240 87605434

Download as pdf or txt
Download as pdf or txt
You are on page 1of 68
At a glance
Powered by AI
The key takeaways are that this document provides a quality checklist for the distribution substation primary plant that must be completed prior to handing over the substation for commercial operation.

The purpose of this document is to provide a quality checklist to ensure all work is completed and meets specifications before a distribution substation's primary plant is handed over for commercial use.

This document covers 14 stages of a distribution substation project from civil works through final commissioning and handover.

Standard Technology

Title: QUALITY CHECKLIST FOR Unique Identifier: 240-87605434


DISTRIBUTION SUBSTATION
PRIMARY PLANT PRIOR TO
HANDING OVER FOR Alternative Reference Number: 34-1238
COMMERCIAL OPERATION

Area of Applicability: Engineering

Documentation Type: Standard

Revision: 1

Total Pages: 68

Next Review Date: March 2020

Disclosure Classification: Controlled


Disclosure

Compiled by Approved by Authorized by

Abre Le Roux Phineas Tlhatlhetji Phineas Tlhatlhetji


Chief Engineer Substations Substations COE Manager Substations COE Manager

Date: Date: Date:

Supported by SCOT/SC

Phineas Tlhatlhetji
Substations SC Chairman

Date:

PCM Reference: 240-53114186


SCOT Study Committee Number/Name: Substations
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 2 of 68

Content
Page
Executive Summary ............................................................................................................................................ 4
1. Introduction .................................................................................................................................................. 5
2. Supporting clauses ...................................................................................................................................... 5
2.1 Scope ................................................................................................................................................. 5
2.1.1 Purpose .................................................................................................................................. 5
2.1.2 Applicability ............................................................................................................................ 5
2.2 Normative/informative references ...................................................................................................... 5
2.2.1 Normative ............................................................................................................................... 5
2.2.2 Informative ............................................................................................................................. 5
2.3 Definitions ........................................................................................................................................... 6
2.3.1 General .................................................................................................................................. 6
2.3.2 Disclosure classification ......................................................................................................... 6
2.4 Abbreviations ...................................................................................................................................... 6
2.5 Roles and responsibilities .................................................................................................................. 7
2.6 Process for monitoring ....................................................................................................................... 7
2.7 Related/supporting documents .......................................................................................................... 7
3. Requirements .............................................................................................................................................. 7
3.1 General Project Information ............................................................................................................... 9
3.2 Requirements applicable to Stages 1 to 12 ....................................................................................... 9
3.2.1 Additional requirements applicable to Stage 5 - “Civil Works: Equipment Foundations
& Cable trenches” .................................................................................................................. 9
3.2.2 Additional requirements applicable to Stage 9 - “Steelwork” and “Fencing” .......................10
3.2.3 Additional requirements specific to Stage 10 - “Power Transformer Delivery &
Assembly” ............................................................................................................................10
3.2.4 Additional requirements specific to Stage 11 - “Primary Equipment Installation” ................10
3.3 Requirements applicable to Stage 13 - “Provisional Handover” ......................................................10
3.4 Requirements applicable to Stage 14 - “Final Handover” ................................................................10
4. Authorization ..............................................................................................................................................11
5. Revisions ...................................................................................................................................................11
6. Development team ....................................................................................................................................12
7. Acknowledgements ...................................................................................................................................12
– Annex B1 – - Stage 1: Civil Works: Platform .................................................................................................18
– Annex B2 – Stage 2: Civil Works: Control and Switch house Building .........................................................24
– Annex B3 – Stage 3: Civil Works: Subsoil Drainage .....................................................................................29
– Annex B4 – Stage 4: Civil Works: Earthmat Installation................................................................................31
– Annex B5 – Stage 5: Civil Works: Equipment Foundations & Cable Trenches ............................................33
– Annex B6 – Stage 6: Civil Works: Roads, Stoning & Kerbing .......................................................................36
– Annex B7 – Stage 7: Civil Works: Transformer Bund Wall, Oil Dam and Fire Wall ......................................38
– Annex B8 – Stage 8: Steelwork .....................................................................................................................44
– Annex B9 – Stage 9: Fencing ........................................................................................................................46
– Annex B10 – Stage 10: Power Transformer Delivery & Assembly ...............................................................49
ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 3 of 68
– Annex B11 – Stage 11: Primary Equipment Installation................................................................................51
– Annex B12 – Stage 12: Conductor, Busbars & Clamps Installation ..............................................................64
– Annex B13 – Stage 13: Provisional Handover ..............................................................................................67
– Annex B14 – Stage 14: Final Handover ........................................................................................................68

Figures

Figure 1: Quality Control handover stages ......................................................................................................... 8

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 4 of 68

Executive Summary
The document provides check sheets and handover sheets for the various phases of Primary Plant
construction of substations. It ensures that all the activities during the period are recoded and acknowledged.
It also includes Preliminary and Final handover check sheets.
The document only caters for Primary Plant. The commissioning procedure for Control Plant is catered for in
the “Standard for commissioning Protection assets” (240-54615413) as well as other discipline specific
documents. All documents must therefore be completed for a substation project if the project includes
Primary and Control plant.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 5 of 68
1. Introduction
Quality control is of utmost importance during the construction phase of a project. Identifying quality
problems at an early stage ensures minimum project delays. The document provides Quality check sheets
and Handover sheets for the various phased of Primary Plant construction.

2. Supporting clauses
2.1 Scope
This standard sets out the requirements for the various Quality Control and Handover process stages for a
substation project from the inception of construction to commissioning and final handover. This standard
shall be used in conjunction with all standard substation documentation and scope of works documentation
that will form part of the substation project Works Information.
The document excludes check sheets for Control Plant activities.

2.1.1 Purpose
The document provides check sheets for the various phases of Primary Plant construction of substations. It
ensures that all the activities during the period are recoded and acknowledged.

2.1.2 Applicability
This document shall apply to Eskom Distribution.

2.2 Normative/informative references


Parties using this document shall apply the most recent edition of the documents listed in the following
paragraphs.

2.2.1 Normative
[1] SANS 121, Hot-dip (galvanized) zinc coatings (other than on continuously zinc-coated sheet and
wire).
[2] DST 34-304: Distribution standard – Part 7: Generic substation design.
[3] SANS 1200: Specification for civil engineering construction
[4] SABS 10400: National building regulations
[5] DST 34-1245: Substation Earthing
[6] DISSCAAD3: Checklist for Large Transformers
[7] DSP 34-1658: Corrosion Protection specification for new indoor and outdoor Distribution equipment,
components, materials and structures manufactured from steel
[8] DISASAAN0: Standard for the labeling of High Voltage Equipment

2.2.2 Informative
[9] 240-54615413: Standard for commissioning protection assets.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 6 of 68
2.3 Definitions
2.3.1 General

Definition Description
Clerk Of Works People responsible for physical quality inspections.
Contract Design Person appointed external to Eskom responsible for the design drawings, bill of
Engineer quantities and approval of Design Change Requests
Contract Project Person appointed as per the NEC contract. The Project Manager is appointed
Manager external to Eskom
As per the NEC contract represented by an Appointed Supervisor or
Responsible Person in writing. The Contractor can also be an Eskom Internal
Contractor Construction team.
Manufacturers of the Power Transformers and other substation equipment.
Control Plant Responsible for the pre-commissioning and final commissioning of the
Maintenance substation project
department
Design Engineer Person responsible for the control plant design (protection, metering, DC,
(Control Plant) telecommunication and telecontrol).
Design Engineer Person responsible for the primary design drawings, bill of quantities and
(Primary Plant) approval of Design Change Requests
Activity for which arrangements have to be made for the Clerk of Works to be
Holding Point
present and to witness the work procedure
Person appointed as per the NEC contract. The Project Manager can be
Project Manager someone within the Eskom Program Management Department or an external
appointment in which case it will be a Contracted Project Manager.
Standards Department responsible for standards
Implementation
department
(Substations)

2.3.2 Disclosure classification


Controlled disclosure: controlled disclosure to external parties (either enforced by law, or discretionary).

2.4 Abbreviations

Abbreviation Description
AD Asset Design
CDE Contract Design Engineer
COW Clerk Of Works
CPM Control Plant Maintenance department
DE Design Engineer
PM Project Manager

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 7 of 68
2.5 Roles and responsibilities
The Standards and Implementation manager (S&I) will ensure that the document is distributed to the
relevant people for implementation. The document should be implemented by the Operational Unit Project
portfolio manager as well as the Network Engineering manager

2.6 Process for monitoring


Operational Unit Project portfolio manager is to ensure that the handover document has been completed for
all Primary Plant substation projects.

2.7 Related/supporting documents


The original document was published as DISASAAQ1 Rev 5 dated September 2005. The document was
revised and published as 34-1238 in February 2013.

3. Requirements
The document contains all possible quality check sheets and handover forms to execute Primary Plant
activities in a substation.
The document only caters for Primary Plant. The commissioning procedure for Control Plant is catered for in
the “Standard for commissioning Protection assets” (240-54615413) as well as other discipline specific
documents. All documents must therefore be completed for a substation project if the project includes
Primary and Control plant.
A Quality Handover document is specific to a project. Only include the relevant sections and duplicating
check sheets where required (e.g. In the case of two transformers two separate transformer check sheets
will be required or if no capacitor bank will be installed, exclude the capacitor bank quality check sheet). This
document is available on the Webb site in Excel format for ease of manipulation.
The document contains detailed check sheets. If the Project manager deems the project to be low risk,
check sheets may be amended. It is however important that handover sheets are duly completed. (This
should not be the norm but rather an exception because of increased risk due to lack of detailed quality
control).
Stages
The process is initiated by collating all relevant detail and documentation regarding the project and
stakeholders. This is catered for in tables in the General information section as per Annexure A.
The next stage is the actual execution of activities. This is catered for in Stages 1 to 12 (Annexure B1 to
B12). Each stage consists of two categories of documents, namely a
Quality Control check sheet (Quality checking of actual activities) and a
Handover form (confirming that the various Quality activity checks had been executed).
The next stage is the Handover stage. Provision is made for two stages for Handover.
Firstly, a Preliminary Handover stage to ensure that all quality checks have been performed in order to
switch the substation on.
The final Handover ensures that all activities relating to the project have been completed and the project is
closed off and handed over for Commercial operation.
The various stages are depicted in figure 1

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 8 of 68

PROJECT STAGES

Control Plant
Primary Plant See Standard for
commissioning Protection
assets: 240-54615413 and
other PTM&C Check sheets
General Project

Civil Works

Platform (Stage

Control Building (Stage

Subsoil drainage (Stage

Earthmat Installation

Equipment Foundations & Cable trenches (Stage 5)

Roads, Stoning & Kerbing (Stage 6)

Transformer bund area, Oil dam and fire wall (Stage 7)

Steelwork (Stage 8)

Fencing (Stage 9)

Power Transformer Delivery & Assembly (Stage 10)

Primary Equipment Installation (Stage 11)

Conductors, busbars & clamps (Stage 12)

Provisional Handover (Stage

Final Handover (Stage 14)

Figure 1: Quality Control handover stages

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 9 of 68
3.1 General Project Information
The Design Engineer shall hand over the Final Design Package and Drawings to the Project Manager. It is
the responsibility of the Design Engineer to ensure that the latest revisions of all documentation have been
issued to the Project Manager.
The Project Manager will ensure that both the appointed Contractor and the appointed Clerk of Works
receive the necessary documents and drawings for all the construction stages. All parties are to complete
the Design Package Handover Form before commencement of construction.
Provision has been made for signatories and the recording of the relevant Drawing Numbers and Revisions
at the time of issue.
Drawing revisions due to Design Changes will be recorded in the Documentation Change Control Form.
The Project Manager will ensure that the Contractor and Clerk of Work receive the latest revision of the
drawings.

3.2 Requirements applicable to Stages 1 to 12


The Quality Control Checksheet will be issued by the Project Manager as part of the quality assurance
documentation and will be on site until the stage has been completed. The activities within the stage are to
be completed and checked against the design drawings and specifications to ensure compliance.
Prior to the commencement of the construction stage, the Clerk of Works will confirm with the Contractor
which activities have been identified as Holding Points and which activities he would like to be photographed
as proof of compliance.
Each activity, once completed by the contractor, will be signed off by both the Contractor and Clerk of Works.
The Clerk of Works will indicate whether the activity was:
Witnessed (W) – present during this activity
Verified (V) – not present but confirm compliance.
Certain Checksheets include key specifications such as soil classification, layer depth and number of layers
required as per the design. This is to ensure the specification is understood by both parties and complied
with.
Once all the activities for a specific stage have been completed, the Quality Control Checksheet shall be
presented to the Project Manager who will confirm that all the activities have been signed off by both the
Contractor and the Clerk of Works
The Handover Checklist is then used as a high level checklist to ensure that all Quality Control activities
have been executed as per the Quality Control Checksheet. The Handover Checklist is the responsibility of
the Project Manager and must be updated at least once a month during the site meeting.
The required forms must be duplicated for multiple products in a substation (e.g. for two transformers make
two copies of the transformer checksheets).

3.2.1 Additional requirements applicable to Stage 5 - “Civil Works: Equipment


Foundations & Cable trenches”
The checksheet for the foundations can be done as a bulk item check or a checksheet for each foundation or
group of foundations. This is to be decided between the Clerk of Works and the Contractor.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 10 of 68
3.2.2 Additional requirements applicable to Stage 9 - “Steelwork” and “Fencing”
The Contractor shall ensure that all manufactured steelwork is inspected at delivery and galvanizing
thickness checked and verified before erection. The Contractor needs to inform the Clerk of Works once the
steelwork is on site. The Clerk of Works needs to arrange an inspection date with the Standards and
Implementation Representative for inspection and approval of steelwork.
The Checksheet for the steelwork can be done as a bulk item check or a checksheet for each item or group
of items. This is to be decided between the Clerk of Works and the Contractor.

3.2.3 Additional requirements specific to Stage 10 - “Power Transformer Delivery &


Assembly”
The Project Manager must notify the Eskom Plant and Control Plant Maintenance Departments of the
projected delivery date in order for them to provide a representative to witness the Transformer delivery and
acceptance activity.
During the delivery of the Power Transformer, the Clerk of Works shall verify and complete the Transformer
Delivery and Assembly Check sheet as per Stage 10 (This excludes DFM 34-1901 that will be completed by
the Plant representative)
Control Plant Maintenance department must witness the on-site transformer tests as executed by the
manufacturer.

3.2.4 Additional requirements specific to Stage 11 - “Primary Equipment Installation”


The Contractor shall inspect all deliveries from Manufacturers in order to ensure that the equipment is in
good condition before off-loading on site.
Only high level data such as equipment type and serial number is captured on the checksheets. Once the
equipment is installed, the Project Manager will inform the Plant Department to commence data capturing as
per the Eskom Data capturing requirements.

3.3 Requirements applicable to Stage 13 - “Provisional Handover”


The Provisional Handover Document will be completed by the Project Manager and presented for
acceptance to the following key persons:
Network Engineering – Acceptance by the appointed Senior Design Engineer (acceptance for primary and
Control Plant)
Control Plant Maintenance - Acceptance by the Control Plant Maintenance Manager
Network Operations – acceptance by the Chief Engineer
The final commissioning of the substation project can commence after the completion of the Provisional
Handover Document.

3.4 Requirements applicable to Stage 14 - “Final Handover”


The Final Handover Document will be completed by the Project Manager and presented for acceptance to
the following key persons:
Asset Design – Acceptance by the appointed Senior Design Engineer (acceptance for primary and Control
Plant)
Control Plant Maintenance - acceptance by the CPM Manager
On behalf of the Zone – final acceptance by Sector Manager.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 11 of 68
4. Authorization
This document has been seen and accepted by:

Name and surname Designation


Phineas Tlhatlhetji Substations COE manager
A le Roux Chief Engineer Substations

5. Revisions
Date Rev Compiler Remarks
March 2015 1 A Le Roux Designation name changes were required due to
structure changes
Change the name to reflect that the document only
relates to Primary Plant
Sections 13 and 14 are now documented in a
separate document (DST 240-54615413: Standard
for commissioning Protection assets)
Remove sections 13 and 14
Remove all references to sections 13 and 14
Revise section 3 to explain the reference to the
protection commissioning document
Feb 2013 1 A le Roux Complete document revision with new stages 1 to
16 and revised handover and quality checklist
documentation
Document number changed to DST 34-1238.
Sept’05 5 C Clark Document approved.
All comments and new comments answered. Send
for Voting 03/2005.
All comments answered. Send for Voting 11/2004.
Telecontrol info updated according to comments
received by Western Region. Electrical Certificate
info on page 9 removed.
Sept 2002 4 C Clark Document approved
June 2002 3 C Clark Page 75 EDNS added

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 12 of 68
Date Rev Compiler Remarks
Nov ‘99 2 C Clark Document changed comments added
Document changed item revised – 4.6.2
Document changed comments added – 4.6.4 , 4.6.5
Comments addressed. General typographical errors
rectified. Item 4.4.2 and associated forms revised.
Annex H (Stage 8) – FS added as a signatory.
Annex I added to include provisional handing over
certificate. Annex C (Stage 3) C13 – Fire Protection
Checklist added. Annex A (Stage 1) A3 –
changes/additions to checklist. General changes to
all other Annexes as per comments
Typographical errors rectified as per request from
western region. Alignment of document to include
signatories on a single sheet.
April ‘99 1 C Clark Project Flow Process taken out, entire document
changed.
Aug ‘98 0 C Clark Project Flow Process added, entire document
revised to allow for Stage takeovers.

6. Development team
The following people were involved in the development of this document

Name Designation

A.Le Roux Chief Engineer – Substations

N. Webber Senior Advisor - Substations

J.Kriel Thabile Eastern Cape – Electrical Engineers

7. Acknowledgements
The author acknowledges the original author, Craig Clark and team as well as the current development
team.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 13 of 68
Annex Contents
Quality Control & Handover Check-sheets

General Project information


Project Detail
Annex A Tracking Page
Design Package Handover
Documentation Change Control

Annex B1 Stage 1 Civil Works: Platform

Annex B2 Stage 2 Civil Works: Control Building

Annex B3 Stage 3 Civil Works: Subsoil drainage

Annex B4 Stage 4 Civil Works: Earthmat Installation

Annex B5 Stage 5 Civil Works: Equipment Foundations & Cable trenches

Annex B6 Stage 6 Civil Works: Roads, Stoning & Kerbing

Annex B7 Stage 7 Civil Works: Transformer bund wall, oil dam and fire wall

Annex B8 Stage 8 Steelwork

Annex B9 Stage 9 Fencing

Annex B10 Stage 10 Power Transformer Delivery & Assembly

Annex B11 Stage 11 Primary Equipment Installation

Annex B12 Stage 12 Conductors, busbars & clamps

Annex B13 Stage 13 Provisional Handover

Annex B14 Stage 14 Final Handover

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 14 of 68
Annex A – General Project Information
Project Detail

Substation Project Name:


Project No:
COW name:
Design Engineer:
Project Manager:

Contractor Civil Platform Works: Contractor Secondary Works:


Contract No: Contract No:
Contractor Supervisor: Contractor Supervisor:

Contractor Civil Buildings: Contractor :


Contract No: Contract No:
Contractor Supervisor: Contractor Supervisor:

Contractor Primary Works: Contractor:


Contract No: Contract No:
Contractor Supervisor: Contractor Supervisor:

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 15 of 68
Project Tracking
The purpose of this page is to track the relevant stages and to record progress.

Quality Control Checklist Handover Checklist


Notes
Completion Date Completion Date
Stage 1 Civil Works: Platform
Stage 2 Civil Works: Control Building
Stage 3 Civil Works: Subsoil drainage
Stage 4 Civil Works: Earthmat Installation
Stage 5 Civil Works: Equipment Foundations & Cable trenches
Stage 6 Civil Works: Roads, Stoning & Kerbing
Stage 7 Transformer bund wall, oil dam and fire wall
Stage 8 Steelwork
Stage 9 Fencing
Stage 10 Power Transformer Delivery & Assemble
Stage 11 Equipment Installation
Stage 12 Conductors, busbars & clamps
Stage 13 Provisional Handover Document
Stage 14 Final Handover Document

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 16 of 68
Design Package Handover

1 Project name:
2 Contract/Order No:
3 Contractor:

Rev Issued by (Project Received by (Clerk of Received by


Stage Construction Activity Drawing Title & Reference Date Date Date
No: Manager Name) Works Name) (Contractor Name)
Access to site documentation completed as per
the NEC contract
Health & Safety Plan and File presented and
approved before start of construction.

1 Civil Works: Platform

2 Civil Works: Control Building

3 Civil Works: Subsoil drainage

4 Civil Works: Earthmat Installation

Civil Works: Equipment Foundations &


5
Cable trenches

6 Civil Works: Roads, Stoning & Kerbing

Civil Works: Transformer bund wall, oil dam and


7
fire wall

8 Steelwork

9 Fencing

10 Power Transformer Delivery & Assembly

11 Primary Equipment Installation

12 Conductors, busbars & clamps

13 Control Plant installation

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 17 of 68

Documentation Change Control

1 Project name:
2 Contract/Order No:
3 Contractor:

Issued by Project Received by Clerk of Received by Contractor


Item Drawing No: Change Rev No: Date Date Date
Manager Name Works Name Name

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 18 of 68
– Annex B1 – - Stage 1: Civil Works: Platform

Quality Control Checksheet for Civil Works: Platform


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V) COW/Civil Engineer


Item Checklist QC items to check or supply Contractor Signature
Required (Y/N) (Y/N) Witnessed (W) Signature
1 Benchmark Installation Surveyor's Name:_______________

Depth:__________mm

Quantity:__________m³

Stockpile position:__________
2 Platform: Clear & grub
Stockpile height:__________m

Disposal within site boundary:__________

Disposal at registered wast:__________km

Layer Depth:___________mm

No of layers:__________
3 Platform: Cut to Fill Operation
No of Compaction & Density tests:__________

No of Compaction & Density tests witnessed by


COW:__________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 19 of 68
Holding Point Photo Required Verified (V) COW/Civil Engineer
Item Checklist QC items to check or supply Contractor Signature
Required (Y/N) (Y/N) Witnessed (W) Signature
Soil classification:__________

Depth Layers :__________mm

No of layers:__________
Platform: Importation, classification
4
& compaction of materials
No of Compaction & Density tests:__________

No of Compaction & Density tests witnessed by


COW:__________

Verified and signed by Civil Engineer:__________

Soil classification:__________

Depth Layers :__________mm

No of layers:__________
Platform: Final layer preparation /
5
Wearing coarse
No of Compaction & Density tests:__________

No of Compaction & Density tests witnessed by


COW:__________

Verified and signed by Civil Engineer:__________

Depth:__________mm

Quantity:__________m³

Stockpile position:__________
6 Access Road: Clear & grub
Stockpile height:__________m

Disposal within site boundary:__________

Disposal at registered wast:__________km

Layer Depth:__________mm

No of layers:__________
7 Access Road: Cut to Fill Operation
No of Compaction & Density tests:__________

No of Compaction & Density tests witnessed by


COW:__________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 20 of 68
Holding Point Photo Required Verified (V) COW/Civil Engineer
Item Checklist QC items to check or supply Contractor Signature
Required (Y/N) (Y/N) Witnessed (W) Signature
Soil classification:__________

Depth Layers :__________mm

Accsee Road: Importation, No of layers:__________


8 classification & compaction of
materials No of Compaction & Density tests:__________

No of Compaction & Density tests witnessed by


COW:__________

Verified and signed by Civil Engineer:__________

Soil classification:__________

Depth Layers :__________mm

No of layers:__________
Access Road: Wearing coarse /
9
Final bed layer preparation
No of Compaction & Density tests:__________

No of Compaction & Density tests witnessed by


COW:__________

Verified and signed by Civil Engineer:__________

Soil classification:__________

Depth Layers :__________mm

No of layers:__________
Access Road: Pavement fill and
10
final bed layer preparation
No of Compaction & Density tests:__________

No of Compaction & Density tests witnessed by


COW:__________

Verified and signed by Civil Engineer:__________

Drainage & Channelling required:__________

Bell mouth: Size and bending radius:__________

11 Access Road: Finishes Entry from Road:__________

No of Compaction & Density tests witnessed by


COW:__________

Verified and signed by Civil Engineer:__________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 21 of 68
Holding Point Photo Required Verified (V) COW/Civil Engineer
Item Checklist QC items to check or supply Contractor Signature
Required (Y/N) (Y/N) Witnessed (W) Signature
Embankment angles and preparation:__________

Seeding:__________

12 Embankments & Soil Detainment Soil Blankets:__________

Retaining walls - Type & size:__________

Verified and signed by Civil Engineer:__________

Type of drain:__________

Drain Positions:__________

Drain sizes:__________

13 Storm water drainage Concrete specification:__________

Concrete supplied:__________

Finishes:__________

Run-offs / Channelling:__________

Type & Position:__________

Corner Posts:__________

14 Boundary Fence Intermediate posts:__________

Fencing:__________

Gates:__________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 22 of 68
Holding Point Photo Required Verified (V) COW/Civil Engineer
Item Checklist QC items to check or supply Contractor Signature
Required (Y/N) (Y/N) Witnessed (W) Signature
Position:__________

15 Earth berm installation Size:__________

Verified and signed by Civil Engineer:__________

16 Levelling of spoiled materials Levelling of spoiled materials.

Position:__________

17 Rehabilitation Seeding:__________

Verified and signed by Environmentalist:__________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 23 of 68

Handover Checklist for Civil Works: Platform


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name
1 Benchmark Installation

2 Platform: Clear & grub

3 Platform: Cut to Fill Operation

Platform: Importation, classification


4
& compaction of materials

Platform: Final layer preparation /


5
Wearing coarse

6 Access Road: Clear & grub

7 Access Road: Cut to Fill Operation

Accsee Road: Importation,


8 classification & compaction of
materials

Access Road: Wearing coarse /


9
Final bed layer preparation

Access Road: Pavement fill and


10
final bed layer preparation

11 Access Road: Finishes

12 Embankments & Soil Detainment

13 Storm water drainage

14 Boundary Fence

15 Earth berm installation

16 Levelling of spoiled materials

17 Rehabilitation

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 24 of 68
– Annex B2 – Stage 2: Civil Works: Control and Switch house Building

Quality Control Checksheet for Civil Works: Control and Switch house building
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)

Setting out of building


1 Building set out according to XY
foundations & levels.
Foundation correctly excavated - width &
depth
Levels/height correct

2 Foundations - excavation Reinforcing installed correctly

Compaction acceptable

Local Municipality approval

3 Concrete - Foundations Concrete - mixture at correct MPa

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 25 of 68

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)

Concrete - mixture at correct Mpa

Waterproofing:
4 Concrete - Floor
Shuttering:
Floating / Power floating:
Note special requirements for indoor SG
Brick type & colour

Cement mixture correct

Waterproofing
5 Brickwork
Jointing

Correct heights & levels

Plastering

Trusses delivery - visual inspection

Trusses designed correctly

Trusses positioned & lined up correctly

6 Roof Installation - Sheeting Roof sheeting type & colour

Roof installation

Roof waterproofing installation

Gutters & down pipes

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 26 of 68

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Concrete - mixture at correct MPa

Reinforcing installation

7 Roof Installation - Concrete Shuttering.

Waterproofing installation

Gutters & down pipes

Ceiling type & colour


8 Ceilings
Ceiling height & level

Plumbing installation
9 Plumbing Installation
Plumbing Installation approval by an
accredited person
Electrical installation
Control Building - Electrical
10
Installation
Certificate of Compliance issued

Electrical installation
Battery room - Electrical
11
Installation Electrical Installation approval a Master
Electrician.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 27 of 68

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Painting

Steps, Ramps & hand rails

Doors, Security gates

Trench covers

Cable rack installations

12 Finishing Key cabinet

Operating Diagram board installation

Fire extinguishers

Furniture

Operating earths

Barricading nets & stands

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 28 of 68

Handover Checklist for Control Building


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name
Setting out of building
1
foundations & levels.
2 Foundations

3 Concrete - Foundations

4 Concrete - Floor

5 Brickwork

6 Roof Installation - Sheeting

7 Roof Installation - Concrete

8 Ceilings

9 Plumbing Installation
Control Building - Electrical
10
Installation
Battery room - Electrical
11
Installation
12 Finishing

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 29 of 68
– Annex B3 – Stage 3: Civil Works: Subsoil Drainage

Quality Control Checksheet for Civil Works: Subsoil drainage


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)
Grid lengths measured out with correct
distances
Subsoil drainage & piping
1 Grid levels to be determined to ensure
setting out
enough fall is created during excavation &
installation of the drainage pipes.
Drainage pipes - size & type

Bidum material
Installation of subsoil drainage
2
pipes, bidum and stone
Stone - size & type

Trenching - width & depth

Backfilling of materials
Subsoil drainage backfill and
3
compaction
Compaction

4 Drainage outlets Number of outlets

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 30 of 68

Handover Checklist for Civil Works: Subsoil drainage


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name
Subsoil drainage setting
1
out.
Installation of subsoil
2 drainage pipes, bidum
and stone
Subsoil drainage backfill
3
and compaction
4 Drainage outlets

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 31 of 68
– Annex B4 – Stage 4: Civil Works: Earthmat Installation

Quality Control Checksheet for Civil Works: Earthmat Installation


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

1 Earth Grid setting out Earthmat - setting out

Excavations

2 Earth Grid Excavations Backfill of materials

Compaction

Earth Conductor - type & size

Earth Conductor installation


Earth Conductor Installation &
3
Connections
Earth Conductor connections

Sacrificial earth installation

4 Earth Continuity test Earth Continuity test

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 32 of 68

Handover Checklist for Civil Works: Earthmat Installation


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name

1 Earth Grid setting out

2 Earth Grid Excavations


Earth Conductor Installation &
3
Connections
4 Earth Continuity test

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 33 of 68
– Annex B5 – Stage 5: Civil Works: Equipment Foundations & Cable Trenches

Quality Control Checksheet for Civil Works: Foundations


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Equipment Foundation - setting out


Foundation dimensions - length, width &
depth
Foundation side walls - stable & vertical

Foundation compaction

Reinforcing
Equipment Foundation
1 Steel Shuttering
No:___________________
Control cabling uPVC pipe

Steel Templates - installed & positioned

HD Bolts

Earthing - installed HD bolt earthing

Concrete - mixture at correct Mpa

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 34 of 68

Quality Control Checksheet for Civil Works: Cable Trenches


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Cable trenches - setting out


Cable trench excavations &
installation
Cable trench bedding preparation.

2 Cable trenches Cable trench cover support brackets

Cable trench (pipe) road crossings

Cable trench covers.


Cable trench entry into Control
Building.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 35 of 68

Handover Checklist for Civil Works: Foundations & Cable Trenches


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name

1 Foundations

2 Cable trenches

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 36 of 68
– Annex B6 – Stage 6: Civil Works: Roads, Stoning & Kerbing

Quality Control Checksheet for Civil Works: Roads, Stoning & Kerbing
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Road kerbing installation


1 Kerbing
Stone kerbing installation

Road stoning - size & depth.

Paving - preparation
2 Roads
Paving - installation

Gate ramp installation

3 Stoning Yard stoning - size & depth.

4 Weed killer Spraying of weed killer.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 37 of 68

Handover Checklist for Civil Works: Roads, Stoning & Kerbing


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name
1 Kerbing

2 Roads

3 Stoning

4 Weed killer

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 38 of 68
– Annex B7 – Stage 7: Civil Works: Transformer Bund Wall, Oil Dam and Fire Wall
Quality Control Checksheet for Civil Works: Transformer Bund Area, Oil Dam & Fire Wall
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Foundation - depth & size

Face Bricks - correct make

Walls - Quality of finish

Walls - Facebrick jointing

Walls - Height & Level

Sump - depth & size

Floor - levels (direction of flow)

Floor - sealing correct

Valve chamber - level & size


1 Transformer Oil Containment Area
Drizit bags - installed

Outlet Valve - level

Drizit bag - level

Drainage pipe - outlet level

Valve Chamber cover - size

Flow stop - invert level

Oil drainage pipes levels - 300mm concrete


Oil drainage pipes joints sealed - 300mm
concrete
Oil drainage pipes direction of flow -
300mm concrete

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 39 of 68

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Foundation - position depth & size

Face Bricks - correct make

Walls - Quality of finish

2 Manholes Walls - Facebrick jointing

Walls - Height & Level


Oil drainage pipes joints sealed - 300mm
concrete
Manhole cover - installed

Foundation - position depth & size

Face Bricks - correct make

Walls - Quality of finish

Walls - Facebrick jointing

Chamber 1 - size

3 Firetrap Chamber 2 - size

Inlet - level

Outlet - level

Level separation wall - position


Oil drainage pipes joints sealed - 300mm
concrete
Manhole cover - installed

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 40 of 68

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Foundation - position depth & size

Oil Dam dimensions - length, width, depth

Waterproofing - installed

Shuttering - install

Oil Dam floor - concrete & reinforcing.

4 Oil dam - Type A Concrete Oil Dam walls - concrete & reinforcing.

Inlet - level

Outlet - level

Ladder - istalled

Cover - installed

Earthing

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 41 of 68

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)

Foundation - position depth & size

Oil Dam dimensions - length, width, depth

Waterproofing - installed

Oil Dam floor - sand bedding

Concrete & Reinforcing - installed.

Face Bricks - correct make

Walls - Quality of finish

Walls - Facebrick jointing

Inlet - level

Outlet - level
Oil drainage pipes joints sealed - 300mm
concrete
Manhole cover - installed

Sealing

Side wall - river sand bedding


Oil dam - Type
5
B Brick
Sump - depth & size

Valve chamber - level & size

Valve chamber - Quality and facebrick

Drizit bags - installed

Outlet Valve - level

Drizit bag - level

Drainage pipe - outlet level

Valve Chamber cover - size

Flow stop installed - invert level

Side wall - river sand bedding installed

Water Pump - installed

Water Pump probes - installed

Water Pump controls & JB - installed

Earthing - Installed

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 42 of 68

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Foundation - position, depth & size

Support - correct height


Stainless Steel
6
Fire Walls
Module 'A' - correct position

Module 'B' - correct position

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 43 of 68

Handover Checklist for Civil Works: Transformer Bund Area, Oil Dam & Fire Wall
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name
Transformer Oil Containment
1
Area

2 Manholes

3 Firetrap

4 Oil dam

5 Stainless Steel Fire Wall

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 44 of 68
– Annex B8 – Stage 8: Steelwork

Quality Control Checksheet for Steelwork


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Steelwork delivery inspection - verification


1 Steelwork Delivery
of material condition & galvanising.

Assembling.

Steelwork : Installed, plumbed & levelled.


2
______________________ Bolts torqued.

Grouting

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 45 of 68

Handover Checklist for Steelwork


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name

1 Steelwork Delivery

2 Steelwork Installation

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 46 of 68
– Annex B9 – Stage 9: Fencing

Quality Control Checksheet for Fencing


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Fencing delivery inspection - verification of


1 Fencing Delivery
material condition & galvanising.
Assembling

Installed, plumbed & levelled

2 Palisade Fence Bolts sheared

Earthing

Labelling

Assembling

Installed, plumbed & levelled


3 Diamond Mesh Fence
Earthing

Labelling

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 47 of 68

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Installation
4 Precast Walls
Labelling

Installed, plumbed & levelled

Locks
5 Gates
Earthing

Labelling

6 Boundary Fence & Gate Installation

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 48 of 68

Handover Checklist for Fencing


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name

1 Fencing Delivery

2 Palisade Fence

3 Diamond Mesh Fence

4 Precast Walls

5 Gates

6 Boundary Fence & Gate

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 49 of 68
– Annex B10 – Stage 10: Power Transformer Delivery & Assembly

Quality Control Check sheet for Primary Equipment: Power Transformer Delivery & Assembly
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)

Transformer Delivery from supplier - Health


& Safety Plan approved
Supplier accept that site is accessible for
the delivery of the transformer.
Transformer plinth & slipway - concrete
works completed and cured.
Transformers - Delivery & Transformer position indicated on the
1
Installation by Supplier plinth.
Supplier tests conducted and witnessed
by Control Plant Maintenance.
Transformer Delivery Checklist to be
completed by the Plant representative.
Refer to Document: DFM 34-1901

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 50 of 68

Handover Checklist for Primary Equipment: Power Transformer Delivery & Assembly
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name

Transformers - Delivery &


1
Installation by Supplier

Accepted by Control Plant Representative:

Name Signature Date

Accepted by Plant Representative:

Name Signature Date

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 51 of 68
– Annex B11 – Stage 11: Primary Equipment Installation

Quality Control Checksheet for Primary Equipment Installation - Power Transformer


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Transformer with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Oil levels – conservator – tap-changer

Ensure no oil leaks. Check at sampling


points, bushings and radiator couplings.

Drawing No:__________
Bushings - Check for broken/chipped.

Check for acrylic covers on MV bushings


Type:_________________ (Covers to have drain holes to prevent
moisture build-up)

Silica Gel Breather - correctly installed


and correct colour.
Make:________________
Labelling

Earthing installation correct.


Serial No:_____________

Oil sample tests & results

Overall Condition

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 52 of 68
Quality Control Checksheet for Primary Equipment Installation - Auxiliary Transformer
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)

Verify items received are in accordance with the Bill


Auxiliary Transformer of Material, LAP List and Scope of work (correct
voltages etc.)

Delivery from supplier - general condition.

Installation

Orientation
Drawing No:__________
Oil levels – conservator

Ensure no oil leaks. Check at sampling points,


Type:_________________
bushings and radiator couplings.
Bushings - Check for broken/chipped.
Check for acrylic covers on MV bushings (Covers to
have drain holes to prevent moisture build-up)
Make:________________
Silica Gel breather - correctly installed and correct
colour.

Labelling
Serial No:_____________
Earthing installation correct.

Oil sample tests & results

Overall Condition

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 53 of 68

Quality Control Checksheet for Primary Equipment Installation - NECRT's


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)

Verify items received are in accordance


NECRT with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Orientation
Drawing No:__________
Oil levels – conservator
Ensure no oil leaks. Check at sampling
Type:_________________ points, bushings and radiator couplings.
Bushings - Check for broken/chipped.
Check for acrylic covers on MV bushings
(Covers to have drain holes to prevent
moisture build-up)
Make:________________ Silica Gel breather - correctly installed
and correct colour.

Labelling

Serial No:_____________
Earthing installation correct.

Oil sample tests & results

Overall Condition

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 54 of 68
Quality Control Checksheet for Primary Equipment Installation - Capacitor Bank
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Capacitor Bank with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Bushings - Check for broken/chipped.

Drawing No:__________
Earthing correct.

Labelling
Type:_________________

Overall Condition

Make:________________

Serial No:_____________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 55 of 68

Quality Control Checksheet for Primary Equipment Installation - Circuit Breaker (Post)
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Circuit Breaker with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Drawing No:__________
Orientation correct.

Bushings - Check for broken/chipped.


Type:_________________

Earthing correct.

Function / Pre-commissioning testing


Make:________________

Labelling

Overall Condition
Serial No:_____________

Breaker filled with gas (if required)

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 56 of 68

Quality Control Checksheet for Primary Equipment Installation - Circuit Breaker (Indoor)
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Circuit Breaker with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Drawing No:__________
Orientation correct.

Bushings - Check for broken/chipped.


Type:_________________

Earthing correct.

Function / Pre-commissioning testing


Make:________________ (include compliance to racking
requirements)

Labelling

Serial No:_____________ Overall Condition

Switch room floor/Trench tolerance to


comply with indoor switchgear
manufacturer requirements.

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 57 of 68

Quality Control Checksheet for Primary Equipment Installation - Current Transformer


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Current Transformer with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Drawing No:__________
Orientation

Oil levels - no leaks.


Type:_________________

Bushings - Check for broken/chipped.

Earthing correct.
Make:________________

Labelling

Overall Condition
Serial No:_____________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 58 of 68

Quality Control Checksheet for Primary Equipment Installation - Voltage Transformer


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Voltage Transformer with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Drawing No:__________
Oil levels - no leaks.

Bushings - Check for broken/chipped.


Type:_________________
1 Earthing correct.

Labelling
Make:________________

Overall Condition

Serial No:_____________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 59 of 68

Quality Control Checksheet for Primary Equipment Installation - Isolators


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)

Verify items received are in accordance


Isolator with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Drawing No:__________ Bushings - Check for broken/chipped


porcelain.

Earthing correct.
Type:_________________

Function / Pre-commissioning testing

Overall Condition
Make:________________

Serial No:_____________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 60 of 68

Quality Control Checksheet for Primary Equipment Installation - Earth Switch


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Earth Switch with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Drawing No:__________
Orientation

Earthing correct.
Type:_________________

Function / Pre-commissioning testing

Overall Condition
Make:________________

Serial No:_____________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 61 of 68
Quality Control Checksheet for Primary Equipment Installation - Surge Arrestors
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Surge Arrestor with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation

Bushings - Check for broken/chipped.

Drawing No:__________
Earthing correct.

Labelling
Type:_________________

Overall Condition

Make:________________

Serial No:_____________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 62 of 68

Quality Control Checksheet for Primary Equipment Installation - Post Insulators


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) Required (Y/N) Witnessed (W)
Verify items received are in accordance
Post Insulator with the Bill of Material, LAP List and
Scope of work (correct voltages etc.)

Delivery from supplier - general condition.

Installation
Type:_________________

Bushings - Check for broken/chipped.

Overall Condition

Make:________________

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 63 of 68

Handover Checklist for Equipment Installation


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Sub Section Signature Assurance Signature
Assurance
Check : Name
Check : Name
Installation
1 Auxiliary Transformer Function testing

Data Captured

Installation

2 Capacitor Banks Function testing


Data Captured

Installation

3 Circuit-breakers - Post Function testing


Data Captured

Installation
Circuit-breakers -
4 Function testing
Indoor
Data Captured

Installation

5 Current transformers Function testing


Data Captured

Installation

6 Earth Switch Function testing

Data Captured
Installation

7 Isolators Function testing

Data Captured
8 Post Insulators Installation

Installation

9 Necrt's Function testing


Data Captured

Installation

10 Power Transformer Function testing

Data Captured
Installation

11 Surge arresters Function testing

Data Captured
Installation

12 Voltage transformers Function testing

Data Captured

Accepted by Project Manager:

Name Signature Date

Accepted by Plant Engineering Manager (Data captured):

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 64 of 68
– Annex B12 – Stage 12: Conductor, Busbars & Clamps Installation

Quality Control Checksheet for Conductor, Busbars & Clamps Installation


1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Delivery inspection - compliance to


specification
Busbars/Stringers - Conductor Installation
1 No:___________________
Type:__________________ Correct strain/suspension insulators

Sag & Tension


Delivery inspection - compliance to
specification
Busbars - Tubular Installation
2 No:___________________
Type:__________________ Correct support insulators

Correct size & lengths

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION PRIMARY PLANT PRIOR TO Unique Identifier: 240-87605434
HANDING OVER FOR COMMERCIAL OPERATION
Revision: 1
Page: 65 of 68

Holding Point Photo Required Verified (V)


Item Checklist QC items to check or supply Contractor Signature COW Signature
Required (Y/N) (Y/N) Witnessed (W)

Delivery inspection - compliance to


specification
Installation

Conductor jumper size


Jumpers, Clamps & Spacers
3
Position:_______________
Correct clamp

Correctly torqued/crimp

Clearances correct
Delivery inspection - compliance to
Shieldwire specification
4 No:___________________ Installation
Type:__________________
Sag & Tension

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 66 of 68

Handover Checklist for Civil Works: Conductor, Busbars & Clamps Installation
1 Project name:
2 Contract/Order No:
3 Contractor:
4 COW:

Contractor -
COW - Quality
Quality
Item Checklist Signature Assurance Signature
Assurance
Check : Name
Check : Name
Busbars/Stringers -
1
Conductor

2 Busbars - Tubular

3 Jumpers, Clamps & Spacers

4 Shieldwire

5 Data Captured

Accepted by Project Manager:

Name Signature Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 67 of 68
– Annex B13 – Stage 13: Provisional Handover
(Project Provisionally handed over for final Commissioning)
1 Project name:
2 Contract/Order No:
3 Project Manager:

Handover per stage


Received by Project
Stage Activity completed for switch Date
Manager
on (Y/N)
1 Civil Works: Platform
2 Civil Works: Control Building
3 Civil Works: Subsoil drainage
4 Civil Works: Earthmat Installation
Civil Works: Equipment Foundations &
5
Cable trenches
6 Civil Works: Roads, Stoning & Kerbing
Transformer bund wall, oil dam and fire
7
wall
8 Steelwork Erection
9 Fencing
Power Transformer Delivery &
10
Assembly
11 Primary Equipment Installation
12 Conductors, busbars & clamps

Plant and Equipment provisionally handed over in order to arrange final commissioning

Accepted by: Project Manager (Name & Signature) Date

Accepted by: Design Engineer (Name & Signature) Date

Accepted by: Plant Sector Engineer (Name & Signature) Date

ESKOM COPYRIGHT PROTECTED

When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the user
to ensure it is in line with the authorized version on the WEB.
Document Classification: Controlled Disclosure
QUALITY CHECKLIST FOR DISTRIBUTION SUBSTATION Unique Identifier: 240-87605434
PRIMARY PLANT PRIOR TO HANDING OVER FOR
COMMERCIAL OPERATION Revision: 1
Page: 68 of 68
– Annex B14 – Stage 14: Final Handover
1 Project name:
2 Contract/Order No:
3 Name of Project Manager:

Handover per stage completed Received by Project


Stage Activity Date
(Y/N) Manager

1 Civil Works: Platform

2 Civil Works: Control Building

3 Civil Works: Subsoil drainage

4 Civil Works: Earthmat Installation

Civil Works: Equipment


5
Foundations & Cable trenches
Civil Works: Roads, Stoning &
6
Kerbing
7 Steelwork Erection

8 Fencing
Power Transformer Delivery &
9
Assembly
10 Primary Equipment Installation

11 Conductors, busbars & clamps

Final Commissioning Complete

Accepted by: Project Manager (Name & Signature) Date

Accepted by: Design Engineer (Name & Signature) Date

Accepted by: CNC Sector Manager (Name & Signature) Date

Accepted by: Plant Engineering Manager (Name & Signature) Date

Accepted by: Plant Sector Engineer (Name & Signature) Date