C CODE C
FT-ZP-TRN-HE-0983 ZP-FT-TRN-RC-0915
FT-ZP-TRN-HE-0917 ZP-FT-TRN-RC-0850 LEVEL-4 (MEZZANINE) POWER DISTRIBUTION 03\11\14 17\11\14 01\12\14 16\12\14
1 FT-ZP-TRN-HE-0928 'ZP-FT-TRN-RC-0867 892-1-KF01-FT-SH-H-4M-Z01-E-E05-4320 CABLE TRAY & CABLE TRUNKING LAYOUT E H Z01 04 E05 4320 05\11\14 23\11\14 04\12\14 17\12\14 16\12\14 24\12\14 17\12\14 NOT APPROVED C
FT-ZP-TRN-HE-0951 'ZP-FT-TRN-RC-0888 (PART-1) CODE C CODE C CODE C CODE C
FT-ZP-TRN-HE-0983 ZP-FT-TRN-RC-0915
FT-ZP-TRN-HE-0917 ZP-FT-TRN-RC-0850 LEVEL-4 (MEZZANINE) POWER DISTRIBUTION 03\11\14 17\11\14 01\12\14 16\12\14
1 FT-ZP-TRN-HE-0928 'ZP-FT-TRN-RC-0867 892-1-KF01-FT-SH-H-4M-Z03-E-E05-4321 CABLE TRAY & CABLE TRUNKING LAYOUT E H Z03 04 E05 4321 05\11\14 23\11\14 04\12\14 17\12\14 16\12\14 24\12\14 17\12\14 NOT APPROVED C
FT-ZP-TRN-HE-0951 'ZP-FT-TRN-RC-0888 (PART-3) CODE C CODE C CODE C CODE C
FT-ZP-TRN-HE-0983 ZP-FT-TRN-RC-0915
FT-ZP-TRN-HE-0947 ZP-FT-TRN-RC-0875 30\11\14 03\12\14
1 892-1-KF01-FT-SH-H-05-Z00-E-E04-4326 LEVEL 5 - LIGHTING LAYOUT (ALL PARTS) E H Z00 05 E04 4326 01\12\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0956 'ZP-FT-TRN-RC-0890
CODE C CODE B
FT-ZP-TRN-HE-0947 ZP-FT-TRN-RC-0875 30\11\14 03\12\14
1 892-1-KF01-FT-SH-H-05-Z01-E-E04-4327 LEVEL 5 - LIGHTING LAYOUT (PART-1) E H Z01 05 E04 4327 01\12\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0956 'ZP-FT-TRN-RC-0890
CODE C CODE B
FT-ZP-TRN-HE-0947 ZP-FT-TRN-RC-0875 30\11\14 03\12\14
1 892-1-KF01-FT-SH-H-05-Z02-E-E04-4328 LEVEL 5 - LIGHTING LAYOUT (PART-2) E H Z02 05 E04 4328 01\12\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0956 'ZP-FT-TRN-RC-0890
CODE C CODE B
FT-ZP-TRN-HE-0947 ZP-FT-TRN-RC-0875 30\11\14 03\12\14
1 892-1-KF01-FT-SH-H-05-Z03-E-E04-4329 LEVEL 5 - LIGHTING LAYOUT (PART-3) E H Z03 05 E04 4329 01\12\14 04\12\14 03\12\14 11\12\14 04\12\14 APPROVED AS NOTED B
FT-ZP-TRN-HE-0956 'ZP-FT-TRN-RC-0890
CODE C CODE B
FT-ZP-TRN-HE-0947 ZP-FT-TRN-RC-0875 LEVEL 5 - LIGHTING LAYOUT LEGENDS & 30\11\14 03\12\14
1 892-1-KF01-FT-SH-H-05-000-E-E04-4330 E H 000 05 E04 4330 01\12\14 04\12\14 03\12\14 11\12\14 04\12\14 NOT APPROVED C
FT-ZP-TRN-HE-0956 'ZP-FT-TRN-RC-0890 DETAILS
CODE C CODE B
07\12\14
1 FT-ZP-TRN-HE-0964 ZP-FT-TRN-RO-0896 892-1-KF01-FT-SH-H-05-Z00-E-E05-4339 Level – 05 – Power System Layout (All Parts) E H Z00 05 E05 4339 08\12\14 07\12\14 15\12\14 08\12\14 APPROVED AS NOTED B
CODE B
07\12\14
1 FT-ZP-TRN-HE-0964 ZP-FT-TRN-RO-0896 892-1-KF01-FT-SH-H-05-Z01-E-E05-4340 Level – 05 – Power System Layout (Part- 01) E H Z01 05 E05 4339 08\12\14 07\12\14 15\12\14 08\12\14 APPROVED AS NOTED B
CODE B
07\12\14
1 FT-ZP-TRN-HE-0964 ZP-FT-TRN-RO-0896 892-1-KF01-FT-SH-H-05-Z02-E-E05-4341 Level – 05 – Power System Layout (Part- 02) E H Z02 05 E05 4339 08\12\14 07\12\14 15\12\14 08\12\14 APPROVED AS NOTED B
CODE B
07\12\14
1 FT-ZP-TRN-HE-0964 ZP-FT-TRN-RO-0896 892-1-KF01-FT-SH-H-05-Z03-E-E05-4342 Level – 05 – Power System Layout (Part- 03) E H Z03 05 E05 4339 08\12\14 07\12\14 15\12\14 08\12\14 APPROVED AS NOTED B
CODE B
LEVEL – 05 – LIGHTING CONTROL SYSTEM 17\12\14
1 FT-ZP-TRN-HE-0988 ZP-FT-TRN-KS-0918 892-1-KF01-FT-SH-H-05-Z00-E-E04-4343 E H Z00 05 E04 4343 18\12\14 17\12\14 25\12\14 18\12\14 NOT APPROVED C
LAYOUT ( ALL PARTS )
CODE C
LEVEL – 05 – LIGHTING CONTROL SYSTEM 17\12\14
1 FT-ZP-TRN-HE-0988 ZP-FT-TRN-KS-0918 892-1-KF01-FT-SH-H-05-Z01-E-E04-4344 E H Z01 05 E04 4344 18\12\14 17\12\14 25\12\14 18\12\14 NOT APPROVED C
LAYOUT ( PART -01 )
CODE C
LEVEL – 05 – LIGHTING CONTROL SYSTEM 17\12\14
1 FT-ZP-TRN-HE-0988 ZP-FT-TRN-KS-0918 892-1-KF01-FT-SH-H-05-Z02-E-E04-4345 E H Z02 05 E04 4345 18\12\14 17\12\14 25\12\14 18\12\14 NOT APPROVED C
LAYOUT ( PART -02 )
CODE C
LEVEL – 05 – LIGHTING CONTROL SYSTEM 17\12\14
1 FT-ZP-TRN-HE-0988 ZP-FT-TRN-KS-0918 892-1-KF01-FT-SH-H-05-Z03-E-E04-4346 E H Z03 05 E04 4346 18\12\14 17\12\14 25\12\14 18\12\14 NOT APPROVED C
LAYOUT ( PART-03 )
CODE C
8.0 ATTACHMENTS

8.2. Materials and Submittal Status


Date :22 Dec., 2014

King Faisal Medical City(South) Phase 01 MAIN HOSPITAL


MASTER MATERIAL SUBMISSION SUMMARY
TOTAL SUBMITTED AS TOTAL SUB TOTAL REVISED NEW MAT
TOTAL APPROVED APPROVED APPROVED
S. N. DISCIPLINE SUB - DISCIPLINE MATERIAL PER PLANNED APPROVED MATERIAL UNDER MAT.UNDER UNDER A B C D N TOTAL
PLANNED (%) SUB MAT. (%)
SUBMITTED (%) MATERIAL SUBMITTED REVIEW REVIEW REVIEW
SUB MAT.

Architectural
01 Architectural 181 12 6.63% 6 50% 24 11 45.83% 0 0 0 0 11 13 0 0
&Landscape
Structural
02 Structural 12 32 266.67% 25 78% 92 57 61.96% 0 0 0 1 56 24 11 0
& Civil
03 Mechanical Mechanical 184 8 4.35% 7 88% 23 18 78.26% 0 0 0 0 18 0 5 0

04 Electrical Electrical 93 15 16.13% 13 87% 48 29 60.42% 0 0 0 0 29 14 5 0


TOTAL 470 67 14.26% 51 76% 187 115 61.50% 0 0 0 1 114 51 21 0 187

A-APPROVED,B-APPROVED AS NOTED,C-NOT APPROVED REVISE & RESUBMIT,D-REJECTED,N-NOTED

Note: Planned quantities are not approved by ZFP but are presented as per FTCO submittal for just monitoring purpose.
8.0ATTACHMENTS
This Month Total Material was Submitted
Date :22 Dec., 2014

King Faisal Medical City(South) Phase 01 MAIN HOSPITAL


MATERIAL SUBMISSION SUMMARY(24 Nov. 2014 to 22 Dec.2014)
TOTAL SUBMITTED AS TOTAL TOTAL REVISED NEW MAT
APPROVED
S. N. DISCIPLINE SUB - DISCIPLINE MATERIAL PER PLANNED APPROVED UNDER MAT.UNDER UNDER A B C D N TOTAL
(%)
SUBMITTED (%) MATERIAL REVIEW REVIEW REVIEW

01 Architectural
Architectural 0 0.00% 0 #DIV/0! 0 0 0 0 0 0 0 0
&Landscape
02
Structural
Structural 1 8.33% 1 100% 0 0 0 0 1 0 0 0
& Civil
03 Mechanical Mechanical 0 0.00% 0 #DIV/0! 0 0 0 0 0 0 0 0
04 Electrical Electrical 0 0.00% 0 #DIV/0! 0 0 0 0 0 0 0 0
TOTAL 1 0.21% 1 100% 0 0 0 0 1 0 0 0 1

A-APPROVED,B-APPROVED AS NOTED,C-NOT APPROVED REVISE & RESUBMIT,D-REJECTED,N-NOTED

Note: Planned quantities are not approved by ZFP but are presented as per FTCO submittal for just monitoring purpose.
Date : 23 October,2014

KFMC - Phase 01 Material Submission Summary(24 Nov. 2014 to 22 Dec.2014)


REV.
REV. 01 REV. 02 REV. 03 REV. 04 ZFP Review

Received Date
00

Actual date
Dedline
Submit To

Trade

RESUBMIT
NEW MAT
Sr.

Date
Matrial Name Name of Manufacturer Supplier\Agent Applicator FTCO-Submittal No. FTCO-Transmittal No. ZFP-Transmittal No. HILL Remark
No.

UR

UR
00 01 02 03 04 Approval Status A B C D N

CONCRETE DESIGN MIX (No. 1)


Design Strength: 40 Mpa - OPC; Admixture 1 – Flocrete 16\11\14 23\11\14
SP124 M1; Admixture 2 – Flocrete RP 322 SAAD BEN HAMMOD FOR READY SAAD BEN HAMMOD FOR READY FT-ZP-TRN-HE-0274 8921-KF-KF01-S-ZP-FT-TRN-FL-0235
1 1 A - FT-MAR-C-0022 C 17\11\14 23\11\14 23\11\14 02\12\14 23\11\14 APPROVED AS NOTED B
Application Use: For Suspended Slab & Beams MIX CONCRETE MIX CONCRETE FT-ZP-TRN-HE-0275 8921-KF-KF01-S-ZP-FT-TRN-FL-0236
CODE C CODE B
Supplier / Manufacturer: Saad Bin Homoud
8.0 ATTACHMENTS

8.3 Document and Submittal Status


Date : 22 Dec., 2014

King Faisal Medical City(South) Phase 01 MAIN HOSPITAL


MASTER DOCUMENT SUBMISSION SUMMARY
TOTAL TOTAL REVISED NEW DOC
S. N. DISCIPLINE SUB - DISCIPLINE APPROVED TOTAL DOCUMENT DOC.UNDER UNDER A B C D N TOTAL
APPROVED UNDER REVIEW
PERCENTAGE(%) SUBMITTED REVIEW REVIEW
01
Architectural & Architectural &
33.33% 1 3 0 0 0 0 1 1 0 1
Landscape Landscape
02 Structural & Civil Structural & Civil 42.06% 53 126 0 0 0 1 52 25 5 43
03 Mechanical Mechanical 50.00% 1 2 0 0 0 0 1 0 0 1
04 Electrical Electrical 12.50% 1 8 0 0 0 0 1 4 0 3
05 General General 37.74% 20 53 0 0 0 2 18 20 0 14
TOTAL 39.58% 76 192 0 0 0 3 73 50 5 61 192

Legend of Documents:
1) Method Statements
2) Various Management Plans
3) Concrete Related Mix Designs and Test Results
4) Submittal Schedule
5) Soil Reports
6) MEP Calculations
8.0ATTACHMENTS
This Month Total Document was Submitted
Date : 22 Dec., 2014

King Faisal Medical City(South) Phase 01 MAIN HOSPITAL


DOCUMENT SUBMISSION SUMMARY(24 Nov. 2014 to 22 Dec.2014)
TOTAL TOTAL REVISED NEW DOC
S. N. DISCIPLINE SUB - DISCIPLINE APPROVED TOTAL DOCUMENT DOC.UNDER UNDER A B C D N TOTAL
APPROVED UNDER REVIEW
PERCENTAGE(%) SUBMITTED REVIEW REVIEW
01
Architectural & Architectural &
#DIV/0! 0 0 0 0 0 0 0 0 0 0
Landscape Landscape
02 Structural & Civil Structural & Civil 0.00% 0 4 0 0 0 0 0 2 2 0
03 Mechanical Mechanical #DIV/0! 0 0 0 0 0 0 0 0 0 0
04 Electrical Electrical #DIV/0! 0 0 0 0 0 0 0 0 0 0
05 General General #DIV/0! 0 0 0 0 0 0 0 0 0 0
TOTAL 0.00% 0 4 0 0 0 0 0 2 2 0 4

Legend of Documents:
1) Method Statements
2) Various Management Plans
3) Concrete Related Mix Designs and Test Results
4) Submittal Schedule
5) Soil Reports
6) MEP Calculations
Date : 23 October, 2014

KFMC - Phase 01 Document Submission Summary(24 Nov. 2014 to 22 Dec.2014)

REVSION REVSION REVSION REVSION ZFP REVIEW

Received Date

Actual date
00 01 02 03

Dedline
Trade
Sr.

Date
DOCUMENT NAME SUBJECT FTCO TRANSMITTAL FTCO SUBMITTAL ZFP TRANSMITTAL REMARK

NEW DOC
No.

RESUBMI
T UR
UR
00 01 02 03 STATUS A B C D N

04\12\14
COMPRESSION STRENGTH REPORT OF
1 TST FT-ZP-TRN-HE-0278 FT-TST-S-0084 ZP-FT-TRN-RA-0179 S 04\12\14 04\12\14 14\12\14 04\12\14 REJECTED D
CONCRETE CORES @ LEVEL-1 SLAB / ZONE-3
CODE D

14\12\14
CONCRETE EVALUATION REPORT OF LEVEL-01
1 TST FT-ZP-TRN-HE-0280 FT-TST-S-0086 ZP-FT-TRN-RA-0179 S 15\12\14 14\12\14 22\12\14 15\12\14 NOT APPROVED C
SLAB IN ZONE-03
CODE C
10\12\14
1 CALCULATION FOR SLAB REPROPPING CALCULATION FT-ZP-TRN-HE-0279 FT-CAL-S-0085 ZP-FT-TRN-HR-0178 S 11\12\114 10\12\14 18\12\14 11\12\14 NO APPROVED C
CODE C
METHOD STATEMENT FOR LOAD TEST ON SLAB 30\11\14 04\12\14
FT-ZP-TRN-HE-0272 ZP-FT-TRN-ME-0174
1 LEVEL-1 ZONE-3 MST FT-MST-S-0081 S 02\12\14 04\12\14 04\12\14 14\12\14 04\12\14 REJECTED D
FT-ZP-TRN-HE-0277 ZP-FT-TRN-RA-0176
WITH RISK ASSESSMENTS CODE D CODE D

Page 1 of 1
Date : 22 Dec., 2014

Medical Cities Submission Phase 02(Hill to ZFP)


DOCUMENT SUBMISSION SUMMARY(24 Nov. 2014 to 22 Dec.2014)
TOTAL TOTAL REVISED NEW DOC
S. N. DISCIPLINE SUB - DISCIPLINE APPROVED TOTAL DOCUMENT DOC.UNDER UNDER A B C D N TOTAL
APPROVED UNDER REVIEW
PERCENTAGE(%) SUBMITTED REVIEW REVIEW
01
Architectural & Architectural &
100.00% 1 1 0 0 0 1 0 0 0 0
Landscape Landscape
02 Structural & Civil Structural & Civil #DIV/0! 0 0 0 0 0 0 0 0 0 0
03 Mechanical Mechanical #DIV/0! 0 0 0 0 0 0 0 0 0 0
04 Electrical Electrical #DIV/0! 1 0 1 0 1 0 0 0 0 0
05 General General #DIV/0! 0 0 0 0 0 0 0 0 0 0
TOTAL 100.00% 2 1 1 0 1 1 0 0 0 0 2

Legend of Documents:
1) Method Statements
2) Various Management Plans
3) Concrete Related Mix Designs and Test Results
4) Submittal Schedule
5) Soil Reports
6) MEP Calculations
Date : 23 October, 2014

KFMC/PMMC - Phase 02 Document Submission Summary(24 Nov.2014 to 22 Dec.2014)from Hill International

REVSION REVSION REVSION REVSION ZFP REVIEW

Received Date
01 02 03

Actual date
00

Dedline
Trade
Sr.

Date
DOCUMENT NAME SUBJECT HILL TRANSMITTAL HILL SUBMITTAL ZFP TRANSMITTAL REMARK

NEW DOC UR
No.

RESUBMIT
UR
00 01 02 03 STATUS A B C D N

10\12\14
1 PAINTING-JOTUN PAINT PRE-QUALIFICATION PQD MC02-HI-ZP-TRN-AT-0035 -- MC02-ZP-HI-TRN-YF-0002 A 11\12\14 10\12\14 18\12\14 11\12\14 APPROVED A 0
CODE A

1 HONEYWELL BUILDING SOLUTIONS PQD MC02-HI-ZP-TRN-AT-0036 MC01-H-HI-PQD-E-0002 -- E 21\12\14 21\12\14 29\12\14 04\09\12 UNDER REVIEW
UR

2 2 0 0 0 1 0 1 0 0 0 0

Page 1 of 1
8.0 ATTACHMENTS

8.4 Minutes of Meetings, Letters and Notices


ZFP LETTERS TO CONTRACTOR(24 Nov.2014 to 22 Dec.2014)
Sr. LETTER
SUBJECT DATE ACTION INFO.
No NO.
1 344 Submit request of inspection for all concreting works 26-Nov-14 FTCO
2 345 Approval of sub Contractors 26-Nov-14 FTCO
3 346 PVC pipe broken after pouring of concrete at C7 along column at Level 01 30-Nov-14 FTCO
4 347 Keep approved concrete design mix & MS at batch plant, check point 30-Nov-14 FTCO
5 348 Resume the repair works immediately 3-Dec-14 FTCO
6 349 Changing the plan of casting 3-Dec-14 FTCO

Page 1 of 1
8.0 ATTACHMENTS

8.5 Financial Report for Contractor


PROJECT NAME: KING FAISAL MEDICAL CITY (KFMC)
LOCATION: ABHA (ASIR), KSA
PHASE NO. 1, INCLUDES 500 BEDS (P+G+14+R) + INFRA(C.U.P.) + SITE DEVELOPMENT

CLIENT: MINISTRY OF HEALTH (MOH)


PROJECT MANAGEMENT: HILL INTERNATIONAL (HI)
SUPERVISION CONSULTANT: ZUHAIR FAYEZ PARTNERSHIP (ZFP)
CONTRACTOR: AL FOUZAN TRADING & GENERAL CONSTRUCTION CO. (FTCO)

DATE START OF CONSTRUCTION: 11-08-1433


DURATION OF CONTRACT: 36 MONTHS
DATE OF COMPLETION: 10-08-1436
Recovery Baseline Schedule-II 28/May/15

SUBJECT: CONTRACTOR'S CASH FLOW STATUS

Duration: From 01 Safar 1436 to 30 Safar 1436 (H)


From 23 November 2014 to 22 December 2014 (G)

Remaining Recovery
Authorized Contract, Cummulative Advance Cummulative Net Remaining Authorized
Contractor from Advance Payment,
SAR Paid Recovery, SAR Amount Payable , SAR Contract Amount, SAR
SAR

FTCO 642,235,175.00 13,795,931.15 55,183,724.57 114,701,103.85 458,554,415.43

Authorized Contract, SAR

458,554,415.43

642,235,175.00 Cummulative Advance Paid Recovery, SAR

Cummulative Net Amount Payable , SAR

Remaining Recovery from Advance Payment, SAR

114,701,103.85
Remaining Authorized Contract Amount, SAR
55,183,724.57 13,795,931.15

Prepared by: Noted by:


Engr.JaimeJr.M.Castaneda Engr. Abdul Nasser Obeidat
Sr.QS-ZFP APM - ZFP page: 1 of 1
PROJECT NAME: KING FAISAL MEDICAL CITY (KFMC)
LOCATION: ABHA (ASIR), KSA
PHASE NO. 1, INCLUDES 500 BEDS (P+G+14+R) + INFRA(C.U.P.) + SITE DEVELOPMENT

CLIENT: MINISTRY OF HEALTH (MOH)


PROJECT MANAGEMENT: HILL INTERNATIONAL (HI)
SUPERVISION CONSULTANT: ZUHAIR FAYEZ PARTNERSHIP (ZFP)
CONTRACTOR: AL FOUZAN TRADING & GENERAL CONSTRUCTION CO. (FTCO)

DATE START OF CONSTRUCTION: 11-08-1433


DURATION OF CONTRACT: 36 MONTHS
DATE OF COMPLETION: 10-08-1436
Recovery Baseline Schedule-II 28-May-15

SUBJECT: CONTRACTOR'S FINANCIAL STATUS

Duration: From 01 Safar 1436 to 30 Safar 1436 (H)


From 23 November 2014 to 22 December 2014 (G)

Gross certified Gross certified


Authorized Contract Advanced Payment Balance Authorized
Contractor amount, cummulative amount, this period
Amount, SAR Balance, SAR Contract Amount, SAR
previous IPC's, SAR IPC, SAR

FTCO 642,235,175.00 114,701,103.85 68,979,655.74 0.00 458,554,415.43

Authorized Contract Amount, SAR


458,554,415.43
Advanced Payment Balance, SAR
642,235,175.00

Gross certified amount, cummulative previous


IPC's, SAR
Gross certified amount, this period IPC, SAR

114,701,103.85
Balance Authorized Contract Amount, SAR
0.00
68,979,655.74

Prepared by: Noted by:


Engr.JaimeJr.M.Castaneda Engr. Abdul Nasser Obeidat
Sr.QS-ZFP APM - ZFP page: 1 of 1
MONTHLY PROJECT COST REPORT: 01 Safar 1436 to 30 Safar 1436 (H)
23 November 2014 to 22 December 2014 (G)
PROJECT NAME : KING FAISAL MEDICAL CITY (KFMC) - SOUTH
PROJECT NUMBER : 892 Planned % Accomplishment : 52.84%
PLEASE REFER TO FTCO's
LOCATION : ABHA( ASIR), KINGDOM OF SAUDI ARABIA Actual % Accomplishment : 10.74% APPROVED RECOVERY BASELINE
PHASE No. : 1 % Advance/Behind Schedule (+/-) : -42.10% SCHEDULE.- II

: 500 BEDS ( MAIN HOSPITAL, P+G+14FLOORS+roof) +C.U.P.+SITE DEVT. Date start of Construction : 11-08-1433
Duration of Contract : 36 months
CLIENT/ OWNER : MINISTRY OF HEALTH (MOH) Original Date of Completion : 10-08-1436
PROJECT MANAGEMENT : HILL INTERNATIONAL (HI) Recovery Baseline Schedule- II : May 28, 2015
SITE SUPERVISING CONSULTANT : ZUHAIR FAYEZ PARTNERSHIP (ZFP)
GENERAL CONTRACTOR : AL FOUZAN TRADING & GENERAL CONSTRUCTION CO (FTCO) Total Payment Made, SR : 183,680,759.58
Authorized Contract, SR : 642,235,175.00 Total Remaining from Contract, SR : 458,554,415.42
Authorized Advanced Payment,20% : 128,447,035.00 Total Advance Payment Balance, SR : 114,701,103.86
Authorized Variation, SR : 0.00

TIME DURATION CONSULTANT'S ASSESSMENT CONSULTANT %

DATE PAID, % Total


DATE, %
DATE, ACTUAL
Month-end claim period covered (ARABIC CALENDAR)
Gross Cumulative Gross Cumulative
Period Application Period Application Material At Site
Advance Payment
Advance Payment Net Cumulative Total Recommended per Remaining in Authorized REVISIO FORWARDED Net Actual Amount Every End IPC
DATE SUBMITTED Application (Original Application Recovery Amount Remark FORWARDED RECEIVED accomplishme REMARKS
Contract) (+ Variation Order)
(Variation Order) (Original Contract) Approved Claims
(20%)
Balance, SR Application Period, SR Contract
N NO. FROM ZFP TO HI
FROM HILL INTL
PAYMENT FROM Paid, SR nt per Month
of the Status
TO MOH Month
CLIENT

FTCO directly submitted the


FTCO got payment, as per verbal info from Mr.
20-Mar-12 0.00 0.00 0.00 0.00 0.00 0.00 128,497,035.00 128,497,035.00 513,738,140.00 Advance Payment 0 Nov.2012 128,497,035.00 invoice to MOH -received on
Abdelrahman, FTCO Coordinator
04-27-2012

50,000.00 THIS DIFFERENCE , AS PER TENDER AMOUNT


JULY 20, 2012 - AUGUST 18, 2012 NO IPC SUBMITTED
AUGUST 19, 2012 - SEPTEMBER 16, 2012 NO IPC SUBMITTED
SEPTEMBER 17, 2012 - OCTOBER 16, 2012 NO IPC SUBMITTED
OCTOBER 17, 2012 - NOVEMBER 14, 2012 NO IPC SUBMITTED
NOVEMBER 15, 2012 - DECEMBER 13, 2012 NO IPC SUBMITTED
14 DEC.2012 - 12 JAN 2013 18-Dec-12 IPC No.1 -Returned claim invoice -incomplete supporting documents on Dec.25, 2012. For Revision Code C REV.00
13 JAN 2013 -10FEB. 2013 NO IPC SUBMITTED
11 February 2013 - 12 March 2013 24 FEB.2013 IPC No.1 -Returned claim invoice with findings and incomplete supporting documents on March 09, 2013. Code C REV.1

13 March 2013 to 10 April 2013 NO IPC SUBMITTED

11 April 2013 to 10 May 2013 PROGRESS CLAIM FROM JULY 1, 2012 TO


27-Apr-13 14,616,961.65 14,616,961.65 0.00 14,616,961.65 0.00 2,923,392.33 125,573,642.67 11,693,569.32 11,693,569.32 502,044,570.68 IPC NO.1 2 29-Apr-13 12/May/13 11,693,569.32 2.28% 2.28% APPROVED
FEBRUARY 10, 2013

11 May 2013 to 09 June 2013 NO IPC SUBMITTED 0.00

10 JUNE 2013 to 08 JULY 2013 NO IPC SUBMITTED 0.00

09 JULY 2013 to 07 AUGUST 2013 NO IPC SUBMITTED 0.00

08 AUGUST 2013 to 06 SEPTEMBER 2013 NO IPC SUBMITTED 0.00

07 SEPTEMBER 2013 TO 05 OCTOBER 2013 NO IPC SUBMITTED 0.00

06 OCTOBER 2013 to 04 NOVEMBER 2013 27-Oct-13 IPC #2 - REV.0 - Returned claim invoice, incomplete supporting documents on 03 Nov.2013. For compliance & revision Code C

05 NOVEMBER 2013 to 03 DECEMBER 2013 NO IPC SUBMITTED

04 DECEMBER 2013 TO 01 JANUARY 2014 PROGRESS CLAIM FROM FEBRUARY 11, 2013
18-Dec-13 46,642,720.59 32,025,758.94 0.00 32,025,758.94 0.00 6,405,151.79 119,168,490.88 25,620,607.15 25,620,607.15 476,423,963.53 IPC NO.2 1 16-Jan-14 21/Jan/14 25,620,607.15 4.99% 7.26% APPROVED
TO SEPTEMBER 30, 2013

02 JANUARY 2014 TO 31 JANUARY 2014 NO IPC SUBMITTED

01 FEBRUARY 2014 TO 01 MARCH 2014 NO IPC SUBMITTED

02 MARCH 2014 TO 31 MARCH 2014 NO IPC SUBMITTED

01 April 2014 to 29 April 2014 NO IPC SUBMITTED

30 April 2014 to 29 May 2014 PROGRESS CLAIM FROM OCTOBER 1, 2013 TO


27-May-14 64,651,705.37 18,008,984.78 0.00 18,008,984.78 0.00 3,601,796.96 115,566,693.93 14,407,187.82 14,407,187.82 462,016,775.70 IPC NO.3 0 4-Jun-14 9/Jun/14 14,407,187.82 2.80% 10.07% APPROVED
APRIL 30, 2014
30 May 2014 to 28 June 2014 - 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 NO IPC SUBMITTED 0 - 0.00 0.00% 0.00% - -

29 June 2014 to 27 July 2014 - 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 NO IPC SUBMITTED 0 - 0.00 0.00% 0.00% - -

28 July 2014 to 26 August 2014 PROGRESS CLAIM FROM MAY 1, 2014 TO JUNE
5-Aug-14 65,638,411.92 986,706.55 0.00 986,706.55 0.00 197,341.31 115,369,352.62 789,365.24 789,365.24 461,227,410.46 IPC NO. 4 0 12-Aug-14 789,365.24 0.15% 10.22% APPROVED
30, 2014
27 August 2014 to 24 September 2014 (G) - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 NO IPC SUBMITTED 0 - 0.00 0.00% 0.00%

25 Sept 2014 to 24 October 2014 12-Oct-14 68,979,655.72 3,341,243.80 0.00 3,341,243.80 0.00 0.00 0.00 0.00 - 0.00 IPC NO. 5 0 - 0.00 0.00% 0.00% ON PROCESS

25 October 2014 to 22 November 2014 PROGRESS CLAIM FROM JULY 1, 2014 TO


12-Oct-14 68,979,655.72 3,341,243.80 0.00 3,341,243.80 0.00 668,248.76 114,701,103.86 2,672,995.04 2,672,995.04 458,554,415.42 IPC NO. 5 0 5-Nov-14 17/Nov/14 2,672,995.04 0.52% 10.74%
AUGUST 31, 2014
23 November 2014 to 22 December 2014 (G) 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - 0.00 NO IPC SUBMITTED 0 - 0.00 0.00% 0.00% - -

SUB-TOTAL 72,320,899.52 0.00 72,320,899.52 0.00 13,795,931.14 55,183,724.58 183,680,759.58 183,680,759.58


128,497,035.00
TOTAL Net Payment Work Done 55,183,724.58

Balance from Advance Payment,


NOTE: CUT OFF DATE for IPC, FTCO 114,701,103.86 128,497,035.00
SAR
to submit IPC on or before 5th day of Recovered from advance
the 1st week of the following month. 13,795,931.14 183,680,759.58
payment,SAR

Total amount paid work done, including Balance from Advance Payment, SR 169,884,828.43 actual % note:
Gross Total, Payments Made, SAR 183,680,759.58 28.60% (80% max.limit on IPC release as per MOH contract)
Gross Total, Balance Amount from Contract, SAR 458,554,415.42 71.40%
Prepared by: Noted by:
Engr.Jaime Jr.M.Castaneda Engr. Abdul Nasser Obeidat
Sr.QS-ZFP Asst. Project Manager- ZFP, KFMC Project
SUBJECT: PROJECT CASH FLOW AND STATUS

KFMC - PHASE 1
CONTRACTOR's (FTCO) PROJECTED CASHFLOW CONSULTANT's (ZFP) ASSESSMENT - CASHFLOW STATUS CLIENT (MOH) PAYMENT

DATE SUBMITTED - REMAINING BALANCE FROM AMOUNT RECOMMENDED, DATE FORWARDED TO


SN MONTH COVERED MONTHLY CLAIM, SAR AMOUNT CLAIM, SAR IPC NO. REVISION NO. DATE FORWARDED TO HI. REMARKS COMPLIANCE AMOUNT PAID, SAR
IPC/INVOICE CONTRACT, SAR SAR CLIENT(MOH) / RELEASED

642,235,175.00

FTCO SUBMIT ORIGINAL


20% ADVANCE PAYMENT CLAIM AS
March-12 - 20-Mar-12 128,497,035.00 642,235,175.00 INVOICE DIRECTLY TO MOH-
PER CONTRACT
04272012
1 -

November-12 1,446,200.15 0.00 513,738,140.00 ADVANCE PAYMENT


6 128,497,035.00 NOVEMBER2012

11 April 2013 to May 10, 2013 596,944.62 27-Apr-13 11,693,569.32 502,044,570.68 1 2 11,693,569.32 29/Apr/13 FOR HI/MOH APPROVAL - CLAIM 11,693,569.32 12/May/13
11 FROM JULY 01, 2012 TO FEB. 10, 2013
4 DECEMBER 2013 TO 01 JANUARY FOR HI/MOH APPROVAL - CLAIM
19 2014
15,767,515.40 18/Dec/13 25,620,607.15 476,423,963.53 2 1 25,620,607.15 16/Jan/14
FROM FEB. 11, 2013 TO SEPT. 30, 2013 25,620,607.15
21/Jan/14

CLAIM FROM 02 OCT 2013 TO 30APRIL


30 May 2014 to 28 June 2014 20,722,740.71 2/6/2014 14,407,187.82 462,016,775.71 3 1 14,407,187.82 3/Jun/14
2014
-
25 14,407,187.82 9/Jun/14
CLAIM FROM 01 MAY 2014 TO 30 JUNE
27
August-14 31,403,932.14 5/Aug/14 789,365.24 461,227,410.47 4 0 789,365.24 12/Aug/14
2014
-
789,365.24
25 October2014 to 22 CLAIM FROM 01 JULY 2014 TO 31
November2014
36,916,933.93 12/10/2014 2,672,995.04 458,554,415.43 5 0 2,672,995.04 5/Nov/14
AUGUST 2014
30 2,672,995.04 17/Nov/14
23 November 2014 to 22
45,225,924.23 0.00 458,554,415.43 0.00
31 Decembere 2014

32 January-15 31,021,910.86

33 February-15 45,867,476.49

34 March-15 70,914,826.03

35 April-15 64,472,214.16

36 May-15 45,380,857.70

TOTAL AMOUNT 642,235,175.00 55,183,724.57 183,680,759.57

NOTE: AS PER RECOVERY SCHEDULE - II

Noted by:
Prepared by: Engr. Abdul Nasser Obeidat
Engr.JaimeJr.M.Castaneda Asst. Project Manager - ZFP
Sr.QS-ZFP KFMC South Page 1 of 1
8.0 ATTACHMENTS

8.6 Attendance Report of the Site Supervision Consultant


8.0 ATTACHMENTS

8.7 Project Personnel


ZUHAIR FAYEZ PARTNERSHIP (ZFP) CENTRAL OFFICE
STAFF DIRECTORY
SN STAFF NAME JOB TITLE PROJECT MOBILE NO. EMAIL ADDRESS

1 DR. ENGR. DHAIF ALMAZROA PROJECT DIRECTOR KFMC/PMMC 504144257 dalmazroa@zfp.com

2 ABDUL NASSER OBEID SR. MECHANICAL ENGINEER KFMC 0536418656 obaidat68@hotmail.com

3 HASSAN AL SAYED SECRETARY KFMC/PMMC 0550477298 hassan.alsayed68@gmail.com

4 KHALID NOUR SECRETARY KFMC/PMMC 0503626736 khalidnoureldin@hotmail.com


0567424391
5 MURAD KHAN DOCUMENT CONTROLLER KFMC 0556508786 muradkhan065@gmail.com

6 ABID RASHEED DOCUMENT CONTROLLER PMMC 0594085421 abid438@gmail.com

7 MOHAMMED IMRAN PLANNIGN ENGINEER KFMC/PMMC 553197431 abdulbaseerimranoof@gmail.com

8 RAHMAT ALI KHAN SR. STRUCTURAL ENGINEER KFMC 557545867 rahmat3599@yahoo.com

9 MOHAMMED EISA AMSID SR. STRUCTURAL ENGINEER KFMC/PMMC 557960637 meisamsid@gmail.com

10 FERDINAND F. LOZANO SR. STRUCTURAL ENGINEER KFMC 509516923 ferdi_lozano@yahoo.com

11 FRANCISCO LAZO SR. ELECTRICAL ENGINEER PMMC 0542945539 fn_lazo@yahoo.com

12 KHALID SHUAIB SR. ELECTRICAL ENGINEER KFMC 0533197306 khalidshuaib@yahoo.com

13 ROEL L. CARANGUIAN SR. ELECTRICAL ENGINEER KFMC/PMMC 569664169 welcar2004@yahoo.com

14 REYMUNDO ORALLO SR. ELECTRICAL ENGINEER KFMC/PMMC 565896217 reymorallo@yahoo.com

15 HISHAM ISMAIL REHANY SR. ELECTRICAL ENGINEER KFMC/PMMC 561959157 hamselrehany@hotmail.com

16 MOHAMMAD SUHAIL ANSARI SR. MECHANICAL ENGINEER KFMC 0503413608 suhail1420@yahoo.com

17 RAGLINE S. SERRANO SR. MECHANICAL ENGINEER PMMC 0532926657 ragline77@yahoo.com

18ALAMEDDIN ABDEL SAMEE AL DAJANI BIO-MEDICAL ENGINEER KFMC 0592601260 alam_dajani@hotmail.com

19 MOHAMMAD WASIQ ALI KHAN BIO-MEDICAL ENGINEER PMMC 0507607482 wasiqk@gmail.com

20 HISHAM ELGHAMRANY MEDICAL PLANER KFMC/PMMC 509053542 helghamrawy@zfp.com

21 RUSSEL AMORY M.DELA CRUZ ARCHITECT/INTERIOR DESIGNER KFMC 0509474365 russel_delacruz26@yahoo.com

22 YOLANDO FRANCISCO ARCHITECT PMMC 507957393 ybj7830@gmail.com

23 OSAMAH ALANZI ARCHITECT KFMC/PMMC 557444573 osamah-05@hotmail.com

24 MOHAMMED ALKHAIBARI ARCHITECT KFMC/PMMC 542507007 mohammedalkhaibari@hotmail.com

25 FAHAD AHMED AL RUSHAID LANDSCAPE ARCHITECT KFMC 0582904031 fhharu@hotmail.com

26 JAIME JR.M. CASTANEDA SE.QUANTITY SURVEYOR KFMC 0564920535 joe2buddy@yahoo.com

27 ALNIZAM BIN JOHARI SE.QUANTITY SURVEYOR KFMC 0503477209 alnizam@msn.com

28 AHMED SABRY SE.QUANTITY SURVEYOR PMMC 0543340611 eng_ahamed77@yahoo.com

29 EDGARDO S.WAHING AutoCAD OPERATOR KFMC/PMMC 0532682028 es_wahing66@yahoo.com

30 ASHRAF ALI AHMED AutoCAD OPERATOR KFMC/PMMC 0594663388 ashraf.ali8080@gmail.com

ZFP CORE TEAM OFFICE


GROUND FLOOR, AL NAHDAH ROAD, RIYADH, KSA (Next to Pizza Hut)
ZFP’s staff list with Positions & contact #

‫زﻫﻴﺮ ﻓـﺎﻳـﺰ و ﻣـﺸــﺎرﻛــﻮة – إﺳـﺘـﺸــﺎرﻳـﻮن‬


Sr # Initials Name Position Contact
MOOA 0506260037
01 3848
MOHAMMAD E. OSMAN SITE MANAGER elmagzoub@yahoo.com
MMQA 0509633596
02 6372
MIAN MAQBOOL AHMAD AZAD CIVIL ENGINEER maqboolazad@gmail.com
YOHS 0551378145
03 8072
SYED YOUNUS HASHMI STRUCTURAL ENGINEER syedyh58@gmail.com
AASN ALI ABDULLAH SHAABAN AL 0536665997
04 CIVIL ENGINEER
8725 SHAABAN eng.alembrator@hotmail.com
MABO 0509942554
05 8195
MOHAMMED ABO ALSOUD ELECTRICAL ENGINEER mohamad_23n@yahoo.com
SYAH 0567352639
06 3807
SYED ANWAR HUSSAIN MECHANICAL ENGINEER anwarzfp@yahoo.com
EHAE 0595236158
07 8633
EL SAYED HUSSEIN BAKKAR MECHANICAL ENGINEER elsayedbakkar@yahoo.com
ROSF 0550884701
08 6354
RONALDO FRANCISCO ARCHITECT franciscoronaldo71@yahoo.com
VDF 0556314465
09 8737
VIRGILIO D. FLORES ARCHITECT vir_flo@yahoo.com
MALA 0550771435
10 5518
MAHMOUD AL-JOHRI CIVIL INSPECTOR almassry2008@yahoo.com
HAAL 0502940517
11 4113
HYDER ABBAS ABDUL LATIF CIVIL INSPECTOR ahmed-haidar401@gmail.com
AAZD 0508357299
12 6258
ABDAL AZIZ AHMAD CIVIL INSPECTOR abd_alaziz2020@yahoo.com
0000 JAVED MAHMOOD MUHAMMAD 0542599786
13 CIVIL INSPECTOR
8473 SAFDAR jmahmood555@gmail.com
ALY
14 3335
ADEL LAHQU AL- YAZIDI CIVIL INSPECTOR 0505761976

SAMQ 0551950640
15 6531
SAEED ALI AL QARNI CIVIL INSPECTOR alisaeed_79@yahoo.com
MRRA 0541837815
16 8069
MUBASHAR RASHID SURVEYOR mubasharone@yahoo.com
AELN 0596443302
17 8194
AYMAN AL-TOOKHY MECHANICAL INSPECTOR Algendy_ayman@yahoo.com
HMSD 0594818352
18 8267
SYED HAMED MUNEER MECHANICAL INSPECTOR syedhm@yahoo.co.in
ARSD 0590635783
19 8293
ABDUL RAHMAN AL-AHMAD MECHANICAL INSPECTOR abdalrahman323@hotmail.com
ASA 0597829496
20 7640
AMIR SHAHZAD AMIR MECHANICAL INSPECTOR amrshzd@gmail.com
IGR 0554147655
21 3738
IJAZ GHANI RAZAQ ELECTRICAL INSPECTOR Igkhyber28@yahoo.com
ALID 0540909213
22 6428
AHMAD ALI AL-DAMRAWY ELECTRICAL INSPECTOR zahmed8024@yahoo.com
MTUK 0534119805
23 8298
MOHAMMAD TAHSEEN KHAJA ELECTRICAL INSPECTOR khajatahseen@gmail.com
ASSE 0566425417
24 4920
ASHRAF AHMED SHARAF ELDEEN ELECTRICAL INSPECTOR a-sh-kr@hotmail.com
ELAA 0564464407
25 8286
ALI AHMAD AL-ASMARI ARCH INSPECTOR eng.relax@hotmail.com
MMLH 0502947949
26 5825
MOAWIA MOHAMMAD AL-HADI DOCUMENT CONTROLLER Moawia.alhadi@gmail.com
0532320887
JKH
27 7349
JAMSHED KHAN SECRETARY jkhan@zfp.com
jamshed4pk@yahoo.com
8.0 ATTACHMENTS

8.8 Manpower Histogram


RESOURCE HISTOGRAM
KING FIASAL MEDICAL CITY (KFMC) PHASE 1 - ASEER REGION

AVERAGE MANPOWER PLAN


40000 4000
Monthly Plan
Monthly Actual
35000 Cum. Plan
3500

Cum. Actual
30000 3000

25000 2500

2192

2075
2068
2039
2021

1835

1774
20000 2000

1705
1661
15000 1500

1202
820
805

796
10000 1000

650
596
515

475
421
407

388

375

369
360
324
313
5000 500

274

263
254

252
230

221

221
216
213
196

193
147

137
103
63

63

52
36

36

36

36

36
30
28

14
10

10

10
7

9
0

0 0
Oct-12

Oct-13

Oct-14
Jul-12

Aug-12

Dec-12

Jan-13

Apr-13

Jun-13

Jul-13

Aug-13

Dec-13

Jan-14

Apr-14

Jun-14

Jul-14

Aug-14

Dec-14

Jan-15

Apr-15
Sep-12

Nov-12

Feb-13

Mar-13

Sep-13

Nov-13

Feb-14

Mar-14

Sep-14

Nov-14

Feb-15

Mar-15
May-13

May-14

May-15
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Time in Months Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15
Monthly Plan 7 8 10 9 10 10 30 14 8 9 9 52 137 407 421 515 596 805 796 650 820 1202 1661 2021 1835 2192 2039 1774 2068 2075 1705 2158 3501 2794 1631
Monthly Actual 0 0 28 36 36 36 36 36 63 63 103 147 196 254 230 193 213 216 221 252 274 313 324 388 375 360 369 221 263 475
Cum. Plan 7 15 25 34 44 54 84 98 106 115 124 176 313 720 1141 1656 2252 3057 3853 4503 5323 6525 8186 10207 12042 14234 16273 18047 20115 22190 23895 26053 29554 32348 33979
Cum. Actual 0 0 28 64 100 136 172 208 271 334 437 584 780 1034 1264 1457 1670 1886 2107 2359 2633 2946 3270 3658 4033 4393 4762 4983 5246 5721
8.0 ATTACHMENTS

8.9 Schedules
Updated Summary Bar Chart KING FAISAL MEDICAL CITY - UPDATED
as of Data Date 18-Dec-14

Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Total Budgeted Total Planned Value Earned Value Schedule % Performance % 2012 2013 2014 2015 2016
Duration Float Cost Cost Cost Complete Complete
1339 31-Mar-12 13-Aug-16 31-Mar-12 A 13-Aug-16 -378 R642,235,175 R365,605,132 R97,018,332 56.93% 15.11%
KING FAISAL MEDICAL CITY - UPDATED
GENERAL REQUIREMENTS 1339 31-Mar-12 13-Aug-16 31-Mar-12 A 13-Aug-16 -378 R0 R0 R0 0% 0%

MILESTONES 1339 31-Mar-12 13-Aug-16 31-Mar-12 A 13-Aug-16 -378 R0 R0 R0 0% 0%


MOBILIZATION 141 01-Jul-12 22-Dec-12 01-Jul-12 A 22-Dec-12 A R0 R0 R0 0% 0% MOBILIZATION
TEMPORARY FACILITIES PREPARING READY FOR USE 141 01-Jul-12 22-Dec-12 01-Jul-12 A 22-Dec-12 A R0 R0 R0 0% 0% TEMPORARY FACILITIES PREPARING READY FOR USE
SAFETY REQUIREMENTS FOR SITE AND OFFICES 60 01-Sep-12 14-Nov-12 01-Sep-12 A 14-Nov-12 A R0 R0 R0 0% 0% SAFETY REQUIREMENTS FOR SITE AND OFFICES
SITE & BUILDING INFRASTRUCTURE PLANNING 90 01-Jul-12 18-Oct-12 01-Jul-12 A 18-Oct-12 A R0 R0 R0 0% 0% SITE & BUILDING INFRASTRUCTURE PLANNING
GOVERNMENTAL AGENCY PERMITS & APPROVALS. 90 01-Jul-12 18-Oct-12 01-Jul-12 A 18-Oct-12 A R0 R0 R0 0% 0% GOVERNMENTAL AGENCY PERMITS & APPROVALS
ENGINEERING 1241 01-Jul-12 20-Jul-16 01-Jul-12 A 20-Jul-16 -359 R0 R0 R0 0% 0%
SITE INVESTIGATION 71 01-Oct-12 26-Dec-12 01-Oct-12 A 26-Dec-12 A R0 R0 R0 0% 0% SITE INVESTIGATION
PERMANENT UTILITIES CONNECTION PREPARATION 60 18-Dec-14 25-Feb-15 18-Dec-14 25-Feb-15 79 R0 R0 R0 0% 0% PERMANENT UTILITIES CONNECTION P
MEDICAL EQUIPMENT PLANNING ( BY OTHERS ) 90 01-Jul-12 18-Oct-12 01-Jul-12 A 18-Oct-12 A R0 R0 R0 0% 0% MEDICAL EQUIPMENT PLANNING ( BY OTHERS
DESIGN 62 31-Mar-13 11-Jun-13 31-Mar-13 A 11-Jun-13 A R0 R0 R0 0% 0% DESIGN
Submittal Date by FTCO 43 31-Mar-13 20-May-13 31-Mar-13 A 20-May-13 A R0 R0 R0 0% 0% Submittal Date by FTCO
Review & Approval Period by HI / MOH 62 01-Apr-13 11-Jun-13 01-Apr-13 A 11-Jun-13 A R0 R0 R0 0% 0% Review & Approval Period by HI / MOH
SHOPDRAWINGS SUBMITTAL & APPROVAL 664 10-Jun-13 16-Aug-15 10-Jun-13 A 16-Aug-15 -340 R0 R0 R0 0% 0% SHOPDRAWINGS SUBMITTAL
ARCHITECTURAL SHOPDR AWINGS 595 04-Sep-13 16-Aug-15 01-Aug-13 A 16-Aug-15 -340 R0 R0 R0 0% 0% ARCHITECTURAL SHOPDRAWING
Submittal Date 581 04-Sep-13 30-Jul-15 01-Aug-13 A 30-Jul-15 -340 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 581 21-Sep-13 16-Aug-15 24-Aug-13 A 16-Aug-15 -340 R0 R0 R0 0% 0% Review & Approval Period by Consul
CIVIL / STRUC TURAL SHOPD RAWINGS 503 10-Jun-13 09-Feb-15 10-Jun-13 A 09-Feb-15 -179 R0 R0 R0 0% 0% CIVIL / STRUCTURAL SHOPDRAWINGS
Submittal Date 489 10-Jun-13 24-Jan-15 10-Jun-13 A 24-Jan-15 -179 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 489 26-Jun-13 09-Feb-15 26-Jun-13 A 09-Feb-15 -179 R0 R0 R0 0% 0% Review & Approval Period by Consultant
MECHANICAL SHOPDRAWINGS 474 04-Sep-13 28-Mar-15 01-Aug-13 A 28-Mar-15 -219 R0 R0 R0 0% 0% MECHANICAL SHOPDRAWINGS
Submittal Date 460 04-Sep-13 11-Mar-15 01-Aug-13 A 11-Mar-15 -315 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 460 21-Sep-13 28-Mar-15 24-Aug-13 A 28-Mar-15 -219 R0 R0 R0 0% 0% Review & Approval Period by Consultant
ELEC TRIC AL SHOPD RAWINGS 571 07-Sep-13 21-Jul-15 05-Aug-13 A 21-Jul-15 -318 R0 R0 R0 0% 0% ELECTRICAL SHOPDRAWINGS
Submittal Date 557 07-Sep-13 05-Jul-15 05-Aug-13 A 05-Jul-15 -364 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 559 21-Sep-13 21-Jul-15 27-Aug-13 A 21-Jul-15 -318 R0 R0 R0 0% 0% Review & Approval Period by Consulta
MATERIALS SUBMITTAL & APPROVAL 698 25-May-13 10-Sep-15 05-Nov-12 A 10-Sep-15 -165 R0 R0 R0 0% 0% MATERIALS SUBMITTAL
MATERIALS FOR MAIN BUILDING & CUP BUILDING 660 25-May-13 28-Jul-15 05-Nov-12 A 28-Jul-15 -195 R0 R0 R0 0% 0% MATERIALS FOR MAIN BUILDING
CIVIL / ARCHITECTURAL MATERIALS 660 25-May-13 28-Jul-15 23-Dec-12 A 28-Jul-15 -197 R0 R0 R0 0% 0% CIVIL / ARCHITECTURAL MATERIAL
METALS 50 19-May-15 16-Jul-15 19-May-15 16-Jul-15 -207 R0 R0 R0 0% 0% METALS
Submittal Date 26 19-May-15 18-Jun-15 19-May-15 18-Jun-15 -207 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 50 19-May-15 16-Jul-15 19-May-15 16-Jul-15 -207 R0 R0 R0 0% 0% Review & Approval Period by Consulta
WOOD & PLASTICS 24 19-Apr-15 17-May-15 19-Apr-15 17-May-15 -189 R0 R0 R0 0% 0% WOOD & PLASTICS
Submittal Date 0 19-Apr-15 19-Apr-15 19-Apr-15 19-Apr-15 -189 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 19-Apr-15 17-May-15 19-Apr-15 17-May-15 -189 R0 R0 R0 0% 0% Review & Approval Period by Consultan
THERMAL PR OTECTION 660 25-May-13 28-Jul-15 23-Dec-12 A 28-Jul-15 -206 R0 R0 R0 0% 0% THERMAL PROTECTION
Submittal Date 636 25-May-13 30-Jun-15 23-Dec-12 A 30-Jun-15 -206 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 660 26-May-13 28-Jul-15 23-Dec-12 A 28-Jul-15 -206 R0 R0 R0 0% 0% Review & Approval Period by Consult
DOORS 50 19-Mar-15 17-May-15 19-Mar-15 17-May-15 -225 R0 R0 R0 0% 0% DOORS
Submittal Date 26 19-Mar-15 19-Apr-15 19-Mar-15 19-Apr-15 -225 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 50 19-Mar-15 17-May-15 19-Mar-15 17-May-15 -225 R0 R0 R0 0% 0% Review & Approval Period by Consultan
WINDOWS / CURTAIN WALLS / GLAZING 128 18-Dec-14 17-May-15 18-Dec-14 17-May-15 -225 R0 R0 R0 0% 0% WINDOWS / CURTAIN WALLS
Submittal Date 104 18-Dec-14 19-Apr-15 18-Dec-14 19-Apr-15 -225 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 128 18-Dec-14 17-May-15 18-Dec-14 17-May-15 -225 R0 R0 R0 0% 0% Review & Approval Period by Consultan
FINISHINGS 180 18-Dec-14 16-Jul-15 18-Dec-14 16-Jul-15 -187 R0 R0 R0 0% 0% FINISH INGS
Submittal Date 156 18-Dec-14 18-Jun-15 18-Dec-14 18-Jun-15 -187 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 180 18-Dec-14 16-Jul-15 18-Dec-14 16-Jul-15 -187 R0 R0 R0 0% 0% Review & Approval Period by Consulta
SPECIALTIES 80 12-Feb-15 17-May-15 12-Feb-15 17-May-15 -189 R0 R0 R0 0% 0% SPECIALTIES
Submittal Date 56 12-Feb-15 19-Apr-15 12-Feb-15 19-Apr-15 -189 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 80 12-Feb-15 17-May-15 12-Feb-15 17-May-15 -189 R0 R0 R0 0% 0% Review & Approval Period by Consultan
MECHANICAL MATERIALS 592 01-Aug-13 16-Jul-15 04-May-13 A 16-Jul-15 -185 R0 R0 R0 0% 0% MECHANICAL MAT ERIALS

Page 1 of 7 This Baseline Schedule was prepared in response to Hill International request and that the same Schedule shall not relinquish Project Baseline
P. ID:KFMC UPDT 18DEC14 our right to claim for any additional Time and Cost as a consequence of the New Design of the Contract Project.
DD:18-Dec-14 FTCO will exert its utmost efforts to complete the Project within the Original Contract Duration as presented in the Summary
Print Date:21-Dec-14 Baseline Schedule. This schedule includes all those new introduced Items which require a New Rates as well as an prior
Baseline: KFMC DD Approval from MOH as per the contract to start any related activities & shopdrawings.
01AUG13 Fast tracking and Crashing of Activities are applied to this Baseline Schedule with which substantial additional Resources are
introduced, which entails additional Cost that will be submitted for MOH approval in due course.
Updated Summary Bar Chart KING FAISAL MEDICAL CITY - UPDATED
as of Data Date 18-Dec-14

Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Total Budgeted Total Planned Value Earned Value Schedule % Performance % 2012 2013 2014 2015 2016
Duration Float Cost Cost Cost Complete Complete
HVAC 431 16-Feb-14 16-Jul-15 04-May-13 A 16-Jul-15 -186 R0 R0 R0 0% 0% HVAC
Submittal Date 407 16-Feb-14 18-Jun-15 04-May-13 A 18-Jun-15 -186 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 431 17-Feb-14 16-Jul-15 05-May-13 A 16-Jul-15 -186 R0 R0 R0 0% 0% Review & Approval Period by Consulta
HYDRONIC 102 18-Dec-14 16-Apr-15 18-Dec-14 16-Apr-15 -201 R0 R0 R0 0% 0% HYDRONIC
Submittal Date 78 18-Dec-14 19-Mar-15 18-Dec-14 19-Mar-15 -201 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 102 18-Dec-14 16-Apr-15 18-Dec-14 16-Apr-15 -201 R0 R0 R0 0% 0% Review & Approval Period by Consultant
WATER SUPPLY SYSTEM 518 06-Nov-13 16-Jul-15 14-Jul-13 A 16-Jul-15 -185 R0 R0 R0 0% 0% WATER SUPPLY SYSTEM
Submittal Date 494 06-Nov-13 18-Jun-15 14-Jul-13 A 18-Jun-15 -185 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 518 07-Nov-13 16-Jul-15 14-Jul-13 A 16-Jul-15 -185 R0 R0 R0 0% 0% Review & Approval Period by Consulta
DRAINAGE SYSTEM 592 01-Aug-13 16-Jul-15 14-Jul-13 A 16-Jul-15 -197 R0 R0 R0 0% 0% DRAINAGE SYSTEM
Submittal Date 568 01-Aug-13 18-Jun-15 14-Jul-13 A 18-Jun-15 -197 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 568 04-Sep-13 16-Jul-15 14-Jul-13 A 16-Jul-15 -197 R0 R0 R0 0% 0% Review & Approval Period by Consulta
MED GAS SYSTEM 154 18-Dec-14 16-Jun-15 18-Dec-14 16-Jun-15 -316 R0 R0 R0 0% 0% MED GAS SYSTEM
Submittal Date 130 18-Dec-14 19-May-15 18-Dec-14 19-May-15 -316 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 154 18-Dec-14 16-Jun-15 18-Dec-14 16-Jun-15 -316 R0 R0 R0 0% 0% Review & Approval Period by Consulta
FIRE FIGHTING SYSTEM 466 06-Nov-13 17-May-15 08-Jun-13 A 17-May-15 -165 R0 R0 R0 0% 0% FIRE FIGHTING SYSTEM
Submittal Date 442 06-Nov-13 19-Apr-15 08-Jun-13 A 19-Apr-15 -165 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 466 07-Nov-13 17-May-15 09-Jun-13 A 17-May-15 -165 R0 R0 R0 0% 0% Review & Approval Period by Consultan
BMS SYSTEM 24 18-Jan-15 15-Feb-15 18-Jan-15 15-Feb-15 -191 R0 R0 R0 0% 0% BMS SYSTEM
Submittal Date 0 18-Jan-15 18-Jan-15 18-Jan-15 18-Jan-15 -191 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 18-Jan-15 15-Feb-15 18-Jan-15 15-Feb-15 -191 R0 R0 R0 0% 0% Review & Approval Period by Consultant
ELECTRICAL MATERIALS 566 01-Aug-13 16-Jun-15 05-Nov-12 A 16-Jun-15 -178 R0 R0 R0 0% 0% ELECTRICAL MATERIALS
POWER DISTRIBUTION, CABLE TR AY & WIRE WAYS 492 06-Nov-13 16-Jun-15 05-Nov-12 A 16-Jun-15 -199 R0 R0 R0 0% 0% POWER DISTRIBUTION
Submittal Date 468 06-Nov-13 19-May-15 05-Nov-12 A 19-May-15 -199 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 492 07-Nov-13 16-Jun-15 06-Nov-12 A 16-Jun-15 -199 R0 R0 R0 0% 0% Review & Approval Period by Consulta
GROUND ING SYSTEM 48 01-Aug-13 02-Oct-13 01-Aug-13 A 02-Oct-13 A R0 R0 R0 0% 0% GROUNDING SYSTEM
Submittal Date 0 01-Aug-13 01-Aug-13 01-Aug-13 A 01-Aug-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 04-Sep-13 02-Oct-13 01-Aug-13 A 02-Oct-13 A R0 R0 R0 0% 0% Review & Approval Period by Consultant
LIGHTING SYSTEM 24 19-Mar-15 16-Apr-15 19-Mar-15 16-Apr-15 -170 R0 R0 R0 0% 0% LIGHTING SYSTEM
Submittal Date 0 19-Mar-15 19-Mar-15 19-Mar-15 19-Mar-15 -170 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 19-Mar-15 16-Apr-15 19-Mar-15 16-Apr-15 -170 R0 R0 R0 0% 0% Review & Approval Period by Consultant
POWER LAYOUT (GENERAL POWER)
POWER 24 19-Mar-15 16-Apr-15 19-Mar-15 16-Apr-15 -181 R0 R0 R0 0% 0% POWER LAYOUT
Submittal Date 0 19-Mar-15 19-Mar-15 19-Mar-15 19-Mar-15 -181 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 19-Mar-15 16-Apr-15 19-Mar-15 16-Apr-15 -181 R0 R0 R0 0% 0% Review & Approval Period by Consultant
PU BLIC ADDRESS SYSTEM 389 07-Nov-13 16-Feb-15 22-Oct-13 A 16-Feb-15 -213 R0 R0 R0 0% 0% PU BLIC ADDRESS SYST EM
Submittal Date 0 07-Nov-13 07-Nov-13 22-Oct-13 A 22-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 20-Jan-15 16-Feb-15 20-Jan-15 16-Feb-15 -213 R0 R0 R0 0% 0% Review & Approval Period by Consultant
MASTER CLOCK SYSTEM 24 27-Oct-13 24-Nov-13 13-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% MASTER CLOCK SYSTEM
Submittal Date 0 27-Oct-13 27-Oct-13 13-Oct-13 A 13-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 27-Oct-13 24-Nov-13 19-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% Review & Approval Period by Consultant
NURSE CALL SYSTEMS 24 27-Oct-13 24-Nov-13 13-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% NURSE CALL SYSTEMS
Submittal Date 0 27-Oct-13 27-Oct-13 13-Oct-13 A 13-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 27-Oct-13 24-Nov-13 19-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% Review & Approval Period by Consultant
INTERCOM SYSTEM 24 27-Oct-13 24-Nov-13 13-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% INTERCOM SYSTEM
Submittal Date 0 27-Oct-13 27-Oct-13 13-Oct-13 A 13-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 27-Oct-13 24-Nov-13 19-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% Review & Approval Period by Consultant
STRUCTURED CABLING 502 27-Oct-13 16-Jun-15 13-Oct-13 A 16-Jun-15 -184 R0 R0 R0 0% 0% STRUCTURED CABLING
Submittal Date 478 27-Oct-13 19-May-15 13-Oct-13 A 19-May-15 -184 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 502 27-Oct-13 16-Jun-15 19-Oct-13 A 16-Jun-15 -184 R0 R0 R0 0% 0% Review & Approval Period by Consulta
MATV SYSTEM 24 27-Oct-13 24-Nov-13 13-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% MATV SYSTEM
Submittal Date 0 27-Oct-13 27-Oct-13 13-Oct-13 A 13-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 27-Oct-13 24-Nov-13 19-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% Review & Approval Period by Consultant
AUDIO VISUAL SYSTEMS 24 11-Sep-13 10-Oct-13 04-Aug-13 A 10-Oct-13 A R0 R0 R0 0% 0% AUDIO VISU AL SYSTEMS
Submittal Date 0 11-Sep-13 11-Sep-13 11-Sep-13 A 11-Sep-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 11-Sep-13 10-Oct-13 04-Aug-13 A 10-Oct-13 A R0 R0 R0 0% 0% Review & Approval Period by Consultant

Page 2 of 7 This Baseline Schedule was prepared in response to Hill International request and that the same Schedule shall not relinquish Project Baseline
P. ID:KFMC UPDT 18DEC14 our right to claim for any additional Time and Cost as a consequence of the New Design of the Contract Project.
DD:18-Dec-14 FTCO will exert its utmost efforts to complete the Project within the Original Contract Duration as presented in the Summary
Print Date:21-Dec-14 Baseline Schedule. This schedule includes all those new introduced Items which require a New Rates as well as an prior
Baseline: KFMC DD Approval from MOH as per the contract to start any related activities & shopdrawings.
01AUG13 Fast tracking and Crashing of Activities are applied to this Baseline Schedule with which substantial additional Resources are
introduced, which entails additional Cost that will be submitted for MOH approval in due course.
Updated Summary Bar Chart KING FAISAL MEDICAL CITY - UPDATED
as of Data Date 18-Dec-14

Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Total Budgeted Total Planned Value Earned Value Schedule % Performance % 2012 2013 2014 2015 2016
Duration Float Cost Cost Cost Complete Complete
IP CC TV SYSTEMS 24 27-Oct-13 24-Nov-13 13-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% IP CCTV SYSTEMS
Submittal Date 0 27-Oct-13 27-Oct-13 13-Oct-13 A 13-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 27-Oct-13 24-Nov-13 19-Oct-13 A 10-Jan-15 -201 R0 R0 R0 0% 0% Review & Approval Period by Consultant
IP ACCESS CONTROL SYSTEM 24 23-Oct-13 20-Nov-13 02-Oct-13 A 29-Dec-14 -155 R0 R0 R0 0% 0% IP ACCESS CONTROL SYSTEM
Submittal Date 0 23-Oct-13 23-Oct-13 02-Oct-13 A 02-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 23-Oct-13 20-Nov-13 03-Oct-13 A 29-Dec-14 -155 R0 R0 R0 0% 0% Review & Approval Period by Consultant
FIRE ALARM SYSTEM 24 23-Oct-13 20-Nov-13 09-Oct-13 A 06-Jan-15 -199 R0 R0 R0 0% 0% FIRE ALARM SYSTEM
Submittal Date 0 23-Oct-13 23-Oct-13 09-Oct-13 A 09-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 23-Oct-13 20-Nov-13 10-Oct-13 A 06-Jan-15 -199 R0 R0 R0 0% 0% Review & Approval Period by Consultant
ELEVATOR SYSTEM 24 23-Oct-13 20-Nov-13 29-Sep-13 A 09-Oct-13 A R0 R0 R0 0% 0% ELEVATOR SYSTEM
Submittal Date 0 23-Oct-13 23-Oct-13 09-Oct-13 A 09-Oct-13 A R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 24 23-Oct-13 20-Nov-13 29-Sep-13 A 03-Oct-13 A R0 R0 R0 0% 0% Review & Approval Period by Consultant
MATERIALS FOR SITE DEVELOPMENT 187 03-Feb-15 10-Sep-15 03-Feb-15 10-Sep-15 -165 R0 R0 R0 0% 0% MATERIALS FOR SITE DEVELOPM
EXTERNAL CIVIL / ARCHITECTURAL MATERIALS 187 03-Feb-15 10-Sep-15 03-Feb-15 10-Sep-15 -165 R0 R0 R0 0% 0% EXTERNAL CIVIL
Submittal Date 163 03-Feb-15 13-Aug-15 03-Feb-15 13-Aug-15 -165 R0 R0 R0 0% 0% Submittal Date
Review & Approval Period by Consultant 187 04-Feb-15 10-Sep-15 04-Feb-15 10-Sep-15 -165 R0 R0 R0 0% 0% Review &
STATEMENT OF METHOD OF CONSTRUCTION & RFI 1241 01-Jul-12 20-Jul-16 01-Jul-12 A 20-Jul-16 -363 R0 R0 R0 0% 0%
PROCUREMENT 591 26-Oct-13 27-Sep-15 03-Dec-12 A 27-Sep-15 -163 R0 R0 R0 0% 0% PROCUR EMENT
PROCURE MATERIALS FOR MAIN BUILDING 591 26-Oct-13 27-Sep-15 03-Dec-12 A 27-Sep-15 -163 R0 R0 R0 0% 0% PROCUR E MATERIALS FOR MAIN
CIVIL / ARCHITECTURAL MATERIALS 591 26-Oct-13 27-Sep-15 03-Dec-12 A 27-Sep-15 -163 R0 R0 R0 0% 0% CIVIL / ARCHITECTURAL MATERI
METALS 88 16-Jun-15 27-Sep-15 16-Jun-15 27-Sep-15 -207 R0 R0 R0 0% 0% METALS
WOOD & PLASTICS 114 17-May-15 27-Sep-15 17-May-15 27-Sep-15 -189 R0 R0 R0 0% 0% WOOD &
THERMAL PROTECTION 591 26-Oct-13 27-Sep-15 03-Dec-12 A 27-Sep-15 -206 R0 R0 R0 0% 0% THERMAL PROTECTION
DOORS 140 16-Apr-15 27-Sep-15 16-Apr-15 27-Sep-15 -225 R0 R0 R0 0% 0% DOORS
WINDOWS / CURTAIN WALLS / GLAZING 218 15-Jan-15 27-Sep-15 15-Jan-15 27-Sep-15 -225 R0 R0 R0 0% 0% WINDOWS
FINISHINGS 218 15-Jan-15 27-Sep-15 15-Jan-15 27-Sep-15 -187 R0 R0 R0 0% 0% FINISHINGS
SPECIALTIES 170 12-Mar-15 27-Sep-15 12-Mar-15 27-Sep-15 -163 R0 R0 R0 0% 0% SPECIALTIES
MECHANICAL MATERIALS 242 18-Dec-14 27-Sep-15 18-Dec-14 27-Sep-15 -165 R0 R0 R0 0% 0% MECHANICAL MAT ERIALS
HVAC 218 15-Jan-15 27-Sep-15 15-Jan-15 27-Sep-15 -186 R0 R0 R0 0% 0% HVAC
HYDRONIC 218 15-Jan-15 27-Sep-15 15-Jan-15 27-Sep-15 -201 R0 R0 R0 0% 0% HYDRONIC
WATER SUPPLY SYSTEM 218 15-Jan-15 27-Sep-15 15-Jan-15 27-Sep-15 -185 R0 R0 R0 0% 0% WATER SUPPLY SYSTEM
DRAINAGE SYSTEM 218 15-Jan-15 27-Sep-15 15-Jan-15 27-Sep-15 -181 R0 R0 R0 0% 0% DRAINAGE SYSTEM
MED GAS SYSTEM 192 15-Jan-15 27-Aug-15 15-Jan-15 27-Aug-15 -316 R0 R0 R0 0% 0% MED GAS SYSTEM
FIRE FIGHTING SYSTEM 242 18-Dec-14 27-Sep-15 18-Dec-14 27-Sep-15 -165 R0 R0 R0 0% 0% FIRE FIGHTING SYSTEM
BMS SYSTEM 192 15-Feb-15 27-Sep-15 15-Feb-15 27-Sep-15 -191 R0 R0 R0 0% 0% BMS SYSTEM
ELEC TRIC AL MATERIALS 591 26-Oct-13 27-Sep-15 03-Oct-13 A 27-Sep-15 -170 R0 R0 R0 0% 0% ELECTRICAL MATERIALS
POWER DISTRIBUTION, CABLE TRAY & WIRE WAYS 242 18-Dec-14 27-Sep-15 18-Dec-14 27-Sep-15 -186 R0 R0 R0 0% 0% POWER DISTRIBUTION
GROUNDING SYSTEM 62 26-Oct-13 05-Jan-14 03-Oct-13 A 28-Feb-15 -24 R0 R0 R0 0% 0% GROUNDING SYSTEM
LIGHTING SYSTEM 140 16-Apr-15 27-Sep-15 16-Apr-15 27-Sep-15 -170 R0 R0 R0 0% 0% LIGHTING SYSTEM
POWER LAYOUT (GENERAL POWER)
POWER 140 16-Apr-15 27-Sep-15 16-Apr-15 27-Sep-15 -181 R0 R0 R0 0% 0% POWER LAYOUT
PUBLIC ADDRESS SYSTEM 88 17-Feb-15 30-May-15 17-Feb-15 30-May-15 -213 R0 R0 R0 0% 0% PU BLIC ADDRESS SYST EM
MASTER CLOCK SYSTEM 88 10-Jan-15 22-Apr-15 10-Jan-15 22-Apr-15 -201 R0 R0 R0 0% 0% MASTER CLOCK SYSTEM
NURSE CALL SYSTEMS 88 10-Jan-15 22-Apr-15 10-Jan-15 22-Apr-15 -201 R0 R0 R0 0% 0% NURSE CALL SYSTEMS
INTERCOM SYSTEM 88 10-Jan-15 22-Apr-15 10-Jan-15 22-Apr-15 -201 R0 R0 R0 0% 0% INTERCOM SYSTEM
STRUCTURED CABLING 223 10-Jan-15 27-Sep-15 10-Jan-15 27-Sep-15 -184 R0 R0 R0 0% 0% STRUCTURED CABLING
MATV SYSTEM 88 10-Jan-15 22-Apr-15 10-Jan-15 22-Apr-15 -201 R0 R0 R0 0% 0% MATV SYSTEM
AUDIO VISUAL SYSTEMS 140 18-Dec-14 30-May-15 18-Dec-14 30-May-15 -213 R0 R0 R0 0% 0% AUDIO VISU AL SYSTEMS
IP CCTV SYSTEMS 88 10-Jan-15 22-Apr-15 10-Jan-15 22-Apr-15 -201 R0 R0 R0 0% 0% IP CCTV SYSTEMS
IP ACCESS CONTROL SYSTEM 88 30-Dec-14 11-Apr-15 30-Dec-14 11-Apr-15 -155 R0 R0 R0 0% 0% IP ACCESS CONTROL SYSTEM
FIRE ALARM SYSTEM 88 07-Jan-15 19-Apr-15 07-Jan-15 19-Apr-15 -199 R0 R0 R0 0% 0% FIRE ALARM SYSTEM
ELEVATOR SYSTEM 208 18-Dec-14 17-Aug-15 18-Dec-14 17-Aug-15 -249 R0 R0 R0 0% 0% ELEVATOR SYSTEM
PROCURE MATERIALS FOR SITE DEVELOPMENT 177 04-Mar-15 27-Sep-15 04-Mar-15 27-Sep-15 -165 R0 R0 R0 0% 0% PROCUR E MATERIALS FOR SITE
CIVIL / ARCITECTURAL MATERIALS 177 04-Mar-15 27-Sep-15 04-Mar-15 27-Sep-15 -165 R0 R0 R0 0% 0% CIVIL / ARCITEC TURAL MATERIAL

CONSTRUCTION - MAIN HOSPITAL 500-BED PHASE 1 1252 10-Jul-12 13-Aug-16 10-Jul-12 A 13-Aug-16 -378 R642,235,175 R365,605,132 R97,018,332 56.93% 15.11%

MAIN BUILDING ( replacing main buiding and dialysis center,


center mosque, MS in tender ) 1252 10-Jul-12 13-Aug-16 10-Jul-12 A 13-Aug-16 -378 R514,609,120 R283,197,641 R96,988,925 55.03% 18.85%
Page 3 of 7 This Baseline Schedule was prepared in response to Hill International request and that the same Schedule shall not relinquish Project Baseline
P. ID:KFMC UPDT 18DEC14 our right to claim for any additional Time and Cost as a consequence of the New Design of the Contract Project.
DD:18-Dec-14 FTCO will exert its utmost efforts to complete the Project within the Original Contract Duration as presented in the Summary
Print Date:21-Dec-14 Baseline Schedule. This schedule includes all those new introduced Items which require a New Rates as well as an prior
Baseline: KFMC DD Approval from MOH as per the contract to start any related activities & shopdrawings.
01AUG13 Fast tracking and Crashing of Activities are applied to this Baseline Schedule with which substantial additional Resources are
introduced, which entails additional Cost that will be submitted for MOH approval in due course.
Updated Summary Bar Chart KING FAISAL MEDICAL CITY - UPDATED
as of Data Date 18-Dec-14

Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Total Budgeted Total Planned Value Earned Value Schedule % Performance % 2012 2013 2014 2015 2016
Duration Float Cost Cost Cost Complete Complete
EARTHWORKS 821 10-Jul-12 29-Mar-15 10-Jul-12 A 22-Apr-15 -48 R14,019,057 R14,019,057 R11,077,435 100% 79.02% EAR THWOR KS
CONCRETE WORKS 962 23-Jan-13 14-Mar-16 23-Jan-13 A 14-Mar-16 -323 R146,680,089 R140,887,724 R70,242,437 96.05% 47.89% CONCRETE WORKS
SU B-STRUC TURE 283 23-Jan-13 30-Dec-13 23-Jan-13 A 21-Dec-14 -261 R51,623,686 R51,623,686 R51,616,688 100% 99.99% SUB-STRUCTURE
1ST PRIORITY TOWER AREA 262 23-Jan-13 05-Dec-13 23-Jan-13 A 13-May-14 A R23,698,423 R23,698,423 R23,698,423 100% 100% 1ST PRIORITY TOW ER AREA
ZONE-1-MIDDLE BAY BETWEEN THE TWO EXPANSION JOINTS 248 23-Jan-13 19-Nov-13 23-Jan-13 A 13-May-14 A R3,681,398 R3,681,398 R3,681,398 100% 100% ZONE-1-MIDDLE BAY BETWEEN THE TWO EXPA
C7 248 23-Jan-13 19-Nov-13 23-Jan-13 A 13-May-14 A R3,681,398 R3,681,398 R3,681,398 100% 100% C7
ZONE-2-NORTH BAY 243 23-Jan-13 13-Nov-13 23-Jan-13 A 17-Apr-14 A R9,914,169 R9,914,169 R9,914,169 100% 100% ZONE-2-NORTH BAY
C5 232 23-Jan-13 31-Oct-13 23-Jan-13 A 27-Mar-14 A R3,178,932 R3,178,932 R3,178,932 100% 100% C5
C3 216 23-Jan-13 08-Oct-13 23-Jan-13 A 17-Apr-14 A R3,367,619 R3,367,619 R3,367,619 100% 100% C3
C1 243 23-Jan-13 13-Nov-13 23-Jan-13 A 14-Apr-14 A R3,367,619 R3,367,619 R3,367,619 100% 100% C1
ZONE-3-SOUTH BAY 262 23-Jan-13 05-Dec-13 23-Jan-13 A 26-Mar-14 A R10,102,856 R10,102,856 R10,102,856 100% 100% ZONE-3-SOUTH BAY
C6 218 23-Jan-13 12-Oct-13 23-Jan-13 A 08-Mar-14 A R3,367,619 R3,367,619 R3,367,619 100% 100% C6
C4 262 23-Jan-13 05-Dec-13 23-Jan-13 A 26-Mar-14 A R3,367,619 R3,367,619 R3,367,619 100% 100% C4
C2 250 23-Jan-13 21-Nov-13 23-Jan-13 A 09-Mar-14 A R3,367,619 R3,367,619 R3,367,619 100% 100% C2
2ND PRIORITY AREA 283 23-Jan-13 30-Dec-13 23-Jan-13 A 21-Dec-14 -268 R27,925,263 R27,925,263 R27,918,265 100% 99.97% 2ND PRIORITY AREA
ZONE-1-MIDDLE BAY BETWEEN THE TWO EXPANSION JOINTS 283 23-Jan-13 30-Dec-13 23-Jan-13 A 21-Dec-14 -268 R7,207,146 R7,207,146 R7,200,148 100% 99.9% ZONE-1-MIDDLE BAY BETWEEN THE TW
C10 250 23-Jan-13 21-Nov-13 23-Jan-13 A 21-Dec-14 -301 R3,293,924 R3,293,924 R3,286,926 100% 99.79% C10
C15 283 23-Jan-13 30-Dec-13 23-Jan-13 A 26-Nov-13 A R3,913,222 R3,913,222 R3,913,222 100% 100% C15
ZONE-2-NORTH BAY 247 23-Jan-13 18-Nov-13 23-Jan-13 A 19-Mar-14 A R10,217,038 R10,217,038 R10,217,038 100% 100% ZONE-2-NORTH BAY
C8 184 23-Jan-13 01-Sep-13 23-Jan-13 A 19-Mar-14 A R3,293,924 R3,293,924 R3,293,924 100% 100% C8
C9 89 01-Jun-13 17-Sep-13 01-Jun-13 A 24-Feb-14 A R3,293,924 R3,293,924 R3,293,924 100% 100% C9
C13 70 24-Aug-13 18-Nov-13 30-Jul-13 A 22-Dec-13 A R3,629,189 R3,629,189 R3,629,189 100% 100% C13
ZONE-3-SOUTH BAY 218 23-Jan-13 10-Oct-13 23-Jan-13 A 16-Apr-14 A R10,501,078 R10,501,078 R10,501,078 100% 100% ZONE-3-SOUTH BAY
C11 206 23-Jan-13 26-Sep-13 23-Jan-13 A 06-Mar-14 A R3,293,924 R3,293,924 R3,293,924 100% 100% C11
C12 102 08-Jun-13 10-Oct-13 11-Mar-13 A 16-Apr-14 A R3,293,924 R3,293,924 R3,293,924 100% 100% C12
C14 186 23-Jan-13 02-Sep-13 23-Jan-13 A 22-Dec-13 A R3,913,230 R3,913,230 R3,913,230 100% 100% C14
SU PER STRUCTURE 644 10-Feb-14 14-Mar-16 05-Feb-14 A 14-Mar-16 -325 R86,296,952 R80,504,587 R18,625,750 93.29% 21.58% SUPER STRUCTURE
1ST PRIORITY TOWER AREA 623 06-Mar-14 14-Mar-16 05-Mar-14 A 14-Mar-16 -325 R67,217,863 R61,425,498 R10,248,033 91.38% 15.25% 1ST PRIORITY TOW ER AREA
ZONE-1-MIDDLE BAY BETWEEN THE TWO EXPANSION JOINTS 416 15-Nov-14 14-Mar-16 13-Nov-14 A 14-Mar-16 -325 R10,426,806 R9,313,500 R712,297 89.32% 6.83% ZONE
C7 416 15-Nov-14 14-Mar-16 13-Nov-14 A 14-Mar-16 -325 R10,426,806 R9,313,500 R712,297 89.32% 6.83% C7
ZONE-2-NORTH BAY 579 24-Apr-14 10-Mar-16 20-Apr-14 A 10-Mar-16 -323 R28,691,353 R25,647,258 R2,863,265 89.39% 9.98% ZONE
C5 553 24-Apr-14 09-Feb-16 20-Apr-14 A 09-Feb-16 -297 R8,972,135 R8,746,303 R1,280,688 97.48% 14.27% C5
C3 579 24-Apr-14 10-Mar-16 20-Apr-14 A 10-Mar-16 -323 R10,747,084 R9,042,128 R829,024 84.14% 7.71% C3
C1 522 31-May-14 09-Feb-16 25-May-14 A 09-Feb-16 -297 R8,972,135 R7,858,828 R753,552 87.59% 8.4% C1
ZONE-3-SOUTH BAY 582 06-Mar-14 26-Jan-16 05-Mar-14 A 26-Jan-16 -284 R28,099,704 R26,464,740 R6,672,471 94.18% 23.75% ZONE
C6 558 06-Mar-14 29-Dec-15 05-Mar-14 A 29-Dec-15 -260 R8,972,135 R8,746,303 R2,396,238 97.48% 26.71% C6
C4 566 25-Mar-14 26-Jan-16 22-Mar-14 A 26-Jan-16 -284 R10,155,434 R8,972,135 R2,192,989 88.35% 21.59% C4
C2 527 24-Apr-14 11-Jan-16 16-Apr-14 A 11-Jan-16 -271 R8,972,135 R8,746,303 R2,083,244 97.48% 23.22% C2
2ND PRIORITY AREA 365 10-Feb-14 22-Apr-15 05-Feb-14 A 22-Apr-15 -99 R19,079,089 R19,079,089 R8,377,716 100% 43.91% 2ND PRIORITY AREA
ZONE-1-MIDDLE BAY BETWEEN THE TWO EXPANSION JOINTS 108 18-Dec-14 22-Apr-15 18-Dec-14 22-Apr-15 -99 R4,480,854 R4,480,854 R0 100% 0% ZONE-1-MIDDLE BAY BETWEEN THE
C10 108 18-Dec-14 22-Apr-15 18-Dec-14 22-Apr-15 -209 R2,818,263 R2,818,263 R0 100% 0% C10
C15 32 18-Dec-14 24-Jan-15 18-Dec-14 24-Jan-15 -23 R1,662,591 R1,662,591 R0 100% 0% C15
ZONE-2-NORTH BAY 286 24-Apr-14 04-Apr-15 20-Apr-14 A 04-Apr-15 -83 R7,299,117 R7,299,117 R2,988,389 100% 40.94% ZONE-2-NORTH BAY
C8 286 24-Apr-14 04-Apr-15 20-Apr-14 A 04-Apr-15 -313 R2,818,263 R2,818,263 R973,979 100% 34.56% C8
C9 286 24-Apr-14 04-Apr-15 20-Apr-14 A 04-Apr-15 -313 R2,818,263 R2,818,263 R803,483 100% 28.51% C9
C13 206 24-Apr-14 31-Dec-14 20-Apr-14 A 31-Dec-14 -3 R1,662,591 R1,662,591 R1,210,927 100% 72.83% C13
ZONE-3-SOUTH BAY 324 10-Feb-14 05-Mar-15 05-Feb-14 A 05-Mar-15 -58 R7,299,117 R7,299,117 R5,389,327 100% 73.84% ZONE-3-SOUTH BAY
C11 273 10-Apr-14 05-Mar-15 05-Apr-14 A 05-Mar-15 -288 R2,818,263 R2,818,263 R2,108,283 100% 74.81% C11
C12 322 10-Feb-14 03-Mar-15 05-Feb-14 A 03-Mar-15 -286 R2,818,263 R2,818,263 R2,070,116 100% 73.45% C12
C14 218 10-Apr-14 31-Dec-14 01-Mar-14 A 31-Dec-14 -3 R1,662,591 R1,662,591 R1,210,927 100% 72.83% C14
EXPANSION JOINT TREATMENT 30 05-Apr-16 10-May-16 05-Apr-16 10-May-16 -297 R0 R0 R0 0% 0% EXPANSION JOINT T REAT
MASONRY WORKS 371 03-Mar-15 09-May-16 03-Mar-15 09-May-16 -326 R20,878,284 R14,236,617 R0 68.19% 0% MASONRY WORKS
METAL WORKS 237 22-Sep-15 25-Jun-16 22-Sep-15 25-Jun-16 -336 R10,453,498 R4,231,565 R0 40.48% 0% METAL WORKS
WOODS & PLASTICS 60 05-Mar-16 14-May-16 05-Mar-16 14-May-16 -300 R7,164,906 R0 R0 0% 0% WOODS
THERMAL & MOISTURE PROTECTION 1034 23-Jan-13 06-Jun-16 23-Jan-13 A 06-Jun-16 -325 R11,374,507 R4,700,761 R4,146,910 41.33% 36.46% THERMAL

Page 4 of 7 This Baseline Schedule was prepared in response to Hill International request and that the same Schedule shall not relinquish Project Baseline
P. ID:KFMC UPDT 18DEC14 our right to claim for any additional Time and Cost as a consequence of the New Design of the Contract Project.
DD:18-Dec-14 FTCO will exert its utmost efforts to complete the Project within the Original Contract Duration as presented in the Summary
Print Date:21-Dec-14 Baseline Schedule. This schedule includes all those new introduced Items which require a New Rates as well as an prior
Baseline: KFMC DD Approval from MOH as per the contract to start any related activities & shopdrawings.
01AUG13 Fast tracking and Crashing of Activities are applied to this Baseline Schedule with which substantial additional Resources are
introduced, which entails additional Cost that will be submitted for MOH approval in due course.
Updated Summary Bar Chart KING FAISAL MEDICAL CITY - UPDATED
as of Data Date 18-Dec-14

Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Total Budgeted Total Planned Value Earned Value Schedule % Performance % 2012 2013 2014 2015 2016
Duration Float Cost Cost Cost Complete Complete
DOORS & WINDOWS 360 20-Jun-15 13-Aug-16 20-Jun-15 13-Aug-16 -378 R42,574,749 R6,923,808 R0 16.26% 0%
FINISHES 360 20-Jun-15 13-Aug-16 20-Jun-15 13-Aug-16 -378 R90,568,484 R52,537,651 R0 58.01% 0%
FLOORS 244 14-Sep-15 25-Jun-16 14-Sep-15 25-Jun-16 -343 R27,714,092 R14,329,233 R0 51.7% 0% FLOORS
WALLS 254 30-Aug-15 21-Jun-16 30-Aug-15 21-Jun-16 -341 R39,396,772 R25,325,726 R0 64.28% 0% WALLS
CEILINGS 233 04-Oct-15 02-Jul-16 04-Oct-15 02-Jul-16 -342 R14,275,447 R6,659,220 R0 46.65% 0% CEILINGS
EXTERNAL FACADE 360 20-Jun-15 13-Aug-16 20-Jun-15 13-Aug-16 -378 R9,182,173 R6,223,472 R0 67.78% 0%
SPECIALTIES 104 28-Feb-16 28-Jun-16 28-Feb-16 28-Jun-16 -339 R8,150,780 R0 R0 0% 0% SPECIALTIES
EQUIPMENT 78 29-Mar-16 28-Jun-16 29-Mar-16 28-Jun-16 -339 R269,644 R0 R0 0% 0% EQUIPMENT
FURNISHINGS 26 29-May-16 28-Jun-16 29-May-16 28-Jun-16 -339 R1,478,291 R0 R0 0% 0% FURNISHINGS
SPECIAL CONSTRUCTION 178 03-Dec-15 28-Jun-16 03-Dec-15 28-Jun-16 -339 R8,522,594 R779,117 R0 9.14% 0% SPECIAL CONST RUCTIO
CONVEYING SYSTEM 180 18-Aug-15 15-Mar-16 18-Aug-15 15-Mar-16 -249 R7,575,376 R7,575,269 R0 100% 0% CONVEYING SYSTEM
MECHANICAL WORKS 719 10-Mar-14 07-Jul-16 26-Aug-13 A 07-Jul-16 -347 R82,451,193 R22,975,558 R6,229,393 27.87% 7.56% MECHANICAL WORKS
1ST & 2ND FIX FOR MECHANIC AL SYSTEMS 702 10-Mar-14 18-Jun-16 26-Aug-13 A 26-Jun-16 -337 R37,088,911 R22,970,586 R6,229,393 61.93% 16.8% 1
HVAC SYSTEM 476 03-Dec-14 11-Jun-16 02-Nov-13 A 11-Jun-16 -324 R14,430,661 R8,939,208 R2,399,009 61.95% 16.62% HVAC SYSTEM
HVAC ACCESSORIES 446 14-Jan-15 18-Jun-16 02-Nov-13 A 18-Jun-16 -330 R2,855,142 R1,684,562 R341,746 59% 11.97% HVAC ACCESSOR IES
CHILLED WATER SYSTEM 539 15-Sep-14 11-Jun-16 02-Nov-13 A 26-Jun-16 -337 R5,943,222 R3,600,920 R731,551 60.59% 12.31% CHILLED WATER SYSTEM
FIRE FIGHTING SYSTEM 559 04-Aug-14 23-May-16 02-Nov-13 A 23-May-16 -320 R4,467,388 R2,818,282 R643,302 63.09% 14.4% FIRE FIGHTING SYSTEM
DRAINAGE / SEWERAGE SYSTEM 693 10-Mar-14 07-Jun-16 26-Aug-13 A 07-Jun-16 -338 R1,726,392 R1,184,217 R337,184 68.59% 19.53% DRAINAGE
WATER SUPPLY SYSTEM 572 23-Jul-14 01-Jun-16 26-Aug-13 A 01-Jun-16 -324 R2,425,044 R2,001,602 R938,161 82.54% 38.69% WATER SUPPLY SYSTEM
MEDICAL GAS SYSTEM 409 19-Feb-15 11-Jun-16 26-Aug-13 A 11-Jun-16 -336 R5,241,062 R2,741,796 R838,441 52.31% 16% MEDICAL GAS SYSTEM
3RD FIX FOR MECHANICAL SYSTEMS 432 19-Feb-15 07-Jul-16 19-Feb-15 07-Jul-16 -347 R45,362,282 R4,972 R0 0.01% 0% 3
ELECTRICAL WORKS 741 10-Feb-14 05-Jul-16 02-Sep-13 A 05-Jul-16 -345 R62,447,667 R14,330,514 R5,292,750 22.95% 8.48% ELECTRICAL W ORKS
ELEC TRIC AL EQUIPMENT & CABLING 363 28-Apr-15 25-Jun-16 28-Apr-15 25-Jun-16 -336 R11,743,043 R2,871,585 R0 24.45% 0% ELECTRICAL EQU IPMENT
1ST & 2ND FIX FOR ELECTRICAL SYSTEMS 721 10-Feb-14 12-Jun-16 02-Sep-13 A 26-Jun-16 -337 R23,415,494 R11,458,929 R5,292,750 48.94% 22.6% 1
LIGHTING SYSTEM - CONDUIT&
CONDUIT WIRING 596 25-Jun-14 01-Jun-16 02-Sep-13 A 01-Jun-16 -324 R2,643,103 R1,556,304 R427,169 58.88% 16.16% LIGH TING SYSTEM
POWER SYSTEM & EMCC/MCC-
EMCC/MCC CONDUIT& WIRING 596 25-Jun-14 01-Jun-16 02-Sep-13 A 01-Jun-16 -329 R214,877 R214,877 R150,414 100% 70% POWER SYSTEM
FIRE ALARM SYSTEM - CONDUIT&
CONDUIT WIRING 554 20-Aug-14 02-Jun-16 28-Oct-13 A 02-Jun-16 -329 R2,805,377 R1,685,884 R373,897 60.09% 13.33% FIRE ALARM SYSTEM
PUBLIC ADDRESS SYSTEM - CONDUIT& WIRING 518 01-Oct-14 01-Jun-16 28-Oct-13 A 01-Jun-16 -316 R893,308 R614,224 R228,969 68.76% 25.63% PU BLIC ADDRESS SYST E
DATA & TELEPHONE SYSTEM - CONDUIT& WIRING 558 24-Aug-14 11-Jun-16 24-Oct-13 A 11-Jun-16 -324 R4,687,451 R3,020,078 R913,266 64.43% 19.48% DATA
AUDIOVISUAL SYSTEM - CONDUIT&
CONDUIT WIRING 530 27-Sep-14 11-Jun-16 24-Oct-13 A 11-Jun-16 -324 R876,966 R528,351 R118,785 60.25% 13.55% AUDIOVISUAL SYSTEM
NURSE CALL SYSTEM - CONDUIT&
CONDUIT WIRING 550 24-Aug-14 01-Jun-16 24-Oct-13 A 01-Jun-16 -328 R2,444,501 R1,520,026 R398,241 62.18% 16.29% NURSE CALL SYSTEM
MASTER CLOCK SYSTEM - CONDUIT& WIRING 550 24-Aug-14 01-Jun-16 24-Oct-13 A 01-Jun-16 -329 R601,905 R401,617 R123,544 66.72% 20.53% MASTER CLOCK SYSTEM
CCTV SYSTEM - CONDUIT& WIRING 550 24-Aug-14 01-Jun-16 24-Oct-13 A 01-Jun-16 -329 R2,001,678 R1,260,227 R298,784 62.96% 14.93% CCTV SYSTEM
MATV SYSTEM - CONDUIT& WIRING 550 24-Aug-14 01-Jun-16 24-Oct-13 A 01-Jun-16 -324 R363,054 R269,631 R118,420 74.27% 32.62% MATV SYSTEM
ACCESS CONTROL SYSTEM-
SYSTEM CONDUIT& WIRING 568 12-Aug-14 11-Jun-16 28-Oct-13 A 11-Jun-16 -324 R55,800 R32,559 R6,054 58.35% 10.85% ACCESS CONTR OL SYST
BUILDING MANAGEMENT SYSTEM 60 02-Dec-15 10-Feb-16 01-Apr-14 A 26-Jun-16 -337 R5,238,080 R0 R1,833,328 0% 35% BU ILDING MANAGEMENT
GROUNDING AND LIGHTNING PROTECTION SYSTEM 721 10-Feb-14 12-Jun-16 02-Sep-13 A 12-Jun-16 -325 R589,393 R355,149 R301,877 60.26% 51.22% GROUNDING AND LIGHTN
3RD FIX FOR ELECTRICAL FIXTURES AND DEVICES 261 05-Sep-15 05-Jul-16 05-Sep-15 05-Jul-16 -345 R27,289,130 R0 R0 0% 0% 3
CUP - CENTRAL UTILITY PLANT ( replacing electro mech. plant,,MG,R.O.plan & STP in tend... 503 18-Dec-14 26-Jul-16 18-Dec-14 26-Jul-16 -364 R75,111,301 R40,171,584 R0 53.48% 0%
SITE WORKS AND ANCILARIES 230 18-Dec-14 12-Sep-15 18-Dec-14 12-Sep-15 -364 R1,289,565 R1,289,565 R0 100% 0% SITE W ORKS AND ANCILARIES
CONCRETE WORKS 268 18-Jan-15 25-Nov-15 18-Jan-15 25-Nov-15 -364 R7,287,620 R7,287,620 R0 100% 0% CONCRETE WORKS
SU B-STRUC TURE 216 18-Jan-15 26-Sep-15 18-Jan-15 26-Sep-15 -364 R3,968,626 R3,968,626 R0 100% 0% SUB-STRUCTURE
SU PER STRUCTURE 238 22-Feb-15 25-Nov-15 22-Feb-15 25-Nov-15 -364 R3,318,993 R3,318,993 R0 100% 0% SUPER STRUCTURE
MASONRY WORKS 28 12-Dec-15 12-Jan-16 12-Dec-15 12-Jan-16 -364 R344,493 R344,493 R0 100% 0% MASONRY WORKS
METAL WORKS 20 14-Jun-16 06-Jul-16 14-Jun-16 06-Jul-16 -363 R131,762 R0 R0 0% 0% METAL WORKS
WOOD & PLASTICS 26 16-Jun-16 16-Jul-16 16-Jun-16 16-Jul-16 -355 R44,919 R0 R0 0% 0% WOOD
THERMAL & MOISTURE PROTECTION 343 10-Mar-15 12-Apr-16 10-Mar-15 12-Apr-16 -308 R830,207 R447,810 R0 53.94% 0% THERMAL
DOORS & WINDOWS 14 21-Jun-16 06-Jul-16 21-Jun-16 06-Jul-16 -363 R753,988 R0 R0 0% 0% DOORS
FINISHES 116 23-Feb-16 06-Jul-16 23-Feb-16 06-Jul-16 -363 R1,397,404 R5,338 R0 0.38% 0% FINISHES
FLOORS 20 26-Apr-16 18-May-16 26-Apr-16 18-May-16 -359 R370,054 R0 R0 0% 0% FLOORS
WALLS 78 23-Feb-16 23-May-16 23-Feb-16 23-May-16 -363 R807,168 R5,338 R0 0.66% 0% WALLS
CEILINGS 20 24-May-16 15-Jun-16 24-May-16 15-Jun-16 -363 R125,161 R0 R0 0% 0% CEILINGS
EXTERNAL FACADE 18 16-Jun-16 06-Jul-16 16-Jun-16 06-Jul-16 -363 R95,020 R0 R0 0% 0% EXTERNAL FACADE
SPECIALTIES 6 07-Jul-16 13-Jul-16 07-Jul-16 13-Jul-16 -363 R26,769 R0 R0 0% 0% SPECIALTIES
EQUIPMENT 6 14-Jul-16 20-Jul-16 14-Jul-16 20-Jul-16 -363 R571,708 R0 R0 0% 0%

Page 5 of 7 This Baseline Schedule was prepared in response to Hill International request and that the same Schedule shall not relinquish Project Baseline
P. ID:KFMC UPDT 18DEC14 our right to claim for any additional Time and Cost as a consequence of the New Design of the Contract Project.
DD:18-Dec-14 FTCO will exert its utmost efforts to complete the Project within the Original Contract Duration as presented in the Summary
Print Date:21-Dec-14 Baseline Schedule. This schedule includes all those new introduced Items which require a New Rates as well as an prior
Baseline: KFMC DD Approval from MOH as per the contract to start any related activities & shopdrawings.
01AUG13 Fast tracking and Crashing of Activities are applied to this Baseline Schedule with which substantial additional Resources are
introduced, which entails additional Cost that will be submitted for MOH approval in due course.
Updated Summary Bar Chart KING FAISAL MEDICAL CITY - UPDATED
as of Data Date 18-Dec-14

Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Total Budgeted Total Planned Value Earned Value Schedule % Performance % 2012 2013 2014 2015 2016
Duration Float Cost Cost Cost Complete Complete
FURNISHINGS 4 21-Jul-16 25-Jul-16 21-Jul-16 25-Jul-16 -363 R13,020 R0 R0 0% 0%
SPECIAL CONSTRUCTION 15 07-Jul-16 24-Jul-16 07-Jul-16 24-Jul-16 -362 R193,607 R0 R0 0% 0%
CONVEYING SYSTEM 30 09-Jan-16 11-Feb-16 09-Jan-16 11-Feb-16 -222 R0 R0 R0 0% 0% CONVEYING SYSTEM
MECHANICAL WORKS 417 29-Mar-15 26-Jul-16 29-Mar-15 26-Jul-16 -364 R25,013,752 R12,170,919 R0 48.66% 0%
HVAC 106 19-Jan-16 21-May-16 19-Jan-16 21-May-16 -307 R19,126,913 R9,665,585 R0 50.53% 0% HVAC
FIRE FIGHTING WORKS 94 19-Jan-16 07-May-16 19-Jan-16 07-May-16 -295 R1,095,481 R774,158 R0 70.67% 0% FIRE FIGHTING WORKS
PLUMBING WORKS 417 29-Mar-15 26-Jul-16 29-Mar-15 26-Jul-16 -364 R4,791,357 R1,731,176 R0 36.13% 0%
WATER SUPPLY SYSTEM 168 13-Jan-16 26-Jul-16 13-Jan-16 26-Jul-16 -364 R2,447,818 R1,058,637 R0 43.25% 0%
MEDICAL GAS SYSTEM 104 21-Jan-16 21-May-16 21-Jan-16 21-May-16 -307 R2,315,812 R645,755 R0 27.88% 0% MEDICAL GAS SYSTEM
DRAINAGE SYSTEM 349 29-Mar-15 08-May-16 29-Mar-15 08-May-16 -296 R27,728 R26,784 R0 96.6% 0% DRAINAGE SYSTEM
ELECTRICAL WORKS 262 22-Jul-15 22-May-16 22-Jul-15 22-May-16 -308 R37,212,486 R18,625,839 R0 50.05% 0% ELECTRICAL W ORKS
LIGHTING SYSTEM - CONDUIT & WIRING 107 13-Jan-16 16-May-16 13-Jan-16 16-May-16 -303 R16,734,520 R2,513,393 R0 15.02% 0% LIGHTING SYSTEM
POWER SUPPLY SYSTEM - CONDUIT & WIRING 92 13-Jan-16 28-Apr-16 13-Jan-16 28-Apr-16 -318 R19,918,022 R16,001,252 R0 80.34% 0% POWER SUPPLY SYSTEM
FIRE ALARM SYSTEM - CONDUIT & WIRING 58 05-Mar-16 10-May-16 05-Mar-16 10-May-16 -298 R87,241 R0 R0 0% 0% FIRE ALARM SYSTEM
IP TELEPHONE & DATA SYSTEM - CONDUIT & WIRING 34 13-Apr-16 22-May-16 13-Apr-16 22-May-16 -308 R361,510 R0 R0 0% 0% IP TELEPHONE
GROUND ING SYSTEM 34 22-Jul-15 30-Aug-15 22-Jul-15 30-Aug-15 -364 R111,194 R111,194 R0 100% 0% GROUNDING SYSTEM
GENERATOR BUILDING 288 18-Dec-14 18-Nov-15 18-Dec-14 18-Nov-15 -227 R13,164,750 R13,164,750 R0 100% 0% GENER ATOR BUILDING
SITE WORKS 54 18-Dec-14 18-Feb-15 18-Dec-14 18-Feb-15 -254 R92,661 R92,661 R0 100% 0% SITE W ORKS
CONCRETE WORKS 71 23-Dec-14 15-Mar-15 23-Dec-14 15-Mar-15 -254 R891,399 R891,399 R0 100% 0% CONCRETE WORKS
SU B-STRUC TURE 63 23-Dec-14 05-Mar-15 23-Dec-14 05-Mar-15 -254 R347,298 R347,298 R0 100% 0% SU B-STR UCTURE
SU PER STRUCTURE 8 07-Mar-15 15-Mar-15 07-Mar-15 15-Mar-15 -254 R544,101 R544,101 R0 100% 0% SUPER STRUCTURE
MASONRY WORKS 13 31-Mar-15 14-Apr-15 31-Mar-15 14-Apr-15 -254 R44,554 R44,554 R0 100% 0% MASONRY WORKS
METAL WORKS 3 14-Oct-15 17-Oct-15 14-Oct-15 17-Oct-15 -199 R14,322 R14,322 R0 100% 0% METAL WORKS
THERMAL & MOISTURE PROTECTION 56 16-Feb-15 21-Apr-15 16-Feb-15 21-Apr-15 -81 R88,159 R88,159 R0 100% 0% THERMAL & MOISTURE PROTECTION
DOORS & WINDOWS 6 14-Oct-15 20-Oct-15 14-Oct-15 20-Oct-15 -202 R67,183 R67,183 R0 100% 0% DOORS
FINISHES 43 14-Sep-15 02-Nov-15 14-Sep-15 02-Nov-15 -254 R152,666 R152,666 R0 100% 0% FINISH ES
FLOORS 16 26-Sep-15 13-Oct-15 26-Sep-15 13-Oct-15 -254 R47,536 R47,536 R0 100% 0% FLOORS
WALLS 18 14-Sep-15 04-Oct-15 14-Sep-15 04-Oct-15 -246 R38,097 R38,097 R0 100% 0% WALLS
CEILINGS 8 14-Oct-15 22-Oct-15 14-Oct-15 22-Oct-15 -254 R33,155 R33,155 R0 100% 0% CEILINGS
EXTERNAL FACADE 9 24-Oct-15 02-Nov-15 24-Oct-15 02-Nov-15 -254 R33,878 R33,878 R0 100% 0% EXTERNAL FACAD E
SPECIALTIES 2 03-Nov-15 04-Nov-15 03-Nov-15 04-Nov-15 -254 R86,192 R86,192 R0 100% 0% SPECIALTIES
CONVEYING SYSTEM 10 08-Nov-15 18-Nov-15 08-Nov-15 18-Nov-15 -254 R261,563 R261,563 R0 100% 0% CONVEYING SYSTEM
MECHANICAL WORKS 177 15-Apr-15 07-Nov-15 15-Apr-15 07-Nov-15 -254 R544,981 R544,981 R0 100% 0% MECHANICAL WORKS
HVAC 177 15-Apr-15 07-Nov-15 15-Apr-15 07-Nov-15 -254 R34,643 R34,643 R0 100% 0% HVAC
FIRE FIGHTING WORKS 28 29-Apr-15 31-May-15 29-Apr-15 31-May-15 -172 R508,945 R508,945 R0 100% 0% FIRE FIGHTING WORKS
PLUMBING WORKS 8 01-Jun-15 09-Jun-15 01-Jun-15 09-Jun-15 -172 R1,393 R1,393 R0 100% 0% PLUMBING WOR KS
ELECTRICAL WORKS 221 30-Dec-14 13-Sep-15 30-Dec-14 13-Sep-15 -197 R10,921,069 R10,921,069 R0 100% 0% ELECTRICAL W ORKS
LOW VOLTAGE DISTRIBUTION INSTALLATION - CONDUIT & WIRING 26 15-Apr-15 14-May-15 15-Apr-15 14-May-15 -254 R10,303,933 R10,303,933 R0 100% 0% LOW VOLTAGE DISTRIBUTION INSTA
POWER & LIGHTING SYSTEM - CONDUIT & WIRING 32 16-May-15 21-Jun-15 16-May-15 21-Jun-15 -254 R494,414 R494,414 R0 100% 0% POWER & LIGHTING SYSTEM
DATA & VOICE SYSTEM - CONDUIT & WIRING 26 22-Jun-15 21-Jul-15 22-Jun-15 21-Jul-15 -254 R5,489 R5,489 R0 100% 0% DATA & VOICE SYSTEM
FIRE ALARM SYSTEM - CONDUIT & WIRING 26 22-Jul-15 20-Aug-15 22-Jul-15 20-Aug-15 -254 R19,118 R19,118 R0 100% 0% FIRE ALARM SYSTEM
CCTV SYSTEM - CONDUIT & WIRING 20 22-Aug-15 13-Sep-15 22-Aug-15 13-Sep-15 -254 R69,750 R69,750 R0 100% 0% CCTV SYSTEM
GROUND ING & LIGHTNING PROTECTION SYSTEM 105 30-Dec-14 30-Apr-15 30-Dec-14 30-Apr-15 -81 R28,365 R28,365 R0 100% 0% GROUNDING
UTILITY TUNNEL (TN01) 697 27-Nov-13 01-Mar-16 10-Apr-13 A 01-Mar-16 -237 R10,782,008 R10,782,008 R29,407 100% 0.27% UTILITY TUNNEL
SITE WORKS 633 27-Nov-13 17-Dec-15 10-Apr-13 A 17-Dec-15 -293 R885,300 R885,300 R29,407 100% 3.32% SITE W ORKS
CONCRETE WORKS 136 26-Apr-15 01-Oct-15 26-Apr-15 01-Oct-15 -293 R4,592,821 R4,592,821 R0 100% 0% CONCRETE WORKS
SU B-STRUC TURE 136 26-Apr-15 01-Oct-15 26-Apr-15 01-Oct-15 -293 R4,592,821 R4,592,821 R0 100% 0% SUB-STRUCTURE
METAL WORKS 26 27-Dec-15 26-Jan-16 27-Dec-15 26-Jan-16 -267 R8,333 R8,333 R0 100% 0% METAL WORKS
THERMAL & MOISTURE PROTECTION 147 29-Apr-15 18-Oct-15 29-Apr-15 18-Oct-15 -293 R444,848 R444,848 R0 100% 0% THERMAL
FINISHES 74 01-Oct-15 27-Dec-15 01-Oct-15 27-Dec-15 -267 R403,679 R403,679 R0 100% 0% FINISHES
FLOORS 18 06-Dec-15 27-Dec-15 06-Dec-15 27-Dec-15 -267 R175,516 R175,516 R0 100% 0% FLOORS
WALLS 30 01-Oct-15 05-Nov-15 01-Oct-15 05-Nov-15 -267 R154,261 R154,261 R0 100% 0% WALLS
CEILINGS 26 05-Nov-15 06-Dec-15 05-Nov-15 06-Dec-15 -267 R73,902 R73,902 R0 100% 0% CEILINGS
MECHANICAL WORKS 130 01-Oct-15 01-Mar-16 01-Oct-15 01-Mar-16 -237 R4,248,491 R4,248,491 R0 100% 0% MECHANICAL WORKS
ELECTRICAL WORKS 130 01-Oct-15 01-Mar-16 01-Oct-15 01-Mar-16 -237 R198,537 R198,537 R0 100% 0% ELECTRICAL W ORKS

Page 6 of 7 This Baseline Schedule was prepared in response to Hill International request and that the same Schedule shall not relinquish Project Baseline
P. ID:KFMC UPDT 18DEC14 our right to claim for any additional Time and Cost as a consequence of the New Design of the Contract Project.
DD:18-Dec-14 FTCO will exert its utmost efforts to complete the Project within the Original Contract Duration as presented in the Summary
Print Date:21-Dec-14 Baseline Schedule. This schedule includes all those new introduced Items which require a New Rates as well as an prior
Baseline: KFMC DD Approval from MOH as per the contract to start any related activities & shopdrawings.
01AUG13 Fast tracking and Crashing of Activities are applied to this Baseline Schedule with which substantial additional Resources are
introduced, which entails additional Cost that will be submitted for MOH approval in due course.
Updated Summary Bar Chart KING FAISAL MEDICAL CITY - UPDATED
as of Data Date 18-Dec-14

Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Total Budgeted Total Planned Value Earned Value Schedule % Performance % 2012 2013 2014 2015 2016
Duration Float Cost Cost Cost Complete Complete

GUARD ROOMS 142 18-Dec-14 01-Jun-15 18-Dec-14 01-Jun-15 -81 R594,024 R594,024 R0 100% 0% GUARD ROOMS
SITE WORKS 30 18-Dec-14 21-Jan-15 18-Dec-14 21-Jan-15 -108 R23,799 R23,799 R0 100% 0% SITE W ORKS
CONCRETE WORKS 33 22-Dec-14 28-Jan-15 22-Dec-14 28-Jan-15 -108 R61,090 R61,090 R0 100% 0% CONCRETE WORKS
SU B-STRUC TURE 27 22-Dec-14 21-Jan-15 22-Dec-14 21-Jan-15 -108 R35,161 R35,161 R0 100% 0% SU B-STR UCTURE
SU PER STRUCTURE 6 22-Jan-15 28-Jan-15 22-Jan-15 28-Jan-15 -108 R25,928 R25,928 R0 100% 0% SU PER STRUCTU RE
MASONRY WORKS 4 14-Feb-15 17-Feb-15 14-Feb-15 17-Feb-15 -108 R15,051 R15,051 R0 100% 0% MASONR Y WORKS
METAL WORKS 2 19-May-15 20-May-15 19-May-15 20-May-15 -71 R0 R0 R0 0% 0% METAL WORKS
WOODS & PLASTICS 4 11-May-15 14-May-15 11-May-15 14-May-15 -66 R26,040 R26,040 R0 100% 0% WOODS & PLASTICS
THERMAL & MOISTURE PROTECTION 38 12-Jan-15 24-Feb-15 12-Jan-15 24-Feb-15 2 R5,156 R5,156 R0 100% 0% THERMAL & MOISTURE PROTECTION
DOORS & WINDOWS 4 19-May-15 23-May-15 19-May-15 23-May-15 -73 R33,852 R33,852 R0 100% 0% DOORS & WINDOWS
FINISHES 30 21-Apr-15 25-May-15 21-Apr-15 25-May-15 -108 R23,371 R23,371 R0 100% 0% FINISHES
FLOORS 17 29-Apr-15 18-May-15 29-Apr-15 18-May-15 -107 R5,000 R5,000 R0 100% 0% FLOORS
WALLS 21 21-Apr-15 14-May-15 21-Apr-15 14-May-15 -108 R10,598 R10,598 R0 100% 0% WALLS
CEILINGS 4 16-May-15 19-May-15 16-May-15 19-May-15 -108 R2,148 R2,148 R0 100% 0% CEILINGS
EXTERNAL FACADE 5 20-May-15 25-May-15 20-May-15 25-May-15 -108 R5,625 R5,625 R0 100% 0% EXTERNAL FACADE
SPECIALTIES 3 26-May-15 28-May-15 26-May-15 28-May-15 -108 R4,336 R4,336 R0 100% 0% SPECIALTIES
EQUIPMENT 3 30-May-15 01-Jun-15 30-May-15 01-Jun-15 -108 R11,197 R11,197 R0 100% 0% EQUIPMENT
MECHANICAL WORKS 79 18-Feb-15 20-May-15 18-Feb-15 20-May-15 -104 R34,231 R34,231 R0 100% 0% MECHANICAL WORKS
HVAC 10 18-Feb-15 01-Mar-15 18-Feb-15 01-Mar-15 -108 R12,090 R12,090 R0 100% 0% HVAC
PLUMBING WORKS 69 02-Mar-15 20-May-15 02-Mar-15 20-May-15 -104 R22,141 R22,141 R0 100% 0% PLUMBING WOR KS
ELECTRICAL WORKS 90 27-Dec-14 09-Apr-15 27-Dec-14 09-Apr-15 -99 R355,902 R355,902 R0 100% 0% ELECTRICAL W ORKS
LOW VOLTAGE DISTRIBUTION INSTALLATION - CONDUIT & WIRING 12 18-Feb-15 03-Mar-15 18-Feb-15 03-Mar-15 -99 R39,689 R39,689 R0 100% 0% LOW VOLTAGE DISTRIBUTION INSTALL
POWER & LIGHTING SYSTEM - CONDUIT & WIRING 12 04-Mar-15 17-Mar-15 04-Mar-15 17-Mar-15 -99 R95,920 R95,920 R0 100% 0% POWER & LIGH TING SYSTEM
FIRE ALARM SYSTEM - CONDUIT & WIRING 10 18-Mar-15 29-Mar-15 18-Mar-15 29-Mar-15 -99 R43,937 R43,937 R0 100% 0% FIRE ALARM SYSTEM
CCTV SYSTEM - CONDUIT & WIRING 10 30-Mar-15 09-Apr-15 30-Mar-15 09-Apr-15 -99 R161,011 R161,011 R0 100% 0% CCTV SYSTEM
GROUND ING SYSTEM 8 27-Dec-14 04-Jan-15 27-Dec-14 04-Jan-15 -108 R15,345 R15,345 R0 100% 0% GROUND ING SYSTEM
SITE DEVELOPMENT ( replacing site works,
works and ancilary building in tender ) 492 18-Dec-14 13-Jul-16 18-Dec-14 13-Jul-16 -353 R27,973,971 R17,695,124 R0 63.26% 0% SITE DEVELOPMENT
CIVIL / ARCHITECTURAL WORKS 492 18-Dec-14 13-Jul-16 18-Dec-14 13-Jul-16 -353 R11,608,465 R5,920,667 R0 51% 0% CIVIL
ROAD S & PAVEMENTS 429 18-Dec-14 01-May-16 18-Dec-14 01-May-16 -353 R2,696,874 R1,341,101 R0 49.73% 0% ROADS
HARDSCAPE WORKS 198 26-Aug-15 12-Apr-16 26-Aug-15 12-Apr-16 -280 R5,209,308 R3,729,393 R0 71.59% 0% HARDSCAPE WORKS
LAN DSCAPE WORKS 70 03-Feb-16 24-Apr-16 03-Feb-16 24-Apr-16 -353 R710,060 R8,329 R0 1.17% 0% LANDSCAPE WORKS
PARKIN G SH AD ES, SIGNAGES & MARKINGS 54 17-Feb-16 19-Apr-16 17-Feb-16 19-Apr-16 -280 R798,084 R67,113 R0 8.41% 0% PAR KING SHADES
PH ASE 1 FENCING, GATES & BARRIERS 181 16-Dec-15 13-Jul-16 16-Dec-15 13-Jul-16 -353 R1,249,967 R349,231 R0 27.94% 0% PHASE
HELIPAD 60 30-Jan-16 07-Apr-16 30-Jan-16 07-Apr-16 -300 R944,173 R425,500 R0 45.07% 0% HELIPAD
MECHANICAL 324 29-Mar-15 09-Apr-16 29-Mar-15 09-Apr-16 -271 R6,519,928 R2,088,141 R0 32.03% 0% MECHANICAL
ELECTRICAL 204 22-Jul-15 15-Mar-16 22-Jul-15 15-Mar-16 -340 R9,845,579 R9,686,316 R0 98.38% 0% ELECTRICAL

PROJECT COMPLETION - ASIR KFMC HOSPITAL PHASE 1 105 12-Apr-16 13-Aug-16 12-Apr-16 13-Aug-16 -378 R0 R0 R0 0% 0%

Page 7 of 7 This Baseline Schedule was prepared in response to Hill International request and that the same Schedule shall not relinquish Project Baseline
P. ID:KFMC UPDT 18DEC14 our right to claim for any additional Time and Cost as a consequence of the New Design of the Contract Project.
DD:18-Dec-14 FTCO will exert its utmost efforts to complete the Project within the Original Contract Duration as presented in the Summary
Print Date:21-Dec-14 Baseline Schedule. This schedule includes all those new introduced Items which require a New Rates as well as an prior
Baseline: KFMC DD Approval from MOH as per the contract to start any related activities & shopdrawings.
01AUG13 Fast tracking and Crashing of Activities are applied to this Baseline Schedule with which substantial additional Resources are
introduced, which entails additional Cost that will be submitted for MOH approval in due course.
8.0 ATTACHMENTS

8.10 Work Flow Procedure


KFMC & PMMC SUBMISSION
WORKFLOW CHART

CODE "D" REJECTED

CODE "C" REVISE & RESUBMIT(07 WORKING DAYS)

SHOP DRAWING
RETURN
Code C & D

MATERIAL
ZFP CORE TEAM‐RIYADH
(PROCEED IN 07 WORKING DAYS)
SHOP DRAWING  APPROVED 
SH DRAWING ‐ ENGINEERS 
SHOP DRAWING  ZFP  SHOP
FTCO        DOCUMENT DOCUMENT 
MATERIAL ‐ ENGINEERS
DOCUMENT ‐ ENGINEERS DRAWING    FTCO SITE ZFP
CONTRACTOR SHOP DRAWING  MATERIAL         Supervision Team
CONTROLLER PAYMENT ‐ QUANTITY SURVEYOR
CHANGE ORDER ‐ QUANTITY SURVEYOR   DOCUMENT

INVOICE
APPROVED
FTCO
PAYMENT    MOH                            
HILL                             
CHANGE  APPROVAL 
CHANGE ORDER MATERIAL APPROVAL  HILL                             APPROVAL 
OREDER
MATERIAL
8.0 ATTACHMENTS

8.11 HSE Statistics


8.0 ATTACHMENTS

8.12 Safety Log


8.0 ATTACHMENTS
8.13 NCRs Log
King Faisal Medical City-South(Phase-01) NCR SUMMARY
PROJECT MANAGER : Hill International Open NCRs 0
CONSULTANT : Zuhair Fayez Partnership Closed NCRs 19
CONTRACTOR : Al Fouzan Trading & General Construction Co. Total NCRs 19
NON-CONFORMANCE STATUS LOG
Completion Proposed
NCR No. Description Contractor Action/Response Issued by Issue Date Due Date
Date follow-up
Reference to attached documents which already shows ZFP
M-001 Septic & Water Tanks. approval for septic tank and water tank and according to ZFP 17/11/2012 1/12/2012 6/Dec/2013 Accepted.
approved RFI this close NCR no 1
Please find attached undertaking letter regarding the excavated
C 002 Dumping of Excavated Material. ZFP 18/Nov/2012 29/Mar/2014 Accepted.
material.
Closure to some gaps is on going continuously and is almost
complete. As for the issue on approved drawings please refer to
ZFP 19/Nov/2012
Temporary Fence. attached minutes of meeting # 9 Rev 0 chaired by Project director
(ZFP final Comments: NCR is closed based on Hill intl and Hill Intl.
G 003 Accepted.
recommendation on letter ref:892-1-KF-KF01-H-HI-ZP-LET-
AZ-0040 (Revised) dated 25-09-2014 Attached herewith the As built dwg of the temp fence the NCR
ZFP 19/Nov/2012 21/Oct/2014
should be closed as per the agreement between FTCO & ZFP.

As per attached calculations the electrical fixtures inside site


E 004 Installation of Electrical Fixture. offices as per specs, electrical lighting fixtures was added to the ZFP 21/Nov/2012 28/Jul/2013 Accepted.
office as per specs.

G 005 Safety Walk round. All offenses mentioned in SWRs closed up to that date. ZFP 9/Dec/2012 17/Jan/2013 Accepted.
Casting concrete with out inspection request. No any Cast bleeding concrete already removed and rectifications were
G 006 ZFP 19/Dec/2012 17/Jan/2013 Accepted.
compaction / filed density test is carried out. done through progressive IRs submitted.

FTCO started casting blinding concrete and shuttering


All comments in RFI 10 were addressed and rectifications were
G 007 formworks with out approved inspection request. Comments ZFP 6/Jan/2013 17/Jan/2013 Accepted.
done.
on RFI 10 regarding the fragmented rock not rectified.
As per attached documents the backfilling under the raft
G 008 Backfilling under the Blinding Concrete. ZFP 6/Feb/2013 10/Jun/2013 Accepted.
foundation meets the specification.
Test result of the concrete compression after 7 and 28 days
of the concrete of the foundation of tower crane 3 at the
Reference to RGF result & recommendation the samples of the
south of phase 1 are 22.8 and 26.3 MPA respectively. Those
G 009 tower crane 3 meets the specifications O/L ACI and foundation of ZFP 23/Feb/2013 11/Jul/2013 Accepted.
results are unacceptable and the tower crane shall not be
tower crane 3 considered safe.
used for the project unless FTCO rectify the concrete
strength.

Page 1 of 3 Prepared By: Jamshed Khan


King Faisal Medical City-South(Phase-01) NCR SUMMARY
PROJECT MANAGER : Hill International Open NCRs 0
CONSULTANT : Zuhair Fayez Partnership Closed NCRs 19
CONTRACTOR : Al Fouzan Trading & General Construction Co. Total NCRs 19
NON-CONFORMANCE STATUS LOG
Completion Proposed
NCR No. Description Contractor Action/Response Issued by Issue Date Due Date
Date follow-up
FTCO has casted the reinforced concrete for the raft
foundation of phase 1 at part 1 prior closing the NCR no 8
Attached the closed NCR no 8 & closed NCR no 12 with DAR letter
G 010 and without receiving any approved RFI according the ZFP 11/Mar/2013 13/Jul/2013 Accepted.
this should close this issue.
formworks rebar and without providing mix design using
cement type V.
7days compressive test results of the poured concrete for the
first section of the raft at part 1 revealed that the strength of
C 011 the concrete samples (29 out of 48) did not meet the attached is core test result from RGF for your review. ZFP 19/Mar/2013 25/Sep/2013 Accepted.
minimum strength values of the 7 days compressive strength
test.

Inspite of the invalidity of the rebar shop drawings rev 4


which is confirmed by Dar Engineering in a meeting that held
on 20 March 2013 FTCO keep proceeding with placing the Please find Dar engineering letter that clearly shows that the raft
C 012 ZFP 24/Mar/2013 16/Jun/2013 Accepted.
rebar for the raft at part 1 & 6 of phase 1 furthermore foundation reinforcement meets the requirement.
FTCO/RGF has not yet solved the issue of the backfill beneath
the casted blind concrete at part 1 & 6.

Temporary fence has been collapsed in many locations due to


the wind three weeks ago which in turn weekend the safety
C 013 All collapsed parts has been rectified and corrected. ZFP 24/Jun/2013 27/Nov/2013 Accepted.
and security of the project site. FTCO has not taken any
action to repair the collapsed temporary fence.
Occurrence of cold joints due to interval of time between
placing of concrete of the successive pouring in some areas
C 014 Please find attached RGF report in Trans# TRN-EG-0110 ZFP 7/Nov/2013 8/Feb/2014 Accepted.
within core 3 zone which caused by the low rate of delivery
of concrete.
It has been observed that some honeycombs and The repair work in on going for podium walls as per approved
C 015 segregations defects/blemishes were appeared in the casted material & MS Hill intl team & ZFP engineers already witnessed ZFP 10/Feb/2014 11/Feb/2014 Accepted.
concrete of the basement walls. the work at site.

It has been observed that the casted concrete walls of core#3 Reference to field curve cylinders (attached) we believe that the
C 016 ZFP 21/Apr/2014 26/May/2014 Accepted.
have not cured as per the project specification. NCR should be closed.

Page 2 of 3 Prepared By: Jamshed Khan


King Faisal Medical City-South(Phase-01) NCR SUMMARY
PROJECT MANAGER : Hill International Open NCRs 0
CONSULTANT : Zuhair Fayez Partnership Closed NCRs 19
CONTRACTOR : Al Fouzan Trading & General Construction Co. Total NCRs 19
NON-CONFORMANCE STATUS LOG
Completion Proposed
NCR No. Description Contractor Action/Response Issued by Issue Date Due Date
Date follow-up
Reference to the technical assessment and evaluation for
Concrete compressive strength tests have been failed after
transmission of column load trough floor system and transmittal Conditional
G 017 28 days(see att photos)Provide 3rd party recommendation ZFP 3/Aug/2014 25/Sep/2014
# 892-1-KF-KF1-H-ZFP-FT-TRN-0157, the 1st floor slab C3 is acceptance
about all these failed testes.
considered safe and the NCR # 17 should be closed.

Concrete compressive strength tests have been failed for axis


Reference to the 28 days crushing test result as attached, we
G 018 10/P level after 7 days (see att copy)Provide 3rd party ZFP 3/Aug/2014 24/Aug/2014 Accepted.
believed that the NCR should be closed.
recommendation about all these failed testes.

Severe defects have been observed on the casted section of


BW1 along axis 31 between (T&V). FTCO to investigate the UPV result had been submitted and repaired statement, we
G 019 ZFP 18/Aug/2014 11/Sep/2014 Accepted.
defects and provide Technical report from approved third believed that this NCR can be closed (Photos attached)
party. The recommended MS for the repair to be followed.

Page 3 of 3 Prepared By: Jamshed Khan


8.0 ATTACHMENTS
8.14 SSRs Log, IR Log, MIR Log
PROJECT : KING FAISAL MEDICAL CITY (KFMC)

LOCATION : ABHA
PM CONSULTANT : HILL INTERNATIONAL
CONSULTANT : Zuhair Fayez Partnership
CONTRACTOR : Al Fouzan Trading & General Construction Co.

SITE SURVEILLANCE REPORT

RESPONSE BY CONTRACTOR
S.NO DESCRIPTION Contractor Action/Response SUBMITTED ON REMARKS
DUE DATE RETURNED

Temporary fence has been rectified and approved through the


SSR-000 COLLAPSE OF TEMPORARY FENCE 6/14/2013 6/21/2013 12/1/2013 CLOSED
attached RFI.
THE CURING OF CASTED CONCRETE IS PERFORMED AS
SSR-001 PER THE PROJECT SPECIFICATIONS AND APPROVED Curing was monitored by ZFP Engineer through submitted log. 9/22/2013 9/29/2013 11/21/2013 CLOSED
QUALITY MANAGEMENT PLAN
All cracks has been tempered by using approved method.
SSR-002 DAMAGED AND CRACKED BLINDING 5/18/2013 5/25/2013 11/21/2013 CLOSED
EMACO R303

ALL DEFECTS THAT WAS OBSERVEDON CASTED SECTION FTCO & ZFP engineers has addressed all the defected area at site
SSR-004 11/19/2013 11/26/2013 12/17/2013 CLOSED
OF WALLS AND COLUMNS AT DIFFERENT LOCATION and repairing

SSR-005 TEMPORARY FENCE DAMAGED PANEL DID NOT REPOAR All damages have been repaired (Attached inspection request) 12/29/2013 1/5/2014 1/5/2014 CLOSED

Issue has been addressed by FTCO,vissual inspection was done


SSR-006 Scaffolding work is unsafe (Lacking of safe access) 24/02/2014 3/3/2014 3/1/2014 CLOSED
by ZFP,Hill and FTO team,improvement has noticed.

Concrete defects that was observed on casted sections of


Please ref to attached RFIs for Raft & walls, moreover the repair
SSR-007 raft foundation at part 6 area and column C15(C50)at grid 15/3/2014 22/03/2014 3/26/2014 CLOSED
for other defects is on going according to method statement.
axis P,30 and shear wall (SW1) between grid axis 10-14

SSR-008 Damaged water proofing at part 4 area Please find attached RFI & photos. 15/3/2014 22/03/2014 19/03/214 CLOSED

Concrete compressive test of 28 days failed and concrete


SSR-009 Ref to attached reports from RGF concrete test & 56 days result 20/04/2014 27/04/2014 6/23/2014 CLOSED
bleeded in SW 4 a letter # 264 was issued
Embedded electrical conduits and boxes are not installed in
SSR-010 Electrical conduits & boxes has been installed for GF slab C9. 5/13/2014 5/20/2014 5/21/2014 CLOSED
the section C9 of the ground floor slab

Concrete compressive test of 28 days failed and concrete


SSR-011 Please ref to attached FTCO letter no:91 6/22/2014 6/29/2014 6/29/2014 CLOSED
bleeded in SW 1 LEVEL

We observed construction joints are not followed during


SSR-012 Ref to FTCO letter no:94. 6/28/2014 7/5/2014 7/1/2014 CLOSED
the casting of C-8 at GF level

SSR-013 We observed that temporary fence has collapsed Temporary fence already repaired and inspected by ZFP team 6/29/2014 7/6/2014 7/5/2014 CLOSED

Layer # 11&25 in the men area has already been replaced by


We observed that backfill material is not according to
SSR-014 new one also the stave has repaired (pls find att photos, 7/1/2014 7/8/2014 7/16/2014 CLOSED
specification
moreover the sample shows A1-b classification which is suitable
for bF.
We observed that bad workmanship during casting FTCO already taken the corrective action regarding the damaged
SSR-015 7/2/2014 7/9/2014 7/16/2014 CLOSED
concrete columns

Electrical PVC conduits have been damaged at the The conduits have been damaged accidently during removing of
SSR-016 7/16/2014 7/23/2014 7/21/2014 CLOSED
construction joints after the pouring of concrete Hy-Rib, any how it has repaired please ref to the attached photos

SSR-017 We have observed that the temporary fence has collapsed. The collapsed part of temporary fence has already repaired. 8/4/2014 8/5/2014 8/5/2014 CLOSED

We observed that FTCO repaired concrete without any


documents. As third party (Al-Thunaya) recommended The official result of the ultrasonic pulse velocity test has been
SSR-018 8/14/2014 8/20/2014 8/24/2014 CLOSED
Ultrasonic test, it has been applied but did not submitted submitted on 13 Aug 2014
official report.
We observed that bad quality of form work & casting
concrete found honeycomb on surface & concrete bleeding Already repaired and inspected by Engr. Haidar. Repair works
SSR-019 8/17/2014 8/24/2014 8/20/2014 CLOSED
for columns axis 10/U and 10/V. FTCO to provide third done as per MS and approved material.
party opinion about these two columns.
PROJECT : KING FAISAL MEDICAL CITY (KFMC)

LOCATION : ABHA
PM CONSULTANT : HILL INTERNATIONAL
CONSULTANT : Zuhair Fayez Partnership
CONTRACTOR : Al Fouzan Trading & General Construction Co.

SITE SURVEILLANCE REPORT

RESPONSE BY CONTRACTOR
S.NO DESCRIPTION Contractor Action/Response SUBMITTED ON REMARKS
DUE DATE RETURNED

The curing of concrete of the casted core 10 is not carried Curing with water and wet burlap is continues up to 7 days
SSR-020 8/18/2014 8/25/2014 8/20/2014 CLOSED
out as per the project specification. inspected by Engr. Haidar

We observed that bad quality of form work still using in


SSR-021 Already changed with new form work inspected by Engr. Haidar 8/20/2014 8/26/2014 8/23/2014 CLOSED
BW4 axis 14-16/N. It will effect quality of work.

FTCO failed to take action for repairing of concrete it will


SSR-022 Repaired already and inspected by Engr. Haidar 8/21/2014 8/29/2014 8/28/2014 CLOSED
effect quality of concrete work.

FTCO to replace old plywood pieces in form work of Already replaced and inspected by Engr. Haidar (with attached
SSR-023 8/25/2014 9/1/2014 9/3/2014 CLOSED
columns. It will effect quality of concrete work photos)
ZFP found concrete bleeding for shear wall (SW6L1). It will
SSR-024 Find attached the Hammer test reading for the said area. 8/26/2014 9/2/2014 9/18/2014 CLOSED
effect quality of concrete work.
ZFP found reinforcement of FF columns between axis 17- All erected rebars for columns on 19-19/W-S have been braced /
19/W-S already installed at site before casting concrete of supported. See attached photos, removal of these erected rebars
SSR-025 8/28/2014 9/4/2014 9/3/2014 CLOSED
slab some of them are bend due to heavy wind, actually will for column is not possible at this time because electrical conduits
effect the quality of rebar & quality of concrete work are already installed.
Concrete defects(Honey comb) were found after removing Most of the repair layer has been removed, the defected area has
9/10/2014 10/13/2014 10/13/2014
shuttering of SW6 axis 15-16 at level 01. identified and repair work will be through inspection request.
AS long as the procedure of repairing status, we believe that the
SSR-026 SSR should be closed as the main description of the SSR is " CLOSED
FTCO to give a clear dead line to finish the repair. 10/13/2014 10/14/2014
Repairing without inspection".FTCO will assure that all repairing
work will be through Irs
Repair work has finished and inspected by ZFP through
10/26/2014 10/29/2014
inspection request.
ZPF found some areas to be needed to repair of concrete in
Work has finished in some locations (Irs attached) and the work
bottom of waffle slab. As we visited jointly (HILL, ZFP &
is ongoing at the other parts, work will be finished soon through
SSR-027 FTCO) on 18th August 2014 and agreed to start repairing 9/16/2014 9/23/2014 11/9/2014 CLOSED
Irs and according to MS. So we request your office to close the
concrete immediately, but this activity is not yet started. It
SSR.
will effect the quality of concrete.
Concrete defects (Honey comb) are found on beam after
Beam defects along grind 19,17 & V in 1st floor slab has been
SSR-028 removing shuttering at different location along grid axis 10/13/2014 10/20/2014 10/28/2014 CLOSED
repaired & witness by Consultant by Inspection request.
17,19 V at level 01.For your ref see attached photos.

We observed bad workmanship during the casting of


concrete, Steel was not clean immediately from concrete,
FTCO to take immediate action to start clean steel, repairing
SSR-029 found bad surface of concrete & removed formwork vertical 11/26/2014 12/3/2014 OPEN
surface of landing & make sure do not happen again in future.
supports after 2 days from landings. FTCO to provide
justification about these two landings & surface of concrete.
Defected waffle domes boxes were found at level 03 slab in
SSR-030 12/3/2014 12/10/2014 OPEN
zone 2 and 5 area, for your reference see attached photos,
 
 
 

 
01 02

04
03
MINISTRY OF HEALTH STATUS CODE

KING FASIAL MEDICAL CITY ( ABHA) A Approved B Approved as noted

ALFOUZAN TRADING & GEN. CONTRACTING CO. C Revise & sub. D Rejected
Submittal 1st Submittal 2nd Submittal 3th Submittal
NO Doc. No Title
FILE NO. Date in Returened Code FILE NO Submittal No Date in Returened Code FILE NO Submittal No Date in Returened Code Rev. Submittal No Date in Returened Code
REQUEST FOR INSPECTION ( R F I )-ARCH.(24 Nov.2014 to 22 Dec.2014)
2 RFI-A-2 CHECK ARCHITECTURAL OPENING IN SHEAR WALL SW1 & SW5 (elev.2097.50) GL: 10-14/R-Q 1 02/12/2014 13/02/2014 A
49 A-49 CHECK DIMENSIONS ARCHITECTURAL OPENINGS of SW 1 , SW5 , 12-14/R - 12-14/Q 2 24.11.2014 24.11.2014 B
50 A-50 CHECK DIMENSIONS ARCHITECTURAL OPENING IN GF CORE # 1 LEVEL 02 14-15/Q-R 2 30.11.2014 01.12.2014 B
51 A-51 CHECK DIMENSIONS ARCHITECTURAL OPENING IN GF BW 4 24-26/N (4.0m after GL 24 up to 4.0m Before GL 26) 2 13.12.2014 13.12.2014 B
52 A-52 CHECK DIMENSIONS ARCHITECTURAL OPENING OF SW2 - LEVEL 02 17-19/R 2 15.12.2014 16.12.2014 B
53 A-53 CHECK DIMENSIONS ARCHITECTURAL OPENING OF SW 6 - LEVEL 02 15-17/Q 2 16.12.2014 16.12.2014 B
54 A-54 CHECK DIMENSIONS ARCHITECTURAL OPENING OF GF CORE # 11 (2104.0) 15-17/Q 2 16.12.2014 16.12.2014 B
55 A-55 CHECK DIMENSIONS ARCHITECTURAL OPENING OF SW 6 - LEVEL 02 17-19/Q 2 18.12.2014 18.12.2014 C 2 A-55R1 12/20/2014 20.12.2014 B
MINISTRY OF HEALTH STATUS CODE

KING FASIAL MEDICAL CITY ( ABHA) A Approved B Approved as noted


ALFOUZAN TRADING & GEN. CONTRACTING CO. C Revise & sub. D Rejected

NO Doc. No Title Submittal 1st Submittal 2rd Submittal 3th Submittal


FILE Date in Returened Code FILE Submittal No Date in Returened Code FILE. Submittal No Date in Returened Code Rev. Submittal No Date in Returened Code
REQUEST FOR INSPECTION ( R F I )-ELECTRICAL(24 Nov.2014 to 22 Dec.2014)
185 CIR-E-185 CHECK EMBEDDED PVC PIPE FOR POWER SYSTEM IN PODIUM AT CORE 1 GL : 14-15/QR 2 02/12/2014 02/12/2014 B
186 CIR-E-186 CHECK EMBEDDED PVC PIPE FOR LITHING SYSTEM IN PODIUM AT CORE 1 GL : 14-15/QR 2 02/12/2014 02/12/2014 B
187 CIR-E-187 CHECK EMBEDDED PVC PIPE FOR LITHING PROTECTION SYSTEM IN GROUND LEVEL AT COLUMNS GL: 10/R-S 2 02/12/2014 13/2/2014 B
901 CIR-E-901 CHECK EMBEDDED PVC PIPE FOR FIRE ALARM SYSTEM (elev. 2104.0) C07 LEVEL 10 23/11/2014 25/11/2014 B
902 CIR-E-902 CHECK EMBEDDED PVC PIPE FOR MATV SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 25/11/2014 B
903 CIR-E-903 CHECK EMBEDDED PVC PIPE FOR INTERCOM SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 25/11/2014 B
904 CIR-E-904 CHECK EMBEDDED PVC PIPE FOR IP-CCTV SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 25/11/2014 B
905 CIR-E-905 CHECK EMBEDDED PVC PIPE FOR EQUIPMENT POWER LAYOUT (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 25/11/2014 B
906 CIR-E-906 CHECK EMBEDDED PVC PIPE FOR STRUCTURED CABLING (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 25/11/2014 B
907 CIR-E-907 CHECK EMBEDDED PVC PIPE FOR LIGHTING CONTROL SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 24/11/2014 B
908 CIR-E-908 CHECK EMBEDDED PVC PIPE FOR PUBLIC ADDRESS SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 25/11/2014 B
909 CIR-E-909 CHECK EMBEDDED PVC PIPE FOR NURSE CALL SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 24/11/2014 B
910 CIR-E-910 CHECK EMBEDDED PVC PIPE FOR MASTER CLOCK SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 25/11/2014 B
911 CIR-E-911 CHECK EMBEDDED PVC PIPE FOR BMS SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 24/11/2014 B
912 CIR-E-912 CHECK EMBEDDED PVC PIPE FOR POWER SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 24/11/2014 B
913 CIR-E-913 CHECK EMBEDDED PVC PIPE FOR LIGHTING SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 24/11/2014 B
914 CIR-E-914 CHECK EMBEDDED PVC PIPE FOR GROUNDING SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 24/11/2014 B
915 CIR-E-915 CHECK EMBEDDED PVC PIPE FOR LIGHTING PROTECTION SYSTEM (elev. 2104.0) C07 LEVEL-01 10 23/11/2014 25/11/2014 B
916 CIR-E-916 ELECTRICAL OPENING (elev. 2115.5) SW 1 GL : 12-14/R 10 24/11/2014 25/11/2014 B 10 E-916R1 07.12.2014 09.12.2014 B
917 CIR-E-917 ELECTRICAL OPENING (elev. 2115.5) SW 1 GL : 12-14/Q 10 24/11/2014 25/11/2014 B
918 CIR-E-918 CHECK ELECTRICAL PVC CONDUITS FOR LIGHTENING SYSTEM @ CORE # 1 @ elevation 2115.5 CORE 1 10 30/11/2014 01/12/2014 C 10 E-918R1 01.12.2014 01.12.2014 B
919 CIR-E-919 CHECK ELECTRICAL PVC CONDUITS FOR POWER SYSTEM @ CORE # 1 @ elevation 2115.5 CORE 1 10 30/11/2014 01/12/2014 B
920 CIR-E-920 CHECK ELECTRIAL PVC CONDUITS FOR LIGHTING SYSTEM IN CORE # 3 @ elevation 2103.5 - GROUND LEVEL CORE 3 10 30/11/2014 02/12/2014 B
921 CIR-C-921 CHECK ELECTRIAL PVC CONDUITS FOR GROUND SYSTEM FOR SUMP PIT @ elevation 2090 - GROUND LEVEL 15-16/Y 10 30/11/2014 30/11/2014 B
922 CIR-E-922 CHECK ELECTRIAL PVC CONDUITS FOR LIGHTNING SYSTEM @ Elevation 2109.5 - LEVEL - 1 31/P 10 03/12/2014 03/12/2014 B
923 CIR-E-923 CHECK ELECTRIAL OPENING IN SW2 @ Elevation 2115 - LEVEL - 2 15-17/R 10 04/12/2014 06/12/2014 C 10 E-923R1 07.12.2014 07.12.2014 B
924 CIR-E-924 CHECK ELECTRIAL OPENING IN SW6 @ Elevation 2115 - LEVEL - 2 15-17/Q 10 04/12/2014 07/12/2014 B
925 CIR-E-925 CHECK ELECTRIAL PVC CONDUITS FOR GROUNDING SYSTEM IN COLUMNS @ Elevation 2109.5 - LEVEL - 1 29-30/U 10 07/12/2014 08/12/2014 B
926 CIR-E-926 CHECK EMBEDDED PVC PIPE FOR FIRE ALARM SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 14/12/2014 C 10 E-926R1 15.12.2014 16.12.2014 B
927 CIR-E-927 CHECK EMBEDDED PVC PIPE FOR MATV SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 16/12/2014 B
928 CIR-E-928 CHECK EMBEDDED PVC PIPE FOR ACCESS CONTROL SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 14/12/2014 B
929 CIR-E-929 CHECK EMBEDDED PVC PIPE FOR IP CCTV SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 14/12/2014 B
930 CIR-E-930 CHECK EMBEDDED PVC PIPE FOR EQUIPMENT POWER SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 16/12/2014 B
931 CIR-E-931 CHECK EMBEDDED PVC PIPE FOR STRUCTURED CABLING SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 16/12/2014 B
932 CIR-E-932 CHECK EMBEDDED PVC PIPE FOR LIGHTING CONTROL SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 16/12/2014 B
933 CIR-E-933 CHECK EMBEDDED PVC PIPE FOR PUBLIC ADDRESS SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 16/12/2014 B
934 CIR-E-934 CHECK EMBEDDED PVC PIPE FOR NURSE CALL SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 14/12/2014 C 10 E-934R1 15.12.2014 16.12.2014 B
935 CIR-E-935 CHECK EMBEDDED PVC PIPE FOR MASTER CLOCK SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 16/12/2014 B
936 CIR-E-936 CHECK EMBEDDED PVC PIPE FOR BMS SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 14/12/2014 B
937 CIR-E-937 CHECK EMBEDDED PVC PIPE FOR POWER SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 16/12/2014 B
938 CIR-E-938 CHECK EMBEDDED PVC PIPE FOR LIGHTING SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 14/12/2014 C 10 E-938R1 15.12.2014 16.12.2014 B
939 CIR-E-939 CHECK BARE COPPER CONDUCTOR EMBEDDED IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 16/12/2014 B
940 CIR-E-940 CHECK EMBEDDED PVC PIPE FOR LIGHTIN PROTECTION SYSTEM IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 14/12/2014 B
941 CIR-E-941 CHECK ELECTRICAL OPENING IN LEVEL 1 SLAB (elev. 2104) C08 LEVEL-01 10 13/12/2014 14/12/2014 B
942 CIR-E-942 CHECK ELECTRICAL OPENING IN SW6 @ Eelevation 2115 level 02 17-19/Q 10 17/12/2014 18/12/2014 B
943 CIR-E-943 CHECK ELECTRICAL PVC CONDUITS FOR LIGHTING CONTROL SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-943R1 20.12.2014 20.12.2014 B
944 CIR-E-944 CHECK ELECTRICAL PVC CONDUITS FOR LIGHTING SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 GROUND LEVEL C13 10 18/12/2014 20/12/2014 C 10 E-944R1 20.12.2014 20.12.2014 B
945 CIR-E-945 CHECK ELECTRICAL PVC CONDUITS FOR LIGHTING PRODECION SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 B 10
946 CIR-E-946 CHECK ELECTRICAL PVC CONDUITS FOR POWER SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-946R1 20.12.2014 20.12.2014 B
947 CIR-E-947 CHECK ELECTRICAL PVC CONDUITS FOR EQUIPMENT POWER SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-947R1 20.12.2014 20.12.2014 B
948 CIR-E-948 CHECK ELECTRICAL PVC CONDUITS FOR BMS SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-948R1 20.12.2014 20.12.2014 B
949 CIR-E-949 CHECK ELECTRICAL PVC CONDUITS FOR FIRE ALARM SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-949R1 20.12.2014 20.12.2014 B
950 CIR-E-950 CHECK ELECTRICAL PVC CONDUITS FOR ACCESS CONTROL SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-950R1 20.12.2014 20.12.2014 B
951 CIR-E-951 CHECK ELECTRICAL PVC CONDUITS FOR NURRSE CALL SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-951R1 20.12.2014 20.12.2014 B
952 CIR-E-952 CHECK ELECTRICAL PVC CONDUITS FOR STRUCTURED CABLING SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-952R1 20.12.2014 20.12.2014 B
953 CIR-E-953 CHECK ELECTRICAL PVC CONDUITS FOR IP-CCTV SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-953R1 20.12.2014 20.12.2014 B
954 CIR-E-954 CHECK ELECTRICAL PVC CONDUITS FOR PUBLIC ADDRESS SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-954R1 20.12.2014 20.12.2014 B
955 CIR-E-955 CHECK ELECTRICAL PVC CONDUITS FOR MATV SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-955R1 20.12.2014 20.12.2014 B
956 CIR-E-956 CHECK ELECTRICAL PVC CONDUITS FOR GROUNDING SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-956R1 20.12.2014 20.12.2014 B
957 CIR-E-957 CHECK ELECTRICAL PVC CONDUITS FOR MASTER CLOCK SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 C 10 E-957R1 20.12.2014 12/20/2014 B
958 CIR-E-958 CHECK ELECTRICAL OPENING IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 10 18/12/2014 20/12/2014 B
959 CIR-E-959 CHECK ELECTRICAL PVC CONDUITS FOR GROUNDING SYSTEM IN COLUMN @ Eelevation 2110 LEVEL 1 GL : V 30 10 20/12/2014 20/12/2014 B
960 CIR-E-960 CHECK ELECTRICAL PVC CONDUITS FOR GROUNDING SYSTEM IN COLUMN @ Eelevation 2110 LEVEL 1 GL : V 30 10 20/12/2014 20/12/2014 B
961 CIR-E-961 CHECK ELECTRICAL PVC CONDUITS FOR AUDIO VISUAL SYSTEM IN C13 GROUND FLOOR SLAB @ Eelevation 2103.5 GROUND LEVEL C13 10 20/12/2014 20/12/2014 B
MINISTRY OF HEALTH STATUS CODE
KING FASIAL MEDICAL CITY ( ABHA) A Approved B Approved as noted
ALFOUZAN TRADING & GEN. CONTRACTING CO. C Revise & sub. D Rejected
Submittal 1st Submittal 2rd Submittal 3th Submittal 4th Submittal
NO Doc. No Title
FILE. Date in Returened Code FILE Submittal No Date in Returned Code FILE Submittal No Date in Returned Code Rev. Submittal No Date in Returened Code Rev. Submittal No Date in Returened Code

REQUEST FOR INSPECTION ( R F I )-Mechanical(24 Nov.2014 to 22 Dec.2014)


255 M-255 Check level of Mech UPVC sleeves in CORE 14 IN PART 5 GROUND LEVEL 17-18/V-W 5 23.11.2014 23.11.2014 B
256 M-256 Check level of Mech UPVC sleeves in CORE 14 IN PART 5 GROUND LEVEL 17-18/V-W 5 23.11.2014 23.11.2014 B
257 M-257 CHECK LEVEL OF MECH. OPENING IN PODIUM LEVEL IN PART - 2 @ SW 6 GL : 19-20/Q 5 24.11.2014 25.11.2014 B
258 M-258 CHECK INSTALLATION FOR MECH. OPENING IN PODIUM LEVEL IN PART - 2 @ SW 6 GL : 19-20/Q 5 24.11.2014 25.11.2014 B
259 M-259 CHECK INSTALLATION FOR UPVC MECH. SLEEVE & OPENING IN FIRST LEVEL IN PART - 4 GL : 28-31/V-S 5 24.11.2014 25.11.2014 B
260 M-260 CHECK INSTALLATION FOR UPVC MECH. SLEEVE LEVEL , SW1 & SW5 IN PART - 1 GL : 12-14 5 26.11.2014 26.11.2014 B
261 M-261 CHECK LEVEL OF MECH. UPVC SLEEVES IN SECOUND LEVEL , SW1 & SW5 IN PART - 1 GL : 12-14 5 26.11.2014 26.11.2014 B
262 M-262 CHECK INSTALLATION FOR MECH. OPENING IN SECOUND LEVEL , SW1 & SW5 IN PART - 1 GL : 12-14 5 26.11.2014 26.11.2014 B
263 M-263 CHECK LEVEL FOR MECH. OPENING IN SECOUND LEVEL , SW1 & SW5 IN PART - 1 GL : 12-14 5 26.11.2014 26.11.2014 B
264 M-264 CHECK INSTALLATION FOR GI MECH. SLEEVE IN SECOUND LEVEL , SW1 & SW5 IN PART - 1 GL : 13-14 5 26.11.2014 26.11.2014 B
265 M-265 CHECK LEVEL FOR GI MECH. SLEEVES IN SECOUND LEVEL , SW1 & SW5 IN PART - 1 GL : 12-14 5 26.11.2014 26.11.2014 B
266 M-266 CHECK INSTALLATION FOR MECH. SLEEVE IN SECOND LEVEL , SW5 IN PART 1 14-15/Q 5 30.11.2014 01.12.2014 B
267 M267 CHECK LEVEL FOR GL MECH. SLEEVE IN SECOND LEVEL , SW5 IN PART 1 14-15/Q 5 30.11.2014 01.12.2014 B
268 M-268 CHECK INSTALLATION FOR MECH. OPENING IN SECOUND LEVEL , SW1 & SW5 CPRE 1 PART - 1 GL : 12-15/Q & R 5 30.11.2014 01.12.2014 B
269 M-269 CHECK LEVEL FOR MECH. OPENING IN SECOUND LEVEL , SW1 & SW5 CPRE 1 PART - 1 GL : 12-15/Q & R 5 30.11.2014 01.12.2014 B
270 M-270 CHECK LEVEL FOR MAKE CORING IN CORE 10 ON GROUND LEVEL PART 1 11-12/S-R 5 01.12.2014 07.12.2014 C 5 M-270R1 07.12.2014 10.12.2014 C 5 M-270R2 11.12.2014 14.12.2014 B
271 M-271 CHECK INSTALLATION FOR UPVC MECH. SLEEVE IN SECOND LEVEL SW2/R IN PART 1 & 2 15-17/Q & R 5 03.12.2014 04.12.2014 B
272 M-272 CHECK LEVEL FOR UPVC MECH. SLEEVE IN SECOND LEVEL SW2/R IN PART 1 & 2 15-17/Q &R 5 03.12.2014 04.12.2014 B
273 M-273 CHECK INSTALLATION FOR MECH. OPENING IN SECOUND LEVEL , SW2/R IN PART 1 & 2 15-17/Q &R 5 03.12.2014 04.12.2014 B
274 M-274 CHECK LEVEL FOR MECH. OPENING IN SECOUND LEVEL , SW2/R IN PART 1 & 2 15-17/Q &R 5 03.12.2014 04.12.2014 B
275 M-275 CHECK INSTALLATION FOR MECH. SLEEVE IN THIRD LEVEL SLAB , 5 & 6 IN PART 1 & 2 16-19/W-S 5 04.12.2014 06.12.2014 B
276 M-276 CHECK INSTALLATION FOR MECH. GF SLEEVE IN CORE # 5 GROUND LEVEL IN PART - 3 24-26/M-N 5 04.12.2014 08.12.2014 B
277 M-277 CHECK LEVEL FOR MECH. GF SLEEVE IN CORE # 5 GROUND LEVEL IN PART - 3 24-26/M-N 5 04.12.2014 07.12.2014 B
278 M-278 CHECK LEVEL FOR MECH. GF SLEEVE IN THIRD LEVEL SLAB - 01 IN PART - 6 15-6/W-V 5 06.12.2014 07.12.2014 B
279 M-279 CHECK LEVEL FOR MECH. GF SLEEVE IN CORE # 8 PODIUM LEVEL IN PART 4 26-27/V-U 5 07.12.2014 08.12.2014 B
280 M-280 CHECK INSTALLATION FOR UPVC MECH. SLEEVE SW2 /R SECOND LEVEL IN PART - 2 16-17/R 5 08.12.2014 09.12.2014 B
281 M-281 CHECK LEVEL FOR UPVC MECH. SLEEVE SW2 /R SECOND LEVEL IN PART - 2 16-17/R 5 08.12.2014 08.12.2014 B
282 M-282 CHECK INSTALLATION FOR MECH. OPENING IN CORE # 11 GROUND LEVEL IN PART 3 29-30/S-R 5 11.12.2014 14.12.2014 B
283 M-283 CHECK LEVEL FOR MECH. OPENING IN CORE # 11 GROUND LEVEL IN PART 3 29-30/S-R 5 11.12.2014 13.12.2014 B
284 M-284 CHECK INSTALLATION FOR MECH. SLEEVE FIRST LEVEL SLAB IN PART 3 & 4 28-31/T-Q 5 13.12.2014 14.12.2014 B
285 M-285 CHECK INSTALLATION FOR MECH. OPENING FIRST LEVEL SLAB IN PART 4 29-30/S-R 5 14.12.2014 17.12.2014 B
286 M-286 CHECK INSTALLATION FOR MECH. OPENING IN CORE # 8 PODIUM LEVEL IN PART 4 26-27/V-U 5 14.12.2014 14.02.2014 B
287 M-287 CHECK LEVEL FOR MECH. OPENING IN CORE # 8 PODIUM LEVEL IN PART 4 26-27/V-U 5 14.12.2014 14.12.2014 B
288 M-288 CHECK INSTALLATION FOR UPVC SLEEVE & MECH. OPENING SECOND LEVEL IN PART 02 17-19/R 5 15.12.2014 16.12.2014 B
289 M-289 CHECK LEVEL FOR UPVC & MECH. OPENING SECOND LEVEL IN PART 02 17-19/R 5 15.12.2014 16.12.2014 B
290 M-290 CHECK LEVEL FOR UPVC SLEEVE & MECH. OPENING GROUND LEVEL SLAB IN PART 2 119-22/N-R 5 18.12.2014 20.12.2014 B
291 M-291 CHECK INSTALLATION FOR GL SLEEVE & MECH. OPENING SECOND LEVEL IN PART 02 SW 6 17-19/Q 5 18.12.2014 18.12.2014 B
292 M-292 CHECK LEVEL FOR GL SLEEVE & MECH. OPENING SECOND LEVEL IN PART 02 SW 6 17-19/Q 5 18.12.2014 20.12.2014 B
293 M-293 CHECK INSTALLATION FOR UPVC SLEEVE GROUND LEVEL SLAB IN PART 02 21-22/Q-P 5 18.12.2014 20.12.2014 B
MINISTRY OF HEALTH STATUS CODE

KING FASIAL MEDICAL CITY ( ABHA) A Approved B Approved as noted

ALFOUZAN TRADING & GEN. CONTRACTING CO. C Revise & sub. D Rejected

NO Doc. No Title Submittal 1st Submittal 2rd Submittal 3th Submittal 4- Submittal
FILE Date in Returened Code FILE Submittal No Date in Returened Code FILE. Submittal No Date in Returened Code Rev. Submittal No Date in Returened Code Rev. Submittal No Date in Returened Code
REQUEST FOR INSPECTION ( R F I )-Civil-Structural(24 Nov.2014 to 22 Dec.2014)
2268 CIR-C-2268 SHUTTERING OF COLUMNS - LEVEL 02 C15B , C17 13-15/S 70 23.11.2014 23.11.2014 B
2269 CIR-C-2269 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF C15B , C17 13-15/S 70 23.11.2014 23.11.2014 B
2270 CIR-C-2270 LONGITUDINAL & TRANSVERSE SLAB REINFORCEMENT FOR FIRST LEVEL SLAB , C-07 GL : 28-29-32/V-S-R 70 23.11.2014 29.11.2014 B
2271 CIR-C-2271 LONGITUDINAL & TRANSVERSE BEAMS & RIBS ALONG FIRST LEVEL SLAB , C-07 GL : 28-29-32/V-S-R 70 23.11.2014 29.11.2014 B
2272 CIR-C-2272 SHUTTERING OF CORE # 17 - PODIUM LEVEL (2092 - 2095) 19-20/Q-R 70 23.11.2014 24.11.2014 B
2273 CIR-C-2273 SHUTTERING OF CORE # 16 - PODIUM LEVEL (2092 - 2095) 21-22/Q-R 70 23.11.2014 24.11.2014 B
2274 CIR-C-2274 SHUTTERING OF SW 6 - PODIUM LEVEL (2092 - 2095) 19-20/Q 70 23.11.2014 24.11.2014 B
2275 CIR-C-2275 SHUTTERING OF SW 7 - PODIUM LEVEL (2092 - 2095) 21-22/Q 70 23.11.2014 24.11.2014 B
2276 CIR-C-2276 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF CORE # 16 & 17 PODIUM LEVEL (2092- 2095) 19-20/Q-R & 21-22/Q-R 70 23.11.2014 24.11.2014 B
2277 CIR-C-2277 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF SW6 & SW 7 PODIUM LEVEL (2092-2095) 19-20/Q & 21-22/Q 70 23.11.2014 24.11.2014 B
2278 CIR-C-2278 CHECK ELEVATION , DIMENSION & COORDINATES STAIRCASE # 01@ CORE # 17 - PODIUM LEVEL (2092-2095.07) 19-20/Q-R 70 23.11.2014 24.11.2014 B
2279 CIR-C-2279 CHECK ELEVATION , DIMENSION & COORDINATES STAIRCASE # 02 @ CORE # 16 - PODIUM LEVEL (2092-2095.07) 21-22/Q-R 70 23.11.2014 24.11.2014 B
2280 CIR-C-2280 REINFORCEMENT OF COLUMNS - LEVEL 02 (2116.0) C15,C15B,C16,C16A 16-19/S - 17-19/P 70 24.11.2014 24.11.2014 B
2281 CIR-C-2281 SHUTTERING OF COLUMNS - LEVEL - 02 (2116.0) C15B , C16 , C16A 71 24.11.2014 24.11.2014 B
2282 CIR-C-2282 REINFORCEMENT OF SW 1 (LEVEL - 02) 12-14/R 71 24.11.2014 26.11.2014 B
2283 CIR-C-2283 REINFORCEMENT OF SW 5 (LEVEL - 02) 12-14/Q 71 24.11.2014 26.11.2014 B
2284 CIR-C-2284 CJHECK COORDINATES & LEVEL OF BEARING PAD ALONG GL : V @ LEVEL 01 28-31/V 71 24.11.2014 24.11.2014 B
2285 CIR-C-2285 REINFORCEMENT OF COLUMNS - STARTER BARS INSIDE SLAB C 07 - LEVEL 01 29-32/V-T 71 24.11.2014 29.11.2014 B
2286 CIR-C-2286 APPLICATION OF TERMITE CONTROL BACK OF CORE # 4 15-17/M 71 24.11.2014 25.11.2014 B
2287 CIR-C-2287 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF COLUMNS - LEVEL -02 16-19/S 71 24.11.2014 24.11.2014 B
2288 CIR-C-2288 SETTING OUT , COORDINATES & FINAL LEVELING GUIDE OF COLUMNS & BW 1 INSIDE SLAB , C07 - LEVEL 01 28-29-23/V-T-S 71 25.11.2014 29.11.2014 B
2289 CIR-C-2289 SHUTTERING OF GF CORE # 15 (2098.0 - 2104.0) 13-14/W-V 71 25.11.2014 26.11.2014 D 71 C-2289R1 14.12.2014 12/15/2014 B
2290 CIR-C-2290 FORMWORK COORDINATES AND SETTING OUT OG GF CORE # 15 13-14/W-V 71 25.11.2014 27.11.2014 D 71 C-2290R1 15.12.2014 12/15/2014 B
2291 CIR-C-2291 SURFACE PREPAATION PRIOR TO APPLICATION OF DAMP COAT MATERIAL IN TOP OF RAFT FOUNDATION AND WALLS OF BW4 & SW6 16-18/Q-N 71 26.11.2014 26.11.2014 B
2292 CIR-C-2292 SURRFACE PREPARATION (STRIP FOOTING ) PRIOR TO APPLICATION OF BITUMNOUS PRIMER 28-31/M 71 26.11.2014 27.11.2014 B
2293 CIR-C-2293 APPLICATION OF BITUMINOUS PRIMER (STRIP FOOTING) 28-31/M 71 26.11.2014 27.11.2014 B
2294 CIR-C-2294 APPLICATION OF (1 ST LAYER) 4mm WP MEMBRANE (STRIP FOOTING) 28-31/M 71 27.11.2014 29.11.2014 B
2295 CIR-C-2295 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF CORE # 14 & GROUND LEVEL (2098- 2104) 17-18/W-V 71 27.11.2014 27.11.2014 D 71 C-2295R1 29.11.2014 11/29/2014 B
2296 CIR-C-2296 SHUTTERING OF SW1 - LEVEL 02 12-14/R 71 27.11.2014 29.11.2014 B 71 C-2296R1 09.12.2014 12/10/2014 B
2297 CIR-C-2297 SHUTTERING OF SW5 - LEVEL 02 12-14/Q 71 27.11.2014 29.11.2014 B
2298 CIR-C-2298 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF SW1 - LEVEL 02 (2110.0 - 2115.5) 12-14/R 71 27.11.2014 27.11.2014 B 71 C-2298R1 09.12.2014 12/10/2014 B
2299 CIR-C-2299 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF SW5 - LEVEL 02 (2110.0 - 2115.5) 12-14/Q 71 27.11.2014 27.11.2014 B
2300 CIR-C-2300 APPLICAATION OF (2ND LAYER) 3mm WP MEMBRANE (STRIP FOOTING) 28-31/M 71 29.11.2014 29.11.2014 B
2301 CIR-C-2301 CHECK INSTALLATION OF SEPARATION LAYER (ALYAF) 3 mm WPM PRIOR TO POURING OF CONCRETE SCREED (STRIP FOOTING) 28-31/M 71 29.11.2014 29.11.2014 B
2302 CIR-C-2302 CHECK ELEVATION PRIOR TO CONCRETE SCREED (STRIP FOOTING ) - 2095.0 28-31/M 71 29.11.2014 02.12.2014 B
2303 CR-C-2303 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF GF SW 8 (2098 - 2104.0) 27-29/q 71 29.11.2014 29.11.2014 D 71 C-2303R1 30.11.2014 12/1/2014 B
2304 CIR-C-2304 SHUTTERING OF SUMP PIT COVER @ PODIUM LEVEL 15-16/X-Y 71 29.11.2014 29.11.2014 D 71 C-2304R1 30.11.2014 11/30/2014 B
2305 CIR-C-2305 SHUTTERING OF GF SW 8 - (2098 -2104.0) 27-29/Q 71 29.11.2014 29.11.2014 D 71 C-2305R1 30.11.2014 12/1/2014 B
2306 CIR-C-2306 APPLICATION OF DAMP COAT MATERIAL (1ST COAT ) IN TOP OF RAFT FOUNDATION AND WALLS OF BW 4 & SW 6 16-18/Q-N 71 30.11.2014 01.12.2014 B
2307 CIR-C-2307 SHUTTERING OF SW 7 - PODIUM LEVEL (2095.0 - 2097.5) 21-22/Q 71 30.11.2014 02.12.2014 B
2308 CIR-C-2308 SHUTTERING OF SW 6 - PODIUM LEVEL (2095.0 - 2097.5) 19-20/Q 71 30.11.2014 02.12.2014 B
2309 CIR-C-2309 APPLICATION OF PROTECTION BOARD / PLINTH BEAM (2097.70) 24-27/W-V 71 01.12.2014 03.12.2014 B
2310 CIR-C-2310 REINFORCEMENT OF CORE # 1 - LEVEL 02 14-15/Q-R 71 01.12.2014 03.12.2014 B
2311 CIR-C-2311 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF SW 6 & SW7 PODIUM LEVEL (2095.0 - 2097.5) 19-20/Q - 21-22/Q 71 01.12.2014 02.12.2014 B
2312 CIR-C-2312 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF COLUMNS - LEVEL 02 13-19/P 71 02.12.2014 02.12.2014 B
2313 CIR-C-2313 SHUTTERING OF COLUMNS - LEVEL 02 - C15 , C17 , C16 , C16A 13-19/P 71 02.12.2014 02.12.2014 B
2314 CIR-C-2314 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF BW 4 & WALL OF CORE # 5 - GROUND LEVEL 22-25/N 71 02.12.2014 03.12.2014 B
2315 CIR-C-2315 SHUTTERING OF BW 4 - GROUND LEVEL 22-25/N 22UP TO CORE # 5 71 02.12.2014 07.12.2014 C 71 C-2315R1 08.12.2014 12/9/2014 B
2316 CIR C-2316 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF GF COLUMNS C15A (2104.0) 71 03.12.2014 06.12.2014 B
2317 CIR-C-2317 APPLICATION OF TERMITE CONTROL BEHIND BW 4 13-15/M-N 71 03.12.2014 03.12.2014 B
2318 CIR-C-2318 REINFORCEMENT OF GF COLUMNS C15A 31/P 71 03.12.2014 03.12.2014 B
2319 CIR-C-2319 SHUTTERING OF GF COLUMNS C15A 31/P 71 03.12.2014 06.12.2014 B
2320 CIR-C-2320 REINFORCEMENT OF GF CORE # 5 24-26/M-N 71 03.12.2014 08.12.2014 B
2321 CIR-C-2321 CHECK OVER ALL CLEANING OF SW 1 - LEVEL 02 PRIOR TO SHUTTERING 12-14/R 71 03.12.2014 08.12.2014 B
2322 CIR-C-2322 REINFORCEMENT OF CORE # 1 - LEVEL 14-15/Q-R (3.0m after GL 14 ) 71 04.12.2014 07.12.2014 B
2323 CIR-C-2323 REINFORCEMENT OF SW 2 - LEVEL 02 15-19/R 71 04.12.2014 07.12.2014 B
2324 CIR-C-2324 REINFORCEMENT OF SW 6 - LEVEL 02 15-19/Q 71 04.12.2014 07.12.2014 B
2325 CIR-C-2325 CHECK COORDINATES & LEVEL OF BEARING PAD ALONG GL ; 19 @ LEVEL 03 13/V-S 71 04.12.2014 07.12.2014 D 71 C-2325R1 14.12.2014 12/17/2014 B
2326 CIR-C-2326 SETTING OUT , COORDINATES & FINAL LEVELING GUIDE OF COLUMNS INSIDE SLAB , C07 - LEVEL - 03 15-16-19/W-T-S 71 04.12.2014 07.12.2014 D 71 C-2326R1 14.12.2014 12/17/2014 B
2327 CIR-C-2327 APPLICATION OF DAMP COAT MATERIAL (2 ST COAT ) IN TOP OF RAFT FOUNDATION AND WALLS OF BW 4 & SW 6 16-18/Q-N 71 06.12.2014 07.12.2014 B
2328 CIR-C-2328 CHECK COORDINATES / ELEVATION OF SRAIRCASE LANDING CORE # 13 & 17 - PODIUM TO GROUND FLOOR (2098.07) 19-20-21-22/Q-R 72 06.12.2014 06.12.2014 B
2329 CIR-C-2329 SHUTTERING OF WALLS INSIDE CORE # 1 - LEVEL 02 14-15/Q-R 72 06.12.2014 07.12.2014 B
2330 CIR-C-2330 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF WALLS INSIDE CORE # 1 - LEVEL 02 14-15/Q-R 72 06.12.2014 07.12.2014 B
2331 CIR-C-2331 FILLING OF BORE HOLES LEFT-OFF FROM CORING @ SLAB , C03 LEVEL - 01 C-03 72 06.12.2014 07.12.2014 B
2332 CIR-C-2332 SHUTTERING OF SW 3 - GROUND LEVEL 22-24/R 72 08.12.2014 13.12.2014 B
2333 CIR-C-2333 OVER ALL CLEANING PRIOR TO SHUTTER OF SW 2 - LEVEL 15-17/R 72 08.12.2014 10.12.2014 B
2334 CIR-C-2334 OVER ALL CLEANING PRIOR TO SHUTTER OF SW 6 - LEVEL 15-17/Q 72 08.12.2014 15.12.2014 B
2335 CIR-C-2335 APPLICATION OF DAMP COAT MATERIAL (3 ST COAT ) IN TOP OF RAFT FOUNDATION AND WALLS OF BW 4 & SW 6 16-18/Q-N 72 09.12.2014 11.12.2014 B
2336 CIR-C-2336 SHUTTERING OF SW 2 -LEVEL 02 15-17/R 72 09.12.2014 10.12.2014 B
2337 CIR-C-2337 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF GF SW 2 - LEVEL 02 (2110.0- 2115.5) 15-17/R 72 09.12.2014 10.12.2014 B
2338 CIR-C-2338 SHUTTERING OF GF CORE # 5 24-26/M-N 72 09.12.2014 11.12.2014 B
2339 CIR-C-2339 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF GF CORE # 5 24-26/M-N 72 09.12.2014 11.12.2014 B
2340 CIR-C-2340 APPLICATION OF WP 4mm MEMBEANE (1 ST LAYER) PLINTH BEAM (2097.70) 28-31/W-V 72 10.12.2014 11.12.2014 B
2341 CIR-C-2341 SURFACE PREPARATION PRIOR TO APPLICATION OF BITUMINOUS MATERIALS (2096.5 - 2097.7) 22-23/W-V 72 10.12.2014 14.12.2014 B
2342 CIR-C-2342 APPLIATION OF BITUMINOUS PRIMER IN BW 2 (2096.5 - 2097.7) 22-23/W-V 72 10.12.2014 14.12.2014 B
2343 CIR-C-2343 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF WALLS INSIDE CORE # 3 - GROUND LEVEL 02 26-27/Q-R 72 10.12.2014 13.12.2014 B
2344 CIR-C-2344 SHUTTERING OF WALLS INSIDE CORE # 3 - GROUND LEVEL 26-27/Q-R 72 10.12.2014 15.12.2014 B
2345 CIR-C-2345 CHECK COORDINATES / ELEVATION OF SRAIRCASE STEEP& LANDING @ GF CORE # 11 (2104.07) 29-30/R-S 72 10.12.2014 13.12.2014 B
2346 CIR-C-2346 SURFACE PREPARATION PRIOR TO APPLICTAION OF BITUMEN PRIMER FOR BW 4 / CORE 4 (2093.5 - 2095.0) 12-16/N 72 11.12.2014 14.12.2014 B
2347 CIR-C-2347 APPLICATION OF BITUMINOUS PRIMER FOR BW 4 / CORE 4 (2093.5 - 2095.0) 12-16/N 72 11.12.2014 14.12.2014 B
2348 CIR-C-2348 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF GF SW 3 22-24/R 72 13.12.2014 13.12.2014 B
2349 CIR-C-2349 APPLICATION OF WP 4mm MEMBEANE (2 ST LAYER) PLINTH BEAM (2097.70) 28-31/W-V 72 13.12.2014 14.12.2014 B
2350 CIR-C-2350 APPLICATION OF WP 4mm MEMBEANE (1 ST LAYER) FOR BW4 / CORE 4 (2093.5 - 2095.0) 12-16/N 72 13.12.2014 14.12.2014 B
2351 CIR-C-2351 APPLICATION OF WP 4mm MEMBEANE (2 ST LAYER) FOR BW4 / CORE 4 (2093.5 - 2095.0) 12-16/N 72 13.12.2014 14.12.2014 B
2352 CIR-C-2352 REINFORCEMENT OF GF CORE # 11 239-30/S-R 72 13.12.2014 16.12.2014 B
2353 CIR-C-2353 LONGITUDINAL AND TRANSVERSE REINFORCEMENT FOR 3 FLOOR (2116.0)
RD
C07 72 13.12.2014 14.12.2014 B
2354 CIR-C-2354 REINFORCEMENT OF LONGITUDINAL AND TRANSVERSE BEAMS & RIBS ALONG 3 RD FLOOR (2116.0) C07 72 13.12.2014 14.12.2014 B
2355 CIR-C-2355 PROTECTION BOARD FOR BW 4 (2093.5 - 2095.0) 12-15/N 72 14.12.2014 14.12.2014 B
2356 CIR-C-2356 COORDINATES / LEVELING GUIDE FOR COLUMNS , SW4 , SW8 & BW 1 INSIDE FF SLAB , C08 C 08 72 14.12.2014 17.12.2014 B
2357 CIR-C-2357 REINFORCEMENT OF COLUMNS ( STARTER BARS - 10 Nos) INSIDE SLAB , C07 - LEVEL - C4A , C6 , C7 , C10 C-07 72 14.12.2014 14.12.2014 B
MINISTRY OF HEALTH STATUS CODE

KING FASIAL MEDICAL CITY ( ABHA) A Approved B Approved as noted

ALFOUZAN TRADING & GEN. CONTRACTING CO. C Revise & sub. D Rejected

NO Doc. No Title Submittal 1st Submittal 2rd Submittal 3th Submittal 4- Submittal
FILE Date in Returened Code FILE Submittal No Date in Returened Code FILE. Submittal No Date in Returened Code Rev. Submittal No Date in Returened Code Rev. Submittal No Date in Returened Code
REQUEST FOR INSPECTION ( R F I )-Civil-Structural(24 Nov.2014 to 22 Dec.2014)
2358 CIR-C-2358 SHUTTERING OF GF CORE # 11 (2101.0 - 2104.0) 29-30/S-R 72 15.12.2014 17.12.2014 B
2359 CIR-C-2359 REINFORCEMENT OF SW 2 - LEVEL 02 17-19/R 72 15.12.2014 17.12.2014 B
2360 CIR-C-2360 REINFORCEMENT OF CORE # 18 - LEVEL 02 15-16/Q-P 72 15.12.2014 18.12.2014 B
2361 CIR-C-2361 SHUTTERING OF GF CORE # 18 LEVEL 02 15-16/Q-P 72 15.12.2014 18.12.2014 B
2362 CIR-C-2362 SHUTTERING OF SW 6 - LEVEL 02 15-17/Q 72 15.12.2014 15.12.2014 B
2363 CIR-C-2363 FORMWORK COORDINATES AND SETTING OUT OF SW 6 - LEVEL 02 15-17/Q 72 15.12.2014 15.12.2014 B
2364 CIR-C-2364 FORMWORK COORDINATES AND SETTING OUT OF CORE # 18 - LEVEL 02 15-16/Q-P 72 15.12.2014 18.12.2014 B
2365 CIR-C-2365 LONGITUDINAL AND TRANSVERSE REINFORCEMENT FOR SLAB C08 - LEVEL 01 (2104.0) C-08 72 15.12.2014 17.12.2014 B
2366 CIR-C-2366 REINFORCEMENT OF LONGITUDINAL AND TRANSVERSE BEAMS & RIBS ALONG SLAB C 01 - LEVEL 01 C 08 72 15.12.2014 17.12.2014 B
2367 CIR-C-2367 REINFORCEMENT OF COLUMNS , SW 4 , SW 8 , & BW 1 (STARER BARS) INSIDE SLAB C 01 - LEVEL 01 C 08 72 15.12.2014 17.12.2014 B
2368 CIR-C-2368 OVER ALL CLEANING OF SLAB , C08 LEVEL 01 C-08 73 15.12.2014 17.12.2014 C
2369 CIR-C-2369 REINFORCEMENT OF COLUMNS - LEVEL 01 29-30/T-U 73 17.12.2014 17.12.2014 B
2370 CIR-C-2370 APPLICATION OF WP 4mm MEMBEANE (1 ST LAYER) FOR BW2 (2096.5 - 2097.7) 22-23/W-V 73 18.12.2014 20.12.2014 B
2371 CIR-C-2371 APPLICATION OF WP 4mm MEMBEANE (2 ST LAYER) FOR BW2 (2096.5 - 2097.7) 22-23/W-V 73 18.12.2014 20.12.2014 B
2372 CIR-C-2372 APPLICATION OF PROTECTION BOARD I PLINTH BEAM (2097.70) 28-31/W-V 73 18.12.2014 20.12.2014 B
2373 CIR-C-2373 LONGITUDINAL AND TRANSVERSE REINFORCEMENT FOR SLAB - C 13 - GROUND LEVEL C 13 73 18.12.2014
2374 CIR-C-2374 REINFORCEMENT LONGITUDINAL AND TRANSVERSE BEAMS & RIBS ALONG SLAB - C 13 - GROUND LEVEL C 13 73 18.12.2014
2375 CIR-C-2375 REINFORCEMENT OF COLUMNS (C14A) SW 2 , SW 3 , SW 6 , SW 7 , & WALLS OF CORE # 2 ( STARTER BARS) INSIDE GF SLAB C13 73 18.12.2014
2376 CIR-C-2376 REINFORCEMENT OF SW 6 - LEVEL 02 17-19/Q 73 18.12.2014 20.12.2014 B
2377 CIR-C-2377 REINFORCEMENT OF CORE # 10 - LEVEL 02 11-12/R-S 73 18.12.2014
2378 CIR-C-2378 SHUTTERING OF SW 2 - LEVEL 02 17-19/R 73 18.12.2014 18.12.2014 B
2379 CIR-C-2379 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF SW 2 - LEVEL 17-19/R 73 18.12.2014 18.12.2014 B
2380 CIR-C-2380 REINFORCEMENT OF STAIR CASE / CORE # 16 - PODIUM TO GROUND 21-22/Q-R 73 18.12.2014
2381 CIR-C-2381 REINFORCEMENT OF STAIR CASE / CORE # 17 - PODIUM TO GROUND 19-20/Q-R 73 18.12.2014
2382 CIR-C-2382 SHUTTERING OF STAIR CASE / CORE # 16 - PODIUM TO GROUND 21-22/Q-R 73 18.12.2014
2383 CIR-C-2383 SHUTTERING OF STAIR CASE / CORE # 17 - PODIUM TO GROUND 19-20/Q-R 73 18.12.2014
2384 CIR-C-2384 CHECK SHUTTERING & SCAFOLDING FOR GF SLAB , C-13 C - 13 73 18.12.2014
2385 CIR-C-2385 COORDINATES / LEVELING GUIDE FOR COLUMNS , (C14A) SW2 , SW3 , SW6 , SW7 , & WALLS OF CORE # 2 INSIDE GF SLAB C13 73 18.12.2014
2386 CIR-C-2386 COORDINATES & FINAL LEVELLING GUIDE OF STAIRCASE/ CORE # 16 & 17 - PODIUM TO GROUND 19-20/Q-R 73 18.12.2014
2387 CIR-C-2387 REINFORCEMENT OF COLUMNS - LEVEL 01 C 8 , C 2 31/T-U-V & 29-30/V 73 21.12.2014
2388 CIR-C-2388 SHUTTERING OF GF SW 3 24-26/R 73 21.12.2014
2389 CIR-C-2389 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF GF SW 3 24-26/R 73 21.12.2014
2390 CIR-C-2390 APPLICATION OF PROTECTION BOARD IN BW 2 (2096.5 - 2097.7) 22-23/W-V 73 21.12.2014
2391 CIR-C-2391 SHUTTERING OF SW 6 - LEVEL 02 17-19/Q 21.12.2014
2392 CIR-C-2392 FORMWORK COORDINATES AND FINAL LEVELING GUIDE OF SW 6 - LEVEL 02 17-19/R 21.12.2014
PROJECT : KING FAISAL MEDICAL CITY (KFMC)
LOCATION : ABHA

PM CONSULTANT : HILL INTERNATIONAL


CONSULTANT : Zuhair Fayez Partnership
CONTRACTOR : Al Fouzan Trading & General Construction Co.

MATERIAL INSPECTION REQUEST (MIR) LOG (24 Nov.2014 to 22 Dec.2014)


MIR No. DESCRIPTION OF DELIVERED MATERIALS RESPONSE BY CONSULTANT REMARKS
DATE IN INVOICE-DATE RETURNED/DATE

MIR-C-233 Scaffolding material (Acrow scaffolding) 1182 30.11.2014 24.11.2014 04.12.2014 B


MIR-C-234 SCAFFOLDING CALCULATION SHEET 1381 07.12.2014 07.12.2014 08.12.2014 B
MIR-C-235 STEEL REBARS 16mm (156 TON) 13.12.2014 12.12.2014

Page 1 of 1
8.0 ATTACHMENTS

8.15 Daily Progress Reports and Photographs


Rebar Placing for L01/C08 in Zone 2

Installation of Scaffolding and Rebar Placing for C13/L01 in Zone 1


The Erection of the Mast of the Placing Boom in Zone 3

Placing of Concrete for SW8 for GF Level in Zone 2


Rebar Placing for C07/L03 in Zone 3

Rebar Placing for L01/C08 in Zone 2


Waffle Installation for C05/L03 in Zone 3

Placing of Rebar and Installation of Waffle for C13 at the Poduim Level
Rebar Placing for L01/C08 in Zone 2

Installation of Scaffolding and Rebar Placing for C13/L01 in Zone 1


Curing of The Casted C07/L01 in Zone 2
Waffle Installation for C05/L03 in Zone 3

Placing of Rebar and Installation of Waffle for C13 at the Poduim Level
Panoramic View for Phase 1 (Towards the North-East)

Panoramic View for Phase 1 (Towards the North-West)


Rebar Placing Columns at C07/L01 in Zone 2

Rebar Placing for L01/C08 in Zone 2


Shuttering Installation for BW4 at Ground Floor Level in Zone 2

Excavation Works for the Strip Footings along Grid M at Part 1


Rebar Placing Columns at C07/L01 in Zone 2

Rebar Placing for L01/C08 in Zone 2


Shuttering Installation for Core 3 at Ground Floor in Zone 2

Excavation Works for the Strip Footings along Grid M at Part 1


Rebar Placing for C08/L03 in Zone 3

Rebar Placing for L01/C08 in Zone 2


The Erection of the Placing Boom at L02 in Zone 3

Panoramic View for Phase 1 (Towards the North-West)


Rebar Placing Columns at C07/L01 in Zone 2

Rebar Placing for L01/C08 in Zone 2


Placing of Rebar and Installation of Waffle for C13 at the Poduim Level

Shuttering Installation for BW4 and Core 5 at Ground Floor in Zone 2


Placing of Rebar and Installation of Waffle for C13 at the Poduim Level

Shuttering Installation for SW3 at Ground Floor in Zone 2


Pouring of Mass filling at the Back of BW4 in Part 1
Rebar Placing for C08/L01 in Zone 2

Rebar Placing for L01 between Gridlines V & W in Zone 3


Placing of Rebar for C13 at the Poduim Level

Pouring of Concrete for BW4 of Groung Floor in Zone 2


Rebar Placing for C08/L01 in Zone 2

Rebar Placing for C11/L01 in Zone 2


Rebar Placing for C07/L03 in Zone 3

Placing of Rebar for C13 at the Poduim Level


Rebar Placing for C08/L01 in Zone 2

Rebar Placing for C07/L03 in Zone 3


Placing of Rebar for C13 at the Poduim Level

Pouring of Concrete for SW3 at Ground Floor in Zone 2


Pouring of Concrete for BW4 of Groung Floor in Zone 2

Panoramic View for Phase 1 (Towards the North-West)


Rebar Placing for C08/L01 in Zone 2

Rebar Placing for C11/L01 in Zone 2


Placing of Rebar and Installation of Waffle for C13 at the Poduim Level

Curing of the Casted C07/L03 in Zone 3


Rebar Placing for Columns along Gridline W in Zone 2

Rebar Placing for C07/L03 in Zone 3


Shuttering Installation for BW1 at Level One in Zone 2

Panoramic View for Phase 1 (Towards the North-West)


Rebar Placing for C11/L01 in Zone 2

Shuttering Installation for BW3 at Level Two in Zone 3


Curing of the Casted C07/L03 in Zone 3

Pouring of Concrete for C08/L01 in Zone 2


Rebar Placing for C09 and C11/L01 in Zone 2

Rebar Placing for C02/L03 in Zone 3


Placing of Rebar for C13 at the Poduim Level

Curing of the Casted C08/L01 in Zone 2


Pouring of Concrete for SW6 at Level Two in Zone 3
Rebar Placing for C01/L01 in Zone 2

Shuttering Installation for Core 1 for L02 in Zone 3


Installation of Scaffolding for C13 at the Poduim Level

Installation of Scaffolding for C02/L01 in Zone 2


Rebar Placing for Columns along Gridline P at L02 in Zone 3

Rebar Placing for L01/C01 in Zone 2


Installation of Scaffolding for C13 at the Poduim Level

Shuttering Installation of Shear Walls at L02 in Zone 3


Installation of Scaffolding for C08 at L01 in Zone 2

Backfilling Works under the Slab on Grade between Gridlines Q & R in Part 2
Excavation Works for the Strip Footings along Grid M at Part 1

Curing of the Casted C01 Slab at L03 in Zone 3


Installation of Scaffolding for C13 at the Ground Floor Level

Application of WPM for The Strip Footing in Part 3


Pouring of Concrete for C01 at L01 in Zone 2

Curing of the Casted C01/L01 in Zone 2


Rebar Placing for L01/C08 in Zone 2

Excavation Works for the Strip Footings along Grid M at Part 1


Fixation of the Geotextile Layer over the WPM under the Strip Footings in Part 3

Panoramic View for Phase 1 (Towards the North-West)


Rebar Placing for C08/L01 in Zone 2

Installation of Scaffolding and Rebar Placing for C07/L03 in Zone 2


Installation of Scaffolding and Rebar Placing for C13 of the Ground Floor

Excavation Works for the Strip Footings along Grid M at Part 1

You might also like