Final Top Sheet of TR-108
Final Top Sheet of TR-108
Final Top Sheet of TR-108
BASIS-ONE
Bid IDENTIFICATION NUMBER : JICA/MPPTCL/TR-108
TOP SHEET DOS-16.04.2012 CP 18 Months
220 KV TL-20 KMS & 132 KV TL-137 KM
%OF
%OF TOTAL INCOME (Rs)
EXPENDITURE TOTAL
SR.NO. DESCRIPTION WORK
(Rs) WORK
VALUE
VALUE
I WORK CONTRACT VALUE (to Quote) 572725151 100.00
SUPPLY ITEM 433207100 75.640
CIVIL & ERECTION 139518051 24.360
A DIRECT COST
1 SUPPLY OF BOUGHT OUT ITEMS 346925935 60.57
2 ERECTION & CIVIL 116023327 20.26
462949262 80.83
B SITE OVERHEADS
1 STAFF SALARIES 12569200 2.19
2 CONVEYANCE COST 1404000 0.25
3 STAFF WELFARE 527000 0.09
4 OFFICE INFRASTRUCTURE 2150350 0.38
5 SITE FACILITY & COMMUNICATION 1365000 0.24
6 SITE STORES 2409000 0.42
7 MOBILIZATION / DEMOB EXPENSES 150000 0.03
8 Labor Cess 1283566 0.22
9 Unanticipated price variation and time over ru 8590877 1.50
SUB TOTAL 30448993 5.32
C CORPORATE OVERHEADS
1 INSURANCE POLICY 2863626 0.50
Safety department
Safety Engineer 1 18 40,000 720000
Safety stuards/ Supervisior 2 18 10,000 360000
Store department
Purchase officer 0 10 40,000 0
Store Officer 1 18 25,000 450000
Store Asst 2 18 15,000 540000
Helper / Lab Technician (NMR) 3 18 5,000 270000
Plant department
Plant Engineer 0 0 40,000 0
Mechanics 0 15 10,000 0
Drafts man 0 20 15,000 0
Account/Admin Dept
Admin Officer 1 18 35,000 630000
Accountant 1 18 30,000 540000
Accounts Asst 1 18 15,000 270000
Time Keeper 0 0 4,000 0
Computer Operator 0 12 4,000 0
Camp supervisor 0 0 4,000 0
office boy 2 18 5,000 180000
NMR staff / Driver 5 18 5,000 450000
TOTAL 30 8978000
Add 40 % for benifits. 3591200
2 of 16
PROJECT- CONSTRUCTION OF TRANSMISSION LINES IN BHOPAL CIRCLE ON TOTAL TURNKEY
BASIS-ONE
Price to Quote: "Q" (Multiplying
Working Price "W" MF
factor)
Sr.no. Description Supply (W) Erection (W) Total (W) Supply(Q) Erection(Q) Total (Q)
1 Option No.1 360255384.572 116023327.0213 476278711.59 433207099.9481 139518050.7431 572725150.6913 1.2025
CONSTRUCTION OF TRANSMISSION LINES IN BHOPAL CIRCLE ON TOTAL TURNKEY BASIS-ONE (Package No.-8)
BID IDENTIFICATION NUMBER : JICA/MPPTCL/TR-108
Schedule No.7 Break Up of Offered Prices (CIP OR FORD) For Plants alongwith Mandatory Spares to be supplied from Abroad or Within the
Employer's Country
2 ACSR Conductor 0
(i) ACSR Zebra 24020574 2968942.9464 539790.3 0 549236.67 472316.546562 28550860.50 129 Kms.
(ii) ACSR Panther 92358176 11415470.5536 2075473 0 2111793.7 1816038.814688 109776952.01 496 Kms.
3 Earth wire (7/3.66mm, 95
6279000 776084.4 141101.7 146442.39 125933.25654 7468561.73143 161 Kms.
kg/mm2 quality)
4 Disc Insulator Strings/Long Rod porcelain
Insulators/Long Rod Polymer Insulators 0
(i) 9 disc single suspension string 2409340 297794.424 54142.69 56191.989 48322.3494684 2865791.45 1346 Sets
(ii) 9 disc double suspension string 295640 36541.104 6643.622 6895.0832 5929.4327064 351649.24 76 Sets
(iii) 10 disc single tension string 1085970 134225.892 24403.92 25327.606 21780.4966722 1291707.91 683 Sets
(iv) 10 disc double tension string 432760 53489.136 9724.983 10093.073 8679.5470776 514746.74 124 Sets
7 Conductor Accessories of ACSR Zebra
0
Conductor:
(i) Midspan joints 53950 6668.22 1212.364 1258.2524 1082.035227 64170.87 83 Nos.
(ii) Vibration damper 607890 75135.204 13660.5 14177.554 12191.9998914 723055.26 881 Nos.
(iii) Repair sleeve 7440 919.584 167.1917 173.51989 149.2185744 8849.51 31 Nos.
8 Conductor Accessories of ACSR Panther
0
Conductor:
(i) Midspan joints 111320 13759.152 2501.583 2596.268 2232.6628632 132409.67 253 Nos.
(ii) Vibration damper 1596870 197373.132 35884.86 37243.105 32027.2399062 1899398.34 3226 Nos.
(iii) Repair sleeve 18796 2323.1856 422.3837 438.37094 376.97746296 22356.92 127 Nos.
9 Earthwire Accessories: 0
(i) Suspension Assembly 176440 21807.984 3964.96 4115.0334 3538.7265144 209866.70 401 Sets
(ii) Tension Assembly with jumper
155760 19251.936 3500.239 3632.7228 3123.9630576 185268.86 264 Sets
cone
(iii) Midspan joint 8610 1064.196 193.4839 200.80729 172.6843986 10241.17 82 Nos.
(iv) Vibration damper for earthwire 421070 52044.252 9462.285 9820.4325 8445.0893982 500842.06 1066 Nos.
(v) Repair sleeve 4510 557.436 101.3487 105.18477 90.4537326 5364.42 41 Nos.
(vi) G.I. earth bond 520240 64301.664 11690.83 12133.331 10434.0687024 618799.90 929 Nos.
10 Tower Accessories
(i) Earthing set – 4 sets
6195000 123900 128589.62 110580.75 6558070.37 525 Sets
(As per drawing)
(ii) Danger Board – 1 No. 73500 1470 1525.6395 1311.975 77807.61 525 Nos.
(iii) Number Plate – 1 No. 27300 546 566.6661 487.305 28899.97 525 Nos.
(iv) Phase Plate (set of 3) 99604 1992.08 2067.4802 1777.9314 105441.49 673 Sets
(v) Anticlimbing Device
including Barbed wire –1 set. (As per
requirement brought out 2445548 48910.96 50762.24 43653.0318 2588874.23 523 Sets
in the bidding document)
TOTAL 360255384.57
SCHEDULE- IB
DETAILS & QUANTITY FOR INSTALLATION & OTHER SERVICES
S.No. ITEM Unit Total Qty Unit rate
4 Tower Erection
(i) Erection of super structure for
double circuit normal tower/
Gantry Structure including all
work above ground level MT 2482 4000
including tightening, punching of
bolts & nuts.
5 Stringing:
i. Stringing of ACSR Zebra
conductor & earth wire including
jointing&hoisting of insulator
strings, armour rods dampers
and other accessories and final
jumpering of for complete route
kM with :
Note: 1. Though the quantity of Check Survey work has been indicated above, commitment for detail survey
only may be included while working out total cost of erection work
2. The stub setting templates required for foundation of towers will have to be arranged by contractor
at his own cost.
Line-1 Line In Line Out (LILO) of one circuit of
220kV double circuit Bhopal-Ashta line at
Mugalia Chhap.
Line-2 132KV Double Circuit Single Strung (DCSS)
line between 220KV Shujalpur Substation
and 132KV Pachhore Substation.
Line-3 Stringing of second circuit of existing 132KV
Khilchipur- Jeerapur Transmission line.
Line-4 132 kV Jeerapur-Susner DCSS Line.
Line-5 132 kV Ichhawar-Sehore DCSS Line.
Line-6 132kV Mugalia Chhap -Sehore DCSS line.
N & OTHER SERVICES
Unit Rate Amount
With S.T.
0.00 0 0 0
0 0.00 0 0 0
0 0.00 0 0 0
0 0.00 0 0 0
0 0.00 0 0 0
0 0.00 0 0 0
0 0.00 0 0 0
123.596 485114.3 0.42 13.596 2.75319 10806.2708
146.068 573316.9 0.49 16.068 3.25377 12771.0473
308.99 1212785.75 1.05 33.99 6.882975 27015.6769
1348.32 0.00 148.32 30.0348 0
116023327.021 2584503.25
PCC 1:2:4(M15)
S.No. Description Unit Qty Rate Amount
1 Cement Bgs 6.4 290 1856.00
2 Sand cum 0.50 1298.3775 649.19
3 Metal (20mm) cum 0.90 680 612.00
labour Charges & Contractor
4 cum 1 600 600.00
T&P
5 Shoring & Suttering cum 1 50 50.00
6 Transportation from Store and l cum 1 200 200.00
7 Curing Charges cum 1 25 25.00
Contractor profit @ 12 % on
8 Metal, Sand, Labour & 247.34
Transportation Charges
9 Head Loading Charges Cum 0 1500 0.00
Workable Rate /Cum 4239.53
Revetment (1:5)
S.No. Description Unit Qty Rate Amount
1 Cement Bags 2.5 290 725.00
2 Sand cum 0.40 1298.3775 522.60
3 Stone cum 1.0 500 500.00
4 labour Charges cum 1 600 600.00
5 Transportation from Store and l cum 1 200 200.00
6 Curing Charges cum 1 25 25.00
Contractor profit @ 12 % on
7 Metal, Sand, Labour & 221.71
Transportation Charges
8 Head Loading Charges Cum 0 1500 0.00
Workable Rate /Cum 2794.31