MSFC Skylab Crew Systems Mission Evaluation
MSFC Skylab Crew Systems Mission Evaluation
MSFC Skylab Crew Systems Mission Evaluation
MEMORANDUM
NASA TM X-64825
O (PAGES) (CODE)
NASA
(NASA CR OI:_T/_,X OR AD NUMBER) (CATEGORY)
• .,/.
i_,::i i:i_¸i_:¸'- _
r r _
v
Errata TMX-64825 Section IV Pages 192 - 212 10/15/74
Page 200 delete the last sentence of the sixth paragraph and substitute with:
The experiment hardware and procedures were adequate and the experiment
operations were acomplished with only minor anomalies; one triple exposure,
and one of the filters became contaminated causing loss of data.
O
Page 205 delete the first sentence in Paragraph one of sub heading 5a.
Operations and substitute with:
The experiment S073/T027 Photometer System was scheduled for operation
during SL-2, SL-3 and SL-4.
Page 206 delete partial paragraph at top of page and substitute with:
o•. was moved out of the camera's view. The T025 Canister was mounted to
the S019 AMS using the S063 adapter• No anomalies were reported. However,
all SL-4 photographs were out of focus, apparently due to a missing pres-
sure plate in the Nikon 02 camera•
O
Page 209 delete line one of the second complete paragraph_and substitute
with:
The crew also experienced a jamming problem with the DAC film magazine
which caused the entire spectrograph to cease functioning.
Page 210 add this sentence as written to the end of the last paragraph:
One of the harness dector modules was left in the MDA for retrieval should
a revisit to the Skylab ever be made.
Page 212 add this sentence as written to the end of the last paragraph.
However, all the photographs were taken at the wrong focus setting, re-
suiting in out-of-focus pictures•
-i:_,_i
_¸_
!!!!ii
!,'! ', !
Errata TMX-64825 Section IV pages 214 - 221 10/15/74
O
Page 214, first paragraph, second sentence, should read:
"The equipment for the D024, consisting of two thermal control coated
samples, two polymeric film sample panels, and two return containers..."
Page 214 delete heading marked "2." written in correct form as:
2. M512 (M551_ M552_ M553, M555) Material Processing in Space
M479 Zero Gravity Flammobality M518 _556-M566) Multipurpose
Electric Furnance
Page 216 delete the words (and surface tension) from the end of sentence
one, paragraph one, and add the following phrase to the end of the sentence:
"_.. and material science investigation in the areas of crystal growth,
immiscibles, composites, diffusion, and eutectics."
Delete the last sentence of the first paragraph and substitute with:
Experiments M551-M553, M555, M556-M566 and M479 utilized the M512
facilities.
Page 217 add a paragraph between paragraph six and seven, correctly written:
Angles between various celestial targets were to be observed, and the
mean error and standard deviation between successive readings in a group
were to be used as a measure of any change in the crewman's ability, to
make decisions and measurements as caused by the space environment.
O Page 217 delete from paragraph seve_ line two "... all three ..." , re-
place with, "... the last two ..."
O
Page 217 add a sentence to the last paragraph, correctly written:
During SL-4, the transparent wardroom window cover was left in place for
all but the last two groups of sightings. The mean error and the standard
deviation were large when the cover was in place.
O
Page 219, second paragraph, after the last sentence add the following:
"Also, the upper atmosphere of the earth was to be photographed."
O
Page 220, first paragraph, first sentence, delete: "... and Zodiacal light..."
O Page 220, first paragraph, lines 5, 6, 7 substitute the work "Nikon" for
the word, "DAC".
I
Errata TMX-64825 Section IV pages 22i i- 232 10/15/74
_:/!i
'__
i T025 was not originally designed for EVA use but, with the addition of
the specially designed EVA bracket, occulting disc assembly and filters
!i:,I _
(illustrated in section VI, E), ultraviolet photographs ware taken of the
i!:i
ii
! i_ earth's upper atmosphere
o Page 228 delete last sentence of seventh paragraph i.e. "The FMU's were
placed..."
o Page 228, eighth paragraph, first sentence, delete, "... adjacent to the
film vault..."
o Page 228, last paragraph, third line, third word change from "five" to "two"
o Page 228 delete last sentence of the last paragraph and rewrite as follows:
Of the two performaces conducted, one shirt sleeve and one suited run was
planned for each of the SL-3 and SL-4 missions.
Page 232 add a sentence to the end of the first paragraph as follows:
] '!
An additional data pass was made on SL-3.
Page 232, second paragraph, second sentence, add to the end of the sentence
the following: "...during the dark cycle of the moon."
•_ • _ • •_ i_'__ _
•_ _i_iii_!i_i_
_ i_ _i_i_ • '_'_,_i _ ,_ii_,_
• _,_,
_ ___ •
Errata TMX-64825 Section IV pages 232 - 241 10/15/74
o Page 232, paragraph four, line two, delete second work "SL-3" and
replace with "SL-4".
o Page 233 delete first word, line two of first paragraph, "SL-3" and
substitute with, "SL-2".
o Page 233, paragraph 5b, second sentence, replace "Ten days..." with
"Twenty-three hours..,"
o Page 234 change the third sentence of third paragraph to read as follows:
The experiment was performed early-, mid-, and late-mission by all three
c rewme n °
o Page 236 delete paragraph 8b amd substitute with the following paragraph:
b. Post Mission Assement Due to the high OWS temperatures after
launch, and subsequent on-ground testing, it was determined that the
seed germination probability had been significantly reduced. Resupply
of seeds was carried out on SL-3 and performance of ED 61/62 was accom-
plished during SL-4. The seeds were implanted and photographed as
scheduled with no anomalies reported.
o Page 240, paragraph lla, second sentence, substitute "behind" for "in".
o Page 240 delete the last sentence of the fifth paragraph, i.e. "Next,
the mass..."
k __!!i!_i_
i! ii_!_i_i_
_I. i_i¸¸¸__ ._ i .
TECHNICAt REPORT STANDARD TITLE PAG
t. REPORT NO. 12 GOVERNMENT ACCESSION NO. 3. RECIPIENT'S CATALOG NO.
NASA TM X-64825 I
4. TITLE AND SUBTITLE
5, REPORT DATE
MSFC SKYLAB CREW SYSTEMS MISSION EVALUATION August 1974
6. PERFORMING ORGANIZATION CODE
16, ABSTRACT
Unclassified-unli mited
19. SECURITY CLASSIF, (of thil teport_ 720. SECURITY CLASSIF. (of this page) ]21. NO. OF PAGES 22. PRICE
MSFC - Form
Unclassified
i, TABLE OF CONTENTS
i' [''
Page
°.°
TABLE OF CONTENTS ..................... Ill
LIST OF ILLUSTRATIONS] .................... viii
LIST OF TABLES ....................... xiii
INTRODUCTION ........................ i
7 ¸
)i:
SECTION I. SKYLAB CONFIGURATION EVOLUTION -
A PERSPECTIVE VIEW ............... 2
iii
TABLE OF CONTENTS (Continued)
Pa e
iv
TABLE OF CONTENTS (Continued)
Page
A •
Scheduled IFM oooeooleoooooooeeoe
242
I. Design Description ............... 242
2. Post Mission Assessment ............ 242
i i
vl
TABLEOFCONTENTS
(Concluded)
Page
D. Twin Pole Sail Deployment ............. 329
i. Concepts for Orbital Workshop Thermal
Shielding . . . _ . . . . . . 329
2. Twin Pole Sail'Hardware Design'and'Description. 329
3. Crew Hardware Evaluation ............ 334
4. Twin Pole Sail Deployment ........... 334
5. Crew/Equipment Interface Anomalies....... 336
6. Summary.................... 337
E. Other EVAActivities ................ 338
i. D024 SampleRetrieval ............. 338
2. $230 Sample Retrieval ............. 338
3. T025 CameraOperations ............. 338
4. $201 CameraOperations ............. 340
5. S020 Solar Photography............. 340
6. S149 Deployment ................ 341
7. ATMDoor RampLatch Removal .......... 343
8. S052 - Disc Cleaning ......... - - • -- . 345
9. ATMContingency Door Opening (S054, S082A)... 345
i0. CBRMRepair .................. 346
ii. Rate Gyro PackageCable Installation ...... 347
12. Sail Sample Installation Retrieval ....... 347
13. S193Antenna Repair .............. 348
14. Skylab Vehicle Exterior Inspection ....... 350
15. S054Filter Wheel Positioning ......... 351
SECTIONVII. TESTDATA............. • • • • . • 352
A° Waste Management ................ 352
i. Waste ManagementDesign and Development
Reviews .................... 352
2. SubsystemConclusions ............. 354
3. SubsystemCertification ............ 360
4. HS and ST Test Summaries............ 363
B. WhoLeBody Shower ................. 365
i. Testing ................... 365
C. Suit Drying .................... 367
i. Development Tests ............... 367
2. Qualification Tests .............. 367
3. Acceptance Test ................ 367
4. Special Tests ....... , ..... , , • . 367
5. Problems and Corrective Actions ........ 367
6. SubsystemConclusions ............. 368
7. SubsystemCertification ............ 369
D. Stowage ...................... 370
i. Stowage System................. 370
E. Crew Systems.................... 372
i. KS-OOIOA- Integrated Crew Compartment
Fit and Functional Test ............ 372
vii
LIST OF ILLUSTRATIONS
viii
LIST OF ILLUSTRATIONS (continued)
Title page ,
ix
LIST OF ILLUSTRATIONS
(continued)
Title Page
/i
Figure 123. S056 X-Ray Telescope C&D ............ 177
Figure 124. S082A and SO82B XUV Instruments C&D ...... 178
Figure 125. S052 White Light Coronagraph C&D ........ 179
Figure 126. S055 Scanning Spectroheliograph C&D ...... 179
Figure 127. S054 X-Ray Spectrographic Telescope C&D .... 180
Figure 128. ATM Restraint Device .............. 182
Figure 129. ATM Alert Status Lights C&D .......... 183
Figure 130. ATM X-Ray History Plotter C&D ......... 183
Figure 131. ATM Extreme Ultraviolet Monitor
Integrated C&D ............... 183
Figure 132. Astronaut Anthropometric Data ......... 185
Figure 133. Sample Building Blocks With Five Parts ..... 188
Figure 134. Scientific Airlock ............... 193
Figure 135. Experiment SOl9/Articulated Mirror
Operating Configuration ........... 198
Figure 136. Spectrograph Assembly ............. 201
Figure 137. S063 EA-I UV Camera Operation Configuration . . 201
Figure 138. S063 EA-I Visible Camera Operation
Configuration ................ 202
Figure 139. S063 EA-II S-SAL Operational Configuration... 202
Figure 140. S149 MD/CSU With Detector Cassette Set,
Operational Configuration .......... 207
Figure 141. Experiment $228 Operating Configuration .... 211
Figure 142. D024 Experiment Panels and Sample Return
Container Configuration ........... 215
Figure 143. M512 Materials Processing Facility Stowed/
Operational Configuration .......... 215
Figure 144. TO03 Stowage Container. 219
Figure 145. T025 Experiment IVA Operational Configuration _ 220
Figure 146. TO27(A) Sample Array System, Operating
Configuration ................ 222
Figure 147. TO27(B) Photometer System, Operating
Configuration ................ 222
Figure 148. ASMU Operational Configuration ......... 225
Figure 149. Astronaut Maneuvering Research Vehicle ..... 225
Figure 150. TOI3 Experiment Operational Configuration . . . 229
Figure 151. FCMU and Backpack Stowed Configuration ..... 230
Figure 152. FCMU Operational Configuration ......... 230
Figure 153. ED41 Experiment Configuration ......... 235
Figure 154. ED52 Experiment Operational Photographic
Configuration ................ 235
Figure 155. ED61/62 Seed Planter .............. 237
Figure 156. ED61/62 Container Assembly ........... 237
Figure 157. ED61/62 Operational Photographic
Configuration ................ 238
xi
•r
LIST OF ILLUSTRATIONS (concluded)
Figure Title Page
xii
_ !<_I<C ?_<i/r_<ii_ _
i
LIST OF TABLES
Xlll
INTRODUCTION
.... j :
Situated between the MDA and the Orbital Workshop. The AM/STS
configuration and functions were perhaps least affected by the
"wet to dry" decision. From the outset, this element was intended
to provide extra-vehicular activity (EVA) capability and serve as the
"systems control center" for the cluster. This module provided the
cluster with its two-gas control systems, power distribution and
control system, and data/communications systems. Most of these
systems controls were located in the STS adjacent to the MDA. The
crew station associated with these controls envisioned the crewman
positioned with his feet secured in the MDA. When the ATM control
and display panel was later repositioned to the MDA, the STS control _
crew station was slightly compromised.
4
Figure I. AAPVehicle Configuration - 1967
i] i ii i F i i i I i i i il
A. Water System
a. Design Description
\_ '_
WASTE MANAGEMENT
COMPARTMENT
• HEATER
PURIrICATI_C'__ L_ .., • DISPENSERS
EQUIPMENT_{:// __::_ --_il • WASH CLOTH
SQUEEZER
PRESSURIZATION PORT'-",. "% " " " " " " GSE FLUSH/BLEEO
L,o ;, , _y,_E
,..E_,O.
• .t _ .- WATE,
LEVEL POR.AB.E
WATER,A.
/ _ WATER
OU.ET
8
i,i
IODINE
ADDITION
CHART ---,
o %
IODINE
CONTAINER
2PUSHBUTTON
VENT VALVES
LOCATEO ON
DOOR SLOE-",
@
© ©
IODINE
CONTAINER
ILOR
WATER COMPARATOR
-Z _Z IODINE
INTROOUCTION IODINE
PROCEDURE INJECTOR
REAGENT
CONTAINER
+Y
"iodine addition chart", which scheduled water tank volume (%) and
iodine concentration. In order to provide safe drinking water, the
iodine concentration was to have been 0.5 ppm or greater. Sampling
equipment and a color comparator provided the crew a means of period-
ically determining the iodine concentration to ensure that the level
was always above 2-ppm. If the level was low, the crew was to use
an iodine injector to increase the iodine concentration.
lO0-ppm. The solution was then to be injected into the water distrib-
ution system for a biocide soak. An illustration of the portable
water tank is included in Figure 6.
i0
POAIAIII.| WATII lANK
PnIUlURIZA_O_ PORTqRzpl
e_'rloN
_r,i mlFi
_ _:;_,',
....
OPlN pR_I mlLI_F VA_V_ IR
cse FLVSMInllid
WATln C_'VL
/ . <-;:';'*°"l'i\
VALVE
/ _ " "l< _ GONTA'"ER/,.-_II_,_=_,DJ.J
SOLUTION ESA=. . ' WAST P
II
WARDRQ OMWATER _'___
DISPENSER VALVE IrlSTALLATION I_%._'_C_,.,- _/_ I
VO,U,.,ESE..ECTORr""P._
_'-,,_SELECTOR ,"..'_'_"
__J
WATER DISPENSER
,,,STA'LAT,ON
H20 GUN _.,'_' HEATER --I"1 L:7111--11," I
zvl i,
__ _ _ r--TOOT"BRUSH
'_ /U,PER_OR,A_r", )
PORT TANK/VVMC
H20 CONNECTOR HEATER
CONDENSATEDUMP POR'
DUMP LI CLOTH
SQUEEZER DUMP LII SQUEEZER
IEEZERBAG
(ENCLOSEDIN COVER)
FILTER
(IN POCKET)
#
H20
Figure 9. Water Management System (WMC)
12
<> : i <t_:!!i:
• VOLUME
_O,_,OURCE,.P"GG",,_ :_ _. /-XOU_ER
,,"e .... _ _][_"--_
f rq
I T I I I WATER
CONTAINER _ \ _BAG
I ['T] ___E___._J | 600 EXPELLABLE WATER I \
L'--'T .... ,i,'-'_ I • 10 TANKS ('rYP) _ A \ _--'WASH
. • _ CLOTH
t _ AGITATOR
_" _IG _ _ P uMpATOR _' \ SQUEEZER
/ "_ ' L / -- ( _ _'_'7 ] _--'HYGIENE WATER
L.,.2. k L-T,.PRE=O.,
BLEED
W CAP ,
XDUCER _ _/",..,_
_
,
I
DISPENSER
VALVE Y"O /
tanks was verified. The temperature of the water tanks was approxi-
mately 130°F. With the deployment of the parasol heat shield, the
vehicle temperatures began to drop. The water tank temperatures also
dropped, at a slower rate, reaching equilibrium temperatures within
several days. During initial water system activation, water tanks
i and 7 were connected to the Wardroom and WMC distribution systems
respectively; the gas pressurization valves on water tanks i (Ward-
room), 6 (fire hose), 7 (WMC), and 9 (AM equipment) were opened; and
the N2 distribution network was activated with no reported anomalies.
Initially, there was some concern that the N 2 supply line from the
AM may have been damaged when the meteoriod shield was lost during
launch. The regulated system pressure of 35-psig was verified in-
flight, during the first mission, by attaching the portable water
bottle (gas side) to the system and monitoring the pressure gauge.
This was the only time the portable water tank was used during the
first mission. It was used during the other missions to check the
N 2 system pressure and for initial Wardroom network sterilization.
The urine flush system was not activated during the three
missions.
For the second and third missions, the Wardroom and WMC water
systems were activated and deactivated without incident, the regulated
gas supply to the water tanks performed in a normal manner, and water
purification equipment was successfully utilized by the crew.
13
Figure ii summarizes the totsl water usage during all three
missions. Water usage, from each mission, was as follows:
14
_o0
OATA (FIRb'T I
. : TELEMETRY'
MISSION} |
_OO
7O0
=
600
I
>
ALLLATEO _0
300
_"_oo
100
o I 1 f I I I I I I I I I I l I I I I I I I I I I 1 1 I 1 I I 1
4 6 8 10 12 14 16 18 30 22 24 Z_S _8 30 32
MISSION OAY
15
\,.,
1.000
8OO
7O0
/,
_.......T_.6 LBS
8OO
O
®0
USABLE
O OQ (_ REMAING.
500
300
100
B4S.OLBS UNUSABLE
O
I I I I I I I I I I I I t I I I 1 I I I I I 1 I I I 1 I I I 1
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32
MISSION DAY
JvE
II]llJl)llll IIIIllllllllllllllllllllllllll
i,or
i
,o)
l _ o_s *CT,VM,O_
SO
M,SllO_OMV
16
i :" .. ' - , :
rU'ICTIO)! MAXl_rdM 3 CREWMEN TOTAL CONTAINERS USABLE REMAINING
USE RATE REQUIREMENT, LB REQUIRED AVAILABLE a, USABLE, LB
I I LB
'_TABOL IC TANKS:
!_t4CTANKS:
a3ASED
Or(ACTUAl.
USABLE
QUANTITY
OF591.6POUNDS
PERCORATINER
Table i. Water Budget
1.000
--ALLOCATED
II00
TANK 3
ALLOCATED --- I
64]0
' --TANK 2
4O0
' _ ' r" USAGE
..... TAN_ (
\
" O0 0 O0 ' "_ '
ALLO(:AT ED'-'/
loo l
\
I J I
o I I I I I , I I I I I I I I
o 8 12 16 20 24 28 32 36 40 44 40 5;t 56 60
MISSION DAYS
Figure 15. Water Consumption - Tanks No. i0 and 2 (Wardroom) - Second Mission
l
17
1,000
Q ACTUAL USAGE
SiX)
_ALLOCATED
BOO
F"TANK 8
ALLOCATED
700
,/ L ¸
6OO
50O
cD Q
> TANK ? USAGE l
QOQ O
4OO e C_O_
3O0
°
O
ALLOCATED "--I
10C
--.q
I t I I I I I I I f t I I I
0
4 9 12 16 20 24 28 32 36 40 44 48 52 56
MISSION OAYS
,lo
ioo
oo
t_
so
s_
*o
Jo
;,o
to
"--'-'-_' '_-__
I-1 _ -U
_ -u_qj__slr_n
I1t I 1 I I I I I I I I I I I I I I I I I I I t I I I I I I I I I I I i I I I I i
o
,,o
,oo
_o
Z
| Jo
,,e
,oo i-
ooL
1o
lo
:[ n_ _ FL,
n_or_ o .. _
:or--r--,--rr_T _ _u uu b_<--u-L_%.
'ol,_,,,,_,.,,-,,,,
o i •
,,, ,,,,,,,, ,, I..., _,.. ;.;.:._,...
i i )o tl i_ li ii i 3,'4 II a ill ii I1 14 x i 4_1 II 44 I ill i(i ii ill H i I l
ul_o_ OAr
18
_'o co_ - CAAR
, i !,'_'.:_
:_i_{_
i,/,
•q,i _ /_j
)o
i • 'Po
,o
*,o
lee
go---.
:[ r
Figure 18. Drinking Water Consumption - Third Mission
|, ,
Water Sampling
19
DOY 265 Wardroom Chiller Data Not Available
DOY 324 Water Tank No. 3 8.0 - 9.0 ppm
DOY 337 Water Tank No. 4 5.0 ppm
DOY 338 Water Chiller 9.0 ppm
DOY 339 Water Tank No. 5 6.0 ppm
DOY 340 Water Tank No. 5 9.0 ppm
DOY 340 Water Tank No. 6 6.0 ppm
DOY 341 Water Tank No. 8 4.0 ppm
DOY 342 Wster Tank No. 9 1.0 ppm
i _
Iodine Injections
2O
Limits Results
prope[tles
(Micromno/cm @ 25°C)
PH (6 25°C) 4-8 4.6
91.
Total Residue (mg/l)
Taste and Odor (at 45oc) Reference Only
Particulate/500 ml
Sterility
21
r
Properties Limits .. Results
(Micromho/cm @ 25°C)
4-8 4.8
PH (@ 25%)
Total Residue (mg/1) 91.
Taste and Odor (at 45°C) Reference Only
II 5
Turbidity (Units)
Reference Only 5 to 10
Color True (Units)
Dissolved Gases (% by Volume) 0.5
.m
Bioeide (ppm) Reference Only
:!_ i ¸
Partlculate/500 ml
S.terillty (Colonies/150 m l)
0.01 .01
Cadmium
Calcium 5.6 .I
0.05 .02
Chromium (hex)
1.0 .01
Copper
Iron 0.3 .29
0.05 .02
Lead
0.05 .01
Manganese
0.005 .005
Mercury
Nickel 0.05 .03
Silver 0.05 .02
5.0 .02
Zinc
Reference " 33.4
Iodide and Iodine
Selenium Reference
.05
12
.5
Silicon
8.8
Potassium
.5
Magnesium
1.74
Soclum
o.
Arsenic
Aluminum .5
Additional Data
.I
Nitrogen (ppm)
Nitrate (ppm) 7.0
.01
Nitrite (ppm)
22
ib
ANALYSIS
AT LOADING ANALYSIS AT RETUI_J
Properties Limits 'l'_dIK#i TiU_K #_ TiU_K #i TN_K #_ CHILLEh
Particulate/500 ml
Additional Data
Organic Carbon 27 30 i
Color 25 20 5
Amoni a Nitrogen 10 ll.2 .h
Chloride 13.5 13.0 13
Table 4. Potable Water - Tank No. I, 5, and Chi ller - Third Mission
m..
23
if the pressure indication was true. Activation, without the trans-
ducer, was no problem. The network was used throughout the second
and third missions with no further difficulty.
During the first mission, a flow decrease from the WMC hot
water dispenser was reported. The dispenser valve was replaced with
the spare unit and the flow returned to normal. The crew reported
evidence of contamination in the removed unit.
A summary of crew observations, relative to the water system_
are as follows:
• The iodine levels in the water tanks remained above the
predicted depletion rates. Iodine taste in the water
wasn't noticeable. Chilled water tended to remove the iodine
taste.
• The water temperature, both hot and cold, was excellent.
There was no condensation associated with the Wardroom
water chiller.
• The food reconstitution dispensers were adequate. The
location of the leak reported on the food reconstitution
dispenser was merely a little blow-by on the dispenser
and tended to collect on small radii, giving the appearance
of being a leak.
• Recommendations were made to have the food reconstitution
water selector dispensing volume increased to 8-ounces,
compared to 6-ounces, because many of the beverage packets
required 8-ounces of water.
• There were no problems encountered distinguishing color
on the low end of the color comparator.
• The tank bellows loeator (water measuring device) worked
satisfactorily on all the water tanks because of the magnet
location stripe provided on the side of each tank.
• The tank bellows locator on the condensate tank provided
less than desirable results because there was no location
stripe on the tank.
The as-flown concept of water storage, transfer, expulsion,
and general management was proven to be completely satisfactory,
workable, and feasible as an approach where weight allowance is not
a critical consideration. However_ it is generally acknowledged
that future space programs will have to explore and develop other
potential concepts, such as water reclamation, which is less
weight-costly.
24
B. Waste Management System
I. Fecal Collection
25
/--UPINE DUMP
COMPARTMENT H822
/ /---URINE SYSTEM
---- --/ DISPENSERH823 _-URINE COLLECTOR
WASTE PROCESSORS-_
_ J DRAWERS
_. __,,_ .DISPENSER
H03,,1..
(PANEL 800) 7
I
URINE
k4_
SPECIMEN RETURN j j
PROVISIONS H005
& WMCwAsTEMAINTENANCE
EOUIPMENT 7
URINE BAG SQUEEZER
PROCESSOR URINE SA_;PLE BAG
,_ _ CRIMPER CUTTER
CHAFABER(6) _ .---
WASTE PROCESSOR "" / _ VOLUME MEASURING
_[_J.,_ -_ PLATE (STOWED)
CONTROL PANEL (8)_ "_ _ _" |/'-" _ FECAL/URINE COLLECTION
, 1 11 MOOULE
_ WMC H2O DISPENSER
(BEHIND DOOR)
SQUEEZERBAO
_URINE DISPOSALBAGS
26
VACUUM
ouiAe
._ r'ALIAGOI_I=E_ER AREA
i' _ L,,
VENT STORAGE
INTERFACE LOCKER
COLLECTIONMOOULE
MOTOR gAG
CONTROL STOWAGE
FILTER
PROCESSOR COLLECTOR
CHAMBERS
OUMP VALVE
(6 REQ'D)
,ECTRICAL
INTERFACE
VACUUM VALVE
SJLMPLE
URINE
URINE
FREEZER
/, :ONTINGENCY)
TANK
*5AM._E Id_'_ MEASUREMEWT
OiVlCi - GFE
AIRFLOW
VALVE
3
I' i' , i I
/ _ v _ URINE
/ DRAWER
DRAWERFRONTAND TOP
L _CALIURIP_ COLLECTOR I1_fP ) PLCS!
27
i i
RFLOWHOLES
___AI y FECALIURINE
COLLECTOR
HINGED FECAL MESH FECAL
,_,=CA,
COL,'C,OR,_XP,OD':DV,_
FECAL
XIP_lll_;_l_/
/_ tY__ __ iiJiiiFF
i':' I_/
28
104
105
101. BAG
102. FLANGE
103. OUTER SEAL
104. INNER SEAL
105. FINGER COT
106. VENT
107. FILTER
108. VENT SEAL
109. SECONDARY SEAL
110. DATA TAG
29
during the first mission and were discarded and replaced with new
bags. It was recommendedby one crewmanthat the fecal bag should be
deeper. Whenexpelling a normal bolus, it touched the bottom of
the fecal bag and, therefore, pushed back on the anus. Whenit broke
free, it started rubbing around on the cheeks creating a messy situa-
tion. If the bag would be three to five-inches longer, this would
have decreased the mess and cleanup time. There were no fecal bags
damagedduring use and no filter or seal leaks. A consumable summary
for fecal bags for all missions is included in the Stowage-Consumable
Summaryportion of this report.
There was no difficulty in wiping; however, the articulating
mirror was always used. All crewmenused approximately two wipes
each, which they placed in the bag, and then used a wet washcloth for
final cleaning which was then deposited in the urine disposal bag.
Controls and wipes were readily accessible, which was most benefical
in terms of system operation and effectiveness.
The WMC odor control system was rated outstanding as odors did
not persist.
There were two contingency fecal collections which occurred
prior to WMC activation. The use of the paste-on contingency fecal
bag was reported to be a messy and undesirable operation requiring
excessive cleanup. It was also a _time consuming task requiring
approximately one hour. No bag damage, leakage or waste management
interface difficulties during subsequent processing were reported.
The excessive time required to perform the "management tasks" associated
with the fecal collection process, such as bag change-out, mass measure-
ment, logging of data, processing, etc., were recognized by the crewmen
as not inherent in the design of the system, but the result of the
M071/M073 experiment requirements.
2. Urine Collection
30
URINE BAG
BOX RESTRAINT
UCTA]
SAMPLE 4,
8AG I"zi
HOSE AOAPTOR
ADAPTOR [_ UCTA]URINE
(FEMALE DO)COLLECTION URINE
FEMALE- I'1
FEMALE ODtcJ
FEMALE OD MATES ._
URINE MALE OD
WITH SAMPLE BAG --'_ I1_, %
SAMPLEBAG
"I._ f
I ":'";L'. ..........................
_.,... ¢*,.., cu.,.
, i
1, 2 AND 3)
60"S 1 -- FRONT
guS Z - REA_
(3 PLACES(
ZYPICAL URINE
INDEX MARKS FOR INSTALLING
COLLECTION ORAWER
URINE BAG BOX ON SEPARATOR
31
, ' : ::::_::_j_:/i
_:(i.,!,:::+:ii:i/!:/ii!+L:
i:iiii_i:::
:
OOOECANE CONTAINER
Fronf Front
_10 31
Fron_
32 3:1 34 315 43 4+1 45 46
Front
41 48 49
11
[F_-- q[
/::. L i:i I_ _ _ _.J
:. _: _ -.i_ ¸
TOP VIEW
/ • It/2 SAMPLE ONLY|
151
, • • +
i:!i!_iii:_i_!_
_:_i SPACER .
i_::i: :i¸I:_:_
i
i i.
UR,NE
RECEIVER
_'? _EMALE--_
CARD.OARD
GREEN
_ENT,'A.
O_--___ 0_
ALIGNMENT MARK
_CE_-__ "_-UTscv_F
¸¸¸¸1:¸
< __ I\ \ 1I II _-URINE BAG
_r I---I GREEN
VENT
CAP
ANDCARDBOARO
"_r"_,!ll
' J SPACER ARE TETHERED TOGETHER _
AND ARE DISCARDED PRIOR TO t
' r
INSTALLATION IN URINE BAG BOX _.,_.J
APOLLO 17
/--- TUBE CRIMPED.
MALE QD--_ / CUT AND STOWED
OVERRUBBERTu . , / / FORFREEZING
_ , "'_'_.J r-- FULL URINE
S'MPLERAG
-- -J URIBE
CUFF ADAPTER
IB_u"!"E
BI II
L,_
L_
URINE E_ URINE
_ BAG
SEPARATOR--_,,,,.,.,,,..._.
_ f
• _ PRESSURE PLATE
TO FECAL
COLLECTOR COOLANT
FILTER AND
AIRFLOW HEAT SINK. T/M PNL 616 OUT
BLOWER UMIT
VALVE PLATE METER
33
Each crewman had a separate urine collection system contained in
one of three drawers mounted in the fecal/urine collector. A 120 ml -
130 ml sample was drawn from each crewman's daily "pooled" urine
collection using the following procedure. The urine bag was attached
to the front of the upper fecal/urine collector door and a sample
bag connected to the urine bag with an interconnecting hose attached
to the sample bag. The sample bag was then placed in a crimper/cutter
mechanism and filled by applying pressure to the urine bag with
squeezer handles. The interconnecting hose was then cut and crimped
with the crimper/cutter. The urine sample was then frozen in the
urine freezer and maintained below a maximum specified temperature
until returned to earth for bio-medical analysis.
Expendable equipment, used to collect and sample urine, included:
urine collection bags, sample bags, receivers, urine collection UCTA/
sample bag adaptors, UCTA/urine collection hose adaptors, hoses and
roll-on cuffs. Table 5 lists the total equipment launched, excluding
additional resupply items, which are included in the Stowage-Consumable
Summary section.
34
HAS__S
SA_ LF,,BAGS
i ¸ _
FULL BAGS: 3 }._N X I_0 DAYS - L20 - 9 (ACTIVATION) - 90 (BLOOD _) _ 5k SPARES - 375
i¸¸¸¸
¸
HALF HAGS: 3 _-_ X 2 ACTIVATION _ALF SA/4_LES X 3 MISSIOR8 - 18
RECEIVERS
< i
I{OSES
_/.0SE
3 r_ X 6 EVA ÷ 1 SPARE - 19 ADAPTERS
the proper fit of the UCTA cups and excessive air in the UCTAs.
The samples were taken per procedure, but air remained in the samples
also. The crew estimated that UCTA samples contained approximately
70-percent air. This was later confirmed by the sample volumes
measured post-flight. Different techniques were employed to reduce
this problem, but a recommended method of reducing air in the sample
bag was not provided. There were no difficulties encountered regard-
ing the method used to squeeze urine samples from the UCTA.
During the first mission, low airflow in the urine receivers was
reported during inital urine collection. This was corrected by
installing a fecal bag in the fecal receptacle, thereby providing the
necessary pressure drop required to balance the airflow between the
fecal and urine collection subsystems for normal operation. Later
in the first mission, with low airflow in Urine Drawer No. 3, the
separator was changed and satisfactory airflow returned. There was
no visible blockage of the urine filter and the centrifuge had no urine
in it when it was changed. This same separator was reported to have
been "cruddy" with a grey substance in the motor to separator gear
areas during deactivation motor and separator replacement. The gear
area was subsequently wiped off before the motor was installed on the
new separator. Only one urine drawer had a tendency to stick while
closing, being difficult to close the last inch of travel. The crewman
35
i _¸_k_r
'_ ••, :
was reluctant to slam the drawer and thereafter applied a force
i_ •
slowly which adequately closed the door. It was reported once, that
two separators were "o_' simultaneously and the resulting current did
not open the circuit breaker. Operation of the urine collector during
the second mission was normal through mission day 59, when, on
deactivation of Urine Drawer No. 3 it was found that the suction line
had debonded and floated away from the suction line. The seal was
captured, taped to the collector face, and photographed. Examination
of the returned photograph pin-pointed the failure and a repair kit
was fabricated for the third mission crew to remedy the problem.
Figure 32 illustrates the problem and the repair technique used by
the third crew successfully. During the latter part of the third
mission, the crew reported that urine crystals began forming over all
separators at the juncture between the two halves of the separator.
The crystals were removed but reformed. It appeared to be the result
of a very gradual time-constant process that was progressive over the
entire mission. This phenomenon was observed occurring on all separa-
tors but did not seriously impair urine collection activities.
There was no major spillage or breakage of urine or sample bags,
although an occasional minor leaked was noted and a few bags broke
during the third mission. The loose urine was readily cleaned up and
created no serious problem. Additional urine droplets were cleaned
up as required at the boot interface to the urine separator. Occasion-
ally, the urine hoses were pinched when caught behind the separator
motor. This was corrected by insuring that the urine hose was not in
a position to become pinched prior to closing the drawer. The crews
changed hoses and receivers on a regular basis, varying from one week
to two weeks. No difficulty was experienced installing a new urine
bag in the urine bag box and on the separator. During the third
mission, in order to conserve the limited supply, the crew started
using urine bags for more than one day due to the extended mission
duration. The urine drawers were considered to be in an inaccessible
area and difficult to properly inspect because the lighting was
inadequate. The connectors were all hidden well back inside the
drawers; however, one crewman stated that he learned to mate and unmate
the connectors by feel during training. One grounding strap on the
urine drawer kept separating frequently, even during normal removal
and reinstallation.
The no_ e level of the separators was not disturbing during use;
however, when used during sleep periods, the sleeping crewmen were on
occasions, awakened by the separator noise. This was mainly attributed
to the relatively low noise levels in the spacecraft which made any
other noises seem loud and disturbing and should be a consideration
in future designs.
The condensation in the urine drawer chillers was minimal and
confined to the chiller plates. This condensation was wiped daily as
a part of bag change-out. The average temperature for the three
chillers for the duration of the mission was 45°F. Early in the missian,
36
URINECOLLECTION
DRAWER
NO. 3
LAUNCH CONDITION
SEALS BONDED TO SUCTION LINE
FLANGE BECAME DEBONDED
"_' I / I I /
REPAIR TECHNIQUE
STAINLESS STEEL COLLET INSERTS INTO
EXISTING SUCTION LINE WITH PROVISIONS
TO SEAL DRAWER MOUNTED VALVE BODY
37
the tray. Removal of all the cardboard spacers from the return
container still did not provide sufficient space for the trays. In
further conversations, the crewman indicated he felt he could force
•!i(i _ the trays into the container adequately. Several of the samples were
decapitated, but it was felt that since they would remain frozen they
would not loose their integrity.
The daily urine volume (mechanical versus LiCI analysis) for
each crewman during the first and second mission is plotted in Figures
33 and 34 respectively. The daily urine sample size for each crew-
ii
T man during the first and second mission is plotted in Figures 35 and
36 respectively. Daily urine volume and sample size data was not
available for the third mission crewmen. The urine volumes for each
of the crewmen as determined by the analysis for lithium concentra-
tion in the returned samples are provided by Tables 6, 7 and 8. Post
mission analyses revealed that the sample volumes were lower than the
planned 120 ml and urine sampling data had a minor learning curve at
the start of each mission for each crewman.
The urine bags were evacuated through the urine dump system, prior
to the daily installation in the urine drawers to void the bags of
air. During urine bag evacuation, one inlet check valve "squealed",
indicating air passing through the check valve. The bag was disposed
and subsequently the general practice by the crew was to use the
inlet boot plug. During the third mission, urine bag "swelling" was
encountered while cycling the trash airlock and the three full urine
bags were dumped into the waste tank through the urine dump system.
On several occasions during urine dump, the crew had difficulties
with undissolved boric acid tablets in the urine bags. On another
occasion the urine dump system became clogged, but was later unplugged.
There was no report of leakage, spillage, or contamination in the dump
compartment resulting from use of the urine dump system.
There was a lack of provisions for securing items, during the
sampling and urine bag changing process, which contributed to ineffi-
cient urine system management and loose items frequently floating
within and out of the WMC.
A way to wipe off the penis after urination is need for future
design iterations. It was felt there could be a slight airflow at a
certain point on the lid of the collection cup that would blow the
urine into the cup, thus eliminating all the hassle. Also, because
of the low airflow, when a crewman urinated an additional volume,
the centrifuge stopped up, thus causing backflow.
As in fecal collection, the amount of time required for the
various management tasks associated with urine collection, i.e.,
sampling, measuring, bag replacement, etc., must be reduced in the
future.
3. Waste Processor
38
z_el
I...........
-- I
VOLUUEON o_err
u V(XUUE
ANALV._S AT
i I ,-_ r-, "1
r_ I r'l I-I i
,
I 'L. • II i _ I I . -'_
i I i i I
,ee_
o_ri_l L i L I i j I i i , i i_j
2
_ KI_R_TN
. .. . r'_ r_ '
I r,_ I _% _- ,_ ' _ Pr_ I
i I i | i i !
I I t lJ N_ I
M_IION O_Y
Figure 33. Daily Urine Volume (Mechanical vs. Li Analysis) - First Mission
._r
; r]
1 I
t_
r_ _ _ E}_ _ _n j._'l_
,_,.I _ _ "_:" _a •
.,, r-j , F" U - -- u _ ,
III I I : I I I I I I I I I I I | I I I
Figure 34. Daily Urine Volume (Mechanical vs. Li Analysis) l Second Mission
39
JL
I-----:'.,.'T;
:_ I------
_.i'
_llllllllll[ll|
//._i
:.LILJ_LLLJ--L-I l "I
U_tON OAY
I
............
V---
o I I l l I I I I i I I I I I I I I I I I I 1 1 I I I l I I
:2 ,
....6 e Io
,_,:,;,;_;;'_o_'_.;66"'6'_: ;,;._,;o;,_'_.;0;._+_',.;o6.
+" -/
i. I // I
$/
'I I I I l I I I I I ] I I I I I I I I I I I I l I I I f I l
_,_ I I I 1 I I I I I I l • I i i l , I i I i I l l I I i I I I
OAYS O_ YtA_
_tOm OAYII
40
DOY MD CD8 "SPT PLT
41
CDR SPT PLT
42
I ;_ _ CDR SPT PIT
43
MIGBION U_INE VOL_4E
MISSION URINE VOLUME
DAY MECRANICAL- ml
DAY MECI!AtIICAI,-ml
SI,-h CDR SPT PLT ,
SL-h CDR , SPT [ PLT
44
Each sealed fecal bag was placed in one of the top four chambers
i_i
_i/ (I thru 4) in the processor after determining the mass on a Specimen
Mass Measuring Device (SMMD). The system was designed for heat applica-
tion to the bag at a nominal temperature of 105°F to decrease the
!
4. Urine Freezer
45
r.--OOOA HANOL! . WENT VALVI_ _A_4DLI
/ "rl
, _i_"-:.i_&8:-_
-'- If
DPIN-
C_8 <.:!_e.:: Ii
....
Figure 37. Fecal Processor
46
Some ice formed around the doors during the second mission which
necessitated removal by scraping; however, it was not reported to
have reoccurred during the third mission.
5. Suit Drying
47
DOME LOCKED 0424
FILTER ASSEMBLY JLE
\
\ ]LD
ASSEMBLY
GAS CONNECTOR
WATER RING
FOOT
POWER
HANGER
STRAP
PGAFOOT
RESTRAINT
48
C. Personal Hygiene Provisions
i. Handwasher
49
CLOTH DRYING
WATER
TISSUE/WIPE DISPENSER
F TIS_UEN_PE
CLOTH DISPERSER
TOOTH BRUSH
STOWAGE
PERSONAL
HYGIENE
EQUIPMENT
SHOWER
,--.HANDWASHER
-- SQUEEZER
F _--- HANORAIL
HANDWASHER _ [ ["_-_"_-7_-
PLUNGER
.OTWATER'/")
: '
Figure 41. WMC Water Module WMC HzO DISPENSER VALVE CUTAWAY
5O
recommended that a double seal be installed on the piston to prevent
leakage and improve the water transfer interface between the cylinder
and the squeezer bag. They also recommended that the system be
enlarged to accept towels. The crews stated that the technique of
placing the washcloth in the squeezer was important to a successful
operation cycle, and that a good vacuum in the squeezer bag was also
a requirement.
During the second mission, the squeezer malfunctioned because
of a bad Bal seal, causing water leakage. The seal was replaced, thus
correcting the problem. To eliminate this problem in future designs,
the crew recommended the use of a double seal.
There were five each squeezer water collection bags and filters
launched in the OWS. This provided a usage rate of one squeezer bag
and filter per mission, plus two spare squeezer bags and filters.
Installation of the squeezer bag was no problem. The crew would
dump the squeezer bag approximately every three days when it was
about 2/3 full, and recommended that the dump cycle be automatic.
Fifty-five soap bars were provided for the three missions, giving
a usage rate of i barman2 weeks and 5 bars/month for housekeeping
and cleaning tasks. This, for example, provided eleven bars for the
first mission; however, the crew reported that they used only one
bar for the entire mission.
2. Shower
51
_Of_-WS----'-,
DISCONNECT-_
f DI SCONNECT
WATER%.
'__i_i
_,, _I4-,N.MAN.
VALVE-_
o .VALV
RELIEFVA_
WATERBOTrLE-J
'
-- SUCT
HEAD
"Z_/
""
_
MOTOR
PRESSURE
EQUALIZATION
I
PRESS. GAUGE- SHOWER
SEPARATOR
POWERMODULE _/
Figure 42. Shower Centrifugal Schematic
52
procedure too time consuming, in the future, the shower system should
be hard-lined to minimize crew imvolvement. This includes both
water dispensing and collecting procedures.
There were some minor complaints concerning the Miranol soap;
specifically, the soap odor and feel, after showering, were considered
undesirable.
All crews agreed that six-pounds of water, per shower, was
adequate.
3. Hygiene Equipment
i!
a. Design Description
53
, _STEEL INSERT
--_ _SOAP MODULE (55 BARSI
J_ VELCRO-LINED STRAP
54
WASHCLOTH MODULE (3)
(28 WAS HCLOTHS/MODULE)
SPRING FEED
(INTEGRAL TO MODULE)
WASHCLOTH -_
TYP ICAL
TOWEL HOLDER
I
I
55
(4) Hygiene Kits - One personal hygiene kit was
provided in each of three lockers (H830, H832, H834) in the WMC for
the first mission. Locker $935, in the Sleep Compartment, contained
6 personal hygiene kits for the second and third mission crewmen
plus a hygiene resupply kit for all missions. The personal hygiene
kits contained equipment for shaving, skin care, dental care, hair
grooming, nail care, and body deodorizing.
The hygiene kit had velcro attached to interface with mating
velcro provided in various locations. The hygiene kit configuration
is illustrated by Figure 47.
56
_'_,-- _ _ _ IENE
, Li_ _
SHAVING CREAM E OZ
PERSONAL HYGIENE KIT 1 RAZOR I
LOCATIONS:
H830
H832
H834
STYPIC PENCIL
TOOTHPASTE
TOOTHBRUSH
1
30Z
1
.... 'I_|
_ MIHRO_ MIRROR
SLEEP COMPARTMENT
TYPICAL MIRROR INSTL '
3 PLACES
WMC VIEW LOOKING TOWARD
SLEEP COMPARTMENT WALL
57
iiii The drying station provided a convenient and effective means
i__ of drying the towels and washcloths. The only problem reported was
that the towels had a tendency to float away from the wall into the
work areas if they were restrained at a single point (one corner).
•_ /i !
The third crew felt the restraints were too crowded. There was no
report of having used the portable towel holders. The restraint
approach should be standard equipment on future missions for towel
and washcloth drying as well as a general fabric restraint.
The crews stated that a more "personalized" hygiene kit would
have been more useful. There were too many items included that they
hadn't previously used and other items that would have been desirable
but were not included. Because of the double flap design, the hygiene
kits were hard to get into. The crews suggested that the individual
kit items should be restrained in an open area for easier accessibil-
iI _
ity.
Because of the elevated temperatures in the OWS prior to initial
crew occupation, the first crew's inspection of stowage locker $935
revealed that certain items in the resupply kit and the personal
hygiene kits for the second and third missions were damaged. The
Alpha Keri hand cream containers and toothpaste tubes had ruptured.
The shaving cream containers were intact, but the cream was unuseable
because it had hardened. The damaged items were discarded and
resupplied on SL-3.
The only crew comment pertaining to the mirrors was that they
were too dull. The articulating mirror, used for hygienic cleansing
after fecal collection, was considered necessary and extremely useful.
58
ii! _ D. Sleep Provisions
i. Sleep Restraints
59
#.'S' ,
,, :',_r ¸
TRIANGLESHOES_ _,
I,-- _ - _-_S'_!_"_, _
L,_ I- I- I,. I- _,- I ",t _i ,_ _ _ /• _li--.'__
_,_'ll
_;i
"_f'Jl_..-_-i _-I
_ _1_
_ ct'i i I
_t_1
il:'l' II
,9,_,-,-!-:_ _" I ( t I ll_l P
7
"i,.L£_'::_ I ', t _IiI,41
_-__] r_ i ! ! IIiT
III ,
%,t,_l, ,"
CONTAINER
_ i ll_/,. ; .J+
! \ I llIlT.-_-'ql
_ l'l_._____.;il'
II I _--SLEEe
_,'i _
_ _\ SLEEP RESTRAINT
<, _ _ _ EQUIPMENT
AmO,FFUSER
J
L PRIVACY CURTAIN _ AIR OIFFU$ER$
i i
RESTRAINT FRAMEAND
THERMALBACK
6O
i
i _
61
restraint. Twelve large body straps and 24 small body straps were
stowed to provide a change of body straps every 28 days. One large
and two small body straps were required for each sleep restraint.
b. Post Mission Assessment- There were no significant
anomalies reported relative to the sleep restraint equipment.
In general_ the crewmenfelt the sleep restraint equipment was
ii: quite satisfactory. Specific commentsrelative to potential improve-
ment and equipment use is summarizedas follows:
2. Privacy Curtains
62
Sleep Compartment passageway, as shown in Figure 49.
The curtain also served as a barrier to block light from sources
in the crew quarters. These privacy curtains were not designed to
block or reduce sound from entering the sleep areas=
Each curtain was held in position with velcro, which mated to
velcro on the lockers and walls. This feature was simple to operate
and provided for breakaway emergency egress from the sleeping area.
3. Lisht Baffles
63
tl i i i
X FAC,NGCR__ N
SNAP
A.ACH,,ENT"'.."%."_-."O-._'_--.
F r2 "-_ SNAP A_rACHMENT TO
? LO'J;AR.,ENT
-----/ _"_'_-o_ -/ SNAPS
.YP,
I CREW QUARTERS _APS "_\_'_ --_L--'LIGHT.BAFFLE
LOUVE'S
TYPICAl, lIGHT BAFFLE SECTION (BLACK ARMALON INTERIOR)
LIGHT BAFFLE 2
64
E. Food Management System
I. Food Galley/Pantry
65
FOOD STORAGE
FOOD FREEZERS
(3)-'_f_ _Jr_E"_ _/CONTAINERS (11)
ON-ORBIT
UTENSIL
RESTRAINT
i!i:
.........
FREEZER ii _
i
-:i!
__ -..--. ,w77z)
-'-_'--_- ON-ORBIT
UTENSIL
: RESTRAINT
fijiiiiiiiiii!;ii
/
_"'_ _'-_- FOOD SUPPLEMENT
STORAGE
66
/--- FOOD TRAY LID STOWAGE (3)
PUDDING TRAY (1)
GALLEY r I
: FOOD CANS
I}
I_qL_
_'- _ _0VERCAN
CODE RED. J
WHITE, OR BLUE) "ml
LARGE AND SMALL FOOD CAN
MAGNETS IN TRA
67
from the containers. This, along with a non-daily menu tray pantry
layout, would minimize food handling requirements, while affording
better accessibility to individual pantry items. Associated with
the food galley/pantry system was the food can disposal system. The
crews criticized this system as being too small to operate effective-
i _
ly and, due to its design intricacies, too difficult to keep clean.
i_I_
:i
All surfaces of the system, including the six lid openings and lids
themselves, became soiled easily and remained that way constantly
because of the continuous contact with used food cans.
The crews also had the following minor criticisms of the
stowage provisions for their individual eating utensils: (i) the
utensils were hard to reach from tile eating stations; (2) the utensil
compartments did not restrain the utensils adequately; and (3) the
compartments were difficult to clean.
68
i rl i
tl
I
I II
I
I II I
41
i ii
• VOLUME SELECTOR--_
69
i_ •
VOLUME
SELECTOR POSITION
INDICATOR
70
LAUNCH
RESTRAI NT
'L / :
.... i
._ ;I '-"-'Y
.... ___._E._'
LEG
_ PI STON
SPRINGS _ IIIIII11
iii II lilt H
VA LVE_
-,,,_ DISPENSE PORT
71
!i i:i ¸
i •_
VELCRO FOR
BARE FOOTED,
STOCKING
FOOTED& IV
SOFT BOOTS "
Figure 62. Food Table Restraints
i
72
Figure 64. Table and Food Tray Launch Configuration
73
¸I¸¸i
¸
74
Six food containers were attached to the Forward Compartment
floor during launch, shown in Figure 67. The first crew then
unbolted and transferred all six food containers to their on-orbit
or use location as illustrated by Figure 68. The five remaining
containers were launched in the container support structure. The
container support structure was designed for easy crew accessibility,
located just in-board of the electrical cabinet adjacent to tile
refrigeration pumping unit_ illustrated by Figure 69.
As the food supplies within the food containers, Figures 70 thru
73, were depleted and the canister restraints discarded_ the empty
food containers assumedtheir second design function. Trash and
transfer items (such as PCUcontainer, CO2 absorbent shims_ etc.)
were removed from the CMand placed in these empty food containers.
As additional food containers becameavailable during all missions_
they were used for this samepurpose.
b. Post Mission Assessment- It is assumedthat the food
containers performed as designed during launch_ transfer_ and instal-
lation into the support structure. The crew reported the flanges on
the edge of the containers were used as holding devices during trans-
fer and installation in the food container stowage rack. The food
containers were amongthe largest items the crews were required to
transfer and relocate on-orbit. Reports from the crews indicated
this was accomplished easily.
4. Food Freezers and Chillers
75
/--STANDARD LOCKER
FOOD
FREEZERS
,, /COMPARTMENTS
FOOD STOWAGE
CONTAINERS
(LAUNCH AND
ON ORBIT)
III
FOOD STOWAGE
CONTAINERS
(LAUI_!CH
ONLY) TYP
IIv
Figure 67. Food Stowage Containers - Launch Configuration
FOODSTOWAGE
CONTAINERS(I1)
III
FOOD
FRE
REFRIGERATION
SUB SYSTEM LOCKER
PUMP PACKAGE
(B COMPARTMENTS)
/IV
Figure 68. Food Stowage Containers - On-Orbit Configuration
76
,i_i/_.i
_:._
ELECTR
ICAL CABINET
/
I_1
FOO_INER
STORAGE
FOODFREEZERS
_
RACK
PUMP PACKAGE
_'_ REFRIGERATION
77
Figure 71. Ambient Food Storage Concept
---CORRUGATED
FI BERBOARD
LOAD SPREADER
78
SCREW CLOSURE LID-_
i¸ •
kll
15. SEAL-'
5 _ EMRALON /_
X COATING--/_
,,
'---. 030 THICK
DRAWN ALUMINUM BODY
_--4. 38-----
CH,LL,,I -- ..--oOO,
L.,cH _/:X/&_ _ _---$---;_
IRIIZIRI RO0_I \_
_ _ I_0 COWrT
I ' ' I _f_l I_ L ii,I( l_i',_, TRIGGER LAD.CH .e tOCATIOR
ADD,2
_R G_xET
m. liI'II _ _P'- -
ILARGE FO0O CARS IN LARGE OVERCAIS |St_0TTEO F0R VEDTIII) I_ I I IL/._ 1 --
• _1 OAY SUPP_.Y FROZEN FOOD CACR • CHILLI FOOD AND lEVERAGES PRIOR TO
• U '4 -II'F
79
was poor (approximately 60% to 70%), even though the freezers were
relatively small; (2) loose food items in the freezers should have
been restrained in some manner; and (3) ice built up in between the
freezer and canister doors, reducing freezer accessibility and
requiring the crews to develop and perform an unscheduled maintenance
/ procedure. The door ice buildup was a progressive event, requiring
the crew to use such implements as a pinch bar or screwdriver to
remove the ice when it impaired freezer access. The crews felt that
significantly more food could have been stored in the freezers had
a different packaging system been used.
80
F. Housekeeping
81
L
i
mmtam¢
CnmTAU_ R m _.Ot
e t5 V4 • Litre*6)
:N ', " ,,
C_1_15 mttl[itm
• _'_ UP C_AmtW(tT
GENERAL PURPOSE
TRASH BAG LOCATION S
• FWO COMPARTMENT
eWARDROOM
eWASTE MANAGEMENT COMPARTMENT
• SLEEP COMPARTMENT
(WASTE TANK)
PLENUM
STOWAGE
BAG WASTE TA_
SCREENS _J
82
The following paragraphs discuss problems and improvements
i¸ associated with the trash collection provisions:
83
of which 62 were used. The third crew used 162 trash bags. The
quantity of trash bags used (246) was less than that allocated
(366). The provisioning for future programs should consider these
actual usage rates.
Onehundred and sixty-eight (168) disposal bags were launched.
Thirty-three (33) disposal bags were allocated for the first mission,
but 48 were used. The second crew used 54 of 68 allocated disposal
bags. The third crew ran out of disposal bags on MD 25, having
used the remaining 66 disposal bags.
Onehundred and forty-nine (149) urine disposal bags were
launched. The first crew used 40 urine disposal bags. Thirty-seven
(37) additional bags were launched in the second CMand a total of
98 urine disposal bags were used during the second mission. Eight-
een (18) additional urine disposal bags were launched in the third
CM. The third crew used 85 urine disposal bags.
Of the 28 plenum bags on board, 5-3/4 were filled by the first
crew. By the end of the second mission, a total of 9 plenum bags
were filled and stowed in the plenum area. The third crew used 13
plenum bags.
2. Vacuum Cleaner
84
/ ¸• /_
! ii̧ •
3. Microbial Control
85
' 5,•
'rr•.
b. Post Mission Assessment - The crews generally used the
microbial control equipment as planned. However_ they developed
some interesting variations. A rag bag was established in the
Crew Quarters near the MI31 experiment for stowage of not too dirty
used clothing and towels. These articles were used for major clean-
up jobs, such as wiping urine spills. They also found that there
was considerable cleaning capability left in the wet wipes after the
first use. After cleaning up their eating utensils and tray, the
wet wipe was used to clean the wardroom area.
In general_ the wipes worked as planned. Crew comments relative
to potential microbiological contamination sources were quite
%
consistant among the three crews and can be summarized as follows:
86
S' %
spills. The rupture of a urine bag in the trash airlock proved to
be a major source of odor. Repeated treatment with the biocide
failed to remove the odor from this area. It was believed that the
biocide did work on the accessible portion of the trash airlock.
However, urine may have passed under the lower lip of the TAL and
became entrapped, causing a foul aroma. The solution to this prob-
lem would appear to be a redesign of the TAL. Similar design prob-
lems were noted when cleaning the spills in the urine separator
compartments. The crews complained of poor accessibility while
i'¸ _i
cleaning spills. Poor lighting in the WMC made inspection and cleaning
of the urine drawers inadequate. Smooth surfaces within the drawer
i i __ would have made cleaning easier. There was no way to completely
clean the urine drawer.
87
G. Trash Disposal
jt
88
SPLIT DIAPHRAGM
(ELASTI C)
SHIELD (TEFLON)
(DISPOSE IN BAG)
IMINUM FOIL
DIAPHRAGM SEALER
EXTENDED
REMOVETEFLONCOVER &
(Average) Closed
/
._e: 13.56 Dia. x 17 In.
_ROLL 3 TI MES
FLAP AND INTEGRAL STAYS
SNAP SHUT (4) PLACES
89
• , .! ,
/!
REMOVETEFLONCOVER &
TFOLD OVER FLAP
FLAP _ AIRLOCKINTERFACE
,_PIN TABS (3PLACES)
' _1
_/ , . tIsi,_:n._,6 Pi,,._
(A'''''') 17 I,,.
c'°''
EIECTOR HANDIE
TRASH AIRLOCK
HATCH INBOARD HATCH
EJECTOR
RESSURE GAGE
0-i5 PSIA
_ECTOR MECH
(EXTENDER)
VALVE/OUTBOARD
HATCH HANDLE
EJECT POSITION JTBOARD HATCH (OPEN)
PRESSURIZATION
/
VACUUM LINE /
SHUTOFF VALVE---
9O
i
LOADING/EQUALIZE PRESSURE
TH.OUO.'?._T
M,_,ONI---_
WA_E TANK
ou,,..o,o.osE, WA_E TANK
a. First Mission
91
crew should not attempt to dispose of the urine separators through the
TAL, but should stow them in the empty T027 Sample Array stowage
container. This container was then evacuated to inhibit possible
bacteria growth.
b. Second Mission
92
Although improvement did not seem likely with a seal changeout,
• J
the crew was advised that if they wanted to "shop around" through
the spare seals and choose the one they considered best, this was
acceptable. The crew elected to leave the TAL "as-is".
c. Third Mission
• i _
93
two urine bags per disposal bag or large items with protrusions.
These precautions reduced the possibility of jamming. The later
mission crews continued to use some form of restraint to maintain
the valve/outer door control handle in the "CLOSE/VENT" or "PRESS"
position when the TAL was not in use. No items were reported to have
been cycled through the TAL without being placed in some type of bag.
The crews expressed on several occasions their dependence on the TAL
!// / and their concern about the situation that would result from a
permanent malfunction. They also, occasionally, criticized the amount
of time needed for trash disposal and termed the operation a "nuisance."
There was 2233-cubic feet of accessible volume in the waste tank
for the ejected trash items. This volume was consumed by biologically
active trash and can be expressed as a packing factor (volume avail-
able/volume used). Table 9 summarizes the full extended volume of
the various trash collection bags in determining the volumes and
packing factors for the waste tank. The trash bags were maintained
at approximately their extended volume by the sublimation of the ice
resulting from a moisture in their contents.
The first packing factor listed would be achieved at the end of
the last mission if all available trash bags were put through the
TAL. The second packing factor is for the waste tank at the end of
the first mission; and the third packing factor is at the end of the
second mission. The fourth packing factor denotes the completion
of the third mission.
Additional biological passive trash was collected in the plenum
bags (4.5 cubic feet each). A total of 28 plenum bags (Figure 83)
were launched; 13 (a total of 58.5 cubic feet) were used during
the entire mission; however, only nine of these (40.5 cubic feet) are
known to have been stowed in the Plenum Area.
94
/ IL ¸ } iliiiiii!ii!ii!i
ii!¸
VOLUME OF TOTAL TRASH BAGS TRASH BAGS USED TRASH BAGS USED TRASH BAGS USED
ITEM ITEM FT. 3 AVAILABLE FIRST MISSION SECOND MISSION THIRD MISSION
Disposal 168
1.41076 237 48 67.73 54 76.18 66 93 .ii
Bag
Urine
Disposal 1.02909 204 190 40 40.84 98 100.85 66 87.47
Bag
Vacuum
Cleaner 0.01236 140 5 0.06 i0 0.12 I0 0.12
Bag
kn
Mi sc. I 0.59 m
!
826 116 123.06 224 244.36 304 356.31
Total Per Mission I 878
Running Total for Missions 878 826 116 123.06 340 367.42 644 723.73
I
Packing Factor = Volume Available
2.70 18.15 6.08 3.09
Volume Used
NOTE: The waste tank original (launch) usable volume was 2233 cubic feet.
OWS. Air was circulated from a plenum chamber, under the crew quart-
ers area, through diffusers, to a mixing chamber located in the dome
area and was returned to the plenum area by fans clustered in three
return air ducts. This configuration provided open area air velocity
ranging from 0.i0 to 0.23 meters/see (20 to 45 feet per minute) and
a screen velocity of 1.48 meters/see (283 ft./min.). The open grid
construction of the OWS floor allowed adequate air and debris passage.
• i• This velocity was sufficient to move all debris and loose parts to
the four 60-mesh screens in the dome area mixing chamber. Circulated
airflow_ similar to the OWS, was used in the other modules for debris
collection. Passive debris control was accomplished by use of various
types of closeouts. The flexible mesh, secured by velcro, in the
MDA was one type. See Figures 84 and 85 for other examples.
The vacuum cleaner was designed to pick up the accumulated debris
from the screens and was scheduled periodically for that use. The
vacuum cleaner was also used to collect spilled liquids even though
the liquid systems (water, urine collection, personal hygiene and
food) were designed to minimize such occurrences.
96
I
FILM
L
UV
/ i PANORA/_IA
:i
FREEZER
HANDHELD
MANEUVERING
UNI CAL
CLOSE-OUTS
HORIZONTAL
CL FOOD
LOCKERS
STOWAGELOCKER
O.020 ALUMINUM
MOUNTING STRIP
BOTTOMOF LOCKER
NUT PLAE
0.062THICK
FLUORO-
CARBON
RUBBER
WMC FLOOR--_
97
I. Hatches
2. MDA Hatches
98
PI.ACiSI
*z
CSM SIDE S
CSM SIDE
REMOVECAPPRIORTOVALVEOPERATION
Figure 87. MDA Hatch
99
. . .*: .., : ?
An additional contingency mode was provided on the axial hatch
by a tool box (MI04) that contained tools for forcing or dismantling
the hatch in case of opening mechanism failure.
valve was removed. This design presented no problems for the Skylab
mission, but a recent analyses of docking an unmanned module to
either MDA docking port brought to light that the use of the pressure
equalization valve, to equalize pressure between the two modules, was
inhibited because the screw-on cap would prevent pressure equaliza-
tion. In that case, pressure equalization would have to be accomp-
lished by removing a bolt that penetrated the pressure hatch. The
requirement to equalize pressure from the MDA side would have been
a contingency mode of operation and somewhat unlikely. However, the
screw on cap as a redundancy provision on hatch equalization valves
should be reconsidered when designing hatches for future spacecraft.
The redundant system should be in the valve itself rather than an
add-on device, that renders the valve inoperable when it is installed.
3. AM Hatches
a. Design Description
i00
# ' ,i __ HANDLE "11+
i_ _ •
i'
(3 pAz4[.S)
(2
WINDOW SHIEL©
SHIELD
PRESSURE
L'PRESSURE I
I EQUALIZATION
VA|VE 311 EQUALIZATION 'v
VALVE 325 e'w
+y
\ HANDLE FIBERGLASS
FIXED HANDLE
\ COVER
ROD ASSY'-'_
:LOSED &
INTERNAL HANDLE
LOCKED
OPEN "-'-
\
LOCKIRG
_!ECHANIS/A
VELCRO_ )OW
VENT VALVE
)OW COVER
TIE-DOWN
HARNESS
LATCH-IZ REQD
HINGE
GEMINI CREWHATCH
INNER WINDOWASSY
(2 PANES)
Figure 89. EVA Hatch
I01
this hatch provided were: (a) the handle lockout, and (b) the
hatch retainer. The handle lockout prevented the latching dogs from
being closed when the hatch is in an open position, thereby precluding
sill damage which might occur due to closing the hatch in that
configuration. The hatch retainer caught the hatch in a partially
open position as it was being opened, thus preventing differential
pressure loads from popping the hatch open if the lock compartment
was not completely vented.
A double pane window in the hatch enabled viewing of the aft
portion of the EVA bay. The space between the panes could be vented
with the window vent control.
102
J. Crew Stations
(I) ATM C&D Crew Station - The ATM C&D crew station
consisted of the ATM C&D panel, foot restraint platform, chair, and
Speaker Intercom Assembly (SIA). The ATM C&D console was originally
designed for seated operation and installation in the Lunar Module
for AAP. Although changes were made in the panel for Skylab, its
basic size and shape remained unchanged. Early in the program, the
crewmen elected to operate the ATM C&D panel from a standing position
on the premise that: (a) two crewmen may be required at the ATM C&D,
and (b) the STS control and display panel would require monitoring
while the crewmen were physically oriented at the ATM C&D panel. At
the time Skylab was being readied at KSC, the Skylab Restraint
Assembly (Chair) was installed, at the request of the crew, to provide
additional restraint while operating the ATM C&D panel.
(2) EREP C&D Crew Station - The EREP C&D crew station
consisted of the C&D panel, the S190 camera array, the S190 stowage
container, a SIA, and the M512/479/EREP foot restraint. The major
i03
Foot Restraint Platform C&D
-CO 2 Absorber Container
ATM C&O Foot 5192 Multtband Electronics
ATH
Umbilical
-Z
_-Vent Panel
Thermostat
Recorder
Restraint Platfom
(Alternative Position For M512)
Container
Panel
+Y
+Z
Ducking Tunnel
Control
i, System Flextble Duct
Assembly
• /
Secondary Oxygen Tenk_
Temperature
,erature Thermostat
-Z
M47g Contafner-_
Camera V
(Position 2)
Single Crystal Growth
+Z
Fllm Sun-End
Exothermtc Expertment-_
Cassette Tree
STS M|scellaneous
Stowage Container
Atmosphere
Duct
Proton
Outlet
Car*era (Position 1)
5194 L-Band
Film Vault 2
_-.Cable Trays
_-Com_ostte Casting
Area Fen |
104
crew interface, with MDAhardware, was the foot restraint. The
original foot restraint concept for the EREPC&Dconsole was a grid
platform, serving both the EREPC&Dpanel and the VTS. Functions on
the C&D panel were not fully developed and quite limited; therefore,
it was decided to remove the EREP C&D panel foot restraint, but leave
the VTS foot restraint. This concept was later reversed thereby
removing it from the VTS and placing the foot restraint back at the
EREP C&D panel. The rationale was that handholds mounted on the VTS
panel would adequately position the crewman and give him the freedom
to quickly move away from the station and back again. The crew
believed this would be easier to do if they did not have to disengage
their feet from the foot restraint grid. The EREP C&D foot restraint
was combined with the M512/479 crew station foot restraint by provid-
ing the capability to mount the grid in either position.
105
The crews performance proved that man can function effectively,
in a cylindrical spacecraft module, in a zero-g environment and
hardware orientation. However, there existed a longer period of
i¸ !
adaptation to working the cylindrical layout of the MDA than in the
floor to ceiling orientation of the OWS. All Skylab crews expressed
a feeling of disorientation when arriving in the MDA, until they
found a familiar piece of experiment hardward to key on. Most crew-
men found that they used the ATM O&D panel or the EREP experiment
hardware to orient themselves in the MDA. It also took the crewmen
longer to locate a particular stowage container in the MDA than in
the OWS, where the stowage containers were installed in a floor to
ceiling arrangement. This suggested that, in future spacecraft, it
7 would be more efficient to lay out experiment and stowage hardware
in a one--g orientation, even in small cylindrical vehicles like the
MDA'. At the very least, the early design ooncept for small cylindri-
cal vehicles should provide for functional grouping of hardware.
Stowage containers should be grouped in a common direction and area
like the OWS experiment compartment stowage containers, or circumfer-
entially in a particular location like the OWS ring lockers.
Each crew considered the volume of the MDA sufficient for working
and hanging onto things, but expressed problems with traffic, when two
crewmen were working in the MDA and a third crewman tried to get past.
The MDA volume was suitable for its designated functions as a multiple
docking adapter for a larger space station and experiments/stowage
module. The volume ideally should be increased for a similar type
module used as a single space station experiments module for a crew
of three.
Comments relative to the ATM C&D crew station were generally
favorable except for the incompatibility of a crewman working at the
ATM C&D panel while another crewman was working at the STS control
and display panels. The layout of the ATM controls and displays is
discussed in the Controls and Displays section. Foot restraint
platform and chair assessment data is contained in the Mobility/
Stability Aids section. Generally, however, reach envelopes were
considered to be less restricted using the foot restraint platform.
The ATM C&D integral panel lighting emitted a pleasant effect when the
MDA floodlights were off; however_ this was not necessary. When the
floodlights were turned on, the ATM C&D edge lighting effect disap-
peared and when the ATM C&D lights were used along, the checklists
could not be read. There was a general degradation in the bright-
ness of the ATM C&D counter lights with usage.
Comments concerning the EREP C&D crew station were favorable.
The crews saved setup time at the EREP C&D by leaving the communica-
tion cables and eommuniaation carrier (soft caps) connected to the
SIA.
A significant deficiency of the EREP VTS crew station was the
lack of a crewmen foot restraint. It is necessary to have a foot
restrain t at all crew stations requiring the crewman to operate
106
controls and manipulate charts/checklists for long durations. The
only annoying problem associated with this crew station was with the
clipboard mounted on the EREP experiment S191 eloseout cable cover.
The clipboard, attached to the cable cover by two snaps, was used to
hold checklists, maps, photographs or target sites, etc. and unsnapped
several times when used by the crewman.
The crew operated at the M512/479 Material Processing Facility
,ii
crew station as planned and reported no major problems. Temporary
stowage of a PGA near the crewman's head caused minor infringement
of work envelope.
2. AM Crew Station
107
• IL
Cabin Heat
Exchanger
AN Data Ftle Partial Pressure Module
Module
(Opposite Side Sensor ,Module (Spare)
of Console)
Ventilation Ducts
Supply Duct to MDA
.y" Molecular +y
Permament
STS Control--_ Stowage Container
Panel Cover Sieve _ver_
\
E_ Fan &
IVA Station
Manua)
Forward Con_artment L-M201 Teleprinter Recorder
Stowage
Paper Stowage Module
Container M301 Forward
Panel Lights
Compartment Stowage
r._
Container Film Tree
C_
Support
CO Film Tree
Support ECS Duct Cabin Pressure
(303) Relief Valve
t (4) (51
2o,-w Hatch
Tmlnel M30S
Compartment Stowage (311)
/
Duct Container
LOck Compartment EVA Panel 1
Instrument
Panel
Vent Plate
Assen_oly
LSU Stowage
(M326)(Stowed)
/
performed. The groupings were also planned such that each module had
at least one side exposed to an access space for entrance into the
interior of a module through a removable cover. Additional access
was provided through hinged doors on the front of the equipment, such
as the doors on the mol sieve covers through which the replacement of
solids traps and/or mol sieve fans was accomplished. Handrails and
handrail lights were installed at strategic locations as a protection
and aid for the crew during translations. A handrail type lamp which
provided a 360 ° , non-glare light source was used. A sufficient but
minimal number of units were utilized to provide an adequate illumin-
ation level for the required inflight operations to be performed.
Placement and arrangement of the lamps provided an even and consistent
lighting level throughout the compartment, including the recessed
areas between the equipment quadrants. As a safety precaution, it
was not considered desirable to bring the unprotected, raw power lines
into the vehicles interior where they would be exposed to an oxygen-
rich atmosphere. To preclude this, the circuit breaker panels were
designed to penetrate the AM pressure wall. Using this method, the
cables from the primary power source were left on the outside of the
spacecraft and the lines on the inside were protected by circuit
breakers. The Forward Compartment served as an extension of the STS
and contained equipment ancillary to that crew station purposes.
The operational units in the Forward Compartment were the AM tape
recorder module and the klaxon for the Caution and Warning System;
the other two units were stowage containers with IFM spares. No
control panels or lights were present in this compartment. The
klaxon was located behind the opened AM forward internal hatch. This
location was selected so that the hatch would act as an audio baffle
for this siren and provide aural protection for a crewman should he
be nearby when it was energized.
109
restraint of the LSU connectors and were temporarily stored in the
aft compartment for EVA. No internal volume was consumedfor this
function and no physical obstructions were created by it.
ii0
accommodate the equipment and crew, yet small enough to provide
adequate body restraint. The functional usage arrangement of the
equipment in the lock compartment was well designed. The ease with
which the LSUs were removed from and returned to stowage was partic-
ularly noticed.
The operations of the hatch mechanisms and repressurization valves
were very smooth. During crew translations, the internal hatch sills
were "knee bumpers" if the trajectory was not perfect. The sill
visible from the airlock, the opening from the STS, and the forward
side of the forward hatch had not been protected.
iii
i i|
FO_ARO
FO_ARO \ \COMPARTMENT
_ COMPARTMENT _i _ -Z
__ QUARTERS
/"%,""_llt I1_ "Y
HABITATION
AREA
FORWAR°
COMPARTMENT
_l_T_
FLOOR_\ _ _ r /
EXPERIMENT _ %. I /
-F-
I '10101
CEILING COM PAR T-MENT J__._/_
/ -SLEEP
i (:¸ i ¸¸ ' CREW
__ +Z COMPARTMENT
QUAR TER £ CREW QUARTERS
/L .
• I .... (VIEW LOOKING AFT)
PLENUM AREA
FLIGHT DATA F LE
"_L__'E_NT_R___IOONDAGEMENT_
1_,_ V,EV_/
._:._- LOOKING
b-IJTBOARD
TABLE
"_ G_/_LLE_!
.,q...,_"%_. ,__ ..L'--IIJ_ JLJ_I r;_-q I_'1 I I STOWAGE J_/____J L_JL_.JJ ENTRANCE
_'_T_ _XI III '_,1 I ILJ LJ L4 CABINETJ | ,, ..... _f..7 CURTAIN $....1
O_TBOAR_
II_' _ I1__ I _11 '_°_'_--
QUARTERS
i12
VIEW LOOKING TOWARD WARDROOM WALL
_:..
i:̧¸
WARDROOM FWMC cSLEMEPAR
TM ENT"_ _r
? AL ..;-_...._..._
-- __j._l CORNER ___.,.J-_.-
/j/ STOWAGE WMC_r J II
GENERAL LI_
i ILLUMINATION _] IJ
I 1 L
I_WMC CEILING
HOLDING I I-_'- [)lr-_F _t_]7,
L DRYING
LOCKER
COMPARTMENT
• El III ' STOWAGE
HANDRAIL
LOCKER
AREA
(_ERSONAL
.YG'ENE
--TELEPHONE BOOTH COLLECTOR"_,IE __ _._:_---
II ,TEMS_
HANDWASHER
STYLE DOOR
L,_" FIX ED LIGHT
(ENTRANCE)
II DUTYFOOT
MOOULE
PROCESSOR _ _
RESTRAINTS
II _SLEEP
URINE J#'_"-- __.J.... /i " ]_r COMPARTMENT
FREEZER_'_ _ - _ LL- WALL
ENTRANCE
INBOARD
_ CORNER STOWAGE
/ CABINET
INTERCOM STATION
m r_,,o
_ _"--SLEEP
/(TYP 3 PLCS)
SLEEP
COMPARTMENT
_COMPARTMENT CORRIDOR_ _'_ _ _ _, _FLOOR
_;_ _ /EGRESS
,_ OPENING
QUARTERS
;_ " _ GENERAL
(TYP 3 PLCS)
PRIVACY , "_x '
TOWAGE LOCKERS
113
CEILING
EGRESS
REMOTE CONTROL _-OPENING PORTABLE
WARDROOM AND WMC _ RESTRAINTS
LIGHTING PANEL _ TEMPORARY
; FIRE
630 ._I_. _ _ FIRE
STOWAGE
--ELECTRICAL
INITIAL CONTROL
CONSOLE EXTINGUISHER_ EXTINGUISHER
ENTRY AND -- EXPERIMENT
EMERGENCY _ COMPARTMENT
/--GENERAL ILLUMINATION
LIGHT
(TYP 4 PLCS)---1 I LIGHT FIXTURE (TYP14 PLCS) '
/
:L _ __ STOWAGE LOCKER ,
i,_, _ _ .
0 L-:";: .. L
i / i
III
114
crew station contained the urine/fecal collection equipment, a H20
dispenser for washing, a washcloth squeezer, stowage lockers for wash-
cloths, towels, wipes and tissues, waste processors, a urine freezer,
towel and washcloth drying provisions, and supplies necessary for
waste management including urine bags, hoses, receivers, sample bags,
fecal bags, etc. The latter items were located in lockers and dis-
pensers within the WMC with resupplies located throughout the OWS.
Figure 96 illustrates the general arrangement and layout of the WMC.
115
crewmen to use the triangle shoe for restraint. The 250-pound food
boxes were relocated from their floor launch position to their on-orbit
/L ,
116
The wardroom window developed an ice problem between the two
layers of glass. A special procedure was developed which evacuated
this inner chamber of the window. The procedure had to be repeated
periodically (every 7 to I0 days) by all crews in order to remove the
ice that formed from the water vapor in the cabin air that slowly
backfilled the cavity.
The WMC was used for normal relief of body waste matter, drying
feces and desiccants in the waste processors, measuring urine, taking
urine samples, storing urine samples in the freezer, personal hygiene
i/'_ •
tasks_ and body washing needs. The WMC was acceptable in size, layout,
J
and function for use by one crewman at a time. However, the lack of
usable foot restraints (grid for triangle shoes) was a problem and the
absence of separation between the waste management and personal hygiene
facilities was somewhat objectionable. The spills and housekeeping
problems anticipated in the WMC did not materialize; therefore, the
floor could have been grid, compatible with foot restraints.
The sleep areas were used for sleep periods or off-duty resting,
as desired. There was a need for more personal stowage and temporary
restraints in the sleep areas. Noise, ventilation, and personal comfort
preferences (lights, music, etc.) were disturbing to the other sleeping
crewmen. Noise sources, in varying degrees, such as the power module
on the WMC fecal/urine collector and the ATM C&D cooling pumps in the
STS, occasionally disturbed sleep periods when in operation. One
crewman reversed his sleep restraint in order to increase the ventil-
ation about his head. In doing so, the SIA was out of reach when he
was in the sleep restraint, and also required him to install a portable
light on the floor for reading. One crew hung moist towels in the
Sleep Compartment to achieve their desired comfort preference.
The Experiment Compartment was used extensively to perform medical
experiments, physical training on the ergometer, trash disposal,
taking showers, and systems monitoring activities. The compartment
was somewhat crowded, but the layout and arrangement was satisfactory.
The "vertical" or l-g orientation made the many experiment operations
seem more like the l-g trainer. The congestion around the shower was
due to the fact that the shower was an experiment added late in the
program. The noise of the ergometer hindered communication and could
be heard on the SIA's and recorded channels.
Access to the plenum for stowage of the "plenum bags" was very
satisfactory.
The open floor grid on both floors (Forward compartment and
crew quarters) provided for crewman foot restraint, attach points for
temporary tethering, handholds, and unaided communication between
compartments. The main floor beams and intercostals were so close
to the grid that the triangle shoes were not usable in some areas.
The grid could have been slightly larger for easier hand accessibility
for debris removal.
117
K. Mobility-Stability Aids
I. Design Description
a. Fixed Aids
118
ATM C&O CONSOLE
HANDRAIL
FILM VAULT
HANDHOLDS
HANDRAIL
TYPI_ _Vl
M§I Z,/M,479 HANDHOLD _ f- HAN DWA.SHER H-ANDHOLO
/HANDRAIL --
INTERIOR AND _,,,,L
EXTERIOR _
HATCH HANGHOLOS " .,_,_
(TYP Z DOCKING AND 3 / I
BULKHEAD HATCH ES)--._ \.
HANDHOLO--_ /
0OCKING PORT /
SEGMENTED HANDRAIL_
HANORAIL
i (TYP 2 PORTSI --/
_,__.._ HANOHOLO -J I
_,___ L_. FIREMANS POLE
_'_UTTON) _,:_
ADJUSTABLE
VELCO AT'r ACHE:
119
ENTS
(HANDOPERATED,
FRICTIONJOINT)
THIGH
ADJUSTMENT
(HANDOPERATE
for use with the triangle shoes. They were designed to assist the
crewmen in restraining and maintaining body orientation for applying
any necessary forces, with both hands free, while accessing equipment
in the dome ring lockers. These restraints were located in the for-
ward compartment immediately below the water stowage tanks.
120
i_
I_:
i
/ LOWERLEGRESTRAINTS
121
0 435 INCH
0'444 INCH DIA. IIOLEAT EACH INTERSECTION
, 'i _
_N . r',', . . . v
._.:_L_.___.l.___.jr_. _r_L--__-.
t "" " '-' "
0 0 0 0 )0
122
FECAL/URINE
,, !
COLLECTOR
,i L/
<
SIDE
HAND HOLDS
fl '
VELCO A'I_ACHES
123
i
i _
1j
Ii II
l
Figure 108. ATM Foot Restraint
I
b. Portable Aids
124
:i
<
PORTABLE HANDHOLD
ADJUSTABLE TETHER
125
(2) Portable Handholds - Six portable handholds were
provided to enable the crewmento install handhold restraints, as
required_ in areas where open grid was available. These items are
shown in Figure ii0.
126
TI
TR I ANGL_
127
In future spacecraft design, particular attention should be
given to specific locations along a translation paths where directional
changes or tunnel entry will be required. A buffer of soft material
should be provided to protect the lower body extremities.
Some problems and design considerations for handling and translat-
ing large cargo or experiment items defined by the crew are as follows:
• The food box was a reasonable size container (approximately
20" X 22" X 30"/200 pounds) to translate and not considered
too large for one man to maneuver in zero-g.
• Large items should be easily grasped to allow guidance during
iii_ i translation.
• Long and thin items are easy to handle if one can see the
/
end of the item being maneuvered.
• Very large or heavy items can be maneuvered if the crewman
is adequately restrained.
A detailed description of crew usage and assessment of specific
mobility/stability items follows.
a. Fixed Aids
128
these devices similarly. The strap was too short to be used with
triangle shoes; the strap was too long for use without triangle shoes;
and it kept getting caught in the urine drawers.
129
(7) Grid - The floor and ceiling grid was used by all
three crews, as anticipated, for mobility and restraint. All crews
commented favorably on the usefulness of the grid. The two most
common complaints were: (i) the lack of more grid and, (2) the
blockage of the grid by either the installed equipment or the support-
•7
ing structure. Besides its use in conjunction with the portable res-
traints, the grid itself was continually used as a handhold or foot-
hold. The WMC restraint evaluation always referred to the lack of
grid. The second crew suggested, during the debriefing, that grid
should have been provided in the WMC.
One minor deficiency associated with the grid was the problem
of particle migration, such as food crumbs and spills. The grid was
difficult to clean because of the small holes, sharp corners, etc.
130
restricted their reach envelope, therefore, used it very little.
The SL-3 and SL-4 crews did not recommend a seatbackrest to be part
of future consoles. For those crewmen who used the ATM seatbackrest
assembly for additional restraint, the freedom of motion and reach
envelope was restricted. The reach envelope at the ATM C&D crew
station, while using the chair, included the entire ATM C&D panel,
SIA, TV selector switch on the left, and the very nearest checklists
and the checklist compartment. By loosening the chair lap belt, the
Video Tape Recorder (VTR), all the checklists, and the radio noise
burst monitor were within easy reach.
/! ii _
b. Portable Aids
131
during most of their missions. The tether was broken (date unknown)
during the first mission, but was repaired with tape from the repair
kit. The adjustable tether was assessed to be minimally adequate
during all missions. It was judged to be unnecessary and not required,
except possibly during the early portions of the mission.
132
PER FORMANCE
i_'i_iii, >_
c_
O
o_
oc_
H F.r..1
F-4
FIXED RESTRAINTS
_ ,i_ _
Fireman's Pole X
/
Skylab Restraint Assembly X
PORTABLE AIDS
Portable Handholds X
Adjustable Thethers X
Triangle Shoes X
133
L. Stowage
i. Containers
134
izi *i_
r s_4 & F$_4-Fg4_
FO(_ SCx[$ QU
/i _
MT m W?I_F_R&WTS$
ST_ Cf_ll _ W FIt_
LOCKERS
FOOD
STOWAGE
CONTAINERS
FOOD FREEZERS
STANDARD
STOWAGE
LOCKERS
135
/
!}•:
: } :
PA_T_T
m _'_FT 1
F-FRICTION
HINGIE
-- DOOR
\
_._n __
FT3 _ITQWA_ C(_PA,_Tt,_NTS
_.,,_ _ COM pA RTh'_rJCf
136
2. Internal Arrangement
3. Equipment Restraints
137
The First Mission crew reported the 400-foot film cassette res-
traints in OWSfilm vault drawer B kept moving to the rear of drawer.
The restraining tab was _pparently not locking the film cassette in
place in the drawer. These restraints existed in other film vault
drawers and worked satisfactorily.
The second crew found camera equipment loose in one of the OWS
film vault drawers. The stowage requirements had not been anticipated
prior to SL-I launch and therefore restraints had not been provided.
In someinstances, mosite restraints allowed small items to
float free. The pudding can restraints in the food galley allowed the
cans to float out. This restraint was categorized as inadequate.
There were no anomalies reported for MDAor AMstowage hardware.
No malfunction of stowed_uipment was reported as a direct result
of the launch environment. All stowage containers, stowage positions,
and restraints were used as anticipated.
The crew recommendedmore temporary stowage facilities throughout
the vehicle. The straps, used extensively in the OWS,were somewhat
difficult to use because they were stiff and rough, and in somecases,
inside stowage containers, the buckles woundup in hard-to-reach places
when the locker was partially empty.
The crewmencormnentedthat there should have been more on-orbit
stowage facilities near use locations. An example is a more permanent
stowage capability for photographic equipment near the Wardroomwindow.
One concept of stowage that the crews disliked was bags in bags
and a little cubical for numerous individual items (e.g., the flash-
light stowage). One point to be made is that launch padding is not
needed for on-orbit stowage.
4. Fasteners
138
CREW
CONSENSUS DESCRIPTION
8.83 Masnetic Latch
RANK MEANRATE FASTENER
COMMENT
:
SKYLAB USE :
ATM VC Film Access Doors
in-orbit.
COMMENT :
SKYLAB USE:
OWS Ring Locker Doors.
139
CREW CONSENSUS DESCRIPTION
3 8.50 Handle and Trigser Latch
RANK MEAN RATE FASTENER
COMMENT :
\
SKYLAB USE :
Food freezer and refrigerator
doors.
•/
COMMENT:
• k
SKYLAB USE:
OWS Crew Compartment Locker
doors.
Table ii. Skylab Fastener Evaluation-2 of i0
140
CREW
CONSENSUS DESCRIPTION
5 7.00 ,Pip Pip, ,,
RANK MEANRATE FASTENER
COMMENT
:
SKYLAB USE:
Multiple usage, but mainly
as a launch lock.
COMMENT :
SKYLAB USE:
Various equipment storage box
lids.
Table ii. Skylab Fastener Evaluation-3 of i0
i
141
CREW CONSENSUS DESCRIPTION
7 6.00 Rifle Bolt Latch
m
COMMENT :
SKYLAB USE:
S082A & B Film Tree and SI90A
Covers.
m
COMMENT :
SKYLAB USE:
MDA Flight Data File, C02
Absorber box, and Miscellaneous
Stowage Container.
Table ii. Skylab Fastener Evaluation-4 of i0
142
CREW CONSENSUS DESCRIPTION
9 5.40 Thumb Screw and Do S Latch
RANK MEAN RATE FASTENER
i_¸_
COMMENT :
SKYLAB USE :
COMMENT :
i°,
SKYLAB USE:
Portable fan cover and T027
storage box lid.
Table ii. Skylab Fastener Evaluation-5 of i0
|
143
CREWCONSENSUS DESCRIPTION
ii 5.20 _Springed Slot Screw
RANK MEANRATE FASTENER
COMMENT
:
SKYLABUSE:
OWSForward Compartment
PLV fan and fan connector access
covers.
CREWCONSENSUS DESCRIPTION
12 5.00 KnobHandle Screw
RANK MEANRATE FASTENER
COMMENT
:
SKYLABUSE:
OWSForward Compartment,
PLV Fan Cluster launch lock.
Table ii. Skylab Fastener Evaluation-6 of i0
144
CREW
CONSENSUS DESCRIPTION
13 4.75 Locking Screw Latch (Calfax)
RANK MEANRATE FASTENER
COMMENT
:
SKYLAB USE:
OWS intercom box installations
and extensively throughout the
airlock as panel and cover
fasteners.
COMMENT :
SKYLAB USE:
Restrain equipment in storage
lockers.
Table ii. Skylab Fastener Evaluation-7 of i0
145
i
SKYLAB USE:
OWS tripod leg lock and MDA
film vault door lock.
CREW CONSENSUS DESCRIPTION
16 3.67 Astro Pin
RANK MEAN RATE FASTENER
COMMENT :
146
CREW CONSENSUS DESCRIPTION
17 3.50 Twist Strap & Hook Latch
//_•_i
•I
RA_ MEAN RATE FASTENER (Dialatch)
COMMENT :
SKYLAB USE :
OWS Portable Lights
COMMENT:
SKYI_B USE :
OWS Water Hose Retention
Table ii. Skylab Fastener Evaluation-9 of i0
147
• j _
CREW CONSENSUS DESCRIPTION
19 2.00 Push Button Latch
RANK MEAN RATE FASTENER
COMMENT •
\.!
SKYLAB USE :
Food Tray lid to tray
fastener.
Table Ii. Sk_lab Fastener Evaluation-10 of i0
b. Post Mission Assessment - Most of the different types
of fasteners onboard were used extensively by one or more crewmen
from each manned mission.
Some of the lift handle latches (used on OWS standard lockers)
were broken as previously mentioned.
Several of the locking screw latch (Calfax) captive retainers
were broken.
The push button latch (used on food tray lid) slipped all the
way through the latching hole in the mating surface several times
and required prying with pointed tools from underneath. Also, when
latched, it did not give a positive latch _nd was accidently
released when bumped.
In addition to the fasteners in Table II, two latches were
provided outside the vehicle on the film access doors of Apollo
Telescope Mount (ATM) for use during Extravehicular Activity (EVA).
The center work station (VC) access door latch, Figure 115, functioned
adequately but was criticized by the crewmen because its operation
(push-to-open 2 pull-to-close) was opposite of that normally expected.
It is
noted, also, that a separate lock was required for launch.
The Sun End Workstation door latching mechanism, Figure 116,
combined launch restraint and orbital operation in the same mechanism.
Its orbital operation as a door lock was excellent. It also served
as a handhold when in the locked position.
148
J
149
The crew's subjective evaluation of the Skylab fasteners is
shown in Table 12. Fasteners are ranked according to mean ratings.
Comments accompanying the completed rating forms indicated that some
ii ,
crewmen used a given fastener more than other crewmen. Ratings
turned in by crewmen who used the fastener frequently were weighted
more heavily than the ratings by crewmen who seldom used the device.
Weighted ratings are indicated by an asterisk. In cases where mean
ratings for two fasteners were identical, the higher rank was assigned
to the fastener with the lower standard deviation, since that would
indicate a greater agreement among the crewmen.
Table 13 reflects the ranking of all nineteen fasteners as a
single group. However, the rating process also involved evaluation
i!!i
_i of each of these for its specifically assigned function(s). For
example, magnetic latches were not directly comparable with threaded
fasteners because each served a different function; certain fasteners
required reinforcement to withstand launch loads, and some did not;
some fasteners were frequently used, some were not. Accordingly,
the fasteners were divided into three categories within which they
were ranked. The results are shown in Table 13.
All nineteen fasteners were rated by each of the six Skylab
crewmen on a subjective I-I0 scale. It is recognized that unique
design requirements will often dictate special fastening techniques,
some of which perhaps received low scores on this evaluation.
However, it is useful to note that the two factors which appear to
account for most of the differences in ratings are:
(i) Design and operational simplicity.
(2) Sensitivity to minor misalignment between mating parts.
The most positively rated fasteners are those of simple_ straight-
forward design and those which can tolerate minor changes in align-
ment. Conversely the most consistent criticism of poorly - rated
fasteners is their alignment criticality. Stringent alignment is
difficult to maintain through launch or with repeated use, and manual
alignment is an additional demand on crew effort.
The magnetic latch, which received the most favorable rating, is
not suitable for launch and return restraint. A useful combination
might be a magnetic latch coupled with a separate launchreturn
positive restraint which could be maintained open during orbit.
In several cases, minor design modifications might have resulted
in significantly higher fastener ratings. For example, the chief
criticism of "suitcase" type latches was that_ after release, it
tended to "flop" and sometimes re-engage. Built-in friction at the
hinge point might eliminate this objection.
Several other criticisms concerned fastener application rather
than faults with fasteners per-se. For example, alignment-critical
fasteners might be acceptable for use on substantially rigid mating
pieces but not on relatively flexible sheet metal covers.
,i
151
b. Post Mission Assessment - The placards and labels were
used as planned with no anomalies reported.
;J L The second mission crew dated the plenum bags to provide ident-
ification for retrieval of an item, if requested.
Confusion was experienced by the first crew with the TAL'. The
stowage location nun_er for the TAL was E699 and the procedure referred
to it by this number. However, that number did not appear on the TAL.
The operational procedure decal for the TAL was designated 634. There
was a distinction between "Panel" numbers and "Stowage Location"
numbers. In most instances, these numbers defined different physical
locations within the vehicle. In this case, the two numbers identified
the same location_ but had two different applications.
Location of labels on the tool kits prevented easy reading and
was a complaint of the crew. A more logical numbering system in the
OWS forward compartment would have been helpful (i.e., separate series
of numbers for OWS forward compartment wall and OWS forward compart-
ment floor). Time was wasted while searching for stowage locations
which were not identified as being on floor or wall.
In areas where many small components with similar names or shapes
are utilized, there should be a picture or sketch for each item at
their use location. An example of this is the OWS Water System.
6. Transfer Stowage
152
k
Urine
149 109 40 28
Olsposal Bags
GP Tissues 11 Boxes
g Boxes 2 Boxes 2.2 Boxes
@ 392 • 4312
*Plenum Bags 28 22 6
Urine
432 360 75 3/Day 84 3 Urine Bags
Collection Bags carried on SL-2 CM
Vacuum Cleaner
140 135 5 24
Bags
* 6 Plenum Bags are in the Plenum Ares (5 full and 1-3/4 full).
U_ne
375 312 63 66
Sample Bags
Contingency
Fecal Bags 185 184 A/R
- k
k • .
Urine
149 48 98 59 138 87 37 Urine Disposal
Disposal Bags
Bags were
resupplted on SL-3.
UttlityWtpes 23 Boxes
@ 196 = 4508 14.8 B_e_ 6.7 Boxes 9.2 Boxes 8.2 Boxes 13.8 Boxes
GP Tissues 11 Boxes
LJl @ 392 = 4312 3,6 Boxes 5.4 Boxes 4.4 Boxes 7.4 Boxes 6.6 Boxes
L_
Wet Wipes 7 Boxes 4.6 Boxes )1.8 Boxes 2.8 Boxes 2.4 Boxes 4.2 Boxes
Urine
Collection 432 185 178 3/Day 168 253 252, 3 Urine Bags
Bags Carried on
SL-3 CM
Fecal Bags 465 282 135 168 183 252
Vacuum Cleaner
140 .125 10 ** 48 15 72
Bags
Urine
375 204 108 132 171 lg8
Sample Bags
Trash Bags 366 120 162 146 246 366 37 Urine Dlsposa
Bags were
Disposal Bags 168 0 66 68 168 168 resupplied on
SL-3.
Urine
Disposal 149 66 5g "204 146 18 Urine Disposal
Bags Bags were
resupplted on
SL-4.
Utlltty Wlpes 23 Boxes .3 Boxes 14.5 Boxes 9.2 Boxes 22.7 Boxes 23.0 Boxes
@ 196 = 4508
GP Tissues 11 Boxes 3 Boxes .6Boxes 4.4 Boxes 8.0 Boxes 11.0 Boxes
&.n @ 392 = 4312
B|oclde Wipes 5 BoXes 2.0 Boxes .1 Boxes 2 Boxes 3.0 Boxes ' 5 Boxes
@ 70 = 350
Wet Wipes 7 Boxes 4.0 Boxes .6 Boxes 2.8 Boxes 3.0 Boxes 7.0 Boxes
Urine Collec-
432 0 185 3/Day 168 438 420
tion Bags
Vacuum Cleaner
140 I15 10 _ 48 25 120
Bags
**Estimated
r
On-Board at On-Board at Quantity Used Quantity Quantity Used iQuantity
SL-I Launch End of Third Third Mission Expected First. Second. Expected Usage
Item Mission Usage - and Third First, Second. Remarks
Third Missions and Third
l . .
Mission _MlSSlOnS
Towel s 420 142 188 168 " 308 420 30 Towels were
resupplied on
SL-4.
a. Design Description
159
Ill) -Z VIIW LOOKING AFT WARDROOM IIIII -Z
_._6 I_ /'-'- UPP[R LIGHTS _ _ _
b
!i'_'_
_i
3 S ,* (I -Y
2 1 §
(, oz _---ourr, CO_,';T_,'_;;TS---/
_ _--SL_E_'coMrr
FWO COMII'T' CREW QUARTERS LIGHTS
i_ i
___ LOCATIONS__ //
160
Center Work Station and seven twenty-watt lights at the Sun End Work
J
Station. All of the above were incandescent lights. Two of the STS
lights and one lock compartment light were utilized as emergency
• i_i_
_
lighting and would have been activated upon failure of both AM busses.
The two STS emergency lights were Instrument Panel Flood Lights
Number 8 and Number I0. The lock compartment emergency light was
Number 4.
General illumination requirements were to equal or exceed 5 ft-c
L
at 3-feet from the source of illumination in all habitable areas. EVA
lighting was to provide a minimumof 2 ft-c at 3-ft from the source of
illumination along EVA routes and 5 ft-c at 3-ft from the source of
_i_ illumination on EVA work surfaces.
161
i
162
k
}
__ ._---_,,,,,
O,AL-LcARRY,NG.
,,, J ATCH
(,)_.__
/ I_'_" NN HOUSING w (COLLAPSIBLE) f e_\
/ - \ "--ZERO'G'
CONNECTOR
ZEHO'G' _ \ -J
'_'UNIVERSALMOUNT "---12 IN. PIGTAIL CONNECTOR_ _ e%,,,.o..,__._._ _---FLOOOLIGHTBULB
(SHOWN INSTALLED)
(_I/__AI NED WITHIN
(INTEGRAL TO HOUSING
• 2 SEPARATE LIGHTING SYSTEMS
FLOODLIGHT
BULB)
• 4 PERMANENTLY INSTALLED FLUORESCENT
LAMPS WITH 2 LAMPS/SYSTEM • 1 REPLACEABLE
FLOODLIGHT
BULB
• INTEGRAL SWITCH CONTROL HIGH-MODE 75 W • INTEGRALLIGHTSWITCHCONTROL
HI.IZ.§W
AND LOW-MOOE 40 W PER SYSTEM AND LOW-10.O
W
• OVERTEMPERATURE PROTECTION PROVIDED (SYS 2) • 3 STOWED ":
• 2 STOWED • POWERED
FROMANY UTILITYOUTLET "
• "POWERED FROM ANY HI-PWR ACCESSORY OUTLET • LAUNCHED
WITHA FLOODLIGHTBULBINSTALLED
163
N. Crew Communications
/
The Skylab Communication System was designed as a functional
part of the Orbital Assembly (OA) Audio System to provide; I) direct
voice link between Skylab and the Space-Flight Tracking and Data
Network (STDN) via the Command Module (CM) S-Band, 2) bio-medical
data to the STDN through the AM PCM Telemetry System, 3) audio and
visual displays of warning tones generated by the Caution and Warning
System, 4) control for the operation of the Voice and Data Recording
System in the AM, and 5) intercommunications between the astronauts
within the OA.
This section will be concerned with the intercommunications
link (audio system) and vocal (unaided) communications within Skylab.
/ i. Audio System
164
/
165
(2) Lightweight CrewmansCommunications Umbilical
(LCCU)and CommunicationsControl Head - The LCCUwas 15-feet long
and carried communications and caution and warning tones. It mated
to the SIA's and was used with the communications control head and
lightweight headset. The communications control head provided volume
control and transmit switch capability for the LCCU.
166
initiation caused loss of the green recording light on the SIA, poor
coordination occasionally occurred. To avert the loss of AM tape
recorder data/information, system design should prevent simultaneous
tape recorder dump and crew operation.
A malfunction of a hand-held microphone occurred. The mike was
subsequently marked with red tape and stowed. The crew considered
the microphone a desirable item and recommended that replacements be
brought up with the third crew. It was also reported, at the Crew
System Debriefing, that the second mission crew replaced the SIA at
the -Z SAL because the transmit switch had failed in the ON position.
With the exception of the acoustic feedback problems, the audio
system (crew interface portion) operated in a satisfactory manner.
Locations of SIA's within the 0WS was reported satisfactory, although
the SIA in the forward dome (401) was not used. Volume level was also
described as satisfactory.
Use of the headset did not disable the speaker in the SIA and
caused interference and annoyance with other crew activities.
Communications performance with the umbilicals was satisfactory;
however, cable stiffness tended to dislodge the lightweight headset
from the crewman's head. The major portion of communications directly
utilized the speaker intercom boxes.
167
SECTION III. CONTROLS AND DISPLAYS
A. Orbital Workshop
168
and a tool kit check performed in the High Fidelity Mockup at MSFC
and recommendations transmitted to JSC. No report of crew action
relative to this problem was reported. The second crew also reported
that this same switch was loose. The crew reported that they would
fix it, but no verification was received. This same problem also
recurred during the third mission, but no fix was attempted. The
crew decided that, during future usage, they would verify that the
rotary switch was all the way to the "A" (Stop) position, and then
count to the desired position to make certain that the switch was
i -
properly positioned.
i_ _ There were no specific adverse or critical crew comments relative
, i _ to the assessment of the OWS controls and displays. The first crew
indicated that the concept of wickets and partial recess, which was
used, was a good compromise toward switch and circuit breaker protec-
tion. The second crew commented that finger clearances between
_i_
wickets and switches/circuit breakers were adequate. The third crew
Ti • 3
made no specific comment relative to OWS controls and displays.
Therefore, it is concluded that the overall layout, arrangement,
groupings, etc. of the OWS controls and displays proved to be adequate
and acceptable for all missions.
i!
169
B. Airlock Module
:ii :i¸
i. Design Description - Control and display mechanization for
the AM was unique. All other U. S. spacecraft had been designed
exclusively for either manned or unmanned operation. The AM was
designed for both. The AM C&D panels provided the crew option of
ground control (via DCS) or onboard control of Skylab systems and
equipment. The primary control capability was thus vested onboard
during the manned phases. The crew had the option of relegating
control of various components within a given system to DCS. Equipment
and controls, unique to manned mission phases (fans, lighting, mole-
: i_
cular sieves), had conventional mechanization with only onboard
controls capability. Conversely, some functions that did not effect
manned phases, such as 2-watt transmitter selection, had only ground
%:
control capability. Controls for remotely mounted systems and equip-
ment were located on the main STS C&D panel along with displays which
/ provided operating information or feedback to the crew.
Panels and controls were numbered to facilitate communication and
documentation reference. The numbering system started with i00 series
numbers for the forward end of the vehicle (MDA) and ran to i000 series
numbers in the OWS aft areas. The AM used 200 series numbers in the
STS and 300 series numbers through the tunnel section for panel identi-
fication.
All circuit breakers for AM power were located on panels 200,
201 and 202 on AMS 157 bulkhead. The circuit breakers, as were all
other panels, were protected by bar guards which provided operating
reaction points, minimized inadvertent operations, and allowed visual
assessment of circuit breaker position. Circuit breaker arrangements
on each panel were grouped by function and system. Color coded bands
beneath the breakers denoted the bus from which e_ch breaker derived
its power. The color code was also depicted in the Bus Distribution
schematic on panel 211.
Schematic diagrams were superimposed directly on control panels,
where panel space allowed. Where a panel was insufficient or controls
seldom used, functional flow diagrams were located on adjacent areas.
/ Control positions were shown by indicator lights for momentary
switches or detents and pointers for valves and rotary switches.
Special tools needed for control operation were tethered adjacent to
the required location. Controls requiring unusual manipulation were
marked with operating instructions.
Controls and displays were located throughout the AM to provide
crew operational capability near the equipment being operated or
controlled. Thus, perceptible cues to equipment operating status,
such as fan start up or compartment venting, could be easily detected
at the control operating position.
The combination of main AM C&D panel and ECS equipment in the STS
provided a crew station arrangement where all system interactions
(cluster attitude, EPS, ECS, C&W, etc) and control responses could be
ascertained at a single control station.
170
L
Caution and Warning (C&W) contained visual annunciators and in-
hibit/enable switches for redundant sensors. C&W generated audible
alarm tones were transmitted by the AM audio system to the SIA
speakers and the low level audio systems. Emergency tones for fire
or rapid Delta-P were sounded by klaxons independent from the AM
audio system. Audio levels were adjustable by controls on panel 207.
Individual C&W sensors could be inhibited by the inhibit/enable
switches to prevent repeated false alarms by malfunctioned sensors.
These switches also allowed parameter isolation for trouble shooting
where one visual annunciator was used for multiple parameters. The
• /!i
171
_!
172
Audible alarms genersted by C&W were suitable for anticipated
orbit conditions. Alarm loudness adjustments on panel 207 were avail-
able had the interior operating noise levels in Skylab required adjust-
ment of alarm audio levels. The preset sound levels, coupled with
SIA and Klaxon locations, provided complete coverage of the orbital
cluster without causing physical hearing damage to the crews. Visual
Z
alarms and annunciators in the C&W system were adequate to initiate
proper crew reaction and provide system trouble-shooting capability.
The sensor isolation capability, made possible by the inhibit/enable
switches, eliminated false alarms from a drifting duct flow sensor
and eased EVA prep time requirements by quick isolation of tunnel
fire sensors.
For future manned spacecraft, circuit breakers, or any controls,
should be separated from paths of high crew traffic. Also, physical
operation of AM breakers is similar to toggle lever switches. Opera-
tion of these breakers requires access from two opposite sides of the
breaker. Consideration should be given to push-pull type breakers
for selected applications.
However, if a circuit breaker is to be used regularly for switch-
ing functions, the toggle type lever is superior to the push,pull
actuation.
Organization of Skylab electrical power system controls physically
separate the AM EPS from ATM CBRM controls. The C&D design of the
two electrical power systems is very different. Since both control
sets perform quite similar functions, some crew training time and
on-orbit operational time could have been saved if the systems used
a common control panel and similar or identical C&D design and
mechanization.
The lack of controls malfunction in the AM EPS indicates possible
advantages in its C&D design. Displays in the AM EPS could be improved
to enhance on-board fine adjustment of AM bus voltages by the addition
of a meter "scaling switch" that would expand meter sensitivity and
scale.
A manual backup (bypass, or control) for critical automatic con-
trol functions should be mandatory for all C&D mechanizations. This
is normal aircraft and spacecraft design practice which would have
been useful for coolant loop temperature control. A central servicing
location for both coolant loops internal to the vehicle would have
greatly reduced the effort required to generate an on-orbit reserviee
technique.
For spacecraft with long orbital lifetime, design parameters for
on-orbit repairs and servicing requirements must be included in the
mechanization and arrangement of vehicle controls and displays. An
on-orbit maintenance plan for all critical systems should be designed
into the vehicle, even with redundant systems.
Caution and Warning parameters provided in Skylab were large in
number and included some items that recent orbital operations have
shown to be unnecessary: "Duct-Flow" for the gas interchange duct
173
• i¸ _.:'_
could be replaced with fluttering strips of paper or eliminated
entirely, since stagnant gas pockets have proven to be no problem as
long as some air mass flow is available. The emergency fire warning
system differs from the rest of the C&W system. This difference
(remote sensors & control panels) required added crew training, in
locating and silencing the alarms. The audible alarms must be
silenced for good crew communication and the difference between
silencing a fire alarm and other audible alarms could cause confusian.
The memory system for "emergency" parameters should be similar to that
of other C&W parameters.
Internal lighting for AMmeters, based on Skylab experience, was
proved unnecessary. In applications such as Skylab, where the
operating crewman did not have to change visual field from outside
the vehicle to inside the vehicle (i.e., docking and station keeping
in CSM), internally lighted meters are not required.
174
C. Apollo Telescope Mount
175
I
:70_1N00 _ .--" ,_
_NIINIOd
,nNV_ i __
3SVH ooooo:
118U0
000000
: (AV7dSIQ) :NOllnel_lJ.Sla
AIIAllOV =_ _3h_Od
: 103dS AV_I-X
o o. _._) I/AVU_-- X :3 )SNO3
:31NIl-
.17S Anx
lO':ldS ^nx
3731 AV_l- X
:VHd7V-H
:SAV7dSIO
:VA':I
SOUXd
:AO7d3O
: SVO/ONnOUe
of the actual position of the switch commanded is solely dependent
on the operator's visual reference. This means that a crewman
looking straight onto the panel at some angle below eye level may be
unable to distinguish the actual position of the switch. This prob-
lem is inherent in the use of latching toggles without position talk-
backs.
POWER/ DOORS CAMERA/TELE IFLAREI F,LM I IDAT-----A-- ,--BE-EP_T POS--:v--AL APRT POS
<-REA PWR _H_ PWrl- EXPOSU_:E [] []
AUTO INCR AUTO INCR
A OfF -- oFF- L
177
READY
V MAIN .ARE fRAMES
PWFI P'vVR/DOO Q c_ _OOE WAVE LTH [X_0$UqE
ABLI REMAINING f I-I
EO#NMA L
S --ON---- AUTO _ SHORT SHOP + _TART
pl T __ • --•
EVENT TIME
XUV SF_CT
,,
V
MAIN
PWR
--ON-
PWN
[]
IDOOR_
• [] _ARE
ABL_E
FRAMES
REMAINING
U'
START
THEPMAL
ON
S
,_,I_1,_h_l
MIN "SEC L
t @
T -Of'F- _IB11 STOP I
r------ .e,L_'W _
-- UNII_ -- STOP J
TONE LIP
ENABLE
t n
with the ATM electronics power distributor located in the ATM console.
The interconnection between the ATM and the auxiliary timer involved
the making of two electrical connections. The crew was able to
perform this using connector pliers contained in the on-board tool
kit. The auxiliary timer was affixed to the top of the ATM console
and operated satisfactorily during the entire Skylab Mission. The
crew incurred no significant interface problems with the exception of
the reach distance between the two modules.
178
F-I WLC ALIGN
• i? i
II
I 'I IIQ21 AST
F
AN
LI I oo_ CLOSE
O,,e_n,Bq See,RD_ IOVEORmEI S 0 _ OFF TV XfO DISC_AN 0
WLC
PWR GRtO
ON NORMAL
jellQ.
OFF OISCH
_ RASTER/SCAN--
HV ENABLE/ RESET --
RESET
05
gRATING 175
PO6rTION ! _ OOO I0COUNTER
179
The installation of the lockout switch guards on the high
-ii_:
I:I
voltage detectors prevented any occurrence of inadvertent selection
of the override position. This design addition facilitated efficient
man/machine interface.
>
r F;L__ J_J
4AIN PWR DOOR HULT POWER
Y
OP_ CLOSE FEGET/I MANUAL STOP CTR TEST SEC
×- RAYSPECT
IMAGE
THRESHOLD
_6
PHu TUMULTIPL:ER 4 64 IMAGE
_ INTENSITY COUNT
FOCUS
BRIGH 1 NESS ._'_ -.,
180
switches, near the inner edge of the experiment borderline, and taped
i::i
¸_i_I to the toggle switch wicket guards. There was no interconnect
between the timer and the ATMswitching circuitry or the experiment.
A 28V auxiliary outlet next the the C/D panel in the MDAwas used as
a power supply.
The problems associated with the timer included the feature of
starting the timer simultaneously with the experiment. This created
the problem of the crew's being distracted by performing two opera-
tions. Another unsatisfactory feature was the color selection of the
READY/OPERATE light, which was a very bright yellow for READYand
white for OPERATE.The crews found these colors and illumination
levels quite annoying.
The X-ray scope which displays PMECX-ray activity was also too
high in intensity, and the crewmenfound it uncomfortable to look
at. They compensated for this inadequacy by placing a paper cone,
Figure 128, over the scope, allowing it to be visible only from
directly above and thereby eliminating its interference with other
C&Dactivities. This significantly improved the operator inter-
face by extending the total time an operator could remain at the
panel without becoming fatigued.
3. System Interface Evaluation
, ,-
181
O0
L
k.
¸{:i}1:4
ExP PW_ [_G
=<f_T_TT
- _,_p .......
X-RAY/RF ACTIVITY
HISTORY PLOT
ORBIT PHASE
BE
MIN [] S_
_ECORD IO'HR
II <_> II
_ECORB _O'HR
I;tEVERSE
i
183
control (toggle switch), held in the DOWN position for a predetermined
time, which stored the image on a memoscope, and, when released,
presented the image on the CRT at 1/30-sec intervals for 10-sec.
This procedure was repeated until the crewman operator had identified
the active source of solar activity. The comments of the crewmen have
validated the importance of this system in aiding data collection;
they felt strongly, however, that due to the repeated use required,
a simplified operational sequence would have helped the operation.
The ATM C&D console restraint, Figure 128, was designed and built
• •i _ because it was known that prolonged hours of operating the ATM console
would be tiring. The restraint, designed for all nine Skylab crew-
men, was based on current anthropometric data, Figure 132. The
primary users of the system were the SL-2 crew, who originated the
concept. Further information on the ATM C/D seat restraint is given
in Section II. K of this document.
184
N N
i
• . |"
O
or,,,l
<3
+
c-, I,,- o
• I \ x. +Lf-<..___._---"
I
,
<u
+
g !+
*#S)/"
I \' \,
i,=_ ...+++__--_--\
!--lu_ 4..3
O
O
i +
,--I
.g
o
18..
. +
. _+ +- + + + +, ,+
the data collection and reduction operations and the conclusions that
were drawn from analysis of the data. These data support many of the
conclusions drawn from the subjective evaluations discussed earlier
in this report section.
i
186
according to the S082A building block procedures. This
probably occurred because the S082A and B controls and
displays were almost identical and had approximately
the same control labeling nomenclature and building
block instructions. These problems could have been
prevented if the experiments had been separated on the
panel, labeled differently (S082 and S084, for instance)
and had different control labeling nomenclature. For
i_! i
the SL-3 and SL-4 missions, large red and blue decal
letters "A" and "B" were placed on the respective instru-
ments. Also, strips of red and blue tape were added to the
outside experiment boundary to aid in distinguishing one
from the other. The effectiveness of this color coding
in alleviating the confusion caused by the similar appear-
ance of the two experiments will be determined during
SL-3 and SL-4 data reduction.
• Isolated control actuations had a higher deviation rate
(21%) than control actuations that were part of a sequence
(2%). Approximately half of these could have been
prevented if an integral timer had been provided for each
experiment that had operating modes requiring manual
timing.
• The panel's left side had a higher deviation rate (6%)
than the right side (2%). This was caused primarily by
several three position toggle switches on the left side
which were used improperly 9% of the time.
• Building blocks with multiple parts (up to five) separated
by a time allocated for pointing commands had distinctly
different control deviation rates for each part. The
first and last parts had low deviation rates (3% and 7%),
and the central part had a significantly higher deviation
rate (18%) as illustrated in Figure 133. An improvement
could probably have been realized by limiting the number
of building block parts, while increasing the number of
building blocks.
187
3% 18% 7%
1 2 3 4 5
0 5 I0' 15 20 30 35 4O
,IM[
(BIN)
L
REMARKS
56
×UV
SLII
SCAN
SPECI
X-RAY
_PECI
(MIN) 5 '0 15 _ 2_ _ 35
cited by most ATM C&D engineers and crewmen when asked, "What would
you change?",is the console structure. More specifically a wrap-around
configuration that would improve crewman reach and visibility and
enhance component allocation. In conclusion, it is imaginable that
a significant number of modifications could be made to improve the
overall ATM design, but effectiveness of design preparation and
implementation is reflected in performance. Based on this criterion,
one might safely say that the design was goodp since the data actually
collected for ATM more than doubled the anticipated _esults.
188
i_:i_
:::!:I!L
:i:!:_?!i:_i
'_;:;L
i:
¸:i:
APPENDIX A
CREW DEBRIEFING
16. A useful tool would have been a lexicon or log to record signifi-
cant ATM comments to update each panel operation on the occurrences
of activities on the sun's disc.
17. The X-ray scope PMC appeared to saturate at a flare utensity of
500 counts rather than the i000 counts for which it was designed.
189
r
18. The GRATING SELECT switch was inadvertently left in the MECHANICAL
position when it should have been in the OPTICAL position.
19. The crews commented that experiment setup times improved with
repetition.
20. One crewman stated that the X-ray Be/AI History Plotter design
was ineffective for continued use because of the tendency of the
paper drive unit to hang up.
21. The RNBM was not useful in data analysis because of characteristic
J_ design in band and range sensitivity.
22. The XUV Monitor was a good correlative display for a flare.
23. The H_ display was a good tool for viewing through the building
blocks and pointing and surveying the active regions on the sun.
24. The Ha reticules worked normally.
190
. _ . ,-_""
- . - , , , , , . •
SECTION IV. COROLLARY EXPERIMENTS
191
i_ii_
• _i¸• B. Scientific Airlock System
I. Scientific Airlock
192
r
j
.... • ! : • ! •i_• _ii I
\ /
VACUUM FITTING
VACUUM HOSE
_ECHANISM COVER _Y
VALVE COVER _I
_ -VA=M
_OSE,N
STO_EO
LO_T,ON
WINDOW
OUTER DOOR
POSITIONING UNIT
{..o
_RLOCK (UNLOCKED)
EXPERIMENTS
SOt9
5020
S063
S073
SI49
SI83
T025
T027
T027 Photometer 0 0 0 0
(Sun Shield)
Actual Total i 0 0 0 0 0
Planned Total 7 0 0 6 0 0
% of Test C5 [es 0.1% 0.1%
I
-Z SAL
S020 0 2 0 0 2
SI90B 17 31 6 17 31
S019 AMS 16 31 8 16 31
S063 8 17 0 8 17
T027/S073 2 0 7 2 0
(Photometer)
T027 (Sample 0
Array)
S149 (Photomete_ !) i 0 0 I 0
$201 0 0 ii 0 ii
Actual Total 23 44 92 22 44 92
Planned Total 9 43 23 9 43 23
% of Test Cycles 2.3% 4.3% 9.2% 2.2% 4.4% 9.2%
;
194
backup SAL tripod was used at the antisolar SAL. There was an align-
ment problem with the backup tripod at the antisolar SAL which was
solved by anchoring the left leg in its proper location and bolting
the other two legs to the floor grid, after rotating them one or
iiii two grid holes. It was later determined that the backup tripod was
misdrilled, causing a 2-inch offset in the alignment. A check indi-
cated that the backup tripod would fit satisfactorily only at the
solar SAL. The flight unit would fit in either SAL position, so the
tripods were exchanged by the second crew. No alignment problems
were encountered during the tripod exchange.
During a condensate dump, one of the crew left the SAL outer door
open and the valve in the "PRESS" position. With the desiccant system
I valve in the "OPEN" position, this allowed cabin air to bleed over-
board, through the desiccant canister, and out of the SAL. The leak
was discovered during the crew sleep period. When the crew woke up
the next day, they were asked to configure the SAL properly. An
analysis was subsequently performed which indicated that the desiccant
system still had at least a 100% margin (5000 grains of H20 ) in spite
of the inadvertant atmosphere dump.
There was not enough illumination to read the SAL delta-P gauge.
The crew used a penlight to obtain accurate readings. The black
background and long viewing tube on the delta-P gauge made it difficult
to read. The crew stated the 0-30 psia range on the gauge was
excessive and not necessary. The gauge should have been designed to
facilitate delta-P reading in increments of .025- psia, from 0 to a
maximum of 20-psia.
No difficulties were experienced aligning experiments in the SAL
and no flanges or "O"-ring seals were damaged. Experiments placed in
the SAL were adequately supported by the tripod.
The crew reported that the SAL system was tight and never failed
a leak check. Pressurization and depressurization of the SAL required
more time than planned. Consequently, this required some lead time to
set up experiments in the SAL. During crew training, actual depres-
surization functions were never performed by the crews. This did not
prepare them with the knowledge of what to expect on-orbit, when
performing this SAL operation.
195
C. Scientific Experiments
i. S009 - Nuclear Emulsion
196
The equipment consisted of an optical canister and the Articu-
lated Mirror System (AMS), launched in individual stowage containers,
and film canister, launched in the OWSfilm vault. Figure 135
illustrates the experiment operating configuration. One crewman
was to set up and operate _he experiment hardware in the SAL to obtain
a total of 150 slides of data from a minimumof 36 starfields. Three
starfields, with three exposures per starfield, were to be photographed
during each operation. To maximize the scientific data return of
S019, the astronaut was allowed as much flexibility in the choice of
starfields and exposure times as possible.
197
OPTICAL
I T I L'i"
I_--. I CONTROL ' +
%:
198
The crew reported earlier that the reticle light was dim and assumed
that the battery charge was too low to illuminate the bulb. The bulb
and battery were not replaceable, but the reticle was for "reference
only" and no data was lost due to the failure. No corrective action
was necessary, however, the crew turned off the reticle light when it
was not required to verify pointing accuracy.
An additional S019 operation requirement was imposed during SL-4
to reduce possible data degradation due to OWSinfluenced disturbances
on the pointing accuracy. During SL-4, all ergometer and Mark I
exerciser operations were prohibited during S019 operations.
The crew recommendedthat the first couple of S019 pads be relative-
ly easy to give them a chance to re-familiarize themselves with the
experiment's operations. The crew felt that 80%of all crew errors
would probably occur during the first runs of the experiment. They
also stated that S019 procedures needed to be updated with more exact
information concerning photography exposure times.
Differences existed between the forces required to operate the
controls of the different S019 canisters. Somecanisters' carriage
retract systems operated easily, while others were quite stiff. The
PI stated that this was normal as they were not all the same. The
operating controls should have been designed with appropriate "STOP"
positions to eliminate tile necessity of counting crank turns to the
"FULL EXTENDED" of "FULL RETRACTED" positions. The crew also recommend-
ed that the locks on the shaft rotation or extension controls not be
used, as they were no longer required after placing the control in the
"UNLOCKED" position.
The S019 timelines were too close; therefore, the crew recommended
that 30-seconds to one-minute be allocated for the operator to perform
a change in pointing. They also suggested adding 15 to 30-minutes to
the timeline, for the first running of the experiment, to allow for
familiarization with the equipment.
The crew requested that the samecrewmannot be assigned to an ATM
pass and an S019 pass with no time in between because any delays in the
ATMpass immediately affected the S019 operations.
The crew suggested having a T-handle on top of the winding valve
instead of the knob. The knob was very slippery when their hands were
moist and a T-handle would have been better for winding the film.
Experiment handling was easy on-orbit compared to ground handling.
The crew said that the carrying handle for the optical canister was
a necessity.
The procedures for changing the viewing coordinates were very sat-
isfactory, but there was a definite source of potential error with the
sign and algebraic manipulations required to compute the rotation. The
crew had not trained for these calculations and thought that they should
have had training to becomefamiliar with the calculations.
There were no problems with dark adaptation when operating S019.
The critical requirements to prevent dark adaptation problems were
the position of the eye with respect to the eye piece and the focus.
The repair work performed on the AMStilt mechanismwould have
been aided by the addition of an Inflight Maintenance facility composed
of a work bench and a high intensity light. An optics cleaning kit
would have been valuable to remove the finger print contamination
from the AMSmirror and should be provided on future flights.
199
i 3. S020 - UV X-Ray Solar Photography
200
BOTTOH VIEW
ASSF/4BLY
FILH MAGAZINE
oP_T_ _LK
Figure 136 Spectrograph Assembly
+¥,
I /I1
_=_= ___, ..-Zv
/
/
UV CAME RA-._
201
VISIBLE CAMERA
_ WARI)ROOH WINDOW
ADJUSTABLE
MOUNT
TER
VISIBLE VISIBLE
C_RA CAMERA
It V
SOLAR SAI,--\
+Z v
S063 SAL
UVOR VISIBLE
CAmeRA
202
b. Post Mission Assessment - Some difficulty was experienced
during the loading of a new Nikon camera for S063 operations. Upon
investigation it was found that a bit of epoxy-like material prevented
the film system from positioning properly. The crew removed this
material with a knife and the camera operated satisfactorily for the
remainder of the mission.
During SL-3, it was noted that an adapter between the AMS and the
S063 window was missing a bolt. This missing bolt did not affect
experiment operations, but a replacement bolt was provided for SL-4.
The crew also reported tightening the mounting shear to the optical
sight of the camera with tape, thereby providing better resolution.
During the initial SL-4 S063 operation, the remote timer did not
operate. This complicated the experiment operation because the crewman
had to use manual timing, in addition to tracking and controlling the
rotation and tilt settings. The timer did not operate because the
crew mistakenly used a timer without any batteries. A new battery
was installed in the remote timer and solved the problem. For sub-
sequent operations, the crew removed the batteries after each use and
taped them to the timer to prevent discharge of the batteries.
The crew reported the ring site was aligned in the wrong direction
and that it should be aligned more towards the camera axis. Part of
the sight was obscured such that the crewmen could not see the whole
mirror. The crewman assumed that although his view was truncated, the
camera was getting the full view. He therefore centered the sight in
203
f
the circle and not in the truncated portion of the field of view.
The crewman found that, by looking right below everything, straight
at the AMS mirror, he could get a better field of view than looking
i '_
through the sights.
A problem was experienced with the S063 reticle light when it
failed to illuminate. The crew checked the prime and backup batteries
and found they had an output of 1.6-volts compared to 3.l-volts pre-
flight. The battery contacts were scraped clean, but neither battery
would illuminate the reticle light. A substitute battery pack was
fabricated from two spare "C" cells, tape, and two multimeter leads.
The substitute battery pack was installed by inserting the probe ends
of the leads into the female terminals of the optical sight housing.
Normal reticle operation was then restored.
The S063 stowage and unstowage operations were accomplished as
planned. In some instances, the crew had to hurry to get two photo-
graphs on the same target, but the tracking task time allocation was
adequate. The time allocated for stowage and preparation of S063
and AMS equipment was also adequate.
The stowage location of the twin filter underneath the S063
stowage container lid was inadequate because of poor lighting and
visibility in that area. This inadequacy was identified in training
but never corrected.
The crew stated that they should have had one extra Nikon camera
body and a minimum of six extra cassettes of 2485 fast film for photo-
graphy of targets of opportunity. A great opportunity to properly
photograph the Aurora, may have been missed, because these items were
not on board. The crew recommended replacing the Hasselblad in the
CM with a Nikon.
The crew recommended that some type of suction-cup mount be
supplied for cameras used in hand-held photography. These cameras
could then be restrained at any window. Such a restraint should be
light, have a shutter release, and designed so that it could be moved
to any position.
The crew recommended that the PI provide a small color chart
identifying the different shades of night airglow gray or white as they
may appear to the crew. This would make identification easier for the
crew and provide a commonality point between ground and on-orbit data.
Crew training for S063 appeared to be inadequate because the
timer was operated incorrectly and the crew had to request information
on how to interpret the reticle.
The SL-4 crew stressed that, due to the lack of an S063 simulator,
the first couple of experiment runs would have to be considered train-
ing sessions. Any operations that called for manual dexterity by the
crewman could not be learned by oral communications. The crew stated
they had more difficulty with S063 than with other more complicated
experiments which they had trained for. Even a relatively simple
task requires a couple of familiarization runs.
204
There was some confusion in determining the frame count on the
UV Nikon camera. The frame count on the top of the Nikon read
differently than the frame count on the bottom of the camera. The crew
decided to use only the bottom frame count indicator. There should
be only one frame count indicator per camera.
/_ i!
The SL-3 and SL-4 crews utilized the T025 hardware to perform
some S073 Gegenschein and Zodiacal light photography. The equipment
was installed upside-down in the anti-solar SAL and the occulting disc
2O5
_i¸' _
was moved out of the cameras view. No anomalies were reported with
this mode of operation.
Experiment T027 handling was a one-man operation and was facili-
tated by the canister handle's proper location through the center of
gravity. On movable items of large volume and mass (i.e. T027,
S183) handles are definitely required. The handle(s) should be
located such that the crewman had complete control of the object
during maneuvering operations.
No problems were encountered during photometer head changeout
and maintenance, despite the compressed operational envelope caused
by the parasol canister/tripod protrusion. Instead of restowing
T027 in its launch container between operations, the crews left the
photometer attached to the launch container lid.
As T027 operations progressed, the crews noticed that the photo-
meter UXM rods became increasingly difficult to screw together. This
was thought to be caused by a buildup of moisture and contamination.
Also, during rod retraction, the crews reported that the thermal
gloves were required but did not hinder the crewman's rod retraction
operations. The SL-3 crew indicated that the T027 system should have
been checked out completely and possibly operated inside the OWS
prior to its use.
206
CASSETTES OPEN
Figure 140. S149 MD/CSU With De_ector Cassette Set, Operational Configuration
|
207
S149 hardware, for both nominal and contingency operations, was
well designed and operated as planned. The contingency hardware,
used in EVA deployment of S149, functioned well. The bracket used
in mounting the MD/CSU on the ATM thermal shield was a little loose
but caused no problems. The ATM thermal shield paint was scratched
as the mounting clamp was attached but this was not considered to be
detrimental.
208
pushed it into the carrousel and stowed the carrousel. Prior to the
i: next operation, an alignment procedure was performed and no problems
or loose glass fragments were reported. Pliers were used to rotate
the carrousel 45 ° to the "00" position. During the fourth operation
J • !
209
The S183 operations timeline did not allow enough time between
exposures. One-minute was added to these times to allow the crew
to adjust pointing and timing for the upcoming exposure. The crew
also complained about being rushed between an ATM pass and S183
operations. The timeline did not allow ample time to debrief the ATM
pass and commence S183 operations. The crew reported no problems
associated with the OWS lighting levels during S183 operations.
, i/!'
210
•• • / •i:::i•
¸/L_ •_: / • .... ;
/
DETECTOR MODULE % , i
V---]
211
b. Post Mission Assessment - On the first SL-3 EVA, the
two outer collector assemblies were retrieved and a calibration shield
was installed on the forward inner collector spool. During the final
SL-3 EVA, the crew retrieved one of the two remaining inner collector
assemblies.
On SL-4, a new inner collector assembly was launched and, on
the first SL-4 EVA, attached to the empty collector spool. During a
subsequent EVAfor ATMfilm resupply and Kouhotek photography, the
crew reported that the $230 calibration shield was missing. Evidently,
the shield had been brushed and knocked loose by one of the crew
during EVAoperations. On the final SL-4 EVA, the remaining two inner
collector assemblies were retrieved for return. During AMrepressuri-
zation operations, one of the two samples was damagedby air from
equalization valve 311. The crew reported the damageto effect
approximately 10%of the sample.
The EVAprocedures for the collector assembly retrievals were
straightforward and no problems were reported. The crew reported
that they were very careful during retrieval so as not to touch, and
consequently contaminate, the collectors.
The calibration shield and the one collector assembly deployment
were performed without any reported crew interface problems. The
restraint/stability provisions were considered adequate for performing
the $230 crew tasks.
212
12. $233K - Kohoutek Photometric Photography
213
D. Technology Experiments
_ ,:_i _
ii il %, _::"i
SAMPLE ' i:" i! '\\ ,.-'::"' !
RETURN .,': i _ 'X ..':."
, i/i CONTAINERS
_/ i! :_', ."::" i _i
!i i: _, :. ." .-"
': 'i : "- ,"..'," ..... i
. : : ..'.,_ _ - .,,. ........
•. : ,:..... :... , _/i ii
i: :_ .: .'2' ._.
_" :.'_'i ..'.." ."', ,. '
:: .:_. : :..." ..-, , : _ ,', _._, .:._ : :
Figure 142. D024 Experiment Panels and Sample Return Container Configuration
_1518 CONTROL
PAC _".G
t,CCESSORI E5 AND
FOP_IING (H55_)
SF ECDILN CONTAINER
GSE ELECTRIC
FURNACE ASSI_BL¥
(STOWED)
WORK CHAMBER
EEOTIIEI@:ICBRAZE
PACKAGE (,'_5 2 )
OR
H518 CARTRIDGE
CONTAINERS
215
The facility permitted exploration of space manufacturing applica-
tions of molten metal phenomena such as metal flow, freezing patterns,
thermal stirring, fusion across gaps, and surface tension. The
requirement was for one crewman to perform the experiments. The basic
functions performed were; installation of the experiment equipment or
specimen in the work chamber, systems control operation, observation,
photography, and monitoring of the experiment, and removal and stowage
i? :117:)
of the equipment and specimen after experiment completion. Experiments
M551, M552, M553, M555, M518, and M479 utilized the M512 facilities.
Experiment M479 was performed at the end of SL-4 with the only
anomaly reported being associated with the water quench system. The
lower nozzle appeared to be completely plugged and the upper nozzle
emitted only a dribble. The crewman completely reserviced the system
but it still did not function properly. In order to get any spray at
all, the crewman had to grasp the accumulator knob and pull sharply
on it to force water through the system. There was not time for
extensive trouble shooting, but the problem was believed to be with
a water supply valve not being turned on.
While burning sample number three, the crewman stated there was
an operator error in that he left the chamber repress valve in the
open position. The only effect was the sample burned slightly longer.
M512 experiment performance on-orbit was similar to ground training with
the exception of the times required to heat or cool the experiment
specimen and to obtain a sufficient vacuum in the facility. The crew
stated that the training unit was excellent, just like the flight
unit, but they never experienced pumping the facility to a vacuum
during their training. Consequently, the first time the vacuum gauge
was used on-orbit, the crew thought that the slow bleed down time
indicated a faulty gauge.
216
During M553operations in the M512 facility, no problems devel-
oped with the facility or accessory equipment. However, pressure
build-up in the facility chamber during the firing of the electron
beamgun occurred more rapidly on-orbit than experienced during
training. In someinstances, the balls on the M553wheel stings
formed a pear shape or did not release. The crew experienced no
problems in handling the specimens as long as they observed proper
cool down times.
The crew expressed enjoyment in performing the M518Multipurpose
Electric Furnace experiment because it was new and different. The
equipment worked as designed and was easily installed into the M512
facility chamber. The specimen cartridges were numbered(identified)
in systematic manner that permitted ease of handling and insertion.
The operations were clearly defined and no problems were experienced
performing the M518 series in the M512 facility.
All M479 specimen samples were in excellent condition and the
burning had no effect on the view ports. The view ports remained
clean throughout the experiment performance.
The M512chamber hatch did not appear to have proper friction
hinges as per the experiment design requirements. No detrimental
crew commentswere received, but during video downlink of M512 facility
operations, the hatch was observed to be floating free.
217
The TO02window hood, which was used to shield the wardroomwindow
from internal reflection, was considered a definite necessity. The
crewmanfound it difficult to hold the sextant steady during sightings.
He also felt it would be extremely helpful to have the sextant read-
out inside the reticle, in order to prevent losing sight of the
star while taking readings. The stowage configuration in locker W740
was excellent, and the foot restraint provisions at the wardroomwindow
were considered adequate.
The crew stated it was difficult to remove their fingers from
the pointing control knobs on the sextant without moving it. They
could get a good alignment, but when they released their fingers, the
knob would move slightly. This created somemediocre scatter in the
system. The control knobs should have been easy to move, but not so
sensitive that they could not remove their fingers without disturbing
its position. The crew also stated the knobs on the filters were
poorly designed because they could not tell whether they were in or
out.
The crew experienced pointing difficulties due to the shape of
the case and the location of the strap. This madeit difficult to
hold the sextant in the proper position at the window. They believed
they needed phosphorescent alignment marks to get the line of sight
directed between two stars. They also suggested the use of a colored
filter so that they would not lose track of which star they were
sighting. This was a problem when holding the sextant at odd angles.
The system should have been designed so that all controls could be
operated without the crewmanremoving his eyes from the reticle sight.
218
!/YI:, ----GAS OUTLET
! _] ]i / F AS INLET
L!II:<I
IIII _ _ I ,.,,.,c,..,+
=.++,..,.,,, _++_-+o,: '._:_+'_'
£iiI_
il
i? ¸
.
i l :!!ii
_I
219
CANISTER OCCULTING DISC
'_ _ASSI_InLY
220
The T025 experiment was performed from the anti-solar SAL with
only minor problems. The T025 hookup with the extension rod worked
well and the procedures/checklists and hardware used for night photo-
graphy were adequate. Pad updates for the experiment reminded the
crew to inhibit the fire sensors prior to experiment initiation because
the Caution and Warning System alarm was activated on SL-3 when the
SALwas opened with T025 installed.
T025 was not originally designed for EVAuse but, with the addi-
tion of the specially designed EVAbracket and filters, (illustrated
in Section VI. E), ultraviolet and visible photographs of the
Kohoutek comet were obtained.
221
CANISTER
PLATE
222
E. Operations Experiments
223
with the Automatically Stabilized Maneuvering Unit (ASMU)while an
observer assisted. Runs i, 2, and 4 were designated to be performed
unsuited whereas run 3 was planned for maneuvers with the Skylab
Extravehicular Mobility Unit (EMU).
Prior to experiment performance, the M509hardware (Figure 148)
and support hardware was to be unstowed and reconfigured for operation,
including Propellant Supply System (PSS) bottle and battery charging.
Once the experiment preparation was completed and the OWSforward
experiment area was cleared of equipment which could impare experiment
operations, the observer was to assist the test pilot in donning the
ASMU(Figure 149). The test pilot was to then undock from the donning
station and perform the designated M509maneuvers. Upon completing
these maneuvers, the subject was to return to thedonning station and
dock the ASMU,concluding the experiment performance.
HAND-HELD
MANEUVERING
UNIT
AUTOHATICAL_
STABILIZED
MANEUVERING
UNIT
SUPPORT
UMBILICAL
225
The M509ASMUwaswell designed and easy to operate. Flight
training skills, commonto all astronauts, was apparently readily
transferred to navigating the ASMU. This transfer of training was
demonstrated during an unscheduled M509performance by a crewmemberwho
had never trained for M509or ever used the training simulator. His
flight was performed with ease and was considered a complete success.
During the M509maneuvers, four potential flying modeswere
evaluated and, in order of preference, were "DIRECT", "CMG", "RATE
GYRO",and'_HMU". The "DIRECT"modewas the easiest and the more
intuitive to control. The "CMG"and "RATEGYRO"modeswere very good
but the precision, inherent to these modes, was unnecessary and will
not be required for a future EVAmaneuvering device. The HHMU was
given a poor rating and was recommendedby the crew to be deleted from
consideration as an EVAmaneuvering mode. The difficulty with the
HHMUwas in locating the center of gravity, which turned out to be an
important factor in this maneuvering mode. In future testing of a
maneuvering unit, it is recommendedthat the HHMUbe eliminated from
consideration because it requires unique and undeveloped operator
skills.
In flying M509, actual EVAconditions were simulated to evaluate
all phases of maneuvering. Suited operations were conducted using
both the LSU and SOP. The SOPconfiguration was preferred over the
LSU configurations because of the dynamic effects present with the LSU.
The LSU, due to its mass and elastic characteristics, imparted an
inertia on the M509ASMU,which proved to be annoying to the test
pilot, constantly requiring guidance corrections to the unit.
Safety was a principle concern during M509pre-mission design
and planning. Due to the ease of operation and maneuverability of
the ASMU,the pre-mission concern of inadvertant and possible catas-
trophic collisions was proven to be unwarranted. The ASMU,though
very large and heavy, was handled without difficulty by the test pilot.
The test pilots were confident that, even with the large ASMUmass and
a maximummaneuvering velocity of 3-4 ft/sec , they could, in the event
of a thruster failure, reposition themselves and absorb the energy of
an impact without bodily or hardware damage.
The crews believed that the M509hardware and supporting equip-
ment was well designed from both a functional and integration stand-
point. However, the crews one negative commentwas that the ASMU
had too many controls located in too many diverse and remote positions.
If possible, these controls should be relocated on a commonpanel to
facilitate crew operations. The safety goggles and ear plugs were
used by all crewmen. The unstowage/stowage of the M509hardware was
straightforward with no problems occurring. PSSbottle charging
required the crew to translate to and from the AMrecharge station
with the bottles. This entire procedure, including recharge, took
less than i0 minutes to perform. It was reported that the bottles
reached a temperature of approximately lO0°F during recharging. Trans-
lation with the bottles was accomplished by the crewmanholding the
bottle ahead of him, pushing off and then following along behind the
hardware. Prior to reaching his destination, the crewmanwould reposi-
tion himself between the hardware and contact point for a safe landing.
226
The ASMUwas an acceptable translational device but was found to
be severely limited in its use as a workstation/platform for perform-
ing work related tasks. In performing relatively easy tasks, the
crewman's body torques would over saturate the ASMUgyros and cause
a loss of stability. To perform EVAtasks, the ASMU,as designed,
would have to be docked/restrained at the designated work area to
achieve the necessary stability required to perform the task.
The next generation EVAmaneuvering device should be back mounted
with the pilot-to-backpack restraint system providing a tight, secure,
and comfortable (seat padding recommended)fit. Backpack donning/
doffing should be designed as a one-man function. The backpack must
have six-degrees of freedom, with the propulsion thrusters located
around the center of gravity of the pilot/backpack combination, and
should be hand controlled. The hand controllers should have the
capability of being relocated during flight to allow multiple working
postures for the pilot. The "DIRECT"mode should be selected as the
maneuvering modewith a capability of a 3-4 ft/sec velocity. Restraints/
docking provisions, i.e., manipulative arms must be provided to
adequately stabilize the pilot and permit him to perform the designated
task. A backpack spotlight should be incorporated to provide the
pilot with an illumination source at his work area. Separate isola-
tion valves/circuit breakers for each thruster, or set of thrusters,
should be provided to insure against a single point failure. Ideally,
backpack should contain all systems required for EVA, such as, pressure
control, oxygen, and maneuvering systems, with all system monitoring
displays/readouts being illuminated. Incorporation of a safety
tether should also be considered.
227
configuration is illustrated in Figure 150. Upon conclusion of the
experiment performance, the cameras, AM tape recorder and the EDSwere
to be turned off and the FMU's caged and pinned. The EDSdata cable
was to then be disconnected and stowed with the LIMS suit assembly
in the TOI3 stowage container.
228
L
i:_!i:
__i
:C! ?
229
• i i i i
EAT
ELECTRICAL
AND ]
1)MBILICAL
M509
PROPELLAN'r
BAC_ACK
SUPPLY
BATTERY
M509 "_
I.5
SUPPORTING D_
230
_: _:i:_;;k'_i
,v,:_'.'_ ,__i_
A second modification was performed by the SL-3 crew on the LSU
in hopes of reducing or eliminating the dynamic effects it imparted
on the maneuvering units. Using a scalpel and scissors, the LSU was
stripped of most wiring and insulation, leaving only the 02 line and
communications line. This LSU was used on all subsequent M509 and
TO20 suited runs not utilizing theSOP configuration.
Because of the lack of rigidity experienced with the TO20
restraint system during SL-3, a new, rigid restraint system was
_/ !i
I designed and fabricated between missions. This rigid restraint
system was launched on SL-4 and used by the crew in their TO20 opera-
t ions.
The first SL-4 T020 run was performed suited and utilized the
new restraint system. The crew reported that the system worked
extremely well and reduced practically all body/backpack motions.
The second T020 performance was conducted in shirtsleeves. The
crew operated T020 with both the rigid and original restraint systems.
Again, the rigid system was considered highly effective whereas the
non-rigid system was considered extremely poor.
This was the last evaluation of experiment T020 as scheduling
considerations prohibited any additional performances.
TO20 stowage/unstowage was fairly simple, although between
operations it was left stowed in such a manner requiring a minimum of
reactivation time...a casual type of stowage.
The T020 restraints and harness were not satisfactory. Also,
seat padding was improvised and is definitely required. The restraints
did not give the operator a secure or tight feeling in the unit. The
harness, due to its unusual design, was difficult to don and connect.
The backpack assembly was not contoured correctly and was too loose
when donned. Incorporation of the required restraint system removed
most of the "play" between the backpack and FCMU and gave the pilot
a more secure fit with the T020 hardware.
The shoe plates seemed to work well, although it was easy to
kick one's foot/shoe plate out of the FCMU. Also, the shoe plate
forces required for thruster control were too high. These seemingly
high shoe plate forces could be attributed to a possible deconditioning
of the crew's leg muscles due to the zero-gravity environment.
T020 should have had six-degrees of freedom for fair comparison
with M509 (which was not the intent of the experiment). As designed,
it is unacceptable as a maneuvering vehicle and the crew saw no
advantage in its concept of foot-controlled maneuvering.
231
F. Student Project Experiments
232
4. ED 31 - Bacteria and Spores
5. ED 32 - Invitro ImmunoloEy
233
No assessments or recommendationswere received from the crew
i!?z concerning ED 32. Therefore, it is assumedthat the experiment hard-
ware, procedures and interfaces were well designed and all functioned
as planned.
7. ED 52 - Web Formation
234
i
CABLE, ASSEMBL_
PATTERN ASSEMBLY
_I"YLUS
E,_PERI _NT
IlllLl!l,
Ii lt]l
235
camera actuator with no results. The actuator was considered failed
and therefore the web forming photography objective was not met.
Photographs were taken periodically by the crew using the hand-held
camera. Due to the actuator failure, someadditional crew time was
spent taking hand-held photographs. Both the prime and backup spiders
died in-orbit and were returned to earth along with web samples.
9. ED 63 - Cytoplasmic Streaming
236
/
LIGHT
237
: I
:_.i
_
CONTAINER
A,SS]_'_IBL¥
CAMERA
BRACKET NIKON
16ram DATA
/ ACQUISITION CAMERA
R_IOTE CO_rrROL
CABLE
MICROSCOPE
ADAPTER
ELDEA VIAL
IMSS_.:ORK
TA3LE(LOCKERW708)
238
In conjunction with performance of ED 63, a ground based test
was performed. A sample slide was prepared on each of the three
plants and observed under a microscope. Two of the three elodea
plants appeared to be totally dead, the third appeared normal and
exhibited good cytoplasmic streaming. The vials containing the two
i
dead plants smelled of hydrogen sulfide and the leaves showed no
resistance when detached. Based on this, it was considered probable
that one or more of the plants in-orbit were dead. From a later
on-ground performance of ED 63, it was discovered that a previously
considered dead plant had exhibited some cytoplasmic streaming.
I_
iii: Therefore, the crew was requested to prepare slides on all three
plants and examine for possible streaming. The crew complied; however,
no streaming was detected. This resulted in termination of the experi-
ment for SL-3 and an eventual resupply for a SL-4 performance.
During the SL-4 performance of ED 63, a hardware anomaly was
reported concerning the DAC camera/IMSS microscope adapter. The
crewman examining for cytoplasmic streaming could not acquire a full
field of view. It was his assessment that the adapter was the cause
of the problem.
The SL-4 performance of this experiment approximated the results
obtained from SL-3. During the first cytoplasmic streaming observa-
tion, one plant provided some evidence of streaming. In subsequent
observations, the elodea plant leaves showed no resistance when
detached, there was a sulphurous smell present and no cytoplasmic
streaming was observed. It was decided that the plants were dead and
the experiment was terminated. The plants were removed from their
vials and placed in the trash airlock.
Other than the DAC camera/IMSS microscope adapter anomaly, the
ED 63 performances were conducted as planned. The crew reported that
the experiment procedures and hardware functioned well and that every-
thing possible was done on their part to acquire usable data. From
the results of this experiment, it was concluded that zero-g has an
undesirable effect on cytoplasmic streaming in plants.
239
b. Post Mission Assessment - The wicking segmentof ED 72
was successfully performed, as scheduled, with photographic data and
crew sketches obtained.
The capillary segmentof ED 72 was unsuccessful. During the
preparation of this portion, the crewmanobserved that both the oil
and water had leaked from their reservoirs. Whenthe lever valves
were operated, no capillary action was observed. The failure was
attributed to the reservoir leakage. Mission Control later suggested
attempting to refill the reservoirs but the crew had already disposed
of the modules through the trash airlock. The leakage was documented
on film.
The wicking portion of ED 72 was successfully completed with the
hardware functioning as designed. However, the capillary segmentwas
unsuccessful due to the hardware failure resulting in the leakage of
the capillary modules.
240
six detectors continued data collection throughout the Skylab missions
and were deactivated and stowed in the CMby the SL-4 crew just prior
to their return.
The SL-4 crew stated that detector Bravo 3 was poorly placed, in
that, as they camethrough the hatch from the forward compartment to
the experiment compartment, it was in a very natural place to grab.
If touching degraded it, it was definitely degraded as it was touched
numerous times.
No assessments or recommendationswere reported by the Skylab
crews concerning ED 76. Therefore, it is assumedthat the experiment
hardware, procedures, and interfaces were well designed and functioned
as planned.
241
SECTION
V. INFLIGHTMAINTENANCE
A. Scheduled IFM
ii iii i i i!i
ii!!!
TASK DESCRIPTION PLANNED
FREQUENCY
Vacuum Clean - ECS Inlet Screens
243
i./_ ,_
: i! iiil
:41
i/ iiiil/!il}
iii}ii
i!!ii!
i!i
_!:
i 2. SL-2 Activities
245
TASK DESCRIPTION ON-BOARD TASK DESCRIPTION ON-BOARD
SPARES SPARES SPARES SPARES
Replace-TV Monitor I
Replace-TV Camera/Monitor Cable I Service/Deservice-Cluster Water
NOTE: Number in parenthesis indic_ !_es spares available on ground for resupply
J
NOTE: Number in parenthesis indic_ :es spares available on ground for resupply
_O
(T013)
Disconnect-Shutter Drive (S190) N/A
o
Install-Camera Filter (S020) 2
Replace-BTMS Probe (MI71) 3
Replace-Valve Assembly (MI71) 3
Replace-Mouthpiece (MI71) 3
Replace-Breathing Hose (MI71) I
Activate-Backup Inverter Lighting Installed
Control Assy.
Replace-Ergometer Drive Assy. (MI71)i
Replace-Lower Body Negative
Pressure Waist Seal
Replace-Sextant Batteries (T002)
-Stadimeter Batteries (T002)
Replace-Color TV Camera I I 1 I -
Replace-TV CameraMonitor Cable i - I
Replace-TV Power Cable 1 - i
Replace-AM Tape Recorder 4 2 i 3 2
Water Syste m
Electrical System
251
TASKDESCRIPTION ON-BOARD
RESUP- SPARES USED/
PLIED TASKS PERFORMED
SPARES
SPARES SPARES SL-2 SL-3 SL-4
Structure
Crew Equipment
Experiment Systems
ReplaceInterchange-Mass
Measuring Device Electronics 0(i) i I i -
Module (MO74/MI72)
Replace-Magazine Drive Assy. I -
(S190)
Replace-Cooler/Dewar/Detector I i - i i
(S192)
Replace-Dessicant Assy. (S190) 18 - 18 - -
Replace-Film Magazine (S190) I - - - 1
Replace-Size D Batteries(M487) 15 - 3 2 -
Install-Camera Filter (S020) 2 - - - 2
Install-Shutter Override 4 - - - 1
Actuator (S054)
Install-Signal Attenuator (S192)
Primary I - 1 - -
i
Secondary I -
Install-EREP Diagnostic Downlink i - 1 -
Unit
252
i L •
e. AM Tape Recorder Replacements - AM Tape Recorder No. 1
failure was reported after completion of the trouble-shooting proce-
dure on MD-15 (DOY) 159). The recorder was replaced with one of the
four spares provided for unscheduled IFM support of the three AM
Tape Recorders. On MD-29 (DOY 173), a second recorder failure was
r reported after splashdown. The second recorder was replaced by the
SL-3 crew. Two additional spares were flown on SL-3 to replenish the
units expended during SL-2.
3. SL-3 Activities
253
c. EREPDownlink Unit Installation - The EREPDownlink Unit
was installed on MD-6 (DOY214). This maintenance activity involved
installation of auxiliary hardware and was not the result of a failure.
The Downlink Unit provided capability of patching between EREPand the
video system to provide direct down link of data from EREPto ground.
254
k. TV PowerCable Replacement - The TV Power Cable was
replaced on MD48 (DOY256) after s malfunction procedure was performed
on the video system to determine the cause of noise generated in the
system. One spare cable was provided on-board. Later investigation
by the crew revealed an open in the center conductor of the coaxial
cable.
4. SL-4 Activities
255
e. S054 Shutter Override Actuator Installation - The S054
Shutter Override Actuator was installed on MD40 (DOY359) during
the EVAoperations in order to perform the S054malfunction procedures
and aid in the contingency task to manually position the filter wheel.
The Shutter Override Actuator was launched on-board SL-I.
256
I. AM Tape Recorder Replacement - AM Tape Recorder No. 3
was replaced on MD 66 (DOY 020) with one of the two remaining spares.
The recorder was replaced because it had exceeded the i000 hour life
limitation. At the time of replacement the unit was still operating
and had 1,579 operating hours in flight and 241 operating hours during
ground test. AM Tape Recorder No. 2 failed on MD 67 (DOY 021) and
i
was replaced with the remaining spare on-board. The failure occurred
after 1446 operating hours. Two resupply spares were provided on SL-3
and an AM Tape Recorder Repair Kit was launched on SL-4. The repair
kit was not used during SL-4.
257
C. Contingency IFM
2. SL-2 Activities
258
• i L /
On MD 14 (DOY 158) using tools which were carried up in the SL-2
CSM for the standup EVA and other on-board tools and equipment, the
crew successfully deployed Wing I. Procedures and tools for deploying
the wing were developed at MSFC and verified in the Neutral Buoyancy
Tank. The procedures were then uplinked to the SL-2 crew.
3. SL-3 Activities
259
to the crew. The crew successfully replaced the rope but experienced
somedifficulty. The Skylab tool inventory did not contain a 9/6_-
inch Allen wrench which was required to tighten the rope clamp screw.
A I/8-inch Allen wrench, cocked to one side in the socket head screw,
was used to tighten the clamp.
260
k. Video Tape Recorder Circuit Board Removal - Four
circuit boards were removed from the Video Tape Recorder Electronics
Unit on MD 42 (DOY 250) to be returned for failure analysis. Two
screwdrivers were used to extract the circuit boards after removal of
the electronics unit cover.
4. SL-4 Activities
261
c. Rate Gyro Package ThermometerInstallation - Liquid
crystal thermometers backed with pressure sensitive adhesive were
installed on each of the six rate gyros on MD6 (DOY325) in order
to monitor the gyro temperatures. The rate gyro temperatures were
monitored every two days throughout SL-4.
262
exerciser was broken during SL-3 and had becomeabraded at the ends.
A temporary repair was madeduring SL-3 but proper tools and spares
were not available for complete refurbishment. The repair kit was
assembled and launched on SL-4.
263
Contingency EVAinflight maintenance conducted during the missions
substantiate the need for adequate planning in this area. Prior to
the SL-I launch, EVAinflight maintenance was intentionally avoided.
During the three mannedmissions_ the EVAinflight maintenance
performed not only initially saved the Skylab program but kept the
spacecraft systems and experiments functioning even longer than
the planned program duration.
264
D. Tools and Equipment
265
\\
II?
_L KIT I
TOOL KIT 2
266
SK_ TOOL KITS I and 2 5/32 ALLEN BIT-MODED CONNECTOR PLIERS
TORQUE HANDLE 3/16 ALLEN BIT PIN STRAIGHTENER PLIERS
TORQUE _RENCH 3/16 ALLEN BIT-MODED 3/32 BLADE DRIVER
SPIN HANDLE 3/16 X 3-1/2 ALLEN BIT 3/16 BLADE DRIVER
RATCHET HANDLE 3/16 LONG ALLEN BIT PHILLIPS DRIVER 1
SPEEDER HANDLE 3/16 LONG ALLEN BIT-MODED PHILLIPS DRIVER 2
EXPERIMENT HANDLE 3/16 90 DEG ALLEN BIT PHILLIPS OFFSET DRIVER
4 INCH EXTENSION 1/4 AI/_N BIT HAMMER
8 INCH EXTENSION UNIVERSAL JOINT 1/16 PUNCH
12 INCH EXTENSION 11/16 CROWFOOT WRENCH 3/32 PUNCH
SOCKETS 3/4 CROWFOOT WRENCH 3/16 PUNCH
1/4 8 POINT STD SOCKET i CROWFOOT WRENCH 0-RING EXTRACTOR
1/4 STD SOCKET 1-1/8 CROWFOOT WRENCH KNIFE
5/16 STD SOCKET 1-3/8 CROWFOOT WRENCH TWEEZER
3/8 STD SOCKET 5/16 WRENCH RETRIEVAL MIRROR
7/16 STD SOCKET 11/32 WRENCH RETRIEVAL HOOK
SOCKETS 3/8 WRENCH MECHANICAL FINGERS
_O
O% 5/16 DEEPWELL SOCKET 7/16 WRENCH PINCH BAR
3/8 DEEPWELL SOCKET 1/2 WRENCH VISE
7/16 DEEPWELL SOCKET 9116 WRENCH C CLAMP
1/2 DEEPWELL SOCKET 11/16 WRENCH VELCRO- PILE
9/16 DEEPWELL SOCKET 3/4 WRENCH VELCRO-HOOK
3/8 BLADE DRIVER BIT 13 / 16 FLARENUT WRENCH 3/4 INCH NEUTRAL TAPE
HI-TORQUE DRIVER BIT 1 ADJUSTABLE WRENCH 1 INCH RED TAPE
HI-TORQUE DRIVER BIT 2 3/64 ALLEN WRENCH 2 INCH NEUTRAL TAPE
HI-TORQUE DRIVER BIT 3 5/64 ALLEN WRENCH SAFETY WIPE
1/16 ALLEN _ BIT 3/32 ALLEN WRENCH LACING TWINE
3/32 ALLEN BIT SLIP JOINT PLIERS LUBRICANT
7/64 ALLEN BIT CHANNEL LOCK PLIERS H20 SYSTEM LUBRICANT
1/8 ALLEN BIT NEEDLE NOSE PLIERS SCISSORS
5/32 SQ ALLEN BIT VISE GRIP PLIERS
5/32 ALLEN BIT CUTTER PLIERS
SPARE TOOLS
7/16 STD SOCKET (I)
7/64 ALLEN BIT (I)
5/32 ALLEN BIT (3)
3/16 ALLEN BIT (I)
3/16 LONG ALLEN BIT (I)
_O 1/4 ALLEN BIT (2)
O_
_O 3/4 WRENCH (I)
3/64 ALLEN WRENCH (3)
3/32 ALLEN WRENCH (I)
3/32 BLADE DRIVER (I)
3/16 BLADE DRIVER (I)
SWISS ARMY KNIFE (I)
End Grip, MSFC Pole Ratchet Handle, 3/8 Drive Screwdriver Bit, 3/16
SAS HOOK Swiss Army Knife Hex, 5 inch
Double Prong Adapter 3/16 Blade Screwdriver
Cable Cutter Rate Gyro Package Tools Swiss Army Knife (3)
Shear Assembly Red Tape, i inch
Pole Tether Restraint Ratchet Handle, 3/8 Drive Diagonal Cutter Pliers,
Tool Extender Rods (3) 9/16 Deepwell Socket, 3/8 Drive 6 inch
Waist Tether (L) No. 3 Hi-Torque Bit, 1/4 Drive (2) General Purpose Tape
Waist Tether (R) Ratchet Handle, 1/4 Drive (2 Rolls)
Release Mechanism Screwdriver Bit, 3/16 Hex, 1/4 Drive
Claw Assembly Universal Joint, 1/4 Drive Miscellaneous
Extension, 4 inch, 1/4 Drive
Parasol Tools 3/8 Open End/Box End Wrench 9/16 Flarenut Wrench
o RGP Connector Pliers (2) 7/8 Crowfoot Wrench
Strap Wrench (2) 90 Degree Nose Connector Pliers Sharpening Kit
Screws/Allen Tools 9/64 Allen Wrench (2)
Parasol Tools Screwdriver Bit, 9/64
Miscellaneous Hex
Hex Head Wrench (2) Hi-Torque Screw Removal
Swiss Army Knife Rod Disconnect Tool Tool
S193 Repair Screwdriver
EPC DRC Connector Pliers
Capture Latch Release
Tool
ATMTV Installation
Tool
The pinch bar which was used during the OWS Solar Wing deployment
activity was left tethered to the wing. A replacement was determined
not to be necessary due to limited usage identified for the pinch
bars and the fact that there were two initially stowed on-board.
During SL-4 the soft inserts in the jaws of the connector pliers
became loose and had to be taped in place.
271
II i
12
r •
k_
•
•i i _
¸ _ i?
_ i•
i_ •
ri•iiill
i i!iiii•
L
• •
_o
Plenum Bag Stowage
Socket, Standard, 3/8 in.
Replace TV Input Station Vise, Bench Type
Clean Solenoid Vent Port Filter Replace Ergometer Pedal Screw
Coolanol System Leak Inspection
Primary Coolant Loop Servicing Wire, Safety
Deploy OWS Solar Array
Socket, Standard, 7/16 in.
SAL Window Initial Installation Wrench, Adjustable
Relocate OWS Electrical Panel Support Condensate System Leak Check
Remove WMC Vent Cover
Shower Activation Wrench, Allen, 5/64
Unstow M509 PSS Stowage Rack Remove Video Tape Recorder Circuit Boards
Remove SI90B Launch Restraints
Wrench Allen 9/64
Tape, $190 Mark I Exerciser Repair
Replace S190 Cassette
it
Wrench, Open End, 5/16 in. Wrench, Open End, 3/4 in.
Replace Video Tape Recorder M172 BMMD Preparation
Install H20 Gun Resupply Connect Radio Noise Burst Monitor Antenna
Remove H20 Gun Resupply Disassemble S054 Film Magazine
Condensate System Leak Check
Wrench, Open End, 11/32 in.
Replace Video Tape Recorder Wrench Strap
Deploy Skylab Parasol
o Wrench, Open End, 3/8 in.
Replace Video Tape Recorder Wrench, S190 Spanner, Small
M074 SMMD Calibration Replace S190 Dessicant Assembly
Replace S190 Magazine Drive Assembly
Wrench, Open End, 3/8 in., RGP Tools
Install Rate Gyro Package Wrench, Torque, 0-600 in.-ibs.
Replace WMC Hotwater Dispenser Valve
Wrench, Open End, 7/16 in. Condensate System Leak Check
Relocate Portable Water Tank
M172 BMMD Preparation
Remove SAL Window Covers from M512 Foot
Restraint
ATMDoor Ramp Latch Removal
281
A tool summaryor listing was not available on-board for crew visibil-
ity of the entire tool inventory. As a consequence the crews were
unaware of the availability of certain tools unless they were speci-
fied in a procedure and their location spelled out. This included
the tools initially provided as spares and those stowed throughout
the cluster other than in the main tool kit in the OWS. The SL-4
crew stated that they would like to have had the tools displayed on
the OWSwall the sameas a work shop would be layed out in order to
provide visibility of the tool inventory.
None of the tools in the initial tool inventory were designed
for EVAuse. As a consequence, tool handle sizes had to be enlarged
by wrapping them with tape. Tape was also used to attach the necessary
tethers, since the tools were not equipped with tethers or tether
attach points. The tools proved to be adequate for EVAafter the
handles were taped and the tethers attached. An adaptable EVAhandle
for standard tools and tether attach points would be desirable for
any future tools required for EVA inflight Maintenance use.
The Velcro patches on the tools were of very little value. In
somecases the patches cameloose and they did not hold tight enough
to retain the tools on the tool caddy during translation. The main
usage was for retaining tools in the area of the SALwhere patches of
velcro pile had been installed.
282
E. IFM Summary and Conclusions
283
Skylab crews expressed a preference for Calfax type quick release
fasteners and magnetic door latches as opposed to dial latches, pip
pins and Expando-Grip pins. Internal wrenching (Allen head) screws
and hex head bolts were the preferred types of attaching hardware.
Hi-Torque and slotted type screws were unacceptable for inflight
maintenance purposes.
The experience gained on Skylab indicates that the astronauts
are capable of performing complicated maintenance tasks during EVA
and bench repair of major componentson IVA. Handling, alignment and
manipulation of large heavy items presented no problems in zero
gravity. Small items such as bolts, screws, washers, nuts, etc., did
present someproblems because they tend to float away and becomelost.
However, these items usually found their way to one of the ECSinlet
screens. Methods and techniques must be developed on future space
programs to enable the astronauts to handle and control these small
items in an effective manner.
Selection of spares to support inflight maintenance capability
should include consideration of non-critical and redundant hardware.
Skylab experience demonstrated the desirability of replacing or
repairing all failed equipment. With the exception of the contingency
maintenance performed, nearly all of the items replaced during the
missions were identified as non-critical or redundant hardware. The
tape recorders, speaker intercom assemblies, water dispenser, mass
measuring device electronics, cameras and fans are just a few examples.
Without these spares and manyothers of the sametype, the Skylab
mission would still have been successful, but the degree of success
would have been reduced.
Spares selection for IFM should include repair parts for certain
items whose design permits inflight bench repair as well as replace-
able assemblies. Skylab has proven that the crew, when provided the
proper tools, procedures and parts, is capable of performing bench
repair of failed assemblies.
Tools selected for Skylab were primarily those required for
specific tasks that were approved for inflight accomplishment. A
few contingency type tools were included such as a pry bar, a hammer
and the Swiss Army knife, which proved to be valuable assets. Allen
wrenches of certain sizes were provided for specific application, all
sizes were not provided. The sameapplied to open end wrenches,
sockets, etc. The crews have expressed a desire for complete sets of
these tools. It has also been indicated that regular off-the-self
type tools are adequate and no special finish is required for use in
space. A tool caddy for carrying tools from place to place should be
developed with the purpose in mind of facilitating the location of the
needed tool after arriving at the work station. Crew commentsindic-
ated a "see through" material would be desirable. The caddy should
also provide a capability to hold small parts such as washers, screws,
bolts, nuts, etc., since containing and locating these items was a
problem in zero gravity.
284
The crew of SL-3 indicated that a portable leak detector should
be considered for future missions. This need becameevident when
coolant leaks and vacuumleaks were suspected and verified, but not
isolated to a specific location. A desire of all crews was a
dedicated work bench or table with a capability for holding things
that tend to float away. This, with the availability of repair parts,
would enhance the repair of failed assemblies. Future spacecraft
design should include a maintenance package, incorporating bench
repair capability and containing a complete selection of general
purpose tools and the necessary special tools and equipment to main-
tain the spacecraft and payload systems. For future missions, tools
should be equipped with tether attach points to restrain them during
EVAmaintenance activities.
The astronauts have indicated that the tasks and procedures were
so well planned and documentedthat many of the maintenance tasks could
have been performed efficiently with little or no maintenance training.
In the future, the engineers and technicians must continue to work
out the procedural details, verify the tasks on trainers and flight
hardware, and provide accurate and concise procedures in order to
reduce and/or eliminate maintenance training for the astronauts.
Training for inflight maintenance should be limited to complex
repair tasks which involve unusual equipment disassembly techniques,
or tasks which could present a hazard to the crew, or result in
damageto spacecraft equipment.
285
SECTIONVI. EXTRAVEHICULAR
ACTIVITY
A. Skylab EVASystemDevelopment
286
SL-2 SL-3 SL-4
2 2 3 i 2 3
Figure 160. AAP 3/4 Cluster Configuration and Film Retrieval EVA Routes
" The first conceptual studies were conducted using limited fidelity,
inexpensive, one-g part-task mockups with a six degree-of-freedom
mechanical simulator to investigate ATM canister access, determine
optimum locations and configurations for ATM film retrieval worksta-
tions, and to develop and evaluate alternative design concepts for
astronaut translation and film transfer.
Four ATM experiments required film packages located in the side
of the canister; three required film packages at the sun end. Rather
than having the astronaut maneuver to each camera, it was decided
that the canister roll capability would be used to bring the camera
access points to the crewman positioned at a fixed worksite. Two
LM/ATM workstations would be developed; one providing access to the
film positioned in the side of the canister and the other located at
the sun end of the canister. These workstations were named "LM-End
Workstation" and "Sun-End Workstation", respectively.
In order to shorten the astronaut translation and film transfer
distances to and from the AM hatch and realizing the capabilities
already built into the I_/ATM (it contained the ATM experiment controls,
had its own independent power source, and astronauts could egress the
LM forward hatch for EVA), it was recommended, in the summer of 1966,
that film retrieval be conducted from the LM/ATM forward hatch rather
than from the AM hatch. In view of this anticipated change, the system
throughout 1967, 1968, and the first half of 1969 was designed using
the LM/ATM hatch for EVA egress/ingress. The film magazines to be
exchanged were stowed in the LM/ATM cabin instead of inside the AM. A
workstation located just outside the LM/ATM EVA hatch, designated the
LM Hatch Workstation, was developed.
288
At the time, there was very little experience with the Apollo
EVASystem, and the Gemini EVAexperience had created a concern for
the total workload to which the crew would be subjected. Egress from
the LM/ATMforward hatch improved the EVAroute, but considerable
translation distance still existed between the LM Forward Hatch and the
two ATMWorkstations. Therefore, the LM-EndWorkstation was movedto
a position between the ATM+Y and +Z axis, putting it nearly adjacent
to the LM hatch. The Sun End Workstation was moved to a position
directly underneath the LM Hatch Workstation at the +Z axis. These
workstation locations were retained throughout the remainder of the
Wet Workshop design. During the time that the EVAegress location and
general workstation configuration were changing, work was proceeding
on the ATMcanister access and on detail design of the film cameras and
their telescope-mounted receptacles. Using preliminary "one-g" mock-
ups, Figure 161, reach envelopes, general door size (based on expected "
camera configurations), and door locations were identified and designs
prepared. Requirements had been defined for camera designers, and
evaluations had begun on the camera-to-receptacle interface. Necessary
guides and aids for correct positioning of the cameras were defined.
Using these mockups, requirements were established for detent forces,
latching flags and locking mechanisms. Upon the receipt of preliminary
camera configurations, which had now decreased from 7 to 6 with the
change of one camera to a video display, work proceeded on film transfer
concepts.
The greatest challenge in developing the EVAsystem lay in finding
a solution to the astronaut and film transfer problem: Howto get the
crewmanand his delicate cargo to and from the workstations unharmed,
without damageto the vehicle exterior, without physically taxing the
crewman, and without exceeding the specified 4-hour EVAduration.
Many factors combined to complicate the task but the main source of
difficulty was the seemingly contradictory requirements for optimiza-
tion of each workstation (in terms of reach and visibility) not just
individually, but with respect to each other workstation and, in
particular, with respect to the crew and cargo transfer system. Inter-
actions between workstations and transfer systems, especially in the
"domino" effects of small changes becameextremely difficult to predict
analytically. Thus, frequent simulations, both suited and shirtsleeve,
and "one-g" and reduced gravity began to play an increasing role in
the conceptual design function.
Many concepts for getting the astronaut and film from the EVA
egress/ingress hatch to the film retrieval/replacement workstations
were investigated and applied, in simulations, to the existing work-
station concepts. Generally as development progressed, and as under-
standing of man's ability to conduct orbital EVAincreased, the complex-
ity of the concepts for the Skylab EVAdecreased; prediction of results
and interactions becamemore intuitive and the emphasis in simulation
shifted from one of searching for potential solutions to one of verifi-
cation of candidate concepts. These candidate concepts, presented
herein, provide an overview of EVAsystem evolution.
289
Figure 161. One-g MockupSimulation
290
In the early Wet Workshopconfiguration, using the AMas the
EVA egress point, design centered around the use of telescoping booms
of various types. Because of the preoccupation with crew workload,
early concepts were relatively highly automated. The serpentuator
(Figure 162), a segmented, highly automatic system for transfering
both the crewmanand the film magazines, was considered. Although
quite heavy and complex, it offered considerable savings in crew work-
load and was, therefore, given initial emphasis. Also considered at
this time was the use of "roll up" booms(Figure 163), which formerly
had been used principally as antennas on unmannedsatellites. At the
time of the decision to use the LM hatch as the baseline EVAegress
hatch, the simpler extendible boomswere being considered for film
magazine transfer.
Two methods of crew transfer were under investigation: i) using
the boomsthemselves, and 2) using fixed handrails on the exterior of
the MDAand the LM/ATM. Handrails were ultimately selected for two
reasons: i) lack of sufficient bending stiffness in the boomsand
2) the potential hazards related to the sharp edged tapes forming
the boomelements.
Whenthe decision was made to use the LM hatch for primary EVA
egress, attention shifted to the use of rail systems of simpler design
and construction than the boomor serpentuator concepts. Several
"aided" rail systems, either poweredor manually controlled, were
considered. In addition, pivoting arms operated through a linkage
which would swing packages to workstations were given heavy emphasis.
The initial rail system was namedthe "trolley" (Figure 164),
and provided the capability to transfer both crew and film simultaneous-
ly. The crewmanprovided the motive force by pulling himself and the
trolley along the rail. A prototype trolley was designed and fabricated
and was evaluated in neutral buoyancy simulation. Although the trolley
system provided excellent control of astronaut body position and could
allow simultaneous transfer of both crew and equipment, it was quite
complex, rather heavy, and the simulations indicated considerable
development would be required to provide an easy rolling system.
Difficulty with this system was due to cocking in the roller system
from off-center loads applied by the crewman(especially in negotiating
curves).
Helping to make the decision not to go ahead with the trolley
was the reclock of the workstations to provide a more direct line from
the LM hatch to the LM End Workstation and the Sun End Workstation.
The equipment transfer design configuration at this point cons_ted
of a pivoting arm (Figure 165), actuated by a handle at the LM Hatch
Workstation, which swungdown to the LM End Workstation with appropri-
ate cameras. For the Sun End Workstation, the S082Aand B film maga-
zines were to be carried on a rail device, nicknamed the "skateboard",
which rolled on the dual handrails provided for translation to the sun
end. Two concepts of the skateboard were pursued initially. One could
be pushed in front of and actuated by the crewman. Another concept
had a simple cable system operated by a handcrank at the LM Hatch
Workstation, allowing transfer of the equipment separately from the
crewmantranslating to the sun end.
291
ao_n_u_da_s "Z91 _anS_
Cq
¢q
-__ii_
ii_Iilr!/_ii_i_!
!_i_,I_
i_ii_i,i
¸_i _ _ ,k
SUN END WORKSTATION
,/ ' END
WO. TA ION
t
%
_ CSM _
[ S-IV
E_ I--1.
293
;r •
/----LMA FORWARO HATCH
TRANSPORTATION
DEVICE
SUN END FILM
I_SKATEBOARD #
LM FILM (
LM ENO FILM
TRANSPORTATION
OEVICE
TRANSLATION
RAILS
N
Figure 165. ATM I_M End Workstation
The dual rail system was provided to maintain better body
stability during translation through the solar panels. There was some
worry of damage to the solar panels or to the crewmen by inadvertent
contact. To assist in body stabilization, an early concept of the
dual rails provided a trough-like gridwork ("Coal-Chute") which
formed essentially a key-slot where the crewman could insert his feet
and thereby stabilize his lower body during translation (Figure 165).
This system of a flipover arm to the LM End Workstation and
skateboard and dual rails to the Sun End Workstation was the design
at the time of the Wet Workshop CDR, just prior to the decision to go
to the Dry Workshop configuration. Both one-g and neutral buoyancy
simulations were used effectively during the development of this final
Wet Workshop concept.
294
seriously hampered. Under Dry Workshop design, the LM End Workstation
of the A_M was renamed the Center Workstation (with the acronym VC)
and the Sun End Workstation was given the acronym VS (in keeping with
the JSC selection of two letter nomenclature for all external work-
stations). The Dry Workshop film retrieval concept resulted in the
development of a workstation in the fixed airlock shroud area, (Figure
166), designated VF. This station would be occupied by the first
crewman out during an EVA. It would provide stowage locations for all
i_
the ATM film, a temporary stowage hook for equipment, sufficient hand-
rails for use of the foot restraints, general mobility in the area of
the workstation, and access to whatever transfer equipment was to be
provided. Thus, one crewman was to provide a general management role
for film equipment and umbilicals, and the other crewman was to actually
translate to the ATM and exchange the film.
Some initial studies considered the use of a skateboard device
for film transfer to the ATM from the fixed airlock shroud. It became
obvious, however, that any rail concepts, being discontinuous across
the ATM/MDA interface (to allow ATM deployment), faced unjustifiable
difficulties in alignment during deployment and were, therefore,
dropped. Extendible booms mounted at the fixed airlock shroud and
"pre-aimed" at the ATM workstations, were next to be considered for
equipment transfer, with separate crew transfer and equipment transfer
being baselined. A simple, endless clothesline system was selected
as a back-up to the booms. The alternative of carrying film magazines,
one at a time, by the crewman performing the film retrieval was consi-
dered and rejected because of the higher probability of damage to the
film magazines and the increased translational workload required.
The fixed airlock shroud workstation was developed using the
combination of one-g and neutral buoyancy mock-up hardware. Concepts
were generated in one-g and, if they appeared reasonable, were fabri-
cated and installed in the neutral buoyancy development article.
Using the combination of one-g and neutral buoyancy development, and
simulation to determine the most effective positioning for the VF foot
restraints and the best utilization of the space around the VF work-
station (again with the selection of extendible booms for film transfer)
proved very effective. There were to be three booms provided: one to
the Sun End Workstation, one to the Center Workstation, and one spare.
The positions of these booms were selected initially using one-g hard-
ware. Their accessibility for replacement and for positioning at the
ATM workstations was then verified in neutral buoyancy simulation.
The clothesline assemblies (alternate film transfer system) were
designed to be mounted to approximate the travel path of the booms as
closely as possible. This took advantage of the previous work done in
positioning the booms for good access to the film packages at both
the airlock and the ATM ends of the transfer. Since the VS Workstation
was not visible from the airlock and since neither selected method of
film magazine transfer would go around the corner, an intermediate
workstation named the Transfer Workstation (VT) was developed (Figure 167).
295
Figure 166. Fixed Airlock Shroud (VF) Workstation
296
\
297
:1 j
Because of its unique location and position with respect to the other
components, this workstation was developed entirely through the use of
neutral buoyancy simulation. With the establishment of the Transfer
Workstation and the concomitant selection of the position for stowage
of the S082A and B magazines on their film transfer tree, along with
the selection and location of a temporary stowage device for the S082
cameras during film exchange, the ATM EVA system development was essenti-
ally complete. The system described above was evaluated during the
EVA CDR in November 1970 and was accepted with little modification.
298
In particular, the changes in the EVA egress position created very
different transfer requirements, thus spawning new options with each
change. The final result was a system which had undergone thorough
evaluation of alternatives and provided a conservative, simple, and
flexible design.
Note: For further details, see MSFC TMX-64855, Skylab EVA Systems
Development.
i!!i
_
299
B. ATMFilm Retrieval
3OO
FTBs were electrically driven and had a manual deployment/return back-
up capability. In the event of total operational failure of a FTB,
a spare unit, located in the VF area, was available as a back-up unit
and could have replaced either the VC or VS film transfer boom. The
FTBs were capable of being operated by EVl with one hand and required
i
301
d. VF Handrails - The VF contained sufficient handrails
to assist all required operations. Handrails were anodized blue and
were numberedto provide easy identification and correlation with
checklists. The handrails were fabricated by compressing a 1.125 in.
tube to 1.42 in. X 0.62 in., and were designed to withstand a load
of 200 ibs. in any direction. They were mounted with stand-offs 3.25
in. away from the mounting surface.
During EVAoperations, the crew noticed that the handrails had
turned turquoise from the original blue color. All EVAhandrails were
adequate for crew stability and translation. Their use on future EVA
missions is recommended.
Although someof the EVAhandrails at the other workstations were
smaller (1.25 in. X 0.63 in.), their general configuration was the
same. Since the handrails at all EVAworkstations were basically
the same, the commentsconcerning design description, on-orbit use,
and recommendations for VS handrails is also applicable for handrails
at other workstations.
302
The VF LSUclamps operated satisfactorily during EVAand were
easier to operate than they had been in the neutral buoyancy trainer.
They are acceptable, as designed, for future use.
Commentsconcerning operation of the VF umbilical clamps apply
to the clamps used at other workstations since they were identical.
303
During EVAoperations, both the Data Acquisition Camera (DAC)
and video cameraswere difficult to mount, point, and operate. If
cameras are to be used during future EVAs, they should have separate,
firm mounting brackets located to minimize accidental contact with
the crewmanin the workstation. The crewmanshould also have adequate
foot restraints and handrails for stability. All camera operations
should be one-handed.
304
was also used to rotate the canister to the proper orientation for
Sun End EVAoperations. The S082Aand B experiment aperture door
switch and status indicators were used to open the S082Aand B doors
for VS operations. The control panel hand controller provided two
speeds in each rotation direction. The handle had !40 degrees of
right or left motion with a maximumtorque of 26 inch-pounds, and was
compatible with pressure suit gloved-hand operation. In order for the
translation from "Low" to "High" speeds to be obvious, a detent cam
was used. The "Roll Enable/Inhibit" switch empowereda solenoid to
release the mechanical brake on the roll drive and brake assembly
when placed in the "Enable" position. The "Inhibit" switch position
allowed the spring loaded brake to operate at 80 foot-pounds of break-
out torque. Primary and secondary power switches were used to either
enable or inhibit redundant electrical power busses. The S082Aand
B aperture door switch was a three position (center-off) momentary
switch. A five watt light in the adjacent talkbacks displayed "Open"
or "barber pole" by meansof back lighting. During EVAoperations the
rotation control panel operated satisfactorily, and its use is recom-
mendedfor future applications without modification.
305
! This bracket was deployed on SL-2. No problems occurred with its
operation. The clothesline boom is acceptable for future use as
designed. This is the attach bracket of choice, given compatible space-
craft structure.
306
Future programs might benefit from the following guidelines:
eMagnetic, or friction latches, may well be sufficient
for orbital use depending on docking loads, etc.
• "First-line" mechanical latches, even if intended only
for launch, should be designed for re-use as though
intended for nominal orbital use.
e"Second-line" mechanical latches (lock-locks, launch
pins, etc.), if required only for launch, may be
designed for "one-time only" use.
The VC LSU clamp operated adequately. One crewman did not use
the LSU clamp at the VC, but encountered no entanglement problems.
307
3. ATM Sun End (VS) and Transfer (VT) Workstations - The VT was
included as a part of the Sun End Workstation (VS) and contains no
separate equipment, except for the standard EVA foot restraint. Since
the VS is "around-the-corner" from the VF and therefore inaccessible
to the boom, the VT served to bridge this gap by providing a position
for acceptance of the Sun End film magazines. Prior to the Sun End
film removal and replacement operations, EV2 ingressed the VT and
received the loaded VS tree from EVI via the Sun End boom. EV2 then
placed the tree in a receptacle located on the ATM solar shield.
The VT was also used for deployment of the VS clothesline attach
bracket and clothesline during SL-4.
The VS was provided to support removal and replacement of the
S082A and B film magazines at the ATM Sun End. Equipment located at
the VS included the S082A and B experiment access doors, handrails,
EVA lights, and the S082 film magazine temporary stowage container,
the VS clothesline bracket, the VS foot restraint platform, and the
S082A and B cameras and receptacles.
308
d. S082Aand B Film Access Doors - Film retrieval access
doors were provided at the VS for S082Aand B. These doors could be
openedwith one gloved hand, by rotating a handle with a mushroom
shaped pushbutton lock-lock. Friction hinges held the doors at any
desired point between the closed and open positions. The experiment
Sun End aperture doors, which in their closed position covered the
access doors, had to have been opened from Panel 160 at the VC before
the film access doors could be opened and the S082 film magazines
removed.
The S082Aaccess door performed nominally. The S082Bdoor also
performed nominally until the second EVAof SL-3 when the crewmanhad
difficulty pulling the door from the door well after unlocking. During
the third SL-3 EVAthe crewmanhad to place both knees on the canister
surface and pull the handle with both hands to free the stuck door.
The problem persisted throughout the other EVAsbut did not prevent
the crewmenfrom opening the door. During the SL-4 fourth EVA, the
crewmanhad to place his hand inside the aperture opposite the hinge
and pull the door open after exposure to the sunlight for several
minutes. This procedure had been suggested to the crew after I-G
simulations had been performed. Possible explanations for the anomaly
might be:
• Thermal warping of the door within the well
oIncomplete retraction of someof the four door latches
(S082Ahad two)
oAdherence of the rubber door seal caused by environmental
conditions.
The S082Aand B doors are generally acceptable. Before they
are used again, however, someprecautions should be taken to prevent
the sticking problem observed on the S082B. Either the hinge, latch-
ing mechanism, seal configuration, or a combination of these, should
be modified prior to future use.
309
insertion/removal tasks, visual and tactile feedback was provided.
Due to weight and volume requirements, however, alignment/insertion
guides were not provided to the degree found elsewhere.
The film magazine containers operated satisfactorily. Their
current design is sufficient to provide thermal and contamination
protection to film or samples during EVAoperations.
310
• _ i _ii
_!¸r k k r r r • , k •
except those at the DA were enclosed in a wire grid and contained a
glare shield. The DA lights were enclosed in a metal box with a
hole provided for directional lighting.
Two LSU clamps were located adjacent to the EVA hatch to facili-
tate life support umbilical management during EVA. The clamps was
made up of two jaws: one fixed, the other movable. The movable jaw
was spring loaded to maintain a slight clamping force on the LSU.
When not in use, the spring, being over-centered, maintained the
movable jaw in the "Open" position for easy insertion of the umbilical.
In the event that the LSU experienced side loads due to a crewman's
activity, the spring loaded jaw would open, freeing the LSU, and
preventing possible LSU damage due to its restraint in the clamp. The
LSU could also be manually released from the clamp. One LSU clamp
is located in each ATM workstation.
All equipment along the EVA path was designed without sharp
corners or edges which might damage the PGA in case of contact by the
crewman. All ATM equipment drawings of hardware along the EVA path
were evaluated to verify that EVA safety consideration had been reason-
ably satisfied, and that all drawings contained statements about the
minimum radius of corners and edges, the finishing process used, the
deburring of milled edges, and the potting or buffing of screw heads.
During EVA operations all translation route handrails were
adequate for crew translation. Lighting was also sufficient, and the
LSU clamps were adequate for umbilical management. This hardware may
be used on future EVA missions without modification.
311
C. Solar Array System (SAS) BeamDeployment
312
• What types of debris were preventing the SASWing
from deploying?
eWhich of the tools selected would be best for specific
cutting and prying jobs?
• What would be the most feasible approach angles for
attempting to cut the debris?
• If the debris were removed, what might be expected as the
result of SASWing dynamics?
• What hardware would be required for one-g and neutral
buoyancy testing?
313
• The remaining portion of the Meteoroid Shield was pushed
under the SASBeamand wrapped slightly around the edge
of the beamfrom the underside.
• There was a "strap" that looked like it contained a row
of bolts which had wrapped over the edge of the beam
fairing.
After the fly-around inspection, the crew soft docked to the
Multiple Docking Adapter (MDA). A review of the fly-around TV
transmission was then conducted at MSFCand JSC to determine the best
approach for attempting deployment of the remaining SASWing. Based
on this reivew, it was felt that the piece of metal bent over the SAS
Wing fairing was a piece of angle, which the crew would probably not
be able to cut but would have to bend in order to free the wing. It
was reco_nended that the tools be configured as follows:
• One pole with the shepherd's hook
• One pole with the cable cutter
• One pole with the mushroom and tether
314
i _
i i'I
_N CLEARANCE
2" TO 3" BOW BETWEEN
AT END OF STRAP
STRAP & SIDE OF BEAM
!
METEOROID SHIELD
_ER
BEAM
SOLAR WING
/ PARTIALLY
/.
DEPLOYED
41
, 7
Figure 168. SAS Beam and Debris Strap
I
315
o
o
g_
',.o
T-4
t_
r_
00
oN
I
201q TG
7075 T6
,_F MICROMETEOROiD
SHIELD
317
It was also predicted that if the strap were removed, the SAS
beamwould rise approximately two feet at that point on the beamand
would then stop because of frozen oil in the damper/actuator. The
beamwould then have to be pulled up with a force of approximately
15 ibs. (measured at beamend) to break the damper/actuator mounting
bracket in the beamhinge mechanism.
From the definition of the overall problem, it becameobvious
that four separate problem areas would have to be addressed:
• Translating one or two crewmanto the FAS area above the
SASbeamand possibly translating one crewmanto the
debris strap
• Restraining a crewmanat the FAS above the beamand possibly
restraining a crewmanin the strap area
• Cutting the strap or prying it loose
• Pulling the beamto an erect position
In order to study the SASwing problem more accurately, the back-
up SASWing was shipped from TRWto MSFC. A review of this wing was
conducted on June 2, 1973. It was learned that what were thought to
have been scratch marks on the top of the beamcaused by the debris
strap were actually two rows of bolts. Also, two bend-relief holes
were found on the base of the vent module. These relief holes were
later selected as tether attach points for manual beamdeployment.
318
discone atenna area. The crewman could hook the cable cutter snugly
on the strap and use the pole as a handrail while he translated to
the strap, with the other crewman holding the mushroom end.
Methods for restraining the EVA crewmen at the FAS ring and at
the debris strap also had to be developed. The crew restraint methods
identified for the FAS ring area were:
(a) Holding the discone antenna with one hand
while placing the
feet against the 02 bottles
(b) Using the OWS N 2 purge line at the FAS ring
as a handhold while placing the feet on the FAS ring
(c) Attaching the OWS EVA foot restraints at the
FAS ring with C-clamps and using this as the only restraint
The first and second options had the advantage of requiring no
equipment setup. The first also had the advantage of being directly
above the strap on the SAS Beam. The third option would offer better
restraint but would require a difficult setup task.
The problem of restraining a crewman at the SAS Beam appeared to
be a more serious problem because of the possibility of sharp edges
on the debris strap and on the remaining section of Micrometeoroid
Shield. The problem solution was also hampered by the fact that there
was no equipment on the SAS Beam that could be used as a handhold or
foot restraint. Therefore, any crew restraint would have to be extend-
ed by the crewman at the FAS.
The restraint methods proposed for solution of this problem
included:
(a) Use of the translation aid from the FAS ring
to the SAS Beam strap as a handhold at the strap area. This transla-
•i
tion aid could be the fireman's pole, extended FTB, or SEVA tool poles
and sail poles. The last option had the advantage of being attached
at the strap end by mounting the cable cutter to a SEVA tool pole and
then securing the cable cutter around the debris strap.
(b) Attachment of the OWS EVA foot restraint to
the fireman's pole and letting the crewman at the debris strap use it
as a single stability aid. This method would allow use of both hands,
but it had the disadvantage of requiring ingress of the foot restraint
with no handholds. Second, it would require the EVA crewman at the
FAS ring to manage the fireman's pole with extreme care, and, finally,
the fireman's pole was only 21-ft. long, while the debris strap was
25-ft. below the FAS ring.
319
Figure 172. Cable Cutter
320
(b) Pry Bar - The pry bar had the advantages of
being simple to use, small, easily carried by a crewman, and operable
one handed. However, the crewmanwouldhave to work very close to the
strap and other debris, thereby exposing his PGAto any sharp edges
that might be present. Also, if the bolts in the strap were suffici-
ently embeddedinto the SASBeamskin, the crewmanmight not be able
to generate enough force to move the strap. The strap also might spring
back into the SASsolar panels after being pried from the beam.
(c) Bone Saw - The dental kit bone saw, a flexible
length of wire with rings at each end and cutting teeth bonded along
the wire surface, had the advantage of being small and easy to carry.
In addition, it was found to be a good cutting tool, provided that the
crewmancould be restrained sufficiently. The bone saw could be used
with the crewman's thumbs in the rings at each end, or it could be
mounted between two standoffs on a pole and used as a hand saw.
(d) Universal Tool - The universal tool (Figure
173) could be mounted on the end of the SEVAtool poles (3) and twin
sail poles (2) and could be used by the crewmanat the FAS to grasp
the debris strap and pull it loose. However, this method did not work
EVA. the SEVAand probably would not be successful during another
during
• Pull line snug at A-frame end using the cleat on the apex
hook (Figure 174).
• Place feet on SAS Beam forward fairing (near hinge) and lift
line until damper bracket breaks and beam deploys (Figure 176).
321
Figure 173. Universal Tool
322
APOLLO
SMALL HOOK
•_ ',31' 10" _ /TYP 2 PLACES)
PBI FROM
SEVA SAIL SEVA SAIL •
CLOTHESLINE i
APEX HOOK
AT ATM I
CONNECTION
...':,-"t"
_____------"__: ' ' ' %>
: L
i i
i,_llcll_rrllollolil lll.lui ,-_
ii I!=
' ill!
I illl
323
r- --
s_IOH 7_!I_2 _InpoI_ InCA n._ p_ll_]SUl s_IOOH N]._M nmeK SVg
k
._.. -k _
¢xl
oh
(b) Use of OWS Squeezer Bag - A second method
of deploying the SAS Beam involved using the OWS washcloth squeezer
bag inflated with nitrogen from the portable water tank. This involved
the IVA tasks of pressurizing the gas side of the portable water tank
to 35 psia from the pressure panel on the water bottle ring in the
OWS and attaching the 25 ft. condensate dump hose and the 15 ft.
condensate tank vacuum hose between the squeezer bag and the water
tank. The EVA procedures necessary to deploy the SAS Beam by this
method included:
e Install folded bag under SAS Beam near hinge; retreat to
FAS ring.
• Crack valve on water tank to pressurize bag.
• Observe SAS movement and close valve as soon as release is
assured.
The squeezer was tested and found to be capable of exerting enough
force to break the damper bracket and deploy the SAS Beam. However,
it involved complex crew procedures and detailed equipment setup.
325
Another neutral buoyancy run was conducted on June i, 1973, to
study various debris removal tools and the manual SASBeamdeployment
method.
On June 2, the neutral buoyancy SASsimulation hardware was
reconfigured based on information received from the crew debriefing on
June i, and on review of the flight back-up SAS(shipped to MSFCfrom
TRW).
An EVAHardware/Equipment Bench Review and EVAprep was also
held at the Neutral Buoyancy Simulator. A suited simulation run was
madethat afternoon with two Skylab crewmenas subjects. Preliminary
EVAcrew procedures were used, and translation of crewmenand equipment
went muchmore smoothly. The cable cutters with five pole segments
and mushroomhead were then the prime method for translating the SAS
work area. Cable cutters were attached to the debris strap and the
mushroomend was tethered to the discone antenna bracket at the FAS
work area. It was noted that more work was needed on methods of
crew restraint and EVApreparation. Total EVAtime was approximately
2 hours, 25 minutes.
On June 3, 1973, another bench review was held with the Skylab
crewmendoing their ownEVApreparation, subsequent to which the final
neutral buoyancy simulation run was madeusing near final EVAprocedures.
The suited run went smoothly. Equipment and hardware transfer was well
executed. The crew debriefing on June I, and review of the flight
backup SASWing provided data that was used to develop better crew
restraints at the debris strap work area. Attaching the cable cutters
to the debris strap was successful on the second attempt. The crewman
tethered himself to the cutting pole with a chest tether during trans-
lation while taking the PBI tether (BET) which he attached to the two
aft corners of the vent module (bend-relief cutouts). The other end
was attached to the discone antenna launch support truss on the deploy-
ment assembly. The crewman's chest tether, attached to the cutter
pole, provided adequate restraint during translation. Restraint at
the work area was provided by the waist tether remaining attached to
the cutting pole and using the BETas a handhold after being attached
to the relief cutouts in the aft corners of the vent module. The three
debris removal tools (cable cutters, pry bar and bone saw) were used,
and it was decided that the tool chosen for debris removal would be a
real-time option of the SL-2 crew.
326
i¸ :
327
SASBeamdeployment was accomplished with very little deviation
from the procedure sent to the crew. Equipment setup (IVA) and pole
assembly (EVA) were performed without any problems or changes to the
recommendedprocedures. Translation to the discone antenna boomalso
presented no problems. Attachment of the cable cutter to the debris
strap was difficult and required several attempts. However, this had
been expected due to the similar difficulty encountered during the
neutral buoyancy tests. The Commandertranslated to the debris strap
area, and attached one BEThook to the vent module relief hole with
moderate difficulty. He was unable to attach the second hook. In
anticipation of this problem, "figure-eight" knits had been tied in
the harness portion of the BETon either side of the loop forming the
end of the main tether (see Figure 174). This eliminated the require-
ment to have both tether hooks attached to the vent module. Lie then
returned to the FASarea.
Cutting the debris strap with the cable cutter provided some
exciting moments. With both crewmenat the FAS, the Science Pilot
attempted to pull the cable cutter rope to cut the debris strap.
After several pulls, the cutter jaws appeared to be spreading without
cutting the strap. The Commander,therefore, decided to translate to
the debris strap to examine the cutter jaws. Upon his reaching the
cutter scissors mechanism, however, the cutter severed the strap. When
this occurred, the cutter camefree from the strap; the SASBeamcame
up about two feet, and the BETbecameslack. This obviously resulted
in an unstable restraint situation for the Commander. He, therefore,
grabbed the BETand pulled himself to the FASwhile performing
"whifferdills" along the way. Although this particular operation was
not anticipated, it did not result in damageto the crewmenor hard-
ware, but it did prevent the crewmenfrom observing the initial SAS
Beamrelease.
The crewmenpulled the slack from the BeamErection Tether (BET),
and attempted to pull the SASBeamup by pulling on the BET from the
FAS. Whenthis was unsuccessful, the Commandertranslated to the
SASBeamhinge and lifted the BETto his shoulder facing the FAS. At
this point, the Science Pilot was also pulling the BET from the FAS.
Whenboth crewmenwere applying significant force to the BET, the beam
released causing slack in the BET. As both were using the BET for a
restraint, this resulted in another unstable restraint condition. This
was no serious problem, however, and they were soon restrained at the
discone antenna boomarea, but without benefit of having observed the
beamdeployment.
The return to the VF and disassembly and stowage of the SAS
deployment hardware in the Airlock Module went according to the proce-
dures with no difficulty.
Because this EVA is obviously not planned for other Skylab missions,
the crew did not commenton improvements that could be madeto the SAS
Beamdeployment equipment or procedures. They did_ however, recommend
a change in the EVAchecklist regarding the Airlock Module fire sensors.
Whenthe sun shone in the AMaft lock compartment, the fire sensors were
activated. This caused serious concern to the Pilot during the EVA.
Therefore, the crew recommendedthat these sensors be deactiviated
during future EVAs.
328
D. Twin Pole Sail Deployment
329
i ,ii!__ , _
REEFING LINES
BASE PLATE
ASSEMBLY
SAIL POLE
SAIL
330
provide a means of attaching the assembly to the vehicle structure.
In addition, the adjustable receptacles were hinged to allow position-
ing of the sail against the OWS after deployment. The assembly was
attached to the A-frame structure by two hinged clamps and mating
side braces. The clamps were positioned around the tubular A-frame
structure and torqued with the threaded end of the clamp and knurled
knob (Figure 180). Also attached to the base plate were alligator
clips for securing the clothesline after the sail was deployed. The
crew incurred no problems in using this piece of hardware.
331
% _:
i;' ¸,
v/:i
_i:i=i:i:ii_i:i'i_i_i:iiiiiiii
:4
M:i:ili:!!zi
332
:::+::::::
:::::::::i:!$i
333
e. Foot Restraint and Adapter Assembly, IOM50445-I - The
foot restraint and adapter plate assembly consisted of the workshop
portable foot restraint, located on board, and an adapter plate made
of stainless steel (Figure 183).
This assembly was required in order for the EVA crewman's lower
body to be adequately restrained in the proper attitude in the
structure of the A-frame on the ATM (from which EV2 could deploy and
adjust the sail).
334
Figure 183. Foot Restraint Adapter Plate
335
q
, _
336
hook was reversed which required the order of pallet
installation reversed from that given in the checklist.
• The crew encountered some difficulty in removing the
5 ft. sections of sail poles from the pallet. The elastic
bands holding the poles were placed behind the threaded
locking collars instead of on the collar. Because of
this, the poles needed to be rotated so the elastic would
roll up on the collar for easy removal. This problem
was encountered with both sail pole pallets.
• The folds in the sail during deployment had a tendency
/•\
to cling together. This was thought to have been due to
the tackiness of the painted surface. After receiving
/ photos of the SL-4 fly around, it appeared that the sail
had a memory due to the folding and packing of the sail in
the sail bag. The crew attempted to remove the folds
during deployment without complete success. However, the
sail covered the exposed area and served the purpose for
which it was designed.
oWhile assembling the poles, a twist in the clothesline was
encountered. The solution to this problem was to disjoin
two sections of poles and pass the line between them, then
reassemble the poles, thus removing the twist.
337
E. Other EVAActivities
338
m i
L
i ! ":_ X::/i !i i i
SAMPLE i_ ' ",_ o.,::." !
RZTURN ! i ", ..'::': i i
CONTAINERS
!i ! ", ..'::" i ,,"
\ il
.::......
........
i 'i
02 HANORAI
FOIL COLLECTOR
CUFF ASSEMgLIES (2)
FOIL STRIPS
(6 PLACES)
'CALIBRATIO,_SHIELDS
COLLECTOR MOUNTING
SPOOLS(z)
FOIL STRIPS
(6 _LACES)
339
The experiment apparatus consisted of a newly designed and built
adjustable EVA bracket, the coronagraph canister and camera, and an
occulting disc mounted on a boom (Figure 188). The EVA bracket was to
be mounted on a DA truss near the D-I handrail at the Fixed Airlock
Shroud workstation (VF).
Fbr the first EVA of SL-4, the T025 apparatus was mounted at the
VF. During camera operation, the shutter speed control knob became
loose. Only five photographs out of a planned 40 were obtained.
Instead of trying to repair the camera during EVA, the picture
taking sequence was stopped, and the equipment was returned (after
removal of the thermal blanket cover) to the AM. There, following the
EVA, the T025 hardware underwent troubleshooting, and the crew success-
fully repaired the shutter speed knob. The T025 hardware was used
during subsequent EVAs to obtain ultraviolet and visible photographs
of Kohoutek. Throughout the remaining three EVAs, no problems occurred
with operation of the camera or EVA bracket, and subsequent T025
experiment performance was without incident.
340
T025 EVA BRACKET
DA STRUT
CORONAGRAPH INSTRUMENTS
Figure 188. T025 EVA Configuration
along with the preceding $201 and T025 experiments, was mounted on the
DA truss on the opposite side of the truss from the other two experi-
ments. A special EVA bracket was designed and installed on the S020
equipment. S020 was successfully performed on three SL-4 EVAs with
exposures up to one hour being obtained.
During deployment of S020, the crew experienced slight difficulty
in attaching the mount to the DA truss. The mount twisted during the
tightening operation. In addition, the ball joint on the mount was
difficult to adjust, and the crew felt a larger ball could have made
adjustments easier.
The SL-4 crew reported a number of pinholes in each of the two
filters during preparation for the final EVA. It was felt, however,
that the size of the holes as described would not allow enough light
through to cause any problems.
341
I)EPLOY)_.NT AP,M R _ , XV
_N_\NIII_.._9_'/_?b_ 2-'-s_rAczs
_Ic_)
CASSR'r_ES OPEN
_$BIELD _tlH
RFtI_S ION
i
V
342
$149 EVA ADAPTER BRACKET
(BOTTOM VIEW) (SEE FIGURE
E]CI'ENS ION. ).
_- '...........
_ -S149 DETECTOR ASSEMBLY
%
• CONFIGURATION
•. .__ i k IN ALTERNATE EVA ATM
(/•:!
%
-z +Y (VZ_CLE_OD_AXlS)
Figure 191. S149 Mounting Configuration
343
latch and the canister. These shims, along with the latch, two screws,
and two lockwashers, were to be retrieved to prevent them from float-
ing into the ATMcanister or distracting the star tracker; on-board
tape was selected to affix the various parts to the ATMSun End (VS)
film tree for return to the Airlock Module.
Another question arose with regard to the position of the S055
ramp latch relative to the crewmanin the Sun End workstation (VS)
foot restraints. With the experiment canister in position for S082A
and B film replacement, the crewmancould not reach the S055 ramp latch.
The ATMmission support mockupwas used to determine the roll angle
(in this case, +3000 arc min) on the ATMControl and Display Panel
(Counter No. i) which would position the ramp latch optimally for the
crewman.
During the first EVA, after nominal film retrieval operation at
the Sun End, the experiment canister was rolled to +3000 arc min for
removal of the S055 ramp latch. The door was cycled open and closed
several times, and a slight, jerky motion was noticed as the door
engaged and disengaged the ramp latch. The bolts, washers, ramp
latch, and two shims were then retrieved and mounted under the tape on
the VS tree. One shim escaped in a direction away from the canister
surface. The other ramp latch gear was successfully returned to the
Airlock Module taped to the Sun End film tree.
The latch was returned with the crew for optical testing of the
S-13G paint. Except for the difficulty of gathering eight small
pieces of gear simultaneously, no problems occurred. After removal
of the ramp latch, the door was cycled open and closed. No binding or
jerking motions were observed.
Later, during the SL-3 Mission, the S056 and S082Adoors began
to malfunction, exhibiting the samesymptomsas the S055 door had
earlier. Because of that similarity, and because of the disappearance
of the sticking problem with the S055 door after latch removal, it
was decided to remove the ramp latches on the S056 and S082Adoors.
As the latches, bolts, and shims were identical to those on S055, the
only change in the removal procedure was the recommendedroll position
of the experiment canister. The ATMMission Support Mockupwas again
used to determine the best canister roll angles. These were found to
be +3000 for S056 and -7200 for S082A. The procedures sent to the
crew were identical to the procedures sent for S055 latch removal.
During the third EVA, after nominal Sun End film retrieval tasks,
the experiment canister was rolled to +3000 arc min for S056 ramp latch
removal. The door was cycled open and closed for crew observation.
A jerky motion was noticed during opening and closing. Removalwas
performed with no difficulty. Nevertheless, as the ramp latch gear was
being taped to the Sun End film tree, all four shims and one screw
departed into their own near-Skylab trajectories.
The canister was then positioned for removal of the 8082A ramp
latch. The door was cycled open and closed. The samejerky motion
noticed on S056was also observed during S082Adoor movement. During
removal of the first latch screw, the crewmanremoved one foot from
the foot restraint to extend his reach envelope. During removal of the
second screw, the crewmanremovedboth feet. All latch gear was retrieved
and taped to the VS tree.
344
The major problem associated with the removal of the ramp latches
was the collection and stowage of the shims, bolts, washers, and latches
after their removal. The use of tape to restrain these pieces (8 per
latch) was not totally successful; four shims and two bolts were lost.
Potentially, each of these hardware pieces, unrestrained, could have
interfered with star tracker operation, ATMobservations, etc. A
dependable stowage method should be developed for use in future EV
operations in instances where small hardware must be removed and re-
trieved.
345
k f?
Two solutions were proposed. The planned method of manually
opening the aperture door at the Canister Sun End during an EVA was
initially proposed. This procedure had been established before the
mission as a contingency procedure, and the crew had been trained for
it. The procedure involved removing a pin from the •door "hub" (the
pin was the only solid connection between the door axle and the door
itself). When the pin was withdrawn (by rotating its "tee" handle),
the door and the axle were free to rotate independently. This allowed
the door to be held open by a latch without affecting the rest of the
door actuation system. The disadvantages were that the open door
would allow contamination to enter the ATM experiment canister, that
it presented a potential thermal problem, and that the procedure was
irreversible (it was virtually impossible to reinsert the pin once it
had been withdrawn). There was also some doubt as to whether or not
the door had actually failed. The alternate procedure consisted of
jamming the S054 "DOOR OPEN" switch (on the ATM C&D Console) to the
open position with either a pencil or a section of wire, thereby
preventing the "DOOR SHUT" command from closing the door. This method
would have allowed more time for evaluating the problem, and for
developing a solution which did not irrevocably lock the door open.
But, eventually, the original plan was chosen and was included in
planning for the first EVA.
During the SL-2 first EVA, after the Solar Array System beam
had been deployed, EV2 translated to the ATM Sun End to open the
S054 door. The door pin was unscrewed and the door was rotated and
latched open with no difficulty.
On SL-4, a similar problem occurred with the S082A aperture
door, and during the third EVA, it too, was latched open. No pKoblems
occurred with the opening of either the S054 or S082A doors.
346
ii. Rate Gyro Package Cable Installation - In the early part
of the SL-2 mission, the orbital attitude rate gyros had begun to give
faulty and sometimes erratic indications. To correct this problem,
an extra set of gyros was assembled into a Rate Gyro Package (RGP)
"Six Pac_' and was flown aboard SL-3. The "Six Pack" was to be
mounted in the Multiple Docking Adapter (MDA). To integrate these rate
gyros into the cluster attitude control system, however, a new cable
would have to be installed between an ATM trunnion plate and the ATM
Workshop Computer Interface Unit (WCIU). A set of procedures was
provided in the Saturn Workshop (SWS) Cue Cards. Special connectors
with extended backshells that enabled the EVA crewman to mate the
connectors by hand were used on the RGP cable. A set of connector
pliers was also developed for use in disconnecting the old RGP cable.
These pliers were similar to standard connector pliers, but had a
tether ring and a handle orientation compatible with the EVA gloves.
The RGP cable was installed during the SL-3 second EVA. The
installation required that the Skylab attitude control system be
disabled from the time the connections were broken at the ATM trunnion
until after the connections were complete. Because the area
around the WCIU and the Deployment Assembly trunnion area were not
illuminated by EVA lights, the crew inspected both areas during the
first dayside pass to verify crew restraint methods, connector acces-
sibility, and the cable routing scheme. The connector pliers were
fitted to the connectors and found to be the proper size. The adjacent
wire bundles were then inspected and found to allow sufficient clear-
ance for removing the connectors. Body restraint was also determined
to be satisfactory at both locations. The cable routing scheme was
discussed among the crewmen and was not considered to be a problem.
Other EVA activities were subsequently performed during the orbital
night and are discussed in the sections below.
Prior to the next sunrise, the cable connection was made at the
trunnion, the cable was routed to the ATM WCIU area, and EV2 restrained
himself at the WCIU for the cable installation operations. Immediately
after sunrise, he began breaking and making the connections at the
WCIU and trunnion while EV3 read the installation procedures. Less than
four minutes later, all connections had been made. No problems were
encountered with use of the tool, connector backshells, crew restraint,
or positioning of the connectors.
347
During the second EVAof SL-2, EV2 installed the JSC sail sample
to a truss near the ATMdeployment motor. As no foot restraints were
available, and as wrapping a flimsy article around a truss is essenti-
ally a two-hand task, crew stability was severely limited. But, with
EVI holding EV2's feet, the sample was eventually deployed. If such
tasks are required during future EVAs, adequate restraints should be
provided.
During the third EVAof SL-3, the sample was retrieved. No prob-
lems occurred.
In order to obtain more data on the effects of the space environ-
ment on the JSC parasol material, two additional material samples were
carried aboard SL-3. These were attached to old crew procedures Cue
Cards, and the Cue Cards were mounted on a clipboard attached to a
universal mount. This mount could be attached to an EVAhandrail and
adjusted to expose the material samples to direct sunlight.
During the EVA, EV2 attached the universal mount to the S-IO hand-
rail while his feet were held by EVl. Except for the lack of adequate
restraint, no problems occurred.
The samples were retrieved during the third SL-4 EVAwithout
difficulty.
348
/
/
, 413 _ (,.z.,) I
,+,.<,.,+, ,+,+, i ..... I ip 0"+°
|
I Octet,ores ,t ue I
I (I.Z+i} ' II,O _I ,,Sm.L_,MPtt I, i ,
IT+S • l+
. !
IsZ4) *OF I
I-' , ,S_+m _O, r---'*'l <A.z-, I I I vm---._--.---s
. I? ,_u i ? I P
I-I,:'+.+,0IIM II I
11.I-5}
I ,,,,,,+°,- I
(l Z-lO) I I + AI,S FU_TXOI_L
, I I +" mOLL+ --
II
•
I
I |I J J I C.[C, (i Z-A) I I L" ' _'E$ -- I I
, " I ms mw,mtmtv[ _ t !
I+U I +_.J | | ' t'? r" PITCH
POt I I-+RoLLPotI
I_+, ,,.,-,,
Z AXIS Fu_:T,ON_.
I ,,._°,-- I _ 13
I I ,SSHO.mOI / ,ss.o._D I
Is., ..,.+ 0.,, ,0 _ t,.+-,,) I IPROBLEmWASI I ! L I
t+_+"+" ,+'+ I , ' I ,AOCO++mCTIOm
I + + .
• .. + ,,o, " t ., • , I l.m , I _,,, _ ,,,,_, i '
I POIWAS SHOeIEO I I _+.+-m I 'l.m I I `'+ I I ..I
I | L-..--. .J I Z AxIS pteom.._ l I I
-- " I TtSt (*,z.s) I | l ....
l'-+',,,s,,,o,,_<+ I I"?,,
,, ,, L,.,+o, I _++''m I I I'++'m l
[Tts, (,.+-*_ l | hm.® to+, -- I " I
I C,_I mT+P._ OX,Vi _ l,Sl I | I .
l mete,+ j._ L_. t'-" m_c+..eamm'o,s I lzol , l'z+l " '
'KS ,F 5 ,A,LS S[_ (tl,Z-S)
++++t ,,,, _,0, / I I%+.,,., I r::;i+,.,s,,s, I
TTTi " -- • l..'-'" I._ l"""" I.+
LJ i _-- i-- ,s_ ,.,,s_mo, _ I ,s,.to.,,+m_0oo,
t-+-C_3
" -- " Ts
[ CL_IUI U_ {i.Jt-IS) V_5 [
350
15. S054 Filter Wheel Positioning - During SL-4, the S054 filter
wheel jammed. Neither ground commands nor onboard commands from the
ATM Control Panel could move the wheel. Since telemetry indicated
that the wheel was jammed between two filters, film data would be
severely degraded until the wheel was positioned at one of the six
filters.
An examination of the ATM back-up unit indicated that the filter
wheel could be turned manually be a crewman at the ATM Center Work-
station (VC) with a long blade screwdriver. However, several signifi-
cant problems had to be solved.
eFirst, none of the SL-4 crewmen had ever seen the filter
wheel or the surrounding hardware, nor were there on-board
photographs or drawings.
• Second, during the EVA, the crewman would not be able to
see the filter wheel without the aid of a mirror and
additional lighting.
The procedure sent to the crew was to: (i) remove the exposed
S054 film magazine from the experiment canister receptacle at the VC,
(2) place a new film magazine in the receptacle with a shutter over-
ride mechanism attached to the base (this latched the shutter open to
permit access to the filter wheel), (3) remove the new film magazine,
and (4) insert the screwdriver through the shutter opening into the
filter wheel, while using the mirror and light to provide adequate
visibility. The crew was then to insert the screwdriver blade into a
filter and force the wheel to the right until another filter could be
seen on the left. This procedure was to be repeated until the blank
filter was positioned in the optical path.
During the second EVA, this task was performed. The used film
magazine was removed, and the new magazine with the shutter override
mechanism was installed, opening the shutter. The film magazine was
removed and, as the filter wheel was being turned, the shutter unexpect-
edly closed on the screwdriver blade. After repeated attempts to
reopen the shutter failed (due to distortion of the blades), and after
consultation with ground controllers, the blades were forced apart,
clear of the light path. EV2 then proceeded with the rotation of the
filter wheel until the blank position was centered. The film magazine
was then replaced.
Although this task was difficult and the crew had not been
trained, the repair operations were successfully performed.
351
Vll. TESTDATA
A. Waste Management
352
ii!iii
ili
¸¸:! iii? ii!i
Subsequent to the CDR, the one- and two-bag schemes were cancel-
led and the separator system implemented.
353
• Design of a hard-metal cone-reciever in place of the old
teflon folded cone construction, and associated inlet
hose.
• Design of a combination urine sample bag holder and
crimper/cutter assembly for use in sampling and sealing
the sample.
• Design of a urine bag box support mechanismcapable through
use of sqeezer handles of applying additional pressure on
the urine collection bag to assure adequate filling of the
urine sample bags. This device is also used in conjunction
with the micrometer volumetric plate for mechanical volume
measuring.
• Modification and simplification of the urine drawer to
accommodatethe new hardware.
• Design of new adapters for use with interface equipment
such as the UTCA'sand the urine dumpsystem.
There are no open action items from the Preliminary and Critical
Design Reviews.
2. Subsystem Conclusions
a. Waste Processor
354
(3) Long Duration Operational Capability - The unit
as a whole had been subjected to life testing of 140-cycles of
operation of each of the six processing chambers to simulate one
chamber operation per day during a 28-day mission and two 56-day
missions. A cycle involved opening and closing the chamber door,
vent valve, and locking handle; the pressure plate assembly and
damper were also operated by virtue of their connection to the
chamberdoor. Somefailures of indicator lamp filaments (each
lamp had two filaments) and timer skipping of i/2-hour increments
occurred. Voltage surges due to the test set-up were believed
responsible for lamp filament failures.
Timers were reworked to the production configuration, employ-
ing aluminum rather than stainless gears for reduced inertia. A
second 140-cycle operational life test was completed.
b. Collection Module
355
(a) Blower Assembly - Two endurance tests were
run on the blower, one for 2000-hours and another for 630-hours,
successfully, although the requirement was 250-hours.
(b) Odor Control Filter Development tests
showedthat the odor control filter had an operational lifetime in
excess of 54-days or nearly twice the lifetime required (28 days).
These tests were run absolutely dry which madethe results extremely
conservative. The odor control filter did demonstrate a greater life
expectancy during qualification.
(c) Time Delay Relay - Any one time delay relay
was required to undergo 840 cycles while in orbit. During qualifica-
tion testing, two units were subjected to 3000-cycles each without
deleterious effects. This was well in excess of the requirement.
356
(3) Long Duration Operational Capability - The opera-
tional life requirement of the power module was 250-hours of running
time with a minimumof 7000-cycles. The operational life require-
ment of the vacuumcleaner was a minimumof 980-cycles for a total
running time of 94-hours.
This latter operational life requirement was demonstrated in
the vacuumcleaner qualification test. In addition, the life cycle
test on the supplier prototype vacuumcleaner verified that the unit
was capable of meeting the specified operational life requirements.
The vacuumcleaner was operated for 1963-cycles of 6-minutes each;
the canister was removed and reinstalled on the power module i00
times; the hose from the vacuumcleaner was attached and detached
980 times; the accessory tools were attached and detached at the
vacuumcleaner, and at the end of the hose, a total of 980 times at
each location (the cycling was divided evenly between the three tool
attachment); the debris bag was changed a total of 280 times.
Two endurance tests were run on the blower, the most critical
time dependent item in the power module.
d. Collection Bags
357
Ca)The Fecal and Fecal Contingency Bag demon-
strated:
• Their ability to collect in a zero-g
environment.
• Their ability to prevent bacteria con-
tamination from escaping into the
atmosphere during collection, mass
measurement and processing.
eTheir capability to collect the maximum
required volume of feces, diarrhea and
vomitus.
• Their compatibility with the operational
requirements of the IB79136-I Waste
Processor Module.
• Their capability to provide sanitary
conditions for the collection, retention
and sealing of feces, diarrhea and
vomitus.
• Their ability to prevent mixing of and
cross-contamination of collected feces,
diarrhea and vomitus.
• Their capability to be disposed of through
the trash airlock and withstand the air-
lock depressurization.
(b) The Debris Collection Bag:
• Demonstrated the ability to contain
waste matter particles and liquid while
installed in the Vacuum Cleaner with the
power module shut-off.
• Provided sanitary conditions for the
collection, retention and sealing of
debris by the crewman.
• Demonstrated its ability to prevent
bacteria contamination from escaping
into the atmosphere.
• Demonstrated its ability to interface
with the vacuum cleaner interlock to
prevent operation unless a bag is
installed.
• The capability to collect 350 ml and con-
tain liquids at 20 inches of water
pressure with no leakage.
• The capability to be disposed of through
the trash airlock and withstand the air-
lock depressurization.
358
(2) Summary of Open Problems and Plans of Corrective
Actions - There were no open problems or plans for corrective action
associated with the Collection Bags. All problems generated during
the development and design phase were resolved satisfactorily.
359
e. Centrifugal Urine Separator
(i) Summaryof Capabilities Versus Design Require-
ments - Based on the successful completion of all special feasibility
testing, Design Verification Testing, and Production Acceptance Test-
ing of each unit, it was concluded that the CUSAwas compliant with
all of the applicable SCDdesign requirements.
(2) Open Problem and Resolution Summary- None
3. Subsystem Certification
360
(4) The materials used in the WMSwere compatible with
crew safety.
ii_i_
(5) The methods used in the WMSwere compatible with
crew safety.
361
The Skylab hardware, beside incorporating all the parameters
established during the development program, had been subjected to
severe laboratory tests such as vibration and cycling to evaluate
its flight worthiness.
All flight units underwent a comprehensive acceptance test before
being installed.
Design safety criteria was emphasizedand carefully monitored
during the design phase. Safety features inherent in the design of
the collector module were:
(a) Supports and restraints safety retained the
crewmanin position during collection in zero-G.
(b) Noxious odors and gases were filtered out of
the collection airstream by an odor control filter.
(c) Fecal bacteria were prevented from escaping
into the Skylab atmosphere.
(d) All controls were guarded against inadvertent
actuation.
(e) Shock hazards were eliminated by the use of
low voltage.
(f) Redundancy, spares, and the ease of replace-
ment enhanced the safety and reliability of the collector.
d. VacuumCleaner and PowerModule
362
(d) Electrical fire hazards were eliminated by
design and construction under strict Quality Control supervision.
e. Collection Bags
363
Note: Redesign of the urine system from 2000 ml capacity to
4000 ml capacity shortened someof the testing. This testing was
picked up later by HS-90.
The portable vacuumcleaner, waste processor, stowed urine
separator, urine dumpcompartment, fecal bag dispenser bag bundles,
and collection bag return assembly all successfully passed their
individual qualification test requirements with no failures or
problems noted. Each specimen tested demonstrated satisfactory
performance and compliance with its design requirements.
364
B. Whole Body Shower
365
c. KSCTesting - The KSCactivity consisted of leak
checking the shower, the inter-connect tubing, and the pump. The
pumpwas functionally verified by operation and the whole system was
stowed aboard the OWS. The testing was completed and all results
were satisfactory.
366
C. Suit Drying
367
b. Problem - During the initial ten-hour functional test
where the test chamber was controlled at 83_F, the power module
electronic controller overheated.
6. Subsystem Conclusions
368
7. Subsystem Certification
369
D. Stowage
370
Six (6) procedure change requests (PCR's) were written due to
stowage changes. Three (3) bench reviews were conducted with crew
participation and all componentsor representative samples were
reviewed. There were 1,255 deviations written and 231 IDRs generated
during the total test run. None of these were any major problem and
all were closed or upgraded to DRs.
All test objectives of this sequence were satisfied and the test
was acceptable.
371
E. Crew Systems
372
/
• Verification of applicable mechanical and certain electrical
functions of certain stowed and installed equipment, including
experiments at in-flight using locations within the OWS
module.
• Verification of fit check and/or functional interface within
the OWSmodule of certain equipment launched in other vehicles
and designated for temporary or permanent OWSmodule occupancy.
• Verification of selected critical tool interfaces.
• Verification of selected in-flight maintenance tasks using
orbital spares.
• Demonstrate and verify functional performance of designated
Habitability Support System (HSS) operations as comprised by
the test environment (IG, 14.7 psia, etc.).
373
-i_,,,i-i
c
APPROVAL
MSFCSKYLABCREW
SYSTEMS
MISSIONEVALUATION
By
Man-SystemIntegration Branch
The information in this report has been reviewed for security class-
ification. Review of any information concerning Department of Defense or
Atomic Energy Commissionprograms has been madeby the MSFCSecurity Class-
ification Officer. This report, in its entirety, has been determined to
be unclassified.
This document has been reviewed and approved for technical accuracy.
H. H. WATTERS R. ISE
Chief, Man-SyStem Integration Branch Manager, Skylab Program Office
H. F o KURTZ _
H. E. THOMASON
Dir., Systems Analysis & Integration Laboratory
374