MOM - EHV Shifting 28-02-2023
MOM - EHV Shifting 28-02-2023
MOM - EHV Shifting 28-02-2023
GI sheet cover to nala crossing bridge - RCPL confirmed the work will
2 15-03-2023 RCPL
start by 02-03-2023 and completion by 15-03-2023.
Providing route marker on road - RCPL informed that route markers are
3 31-03-2023 RCPL
ordered and installation to complete before 31-03-2023.
Restoration work -
1) Compond wall of H1 substation near MDN
2) Compound wall of college near CTT
3) Protection wall around CTT.
4 4) 22kV cable trench around CTT. 31-03-2023 RCPL
5) Removal of debries at H2 Substation.
6) Reinstatement of road at H2 Substation.
- RCPL agreed to complete all the above restoration works by 31-03-2023,
RCPL to submit the weekly progress.
Handing over of A1 & A2 section - RCPL agreed to attend all snag points
5 notified by MSETCL and complete handing over process including 31-03-2023 RCPL
certifcate of Taking Over by MSETCL.
09-01-2023
14-01-2023
RCPL to give manufacturing clearance for monopole of L 160 after
b 19-01-2023 RCPL
approval of revised foundation design by MSETCL.
03-02-2023
06-03-2023
02-01-2023
Loc-161A :- First lift concreting done on 18-02-2023, second lift not yet 14-01-2023
c done. RCPL agreed that second lift of concreting will be done on 02-03- 19-01-2023 RCPL
2023. RCPL to give intimation one day in advance. 06-02-2023
02-03-2023
10-01-2023
Location No. 17A - Approval of tower profile & foundation design by
15-01-2023
MSETCL at changed location (Drawing & Profile submitted on 14-02-2023). RCPL &
b 19-01-2023
PMRDA to confirm distance of proposed road from new location by 01-03- PMRDA
02-02-2023
2023.
06-03-2023
03-01-2023
12-01-2023
Location No. 18 - Steel cage inserted on 30-12-2023. GP has given NOC on PMRDA &
c 24-01-2023
23-02-2023. PMRDA to give letter to MSETCL by 01-03-2023. RCPL
06-02-2023
01-03-2023
31-01-2023
d Target date for completion of Package – C by 31-03-2023. 28-02-2023 RCPL
31-03-2023
10 Package - D
Location No. 13 - PMRDA to conduct meeting with land owner for
14-01-2023 PMRDA to issue letter to land-owner
consent. If land owner doesn't agree submit proposal to collector through
a 02-02-2023 Mr. Chaitnya Subhas Nelge for PMRDA
MSETCL for order.
10-03-2023 consent. Survey No. 28/1A Balewadi
10-01-2023
MSETCL approved cable route on 30-01-2023. Work to be started by 15-03-
20-01-2023 Approval pending at Project Circle
a 2023 except private land. PMRDA to resolve ROW RCPL
23-01-2023 office since 13.01.2023
02-02-2023
09-01-2023
Monopole design and foundation design submitted to MSETCL corporate 16-01-2023
PKG E & F Submitted to MSETCL &
b office for approval. SLD will be submitted by 01-03-2023. Monopole & SLD 31-01-2023 RCPL
secure approval by 10-02-2023.
approval will be obtained by 10-03-2023. 10-02-2023
10-03-2023
c RCPL to submit NCL Substation SLD and bay layout for approval. 10-03-2023 RCPL to follow-up RCPL
ROW permission from Gole, Subhas Gaikwad & green park socity for cable
d laying of package-E to be obtained by PMRDA. PMRDA
12 Package - F
02-01-2023
RCPL to submit detail cable route & trench drawing for approval of
a 24-01-2023 RCPL
MSETCL.
10-03-2023
03-02-2023
b RCPL to submit Ganeshkhind Substation SLD & Bay layout RCPL to follow-up with MSETCL RCPL
10-03-2023
ROW permission from Police department (Police ground land) and modern
collage land for cable laying to be obtained by PMRDA. PMRDA to issue 24-02-2023
c Letter to be given by PMRDA PMRDA
letters by 02-03-2023. 02-03-2023
13 Approvals from MSETCL: - Revised date in red color
13-01-2023 for
Revised check survey of B,C&D pkg to
submission & 20-01-
a Package B, C & D Monopole design/check survey approved. be submitted after finalization of all RCPL
2023 approval.
locations.
15-02-2023.
10-01-2023
For package-B & C to be submitted by
13-01-2023
SE (Inspection) approval for tower profile and method of construction for 02-02-2023 and approval by 10-02-
b 20-01-2023 RCPL
all packages. RCPL should submit online application through MSETCL. 2023, for package-D after finalization
02-02-2023
of all location.
08-03-2023
17-01-2023
20-01-2023
c Target date for obtaining approval of SE inspection. RCPL
07-02-2023
20-03-2023
PTCC approval - RCPL to submit letter to MSETCL regarding necessity of
d 10-03-2023
PTCC approval for all packages.
RCPL to give RFI well in advance (Two days before) to TUV, MSETCL,
PITCMRL & PMRDA for foundation casting as well as other activities at
15 To be confirmed by RCPL RCPL
every stage and work should be taken in hand and after clearance from
TUV & MSETCL.