FSE215
Concrete tunnels Skärholmen
BUILDING POLICY
2016-02-01
2Z140002-FSE215
Content
GENERAL MANDATE AND ............................................. contract ........ 4
1 BRIEF measuring technical description ............................................... ........................ 4
1.1 Contractor's supply of instruments, equipment and surfaces during the planning and construction stage as well
as the warranty period. ............................................. 4
2 Basic technical requirements ............................................... ........................................... 4
2.1 Reference ................................................. .................................................. 5
2.1.1 Coordinate and height system .............................................. .................................. 5
2.1.2 Reference system for satellite measurement ............................................... .................... 5
2.2 Transformations, fitting and over behalf ............................................. ... 5
2.3 Control / testing instruments and associated equipment .......................... 5
2.4 Checking the supplied core network .............................................. .................... 5
3 Ask the client ............................................... ............................................ 6
3.1 Delivery of materials supplied .............................................. .................... 6
3.2 Core network in plan and elevation ............................................. ......................................... 6
3.2.1 Core network in the plan ............................................... .................................................. .... 6
3.2.2 Core network in height ............................................... .................................................. .... 6
3.2.3 GNSS - Satellite Measuring ............................................... ....................................... 6
3.2.4 Local permanent reference station GNSS ............................................. ......... 7
3.2.5 Local temporary reference station GNSS ............................................. ............... 7
3.2.6 Network RTK service ............................................... .................................................. ....... 7
3.3 Digital models ................................................ ................................................. 7
3.3.1 Mark Model ................................................. .................................................. ...... 7
3.4 Map material ................................................. .................................................. ..... 7
3.5 Photogrammetric material ................................................ 7 ................................
3.5.1 Orthoimagery ................................................. .................................................. ............ 7
3.5.2 Aerial ................................................. .................................................. .......... 7
3.6 Laser scanning ................................................. .................................................. 7 ..
4 Agreements and contracts ............................................... ............................................ 7
PLANNING ................................................. .................................................. ................... 8
5 Core network ................................................. .................................................. .......................... 8
5.1 Connection network plan ............................................... ........................................... 8
5.2 A switching network in height. .................................................. ....................................... 8
5.3 Bruksnät plan ............................................... .................................................. ... 8
5.4 Bruksnät in height ............................................... .................................................. ... 8
5.5 Other networks ................................................ .................................................. .......... 8
6 Data Collection and Models ............................................... ............................................. 9
6.1 Aerial photography ................................................. ................................................ 9
6.2 Laser scanning ................................................. .................................................. 9 ..
6.2.1 Airborne laser scanning ................................................ .................................... 9
6.2.2 Car-borne laser scanning ................................................ ....................................... 9
2 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
3 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
Implementation Descriptions shall be prepared for all measuring jobs. Implementation descriptions must be submitted to the customer for
approval before starting work. Implementation description should include the following:
1 Enter the planned start and end date for implementation, and, where applicable dates for major papers in the
mission.
2 Enter selected method / technique and describe the performance of the various operating steps of the respective product / service
(process description).
3 Specify how it verified that the chosen methodology / technology meets the requirements.
5 Enter the selected equipment and related software implementation. Specify the instruments and equipment are
tested and calibrated, and when this is done in connection with the commission.
8 Enter the risk assessment and the elements in the mission to which it relates and how the consideration or
controlled in implementation. Risk evaluation can for example relate to a planned work performance can not occur
without complications, or to a quality characteristic on the requested product is not fully obtainable, etc.
9 Define what is included in the delivery and the form of products delivered.
1.1 Contractor's supply of instruments, equipment and surfaces during the planning and
construction stage as well as the warranty period.
The contractor shall object all stages and guarantee to provide the customer base as up to date maintained models, measurement and control
data from different measurement tasks etc. Delivery format should be as IT supervision or consultation with the client. The Purchaser shall, on
request, be given access to the contractor's measurement equipment for temporary controls.
• Have the transport department issued "certificate of qualification for the measurement of technical work in the transport department" with specified
minimum level credential I.
4 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
• Have a proven track record as a responsible Chief Measurer of large and complex construction contracts
of similar type.
2.1 reference
For contract valid reference in plan and elevation seen in IT Tutorial "E4FS 2012: 0106 Overall", section 2.9.
The height system is a project specific system designed especially for the Stockholm bypass (FS). Height system described in
Annex 5 to the measurement technical basis 2Z140003.
For the contract, the following geoid model, specially adapted to FS RH 00:
• SWEN08_RH00FS
The contractor provided the geoid model in DAT, GRD, and txt after the contract signing.
Coordinate Transformation of plant geometries, structures, etc. should not be performed with the method that changes them. In such
calculations, the unitary transformation used. Performed transformations contractor must supply original coordinates and the transformed
coordinates to the customer upon request. Coordinate Transformation of points in the core network may only be carried out with the consent
of the client.
As some points of the supplied core network within the contractor's work is a risk that they will be destroyed due to the construction of the new
facility. It is therefore important that the entrepreneur at an early stage, a suggestion immediately after clearing, condenses supplied network in
such a way that the points that will later disappear are replaced with new, representative points.
Upon clearing of trees and shrubs, or at the unveiling of the surface of the work area, it is important that the contractor takes into account the
points in the provided core networks and carry out clearing work in such a way that the points in the network is not damaged.
5 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
The contractor shall immediately inform the client of the risk that the control points can be lost or destroyed.
The provided control points in the plan that the contractor intends to use for the measurement must be checked according to SIS-TS 21143:
2009 6.3, with non-compliance of the contractor's inspection and verification of the calculation documents of the existing network. The visual
inspection under SISTS 21143: 2009 6.3 refers not hard to reach points marked on buildings or structures. It remains with the contractor to
check the existing networks in such a way that it is possible to verify that they hold sufficient accuracy to complete your mission. Inspection of
inaccessible points be performed by station setup with resection against at least three points on the evaluation of residuals. The contractor
shall establish an audit program that describes the control of the points to be used.
In the control test by measuring from the prior paragraph, deviations from nearby known points lie within the error limits of SIS OR 21143:
2009 Table 22.
All provided points in height must be checked according to SIS-TS 21143: 2009 6.3, with non-compliance of the contractor's inspection
and verification of the calculation documents of the existing network.
Control Balance to be carried out by double leveling the instrument according to SIS-TS 21143: 2009 Table 3, the lowest "Class A2" or
better. Control Balance to be connected to at least two known (mountain marked) starting points.
If the contractor checks show discrepancies should the client's measurement manager promptly informed.
Reporting from the control of the control points must include description, status, measurements and calculations according to SIS-TS 21143:
2009 6.3.
For all measurements with GNSS in the contract concerns a specific geoid model adapted to FS RH 00. The geoid is called
SWEN08_RH00FS and described in section 1.3 of the measurement technical basis 2Z140003.
At RTK survey should daily check of the accuracy of measurement carried out according to the exporter established control. The control
program must be approved by the customer before the RTK measurements begin.
6 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
The client should be given the opportunity to use the contractor's system during the time that the system is established and cultivated.
If the contractor intends to establish a permanent local reference station that will be performing as SISTS 21143: 2009 7.3.2, 7.3.2.1,
7.3.2.2, 7.3.2.4. Control of RTK accuracy of the measurement should be performed according to SIS-TS 21143: 2009 7.2.
Implementation description shall be established and approved by the client before proceeding.
Local temporary reference station is controlled according to SIS TS 21143: 2009 7.3.2.3 before use in the contract.
Definition of temporary reference station is that it is intended to be used for short periods, eg the disruption of Network RTK services.
Network RTK service is controlled according to SIS TS 21143: 2009 7.3.2.3 before use in the contract.
Note that maps the design does not keep adequate accuracy for detailed design but can be used only for orientation and visualization.
The client does not respond to provided map data is updated completely. Necessary additions to be performed by the contractor.
3.5.1 Orthoimagery
3.5.2 aerial
Provided no.
7 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
Where necessary, the base is contained in an agreement or agreements (LMV SGU Municipality) that will capture made by call-offs.
Blanket and supply of material should be done by the client's participation.
Documents which copyright is claimed should always be named by the author / owner together with the registration number of
the agreement governing the usufruct.
Name of the author / photographer / editor and responsible organization and execution of the derived result the products are always specified
in the product, including the date of completion.
The client holds agreements with certain property owners regarding the selection of points of network plan for construction works. Contact
with these property owners regarding access points is done by the client.
PROJECTION
The term planning refers to the planning carried out by the contractor procured before and during construction.
5 Core network
Provided stomnätspunkter listed under 3.2, which of these should be checked listed under Chapter 2.4
It is the responsibility of the contractor to self-establish temporary work locations within the work area adequately in order to continue the
necessary work if provided points blocked or destroyed. The purchaser shall, upon request, access to the coordinates of these points.
For the establishment of new networks and new items may only be provided by control points used as starting points.
Generally, the contractor if needed to complement existing networks to the extent necessary to carry out the necessary work.
The construction works have networks in plan drawn up by the client. It is the responsibility of the contractor to immediately notify the customer
if problems arise with the provided online. When certain points at certain times may be directed against neighboring contracts can have full
access to the network can not be guaranteed during the entire construction period. It is the responsibility of the contractor to supplement the
grid with points for their own needs survey and stake.
8 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
When certain points in the network of the plan for construction works within the contractor's work is a risk that they will be destroyed due to the
construction of the new facility. It is therefore important that the entrepreneur at an early stage, a suggestion immediately after clearing,
condenses the supplied network in such a way that the points that will later disappear are replaced with new, representative points.
Upon clearing of trees and shrubs, or at the unveiling of the surface of the work area, it is important that the contractor takes into account the points in the
network of the plan for construction works and performs the clearing work in such a way that the points in the network is not damaged.
Grids plan for operating and setting measurement shall be drawn up according to SIS-TS 21143: 2009 chapter 6.1.4. Measurement
Program will be prepared and presented at the review meeting with the client's measurement controller before selection and
measurement.
Nets at the height of the movement and settlement measurement shall be drawn up according to SIS-TS 21143: 2009 chapter 6.2.3.3.
Measurement Program will be prepared and presented at the review meeting with the client's measurement controller before selection and
measurement.
6.1 aIR-PHOTOGRAPHY
If the scan is performed, the results provided to the client. The contractor must verify that the performed scanning fulfills the tolerance
requirements for the application it is used for.
If the scan is performed, the results provided to the client. The contractor must verify that the performed scanning fulfills the tolerance
requirements for the application it is used for.
6.3.1 Survey
The aforementioned references below refer to HMK Building & construction BA3, Annex C and D inputs should be performed according to tolerance
indications in column construction document in Annex D to HMK Building & construction BA3.
The object's connections to existing roads, maps completions and completion of photogrammetric processing should be measured in
the extent of establishing construction document requires. The measurements will be carried out as follows:
• Paved road should the plan be measured in accordance with 4.1 - 4:10.
• Connecting gravel roads to object to the level measured in accordance with 4.1, 4.3, 4.4, 4.6 - 4:10.
• Tolerances in the height of the measurement should be under 4:11 to 4:13
• Connecting roads to objects located in the straight line or curve to be measured into the plane, so that raklinjens direction
respectively. curve radius can be ensured / calculated.
• Boundary points within respectively. in vägområdets proximity should be inventoried and measured up. Surveying the plan should be carried out with
the tolerance of 20 mm, as defined in Annex C.
9 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
• Measured boundary points are the special documentation listed regarding designation, marking, verification and coordinate
tasks. Surveyed boundary markers will be verified against the actual property map.
• Existing building to be moved to be measured in accordance with 1.1 -1.7 and 2.1 - 2.21, 2.3 and 3.1 - 3.3. Entries must be
documented and reported in accordance with special instructions.
• Existing leads and lead measured in details under 8.1 -8.10.
• Fences and walls within or adjacent to the road area is measured in accordance with 5.1 - 5.8. Tolerance for measurement should be
under 4.6.
• Trees with special natural value, in or near the road area, measured and indicated as 6.1 - 6.2.
• Ground facilities within or near the road area is measured in accordance with 13.1.
• Measure the object crossing the track facility shall be carried out according to specific instructions from the track property and
under specific restrictions.
• Ägoslagsgränser and areas of special natural values should be defined and measured in accordance with
14.1 - 14.2.
• Trenches crossing items and trenches to be used for the removal of water should be loaded in tolerance plane 50 mm and height
30 mm of 4.10. The measurements must be performed to determine the dikens bottom slope can be.
• Surfaces which require supplementing measured, for example in dense forest etc.
The contractor will perform the surveying of all VA facilities in addition to the owner's own management input, to the extent that
related documents can be established.
The piping and associated connections and devices to be measured in accordance Property Specific Technical Description, H. sewage network
Reporting of measurement programs for the execution of the motion and composition measurements must be performed according to SIS-TS 21143:
2009 chapter 7.4.4.
Mark Model with underlying models should be described as IT tutorial "E4FS 2012: 0107Cad and drawings", chapter 3.7.1. Deviations
from the complete model to be specified and approved by the client.
10 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
Mark Model shall also be drawn up of complete plant. The same requirements apply as for the land model drawn up for the construction
documents and as described above.
Model of construction documents to be created by the characteristic break lines separating height differences and lines as SIS TS
21144: 2007 Table 10 object Roads.
Mark Model will be built as an edited triangle model as SIS TS 21144: 2007 chapter 9.3.
quality labels
Mark Model should be labeled with quality content as SIS TS 21144: 2007 Section 9.6.
The contractor must, by measuring, verifying if uncovered rock surface is outside the uncertainty model. The customer will be offered the
opportunity attend this rock scaling.
triangulation
Berg Model will be built as an edited triangle model as SIS TS 21144: 2007, 9.3
Delivery
11 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
Berg Model name will be supplied in accordance with IT tutorial "E4FS 2012: 0107-Cad and drawings."
7 Withdrawal
The following applies to release both at the design stage as well as in the construction phase: Withdrawal should be performed according to SIS-TS 21143:
2009 7.5. Measuring method of withdrawal will be selected and the work to be carried out so that the tolerances according to SIS-TS 21143: 2009 7.1.2
achieved. Quality assurance of the releases to be performed according to SIS-TS 21143: 2009 8.2.
Reporting Performed release and marking should be included in the measurement technical report entitled Technical PM
Measurement Work Chapter 1:11.
8.1 Maps
Delivered planning maps must be kept up to date by the contractor. Project Map will be made as follows:
• Content, code, and mannerisms management should be carried out according to IT tutorial "E4FS 2012: 0107-Cad and drawings." Map should
be designed in 2D.
• Items will be reported as closed polygons where possible.
• The map mannerisms be adapted for plotting a scale of 1: 1000.
• Kartas content with complete stock content should be quality marked the sourcing, timeliness and accuracy.
8.2 Orthoimagery
Not included in the contract.
The presentation will take place digitally, unless otherwise specified in the contract documents. The following information shall, to the extent that it affects
the contract, included in the measurement technical account. All headlines below should be included regardless of whether the work was performed or
not. If the work is not done, this is marked by "have not been conducted" under each heading.
12 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
Completed construction The contract scope Regulatory and X The section should provide a general
references Surface Materials description of the work.
Staff
- Responsible person including competence requirements
Implementation
- Core network
- aIR-PHOTOGRAPHY
- laser scanning
- Maps
- Orthoimagery
Technical PM Core Full report for the core network in plan X 5 Core network
Technical PM Laser Technical memo describes the planning, X 6.2 Laser scanning
scanning execution, including systems / equipment,
software, control, performance and delivery is
established.
13 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
Mark Model and underlying Regulatory and design assumptions X 6.4 Model Mark with underlying
models Descriptions Software Data models
collection method Surface Quality
labels Variations (known) Personal
Delivery Reviews
14 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
interpolationens embodiment
described
Road geometry and Road geometry and the phenomena under. X 11.5 Delivery of road geometry to NVDB -
phenomena to NVDB National road database
11.6. Delivery of events to NVDB -
National road database
Core network
Bruksnät the plan will be established before the start of construction and be built fitted adjacent to the road area. Use the Net to be resistant
to be used for measurement during the warranty period. Use network will cover the entire work area.
Establishment, Selection, återfinning and item description should be performed according to SIS-TS 21143: 2009 given in Chapter 6. Paragraph
numbering should be according to the customer's instructions.
Bruksnät in plan shall be established as SIS OR 21143: 2009 Section 6.1 relating requirements indicated under Weight Composition and
Error limits, Measurement of Table 10, measurement, accounting from establishment of bruksnät of Chapter 6.1.2.
Reporting of planned bruksnät the plan should be carried out at the review meeting with customer's metering manager as SIS TS 21143:
2009 chapter 6.1.2, specified under Accounting. A review should be carried out before the selection and measurement.
With bruksnät referred to in this chapter is finally marked and measured core network in the plane of concrete tunnel and in the pan, which
will be handed over to the client. For all the main tunnel contracts in the Stockholm Bypass Project sets the client common requirements
for establishing bruksnät.
Bruksnät in trays and tunnel should be performed according to SIS-TS 21143: 2009 6.1 and food class G1 according to Table 9, with the following deviations:
• Introductory text SIS TS 21143: 2009 Chapter 6 under the heading "Selection, återfinning, item numbers and item
description" starts
• Table 1 and 2 of SIS OR 21143: 2009 4.1.1 is replaced with the following instrument conditions: In the measurement of core
network in plan tunneling shall total station with the accuracy of the following specification or better used:
15 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
• The following text in the SIS TS 21143: 2009 6.1 Table 9 deleted: Number helsatser ≥3 and replaced with: Number of approved helsatser ≥4
Measurement Program established pursuant to the SIS TS 21143: 2009 6.1.3.1 and approved by the client before stomnätsarbete begins.
The contractor will be in the implementation description to describe the connection between building the network and use the network. The same measurements and
discrepancies between building the network and use the network to be reported.
• The distance between point pairs should be a maximum of 100 meters, however, at least two pairs of points marked.
• Homogeneous nätgeometri, ie small distance deviations between point pairs should be sought.
Selection of the operating points of the tunnel and troughs should be performed with Unikonsol 400 mm. Unikonsolen be installed at a height of 1.30 m
above the finished road. ID badge must be mounted at each stompunkt in consultation with the client. Paragraph numbering should be carried out
according to the customer's instructions.
Use network in the tunnel will connect to the core network for tunneling in the following order of priority:
Reporting should be carried out according to SIS-TS 21143: 2009 6.1.2. If possible, the deviation from the adjacent Entreprenad's core
network for tunneling reported.
Data from stomnätsmätningarna be delivered to the client in a format that allows independent calculation as follows:
• Disclosure containing any renumbering, underlined measurements, identified serious errors and other inaccuracies.
• Excel file containing correct item numbers and reduced data rate, corrected for temperature, pressure and the earth curvature.
A model for Excelfilens design will be submitted by the client.
• Station Protocol containing: station number, operator, the serial number, the date, the instrument height, pressure,
temperature, paragraph numbers backward items, prism constant and signal heights.
16 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
The contractor shall establish networks in height. These shall be established as follows:
• Nets in height for the touchdown measurement according to SIS TS 21143: 2009, Section 6.2.3.3.
• Nets at the height of the tunnel under the SIS TS 21143: 2009, Section 6.2.3.1.
With bruksnät referred to in this section is final and measured the backbone network at the height of the concrete tunnel and trough, which will
be handed over to the client. For all the main tunnel contracts on the Stockholm Bypass Project sets the client common requirements for
establishing bruksnät in the tunnel.
Measurement Program for establishing bruksnät the height of the tunnel to be established according to SIS-TS 21143: 2009
6.2.3.1. Measuring program must be approved by the client before proceeding.
The initial text of the SIS TS 21143: 2009 6.2 applies with the exception of Section Simulation. In Table 16, the food class J2.
Use the Net to be performed according to SIS-TS 21143: 2009 6.2.3.1.2 and the same measurement as 6.2.3.1.2.2.
The contractor will be in the implementation description to describe the connection between byggnät and bruksnät. The same measurements
and discrepancies between byggnät and bruksnät be reported.
Use network in the tunnel should be measured adjacent to the core network at the height of the tunnel construction in the following order of priority:
Marker selected in consultation with the client. ID badge must be mounted at each stompunkt in consultation with the client. Paragraph numbering
should be carried out according to the customer's instructions.
Data from stomnätsmätningarna will is delivered to the client in a format that allows independent calculation as follows:
• Disclosure containing any renumbering, underlined measurements, identified serious errors and other inaccuracies
• Excel file containing correct item numbers and data. A model for Excelfilens design will be submitted by the client
• Station Protocol containing: station number, the operator, the instrument's serial number, date and item number for back
and forward items.
17 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
10.2.2 Brofixpunkter
Not included in the contract.
10.2.3 Brodubbar
All measurement data, calculations and reports will be stored for at least ten years of the construction phase is completed.
Requirements for the management and calculation of tolerances (release tolerances) as SIS OR 21143: 2009 Chapter 7 and annexes C
and D.
Measuring instruments and associated equipment and measurement methods should be adapted to the objects of accuracy required.
The contractor shall perform said check measurements of all of the reported structures, individual building components, structures or
components.
Said check measurements should be documented and the accuracy of the measurement will be reported as standard error unless otherwise specified.
Way
All roads control measured according Object Specific Technical Description, C3. TEMPORARY CONSTRUCTION AND DEVICE
FOR TRAFFIC / road structure and subgrade, DB1. Roadbed and subgrade, DB1. Roadbed and subgrade // GROUP 1, DB2.
Roadbed and subgrade // Groups 2.
concrete tunnel
Concrete Tunnel entrance ramp to E4 (249) and the exit ramp from the E4 (24B).
18 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
For typesetting controls in the contract, the touchdown and movement measurements performed. Verification is carried out from the network described in
paragraph 5.5, and should follow the SIS TS 21143: 2009 in the following chapters:
Monitoring should include the location of the measurement points, schedule, accuracy requirements, and reporting list prepared for
typesetting and motion measurement and deformation. Results for each measurement point must be reported in tables and graphically in
the chart. Measurements shall be presented in digital form.
Control measurements should primarily be carried out when the ground is not tjälad. Documentation from the control measurement
should be reported to the client Measurement manager.
Measurement works should be coordinated with the control measurement of backbone in the plane and height specified in 13.1.
Measurement works should be coordinated with the control measurement of backbone in the plane and height specified in 13.1.
19 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
The contractor must disclose to the client all the checks and measurements performed during the warranty period.
SIS TS 21143: 2009 Geodetic measurement, calculation and reporting at the elongated object SIS TS 21144: 2007
Specification for the production of digital terrain models SIS TS 21145: 2007 Statistical testing terrain model HMK Building &
Construction, Designing
HMK BA3
HMK Building & Construction, Planning HMK-BA2
HMK Building & Construction, Construction HMK BA4
Measurement Technical file Matu
IT Tutorial
The HMK recognized award criteria will be for the construction construed as skakrav.
15.2 Concepts
Concepts which occur in the SIS TS document recognized as follows: SIS TS 21143: 2009
Appendix A
SIS TS 21144: 2007 Chapter 3
SIS TS 21145: 2007 Chapter 3
Concept Explanation
geoid The geoid is used to define the shape of the earth. A certain geoid model corrects for the
uplift and the heights above the ellipsoid and altitudes for a certain specified height
system. The correction is done by restfelsinterpolering. Examples of the geoid is
SWEN05_RH2000 (SWEN 05LR)
Mark Model Model (digital) in 3D that describes the height of the top surface of the ground including
"outcrop" and the bottom surface of lakes and rivers. Model can be prepared for example
from terrestrial field measurement, laser scanning, photogrammetric measurement or other
substrate materials of SIS OR 21144: 2007 Table 6.
20 (21)
FSE215 / \\ TRV8126 \ PWDCSforPDF \ 19641 \ 5062_63 \ 2Z140002-FSE215.docx / / 2016-02-01 / / (Printed 2016-01-08 08:39)
E4 Stockholm Bypass
FSE215 concrete tunnels Skärholmen Object Specific
Technical Description Measure
Orthoimagery With orthophoto referred photographic image converted from the central projection to
the orthogonal scale real projection. Orthophotos can refer rectified single image or
multiple images together into a so-called mosaic.
Underlying models to Underlying models described as model associated ground model. These models
land model describe the height of the top surface of the respective surface layer. Examples of
underlying models can be fixed soil, rock and groundwater. The models are developed
through the interpretation of geotechnical surveys or other substrate materials.
Ytbildad land model Mark Model where the model can also account for soil type and its limitations.
21 (21)