Piping Guide
Piping Guide
Piping Guide
2) Globe Valve
3) Check Valve (Non Return Valve)
4) Ball Valve
5) Butterfly Valve
6) Diaframe Valve
7) Plug Valve
2) Slipon Flange Do
A GENERAL PURPOSE
1) Control Valves (Globe, Ball, Butterfly)
2) On/Off Valves (Ball, Butterfly)
3) Relief Valves (Pressure, Thermal)
4) Rapture Disc
5) Restriction Orifice
E.1 DRAWINGS
1) Study Layout
2) General Arrangement Drawings
3) Piping And Instrument Diagrames
4) Sectional Layouts
5) Civil Layouts
6) Equipment Layouts
7) Fabrication Details Drawing
8) Foudation Details Drawings
9) Structural Layout
10) Isometrics
11) Piping Details Layout
12) Nozzle Orientations
13) Plot Plan
14) Flow Diagrame
Constructability to ensure no obstruction to transportation, lifting & erection of equipment due to adjacent
plant, structures or equipment and compliance to sequenced construction plan.
Potential late delivery of large equipment items to avoid serious impact on construction schedule.
One overall site plan for the entire complex, interconnecting piperacks and their relative locations to be
made.
Process units and offplot facilities, to be constructed to common schedule to be grouped and located to
ensure minimum impact from and to the operating plant during construction for later phases.
Prevailing wind direction to be considered for special cases.
For e.g., Flares for the refinery to be located upwind of the process units.
Layout of the tankage area to suit the flow of products and feed stocks with the pumps stations located
outside of the bunded area.
Roads to be provided around the tanks for access to all areas for maintenance & fire fighting.
Unit Plot Plan
One unit plot plan for each process unit.
Furnaces and boilers to be located at plot boundaries for ease of access. Adequate dropout
and swinging space for tube pulling by mobile crane.
Fired heaters to be located upwind of process units. In congested process areas, heater
locations to provide the lowest risk of fire or explosion.
Exchangers to be with channel end away from piperacks to facilitate tube bundle removal
Pumps handling flammable materials not to be located below piperacks but to be placed
with centreline of discharge at min. 1.5 m from the centre line of pipework column.
Horizontal vessels to be located to minimise piping runs & to be lined up with their
tangents on a common locating line.
Reactors to be located for ease of access during catalyst unloading and loading
operations. Space to be provided for cranes and storage of spent and new catalyst.
Pipe Stress Analysis
Purpose
To ensure that piping is routed and supported so that no damage occurs to either the pipe or
associated equipment due to the effects of thermal expansion or contraction, or loads resulting from
weight, pressure, wind earthquake, pulsation, shock, foundation settlement, etc.
Procedure
Ensuring compliance to all Code, Client and Inspection Authority requirements pertaining to Piping
Stress Analysis.
Check for flange leakage where bending moments are large, including flanged connections at
equipment.
Finalising the location of spring supports with required loads and movements on the Stress sketch.
Checking position of fixed and sliding supports of heat exchangers, horizontal drums, etc.
Pipe rack widths, bent spacing and top of support elevation of main pipe racks.
Allocation of space for electrical, instrument racks, analyser houses, switchgear, and utility hose
stations.
Elevations of structural levels and extent of platforms, ladders and stairs required.
Contents of Piping Layout
Equipment co-ordinates.
Elevations (Piping, Equipment, Platforms, etc.).
Line No. Identification and Flow Arrow.
Instrument Identification
Match lines.
Drawing Continuation References.
Key Plan Identification.
Complete "Holds" List.
Reference Drawings.
Adequate information for locating & identifying pipe supports welded to shop fabricated pipework.
Methodology
Shop and field isometrics to be extracted/drawn & self-contained within a model base, plant or unit as
defined at start of job.
Non-CAD Isometrics
– Manually prepared on Isometric Sheet.
– Both dimensional and P&ID checks to be done.
– Material to be manually entered.
Contents of Piping Isometrics
Line Number & Size
Pipe Classification
Direction of Flow
Orifice Assemblies
Instrument Connections
Sample Points
Dummy Legs
Cold Pull
Special Line Features, such as Fall, Reinforcing Pads, Weep Holes, Welded Lugs, etc.
Responsibility
Lead Piping Engineer to schedule and co-ordinate all piping material take-off activities and material
requisitioning.
Civil Group to give take-off of underground carbon steel non-pressure piping using the appropriate
piping class.
Instrument Group to give take-off of all instrument piping beyond the primary (root) block valve
(except at level instruments).
Electrical Group to give take-off of all electrical cable duct piping.
Piping Materials Engineer to transmit a summary of all tubing and tubing fittings requirements to
Instrument Group for requisitioning.
Material Control
Initial material take off from :
– Completed preliminary line routings in the CAD model
– Manual take off from P&IDs
Total forecast material requirements including working surplus and contingency form the basis of
the Bulk Material Requisitions.
Frequency & timing of material extractions from CAD model & manual MTO ensure that bulk
material status is concurrent with design.
Field material control is possible as the data within the piping material control programme is
downloaded to Procurement Tracking System.
Material requisitions issued to procurement for enquiry/ purchase.
MR quantities issued for purchase (initial & at each revision) are downloaded to Procurement
Tracking System.
Statutory Requirements
Applicable Codes
International piping codes and standards accepted in India
– ASME/ANSI B31.1, “Power Piping”
– ASME/ANSI B31.3, “Chemical Plant and Petroleum Refinery Piping”
Oil Industry Safety Directorate,Standard 118.
– Layout & spacing of roads,buildings,storage tanks and all equipment
Authority Approval
Indian Boiler Regulations (IBR)
– Materials and fabrication associated with steam and boiler feed systems.
Chief Controller of Explosives. (CCOE)
– All Plot Plans for approval together with safety radii from various sources. (Hazardous Area
Drawings).
Tariff Advisory Committee (TAC)
– Fire protection system & material selection .
.