Pestpc3 PDF
Pestpc3 PDF
THIS PAGE LEFT BLANK INTENTIONALLY
ii
Wind and Solar Plant Collector Design Working Group Contributors
iii
Wind and Solar Plant Collector Design Working Group History
The Wind and Solar Plant Collector Design working group was initiated by the IEEE Power and
Energy Society in 2007 in response to the extreme growth in wind power installations in the
United States that kicked off in 2005. The Power and Energy Society saw a need for broad
distribution to its members of the significant issues that were unique to wind power plants.
Original research papers were not what were sought; rather a gathering of established best
practices and guidelines pertinent to the practical design of a utility scale wind power plant.
To this end, Dick Piwko, chair of the PES Wind Power Coordinating Committee, began this
endeavor by creating the working group and recruiting action officers. First to step to the plate
as working group chair was Ernst Camm who recruited the initial working group team members.
The group met four times in 2008 at both IEEE and AWEA conferences laying the foundation of
the group’s efforts and setting four years of productivity in motion. The first five papers were
presented at the 2009 PES General Meeting in Calgary.
Following this, Mitch Bradt took the chairmanship, shepherding the publication of four
additional papers at the 2010 PES Transmission and Distribution Conference & Expo in New
Orleans, followed shortly thereafter by a full day tutorial on Wind Plant Collector Design at the
2010 PES General Meeting in Minneapolis. The working group at this point had swelled to 45
contributing members.
Michael Starke became chair followed by Wayne Dilling. During their chairmanships the
remaining papers in this compendium were presented at several different PES conferences, along
with presentations on Testing and Commissioning, NEC versus NESC, and topics on personal
safety. The domain of this group was expanded from just wind to include solar, and a task force
was created for Wind Plant Grounding for Personal Safety. The task force has created its own
presentations and tutorials on wind plant design.
In total, more than a hundred participants and 45 active contributors collaborated to produce the
working group’s publications and presentations. The past chairs of this group want to extend
their gratitude to all these participants and to the companies and universities who supported this
working group’s activities. We hope that you find this publication valuable.
Ernst Camm, Mitch Bradt, Michael Starke and Wayne Dilling (posthumously)
Boston, MA 2016.
This work is dedicated to the memory of our friend and colleague, Wayne Dilling, who inspired
us, kept us grounded and fostered a wonderful environment of fun and productivity.
iv
TABLE OF CONTENTS
INTRODUCTION vii
Wind Power Plant Substation and Collector System Redundancy, Reliability, and
Economics 13
Design and Application of Cables and Overhead Lines in Wind Power Plants 19
v
Reactive Power Compensation for Wind Power Plants 38
APPENDIX
Abbreviations and Terms Used in Wind Power Plant Collector System Design and
Operation 74
vi
INTRODUCTION
By Andrew Leon
The wind power industry has experienced rapid growth resulting in more than 60 gigawatts of
installed wind capacity in the United States and over 300 gigawatts worldwide. Despite the
similarity to traditional utility power generation infrastructure, a number of critical design
considerations and issues unique to wind power plants (WPPs) have become evident. This recent
expansion of utility-scale renewable energy facilities led to the creation of the Wind and Solar
Plant Collector Design Working Group within the IEEE Power & Energy Society. This group
serves as a focal point within the PES for addressing topics related to the practical design issues
of collector systems for wind and solar plants.
Diverse challenges are encountered during the design and construction of wind power plants.
Typical WPPs consist of an interconnection substation, collection circuits, reactive compensation
equipment, step up transformers, as well as five main types of WTGs - each with their own
power conversion and performance characteristics. Improper system grounding can lead to
premature failure of collection circuit equipment, potentially resulting in costly repairs and
reduced availability. Utilities and system operators outline local reactive power requirements.
Mandatory compliance with these requirements can be approached in a number of different ways
each having its advantages and disadvantages. Additionally, the combination of complex
capacitive and inductive elements in a WPP can cause significant power quality issues related to
harmonics and resonance. Conventional utility design practices prioritize reliability, which is
addressed with increased levels of redundancy. In contrast, maximum economic availability of
wind turbine generators (WTGs) is the ideal focus for optimizing a new WPP.
This special publication is a compendium compiled from a series of 11 technical papers by 45
authors. These papers were published and presented by the working group to provide general
design guidance as well as to address specific issues encountered in WPPs. Covered design
principles include considerations for underground versus overhead collector lines, power
transformer specifications, reactive power compensation guidelines, as well as SCADA and
Control philosophy. Industry specific issues such as the system grounding of WPPs and
harmonic/resonance issues are discussed along with available protection and mitigation options
that may address these concerns.
The compendium is organized into two parts. A brief summary of the papers within each section
is provided for the reader. An appendix includes abbreviations & terms related to WPP collector
systems.
PART 1 Wind Power Plant Design Principles
1. “Wind Power Plant Collector System Design Considerations”
A summary of the most important design considerations for wind power plants are presented.
The configuration of feeder strings is discussed aside important design aspects such as conductor
sizing and the thermal characteristics of site-specific soil. Substation design and equipment
specifications are explained as well as the various engineering studies required to support the
overall design of a wind power plant.
vii
2. “Characteristics of Wind Turbine Generators for Wind Power Plants”
Summary of the most important characteristics of wind turbine generators applied in modern
wind power plants is presented. Various wind turbine generator designs, based on classification
by machine type and speed control capabilities are discussed highlighting their operational
characteristics, voltage and power factor control capabilities, voltage ride-through characteristics,
behavior during short circuits, and reactive power capabilities.
3. “Wind Power Plant Substation and Collector System Redundancy, Reliability, and
Economics”
Basic guidelines on design considerations for wind power plant substations and collector systems
are discussed. Wind power plant design often prioritizes aspects not normally considered in
traditional utility systems. Power loss and overall economic analysis in a typical wind power
plant is explained.
4.“Design and Application of Cables and Overhead Lines in Wind Power Plants”
This paper presents a summary of the most important considerations for wind power plant
collection system underground cable and overhead designs. Various characteristics, including
conductor selection, soil thermal properties, installation methods, splicing, concentric grounding,
and NESC/NEC requirements are discussed.
5.“Power Transformer Application for Wind Plant Substations”
Here, the application of wind power plant transformers with regard to the selection of winding
configuration, MVA rating, impedance, loss evaluation, on-load tap changer requirements, and
redundancy is presented. Wind power plants use power transformers to step plant output from
the medium voltage of the collector system to the high or extra high voltage transmission system.
6. “Wind Power Plant SCADA and Control”
This paper discusses the range of application for SCADA and control systems in a wind power
plant, the most important SCADA and control system considerations, and contractual
requirements for SCADA and control systems.
7.“Reactive Power Compensation for Wind Power Plants”
The basic guidelines for the application of reactive compensation systems to be used as part of a
wind power plant are presented. A brief history of wind plant reactive compensation systems is
discussed, including the fundamental need for reactive power compensation. This paper provides
alternatives for reactive compensation, reactive compensation analytics, and an overview of the
operating principles in various compensation devices.
PART 2 Wind Power Plant Equipment Protection and Safety
8.“Wind Power Plant Grounding, Overvoltage Protection, and Insulation Coordination”
Presents a tutorial description of the process of selecting and applying surge arresters to wind
plant medium voltage collector systems, with emphasis on the peculiar properties of this
viii
application. Proper insulation coordination is critical to preventing premature failure in wind
plant equipment. The collector systems of large wind plants require the application of surge
arresters to protect the equipment insulation from transient overvoltages. This application is
constrained by maximum operating and temporary overvoltage levels.
9. “Arc-Flash Hazard in Wind Power Plants”
A brief review of the concept of arc flash and a methodology for arc-flash hazard analysis on a
WPP collector system follows. Addressed topics include faults fed by multiple sources and
modeling of the resultant wind turbine generator fault current. The paper concludes with two
examples using the presented methodology.
10. “Wind Plant Collector System Fault Protection and Coordination”
Presents a summary of the most important protection and coordination considerations for wind
power plants. Short-circuit characteristics of both aggregate wind plant and individual wind
turbine generators, as well as general interconnection protection requirements are discussed.
Many factors such as security, reliability, and safety are considered for proper conservative
protection of the wind power plant and individual turbines.
11. “Harmonics and Resonance Issues with Wind Plants”
Summarizes the most important issues with respect to harmonics and resonances within wind
power plants. An introduction is given to provide an overview of the various power quality
related issues encountered when designing, commissioning, or operating a wind power plant, as
well as typical characteristics of the components associated with wind power plants. The many
variables which influence harmonics and resonance in wind power plants will be described with
respect to analysis methods, avoidance, mitigation, and compliance with IEEE Std 519-1992
recommended practices.
ix
1
Contributing Members: E.H. Camm, M. R. Behnke, O. Bolado, M. Bollen, M. Bradt, C. Brooks, W. Dilling,
M. Edds, W. J. Hejdak, D. Houseman, S. Klein, F. Li, J. Li, P. Maibach, T. Nicolai, J. Patiño, S. V. Pasupulati,
N. Samaan, S. Saylors, T. Siebert, T. Smith, M. Starke, R. Walling
Abstract—This paper presents a summary of the most impor- system voltage of 34.5 kV (Figure 1). In this configuration,
tant design considerations for wind power plants. Various con- turbines are connected together in a “daisy chain” style, mov-
siderations, including feeder topology, collector design, intercon- ing outward from the project substation to the furthest located
nect and NESC/NEC requirements, and design engineering stu- turbine. These feeder strings are commonly underground but
dies are discussed. may be of overhead construction as well. Each individual
feeder string may also have branch strings, connected by sec-
Index Terms— Wind turbine generator, turbine layout, tran-
sient analysis, harmonics analysis, wind power plants.
tionalizing cabinets that can make up several string paths
within a feeder string. Sectionalizing cabinets, sometimes
I. INTRODUCTION referred to as junction boxes, have separable connectors, or
elbows, that can isolate a feeder string to allow the remaining
2
3
to land owner requirements. dards may be purely local and in large WPP may vary from
Conductor sizing starts with the soil Rho data and layout of machine to machine as you cross local jurisdictions.
the collector circuit trenches. In multiple circuit trenches de- Some of the key standards bodies and regulators that should
rating factors must be applied due to mutual heating effects of always be reviewed include:
close proximity circuits. Commercially available software is 1. IEC and IEEE - both standards bodies have a large
typically used to perform an analysis on various circuit trench number of standards that can be applied to the collec-
layouts and many variables including trench dimensions, cir- tor design. These include standards like C37 (Circuit
cuits per trench, trench spacing and soil Rho can be manipu- Breakers, Switchgear, Relays, Substations, and Fus-
lated until the optimum trench layout is achieved. In some es), C57 (Transformers), C62 (Surge Arresters), and
other emerging standards. IEC standards include the
cases where specific circuit ampacities are required the cables
IEC 61400 Series (Wind turbine generator systems).
may need to be oversized due to trench parameter limitations.
2. ISO has a number of standards that apply to wiring
and cables.
IV. SUBSTATION DESIGN 3. Many national organizations have taken ISO or IEC
The planning of the substation and switchyard is not strictly standards and renumbered them for local use.
focused on a single design but does have some flexibility. It is 4. State and provincial regulators. In many cases the
important, however, that the substation be planned for reliabil- regulators in a sub-jurisdiction (e.g. a state in the US
ity, operability, as well as maintainability. or a province in Canada) have developed additional
Substation designs typically consist of both medium- guidelines that need to be followed.
voltage (MV) and high-voltage (HV) bus configurations that 5. Local zoning. Most local zoning agencies have
are interconnected through wye-wye, delta-wye, or even wye- height, noise, setback, landscaping and road require-
delta transformers. Wye-wye transformers with buried tertiary ments that are not covered in any other standard.
are often used. In wind plant substations, the medium- voltage These can quickly impact collector and WPP design
buses are primarily of the single and sectionalized bus type by restricting what can be done and how it can be
while the high voltage buses could be composed of five dif- done. In almost every case local zoning and regula-
ferent types: ring, single, sectionalized, main and transfer, tion reduces the number of options that are available
breaker-and-a-half, double breaker double bus. for designing and building the collector and place-
The location of substation(s) will typically be at the wind ment of WTGs.
plant site, but if the POI is several miles away there may be a 6. Utility requirements. In most utilities there are re-
need for switching station(s) for locating line breakers and quirements that are set by the planning and standards
associated equipment. There are many IEEE substation design groups. While many of these mirror the requirements
standards and guidelines such as IEEE-605 for rigid bus struc- of national and international standards, some do not,
tures and IEEE-80 for substation grounding. These are availa- and for good reason in most cases. The design of the
ble as references in the planning and engineering of substation existing grid may not match the ideal that was used to
facilities. Also refer to a companion WG paper on Wind Pow- create the international standards and to help main-
er Plant Substation and Collector System Redundancy, Relia- tain the function of the grid, each utility has devel-
bility, and Economics [10]. oped standards that keep the grid functioning.
7. Manufacturer's requirements and standards. As trans-
V. INTERCONNECTION REQUIREMENTS AND REGULATIONS formers, wind turbines, and other equipment are se-
In the United States, Federal requirements for certain as- lected they come with their own set of standards and
pects of WPP interconnection are contained in the provisions restrictions. To keep warranties in force, these will
of FERC Order 661-A [13], which have been adopted as Ap- have to be reviewed and accounted for in the collec-
pendix G to the Large Generator Interconnect Agreement tor design.
(LGIA). This Appendix contains requirements for voltage In all there will be many documents that will have to be
ride-through (VRT), power factor design criteria (reactive reviewed and it is not unusual for them to conflict with each
power), and Supervisory Control and Data Acquisition other. In most cases, that conflict can be resolved most easily
(SCADA) capability. Other provisions contained in the LGIA by starting with the most local requirements. They are typical-
for each project include metering and protection requirements. ly the easiest ones to get changed when a higher authority
Note, for WPPs located within the Electric Reliability Council conflicts with them.
of Texas (ERCOT) region, similar interconnection require-
ments exist, but do not necessarily follow FERC guidelines. VI. NESC AND NEC CONSIDERATIONS FOR WIND POWER
Refer to companion WG paper for additional details [4]. PLANTS
There are a large number of agencies that can impact the The application of the National Electrical Code (NEC) and
design and construction of the collector system. They range the National Electrical Safety Code (NESC) to wind power
from local zoning agencies to international agencies. The final plants is in general a shared concern. Local jurisdictions also
design of the collector system will be heavily dependent on have rules, ordinances, and laws that may supersede both the
the regulations and standards that you are required to follow. NESC and NEC, so thorough advance research with local
Some national standards, like the National Electric Code professional engineers, electricians, and inspectors is critical.
(NEC) may apply in some states and not in others. Other stan-
3
4
Any WPP with a medium-voltage (MV) collector system VII. TURBINE STEP-UP TRANSFORMER APPLICATION
design and construction may be considered by some to be sub- For wind turbines in the MW rating category, a dedicated
ject to the NESC rules, but inside the wind turbine tower the step-up transformer is used for each turbine.
best approach is to assume that both codes may apply. The
tower is both a “generation” plant, which is covered by the A. Transformer Type
NESC, but it also has aspects of being an industrial site, which Padmounted three-phase distribution transformers are used
falls under the NEC. Regardless, each US state has the right for WTG step-up transformers. These transformers are a
to enforce whichever code or create new ones for its own pur- commodity and meet the required function at minimum cost.
poses. It is also well known that there are now many states WTGs with transformers in the nacelle or on platforms in the
with permitting laws and regulations specifically for WPP tower are outside the scope of this document since it is pro-
which could impact the application of these safety rules. vided by the WTG manufacturer as part of the WTG installa-
On the collector system NESC rules may apply because tion.
they involve grounding (sections in the 90’s), overhead con-
B. Winding Connection
ductor clearances and loadings (Part 2), and underground ca-
ble clearances and considerations (Part 3). A quick example Many WTG manufacturers specify delta (MV) – grounded-
of each would be: For grounding – collector cables or over- wye (LV) winding connections for wind turbine step-up trans-
head must be grounded at least every quarter mile. As a spe- formers. The reasons for this connection are to provide isola-
cial note - when grounding a collector cable special considera- tion of the WTG from the zero-sequence behavior of the col-
tion must be taken to cross ground all sheaths and external lector feeder; e.g., unfaulted phase voltage rise during ground
grounds to reduce induced effects (see IEEE 575-1988). For faults, and to provide a solid ground source for the LV side
overhead (sections in the 200’s) – overhead collector conduc- connected to the WTG.
tors must be designed for local temperature, ice and wind Grounded wye-wye transformers are more commonly used
loading conditions and maintain minimum clearance distances for utility load-serving applications, and are thus more widely
from the ground surface and other objects and structures. For available. There is a common misconception that this connec-
underground (sections in the 300’s) – cables must be set at tion provides a ground source to the collector feeder, in the
proper burial depths and have certain underground clearances. case that that the feeder becomes isolated from the collection
NESC rules are generally self-regulated by the power and substation. This is only correct when the WTG is a grounded
utility industry, but a few states have inspectors who will
source, which is generally not the case.
check new installations.
In the tower the best approach is to assume both the C. Transformer Protection and Switchgear
NESC and NEC may apply. From the NESC it is mainly the Padmounted transformers are usually protected by internal
grounding rules and the supply station rules in Part 1 (sections fuses. Due to the short-circuit current available in most wind
in the 100’s), which may apply and these would also include farm applications, current-limiting fuses are usually needed.
the rules for WTG unit transformers whether located inside or These fuses are either coordinated with expulsion fuses, or
outside of the tower. From the NEC there are applicable rules full-range current-limiting fuses are applied. Since fusing
for the LV cables and equipment that may apply. Such rules options are limited for 34.5 kV delta configurations, careful
include cable ampacities, cable routing, small LV transformer consideration must be made when selecting coordinated fus-
use, LV circuit protection, and cabinets. There are also local ing to ensure the fuse combination is matched for the applica-
(city, county, and/or state) inspectors who interpret the NEC tion in which it will be applied.
in different ways, so advance meetings with the local authori- In some applications it can be difficult to ensure that prima-
ties are important to determine what is most important to ry (MV) fuses can adequately protect against faults at the
them. point of secondary interconnection to the WTG equipment,
As to arc-flash considerations, the most basic approach particularly if a delta-wye transformer is used (in the case of
would be to consider the NESC arc-flash rules from Section single-phase faults, due to the lack of one-for-one correspon-
410 to the collector system and the NFPA 70E rules to the dence between primary and secondary phases.)
inside of the tower. This would provide good coverage of the LV molded-case circuit breakers are sometimes installed
inside equipment and the proper approach to the power lines inside the transformer secondary compartment to provide
outside and will define the proper personal protective equip- coordinated protection through to the end of the secondary
ment (PPE) for both working situations. cables and also may help in reducing arc-flash levels. Atten-
Lastly, there are rules for safe practices once the site is tion needs to be given to the ambient temperature for this
operational that must also be followed by workers. These mounting location, with respect to the molded case circuit
include the rules in Part 4 (sections in the 400’s) of the NESC, breaker specifications.
in NFPA documents, and in federal (OSHA) and state occupa- An internal primary MV oil switch, typically referred to as
tional safety rules and regulations when working in a tower or a LBOR (Load Break Oil Rotary) switch is commonly speci-
on the power line. fied to allow isolation of the transformer and permit continued
operation of other “downstream” WTGs.
4
5
D. Transformer Primary Terminals the wind on the transformer; C57.91’s algorithms assume still
Transformer primary terminals can either be live-front air. For this wind plant, an under-sized transformer was suc-
bushings, or separable connector (“elbow”) bushings. There cessfully applied.
are two different types of elbows in IEEE standards: load- Selection of transformer rating on a thermal basis must
break elbows which are rated up to 200 A load current, and consider factors such as additional loading on transformers
dead-break elbows which are rated for up to 600 A. Load- due to passage of harmonic currents. In one wind power plant
break elbows allow the transformer connections to be opened application, WTG unit transformers failed from overloads
“live” under load current conditions, using a hot-stick. The caused by grid background harmonics resonating with WTG
circuit must be de-energized to operate (make or break) the power factor correction capacitors. Harmonics can have a
600 A elbow connections. disproportionate impact on transformer heating. Refer to
When elbows bushings are applied, it is common to specify C57.110.
a feed-through bushing configuration, which provides two 10000
bushings for each phase, and an internal connection between
each pair of bushings. This allows both the substation-side
and remote-end side cables in a daisy-chain radial configura-
formers rated 750 kVA and larger have a minimum impedance Rated kVA
5
6
output of any substation-based reactive compensation system, needed in most cases to determine TOV levels and to choose
to determine the WPP net active and reactive power flows and the best method for the mitigation of TOV due to feeder isola-
voltage profiles at the POI during different operating scena- tion and to select arrester ratings [7]. The use of high-speed
rios. grounding switches or grounding transformer banks on each
feeder will help in solving the TOV problem in most WPP
B. Short Circuit Analysis
collector circuits. The type of the WTG plays an important
This analysis, using a detailed model of the WPP as de- role in selecting which grounding method to be used.
scribed for the load flow studies above, is performed to de-
termine momentary and interrupting ratings of circuit break- E. TRV Analysis for Circuit Breakers
ers, cable ratings for proper short-circuit withstand capabili- The Transient Recovery Voltage (TRV) analysis is needed
ties, and momentary ratings of all equipment Special consid- in special cases where circuit breakers are used to switch ca-
eration must be given to the WTG short-circuit contribu- pacitor banks with current-limiting reactors (CLRs) in series
tions[5], [12]. Both the maximum and minimum short circuit or where current-limiting reactors are used to limit feeder fault
current contribution from the grid should be considered. It currents. The very high inherent frequencies of CLRs can
should also be noted that, the line-to-line or single-line-to- challenge the ability of the circuit breaker to interrupt succes-
ground faults can result in higher short circuit currents than sively and may in some cases require TRV “taming” capaci-
three-line-to-ground faults in some WPP configurations. tors to be applied across the circuit breaker or connected
phase-to-ground.
C. Harmonics Analysis
It is realized that due to the significant amount of capacit- F. Grounding Studies
ance in a typical WPP, there is a high potential for resonance The overall grounding design of the WPP should begin in
problems to occur. That can result in unacceptable levels of an early stage of the project and involves the substation, col-
harmonic current distortion at the substation capacitor banks, lector system, and tower grounding. Data must be acquired on
significant voltage distortion at the MV bus of the plant main soil resistivity, short-circuit duty at different locations in the
substation, and unacceptable harmonic current injected from collector circuit, and short-circuit duty at the POI. Soil resis-
the plant at the POI. tivity can vary widely in the landscape of the project and
The first stage is to collect the data needed for harmonic should be measured in many locations. The collected data is
analysis such as measuring background harmonic voltages at applied in grounding software to obtain best design geometry,
the POI and to obtain power quality test results for the WTG. ground potential rise, and step and touch potentials [9].
Measurement of background harmonics may be useful even if
switched capacitor banks are not used in the WPP. The second G. Arc Flash Assessment Studies
stage is to use the appropriate frequency dependent models for Arc-flash studies for the WPP will vary with the applicable
different types of WTG, padmount transformers, collector code. For MV collector circuits under the NESC an assess-
system cables and overhead lines, shunt capacitor and reac- ment of the cal/cm2 levels throughout the system will be re-
tors, substation transformer and equivalent model for the quired. That assessment uses a short circuit evaluation and
transmission network. Appropriate frequency-dependent mod- the knowledge of the length of time it takes to clear the fault at
els should be used to represent the transmission system. This any given location. These two values are then used in a loo-
can be a complex task, which can be simplified by modeling kup table in the NESC to define the minimum level of PPE.
the system for several buses after the POI. The third stage is to For locations under the NEC the proper standard for an arc-
perform frequency scans and harmonics load flow. The fre- flash assessment is the NFPA 70E. This standard defines a
quency scans is used to identify series and parallel resonance detailed procedure that uses a series of lookup tables or an
problems while harmonics load flow is used to calculate har- assessment study can be done that accomplishes the same
monic distortion indices to determine if the relevant IEEE goal. The basic results of an NFPA 70E assessment will be a
standards are satisfied in the WPP. Finally, solutions to over- set of information labels for various pieces of apparatus and
come identified harmonic problems such as filter installation switchgear that will inform the worker of the arc flash hazard
or changing the size of substation capacitor banks should be level that must be prepared for in terms of cal/cm2 and the
investigated [6]. appropriate PPE level. The NESC assessment results must be
communicated to the workers, but does not require posting
D. Temporary Overvoltage and Insulation Coordination Stu- any labels, and also does not exclude it. To best address these
dies details, the WG is planning a future separate paper on arc-
There is a potential for severe temporary overvoltage to flash assessment for WPPs.
develop in WPP collector circuit when a single line to ground
H. Other Special Studies
fault occurs on one of the plant feeders. Transient analysis is
needed to determine the level of TOV and to assess the dam- These studies include protection and coordination studies
age possibility of surge arresters in WPP collector circuit due for the WPP and reactive compensation system (if any),
to temporary overvoltages. SCADA, communication, and control interaction studies, and
A detailed transient simulation with accurate WTG model voltage ride-through studies (in cases where alternative tech-
using an Electromagnetic Transient Program (EMTP) is nologies from that used in the System Impact Study are consi-
6
7
dered). [22] IEEE Std. C57.110-2008, IEEE Recommended Practice for Establishing
Liquid-Filled and Dry-Type Power and Distribution Transformer Capa-
bility When Supplying Nonsinusoidal Load Currents.
IX. REFERENCES
[1] Robert Zavadil, Nicholas Miller, Abraham Ellis, and Eduard Muljadi,
“Making Connections [Wind Generation Facilities],” IEEE Power &
Energy Magazine, vol. 3, no. 6, pp. 26-37, Nov.-Dec. 2005.
[2] E. Muljadi, C. P. Butterfield, A. Ellis, J. Mechenbier, J. Hochheimer, R.
Young, N. Miller, R. Delmerico, R. Zavadil, and J. C. Smith, “Equiva-
lencing the collector system of a large wind power plant,” in Proc. 2006
IEEE Power Engineering Society General Meeting, Montreal, Canada,
June 2006.
[3] M. Behnke, A. Ellis, Y. Kazachkov, T. McCoy, E. Muljadi, W. Price,
and J. Sanchez-Gasca, “Development and Validation of WECC Variable
Speed Wind Turbine Dynamic Models for Grid Integration Studies,” in
Proc. 2007 WindPower Conference, Los Angeles, USA, June 2007.
[4] Wind Plant Collector Design WG, “Reactive Power Compensation for
Wind Power Plants,” in Proc. 2009 IEEE Power and Energy Society
General Meeting, Calgary, Canada, July 2009.
[5] Nader Samaan, Robert Zavadil, J. Charles Smith and Jose Conto, “Mod-
eling of Wind Power Plants for Short Circuit Analysis in the Transmis-
sion Network,” in Proc. of IEEE/PES Transmission and Distribution
Conference and Exposition, Chicago, USA, April 2008.
[6] Jun Li, Nader Samaan and Stephen Williams, “Modeling of Large Wind
Farm Systems for Dynamic and Harmonics Analysis,” in Proc. of
IEEE/PES Transmission and Distribution Conference and Exposition,
Chicago, USA, April 2008.
[7] R. A. Walling, “Overvoltage Protection and Arrester Selection for Large
Wind Plants,” in Proc. IEEE/PES Transmission and Distribution Confe-
rence and Exposition, Chicago, USA, April 2008.
[8] E. R. Detjen and K. R. Shah, “Grounding Transformer Applications and
Associated Protection Schemes,” IEEE Trans. Industrial applications,
vol. 28, no. 4, pp. 788-796, Jul.-Aug. 1992.
[9] Steven. W. Saylors, “Wind Farm Collector System Grounding,” in Proc.
of IEEE/PES Transmission and Distribution Conference and Exposition,
Chicago, USA, April 2008.
[10] Wind Plant Collector Design WG, “Wind Power Plant Substation and
Collector System Redundancy, Reliability, and Economics” in Proc.
2009 IEEE Power and Energy Society General Meeting, Calgary, Cana-
da, July 2009.
[11] Deepak Parmar and Jan Steinmanis, “Underground Cables Need a
Proper Burial,” Transmission & Distribution World, April 2003.
[12] Wind Plant Collector Design WG, “Characteristics of Wind Turbine
Generators for Wind Power Plants,” in Proc. 2009 IEEE Power and
Energy Society General Meeting, Calgary, Canada, July 2009.
[13] FERC Order No. 661-A, Interconnection for Wind Energy, Docket No.
RM05-4-001, December 2005.
[14] 2007 National Electrical Safety Code, C2 Standard, IEEE, 2006.
[15] 2008 National Electrical Code, NFPA 70 Standard, National Fire Pre-
vention Association, 2008.
[16] 2009 NFPA 70E Standard, National Fire Prevention Association, 2009.
[17] IEEE guide for the application of sheath-bonding methods for single-
conductor cables and the calculation of induced voltages and currents in
cable sheaths, IEEE Std. 575-1988, Nov. 25, 1987.
[18] IEEE Std. 386-2006, IEEE Standard for Separable Insulated Connector
Systems for Power Distribution Systems Above 600 V.
[19] ANSI C57.12.10-1997, American National Standard Requirements for
Transformers 230 kV and Below, 833/958 through 8333/10 417 kVA,
Single Phase, and 750/862 through 60 000/80 000/100 000 kVA Three-
Phase without Load Tap Changing; and 2750/4687 through 60 000/80
000/100 000 kVA with Load Tap Changing—Safety Requirements.
[20] IEEE Std C57.12.00-2000, IEEE Standard General Requirements for
Liquid-Immersed Distribution, Power, and Regulating Transformers
[21] IEEE Std C57.91-1995(R2004), IEEE Guide for Loading Mineral-Oil-
Immersed Transformers.
7
1
Contributing Members: E.H. Camm, M. R. Behnke, O. Bolado, M. Bollen, M. Bradt, C. Brooks, W. Dilling,
M. Edds, W. J. Hejdak, D. Houseman, S. Klein, F. Li, J. Li, P. Maibach, T. Nicolai, J. Patiño, S. V. Pasupulati,
N. Samaan, S. Saylors, T. Siebert, T. Smith, M. Starke, R. Walling
M odern wind power plants (WPPs), comprised of a Stall regulation is achieved by shaping the turbine
blades such that the airfoil generates less aerodynamic
large number of wind turbine generators (WTGs), a
force at high wind speed, eventually stalling, thus reducing
collector system, collector and/or interconnect substation
the turbine’s torque—this is a simple, inexpensive and ro-
utilize machines that are designed to optimize the genera-
bust mechanical system. Pitch regulation, on the other
tion of power using the energy in the wind. WTGs have hand, is achieved through the use of pitching devices in the
developed from small machines with output power ratings turbine hub, which twist the blades around their own axes.
on the order of kilowatts to several megawatts, and from As the wind speed changes, the blade quickly pitches to the
machines with limited speed control and other capabilities optimum angle to control torque in order to capture the
to machines with variable speed control capabilities over a maximum energy or self-protect, as needed. Some turbines
wide speed range and sophisticated control capabilities now are able to pitch each blade independently to achieve
using modern power electronics [1]. more balanced torques on the rotor shaft given wind speed
The application of WTGs in modern WPPs requires an differences at the top and bottom of the blade arcs.
understanding of a number of different aspects related to Beyond mechanical power regulation, turbines are fur-
the design and capabilities of the machines involved. This ther divided into fixed speed (Type 1), limited variable
paper, authored by members of the Wind Plant Collector speed (Type 2), or variable speed with either partial (Type
Design Working Group of the IEEE, is intended to provide 3) or full (Type 4) power electronic conversion. The dif-
insight into the various wind turbine generator designs, ferent speed control types are implemented via different
based on classification by machine type and speed control rotating AC machines and the use of power electronics.
capabilities, along with their operational characteristics, There is one other machine type that will be referred to as
voltage, reactive power, or power factor control capabili- Type 5 in which a mechanical torque converter between
ties, voltage ride-through characteristics, behavior during the rotor’s low-speed shaft and the generator’s high-speed
short circuits, and reactive power capabilities. shaft controls the generator speed to the electrical syn-
chronous speed. This type of machine then uses a syn-
II. TURBINE CHARACTERISTICS chronous machine directly connected to the medium vol-
tage grid.
The principle of wind turbine operation is based on two The Type 1 WTG is implemented with a squirrel-cage
well-known processes. The first one involves the conver- induction generator (SCIG) and is connected to the step-up
sion of kinetic energy of moving air into mechanical ener- transformer directly. See Figure 1. The turbine speed is
fixed (or nearly fixed) to the electrical grid’s frequency,
and generates real power (P) when the turbine shaft rotates
978-1-4244-4241-6/09/$25.00 ©2009 IEEE 8
2
faster than the electrical grid frequency creating a negative Soft Starter Cap Bank
slip (positive slip and power is motoring convention).
Gear Collector
IG Feeder
Box
Gear Collector
IG Feeder
Box
Figure 3: Typical Configuration of a Type 2 WTG
Figure 2: Variation of Real and Reactive Power for SCIG Figure 4: Variation of Real and Reactive Power with External Rotor Resitor
in a Type 2 WTG
9
3
Figure 6: Typical Configuration of a Type 4 WTG III. VOLTAGE, REACTIVE POWER, AND POWER FACTOR
CONTROL CAPABILITIES
The voltage control capabilities of a WTG depend on the
The Type 4 turbine (Figure 6) offers a great deal of wind turbine type. Type 1 and Type 2 WTGs can typically
flexibility in design and operation as the output of the ro- not control voltage. Instead, these WTGs typically use
tating machine is sent to the grid through a full-scale back- power factor correction capacitors (PFCCs) to maintain the
to-back frequency converter. The turbine is allowed to power factor or reactive power output on the low-voltage
rotate at its optimal aerodynamic speed, resulting in a terminals of the machine to a setpoint. Types 3 through 5
“wild” AC output from the machine. In addition, the gear- WTGs can control voltage. These WTGs are capable of
box may be eliminated, such that the machine spins at the varying the reactive power at a given active power and
slow turbine speed and generates an electrical frequency terminal voltage, which enables voltage control [2]. In a
well below that of the grid. This is no problem for a Type Type 3 WTG voltage is controlled by changing the direct
10
4
component of the rotor current (this is the component of rated output can vary from 0.8 leading to 0.8 lagging. A
the current that is in-line with the stator flux). In a Type 4 range of 0.9 leading and lagging is more typical. At power
WTG voltage control is achieved by varying the quadrature outputs below rated power, the reactive power output is
(reactive) component of current at the grid-side converter. only limited by rotor or stator heating, stability concerns,
To allow voltage control capability, the grid-side converter and local voltage conditions and it is unlikely that PFCCs
must be rated above the rated MW of the machine. Since a would be required. As with some Type 3 and 4 WTGs, it
synchronous generator is used in a Type 5 WTG, an auto- is also possible to operate the machine as a synchronous
matic voltage regulator (AVR) is typically needed. Modern condenser, requiring minimal active power output with
AVRs can be programmed to control reactive power, pow- adjustable reactive power output levels.
er factor and voltage.
The voltage control capabilities of individual WTGs are
typically used to control the voltage at the collector bus or
on the high side of the main power transformer. Usually a
centralized wind farm controller will manage the control of
the voltage through communication with the individual
WTGs. A future companion Working Group paper is
planned to discuss the WPP SCADA and control capabili-
ties.
11
5
tions. In order to meet utility VRT requirements, the set- obtainable from the generator manufacturer. Fault current
tings and operation of the turbine control system, excita- contribution for line to ground faults will depend on the
tion system and protection systems must be generally type of generator grounding used. Typical generator fault
coordinated and then fine-tuned for a specific site. current contribution can range from 4 to more times rated
current for close-in bolted three-phase faults. Fault current
VI. WTG BEHAVIOR DURING GRID SHORT CIRCUITS contribution for single-line to ground faults can range from
The response of WTGs to short circuits on the grid near zero amps (ungrounded neutral) to more than the
depends largely on the type of WTG. While the response three-phase bolted level (depending on the zero sequence
of Type 1 and Type 2 WTGs are essentially similar to that impedance of solidly grounded generators.)
of large induction machines used in industrial applications, A joint Working Group sponsored by the Power Systems
the response of Type 3, 4, and 5 WTGs is dictated by the Relaying Committee (PSRC) and the T&D Committee on
WTG controls. In short circuit calculations, a Type 1 short-circuit contributions from WTGs is currently discuss-
WTG can be represented as a voltage source in series with ing this topic. It is expected that more specific guidelines
on considerations in determining short-circuit contributions
the direct axis sub-transient inductance X d′′ . This practice
from different types of WTGs will be forthcoming.
is used to consider the maximum short-circuit contribution
from the induction generator as it determines the symme-
trical current magnitude during the first few cycles after VII. REFERENCES
the fault. A Type 1 WTG can contribute short circuit cur-
[1] Robert Zavadil, Nicholas Miller, Abraham Ellis, and Eduard Muljadi,
rent up to the value of its locked rotor current which is “Making Connections [Wind Generation Facilities],” IEEE Power &
usually on the order of 5 to 6 p.u [6]. Energy Magazine, vol. 3, no. 6, pp. 26-37, Nov.-Dec. 2005.
Type 2 WTGs employing limited speed control via con- [2] W.L. Kling, J.G. Slootweg, “Wind Turbines as Power Plants”
IEEE/Cigré Workshop on Wind Power and the Impacts on Power Sys-
trolled external rotor resistance are fundamentally induc-
tems, June 2002, Oslo, Norway.
tion generators. If, during the fault, the external resistance [3] Wind Plant Collector System Design Working Group, “Wind Power
control were to result in short-circuiting of the generator Plant Collector System Design Considerations,” in Proc. 2009 IEEE
rotor, the short-circuit behavior would be similar to Type Power and Energy Society General Meeting, Calgary, Canada, July
2009.
1. On the other hand, if the control action at or shortly after [4] Wind Plant Collector SystemDesign Working Group, “Reactive Power
fault inception were to result in insertion of the full exter- Compensation for Wind Power Plants,” in Proc. 2009 IEEE Power
nal resistance, the equivalent voltage source-behind- and Energy Society General Meeting, Calgary, Canada, July 2009.
[5] FERC Order no. 661-A, "Interconnection for Wind Energy,” Docket
Thevenin impedance representation for the WTG should No. RM05-4-001, December 2005.
be modified to include this significant resistance value in [6] Nader Samaan, Robert Zavadil, J. Charles Smith and Jose Conto,
series with the equivalent turbine inductance. “Modeling of Wind Power Plants for Short Circuit Analysis in the
Transmission Network,” in Proc. of IEEE/PES Transmission and Dis-
Other wind turbine topologies employ some type of tribution Conference, Chicago, USA, April 2008.
power electronic control. Consequently, the behavior dur- [7] J. Morreu, S.W.H. de Haan, “Ridethrough of Wind Turbines with
ing short-circuit conditions cannot be ascertained directly Doubly-Fed Induction Generator During a Voltage Dip,” IEEE Trans-
from the physical structure of the electrical generator. actions on Energy Conversion, vol. 20, no. 2, June 2005
[8] Ackermann, Thomas, ed. Wind Power in Power Systems. West Sus-
Algorithms which control the power electronic switches sex, UK: John Wiley & Sons, 2005. ISBN 13: 978-0-470-85508-9
can have significant influence on the short-circuit currents [9] Hau, Erich. Wind Turbines: Fundamentals, Technologies, Applica-
contributed by the turbine, and the details of these control- tion, Economics, 2nd Edition. Trans. Horst von Renouard. Sidcup,
Kent, UK: Springer, 2006. ISBN 13: 978-3-540-24240-6
lers are generally held closely by the turbine manufactur-
ers.
For Type 3 WTGs (DFIG), if during the fault, the rotor
power controller remains active, the machine stator cur-
rents would be limited between 1.1 to 2.5 p.u. of the ma-
chine rated current. Under conditions where protective
functions act to “crowbar” the rotor circuit, the short-
circuit behavior defaults to 5 to 6 p.u. in the case of a fault
applied directly to the WTG terminals. [7]
In turbines employing full-rated power converters as the
interface to the grid (Type 4), currents during network
faults will be limited to slightly above rated current. This
limitation is affected by the power converter control, and is
generally necessary to protect the power semiconductor
switches.
Type 5 WTGs exhibit typical synchronous generator
behavior during grid short circuits. Generator contribution
to grid faults can be calculated from the machine constants,
12
1
Contributing Members: E.H. Camm, M. R. Behnke, O. Bolado, M. Bollen, M. Bradt, C. Brooks, W. Dilling,
M. Edds, W. J. Hejdak, D. Houseman, S. Klein, F. Li, J. Li, P. Maibach, T. Nicolai, J. Patiño, S. V. Pasupulati,
N. Samaan, S. Saylors, T. Siebert, T. Smith, M. Starke, R. Walling
C onventional utility design practices for substations and possible, and reconfigure the system appropriately to ensure
distribution systems are typically very different than the service continuity. Designs for increased reliability require
those applied for the medium-voltage collector system, large initial capital investments, increase the land area
collector and/or interconnect substation, and high-voltage required for the design, and can increase system losses and
transmission line of a wind power plant (WPP). This is due to complexity. These initial investments are justified by the
substantial differences in purpose and economics of these two value of uninterrupted service to the utility consumers. Since
respective applications. For example, the economic disruptions as brief as a few cycles can result in significant
incentives for a WPP are measured by availability, while production losses in manufacturing operations [2], the higher
utility designs focus on reliability, which often requires cost of the reliability design is justified by the increased
increased levels of redundancy. Due to incentives, such as the continuity of service.
Federal Production Tax Credit (PTC) in the United States, The variability of the wind forces the WPP to operate as a
provided for WPP production the economic penalties of source of energy, with a limited capacity value. Thus, the
inefficiency in a WPP are often substantially greater than requirements for service continuity and reliability are not as
those applied to a typical utility application. In contrast to critical as in the utility system design. However, the value of
conventional thermal/nuclear power plants, an off-line WPP “green” power is increasing and WPPs are now the most
can return back on-line in much less time; it also has the significant contributors to “green” power production targets.
advantage of operating at partial power output levels based on In addition to this significant requirement, the WPP
individual wind turbine generator (WTG) availability. infrastructure must be designed to efficiently deliver energy.
To optimize an electrical system design for a WPP, the Thus, consideration of economics and availability are more
life-cycle cost implications of various aspects such as lost critical in the design. A WPP requires auxiliary power for
availability, full load losses, and no-load losses must be WTG heaters, fan, auxiliary motors, and transformer no-load
considered. As discussed in [1], three economic factors losses when the WPP is not producing power due to wind
condense the complexities of the WPP business model into a unavailability; the WPP will need to buy power from the
form that can be conveniently used in simple spreadsheet utility at a rate which may be higher the purchased power rate.
calculations to optimize electrical system design for
1 2 3
Collector substation(s) for WPPs typically use an open-air Fig. 1. Single bus arrangement.
buswork design with single bus or sectionalized bus
arrangements. The latter design is typical for large WPPs
(typically 80 MW or larger.) The single bus design shown in
Figure 1 is simple and has the lowest overall cost, but has the
lowest reliability. The sectionalized bus arrangement shown
in Figure 2 enables continued availability when one
transformer is out of service. The economic value of the
redundancy offered by the second transformer can be
evaluated by considering the value of the increased energy
production through the life of the WPP. A detailed example of
redundant transformer evaluation is given in [1].
The design of the interconnect substation, if separate from
the collector substation, is largely dictated by the interconnect
requirements. The simplest design can be a pole-mounted
disconnect for a small WPP. A more typical design for larger
WPPs not involving an additional transformation is shown in
Figure 3. In some cases, a ring bus arrangement as shown in
Figure 4 is required for reliability at the point of interconnect.
For WPPs where a second transformation of voltages occur
(typically for interconnection voltages of 345 kV and above),
a single bus design is typical.
There are six different bus configurations for consideration
when designing the substation of a new WPP. Table I
compares the cost and reliability associated with each, noting
that three of these would apply to medium-voltage buswork. It
is apparent that the double breaker-double bus and breaker-
and-a-half configurations have the highest reliability, but also
have the highest cost. The configurations that are utilized in
the medium-voltage bus design have relatively low reliability Fig. 2. Sectionalized bus arrangement.
compared to the more complicated buswork. Due to the
14
3
52 52
V. WIND POWER PLANT LOSS CONSIDERATION
The WPP economic evaluation involves consideration of
HV the economic impact of various electrical losses in the WPP. .
HV
There are two different approaches commonly used in
evaluation of WPP collector losses during design: (1)
T1 T2
34.5kV
34.5kV optimized design where the costs of loss reduction are traded
34.5kV Bus
off with the revenue gains realized, and (2) design to a fixed,
PT’s 34.5kV Bus
No.1 No.2 arbitrary loss goal. Where the latter practice is utilized,
typical collector system loss targets are on the order of 2% to
3%. The optimized approach can realize very substantial
incremental investment returns for long-term WPP owners.
Estimated total electrical losses in WPP are usually
52-1 52-2 52-3 52-4 52-5 52-6 52-7 52-8
15
4
and the total number of annual hours. F. Forced Loss of Energy Production
Another loss component not generally considered in the
B. WTG step-up transformer losses loss calculations for the WPP is the loss of energy due to
WTG step-up transformer losses are determined based on unavailability of electrical equipment. This would include
the no-load and load losses reported in the transformer test loss in energy production due to loss of, for example, a WTG
report or from representative data for the type and size of transformer or cable failure. Representative loss calculations
transformer involved. If the transformer is operated at less are explained in [1].
than rated kVA, the energy losses are adjusted by the square
of the ratio of the operating kVA and the rated kVA. Annual
VI. OVERALL ECONOMIC EVALUATION OF WIND POWER
energy losses are determined based on the loss factor and the
PLANT
total number of annual hours. Due to the high value of the
wind generation, and various U.S. tax code provisions, there is Based on the established economic evaluation process in
a strong incentive for WPP owners to select transformers [4], utility planning should be performed in an incremental
based on economic loss evaluation. The low loss factor of cost evaluation. When this principal is applied in WPP
WPP applications, and provisions that may require the WPP economic evaluation, especially for existing plants, the capital
to procure no-load losses during no-wind conditions at investment to reduce the next per unit losses should be
unfavorable (e.g., retail) rates, increases the relative justified by the savings from reduced losses. This can be
importance of no-load losses. For this reason, a number of further classified to two factors in utility planning process [3]:
major WPP developers are now procuring transformers with the A factor for fixed losses and the B factor for the variable
very low-loss amorphous metal cores. losses. Taking the A factor as an example, it means an initial
incremental capital investment of $A (after considering
C. Feeder and substation grounding transformer losses amortization, property taxes, insurances, asset depreciation,
and desired rate of investment return) will yield the same
Feeder and substation grounding transformer losses are
amount of cost savings from reduced fixed losses. Similarly,
also based on no-load losses from transformer test data or
the B factor means investment for variable-loss-saving capital
representative loss data. Annual energy losses are determined
investment that reaches the desired investment rate of return.
based on the total number of annual hours.
For a capital investment to reduce either fixed cost or
D. Collector and/or interconnect substation transformer variable cost, it should be justified by the annual savings from
losses the reduced cost. Certainly, if the amortization, property
taxes, insurances, and asset depreciation are all considered,
Collector and/or interconnect substation transformer losses
the model will be complicated. The A and B factors allow the
are based on no-load losses from transformer test data or
engineer to be relieved from directly dealing with these
representative loss data. If the transformer is operated at less
financial intricacies while still allowing these details to be
than rated MVA, the energy losses are adjusted by the square
fully included in design optimization. Refer to discussion
of the ratio of the operating MVA and the rated MVA.
below on how to obtain the A and B factor as a guideline for
Losses associated with cooling fans are also estimated for
economic evaluation of projects to reduce losses.
various stages of cooling. Annual energy losses are
Fixed losses are present at all times. However, the
determined based on loss factor and the total number of
associated cost when the WPP is generating will be different
annual hours.
from the cost when the WPP is not generating. When it is
generating, the reduced cost is the selling price from the WPP
E. Reactive power compensation system losses
to the grid. As a comparison, when the WPP is not generating,
Reactive power compensation system losses are estimated the cost associated with losses should be the purchase price
based on representative no-load and load losses associated from the grid to the WPP. Based on this guideline, the
with the type of reactive power compensation system. For present worth of net after-tax revenue change (increase) by a
hybrid systems consisting of a dynamic reactive power 1 kW reduction in fixed loss can be calculated as:
compensator and mechanically-switched capacitors and
reactors, losses associated with the various components must
[ ]
i
16
5
power per kWpeak per year The calculation of the unavailable hours can be a complicated
Cptc = Production tax credit, per kWh of wind process that is not covered here. However, once the average
generation unavailable hours are calculated, the economic analysis can be
life_ptc = Duration of production tax incentive performed with an evaluation factor that is derived similarly
to the derivation of the A and B factors. Reference [1]
The present value of capital investment associated with a provides the details of this unavailability evaluation.
capital investment A, with consideration of amortization,
property taxes, insurance, and the effect of asset depreciation VII. AVAILABILITY/RELIABILITY CONSIDERATIONS FOR WIND
on income taxes can be calculated as: POWER PLANTS
There are a number of factors that affect reliability and
∑
life i i
PVcap = A − A ∗ T ∗
⎡⎛ p ⎞ ⎤
A⎛⎜ p ⎞ (2) availability. The general formula for availability is
⎢⎜ ⎟ ∗ D (n )⎥ + ∗ (1 − T ) ∗ P
n =1 ⎣⎝
f ⎠n ⎝ a ⎟⎠ life MTBF/(MTBF+MTTR), where MTBF is the mean time
⎦
between failures and MTTR is the mean time to repair. The
where: reciprocal of MTBF is the failure rate.
A = Initial capital investment A redundant system increases the aggregate failure rate of
T = Income tax rate components (called the “logistics failure rate”), but reduces
p
y the overall system failure rate. In a WPP, the effect of a
⎛
⎜
⎞
⎟ = Present value of a future cash flow in year x failure on production depends on the details of the collector
⎝ f ⎠x
structure, any associated redundancy, and the extent to which
using the compound interest rate y
the failure affects the individual WTGs and their associated
D(n) = Tax depreciation of capital asset in year n
y
equipments.
⎛ p ⎞ = Present value of a uniform set of future cash The MTTR for an individual component includes several
⎜ ⎟
⎝ a ⎠x elements:
flows from year 1 until year x, at a compound • Time to discover the failure.
interest rate y • Time to travel to the site.
T = Property tax rate • Time to diagnose the cause of failure.
Life = Economic life of WPP desired after-tax • Time to obtain any needed replacement parts.
return on investment. • Time to complete and test the repair.
Hence, as (1) and (2) should be equal to each other, we can If the WPP has redundancy and can be reconfigured, the
easily find the A factor. process of system “repair” is the reconfiguration. Any failed
Similarly, we can find the B factor by finding the present individual components can be subsequently repaired with less
value of future net revenues from the capital investment to urgency regarding system availability.
reduce variable losses and the present value of the capital The individual element times in the MTTR can be reduced
investment. by remote monitoring and control, implemented in a SCADA
The present worth of future net revenues is given by: system. IEC-61400-25 is a standard for control of wind
power equipment that extends the IEC-61850 utility
automation standard by adding objects found in a WPP.
PVrev = ( p a )life × 8760 × K Loss × Cew × (1 − T ) +
i
17
6
VIII. REFERENCES
18
1
Abstract-- This paper presents a summary of the most impor- cable selection for the WPP application.
tant considerations for wind power plant collection system un- While a power cable needs to be sized for its current carry-
derground and overhead cable designs. Various considerations, ing capacity, ease of installation and handling must be consi-
including conductor selection, soil thermal properties, installa-
dered as well. The underground power cable on wind plants
tion methods, splicing, concentric grounding, and NESC/NEC
requirements are discussed. often requires trenching or plowing in the middle of a field far
from a navigable road. With wind turbines being placed ap-
Index Terms— Turbine layout, wind turbine generator, wind proximately 1000 feet apart, it would be a nuisance to change
power plant, collection system. the size of cable every 1000 feet for each wind turbine added
to a feeder string. Minimizing the number of different sizes of
I. INTRODUCTION cable used on a WPP can simplify installation, minimize the
voltage between the conductor and the grounded shield. Two with Concentric Neutral (CN) that is commonly used in WPP
insulation technologies compete in the market: insulation applications. At the center of the cable is the phase conductor,
based on mineral filled ethylene propylene rubber (EPR) and then comes a semiconducting conductor shield, next the pri-
insulation based on relatively pure cross linked polyethylene mary insulation material (EPR or TR-XLPE), a semiconduct-
(TR-XLPE). ing insulation shield, the neutral or shield, and finally an over-
all covering jacket. Since the collection system of a WPP has
B. Commonly used cables in WPP
no intentional neutral current flow, the concentric neutral is
1) EPR not used as a neutral, but rather is bonded to the earth ground
Ethylene-Propylene Rubber (EPR) compounds are thermo- system to provide shielding. Any charges induced on the out-
set, normally with a high-temperature steam curing process side of a cable will likely be shielded by this “neutral,” which
that ‘sets’ cross-linking agents. Most new EPR insulated has been grounded to a theoretical zero potential. The outer
cables are rated to 105 ºC under normal conditions and to 140 protective jacket has markings to indicate the type, manufac-
ºC for emergency conditions, giving the cable the UL Stan- turer, and other ratings of the cable.
dard 72 designation of MV-105. EPR, with its rubber compo-
nent, is more flexible, and is considered naturally more water
tree retardant than TR-XLPE and has a proven reliable record
in the field since first introduced in the early 1960’s. Howev-
er, EPR has a higher dielectric constant leading to slightly
higher losses over the lifetime of the cable and has traditional-
ly had a higher upfront cost than TR-XLPE.
2) TR-XLPE
The cross linked polyethylene insulation used today for MV
cables is significantly cleaner than the XLPE introduced in the
mid 1960’s and has been modified to inhibit the growth of
water trees, thus allowing for increased reliability for wind Fig. 1. Typical Medium-Voltage Cable with Concentric Neutral (or Shield).
farm applications. Tree retardant XLPE (TR-XLPE) insula-
tion is now the standard for MV XLPE cables. TR-XLPE is a The conductor can be either aluminum or copper with the
pure, simple unfilled polymer compound composed of greater predominant use on WPPs being aluminum due to commodity
than 96% polyethylene, the rest composed of the cross-linking pricing of copper versus aluminum, even when including life-
(cure) agents, anti-oxidants and an effective water tree retar- cycle costs. Copper has lower resistivity and higher ampacity
dant additive. TR-XLPE material has been successfully tested for a given size, while aluminum is less expensive with lighter
for MV-105 applications and several North American cable weight, making it easier to handle.
manufacturers have this certification, but it is more commonly
specified as MV-90. The MV-105 rating is not commonly
used for WPP applications since operating at the elevated D. Cable Splicing: Underground / Above Ground Splice Box-
temperature results in higher losses and can alter the soil es /Sectionalizing Cabinets
thermal resistivity by drying out a normally damp soil. Care 1) Cable splicing should be avoided as much as possible,
must also be used when specifying cable with the MV-105 but is necessary because of the limitations of practical cable
since many of the connectors and terminations are only rated length on transportable and manageable reels. The cable
for 90 ºC. splices can be underground or above ground. The main com-
ponents of an underground splice kit are the cable connector,
C. Cable Properties the shield sleeve, the splice body, and either a heat or cold
shrink jacket. Typically a marker ball is placed at the under-
Standards specify different levels of insulation thickness ground splice location and is GPS referenced for locating pur-
based on how the cables are applied. The primary factors are poses. An above-ground splice consists of a junction box,
grounding and the duration needed to clear line-to-ground also referred to as a sectionalizing cabinet that utilizes ‘elbow’
faults. 100% and 133% insulation levels are commonly avail- termination joints. There are advantages and disadvantages to
able, although other thicknesses can be custom ordered. The both types of methods for joining cables but in the end it
100% insulation level, 345 mils at the 34.5 kV rating, is the comes down to preference or may be governed by require-
most common type used in WPP applications and is allowed ments of specific cable testing. A relatively new field cable
where line-to-ground faults are cleared by upstream protection testing procedure gaining acceptance is partial discharge (PD)
within one minute; this is common for grounded circuits. testing. This type of testing has limitations in the length of
Where line-to-ground faults can be cleared within one hour, cable section that can be tested and has generally been limited
typically ungrounded circuits, 133% insulation is required. to 8,500 feet. Therefore, in order to accommodate PD testing,
Figure 1 illustrates a typical Medium Voltage (MV) Cable either for acceptance testing or future maintenance testing, the
20
3
underground sections will need to be less than this defined III. CABLE NEUTRAL (CONCENTRIC)
limitation by utilizing above-ground junction boxes where
appropriate. A. Definition
The definition of concentric, according to Merriam-
2) “Cold” Shrink Splice Webster’s dictionary, is “having a common center or axis.”
The cold shrink tube is made from elastomers with high- The definition of shield, according to Merriam-Webster’s dic-
performance physical properties. The tube is pre-stretched at tionary, is “a device or part that serves as a protective cover or
the factory and supported with a removable plastic core. The barrier.” Electrically speaking, the concentric shield wires
cold shrink tube is placed (parked) in position and the remov- hold the outside of the cable at (or near) ground potential.
able plastic pull cord core is removed. The tube collapses The National Electrical Code (NEC) states that metallic electr-
around the cable and creates a watertight seal. Depending on ically- shielding components such as tapes, wires, braids, se-
the installation conditions the cold shrink splice may take days miconducting material, or combinations thereof are the con-
to reach its preferred final state. It is imperative to follow all centric shield wires. It also states that cables rated 2400 V
of the splice manufacturer’s requirements for temperature and and higher must be shielded by a sheath or metallic path that
environment of installation. It is generally recommended that is grounded. In order to properly electrically shield the vol-
the splice set for a minimum of 24 hours before a test voltage tage of the conductor the shield wires must be grounded. This
is applied, especially when PD testing is performed. brings up a common mistake on WPP applications: calling the
concentric wires concentric neutrals. Grounding of the con-
3) “Heat” Shrink Splice centric neutral wires, or the more correct term shield wires,
every ¼ mile as stipulated in the National Electrical Safety
The heat shrink tube is made from a cross-linked polyole- Code (NESC) and NEC would only be necessary if required
fin. The tube is placed in position and heat is applied. The to limit the shield voltage rise to safe limits. In a typical WPP
heat collapses the tube around the cable and creates a water- collection system, the design is a balanced three-phase system
tight seal. Upon completion the heat shrink splice is at its that is effectively grounded, which has no intended neutral
optimal condition and will not increase in integrity after this current flow but only grounds to help carry the fault current.
point. Thus, there is no neutral wire but only a grounded concentric
shield wire. The purpose of the concentric shield wires is for
shielding and carrying fault current and is not intended to car-
E. Direct Burial (Plowing/Trenching) vs. Duct Bank
ry load current back to the source.
There are several methods of installation for the medium-
voltage cable with the most common being direct buried via B. Sizing of Cable Neutral (or Shield)
trenching or plowing. Due to the extremely long cable lengths Sizing the concentric shield wires for a WPP in the common
on WPPs, lengths of 10 miles for a single circuit are not un- three phase configuration is determined by the available fault
common. Conduit duct banks are rarely used, except for areas current. It is important to understand that, under fault condi-
of high congestion and in some cases when entering the subs- tions, the damage to the shield is more likely than damage to
tation. Plowing utilizes a plow blade that breaks up and lifts the phase conductor. During a ground fault, the shield will
the earth as it feeds the cable into a ‘shoe’. Plowing elimi- conduct almost as much as the phase conductor, and as men-
nates the need for backfilling, but is not practical in rock or tioned above, the shield is typically a fraction of the size of
other hard surfaced regions. In regions with a significant the phase conductor. One must size these wires to withstand
amount of drain tile installed, plowing is not recommended the available fault current in order to protect the cable from
since tile damage may go unnoticed causing flooding of crops damage during a fault condition. Particular attention should
or other landowner property. Also, when plowing, considera- be paid to those conductors closer to the substation where the
tion must be given to ampacity, since air pockets can develop fault currents are higher. One way to help minimize the size
between the cable and the soil, creating a thermal barrier cap- of the shield wires is to add a bare ground wire throughout
turing heat. your system to help carry the fault current. Some turbine
Trenching is probably the most utilized method for instal- manufacturers require a separate ground wire to be routed
ling cable on WPPs. Trenching methods vary widely and can with the underground collection circuit to help mitigate effects
consist of either a multi-step or a one-pass process. In the from lightning strikes to the wind turbine tower.
multi-step process a trench is dug, cable installed, backfill is
C. Single/multi Point Grounding and Cross-Bonding
added and tamped, and the surface restored. A more common
and efficient method is the one-pass process where the instal- Cross-bonding has been confused with multi-point groun-
lation is a seamless operation with the trenching, installation, ding but are very different subjects. The intent of cross-
backfill, and surface restoration being performed at the same bonding is to limit the induced voltage on the concentric
time. With trenching, it is critical to properly backfill and shield wires, which helps increase the current-carrying capa-
stamp the soil to the compaction levels identified in the cable bility of the conductor. When designing any collection system
ampacity design parameters in order to maintain proper soil it is important to take into account the induced voltage on the
thermal properties. concentric shield wires. For safety reasons, cable sheaths, or
shields, must be earthed, at least at one point in a run. The
three basic bonding methods are single-point, solid bonding
21
4
(or multi-point), and cross-bonding. ues observed in practice where wind plants have been built,
In a single-point bonded system, the heating effect of circu- range from 120 to over 300 when considering dry-out condi-
lating currents is avoided, but voltages will be induced along tions. It is of utmost importance to verify the actual thermal
the length of the cable. Care must be taken to insulate and resistance properties of a given site to ensure proper ampacity
provide surge protection at the open end of the shield to avoid calculations are performed.
dangerous voltages to personnel. A common procedure used for testing thermal resistance is
Solid bonding, sometimes referred to as multi-point groun- taking a sample of the soil, sending it to a laboratory, and
ding, will eliminate the induced voltages by bonding both compacting the sample to 85%-90% of its density found at the
ends of the cable run. The disadvantage of this is that the cir- test site. Compacting the soil eliminates air voids in the soil
culating currents which flow in the shields will reduce the which will act as an insulator and raise the thermal resistivity
ampacity of the cable. The induced voltage is highest at the of the sample. It is important to verify that the compaction of
center point of the cable between grounds. the soil surrounding the installed cable conforms to the design
Cross bonding (see Figure 2) is a method of avoiding circu- parameter as tested in the lab. Thermal resistance testing
lating currents and avoiding excessive sheath voltages while should be conducted at several locations along the defined
permitting increased cable spacing and long run lengths. In routing path of the collection circuit, particularly at those loca-
cross bonding, the cable length is divided into three equal sec- tions where the cables with the highest current-carrying capac-
tions. Each of the three shields are transposed ‘cross-bonded’ ities will be located. This is usually completed at the same
at each of these sections resulting in each section being 120 time as the geotech study that is performed for the wind tur-
degrees apart, and summing the three sections together results bine tower foundation design and access road design.
in a total sheath voltage of zero for a balanced system. For
B. Calculating Cable Losses
slight unbalances due to cable layout and configuration, these
unbalances can be minimized further by also transposing the There are many factors that affect the losses of cables, such
main conductors at each 1/3 section as the cable is laid. The as the current flowing through the cable, the temperature of
largest benefit of cross bonding is evident when three phase the cable and area surrounding the cable, the resistance of the
cables are installed in a flat configuration as opposed to a tre- cable, and the concentric shield wires.
foil configuration since the trefoil configuration will inherent- The current flowing through the cable is the largest factor
ly have some sheath voltage reduction. Cross bonding can be in calculating cable losses. The basic I2R calculation provides
expensive and also introduces additional failure points since the most basic information about power loss that the cable will
the cable jacket must be opened to expose the concentric have.
shield wires. It is a more common practice at higher voltage The concentric shield wires around the conductor will have
levels. a current flowing through it caused by induced voltage from
the power conductor. This induced current on the concentrics
will cause an added loss to the power conductor and should
also be considered. There are various commercially-available
software programs in which manufacturer data for a cable can
be entered and which can calculate the added power loss per-
centage caused by the concentrics. These programs will also
determine the cables ampacity at a defined operating tempera-
ture, configuration of the cables, the soil thermal resistivity
data, soil ambient temperature, and effects from other heat
sources, such as nearby cables.
The losses throughout a wind farm can become very com-
plex as the size of the farm increases. Commercially-available
Fig. 2. Cross Bonding Example. energy loss software programs can be used to determine pow-
er loss at different output levels of the wind farm to aid in
energy loss studies. These programs take in information, such
IV. CALCULATION OF CABLE AMPACITIY as steady-state conductor temperature, conductor size and
A. Soil Considerations length, and no-load and load losses of transformers to deter-
mine the losses throughout the entire wind plant system. Typ-
Soil Thermal Resistivity is dependent on the type of soil,
ically, the engineer is provided with a wind frequency distri-
moisture content, mineral content, and degree of compaction
bution table that has been normalized across the site. This
of the soil. A common thermal resistance, or Rho value, given
table will identify the expected number of hours over the
by the National Electrical Code (NEC) is 90 °C-cm/W and is
course of a year the wind turbine will be operating at for spe-
often assumed for ampacity calculations. This thermal resis-
cified wind speeds. Steady state power flow studies must be
tance value cannot be used indiscriminately when determining
performed at each generation output level and results summed
the ampacity of cables carrying high power since the heating
proportionally with the number of hours at each output level
caused by these cables is often significant. Typical Rho val-
22
5
to determine an annualized loss percentage ACCR, etc.), which provide increased ampacities with smaller
diameters and/or reduced sag, T2 or VR conductors, which are
C. Circuit Configuration/Spacing
resistant to galloping and also Aeolian vibrations (large ampli-
There are different configurations used to arrange the tude conductor oscillations), reduce the likelihood of outages
cables in a WPP collection system. Each configuration has due to conductor-to-conductor contact during wind and ice
certain requirements for optimum performance. conditions. Another option is spacer cable, which is a covered
The trefoil configuration consists of cables placed in a tri- conductor. It is supported by a messenger for mechanical
angle with two cables laid next to each other and the third strength. It performs well during storms and is used for long
cable centered above the first two. This configuration negates runs or tight right of way. Covering provides protection
a large amount of the induced fields that each cable creates against momentary contact.
and lowers the losses on the concentric caused by the induced The NESC specifies the minimum wind and ice loads which
currents. structures must be designed to withstand. These wind and ice
The flat layout and the stacked layout are similar in that the loads are regional requirements, and designs may include
three cables are placed in parallel with each other. The differ- larger wind or ice loads in locations where the known wind
ence in these two layouts is that, in the flat arrangement the and ice conditions exceed the NESC levels.
Conductor configuration and insulator size have an impact
cables are paralleled horizontally, and the stacked configura-
on outages due to lightning. Higher-voltage transmission
tion is vertical. These configurations can be easier to install
lines are configured with one or two overhead ground wires,
than the trefoil configuration, but do not negate induced cur-
also called shield wires, at the top of the poles to shield the
rents on the concentric shields as well as the trefoil configura- conductors from lightning strikes. A lightning strike to a con-
tion. Because of the induced currents on the concentrics in the ductor at any voltage may result in a flashover across an insu-
flat and stacked configurations, cross bonding can provide a lator to the pole ground, which results in a 60 Hz flashover to
greater benefit for those installations. The random lay confi- the pole ground and an outage to the line. A lightning strike
guration is by far the simplest layout. This layout is very dif- to an overhead ground wire is diverted to ground through the
ficult to determine the effects of induced currents and losses pole ground and the pole ground rods. If the insulation level
of the system because the cables are in a random lay. is adequate, and the pole ground resistance is low, the
Spacing of the conductors can also play a major role in the lightning strike will not result in an outage to the line.
ampacity of a circuit. Spacing the conductors farther apart Most 34.5-kV and lower voltage lines are configured with
will expose each cable to less heat from the other two cables the overhead ground wire, usually a neutral wire, below the
but also increase the losses due to the induced current on the phase conductors, where it is more accessible to transformers
concentrics. and other equipment. At voltages of 34.5 kV and below, the
overhead ground wire is ineffective as a shield wire for pre-
V. OVERHEAD CONSTRUCTION venting outages due to lightning, unless larger insulators, such
as 69 kV insulators, are used. Without larger insulators, or
A. Design Considerations where a low ground resistance cannot be achieved economi-
Overhead line design considerations include conductor type cally, installing surge arresters on the top phase is a more ef-
and size, structure type, strength, conductor configuration and fective means of reducing outages due to lightning.
insulator size. Conductor size is chosen based on current- B. Transition from Underground Sections
carrying capacity (ampacity) as well as energy loss considera-
Transitions from underground sections require structures
tions. Structure type, strength, conductor configurations, and
that will support and accommodate the underground cables
insulator size are selected to minimize cost and avoid exces-
and accessories, and support the overhead conductors. The
sive outages due to mechanical failure and lightning.
underground cable accessories include riser pipes, cable ter-
The most common conductor type used is ACSR, which
minations, surge arrestors, and switches. The riser pipes pro-
consists of steel strands for mechanical strength, and alumi-
tect the cables from being damaged. The cable terminations
num outer strands for electrical conductivity. The conductor
prevent moisture ingress into the cable, and insulation to pre-
size is chosen to optimize strength and ampacity, while mini-
vent flashovers from the exposed conductors to ground. The
mizing conductor diameter. Increased conductor diameter
arresters prevent damage to the cable insulation from surges
results in increased mechanical load on the structures due to
and lightning strikes. Switches allow isolation of circuit sec-
wind and ice on the conductors, and necessitates larger and
tions for maintenance.
more expensive poles. Note: TW (trapwire) is also an option.
Regarding support for the overhead conductors, the transi-
The diameter is equivalent to ACSR/TW, has lower losses,
tion structures are designed with similar criteria for strength
and more capacity for variable loading without changing
and configuration as other structures.
structure designs.
Conductor ampacity is calculated using IEEE 738, Standard
VI. REFERENCES
for Calculating the Current-Temperature of Bare Overhead
[1] Deepak Parmar, “Underground Cables Need a Proper Burial,” Transmis-
Conductors, using local ambient temperature and wind speeds.
sion & Distribution World, April 2003.
Conductors are sized to carry the maximum output of the tur- [2] IEEE PES Wind Plant Collector System Design WG “Wind Plant Col-
bines connected to the collector. Others conductor types lector System Design Considerations,” 2009 IEEE PES General Meet-
available include “high temperature conductors” (i.e. ACSS, ing, Calgary, Alberta, Canada, July 2009.
23
6
[3] IEEE PES Wind Plant Collector System Design WG “Wind Power Plant
Substation and Collector System Redundancy, Reliability, and Econom-
ics,” 2009 IEEE PES General Meeting, Calgary, Alberta, Canada, July
2009.
[4] AEIC CS5-94, Specification for Cross-Linked Polyethylene Insulated,
Shielded Power Cables rated 5 through 46 kV, Association of Edison Il-
luminating Companies, 1994.
[5] AEIC CS6-96, Specification for Ethylene Propylene Rubber Shielded
Power Cables rated 5 through 69 kV, Association of Edison Illuminating
Companies, 1996.
[6] ANSI/ICEA S-94-649-2000, Standard for Concentric Neutral Cables
Rated 5 through 46 kV, Insulated Cable Engineers Association,
2000.PSS/E, version 30, Feb. 2006, Siemens Power Technologies Inter-
national.
[7] ANSI/ICEA S-97-682-2000, Standard for Utility Shielded Power Cables
Rated 5 through 46 kV, Insulated Cable Engineers Association, 2000.
[8] Tom A. Short, Electric Power and Distribution Equipment and Systems,
CRC Press, Taylor & Francis Group, 2006.
24
1
Contributing Members: M. Bradt, M. R. Behnke, W. G. Bloethe, C. Brooks, E.H. Camm, W. Dilling, B. Goltz,
J. Li, J. Niemira, K. Nuckles, J. Patiño, M. Reza, B. Richardson, N. Samaan, J. Schoene, T. Smith, I. Snyder,
M. Starke, R. Walling, G. Zahalka
Abstract—Wind power plants use power transformers to step • Loading patterns of wind plant transformers are
plant output from the medium voltage of the collector system to significantly more variable, which is due to the
the HV or EHV transmission system voltage. This paper intermittency in the primary energy sources (wind
discusses the application of these transformers with regard to the
speed), than typical power transformer applications,
selection of winding configuration, MVA rating, impedance, loss
evaluation, on-load tapchanger requirements, and redundancy. with a relatively low load factor (20% to 40% load
factor, from field experience).
Index Terms—Wind generation, power transformers, • The value of wind-generated energy that is
substations. transformed by and lost within the transformer is
greater than typical transformer applications due to the
I. INTRODUCTION incentives and mandates related to renewable power
W
generation.
IND power plants that are too large for direct
connection to a local distribution system, are • The value of transformer reliability (frequency of
interconnected to HV or EHV transmission systems. failure) becomes less significant than availability
Today, the vast majority of wind generation is interconnected (capacity loss times duration of loss) due to the
to the utility grid at the transmission level. This relatively low contribution of the wind plant to system
interconnection is accomplished using one or more power generation capacity requirements. However, it should
transformers to step-up plant output, from the medium voltage be recognized that low transformer reliability can
level used for the plant’s collector system to the transmission directly result in low availability when the mean time
system voltage level. These transformers, along with to replace or repair is long. Transformer replacement
switchgear, protective relays, metering, reactive compensation and major repair lead times tend to be long, and
equipment (in some plant designs), and other equipment outage times can be particularly long for wind plants
needed to perform the interconnection and control and protect in remote or offshore locations
the collection system, are located in a substation. • The transformer must usually provide a ground source
The functional requirements for wind plant substation to both the transmission and collector systems.
transformers are to reliably transfer power to the transmission This paper describes the unique considerations of wind
system, provide ground sources for the transmission grid and power plant substation transformer application. Some use the
collector system, and maintain acceptable collector system term “wind plant step-up transformer” to indicate the
voltage (sometimes aided in this function by the controllable transformer between the MV collector and HV/EHV
reactive power output of the wind generators or supplemental transmission voltage levels. However, wind plants also have
reactive compensation equipment) at the least life-cycle cost, small step-up transformers at each wind turbine generator
including losses as well as initial capital costs.
(WTG) to transform unit output from the voltage level of the
The application considerations for a wind power plant
generator to the collector system voltage. Thus, the term
substation transformer have elements in common with
“step-up” is ambiguous in usage. For this reason, this paper
conventional power plant step-up transformers, as well as
elements in common with primary distribution substation will use the term wind plant substation transformer
transformers. However, there are a number of unique aspects exclusively.
of the wind plant application that strongly influence substation
transformer application, including: II. WINDING CONNECTIONS
The choice of winding connections for wind plant
substation transformers is constrained by the necessity to
provide ground sources, and sometimes also by requirements
to provide zero-sequence isolation.
A. Ground Source Requirements generally requires use of 200 kV BIL equipment. While
All transmission systems in North America, as well as most substation-class equipment of this insulation level is widely
transmission systems around the world, are designed to be available, it is generally cost prohibitive to apply 200 kV BIL
effectively grounded. This means that the ratio of driving substation class equipment throughout the wind plant
point zero-sequence reactance to positive-sequence reactance collection system.
(X0/X1) must be less than three, and the ratio of zero-sequence B. Winding Configuration Alternatives
resistance to positive sequence reactance (R0/X1) must be less
As previously discussed, the grounded-wye/delta winding
than one at any point in the transmission system [1]. If a
configuration for wind plant substation transformers is
power plant were to be interconnected such that it did not
generally not favored due to the necessity of providing wind
contribute a zero-sequence shunt admittance (ground source),
plant collector system grounding via alternate means. The
its positive sequence short-circuit contribution would reduce
exception is where this winding configuration is mandated by
the system’s positive sequence reactance, X1, without
the transmission system operator. Some Canadian utilities
providing a commensurate reduction of its zero sequence
have required grounded-wye/delta wind plant substation
reactance, X0. As a result, the X0/X1 and R0/X1 driving point
transformers in order to completely block the zero sequence
impedance criteria might not be met at points in the
currents from any wind plant collector faults from being seen
transmission system near the wind plant interconnection.
by the utility ground relays.
Excessive temporary overvoltages could result during ground
A delta (HV/EHV side)/grounded-wye (MV side)
faults due to insufficient grounding.
transformer is generally not acceptable to transmission system
An additional consideration is the possible contingency
operators due to the absence of a ground source contribution
involving the power plant, and a portion of the transmission
to the transmission system. There have been some situations
system, becoming isolated from the remainder of the grid. If
where the existing grid X0/X1 ratio is sufficiently low that
the power plant provides no ground source, then the isolated
interconnection of a wind plant with this transformer
subsystem may be completely ungrounded. Extreme
connection has been deemed tolerable, when combined with
overvoltages could result.
protection schemes that ensure that sufficient grounding is
Therefore, most transmission system operators require that
maintained under all conditions.
power plants present a ground source to the transmission
A grounded-wye/grounded-wye connection does not
system. For conventional power plants, this is typically
provide a substantial zero sequence admittance; thus it does
accomplished using a grounded-wye/delta step-up
not create a ground source. This connection, however, will
transformer. This transformer configuration, however, does
transmit a ground source existing on one side of the
not present a ground source to the collector system. A
transformer to the other side. In general, this winding
previous Wind Plant Collector Design Working Group paper
connection is not used because it does not create a ground
[2] provides substantial discussion regarding collector system
source.
grounding requirements.
A possible exception, however, is when a grounded-wye/
Some grounding must be provided for the collector system
grounded-wye three-phase transformer, wound on a three-leg
in order to avoid extreme overvoltages due to the repetitive
core, is used. Because the return path for zero sequence flux
interruption and restriking of low-current arcing ground faults
in this transformer design is outside of the core, the zero-
that can occur in ungrounded medium voltage systems.
sequence shunt impedance is moderately low. Typically, the
Actually, such a system without intentional grounding is not
zero-sequence shunt impedance is on the order of one per-unit
truly ungrounded, but rather it is grounded via the capacitance
on the transformer base, and this may be a sufficient ground
of the collector cables and lines; a highly dangerous condition.
source in some applications. In the normal operating
Grounding can be provided by a supplemental device, such
condition, with the wind plant interconnected to the
as a grounding transformer. However, if the collector system
transmission grid, the zero-sequence driving point impedance
is to be effectively grounded, the grounding transformer must
of the transmission system reflects through the transformer
be very large as it must present a shunt zero-sequence
and usually transfers sufficient grounding to allow the MV
reactance that is less than three-times the sum of the
collector system to be considered effectively grounded. If the
substation power transformer leakage reactance plus the
wind plant should become separated from the grid, the
minimum driving point positive-sequence reactance of the
grounding source provided by the three-leg three-phase
transmission grid at the point of interconnection. An
grounded-wye/grounded-wye substation transformer may be
impedance-grounded collector system is a possible option that
sufficient to maintain effective grounding considering the
allows use of a smaller grounding transformer. However, an
relatively low short-circuit current capacity of the wind
impedance-grounded system will generally require an increase
turbines in the plant. On the transmission voltage side during
in the insulation levels of all the collector system equipment.
the islanded condition, grounding also may be sufficient.
The maximum basic insulation level (BIL) available for many
The isolation of the wind plant zero sequence from the
of the distribution-class components used in a collection
transmission system zero sequence provided by this type of
system, such as separable cable connectors, is 150 kV. This is
transformer is only partial, and may not be acceptable to the
problematic for a 34.5 kV collector system as coordination
transmission system operator from the standpoint of
with this maximum available BIL usually requires an
transmission system protective relaying coordination.
effectively-grounded system. Insulation coordination with an
impedance-grounded 34.5 kV (nominal voltage) system
26
3
A grounded-wye/grounded-wye transformer with a delta particular loading and temperature conditions of the specific
tertiary provides a low impedance grounding source to both wind plant. IEEE Standard C57.91-1995 provides transformer
the transmission system and to the wind plant collector thermal and insulation aging models which can be used to
system. Zero sequence isolation of the wind plant from the model the specific application, allowing the transformer
grid is not complete, but is usually sufficient. It is for this specifier to determine a transformer rating that can provide
reason that this connection seems to be predominately selected adequate insulation life [3].
for wind plants in the US. Often, the delta tertiary is Because the substation power transformer is critical to the
unloaded, and is solely present to provide a low-impedance wind plant’s revenue stream, transformer rating specification
ground source. In this case, the delta winding may not even should be performed conservatively. Although the principles
be brought out to external bushings (embedded delta tertiary). of transformer thermal loading and intentional overloading,
In other applications, the delta tertiary is used for supplying according to C57.91, are well accepted in the utility industry,
station service load. the institutions financing a wind plant may require a full
When the ratio of transmission voltage to wind plant capacity transformer MVA rating.
collector voltage is less than approximately three, it may be
feasible to consider an autotransformer. An autotransformer IV. TRANSFORMER IMPEDANCE
constrains the main windings to the grounded-wye There tends to be a “natural impedance” of a transformer
configuration, but a delta tertiary may be specified. An that is dependent on the MVA rating, nominal voltages,
autotransformer is physically smaller, and less expensive, than insulation levels, and manufacturer. The manufacturer can
a two-winding transformer because only a portion of the produce a transformer with natural impedance at less cost than
transmitted power is magnetically transformed. The ratio of if a greater or lower impedance is specified. Unless the design
the physical MVA of an autotransformer to the MVA of a of the wind plant dictates otherwise, it is preferable to specify
two-winding transformer having the same throughput capacity an impedance near this value.
is equal to the transformer’s co-ratio. The co-ratio is the A greater impedance than this natural value may need to be
difference between the high and low side voltages, divided by specified to reduce the maximum short-circuit current on the
the high-side voltage. wind plant MV collector bus. High short-circuit current can
be an issue for large wind plants where a single transformer is
III. TRANSFORMER MVA RATING used. Alternatives to an artificially-high power transformer
Power transformers have a self-cooled rating, and usually impedance include designing with a two-transformer design
one or more forced-cooled ratings. The most conservative having a split MV bus, specification of higher short-circuit
approach to wind plant substation transformer MVA rating current rated MV equipment, or inclusion of current-limiting
selection is to specify a transformer with the maximum self- reactors in the design.
cooled MVA rating equal to the plant’s rated real power Wind turbines need to have a specified system strength in
output, divided by the minimum required power factor. order to meet performance specifications, such as low-voltage
Transformer MVA ratings do not present a hard limit to the ride-through, and to avoid instabilities. The system strength
loading MVA that can be safely applied. Load current causes seen by the wind turbines is defined by the grid driving point
heating of the transformer winding, which in turn causes impedance, substation power transformer impedance, as well
aging of the transformer insulation. Loss of transformer as the collector system impedances, including individual unit
insulation life is a highly non-linear function of transformer transformers. In situations where the transmission grid is
winding temperature, as well as the duration of exposure. A particularly weak (high impedance), a design alternative may
period of excess winding temperature causes accelerated be to specify a reduced substation power transformer
aging, but aging progresses at less than the nominal rate when impedance.
the winding temperature is less than the nominal full-load
value (110 °C at the hottest spot on the winding). Thus, V. TRANSFORMER LOSS EVALUATION
retarded aging during low-load periods tends to offset All transformers have load loss, which is proportional to the
accelerated aging caused by overload periods. square of the current loading, and no-load loss that is present
Transformer rating is based on continuous loading at the whenever the transformer is energized, whether it is loaded or
MVA rating, at an ambient temperature of 30 °C. Wind plant not. (No-load losses vary in a non-linear relationship to
output, however, tends to be highly variable, and plants are applied voltage. However, because voltage is usually
infrequently required to operate continuously at the minimum maintained within a defined range, no-load losses are typically
power factor. Thermal time constants of a power transformer considered fixed, without consideration of voltage variation.)
are typically hours long, thus tending to smooth the winding In addition, a power transformer will also have auxiliary
temperature rise caused by a variable load. Wind plants in losses (fans and sometimes pumps) that increase step-wise
many locations rarely reach full output during weather with loading.
conditions that produce high ambient temperatures, and In a wind plant, these losses decrease the metered power
maximum loading tends to occur primarily during the cooler delivered to the utility grid, and thus decrease the plant
seasons. All of these factors make it technically feasible to revenue. In addition, no-load losses are present even when
select a transformer MVA rating that is less than the the wind is below cut-in speed, and the plant is not generating
maximum wind plant MVA. To do so, however, requires power. In this situation, the power flows from the utility grid
careful analysis of the transformer aging that occurs for the
27
4
to supply the no-load losses. Depending on tariffs and particularly those where the wind turbines are capable of
agreements, this power may need to be purchased at a cost per providing voltage regulation functionality, do not need
kWh rate that is greater than the value of energy sold by the OLTCs. Where possible, OLTCs should be avoided. They
plant to the market or power purchase agreement recipient. add substantially to transformer costs and maintenance
It is in the long-term interests of the wind plant owner to requirements, and decrease transformer availability.
select a transformer that balances initial capital costs and the Application considerations which drive the need for OLTC
present worth of losses accrued over the life of the specification include:
transformer. Instead of specifying a certain loss levels, the • Unusual range in transmission system voltage,
preferable means to achieve this optimization is to allow the typically greater than the usual 0.95 to 1.05 p.u.
competing power transformer vendors to optimize their range
designs given specified loss evaluation factors. • Very long collector feeders, where the collector bus
The no-load loss factor, typically called the “A factor” in voltage must be decreased with increasing power
the utility industry, is the amount of initial transformer capital output, to compensate for the impedance voltage
cost increase that justifies a unit of no-load power loss rise along the feeders and maintain adequate voltage
reduction. The load loss factor, typically called the “B range at all of the wind turbine generators.
factor,” is the amount of initial transformer capital cost • Wind turbines that are not capable of regulating
increase that justifies a unit of power loss reduction at rated collector system voltage using variable reactive
load. The unit of power typically used for a power power generation and absorption.
transformer is one kW, and the typical unit for a distribution-
type padmount transformer (such as used for individual wind On-load tapchangers are typically applied to the
turbine unit step-up transformers) is one Watt. The total transformer winding having the greatest voltage variation.
evaluated cost of the transformer is: Where an OLTC is used to compensate for transmission
Initial Cost + A × No-Load Loss + B × Load Loss (1) voltage variation, the OLTC is on the HV/EHV winding.
Off-load tapchangers are routinely applied to power
Each transformer manufacturer has different manufacturing transformers. They allow taps to be changed only with the
costs and design tradeoffs, yielding a different relationship transformer de-energized.
between transformer price and losses. Using the A-B factor
methodology allows the manufacturers to compete with each VII. MULTI-TRANSFORMER APPLICATIONS
other on the common basis of total life-cycle cost to the
For large wind plants, multiple substation power
owner. This results in a far better optimization of design than
transformers may be considered. The unit cost (cost per
specification of a given kW loss limit.
MVA) of power transformers tends to decrease with MVA
The A and B factors are specific to a given wind plant
rating. All other considerations aside, a single substation
project. Proper calculation of these factors considers the wind
power transformer provides the lowest cost solution.
plant load-duration curve (diurnal curve), project financing,
However, there are a number of considerations that can drive
taxes, value of sold and purchased energy, as well as other
application of multiple wind plant substation transformer;
technical and financial factors. A previous Wind Plant
either as multiple transformers in a common substation, or
Collector Design Working Group paper [4] details the
construction of multiple substations dispersed within the wind
derivation and calculation of A and B loss evaluation factors.
plant. These considerations are discussed below.
Compared to typical power transformer loss evaluation
factors, the factors for a wind plant may differ substantially A. Practical Constraints
due to a number of reasons. The loading factor of a wind Very large transformers are difficult to ship, due to their
plant substation transformer is less than a typical power physical dimensions and weight. Many wind plants are
transformer which would tend to reduce the B factor. located in remote areas, distant from heavy-duty roads and rail
However, the higher value of wind-generated energy due to lines. The logistical costs of transporting a very large
incentives (e.g., Production Tax Credit) and mandates transformer may offset the benefits of scale of using a very
(Renewable Energy Standards), plus the reduced effective cost large transformer.
of capital investment due to the special tax depreciation Another constraint relates to the practical limits on the
schedules for wind plant equipment, tends to result in a larger current rating of the transformer on the medium-voltage side.
than normal B factor. The high value of produced energy, and Load currents above 3000 A pose difficulty with regard to the
possibly the higher cost of purchased energy for non- ratings of commonly-available switchgear and the capacity of
generating hours, combined with the tax depreciation impacts practical bus conductor sizes. While equipment is available to
result in A factors that tend to be far greater than typical handle higher currents, the associated cost premiums may
transformer applications. offset the transformer cost advantage of a single large
transformer.
VI. LOAD TAPCHANGER APPLICATIONS
B. MV Collector System “Reach”
On-load tapchangers (OLTC) are specified for some wind
plant substation power transformers to compensate for Wind generation inherently requires a minimum geographic
transmission system voltage variations, or to provide means to area per MW of generation capacity, in order to sufficiently
adjust the collector bus voltage. Many wind plants,
28
5
separate turbines to minimize aerodynamic wake effects. compare single and multi-transformer designs, and to
Except in flat areas, terrain features dictate the placement of determine transformer MVA ratings for multi-transformer
wind turbines, and in practice, may require mean distance designs, should consider the probability of transformer failure,
between turbines to be far greater than the theoretical mean time to repair or replace, value of energy output,
minimum. A large wind plant MW rating inherently results in transformer losses (a single, full-sized transformer generally
the wind plant covering a large geographic extent. Use of a has lower no-load and load losses than two, half-sized
single substation in a large wind plant requires transmission of transformers), transformer costs, costs of ancillary substation
power from wind turbines at the outer extent of the plant to equipment, and financial parameters including tax
the substation via MV lines. This affects the cost of the MV implications. Ancillary substation costs in a multi-transformer
design include additional buswork, switchgear, and protection.
collection system, increases losses, and may create voltage
regulation issues. The costs of an extended MV collector
system can offset the benefits of scale derived from a single
substation design, and at some size, the extent of the MV
collector system becomes technically impractical.
29
6
plant. That is due to the fact that the series and parallel
resonances frequencies will be shifted from the designed
points to other values. Frequency scans should be performed
for all modes of operation of the substation transformers and
the modes of operation where resonance problems can occur
at low order odd harmonics should be avoided.
VIII. REFERENCES
[1] IEEE Guide for the Application of Neutral Grounding in Electrical
Utility Systems—Part I: Introduction, IEEE Standard C62.92.1-2000.
[2] IEEE PES Wind Plant Collector System Design Working Group, "Wind
Power Plant Grounding, Overvoltage Protection, and Insulation
Coordination" Proceedings of the 2009 IEEE Power and Energy Society
General Meeting.
[3] IEEE Guide for Loading Mineral-Oil-Immersed Transformers, IEEE
Standard C57.91-1995.
[4] IEEE PES Wind Plant Collector System Design Working Group, “Wind
Power Plant Substation and Collector System Redundancy, Reliability,
and Economics" Proceedings of the 2009 IEEE Power and Energy
Society General Meeting.
30
1
Abstract— This paper discusses the range of application substation. A WPP’s ability to maximize efficiency is
for SCADA and control systems in a wind power plant, directly related to monitoring and control infrastructure.
the most important SCADA and control system SCADA and control requirements are contractually
considerations, and contractual requirements for specified under interconnection agreements (IA), and are
SCADA and control systems. subject to security and reliability requirements under
mandatory reliability compliance provisions. SCADA
Index Terms— SCADA, wind power plant, wind systems and options are integral to compliance with
turbine control, data acquisition, supervisory control, interconnection requirements including voltage and power
plant control, security and reliability compliance. factor control, curtailment, and ramp control. SCADA
systems are also a medium for data transportation and
List of Acronyms—
communication with external sources, such as, providing
BOP Balance of Plant
meteorological data necessary for forecasting to
CIP Critical Infrastructure Protection
DFAG Doubly Fed Asynchronous Generator Independent System Operators (ISOs). SCADA systems
FERC Federal Energy Regulatory Commission are integral to availability and performance measurement
IA Interconnection Agreement and warranty enforcement.
IEC International Electrotechnical There are many different options for control and data
Commission acquisition in a WPP. This paper provides an overview of
IED Intelligent Electronic Device common applications, considerations, and requirements for
ISO Independent System Operator WPP SCADA and control systems.
LGIA Large Generator Interconnection
Agreement II. WIND TURBINE CONTROLS
NERC North American Electric Reliability A wind turbine’s control system enables the safe,
Corp. reliable, and automated control necessary for continuous
OEM Original Equipment Manufacturer power production and shutdown, as required. A typical
OLE Object Linking & Embedding wind turbine’s control system consists of control hardware,
OPC OLE for Process Control supervisory controls, safety systems, and closed-loop
PDD Presidential Decision Directive controls that enable power production by controlling the
PLC Programmable Logic Controller blade pitch angle and the generator torque of the turbine
POI Point of Interconnection [1].
PRC Protection and Control A horizontal axis wind turbine control system will
PRR Power Ramp Rate
consist of several sensors, actuators, and a microprocessor
PSR Protection System Relaying
controller. A list of common hardware elements include:
RAS Remedial Action System
RTO Regional Transmission System Operator • Nacelle mounted anemometer and wind vane;
SCADA Supervisory Control and Data • Rotor speed sensor;
Acquisition • Electric power sensor;
SPS Special Protection System • Pitch position sensors;
WPP Wind Power Plant • Vibration sensors;
XML Extensible Markup Language • Oil level and temperature indicators;
• Hydraulic pressure sensors; and
I. INTRODUCTION
• Operator switches.
Modern wind power plants (WPPs) include an
amalgamation of Supervisory Control and Data Acquisition The microprocessor controller uses defined logic to
(SCADA) systems, control systems, and various other process inputs from the various sensors and generates
intelligent electronic devices (IEDs). SCADA and control outputs to operate the turbine. Commercially available
systems are critical parts of all WPPs, regulating nearly programmable logic controllers (PLCs) are commonly
every aspect from the individual turbine to the collection used.
32
3
original equipment manufacturer (OEM). For fleet wide constraints will typically dictate the type of fibre optic
monitoring and control across different OEM’s turbines, a implementation. Examples of design considerations
third-party SCADA solution can be implemented. include:
• Distances: Multimode has shorter distance
A. OEM SCADA
capabilities than single mode, splices may be
The SCADA system provided by the turbine necessary,
manufacturers is typically a fully integrated system. OEM • Costs: Single mode cable cost less than
SCADA systems have variable functionality depending on multimode, but single mode transmitters cost
the manufacturer. Some of the potential advantages of an more,
OEM SCADA system include: • Mixed Mode—using single mode for long
• Tightly integrated with the turbine control home runs and multimode inter-turbine: This
system; increases inventory and construction
• Turbine specific monitoring and control complexity.
interface; Additional information on network, SCADA, and
• Advanced turbine details and diagnostics; control design considerations is available in [5].
• Robust and integrated security model;
• Advanced troubleshooting and data analysis; Information Management
• Preconfigured displays and reports; The SCADA system typically provides the ability to
• Flexible and open system for data access manage the wind plant remotely and locally. The
• Verification of contractual obligations robustness of the security model is extremely critical to
(production, availability guarantees, wind provide the appropriate level of access control. To avoid
distribution, loss of production, power curves, unintentional start or stop of the wind turbines, the SCADA
etc); system is generally equipped with hardware token based or
• Service and error correction; username-password based authentication.
• Data collection for statistical analysis – both The SCADA system also consists of databases to
long-term for product improvement and short- manage both real-time and historical information. The
term for prediction of potential errors; real-time data update from the turbine is typically done
• Reducing downtime and improving reliability once every second, while the SCADA system aggregates
and availability; and compiles the raw data into meaningful information.
The real-time data server also feeds the graphical interfaces
• Ability to monitor practically all WPP
and displays, referred to as “mimics,” to provide visibility
equipment placed inside the substation;
into wind plant operation. Turbine status and performance
• Compliance with grid codes; and
metrics such as production, wind speed, availability,
• Reducing the number of service inspections.
capacity factor, and fault notifications are examples of key
information that the user would typically visualize via the
System Overview
graphical interface. Mimics can also be used for control
A SCADA system interfaces with the different devices
purposes, for example manually stopping or starting
such as turbines, meteorological (met) masts, substations,
individual turbines or a group of turbines, opening and
and other IEDs within the wind plant to acquire data and
closing circuit breakers, changing transformer tap position,
provide an aggregated view of the plant operation.
and various other functions. The graphical interface
Typically, the SCADA system architecture is designed to
module typically provides preconfigured displays, which
be scalable, to address different sizes of wind plants, as the
may include a plant level view, turbine specific details,
constraints and needs are different. Also, the SCADA
control user interface, and auxiliary device user interface.
system should be capable of accepting additional
Most mimics are standard mimics and appear in all WPPs.
monitoring control points to assist in troubleshooting and
A small number of mimics might be implemented for
remediation of faults, errors, and other issues that may
specific projects.
arise.
The turbine data is normally sufficient for detailed
The site network, which forms the backbone of the
reporting but sometimes data is insufficient or missing, for
SCADA system, is a very critical component of the system
example when turbines are without power, or when turbine
architecture. The internal SCADA network connecting all
computer is shut down. In such cases, the SCADA system
wind plant assets typically uses fibre optics for speed and
makes use of complex methods to estimate loss of
high bandwidth. Possible network configurations include
production based on the data available from neighbouring
bus, star, and ring. To enable high availability and high
turbines or meteorological stations.
data integrity the network is typically designed to have
The historical database typically retains the ten-minute
redundancy. The wind plant size, layout, and cost
average data from all turbines, high voltage substations,
33
4
meteorology stations, and the event/fault data for at least plant which has assets (turbines) from different OEMs, or
12 months. The ten-minute data is gathered from more to have an enterprise level view of many wind plants. The
than 100 sensors and counters on each wind turbine. Older SCADA system commonly provides standard monitoring
data are usually archived and stored in external hardware and control capabilities. Some of the potential advantages
such as tape. The historical database, along with a of a third-party SCADA system are listed below.
reporting module, is used for generating reports and data • Consolidated view of all assets;
analysis. Typically, the reporting module of the SCADA • Common monitoring interface across various
systems consists of pre-configured reports, which may OEMs;
include standard reports such as performance, power curve, • Common control interface across OEMs;
fault analysis, and wind rose. • Platform to have consolidated and standard
Typically, SCADA systems offered by the turbine OEM reporting module;
are divided into two categories: The first solution is • Single interface for communication with
intended for small WPPs in range of 10-20 MW, whereas system operators; and
the second solution allows the operator to utilize the WPP • Flexibility in incorporating substation SCADA.
in the same fashion as a conventional power plant in terms
of meeting the grid code requirements. The turbine itself IV. PLANT CONTROL
can meet some of the grid code requirements, but more
stringent requirements often necessitate the use of an In general, WPPs will have a SCADA system for
additional centralized intelligence. A SCADA system can control and acquisition of data from each of the individual
be used for this purpose. wind turbines. To enable the wind plant to behave like a
Both solutions are designed as a server-client system conventional power plant and meet the specific electric
and generally utilize the same software platform but with grid requirements, advanced plant controls are typically
different level of capability. The main options included in required at the point of interconnection (POI). The
the second solution are remote monitoring of advanced plant controls may include the provisions that
meteorological data, grid monitoring system, and power general plant information be provided in a format
plant controller. The metrological data gathered include compatible with the interconnecting utility’s or system
wind speed, wind direction, ambient temperature, operator’s SCADA system. The information allows the
atmospheric pressure, relative humidity, rain direction, and balancing authority to communicate system and stability
other meteorological information. The grid monitoring information and make necessary adjustments between
system measures quantities, such as, harmonics and entities. It is important to coordinate the turbine operation
flickers, grid voltages and currents, and grid frequency and and provide a stable response to the grid requirements.
power factor at the point of common coupling. The power Some of the advanced plant control features are listed
plant controller is employed to control the output of the below.
WPP, and generally utilized in counties with stringent grid A. Voltage and Power Factor Regulation
code requirements. Its commands are generated by site
specific control algorithms depending on the particular grid Voltage and power factor regulation can be
code requirements. To achieve a very fast response the accomplished by closed loop control of the reactive power
power plant controller is normally run on dedicated capability of the individual wind turbines, through a plant
hardware instead of the SCADA server. control system. This allows the wind plant to provide
regulation services much like a conventional generating
System Interface of Plant SCADA plant. The plant control system is an integral part of the
The SCADA system typically uses a controller specific voltage regulation strategy within a WPP, in order to
protocol to communicate with the turbine controller and transmit all needed decision making data between
uses an industry standard protocol, such as, Modbus for controllers within a given time period, typically in the
data exchange with auxiliary devices. Besides the internal millisecond range. More coarse voltage regulation can be
communication interface, the SCADA system is designed accomplished using static capacitor and reactor banks
typically to support data exchange with external systems located at the substation or individual wind turbines.
such as enterprise SCADA, weather forecasting system, Regulation to a remote point such as an interconnection
and historian systems. The list of such interfaces may switchyard connected to the WPP requires input from
include OPC, web services, and XML. remote instruments or interface to remote switchyard
SCADA systems.
B. Third-Party SCADA
A third-part SCADA system is often implemented for B. Capacitor/Reactor Banks and Dynamic Var Devices
manufacturers that do not offer OEM SCADA, to overlay Reactive compensation equipment such as capacitor
or supplement the OEM SCADA, to manage operation in a banks, reactor banks, switched static reactive
34
5
compensators, and dynamic reactive compensation System Interface of Plant Control
equipment are typically located at the wind plant The plant control system is typically integrated with the
substation(s), switchyard(s), and wind turbine generator(s). wind plant SCADA system to provide real-time visibility
The plant control system will coordinate the operation of and the ability to provide control set points. The plant
these BOP (Balance of plant) equipment, in order to control system can accept set-points from multiple systems
achieve the desired reactive power behaviour at the POI. via different methods. For example, system operators can
Further discussion of WPP reactive power compensation is provide control set-points as an analog signal using a RTU
presented in companion paper [6]. or a user can provide set-points via plant control user
interface. The plant control system can interface with other
C. Ramp Rate Control auxiliary devices in the substation and also inputs from
System operators increasingly require the ability to CTs/PTs at the POI.
control the power removed or inserted at any given point of
time, in both up and down directions. The plant control
system’s ability to enforce a MW per minute ramp rate V. SECURITY AND RELIABILITY COMPLIANCE
maximum is required for the wind plant to accomplish this. Implementation of SCADA and control systems in a
Often referred to as the PRR (power ramp rate), PRR is WPP is not just prudent engineering. WPPs must comply
typically calculated in ten minute or less intervals. Power with contractual obligation under an IA, which often has
fluctuations, which are caused by variations in wind speed, specific SCADA and control provisions necessary for
can be compensated quickly by adjusting the power output maintaining the security and reliability of the grid. Failure
of the individual turbines in order to provide a wind plant to comply with IA requirements can result in default and
level ramp rate control. termination. IA provisions vary regionally, and are
dependent on project specific parameters such as size,
D. Frequency Droop Control interconnection point, and expected impact to the grid.
Conventional power plants typically have frequency Articles 7, 8, and 9 of the Federal Energy Regulatory
droop capability (i.e. varying power output as a function of Commission (FERC) Standard Large Generator
grid frequency). Depending on the turbine manufacturer, a Interconnection Agreement (LGIA), used by many electric
WPP’s plant control system may be able to provide similar reliability entities, contain common requirements
governor response capability by adjusting turbine power governing metering, communications, and operational
output in response to grid frequency variation. capabilities, such as those discussed in Plant Controls
above. Following are other common IA requirements,
E. Power Curtailment standards, and considerations, which influence WPP
System operators often require the ability to control the SCADA and control system capabilities.
power output of a WPP at any given point of time to deal
with grid stability and transmission constraints. The power A. Remedial Action Scheme (RAS)
curtailment feature of the plant control system ensures that An RAS, also known as a Special Protection Scheme
the WPP power output is capped to the desired limit. The (SPS), is an automatic protection system specifically
SCADA system may utilize a simple turbine shutdown designed to detect abnormal or in some cases,
curtailment algorithm, offer global turbine power setpoint predetermined system conditions to take corrective actions.
curtailment, or utilize combined algorithms to optimize The corrective actions from an RAS would take place, in
efficiency and consider other turbine constraints. place of or in addition to the isolation of faulted
Curtailment rotation may be employed to balance components, to maintain system stability and reliability.
curtailment time across the WPP. The actions of an RAS can include changes in:
• Demand;
F. Auxiliary (i.e. battery banks, alarms etc)
• Generation (MW and Mvar);
There are many auxiliary SCADA points that provide • System configuration to maintain system
normal and critical alarms for the wind plant and stability;
interconnecting substations. These alarms are for • Acceptable voltage;
equipment such as: wind turbines (over speed safety • Power flows; or
system, controllers, auxiliary power, batteries, battery • Frequency or rate of change of frequency.
chargers, protection, reactive equipment) and substation
(battery chargers, batteries, system over/under voltage The use of SPS is generally justified for loss of network
alarms, protection lockout alarms, trip coil failure alarms, integrity characterized by one or more of the following
low SF6 gas pressure, transformer alarms, substation entry). phenomena [7]:
• Transient angle instability;
• Small signal angle instability;
35
6
• Frequency instability; C. Data Telemetry
• Short-term voltage instability, IAs typically requires WPPs to provide a variety of data
• Long-term voltage instability, and to external sources such as a Utility, ISO, and/or balancing
• Cascaded tripping. authority control centers. In order to better manage the
schedule and generation of the grid, interconnecting
Some of the most commonly used RAS implemented in entities will often require ongoing forecasts for availability
conventional power systems include [7]: of power (net output) from the generator. The balancing
• Under frequency or under voltage load authority may place restrictions on output from the
shedding; generator depending on forecasted system loads and the
• Generator rejection and fast valving of steam expected availability of other generating resources.
turbines; WPPs commonly have meteorological towers onsite
• Automatic Generation Control (AGC); which require connection to the site communications
• Dynamic braking or braking resistor; network or SCADA system to transmit data to the other
• HVDC fast power change; systems or entities to help with forecasting. Increasingly,
• Tap changers blocking; transmission owners and service providers are requiring
• Controlled opening of an interconnection; live meteorological SCADA points to optimize wind power
• Automatic shunt reactor/capacitor switching; forecasting. Accurate wind forecasting is critical to
and reliable and economic system operation, especially as wind
• Fast increase in the generator voltage set-point. penetration increases in certain regions.
D. NERC Reliability Standards
An RAS does not typically include the functions needed
In 1998, Presidential Decision Directive (PDD) 63 was
for the following:
issued with the intent of protecting critical infrastructure in
• Fault conditions that must be isolated or
the U.S. PDD 63 was general and applied to a wide range
• Out-of-step relaying (not designed as an
of industries including electric generators. Compliance
integral part of RAS).
with PDD 63 was explicitly required for electric generators
under Appendix D of the standard LGIA, which lacked
The entity responsible for regional system impact,
specifics.
stability, and reliability generally develops standards for
The North American Electric Reliability Corporation
the remedial action schemes and their design, operation,
(NERC), whose mission is to insure the reliability of the
and testing.
bulk power system within North America, eventually
B. Protection System Relaying (PSR) established a specific series of reliability standards
The protective scheme needs to be interoperable with covering such areas as communications, transmission,
existing systems and technology in the immediate critical infrastructure protection (CIP), and protection and
interconnection area. Given the need to interact with a control (PRC). The standards are enforced after approval
system greater than the generator (beyond the by FERC under provisions of the 2005 Energy Policy Act.
interconnection point) it will be necessary to provide the Specifically, NERC CIP, governing cyber security, was
interconnecting entity with balance control capabilities. approved by the FERC under Order 706 in January 2008,
Allowing this control will improve safety and help protect thus making the standard mandatory in the U.S., and
equipment at the generator and within the interconnecting applied at a regional level with monitoring and
entity’s system. enforcement by the local reliability councils, corporations,
The PSR control scheme will be governed by the and organizations. Consequently, WPP SCADA and
interconnection agreement executed between the control system are required to comply with cyber security
interconnecting entities and the WPP. Parties to the provisions of NERC CIP, as well as, many other standards
agreement may also include third party entities like a such as PRC-012-0 regarding RAS/SPS procedures. The
system balancing authority. The control process is need for further improvements in communications between
generally facilitated through the provision of SCADA
wind plants and balancing area operators was identified in
summary information to the interconnecting entity. The
[8].
information requested may include current and forecasted
In addition to the NERC CIP requirements, the Smart
WPP output. The information is then used to perform
dynamic system analysis and provide feedback to the WPP Grid efforts have produced NISTIR-7628 V1.0 that
about the ability of the utility to accept the energy addresses Smart Grid cyber security strategy and
produced and any limitations that must be placed upon it. requirements.
Signals are transmitted through the WPP SCADA system
to each individual unit for total system adjustments to
minimize impacts caused by system disturbances.
36
7
E. IEC Standards Beyond meeting requirements and obligations,
The International Electrotechnical Commission (IEC) sophisticated developers and owners recognize the solid
Standard 61400-25 (communications for monitoring and return on investment that proper SCADA implementation
control of wind power plants) provides uniform provides. More and more data isn’t the whole answer. The
information exchange for monitoring and control of wind right data must be acted on to implement operational,
power plants. It deals with communications between wind maintenance or other changes.
power plant components such as wind turbines and actors The publication of this paper was the result of two years
such as SCADA systems. It is designed for a of concerted effort by the authors and the IEEE PES Wind
communication environment supported by a client-server and Solar Plant Collector System Design working group.
model. The application area of IEC 61400-25 covers all The authors sincerely hope that this and other working
components required for the operation of wind power group papers are found to be valuable to those who will
plants, not only the wind turbine, but also the plan, design, analyze, construct, and operate wind power
meteorological system, the electrical system, and the wind plants. Recognition is given to the authors and their
power plant management system. employers for contributing the resources for the
IEC 61400-25 extends the technology of the IEC 61850 preparation of this work.
utility automation standard to address needs particular to For more information on available materials, or to find
wind power. The core of IEC 61850 is an abstract data out how to participate in this working group’s activities,
model that includes data objects that describe power please see: http://grouper.ieee.org/groups/td/wind
system equipment and services that provide data
communications functions. Examples of the services
include report-by-exception and definition/management of
VII. REFERENCES
device logs. The data model is mapped onto
communications technologies by specifying how particular
data types and services are to be communicated using the
technology. There is also an XML-based language for [1] T. Burton, D. Sharpe, N. Jenkins, E. Bossanyi, Wind
Energy Handbook, West Sussex, UK: John Wiley &
defining the configuration of the facility and setting the
Sons Ltd, 2001.
values of pre-defined parameters.
[2] G. Smith, Development of a Generic Wind Farm
IEC 61400-25 provides two major areas of extension. SCADA System, DTI Publishing 2001.
One is an extension to the data model to cover equipment [3] Wotruba, Bill. “The Essentials of Ethernet Equipment
found in wind plants. For equipment such as switches, in SCADA Systems.” North American Windpower,
breakers, protective relays, and transformers, the 61850 June 2010.
objects can be used. The other extension area is mapping [4] Wind Plant Collector Design WG, “Characteristics of
to additional communications technologies beyond those Wind Turbine Generators for Wind Power Plants,”
found in 61850. For example, 61400-25 adds XML-based Proceedings of 2009 IEEE Power and Energy Society
web services communications that offers improved General Meeting, Calgary, Canada, July 2009.
compatibility with communications in enterprise systems. [5] IEEE Std. C37.1-2007, IEEE Standard for SCADA
The data objects in 61850 and 61400-25 are named and Automation Systems.
rather than numbered. Part of the name is defined in the [6] Wind Plant Collector Design WG, “Reactive Power
standard and part is defined by the using organization. Compensation for Wind Power Plants,” Proceedings
Object naming removes any limit on the number and scope of 2009 IEEE Power and Energy Society General
of objects that can be handled thus, new power system Meeting, Calgary, Canada, July 2009.
equipment technologies or data requirements can be [7] System Protection Schemes in Power Networks,
accommodated by simply adding the relevant objects to the CIGRE Technical Brochure 187, Task Force 38.02.19,
data model. This approach is being used by Smart Grid June 2001.
efforts focused on ensuring that 61400-25 can support wind [8] North American Electric Reliability Corporation
(NERC), Special Report on Accommodating High
power data needs particular to North American practices.
Levels of Variable Generation, 2009
VI. CONCLUSIONS
In the past SCADA systems were almost or literally
afterthoughts, put in as needed to get the job done.
SCADA in modern WPPs is recognized as integral to
optimize WPP performance and financial return, and
necessary to meet contractual obligations including strict
security requirements.
37
1
Contributing Members: E.H. Camm, M. R. Behnke, O. Bolado, M. Bollen, M. Bradt, C. Brooks, W. Dilling,
M. Edds, W. J. Hejdak, D. Houseman, S. Klein, F. Li, J. Li, P. Maibach, T. Nicolai, J. Patiño, S. V. Pasupulati,
N. Samaan, S. Saylors, T. Siebert, T. Smith, M. Starke, R. Walling
Abstract—This technical paper provides the basic guidelines II. REACTIVE POWER COMPENSATION
for the application of reactive compensation systems to be used as
The requirements and type of reactive power compensation
part of a wind power plant. A brief history of wind plant reactive
compensation system is discussed, then the fundamental needs of in conjunction with the collector system are key to having a
why reactive compensation is required. The paper will then compliant wind plant system.
provide some alternatives for reactive compensation, how to size
A. Requirements
the reactive compensation, and finally some of the principles on
how different compensation devices work. There are multiple areas for consideration when deciding
on the reactive power compensation system within the WPP
Index Terms— voltage ride-through, induction generator, collector design. Most WPPs have an interconnection
reactive power, wind power generation agreement that may define the parameters of what is required.
In the United States the Large Generator Interconnection
Agreement (LGIA) for WPPs rated 20 MW or more defines
I. INTRODUCTION
the requirements associated with reactive power
of the system. It is typically stated that the power factor (PF) 4) High Voltage Ride-Through Requirements
compliance of the WPP must be met at the POI (Point of WPPs are subject to high voltages that can occur in the
Interconnection). The WPP is allowed to meet power factor transmission system following fault clearance, loss of large
requirement through the capabilities of the WTG (Wind loads, or other system transients. There is no HVRT
Turbine Generator), fixed and switched shunt requirement in FERC Order 661-A. Some ISO/RTOs, NERC,
capacitors/reactors or a combination of the two. The WPP is and Hydro Quebec are in the process of implementing or have
usually required to follow the voltage schedule (static voltage) implemented such requirements. In many European countries
imposed by the Transmission Provider which consequently WPPs are required not to trip for a high voltage level up to
determines the WPP operating PF required at any given time. 110% of the nominal voltage at the POI. WPPs are also
It is recognized that the WPP may not be able to meet the required not to trip for higher voltage level if it lasts less than
power factor range requirement under all possible operating a pre-specified time period.
scenarios. For instance, when there is near zero power
B. Wind Plant Details
generation and only a couple of turbines may be online at low
power levels, some transmission providers and grid codes With the requirements known the actual design and sizing
of the reactive compensation can begin. The details of the
allow a lower amount of power factor control [9].
wind plant will need to include the following items:
2) Dynamic Voltage Support Requirements • Point of interconnection (POI).
FERC Order 661-A states that WPPs shall be able to • Minimum and maximum short-circuit levels with
provide sufficient dynamic voltage support (as opposed to associated X/R ratios at the POI.
static) in lieu of power system stabilizer and automatic • Make, model, MW rating and number of wind turbine
voltage regulation of conventional generating units. Such generators (WTGs).
requirements are imposed only if the Transmission Provider's • Control mode(s) at the POI; (i.e. voltage control,
System Impact Study concludes that the dynamic capability of power factor control, constant susceptance control)
the WPP is necessary for operational security of the system. along with the acceptable tolerances, dead bands,
Some ISOs/RTOs further define the response time for slopes, or other measures of dynamic response for
reactive support. these items.
• Location of turbines relative to the POI.
3) Low Voltage Ride-Through Requirements
• WTG power factor capability, control modes available
WPPs are required to demonstrate low voltage ride-
(i.e., power factor, voltage, or reactive power).
through capability to interconnect to the transmission system.
• WTG and wind power plant SCADA dynamic
FERC Order 661-A states that the WPPs are required to
response times, WTG VRT capability.
remain in-service during three-phase faults with clearing time
• WTG step-up transformer details (MVA, percent
between 4 to 9 cycles. In other words, the WTGs should not impedance, X/R ratio, and available taps).
trip for zero voltage at the high voltage side of the WPP
• Collector cable schedules, including cable types, sizes,
substation transformer lasting up to 0.15 seconds. The WPP and lengths.
should also remain in-service during single-line-to-ground • If applicable, details of collector substation
faults with delayed clearing, and subsequent post-fault voltage transformer(s) (MVA, percent impedance, X/R ratio,
recovery to pre-fault voltage. The LVRT requirements do not and available taps)
apply for faults between the WTG terminals and the high • If applicable, transmission line data (R, L, C) and
voltage side of the WPP. The WPP may meet the LVRT distance from the collector substation transformer to
requirements of this standard by the performance of the the POI.
generators or by installing additional equipment or both
The LVRT requirements in the FERC order represents the C. Wind Plant Analysis
minimum requirements. Some ISOs/RTOs have adopted these As mentioned previously, a system impact study may have
requirements, and others such as WECC have proposed been completed already to provide the requirements of the
additional requirements. The WECC has a proposal [2] that is reactive power compensation system for the wind power
currently out for comment and balloting which applies to all plant. It will be necessary to perform more detailed studies to
generating units, including WTGs. In this proposal, beside the further define the actual components of the reactive power
previously mentioned LVRT requirements, the generator's compensation system. Some of the standard studies that are
protection system is required not to trip the generator for the done in conjunction with the reactive compensation system
low voltage deviations of 20% for 40 cycles (post-disturbance are steady-state load flow, dynamic (or voltage stability), and
undervoltage) at the high voltage side of the WPP substation harmonic analyses.
transformer. It is also required that the owner of the WPP The studies will incorporate the wind plant requirements
have evidence that their protection systems for WTG do not and the actual details of the wind plant. The type of reactive
trip the generator during three-phase faults with normal compensation could be from any combination of the WTGs,
clearing (for a maximum of 9 cycles). mechanically-switched devices (i.e., shunt capacitor or reactor
banks), STATCOMS, SVCs, etc. The actual devices chosen
39
3
will have to comply with the requirements of the wind plant. Some ISO’s require that the WPP responds similarly to that of
Further items for consideration may include voltage conventional synchronous generators and that power factor
limitations during switching of shunt capacitors, power quality targets are met within a short duration (i.e. 1 second). This
requirements such as flicker during start up or cut-in, may be equivalent to traditional excitation systems on
harmonics, etc. generators.
Studies which involve the reactive power compensation 3) Harmonic and Flicker Analysis
system are discussed next. Other wind power plant studies Harmonic analysis will require the same inputs as used for
are discussed in a companion Working Group paper. the load flow studies with the addition of a few items. Any
1) Load Flow Studies harmonics generation sources within the wind farm shall be
Load flow studies typically require a detailed model of the included. This typically includes the WTGs and, if applicable,
collector grid with the actual cables and routing taken into the reactive compensation devices. All types of turbines can
account. The POI should be clearly defined and in accordance create resonance conditions, due to passive elements in their
with the interconnection requirements. This may be on the design. In addition Type 3 and 4 [10] WTGs can create
high side or low side of the main substation transformer, or resonance due to their control design. The short-circuit level
even located miles away if an additional transmission line was range at the POI with associated X/R ratios will also be
added for the wind power plant. needed. Care should be taken to insure frequency dependent
Some wind power plants have on-load tap changers elements are modeled correctly. It is also sometimes required
(OLTCs) on the main substation transformer. The turbine PF to include any background/existing “ambient” harmonics and
range capability shall be taken into account. Note some local reactive compensation devices. Typically the
turbines have the ability to vary power factor while others background harmonics are not known at the time of the
maintain a constant power factor. The reactive compensation studies, but may be required if analysis reveals resonance
needs to be modeled also. The types of reactive compensation conditions at characteristic harmonic frequencies.
are discussed in section III.B. The harmonic analysis should cover all reasonable
Typically the power factor range is required at nominal operating scenarios. Different combinations of generation
voltage, but it may also be required if the POI voltage is output, components of the reactive compensation, short-
varied (i.e. +/-5%) while maintaining required power factor circuit levels, etc will need to be modeled. Resonance
range. The reactive compensation system usually is required conditions can occur due to substation switched capacitor
to be operational between +/-10% voltage at the POI, but the banks and power factor correction capacitors (PFCCs) in
available range may have a reduced range during this WTGs. Detuning of the capacitor banks may be required in
condition. The power factor requirement may also change as a some cases, to ensure potential impacts do not negatively
function of the generation level [9]. The WPP does have affect the collector system and equipment. It may not be
auxiliary load that should be included in the analysis. possible to avoid all resonance conditions, but it should be
2) Dynamic Analysis avoided in the most common operating scenarios.
Dynamic analysis is performed to varying degrees between The harmonic generation level requirements may be
projects. This analysis may be provided by the transmission defined in the generation interconnection details. In the
provider/ISO or by the WPP. If the interconnecting utility can United States IEEE Std. 519 [11] is commonly used as a
supply the actual phasor (or rms) model with the base cases guideline for these requirements.
and contingencies this will yield the best results. Some Power quality of the WPP may be limited to the harmonic
utilities do not provide their system details, thus it may be analysis, but may also include flicker calculations. The main
required to build an equivalent utility system model (less concern for flicker is the voltage change that may occur when
preferred) from the known data. In addition to this model a SSD is switched or during WTG startup and cut-in. Large
provided by the interconnecting utility or equivalent system, steps in voltage, 1% to 5% depending upon the turbine
models of all other devices should be added as mentioned manufacturer, may have an adverse effect on the WTG, in
above for the load flow. The turbine dynamic model with particular the gear box. Other flicker concerns due to
actual settings is important. Refer to section IV on voltage continuous or switching operations (such as startup and cut-
ride-through for more detail. in) are usually limited to small wind power plants connected
Dynamic analysis has a base requirement per FERC Order to distribution systems that other customers may be directly
661-A. This requires zero voltage ride through for 3-phase connected to. To analyze this detail of flicker the turbine
faults on the high side of the main power transformer cleared manufacturer needs to provide the associated flicker test data
in 4-9 cycles (depending on the fault clearing times of the of their units.
circuit breakers involved and further definition provided by
the local transmission provider) and single line-ground faults III. REACTIVE POWER FLOW DURING NORMAL OPERATION
with delayed clearing. Typically single line-ground fault The reactive power flow from the grid to the wind plant at
clearing times are provided by the transmission provider. the POI is given, simplified, by the following expression:
The studies may also include the response time of the
complete system to meet the reactive power requirements.
Q poi = Qgen + 3I 2 X − V 2ωC − Qcomp (1)
40
4
where Qgen is the leading (inductive) reactive power power compensation equipment and some general principles
consumption of the turbines (which is negative when WTG is of operation.
operating at a lagging (capacitive) power factor), X the
1) Mechanically-Switched Shunt Capacitors
equivalent series reactance of cables, lines and transformers,
Capacitors banks typically consist of a grouping of
C the equivalent shunt reactance of (especially) cables, and
individual capacitor units. The bank is then either considered
Qcomp the reactive-power injected by any centralized reactive
fixed or it can be switched using appropriately rated devices.
power compensation system. For simple induction generators
These banks can either be “metal enclosed” or “open rack”
the reactive power consumption depends on the loading and
design. It is important that special attention be paid to the
on the terminal voltage according to the following
switches. They should be rated for capacitor switching [4]. It
approximation:
is only possible to control slow variations in reactive power.
V2 The capacitive VAr output is a function of the voltage such
Qgen = + 3I 2 X l (2)
Xm that the VArs decrease with the square of the voltage (i.e.
90% voltage will provide 81% VAr capability) Using a
Where Xm and Xl are the magnetizing and leakage
number of capacitor banks of different size, the reactive
reactance, respectively. For DFIG and full-power-converter
power exchange can be kept within a range. Capacitor banks
machines the reactive power can be controlled on the
typically require a 5 minute discharge time before they can be
terminals of the machine or at the grid side of the turbine
re-energized, but there are also designs that allow for shorter
transformer within the WTG capability.
durations on a limited basis.
Without any reactive power compensation, the reactive-
power exchange consists of a term proportional to the square 2) Mechanically-Switched Shunt and Regulated Reactors
of the voltage and a term proportional to the square of the Reactors are typically mechanically switched devices.
current. As the voltage variations are much less than the Again, it is only possible to control slow variations in reactive
current variations, it is the latter term that requires the main power. The inductive VAr output is a function of the voltage
compensation. such that the VArs decrease with the square of the voltage
(i.e. 90% voltage will provide 81% VAr capability).
A. Example
Regulated shunt reactors are shunt reactors equipped with
The generation and consumption range of reactive power a tap-changer as used for voltage control with a transformer.
for 200 MW WPP is summarized in Table I. The WPP Using such a ”regulated shunt-reactor”, a more smooth
consists of 100 2-MW Type 3 WTG with PF capabilities from control of reactive power can be achieved [6]. A study
0.98 leading to 0.98 lagging. A total of 72 MVAR (6 steps, 12 presented in [5] shows the feasibility of this tool for reactive
MVAR each) of reactive power compensation is installed on
power control with large wind power plants.
the substation MV bus. The reactive power generated by the
cables is given for rated voltage. The variations in collector 3) Static Var Compensator
cable reactive-power generation are small during normal An SVC is typically a fixed shunt capacitance in parallel
operation. The reactive power consumed by the series with reactance that is controlled using thyristors. This type of
reactance of the cables and transformers is given for rated controller is made using static components. When the
current. The reactive-power consumption varies with the thyristors are used in the control process, then the controller is
square of the current. It is this variation that requires considered dynamic. These allow for a control of reactive
compensation to meet the requirements at the POI. power at time scales down to the order of a 100 milliseconds.
Additional filters must be used to avoid harmonics which are
TABLE I
REACTIVE POWER FLOWS FOR A CERTAIN OPERATING SCENARIO IN A 200 MW
created when the current wave shape distorts from the
WPP thyristor switching. Further details on SVC can be found in
Elements of WPP Reactive power Reactive power IEEE Std.1031.
generated at rated consumed at rated
voltage current Transmission Voltage
Substation transformer (235 ------ 38 Mvar
MVA, 345/34.5 kV) POI
Substation based reactive 0 to 72 Mvar ------
compensation
Collector 38 kV cables/OH lines 11 Mvar 7 Mvar
WTG Transformers ------ 23 Mvar
WTGs (Type 3, PF range from 0 to 40 Mvar 0 to 40 Mvar Medium Voltage
0.98 leading to 0.98 lagging)
Total 11 to 123 Mvar 68 to 108 Mvar
41
5
42
6
43
7
44
1
Contributing Members: E.H. Camm, M. R. Behnke, O. Bolado, M. Bollen, M. Bradt, C. Brooks, W. Dilling,
M. Edds, W. J. Hejdak, D. Houseman, S. Klein, F. Li, J. Li, P. Maibach, T. Nicolai, J. Patiño, S. V. Pasupulati,
N. Samaan, S. Saylors, T. Siebert, T. Smith, M. Starke, R. Walling
including remote ends of feeders. With effective grounding, Another consequence of the “capacitive grounding” of a
TOV from ground faults tends to be within the capability of nominally ungrounded feeder is the fact that the fault arc can
arresters selected based on the MCOV. However, some clear itself, due to the very low fault current present once the
plants have been designed with impedance grounding that feeder is isolated, and then restrike. The restrike triggers a
intentionally results in a higher X0/X1 ratio. Maximum voltage oscillation and the arc may again interrupt at a current
unfaulted phase voltages need to be calculated at each arrester zero, trapping an even higher voltage. This process can
location for any ground fault, as well as expected duration of repeat, escalating the voltage to higher and higher levels.
the fault. This establishes a constraint on the minimum TOV To avoid these TOVs, many wind plants are constructed
capability of the applied arresters. with dedicated grounding transformers on each wind plant
2) Loss of Ground Reference feeder. This eliminates the possibility of ungrounded
Typically, neither wind turbine generators (WTGs), nor operation due to feeder isolation. The sizing of the grounding
their unit step-up transformers, provide neutral grounding for transformers must consider the rating of the WTGs connected
the wind plant MV system. The wind plant substation to the feeder, the WTG characteristics, and the amount of
provides the normal source of grounding for the collector cable charging capacitance. In some cases, the WTG
feeders. If a ground fault should occur, and a collector feeder behavior for such a feeder isolation condition is sufficiently
is tripped but the wind turbine generators continue to operate, complex to preclude simple calculation of grounding
the feeder becomes isolated without a ground source but with transformer impedance requirements. In such a case, detailed
one phase connected to ground. As a result, unfaulted phase simulations are necessary.
voltages will rise greatly, typically to 1.73 times pre-fault
voltage or more as shown in Figure 1.
3
Field experience has shown that WTGs may continue to
2
by grid operators. 1.8
1.6
C B 1.4
1.2
1
N
0 5,000 10,000 15,000 20,000
Feet of 500 kcmil 34.5 kV cable per MVA of WTG
1 p.u.
1 p.u. Figure 2 – Increase of TOV due to feeder capacitance for an isolated feeder
1.73 p.u.
cable with a ground fault applied.
A 3) Self-Excitation
WTGs, when isolated from the grid, can produce
temporary overvoltages due to various phenomena, including
Figure 1 – Illustration of TOV due to a single-phase fault in an ungrounded
system. the phenomenon known as self-excitation. Induction
generators, which have no direct means of voltage control,
The actual TOV can be significantly more severe than the can interact with system capacitance to create high voltages
173% value, due to the capacitance of the isolated feeder. [2]. This occurs when there is capacitive compensation in
The “ungrounded” feeder is not actually ungrounded, but is excess of the magnetizing VARs required by the generator.
grounded via the capacitance of the feeder cables. The Excess compensation can occur when all but one turbine trips
negative reactance of the capacitance results in a negative on a feeder that becomes isolated, and the feeder has a large
X0/X1 ratio, that will further increase unfaulted phase voltage. amount of cable footage, resulting in a high ratio of capacitive
Figure 2 relates TOV to the amount of feeder capacitance, susceptance relative to generator rating.
assuming the WTG is a synchronous source. Note that a fault 4) Transformer Saturation Interaction
may cause some WTGs to trip and not others, allowing the Transformers may become saturated during TOV.
ratio of total cable charging capacitance to the connected However, in contrast to common expectation, saturation does
wind turbine capacity to become much greater than that of the not always limit overvoltage peaks. Peak voltages can be
feeder with all WTGs connected. Because the series increased because saturated transformers inject large amounts
impedance of the collector cable is very small compared to of harmonic current into the system. The system, dominated
the shunt impedance of the cable capacitance, the voltages by generator and transformer inductances and cable
shown in Figure 2 are insensitive to location on the feeder. capacitances, are often resonant near the low-order harmonic
frequencies at which transformer exciting current is injected.
46
3
The interaction of the injected harmonic currents, and the padmounted unit transformers. Some collector systems have
high harmonic impedance caused by resonance, can result in a mix of overhead and underground line sections. In these
very large harmonic voltage superimposed on the voltage systems, lightning can enter the MV system by direct strikes
waveform. Sometimes this is called “ferroresonance”, but to the overhead line.
this is not an appropriate use of this term. Lightning is generally considered to be a current source,
5) Ferroresonance and the lightning current rise time can be less than one
True ferroresonance involves a capacitance in series with a microsecond. The fast rise of the current, and the resulting
nonlinear inductance, such as the excitation impedance of an voltage, imposes arrester location considerations due to the
unloaded transformer. Ferroresonance typically occurs as the traveling wave effects.
result of having one or two phases open. A stuck pole on a
collector feeder breaker (open or closed) can result in III. INSULATION COORDINATION
ferroresonance that produces voltage several times normal IEEE Standard 1313.1 defines insulation coordination as
magnitude on the open phases. This overvoltage is due to the “The selection of insulation strength consistent with expected
interaction between the feeder cable capacitance and the overvoltages to obtain an acceptable risk of failure.”[3]
magnetic cores of WTG unit transformers, particularly when Overvoltage protective devices, invariably metal-oxide surge
the WTGs are not connected. Switching unloaded WTG unit arresters, are applied to constrain transient overvoltages, but
transformers phase-by-phase by operating load break elbows these same devices are vulnerable to failure from extended-
or single-phase disconnect switches can also result in duration temporary overvoltages. System grounding plays an
ferroresonance. In this case, the winding capacitance of the important role in minimizing temporary overvoltages. Thus,
unit transformers may alone be sufficient, particularly when the selection of surge arrester, equipment insulation, and
combined with delta-primary transformers or transformers system grounding requirements are inexorably intertwined.
with low core loss.
Ferroresonance is dealt with by avoiding the conditions A. Surge Arrester Characteristics
creating the phenomenon. Breaker failure protection schemes Virtually all surge arresters for MV system application use
avoid continued energization of feeders with one or two metal-oxide varistor (MOV) technology. The MOV is a
phases open. Use of three-phase switches (e.g., internal highly nonlinear resistance, with the current through the MOV
transformer under-oil switches) to energize or deenergize a function of the voltage raised to a very high exponent.
WTG unit transformers, or performing switching operations Under normal operating voltages, the MOV conducts only a
with the feeder deenergized, avoids single-unit very small current, on the order of microamps. This current
ferroresonance. has no significance to the system, but it does have
significance to the arrester because this current causes
C. Switching Transients
heating. One key rating parameter of an arrester is the
Switching of system elements such as cables, lines, and maximum continuous operating voltage (MCOV), and this
capacitor banks, can create transient overvoltages. In a wind relates to the allowable steady-state temperature rise of the
plant, most switching transients are of inadequate severity to arrester.
be either a concern for equipment insulation protection, or a At voltages on the order of twice the maximum peak
concern for surge arrester duty. Typically, the only type of operating voltage, the arrester conducts significant current,
switching event that may be significant is restrike of a sufficient to effectively “clamp” the overvoltage condition. It
capacitor bank switch or breaker during deenergization. is this clamping effect that is employed to protect equipment.
Modern switchgear is designed to make such an event a very A key parameter of the arrester is its voltage protective level,
infrequent occurrence. If a restrike should occur, the which is defined at a specified current, typically 5 kA or
resulting energy duty may exceed the capability of a surge 10 kA. However, for current variations over a considerable
arrester. Transient studies are necessary to determine the range around these current levels, the voltage protective level
energy duty produced by restriking. However, it is not does not change greatly. For the same peak current level, the
common to consider this event as a MV collector system peak discharge voltage of the arrester varies according to the
design constraint. rise time of the applied surge, with higher discharge voltages
D. Lightning Transients for faster rise times.
The dominant risk to equipment insulation is impulsive At currents of this magnitude, the arrester conducts enough
transients due to lightning. Even if a collector system has no current to heat the arrester very rapidly. Another application
overhead lines, it is prudent to consider lightning surge characteristic of an arrester is its energy rating, which defines
protection for equipment. Lightning transients may enter the its ability to withstand transient current discharges without
MV system by various means, including coupling through the excessive overheating or otherwise damaging the MOV
substation power transformer from exposed HV lines, direct elements.
strikes to open-air substation equipment, and from the wind Between the MCOV, and the voltage levels where arrester
turbines via ground potential rise and coupling through the current is sufficient to clamp the voltage, is a range of
voltages where the arrester discharges too much current to
47
4
withstand the situation for an extended period, but not so overhead line.
much current that the interaction of the current with the 2) Separation Effects
system impedance causes the applied voltage to be modified. Voltage changes propagate as traveling waves, at near the
These overvoltages can be withstood for a period that is a speed of light in overhead lines and bus work, and at
function of the applied voltage magnitude. Thus, the ability approximately 40% of the speed of light in underground
of surge arresters to withstand voltages in this range is defined cable. For lower frequency phenomena, such as TOV and
as the “temporary overvoltage” (TOV) rating. It is important capacitor switching surges in a collector system, the traveling
to emphasize that, except in very specialized applications, a wave effects are not significant because the propagation time
surge arrester cannot be considered as a means to reduce is a small fraction of the voltage rise time. For lightning
TOV, but rather the arrester must be able to survive the TOV transients, however, the propagation times even within a
to which it is subjected. Thus, TOV conditions in a system substation can be significant compared to the rise time of the
establish a constraint on the minimum arrester voltage rating current. As a result, the lightning transient voltages at an
that can be applied. Sometimes, other means allow the TOV arrester are not the same as that at a piece of equipment that is
to be avoided or minimized, so the unmitigated TOV is not some distance away. Voltages at the equipment can be
always a firm constraint to the overall insulation coordination considerably greater due to the separation effect. In a wind
process. plant substation, arresters are typically installed adjacent to
Surge arrester manufacturers provide a TOV curve that the terminals of the most critical and vulnerable piece of
defines as a function of the duration of exposure the equipment, the substation transformer. Separation effects are
magnitude of sinusoidal fundamental-frequency voltage that considered to coordinate the overvoltage protection of other
can be applied to the arrester without causing failure. This equipment in the substation such as breakers, PTs, etc.
TOV capability is defined in terms of a root-mean-square Reference [4] provides simplified methods for calculating
(rms) voltage magnitude, as a matter of documenting the test separation effects. Alternatively, transient simulations, with
conditions applied. However, it must be emphasized that the the substation bus work modeled as “transmission lines”, can
rms magnitude of a distorted voltage waveform should not be be performed.
used as the basis for comparing the ability of an arrester to 3) Open End Reflection Voltages
survive the distorted TOV. Metal-oxide surge arrester When voltage waves reach the open end of a line, they
conduction is a function of the voltage raised to a very high reflect causing a doubling of the voltage at the end.
exponent, thus thermal duty is overwhelmingly dominated by Reflections also occur when voltage waves reach a
the peaks of the applied voltage. A far better means to discontinuity in line surge impedance, such as a transition
evaluate a distorted TOV is to compare the recurring peak between overhead line and underground cable. Cables have a
magnitude of the distorted voltage to the equivalent peak low surge impedance, and lines have a high surge impedance.
magnitude of the arrester TOV test rms voltage documented Because of voltage doubling, surge arresters located in a
by the manufacturer (sqrt(2)×rms). It should also be noted wind plant substation do not provide good overvoltage
that the published TOV curves describe the duration that a protection for equipment along the collector feeders, even if
particular TOV magnitude can be endured, followed by a the surges only can enter the collector system via the
voltage less than or equal to the MCOV. Although the substation. For this reason, it is highly desirable to locate
arrester TOV curve plots as a voltage magnitude decreasing surge arresters at the ends of each feeder. If a feeder is
with increasing exposure duration, it is incorrect to interpret bifurcated, and thus has many ends, arresters should be
the curve as an envelope of acceptable voltage; the arrester is located at each open point.
not designed to endure a voltage of decreasing magnitude that
follows along the TOV curve line. C. Insulation Coordination Steps
B. Arrester Installation Considerations In the conventional approach described in IEEE C62.22
1) Arrester Lead Length [4], insulation coordination is performed in the following
The rate of lightning current rise (dI/dt) is very large. steps:
Arrester leads, both on the hot end and ground end, create an 1. Select the surge arrester to be used, considering the
inductance proportional to their length. The dI/dt, multiplied maximum continuous operating voltage (MCOV) and
by a few microhenries of lead inductance result in many kV of temporary overvoltage (TOV) constraints, as well as
voltage which must be added to the discharge voltage of surge the type of arrester. The duration of TOV caused by
arresters. For MV arresters, this added lead-length voltage wind plant feeder isolation is difficult to determine
can be a significant increase in the voltage protective level. with accuracy, and can extend for seconds. A common
practice is to coordinate assuming a ten second
For this reason, it is desirable to keep arrester lead lengths as
duration.
short as practical, particularly for arresters at the interface
2. Determine the protective level of this surge arrester at
between overhead and underground sections of hybrid
a “coordinating current” which is the presumed arrester
collector systems that are exposed to the high lightning
discharge current for an impulsive (lightning) transient.
current magnitudes possible from direct strikes to the
48
5
3. Determine where the surge arrester is to be located transmission connection, but does not provide complete zero-
with respect to the protected equipment. Voltage wave sequence isolation. Some transmission operators demand that
behavior can cause voltages to be significantly greater a grounded-wye (HV) delta (MV) transformer be used to
as distance from the arrester is increased. totally isolate the grid from wind plant zero-sequence
4. Determine the voltage at the terminals of the protected currents. A separate grounding transformer is needed on the
equipment. MV bus to provide some degree of system grounding to avoid
5. Select equipment insulation level. extreme TOV. However, a very large grounding transformer
6. Evaluate voltage protection margins. A minimum 20% is necessary to provide an effectively grounded MV system.
margin is desirable. The ground source at the wind plant MV bus typically
7. If margins are inadequate, consider alternatives such as provides effective grounding for the entire MV collector
different arrester placement, higher insulation level,
system, as long as the collector feeders remain connected to
etc.
the bus. Severe TOV can potentially occur on a feeder, if the
For wind plants, a modification of this conventional
feeder should become isolated from the MV bus with the
approach is usually necessary from a practical standpoint.
WTGs remaining in operation, due to loss of ground and
Wind plant collector systems have similarity in topology and
possible self-excitation. There are several strategies
voltage level with primary distribution systems. Commodity
described below for mitigating feeder TOVs related to feeder
distribution-grade equipment is usually much less expensive
islanding.
than substation-grade equipment, and is thus favored for wind
plant collector system design. For example, WTG unit step- A. Grounding Transformer Application
up transformers are usually large three-phase padmounted Application of grounding transformers on each collector
distribution transformers. The insulation level choices feeder can reduce TOV due to the loss of ground reference
available for commodity distribution transformers are limited. phenomenon in the event that the feeder becomes isolated
Therefore, the usual insulation coordination process for wind from the substation bus, and the wind turbines continue to
plants is to select the available insulation level of commodity generate. A grounding transformer will stabilize a ground
distribution transformers, select the arresters needed to fault arc, by increasing its magnitude, and thus avoid the
protect that insulation level, and then determine amount of repetitive fault arc restriking that can lead to extremely
TOV that can be withstood. Using this knowledge, design escalated overvoltages in a system that is not intentionally
steps are taken to avoid or mitigate the TOV, such that the grounded (and thus grounded unintentionally via capacitance).
desired arrester voltage rating can be applied. In some cases, The impedance of the grounding transformer must be chosen
the designers of wind plant collector systems have chosen to so that the unfaulted phase voltages during a ground fault, and
ignore the TOV constraints, with the expectation that TOV subsequent cable isolation, are within the temporary
events are rare. However, some of these wind plants have overvoltage capability of the surge arresters. With
experienced numerous surge arrester failures, with synchronous generators, this grounding transformer
consequential generation unavailability due to the failures. impedance can be easily calculated. However, direct
There are also risks to equipment and personnel from ignoring calculation is not adequate for wind generation. This is due to
TOV, as explained later in this paper. the complexities of self-excitation, in the case of induction
wind generators, and interactions between controls, power
IV. MITIGATION OF TOV electronics, and the isolated system in the case of doubly-fed
Mitigation of TOV in wind plants allows surge arresters to and full-conversion wind generators. Detailed transient
be applied that provide adequate surge protection margins for simulations studies (using EMTP or equivalent tools), with
equipment with economically preferable insulation levels, detailed representation of any power electronic converters and
while avoiding undue risk of arrester failure. associated controls, are essential to defining the necessary
For the HV bus of the wind plant collector substation, a grounding transformer impedance and current capacity.
design that provides an effectively grounded system, under all Grounding transformers provide no mitigation in the event
circumstances, is desirable to avoid excessive TOV. While of a feeder islanding event where there is no permanent
the transmission grid might provide effective grounding to the ground fault on the feeder, and overvoltages are produced by
HV bus when the wind power plant is connected to the grid, self-excitation or interaction of the wind turbine generators
isolation (islanding) of the plant could remove this source of with the abnormal system impedance.
grounding. Therefore, the substation design should provide a Installation of a grounding transformer on a feeder
local source of grounding to the HV bus. eliminates the risk of ferroresonant overvoltages due to one or
The MV bus of the collector substation is generally two feeder breaker phases stuck open or closed.
effectively grounded as well. A substation power transformer When grounding transformers are located on the feeder
winding configuration providing ground sources to both the side of the breaker, the reverse ground current contribution to
HV and MV buses is the grounded-wye grounded-wye, with adjacent feeder faults should be considered. This may require
delta tertiary, connection. This winding configuration reduces directionality of the feeder breaker ground relay due to
zero-sequence coupling between the collector system and the coordination issues with adjacent feeders.
49
6
A grounding transformer is rated the neutral or ground 3) Wye-Broken Delta Grounding Transformers
current that the transformer is designed to carry under fault A variation of the grounded-wye delta grounding
conditions for a specified time, and the normal line-to-neutral transformer is one where the delta secondary is “broken” to
voltage. A one-minute-duration current rating is often used for allow insertion of an external impedance (typically
grounding transformers, though other ratings can be specified resistance). This allows the zero-sequence impedance to be
depending upon the probable duty to be imposed on the unit increased above the leakage impedance of the transformer
in service. The grounding transformer is continuously rated without inserting a resistor between the neutral of the wye
for a specific current at rated phase-neutral voltage, without primary and ground. This approach has application where it
exceeding the temperature rise of the insulation class as is desired to make a direct connection from the wye point to
specified in ANSI/IEEE Std. 32 [5]. For example, the ground, while increasing the zero-sequence impedance (such
standard requires, for a 1-minute rated unit, a continuous as to limit the magnitude of ground fault current). The
rating of 7% of maximum thermal current. resistance in the broken delta has a lower voltage rating and
For the same short circuit level, the zig-zag transformer will cost less than the higher voltage grounding resistance in
will have a smaller physical size in comparison to the wye- the wye-delta grounding transformer.
delta transformer. The zig-zag transformer is a custom-made
transformer. As a result, the procurement lead time for a B. Transfer Tripping
zig-zag transformer is usually much longer than the lead time Wind turbine generator tripping to remove all sources of
for procurement of a wye-delta grounding transformer. A generation from an isolated collector cable is a means to avoid
brief explanation of different types of grounding transformers overvoltages on islanded collector feeders. Because
is given in the next subsections [6-9]. overvoltages can be severe, and the ability of normally-rated
surge arresters to survive these overvoltages is very limited, it
1) Zig-Zag Grounding Transformer is important that the generators cease to energize the isolated
Each core leg of the zig-zag transformer has two coils
system by the time that the circuit breaker at the substation
wound on it. One coil is the outer coil and the other is the
interrupts. Thus, it is generally not a feasible solution to
inner coil. Each coil has the same number of windings turns
detect the isolation at each wind turbine through local voltage
but they are wound in opposite directions. Each phase has two
or current measurements, such as in an anti-islanding relay,
coils, which are wound on different core legs. Each of the
and then execute generator tripping. To do so exposes the
inner coils are connected together at one end to form the
system to a potentially severe overvoltage condition for the
neutral which is tied to ground either directly or through a
entire detection time plus the time to effect the deenergization
grounding resistor. A zig-zag grounding transformer can
(e.g., wind turbine generator breaker interruption time).
either be dry type or oil-filled.
A transfer trip scheme, with high-speed communications
Under normal system operation, with only positive
between the substation protection system and the individual
sequence voltage applied, the outer and inner coil windings’
wind turbine generators, is usually necessary to implement a
magnetic flux will cancel each other and only negligible
tripping solution. The transfer trip signal needs to be initiated
current will flow in the neutral of the zig–zag transformer.
by the protective relays causing the collector cable circuit
Application of zero sequence voltage, as during a ground
breaker to trip. The communication delay, plus the time
fault, the zig-zag transformer’s coils magnetic fluxes are no
needed to interrupt energization by the generators must be
longer in balance allowing zero sequence current to flow.
less than or equal to the interruption time of the collector
2) Wye-Delta Grounding Transformer cable circuit breaker to avoid isolation prior to deenergization.
A grounded-wye delta transformer will provide grounding In many cases, the trip signal to the collector cable circuit
functionally equivalent to a zig-zag transformer. The breakers at the substation may need to be intentionally
grounding function is independent of whether any load is delayed in order to coordinate generator tripping with
applied to the delta. Therefore, in a pure grounding collector cable isolation. The communication means used to
application, the delta winding need not have connection implement transfer tripping is typically fiber optic or radio,
terminals. but also power line carrier and hard-wired communication is
The neutral terminal of the wye winding is connected to also used.
ground either directly or through a neutral grounding resistor
C. High-Speed Grounding Switches
or reactor (i.e., impedance grounded).
An unloaded wye-delta grounding transformer provides A means to avoid TOV on an islanded feeder is to simply
high impedance to positive or negative sequence voltage apply a three-phase fault to the feeder with a high-speed
excitation, with only a small magnetizing current flow. grounding switch. This switch can be located at the
Application of zero-sequence voltage causes a current to substation and operated whenever the feeder breaker opens.
circulate in the delta, thus allowing current flow in the Reliable synchronization of the feeder breaker interruption
grounded wye winding. and the grounding switch closing is essential to minimize the
duration of any TOV due to islanding. Poor synchronization,
where the grounding switch closes before the breaker
50
7
interrupts, exposes the WTGs on other feeders, and the grid, the failed metal-oxide varistor disks out of the circuit.
to unnecessary fault transients and can expose the crowbar This can leave the protected equipment exposed to
switch to very high momentary currents. Interlocking of the future overvoltage events, and may leave the
breaker and grounding switch actions is desirable. On the equipment exposed to the TOV event causing the
other hand, any delay in closing of the grounding switch arrester failure if the short-circuit current available
exposes arresters and other equipment to overvoltages, and during feeder isolation is sufficiently small such that
thus the time between feeder interruption and ground switch the arrester failure fault self-extinguishes.
closing needs to be coordinated with surge arrester TOV Surge arresters failing due to TOV often do not
withstand capability. present readily visible evidence of failure, particularly
If the grounding switch is located within a bus differential prior to re-energization of the feeder from a strong
zone, to avoid misoperation of the differential protection short-circuit source (i.e., substation). After an
when the feeder breaker is open, current transformers will be isolation event of a feeder without TOV mitigation
needed for subtraction of grounding switch currents from the means, all arresters should be removed from service
differential current circuits. Otherwise, if these crowbar and tested, or alternatively all arresters should be
switch currents cannot be subtracted from the differential, the replaced.
differential current transformers will need to be located on the
bus side of this type of feeder breaker. This can significantly V. SYSTEM GROUNDING AT THE SUBSTATION
extend the feeder breaker failure clearing time, typically from The prior discussions of system grounding pertain to the
nine to fifteen cycles. collector feeders, with the assumption that the normal source
Closing a grounding switch on an islanded feeder does not grounding in the MV collection system is provided from the
make a significant step in real power, and thus does not substation bus. The selection of the wind plant’s main power
introduce a significant torque transient to the wind turbine transformer(s) winding configuration is critical to system
generator mechanical systems. Torque is associated with real neutral grounding. Assuming the utility transmission system
power and the only real power delivered by the WTGs after is effectively grounded, a grounded-wye-wye transformer will
ground switch closing is to supply I2R losses in the generator pass through the grid’s ground source to the MV level. If,
windings, transformers, and cables. The fault current is however, the wind plant becomes disconnected from the grid,
primarily limited by the inductive reactance (X) of the the source of grounding is lost. A delta (HV) grounded-wye
generators and transformers, and the resistive component of (MV) power transformer provides good system grounding for
total impedance is small. Thus, the positive torque step the MV system. However, in the event of separation from the
caused by applying the grounding switch is much smaller than grid, the HV side is not grounded. The solution used in most
the negative step caused by isolating the feeder. current wind power plants is to use a grounded-wye-wye
D. Do Nothing – Accept Failures transformer with a delta tertiary. The delta tertiary provides a
ground source to both the MV and HV levels.
A strategy used by some wind plant designers is to
Some utilities demand that wind plants use a grounded-wye
purposely do nothing about the TOV caused by feeder
(HV) delta (MV) transformer, identical to the connection
isolation and to accept the equipment failures that may result.
typically used for conventional power plants. This connection
Surge arresters are the most equipment most vulnerable to
provides no grounding for the MV system. If grounding
TOV, and the expected failure mode of arresters is to become
transformers are connected to the individual feeders, these
a low shunt impedance or short circuit, thus sacrificially
transformers together will provide some degree of grounding
protecting other equipment. Distribution-class surge arresters
for the MV bus, only to the degree that the feeders are
are relatively low-cost equipment, particularly when
connected. If all feeders are disconnected, the MV bus will
compared to the costs of the various options for limiting
not be grounded at all. If the feeder grounding transformers
TOV.
are sized for the purpose of providing grounding to control
There are some potential pitfalls with this strategy,
TOV during feeder isolation events, their zero-sequence
however:
admittance will be much too small to provide effective
Surge arresters are designed and tested to fail in a
grounding when the power transformer is connected to the
manner specified by IEEE Standard C62.11 [10]. The
strong short-circuit source of the grid. Therefore, where a
conditions of the standard test do not reflect all the
grounded-wye delta power transformer is mandated by the
conditions of TOV failure that may occur in the field.
utility, a very large and expensive grounding transformer is
Failure of arresters, particularly delayed failure that
needed on the MV bus if effective grounding is desired. It
may occur after an islanded feeder is reconnected to
may be possible to design the MV system to have acceptable
the substation, can be eventful and is not without risks
insulation coordination with a high-impedance ground using a
of personal injury and consequential damage.
smaller grounding transformer. This can be very challenging
A surge arrester, particularly a distribution class
where a 34.5 kV collector voltage is used because of the
arrester, may fail to an open circuit condition due to
unavailability of distribution-grade equipment that has
excess TOV that causes the housing to fail and drop
51
8
sufficient insulation levels (BIL). step potentials around the WTG tower base, due to lightning
and MV ground fault currents.
VI. APPARATUS GROUNDING WTG grounding systems typically consist of a perimeter
ring of bare copper with driven rods that serve as the
A. Collector Substation grounding electrode. A specified maximum resistance to earth
The grounding, or earth bonding, of the collector is typically specified by WTG manufacturers, usually 1 to 10
substation is essential for control of step and touch potentials ohms.
resulting from ground faults, due to the very high fault current A new approach to grounding design eliminates the WTG
capacity present. Substation grounding design for a wind grounding ring, replacing it with designs that utilize the
plant is identical to the practices used for utility and industrial turbine’s foundation metal and concrete as a grounding
substations. electrode. To ensure mechanical and electrical continuity
connections between the foundation ground conductor require
B. Wind Turbine Generator
specific clamps that are rated for grounding purposes; and any
Providing an adequate equipment grounding, or bonding, place where the conductor crosses rebar in the foundation it is
system within the design of the WTGs is critical for secured with wire ties to make sure it does not shift when the
protection of personnel, equipment and buildings, as well as concrete is poured.
the reduction of electrical noise, proper operation of electrical Some grounding designs also include bare ground
and electronic communication and control equipment, and conductors interconnecting the WTGs in the wind plant. If
protective circuit breakers and fuses. Apparatus grounding these interconnecting cables share a common trench with the
within a WTG is part of the WTG design and installation, and power cables, voltages across the cable jacket are reduced.
is not a collector system design issue. Otherwise, these interconnections provide limited benefit for
The apparatus grounding issue germane to collector design lightning surges, due to surge propagation effects.
is the bonding of the WTG to the earth. A good earth
electrode design provides a path for lightning current, and a VII. REFERENCE
path for MV-system ground fault currents. (The LV system at
[1] IEEE Guide for the Application of Neutral Grounding in Electrical
the wind turbine generator is typically a “locally derived” Utility Systems—Part I: Introduction, IEEE Standard C62.92.1-2000,
system using a delta (MV) grounded-wye (LV) unit April 4, 2001.
transformer winding connection. Any LV ground fault [2] W. E. Feero and W. B. Gish, “Overvoltages Caused by DSG Operation:
Synchronous and Induction Generators,” IEEE Trans. Power Delivery,
currents stay locally within the confines of the WTG and vol. 1, no. 1, pp. 258 - 264 Jan. 1986.
transformer.) Large earth electrode impedance will cause [3] IEEE Standard for Insulation Coordination—Definitions, Principles, and
elevation of the potential of the electrode, and the WTG Rules, IEEE Standard 1313.1-1996, Oct. 2, 1996.
[4] Guide for the Application of Metal-Oxide Surge Arresters for
structure bonded to it, in the event of a lighting strike to the Alternating-Current Systems, IEEE Standard C62.22-1997, July 17, 1998.
WTG. The earth connection impedance, however, has little [5] IEEE Standard Requirements, Terminology, and Test Procedure for
impact on voltage differences at the WTG, and thus does not Neutral Grounding Devices, ANSI/IEEE Standard 32-1972 (Reaffirmed
directly affect insulation levels or surge arrester requirements. 1990).
[6] E. W. Bogins, Industrial Power Systems GER-2659 Grounding
Some manufacturers, however, tie LV surge arrester Transformers.
requirements to the resistance of the WTG earth electrode. [7] Electrical Transmission and Distribution Reference Book, ABB, 1997.
A poor earth electrode, however, will cause large surge [8] E. R. Detjen and K. R. Shah, “Grounding Transformer Applications and
Associated Protection Schemes,” IEEE Trans. Industrial Applications,
currents to pass through the concentric neutral conductors of vol. 28, no. 4, pp. 788-796, Jul.-Aug. 1992.
the MV collector cables. Insulated-jacket cable is commonly [9] iGard, Neutral Grounding Resistors Technical Information Application
used, and these surges can cause large potential differences Guide, available online at: http://www.i-gard.com/appguides.htm
[10] IEEE Standard for Metal-Oxide Surge Arresters for AC Power Circuits
between the cable neutral and local ground at locations (> 1 kV), IEEE Standard C62.11-2005.
remote from the WTG where a lightning strike occurs. This
can cause breakdown of the jacket insulation, and a flashover
from the neutral to the local soil. Compromise of the cable
jacket does not have an immediate impact on operation of the
cable. The piercing of the jacket, however, can allow a path
for moisture ingress, possibly leading to long-term breakdown
of the cable’s major insulation (core to neutral) and corrosion
of the neutral strands. A poor earth connection will also cause
surge currents to propagate over any metallic communication
wires connecting the WTG to remote facilities. This can
cause damaging voltage surges at the remote facilities. For
this reason, the use of fiber communication links to WTGs is
common.
A poor earth electrode design can also result in increased
52
1
Contributing Members: M. Bradt, M. R. Behnke, T.A. Bellei, W. G. Bloethe, C. Brooks, E.H. Camm,
W. Dilling, B. Goltz, J. Li, J. Niemira, K. Nuckles, J. Patiño, M. Reza, B. Richardson, N. Samaan, J. Schoene,
T. Smith, I. Snyder, M. Starke, K. Tay, R. Walling, G. Zahalka
Abstract— The topic of this paper is the arc-flash hazard in • Overvoltage conditions
Wind Power Plants (WPP). A brief introduction of the concept • A combination of the above.
of arc flash is followed by the presentation of a methodology to
perform an arc-flash hazard analysis on a WPP collector system. In power systems the path of the arc can be between two
Issues such as faults being fed by multiple sources, as well as the phases, multiple phases, single phase and ground, and multiple
modeling of the fault current of the wind turbine generator are phases and ground. The arc flash is surrounded by a conduc-
addressed. The paper concludes with two examples using the tive plasma cloud and often vaporized conductive material,
presented methodology.
which increases the likelihood of a single-phase fault making
Index Terms— Arc-flash hazard, shock hazard, wind power contact with nearby phases and escalating into a three-phase
plants. fault. This is more likely to happen on systems with low insu-
lation level and at locations with small clearance between
I. INTRODUCTION conductors, such as low-voltage systems and switchgear
equipment. For these cases a single-phase fault often escalates
This paper investigates and discusses the arc-flash hazard
into a three-phase fault within a few milliseconds (Schau and
in a Wind Power Plant (WPP) collector system. It will define
Stade, 1995).
an arc-flash calculation methodology for multiple sources and
A large amount of energy is released during an arc flash,
provide two examples of the methodology.
primarily in the form of heat. The burn hazard during an arc
The approach this paper will be as follows: Section II dis-
flash is the main concern for worker safety (e.g. Lee, 1982).
cusses the arc-flash hazard in general – the causes of arcs, the
Additionally, the energy released in the form of pressure is of
available models to calculate incident energy levels and cer-
concern for worker safety since the pressure wave can directly
tain concerns, which are specific to wind power plants. Sec-
injure the worker or can destroy objects resulting in shrapnel
tion III describes the possible mitigation strategies – defining
that can injure the worker (Lee, 1987). The part of the arc
an arc-flash protection boundary, the types of personal protec-
flash that is associated with the release of a pressure wave is
tive equipment (PPE) available, and possible means of reduc-
commonly referred to as the ‘arc blast’ (Dugan, 2007).
ing incident energy levels through various technologies. Sec-
The arc-flash fault current is generally smaller than the
tion IV presents a detailed, structured method to calculate arc-
bolted fault current of the system due to the impedance of the
flash incident energy levels in a WPP. Section V concludes
arc. The incident energy is the energy impressed on a surface
the paper with two examples.
at a certain distance from the arc and is used as a measure to
II. ARC-FLASH HAZARD quantify the burn hazard from an arc-flash.
Arc-flash energy is transferred to the surroundings by con-
A. General Description of Arc-flash Hazard duction, convection, and radiation energies (Wilkins et al.,
An electric arc is the result of the electrical breakdown of 2004). For enclosed equipment, a substantial part of the
an insulator (typically air) resulting in current flowing through arc-flash energy is also converted to pressure. Figure 1 illu-
the insulator. An arc-flash fault is often caused by: strates the energy dissipation for open-space and enclosed-
• Human mistake (e.g., dropping a tool, accidental con- space configuration. For arcs in open spaces, the geometry of
tact with live parts) the energy emission is spherical and consequently the fraction
• Environment (e.g., contamination, water vapor) of the total arc energy that is emitted as radiant energy is pro-
• Equipment failure (e.g., insufficient insulation, deteri- portional to 1/D2. On the other hand, there is a focusing effect
orated insulation, corrosion) for the enclosed-space configuration, which increases the
energy emitted in the direction of the opening. Consequently,
the radiation emitted from the box is less divergent than for
the spherical geometry resulting in a distance relationship of
1/Dx with the distance exponential x being smaller than 2.
54
3
energy levels that are potentially much higher than predicted III. ARC-FLASH HAZARD PROTECTION
by any of the models discussed here. There is no consensus in
A. Protection Boundary
the literature about the dimension of the plasma cloud. Lee
(1982) assumed a spherical dimension for the plasma cloud IEEE 1584 defines the arc-flash protection boundary to be
and predicted for one configuration an arc plasma diameter of the area around an energized object in which a person without
170 mm. On the other hand, for the same configuration, PPE is at risk of receiving at least second degree burns from
Stokes and Sweeting (2005) experimentally determined a an arc-flash originating from the energized object. Skin expo-
much larger plasma expansion – they measured an arc plasma sure to energy levels that exceed 1.2 cal/cm2 can cause
dimension of 3m x 1.5m from a photograph. Also, for en- second-degree burns. Persons within this area are required to
closed space configurations the plasma cloud is likely to ex- wear PPE. The flash protection boundary is determined in an
pand farther in the direction of the worker due to the focusing arc-flash analysis.
effect (see Section IIA) B. Protection Equipment
C. Arc-flash Concerns specific to Wind Plants NFPA 70E (2004) classifies the arc-flash hazard according
Typically, during wind plant commissioning, the equip- to maximum incident energy a person can be exposed to. The
ment inside the wind turbine tower has to be approached in an NFPA 70E hazard categories are listed in Table 1. Protection
energized state. This is a problem if the arc-flash analysis requirements, such as Personal Protective Equipment (PPE),
predicts large incident energies at locations inside the turbine. are selected based on the hazard category. The PPE should
Temporary protection settings (e.g., relays set on instantane- limit the energy exposure of the chest and face during an arc-
ous trip) may be applied to reduce the incident energy at loca- ing fault to curable burn energies (below 1.2 cal/cm2 accord-
tions with excessively high incident energy levels. ing to IEEE 1584). In some cases the maximum incident
In particular, the arc-flash hazard inside the wind turbine energy level may exceed 40 cal/cm2. For these cases, risk
tower may be more severe than predicted by the arc-flash ha- consideration will play a major role. There is PPE available
zard analysis because of the following concerns: above 40 cal/cm2, however the preferred approach is to always
work such high levels de-energized.
• Convective heat transfer that is not properly accounted
for in models used for the arc-flash hazard analysis in-
TABLE 1: NFPA 70E HAZARD CATEGORIES
creases the incident energy if the worker is inside the
Energy
plasma cloud (see Section IIB). A worker location inside
Category Level Protective Clothing/PPE
the plasma cloud is likely due to (1) the focusing effect of
(cal/cm2)
the arc-flash in the enclosed space configuration, which
Long-sleeve shirt and long pants
directs the plasma towards the worker and (2) the tight
0 <1.2 composed of non-melting or un-
space inside the turbine tower, which may result in a re-
treated natural fiber, safety glasses
duced working distance.
FR long-sleeve shirt, FR pants, hard
• The arc-blast hazard (the hazard due to the pressure 1 1.2-4
hat, safety glasses
from the arc fault) is potentially more severe inside the
Category 1 protection + arc-rated
turbine tower because of (1) the focusing effect of the
2 4-8 face shield, hearing protection,
blast in the enclosed-space configuration, which increases
leather gloves, leather work shoes
the pressure exerted on the worker, (2) the inability of the
Category 2 protection + FR cove-
worker to move away from the blast, and (3) the fall ha-
3 8-25 rall, FR hard hat liner, flash suit
zard inside the turbine tower. Note that the arc-flash ha-
hood
zard analysis does typically not assess the blast hazard.
Category 3 protection + flash suit
• The two-second rule in IEEE 1584 (i.e., using two 4 25-40
jacket, flash suit pants
seconds as the maximum time a person is exposed to an
arc-flash because the person will be able to move to safety
within that time) does not necessarily apply due to the re- 1) Protection Devices
stricted ability to move inside the turbine tower. Protection devices, such as Overcurrent Protection Devices
• The duration of the arcing fault current contribution (OCPDs) are used for fault clearing. OCPDs and other protec-
from the turbine may depend on the turbine protection on- tion devices are:
ly (i.e., there may not be any fuses/relay protection be- Fuses: Fuses are reliable OCPDs which do not require pe-
tween the turbine and the arc fault location that discon- riodic maintenance. A Fuse clears a permanent fault by re-
nects the turbine from the fault). Consequently, to prop- moving the faulted segment from the circuit. The fusible ele-
erly account for the fault current contribution from the ment is heated and melted by the overcurrent. The behavior of
turbines, some insight into the protection mechanism of the fuse is characterized by a time-current plot, which shows
the turbine is required, which may not be always available two curves – (1) the minimum melting curve and (2) the total
to the person performing the arc-flash analysis. clearing curve. The minimum melting curve gives the melting
time of the fusible element for any given current. After the
fusible element melts, the circuit is not immediately inter-
rupted due to arcing between the fuse terminals. The sum of
maximum melting time and the duration the fuse arc is sus-
55
4
tained (i.e., the fuse arcing time) represents the total clearing Ground Fault Sensors: Ground fault sensors detect the
time. The fuse clearing time increases with decreasing current current imbalance during a phase-to-ground fault (most arcing
magnitude and consequently arc flashes during low-current faults start as a phase-to-ground fault and may develop into a
faults may have larger energies than arc flashes during high- multiphase fault). They have the advantage over overcurrent
current faults. sensors in that they are more sensitive and can therefore trip
faster. Ground fault sensors should be installed in multiple
places to allow low settings resulting in faster clearing times.
(Dugan, 2007).
56
5
57
6
with each of the separate fault flows that would be contribut- Collector Crow Bar
WT Tower
Crow Bar
WT Tower
ing to the event. The initial fault calculation run may be ade-
Top Top
Sub Sub Transf
lar location to obtain its fault flows for the momentary, inter- MV CB LV CB
WT Tower
Base LVCB
WT Tower
Base
Flow 1 LV LV
rupting, and steady-state conditions from all sources and de-
termine how much is flowing through the protecting devices to MV
4) Determine the total clearing times for all the protecting Flow 2 C.L. Fuse
Transformer
Tank C.L. Fuse
Transformer
Tank
devices that are allowing fault flow to the fault location, such Exp. Fuse Exp. Fuse
MV
Feed Thru w/ Sw.
a) At the collector feeder breaker relay – use the TCC curve <----------- Collector Circuit ------------> : Possible fault location
and find the respective time for the fault flow passing through
it (taking into account a faster trip of the breaker due to a Figure 5: Example of fault and arc-flash in air at MV feeder.
higher momentary current) from the substation and external
power system, or
b) In the LV secondary cabinet of a wind turbine step-up There are three sources contributing to the fault: the system
transformer use the transformer fuses, the LVCB TCC, or the and each of the two turbines. Since this is an open-air loca-
control logic to the LVCB to estimate the time depending on tion, the NESC default values from Table 410-1 offer a good
the fault flow direction – use either the transformer fuses or baseline. Fault flows to this location will determine the loops,
the control logic to trip and clear the LVCB to estimate the which are two in this case, Flow 1 and 2. The fault flow from
time. the substation bus (Flow 1) will be seen by the MVCB relay
5) Determine the amount of incident energy occurring at and it will clear its portion of the fault flow first. For this ex-
this location by using an arc-flash model (such as the IEEE ample (Figure 5), a fault flow for Flow 1 will be 5 kA and the
1584 model, the ARCPRO model, or another model) with all clearing time, which was obtained from reading the TCC plot
the respective contributing fault current sources (step 3) and for the collector feeder relay at 5 kA, will be 0.10 seconds.
the clearing time of the next fastest clearing device (step 4). However, there is a second delayed fault flow (Flow 2)
For instance: that continues from the two turbines. At the wind turbines the
a) At a 34.5kV substation collector feeder exit - use clearing devices are the LVCBs at 600 V and the two internal
ARCPRO with the parameters from step 2, such as the open- transformer fuses on the 34.5-kV side. If the contributing cur-
air three-phase case at 15-inch working distance and a 6-inch rent from any one turbine is not large enough to trip the LVCB
arc gap (NESC Table 410-1), or on overcurrent, then the control scheme for the LVCB will
b) in a 600V secondary cabinet of a step-up transformer – respond to a low-voltage condition and wait a predefined
use IEEE 1584 with the parameters from step 2, such as the amount of time based on the actual voltage that each turbine
under-1000V and in-a-box options that will provide a 24-inch sees against the predetermined low voltage ride-through
working distance and an 1.25-inch arc gap (IEEE 1584 Tables (LVRT) envelope. Note that the LVRT time delay is depen-
2 and 3). dent on how low the voltage drops. Typically, if it goes below
6) Loop steps 3 though 5 for each successively slower pro- 15% of nominal it will be at its shortest delay, which will be
tecting device as it removes its respective amount of contribut- 0.15 seconds in this example. However, the delay could be
ing fault flow from this location from the quickest device to longer if the voltage during the fault is higher than 15%. For
slowest device, until all the fault flow is eliminated. this example, the assumption will be that the control schemes
7) Sum the arc-flash incident energy from each of the suc- on all WT LVCBs on the collector feeder will simultaneously
cessively passes for this location. This sum will be the total see a sustained zero voltage to initiate a trip to their LVCB at
incident energy for this location. the minimum time delay. The total time delay for Flow 2 will
8) Finally, repeat the steps 3 through 7 for all selected loca- be 0.35 seconds. In this example, the 0.35 seconds consists of
tions. 0.15 seconds delay from the LVRT envelope and 0.10 seconds
58
7
for the control circuit and LVCB clearing time to respond to Since the fault currents are much higher on the 600 V side, the
an external trip signal, as well as the initial 0.1 seconds for the arc-flash values are certain to be larger as well.
feeder circuit breaker to clear. As mentioned, it will be as- Assuming the MVCB feeder relay, the transformer fuses
sumed that both turbines will respond identically and at the and the LVCB are all coordinated, then the sequence of clear-
same time. However, this methodology is flexible enough to ing can be determined from the TCC plot that was used in
allow for multiple delayed devices clearing at different times. their coordination. That coordination would have the trans-
It is understood that the fault current from the WTG for the former fuses clearing before the feeder breaker to keep the
initial few cycles will be obtained from the momentary condi- feeder energized while the generator is taken off-line. There-
tion of the short circuit, or around five times the rated current, fore the clearing sequence for this location will be between the
and then drop off very quickly as the turbine responds electri- LVCB and the fuses, with the fuses generally taking the longer
cally. However, fault current from the WTG, before it drops time and the LVCB tripping first to clear the local generator.
off as seen on the 34.5-kV system at the MVCB will be small The LVCB’s clearing time will be defined the same way here
compared to the contribution from the substation and external as it was in the first example by the LVRT with a total time of
system. By the time the MVCB clears, the WTG contribu- 0.35 seconds. The clearing time will be shorter if the overcur-
tions will either be at the interrupting or steady-state condi- rent mechanism responds before the LVRT trip.
tion. For our example, the interrupting condition will be used,
or about 99 Amps (three times the rated current of 33 A).
Since both turbines are contributing to the fault flow, the de-
layed contribution is approximately 198 Amps. With these
values the incident energy is calculated with the respective
calculator, which is this case for both loops of the method
produced the values in Figure 6 for a total of 8.4 cal/cm2.
Fault
Current Total 8.4 cal/cm
2
at the
Site of
the Arc-
flash
Event
0.10 sec
Time Duration of Arc-flash (sec) The fault flow from the wind turbine generator, Flow 3, in
Figure 7, will be the momentary condition fault current value
Figure 6: Arc-flash results for a fault in air at MV feeder ((not-to- which could be nearly five times the rated current, or about
scale). 10,000 Amp plus the steady state fault flow from the collector
feeder, Flow 4, of 35 kA. The momentary condition is used
because it represents a conservative value. Thus, a total fault
Example 2 – Using the same WPP setup, the fault and arc- flow of about 45 kA will result for 0.35 seconds. After the
flash now occurs in the LV (600 V) cabinet of the first wind LVCB clears the fault flow (Flow 3) from the local WTG, the
turbine step-up transformer. See Figure 7. fault flow from the collector (Flow 4) will still be contributing.
At this location there are also three sources, but two fault The total clearing time for this portion is found by locating
flows. One flow is from the generator associated with this this fault flow of 35 kA on the TCC of the transformer fuse set
transformer (Flow 3), and the other is from the collector feeder and finding where it crosses the total clear curve of the first
(Flow 4), which represents the contributions from the other fuse in the transformer to open. For this example 0.55 seconds
turbine, the substation and the external power system. Since will be used. However, this delayed clearing will have its arc-
this location is in a cabinet (a.k.a. in-a-box) and is on the low- flash contribution bounded by the duration of the difference
voltage side, the assumptions and equations from IEEE 1584 between the fuse total clearing time and the LVCB clearing
empirically will be the best choice and will provide a good time of 0.35 seconds, which will provide a final interval of 0.2
baseline. Therefore, the working distance, gap size, and de- seconds of fault flow from the collector feeder, before the
fault values will come from their respective tables in the IEEE transformer fuse opens. Figure 8 shows both intervals and
1584 document. Because this fault is at 600 V, the Ampere their respective incident energy contributions with the total
level of the fault flows (Flows 3 and 4) will be much higher being about 34.2 cal/cm2.
compared to a similar power level on the 34.5-kV system.
59
8
[8] Lee, R.H., “The Other Electrical Hazard: Electric Arc Blast Burns,”
IEEE Transactions on Industry Applications, Vol. 1A-18, No.3,
May/June 1982.
[9] Lee, R.H., “Pressures Developed by Arcs,” IEEE Transactions on Indus-
45kA 2 try Applications, Vol. 1A-23, No.4, July/August 1987.
Total 34.2 cal/cm
[10] Martin, L., J. Beattie, “Arc Protection Recommendations for SaskPower
Transmission and Distribution,”, TS&R Report Number 05-345, 2005.
0.35 sec [11] Schau, H. and D. Stade, “Requirements to be met by protection and
35kA
switching devices from the arcing protection point of view,” 5th Interna-
tional Conference on Electric Fuses and their Application, September
Fault 1995.
Current 0.20 sec
[12] Reilly, J.P., H. Antoni, M.A. Chilbert, “Applied Biolectricity,” ISBN
at the
0387984070, Springer, 1998.
Site of 23.6 cal/cm
2
the Arc- 2 [13] Wallace, K., L. Garrett, and S. Patel, “Protective Grounding Methods
10.6 cal/cm and Requirements on Distribution Line Wood Pole Construction,” Pro-
flash
Event ceedings of the 11th International Conference on Transmission & Distri-
bution Construction, 15-19 October 2006.
[14] Wilkins, R., M. Allison, and M. Lang, “Improved Method for Arc-flash
Hazard Analysis,” IEEE Industrial and Commercial Power Systems
0.0 0.35 0.55 Technical Conference, pp. 55-62, 2-6 May 2004.
Time Duration of Arc-flash (sec)
VI. CONCLUSION
This paper has investigated and discussed the arc-flash ha-
zard on a WPP collector system. A brief discussion of the arc-
flash hazard and its causes were presented along with a me-
thodology and two examples for tallying the total incident
energy from multiple sources.
The use of the various conditions of fault current in the me-
thodology, are presented as a conservative measure for esti-
mating the arc-flash incident energy, but it must be understood
that the real behavior of the fault current from the WTG is
very unpredictable and situation dependent. From these two
brief examples it can be seen that one of the highest levels of
the arc-flash hazard in a WPP collector system can be on the
LV cable and inclusive cabinets between the LVCB and the
step-up transformer. However, these results could be very
different if another arc-flash calculator were used, such as the
IEEE 1584 theoretical model, which has a dependence on vol-
tage.
VII. REFERENCES
[1] Ammerman, R.F., T. Gammon, P.K. Sen, and J.P. Nelson, “Comparative
Study of Arc Modeling and Arc-flash Incident Energy Exposures,” Pe-
troleum and Chemical Industry Technical Conference, pp. 1-12, Cincin-
nati, OH, 22-24 Sept. 2008.
[2] Dalziel, Charles F., “The effects of electric shock on man,” IRE Trans-
actions on Medical Electronics (PGME-5), May 1956.
[3] Doughty, R.L., T.E. Neal, T.A. Dear, and A.H. Bingham, “Testing up-
date on protective clothing & equipment for electric arc exposure,”
Conf. Rec. IEEE PCIC, pp. 323-336, Sept. 1997.
[4] Doughty, R.L., T.E. Neal, H.L. Floyd II, “Predicting Incident Energy to
Better Manage the Electric Arc Hazard on 600-V Power Distribution
Systems,” IEEE Trans. On Industry Applications, Vol. 36, No.1, Janu-
ary/February 2000.
[5] Dugan, T.B., “Reducing the flash hazard,” IEEE Industry Applications
Magazine, May/June 2007.
[6] Kinectrics, “User’s Guide for ArcPro,” 2004.
[7] King, Clayton, “Maintaining line worker safety through maintenance
and testing of protective grounding equipment,” T&D construction, op-
eration & live-line maintenance proceedings, pp. 101-107, 26-30 April
1998.
60
1
Contributing Members: M. Bradt, M. R. Behnke, W. G. Bloethe, C. Brooks, E.H. Camm, W. Dilling, B. Goltz,
J. Li, J. Niemira, K. Nuckles, J. Patiño, M. Reza, B. Richardson, N. Samaan, J. Schoene, T. Smith, I. Snyder,
M. Starke, R. Walling, G. Zahalka
Abstract- This paper presents a summary of the most im- II. WIND POWER PLANT SHORT-CIRCUIT MODELING
portant protection and coordination considerations for The WPP short-circuit model and associated fault plot is an
wind power plants. Short-circuit characteristics of both initial step in any protection and coordination study. There
aggregate wind plant and individual wind turbine genera- are three main types of short-circuit contributions within a
tors, as well as general interconnection protection re- WPP: (1) the utility, (2) WPP aggregated or individual WTG,
quirements are discussed. Many factors such as security, and (3) any dynamic reactive compensation equipment contri-
reliability, and safety are considered for proper conserva- butions. There are many guidelines and standards available
tive protection of the wind power plant and individual for modeling of generators, transformers, lines, cables, bus
turbines. work, and reactive compensation equipment for all voltage
systems.
62
3
low a protection engineer to analyze the contingencies that system. Some of this communication will be in the form of
result in the minimum and maximum fault currents to develop interconnection agreements, interconnection standards, and
the protective relay settings for the WPP. providing for special protection scheme integration with the
utility power system. There are many standards, such as IEEE-
III. WIND POWER PLANT ZONES OF PROTECTION 1547, FERC-661, as well as NESC and NEC standards, which
There are several potential zones of protection within a address interconnected generation. For a transmission con-
wind power plant. These protection zones are outlined below nected WPP, the protection scheme requirements are often
and generally consist of utility interconnection, wind plant dictated by utility requirements for integration into the exist-
substation, wind plant collection system, and wind turbine ing power system protection schemes. These schemes are part
generator. The interconnected utility zone will consist of of a larger transmission network and need significant consid-
connections to a transmission network, a radial sub- eration when adding new generation to these systems. For
transmission circuit, or a medium or low voltage distribution example older line distance relay schemes may have one zone
circuit. For the transmission network interconnection, protec- of line protection with individual phase and ground distance
tion schemes typically consist of high speed communications electromechanical relays. These schemes often employed
assisted power line carrier blocking or unblocking schemes, backup protection in the form of individual time overcurrent
permissive over or under reaching transfer trip, line current relays, which will require significant coordination considera-
differentials, as well as overcurrent, breaker failure, voltage, tion when adding a wind power plant and its contribution to
and frequency protection schemes. The radial sub- the network line.
transmission circuit interconnection will typically employ For interconnecting transmission lines it is sometimes ne-
radial distance, overcurrent, voltage, frequency and breaker cessary to use high speed clearing schemes incorporating
failure protection located at the utility interconnection substa- power line carrier blocking and unblocking schemes, and
tion which will have a protection zone overlapping reach into transfer trip schemes which will have backup distance and
the high side winding of the main WPP substation transfor- overcurrent relays. For sub-transmission connected WPP,
mer. The distribution interconnection for a WTG or WPP will radial lines are common and the utility line protection is coor-
typically consist of utility feeder circuit overcurrents, reclos- dinated with the WPP main transformer high side backup
ers, circuit fuses, breaker failure, voltage, and frequency pro- overcurrent relays and utility distance relays reach into the
tection. The WPP substation can consist of high side bus, high voltage winding of the WPP main transformer. Other
low side bus, transformer, static and dynamic reactive com- schemes may simply incorporate bus differential relays which
pensation equipment, and effective grounding transformers. wrap the high voltage bus of the WPP with the adjacent inter-
The main transformer is protected with differential and back- connection transmission substation high voltage bus, in this
up overcurrent relay schemes. Substation bus protection will instance coordination is fairly simple. Distribution connected
consist of high-impedance, low-impedance, or current diffe- WPP or WTG installations often require coordination with
rential schemes and associated overcurrent relaying. Effective reclosers, inline circuit fuses, and utility feeder overcurrent
grounding equipment is usually protected by differential and relays. For all of the above interconnection configurations,
negative sequence overcurrent schemes. Reactive compensa- it is also important to coordinate the PCC voltage, frequency,
tion equipment, such as capacitor or reactor banks, are typical- breaker failure, and excitation relays with the utility, which
ly equipped with overcurrent, voltage, and breaker failure are incorporated within the utility interconnection agreement
protection schemes. The WPP collector system zone consists for the specific wind plant. For distribution connected WTG
of substation circuit breaker and associated overcurrent, vol- or WPP, there are other protection schemes which are some-
tage, frequency, and breaker failure protection scheme. Some times required such as reverse power relaying, special sectio-
collection system circuits consist of grounding transformers or nalizing, and throw-over schemes to maintain system security
ground switches, which protect the circuit during unbalance and reliability.
and temporary overvoltage conditions, these devices can pro-
vide a significant zero sequence current contribution during V. WPP PROTECTION
unbalance conditions and should be considered for protection
A. WPP Substation Transformer
coordination. The WTG zone consists of a WTG step-up
transformer with high side fuse or protective relay, current The design of the WPP substation main transformer will
limiting fuse, WTG protective overcurrent trip unit and asso- vary, depending on the design requirements and availability.
ciated WTG voltage and frequency protection. Main transformer winding configurations that have been im-
plemented on wind plants primarily consist of wye/wye/delta,
IV. WPP INTERCONNECTION COORDINATION delta/wye, and wye/delta connections [11].
Protection coordination of a wind power plant with the in- The WPP main substation transformer banks will typically
terconnected utility is achieved at the PCC (point of common be equipped with high-speed primary and secondary differen-
coupling). During the engineering phase of any wind plant tial relays. The transformer high-side protection will also in-
development, the protection coordination is achieved, at the corporate instantaneous and backup overcurrent elements. If
PCC, by specific communication between the utility protec- available, the high and/or low side neutrals of each of these
tion engineer and wind plant developer. This communication main transformers will typically incorporate a ground time
assures that proper protection scheme requirements are met overcurrent and sometimes even restricted earth fault protec-
within the guidance of the existing transmission or distribution tion [1,2,4,10]. The primary function of the transformer
63
4
ground relay is to protect the transformer and provide backup tective relay targets indicate location of faults that may have
to the bus, collectors, bus tie breakers, and capacitor banks occurred on the transformer or on one of the buses or bus tie
[6]. For cases when the transformers have neutral ground breakers. With modern differential relays it is important to
connections, fault current-limiting resistors or reactors are select the proper current transformer to avoid mismatch and
sometimes used and a zero sequence voltage relay becomes saturation affects. The current transformers used are usually
necessary for protection of the resistor or reactor [1, 2, 5, tapped to the highest ratio in order avoid saturation. Harmonic
10]. restraints are often set to avoid false tripping under certain
For substations equipped with wye/delta type main trans- conditions [1, 2, 3]
formers, there is often a requirement for effective grounding Medium-voltage bus differentials are most often current or
where X1/X0 < 3 [1, 7]. To reduce the effective ground im- high-impedance differential relays. The high impedance diffe-
pedance, grounding transformers, usually in zig-zag or rential senses the differential voltage of the bus connections,
wye/delta configurations as shown in Figure 5, are used and and therefore requires that all of the current transformer knee
require separate differential protection as well as negative voltages and lead cables be considered in the calculation of
sequence overcurrent protection. Since the transformer is not the differential trip point. Since there will be a small operating
a source of ground current, the negative sequence elements are voltage at the relay terminal due to the voltage drop of current
deployed for internal faults. transformer lead cables, the trip point must be set to avoid
tripping for this steady state bias [8]. Other considerations for
high impedance differentials are to de-sensitize any phases
which have station service transformers within the differential
zone [1, 2].
C. WPP Collector Protection
Wind plant collector systems have primary protection for
the overhead or underground collection system and are inter-
rupted via circuit breaker in the WPP substation. These collec-
tor system breakers incorporate phase and ground overcur-
rents, voltage, frequency, and breaker failure protection. The
primary function of these collector circuit relays is to protect
the forward reaching cable system and backup the WTG step-
up transformer protection devices. It is important to consider
the cable or overhead line damage curves, as well as minimum
and maximum melt curves for WTG high side step-up trans-
former protection.
The collector relays and backup protection should be time-
coordinated with each WTG step-up transformer’s high-side
protection. Each of these collector relays will typically be set
Figure 5. Wye-Delta Main Transformer Configuration to have directional time overcurrent elements for fast clearing
of the collector circuits. Directionality should be used if the
reverse load or reverse fault is greater than the pickup value
For three winding transformers, differential relays are used used. Sometimes backup directional and non-directional nega-
to protect for internal transformer faults and typically incorpo- tive sequence protection for each of the generator step-up
rate one or more neutral connected ground relays, high-side transformers is incorporated. Since high current faults can
backup overcurrents, breaker failure, and sometimes low side damage the cable system, sometimes definite time overcurrent
backup overcurrent relays when there is a low-side breaker elements are implemented for main circuit protection for cases
[1,2,3,4] where there is concern that the WTG transformer may not
clear on a close-in high side fault. The zero sequence contri-
B. WPP Substation Bus bution from WTG step-up transformers will be zero but the
The WPP substation will have a high side and low side bus collector grounding transformers will contribute a significant
differential. Typically the high side bus differential is only amount of ground current. As a result, the ground elements
needed when there is more than one interconnecting line or should be set sensitive in the forward direction. Automatic
transformer terminating at the substation. In this case, current reclosing should not be used for these cable systems, unless
differentials are common for transmission level bus protec- required. [1, 2, 5, 7]
tion. Collector feeders also have timed under/over voltage and
With two bus arrangements that have bus tie breakers, there frequency tripping elements, which will backup the WTG
is a need to coordinate the transformer overcurrents to prevent generator voltage and frequency protection functions. Under-
overload conditions. It is often the case that the primary diffe- voltage elements should be set to open the collector feeder
rential relay protects the main transformer and the secondary when the source, all three phases, is gone for a few seconds.
differential relay wraps both the high side and low-sided buses These settings are typically set to approximately 70% and
and allow for bank bus protection. With these schemes, pro- 80% of the nominal bus voltage and typically have delayed
64
5
tripping times of a few seconds. Overvoltage elements should [2] Blackburn, J. Lewis, "Protective Relaying Principles and Applications,”
second edition, 1997, Marcel Dekker Inc.
be set to approximately 110% and 115% of the nominal bus
[3] ANSI/IEEE standard 242-1986, "IEEE Recommended Practice for Pro-
voltage with delayed tripping times of 10 minutes and 10 tection and Coordination of Industrial and Commercial Power Systems,”
second delays respectfully. Elements for the five steps of un- IEEE Standards Board.
der-frequency are typically implemented. Breaker failure [4] Anderson, P.M., "Power System Protection,” 1998, IEEE Press power
relays will typically be incorporated into all WPP circuit engineering series.
[5] Blackburn, J. Lewis, "Symmetrical Components for Power Systems
breaker protective relays. A suggested breaker failure time of Engineering,” 1993, Marcel Dekker Inc.
12 to 15 cycles is often used, which is determined by looking [6] Griffin, C.H., "Principles of Ground Relaying for High Voltage and
at the operating times of the various protective and auxiliary Extra High Voltage Transmission Lines,” IEEE Transactions on Power
relays associated with the trip circuits [1, 2, and 4] Apparatus and Systems, Vol. PAS-102, February 1983.
[7] ANSI/IEEE standard 142-2007, "IEEE Recommended Practice for
D. WPP Capacitor Banks Grounding of Industrial and Commercial Power Systems,” IEEE Stan-
dards Board.
Switched capacitor and/or reactor bank breakers are typical- [8] ANSI/IEEE standard C37-97, "IEEE Guide for Protective Relay Appli-
ly protected within the bus or main transformer differential cations to Power System Buses,” IEEE Standards Board.
zone and incorporate forward looking overcurrent, and vol- [9] ANSI/IEEE standard C37-99, "IEEE Guide for Protection of Shunt
Capacitor Banks,” IEEE Standards Board.
tage relays, which protect the reactive compensation equip- [10] ANSI/IEEE standard C37-91, "IEEE Guide IEEE Guide for Protective
ment up to the bus. The capacitor banks themselves are typi- Relay Applications to Power Transformers,” IEEE Standards Board.
cally protected by special protection schemes that sense either [11] IEEE PES Wind Plant Collector System Design Working Group, "Power
neutral current unbalance or neutral to ground over voltage Transformer Application for Wind Plant Substations” to be presented at
the 2010 IEEE PES Transmission and Distribution Conference and Ex-
depending on the configuration. These protection schemes are position.
well defined within the IEEE capacitor bank protection stan-
dards. [1,2,9]
E. WTG Step-up Transformer
The WTG step-up transformer could be located outside the
tower, inside the tower, or inside the nacelle. These transfor-
mers incorporate high-side fuses or interrupting devices with
protective relays, and internal current-limiting fuses for low-
voltage winding faults. These transformers have suggested
winding configurations of delta/wye, but often enough
wye/wye step-up transformers are used. For delta/wye trans-
formers no zero sequence will pass for low voltage winding
faults; for wye/wye transformers there will be current contri-
bution sourced back to the collector feeder through the me-
dium-voltage wye-connected ground connections. It is also
important to note that grounding transformers will often be
added to the collector system and located close to the substa-
tion. These transformers can provide a significant ground
source and should be considered in ground relay setting calcu-
lations. The WTG step-up transformer may also have a low-
voltage protection trip unit and circuit breaker. This breaker
typically has overcurrent settings, which protect the generator
for internal faults, and offer very little backup protection for
the collection system or WTG step-up transformer since the
operating times can be in the range of 2 to 3 seconds.
F. WPP WTG
WTGs typically have a breaker/contactor with integral relay
protection unit usually located either at the base of the WTG
tower or within the nacelle. Most WTGs operate within the
range of 400 to 690 VAC. It is important to note that WTG
control systems provide trip signals to the protection circuits.
Emerging wind turbine technologies have eliminated WTG
step-up transformers and can have generator connection vol-
tages at 12 kV and higher.
VI. REFERENCES
[1] Elmore, Walter A., "Protective relay theory and applications,” 1982,
ABB Power T&D Company Inc.
65
1
Abstract—This paper presents a summary of the most important Utility Wind Integration Group (UWIG) has documented this
issues with respect to harmonics and resonances within wind phenomenon very well [1] and it will therefore not be further
power plants. An introduction is given to provide an overview of addressed in this paper.
the various power quality related issues encountered when de- Resonance issues arise in wind power plants because wind
signing, commissioning, or operating a wind power plant, as well
as typical characteristics of the components associated with wind power plants contain both inductive source characteristics and
power plants. The many variables, which influence harmonics capacitive elements. Wind power plants typically consist of
and resonance in wind power plants, will be described with re- an interconnection substation which transforms from high to
spect to analysis methods, avoidance, mitigation, and compliance medium voltage, several medium voltage underground cable
with IEEE Std 519-1992 recommended practices. collector system circuits, reactive compensation equipment,
wind turbine transformation from medium to low voltage, and
Index Terms— Power system harmonics, wind power plants, wind
turbines, harmonic penetration, harmonic impedance scan, system wind turbine generators with internal power factor correction
resonances, harmonic compliance, harmonic filters. capacitors or dynamic power controllers which can also ab-
sorb or contribute reactive power. Wind power plants typically
List of Acronyms— have vast underground cable systems, which can result into
CP Cumulative Probability many series and parallel resonance points. Resonance condi-
CP95% CP 95% Level tions can be located using frequency domain analysis of im-
DFIG Doubly Fed Induction Generator
pedances and/or amplification factors, recognizing that peaks
EMT Electromagnetic Transients
HVDC High Voltage Direct Current and valleys of the frequency scan represent parallel and series
LGIA Large Generator Interconnection Agreement resonances, respectively.
PCC Point of Common Coupling Feeder line and cable capacitance and the substation reac-
RLC Resistor-Inductor-Capacitor tive compensation equipment, such as medium voltage
STATCOM Static Compensator switched or fixed shunt capacitor banks, can create significant
SVC Static Var Compensator
parallel resonance interaction with the main transformer and
TDD Total Demand Distortion
THD Total Harmonic Distortion any associated load tap changing apparatus. Due to the many
UWIGUtility Wind Integration Group steps of shunt capacitor steps within the substation capacitor
VSC Voltage Source Converter banks, parallel resonance between adjacent capacitors must
WTG Wind Turbine Generator not be overlooked.
WPP Wind Power Plant Harmonic sources can be comprised of power system back-
I. INTRODUCTION ground levels of harmonics and WTGs. One or both of these
sources inject harmonic currents that have to be considered
The ideal electrical system sinusoidal waveform is pure, when assessing voltage and current distortion compliance re-
continuous, and of a constant fundamental frequency. Power quirements.
quality issues are a deviation from this ideal system wave- There are two primary methods for controlling harmonics
form, and limits have been adopted through various standards impacts in wind power plants. (1) The method of avoidance
and guidelines for maintaining continuity, voltage magnitude, during the design process of the wind plant collector system
harmonic limits, and transient nature of electric power sys- allows for careful consideration of equipment to prevent re-
tems. Two of the most common power quality issues encoun- sonance problems. (2) Designing harmonic filters based on
tered within wind power plants are harmonic resonance and measurements and simulation results in order to reduce or
voltage flicker. control series resonance conditions of the wind plant. The later
Flicker is a variation in the system ac voltage, which can method is the most common mitigation approach, when capa-
result in observable changes in light output and in some cases citive compensation is required.
become annoying and objectionable. In wind farms flicker is
caused by variations in wind turbine generator (WTG) power II. RESONANCE AND FREQUENCY CONSIDERATIONS
output due to variation in wind speed, blade pitching, tower One objective of a harmonic analysis is to characterize the
shadowing, wind shear or gradient, and WTG start and stop potential of the wind collector system for series and parallel
operations. Flicker is usually a concern for interconnections resonance conditions. Series resonance problems are characte-
to “weak” systems, such as distribution interconnections in rized by series inductance and capacitance driven by back-
areas of the system where fault currents are very low. The ground harmonic voltages from the grid (see Fig. 1). Series
resonance points are identified by dips in the frequency scan
Please see reference [11] for a discussion of WTG types.
on the high side of the interconnect transformer. The relatively When dealing with parallel operation of two wind power
small impedances at the series resonance points can result in plants located within close proximity, it is necessary to also
high harmonic currents. avoid resonance conditions between the two plants and the
associated shunt capacitor banks.
A. Frequency Scan Analysis
Frequency scan analysis is a characterization of the system
equivalent impedance at a bus in the system as a function of
frequency. Figure 3 provides an example of a frequency scan
at the main 34.5 kV wind plant bus with over 50 turbines and
30 miles of underground collector cable. In the case where all
of the turbines are in operation, the parallel resonance of this
example system was near the 10th harmonic frequency (600
Hz).
Frequency Scan Result at the Main 34.5kV Bus
100
80
60
Voltage (V)
40
20
67
3
Fig. 4. Contour plot of the driving point series impedance for a large number
of system configurations Fig. 5. One-line diagram depicting a Type 3 (DFIG) turbine harmonic model
As an example, Fig.4 shows a contour plot of the driving Frequency Scan Results
point series impedance for a large number of system configu- Case 1a> 80 kvar Filter at Each Turbine Case 1b> 40 kvar Filter at Each Turbine
68
4
harmonic impedances of the current source HVDC converters impedance of the grid at harmonic frequencies.
can affect system resonances, and ignoring them can lead to
excessively high harmonic voltage distortion and ineffective 1) Ambient Voltage Distortion
harmonic filter designs. The main reason for the oversimplifi- Ambient harmonic voltage distortion is characterized in
cation is the inability of present commercial programs to mod- terms of the voltage magnitude by harmonic order. This dis-
el the effective converter impedances. tortion tends to vary over time, due to variations in the har-
Most wind turbines use a VSC, which have very low har- monic current injected by sources distributed throughout the
monic impedance, compared to a current sourced conver- grid, and also due to variations in the transmission system
ter. Despite having low harmonic impedance, representation resonant characteristics, which can amplify distortion at a par-
of the VSC by an ideal current source may have considerable ticular location. Because of the variability in ambient distor-
inaccuracy, which can lead to misleading results. This is be- tion, data used for wind plant harmonic analysis may be statis-
cause in reality the harmonic current of VSC will not remain tically characterized. This will allow the plant design to be
constant, and varies depending on the converter control. made on the basis of the appropriate degree of conservatism.
A voltage source converter is better characterized as a Nor- The interconnection utility may have records of compliance
ton equivalent source [4]. The equivalent shunt impedance with IEEE Std 519-1992 [6] and other power quality standards
has real and reactive components that vary by frequency, and in regards to power quality limits for their transmission system
phase sequence, in a complex manner defined by the conver- in general. Availability of ambient voltage distortion charac-
ter’s controls as well as the parameters of the converter’s teristics for the particular point of proposed wind plant inter-
physical components. The impact of the source shunt imped- connection, however, is typically not available. This voltage
ance can be very significant, as the magnitude can be a few distortion may be characterized with access to operational
tenths of the wind turbine’s base impedance. As a result, the utility electrical system data from planning, protection, and
harmonic current of a wind turbine can vary over a very wide system operations.
range for the typical range of driving point impedances de- More accurate characterization of ambient voltage distor-
fined by the collector system and grid characteristics. tion levels may require installation of harmonic monitoring
Typically, wind turbine generator manufacturers provide equipment at the proposed interconnection point, for an ex-
test data, defined in terms of current injection, demonstrating tended period of time.
compliance with power quality standards and assessing cha- If the ambient voltage distortion is not available and a har-
racteristics at the turbine terminals [5]. It should be noted that monic study is being performed the voltage distortion limits
it is not feasible for a manufacturer to certify compliance at contained in Table 11.1 of IEEE Std 519 can be used as a ref-
the point of grid interconnection, because the collector system erence for interconnection bus voltage ambient conditions.
and the particular grid affect the currents at that location. However, it should be realized that actual distortion might
These test data are influenced by the characteristics of the sys- exceed IEEE Std 519 limits. It should also be realized that
tem in which the tests are conducted, both in terms of imped- applying each of the individual harmonic limits collectively
ance and in terms of ambient voltage distortion. It is highly might yield unrealistic results. The value of the actual indi-
difficult to find a test location free of ambient harmonics, and vidual frequencies modeled might depend upon local condi-
it is also difficult to segregate harmonic current flow caused tions such as other harmonic sources in the area. Some utilities
by the wind turbines and flow caused by grid distortion driv- may also provide a planning limit that can be used for studies.
ing current into the wind turbines and wind plant shunt capa-
citances. Information on the equivalent source impedance of 2) Transmission System Harmonic Impedance
wind turbines is generally not available. Proper representation of the transmission system’s imped-
Modeling the source characteristics of wind turbines is ance at harmonic frequencies is important for both analysis of
more complex than was initially considered, certainly requir- harmonic currents produced by the wind plant, and interaction
ing more complexity than the harmonic current source models of the wind plant with ambient grid distortion.
used for industrial studies. Practices are still evolving to more There are grid representation practices in use for wind plant
sophisticated representations for the WTG harmonic source harmonic studies, which are often less than adequate. Some-
characteristics. Measurements continue to be an important times, the impedance of the transmission system is ignored
part of the validation process for harmonics studies, as expe- altogether by assuming the point of interconnection to be an
rience from the field provides a better understanding of what infinite bus or as an ideal voltage source representing ambient
level of detail is necessary in the system modeling. voltage distortion. While this simplification is reasonably ade-
quate when the wind plant is small, and connected to a very
C. Source Characteristics of Utility Interconnection stiff transmission system, it is not adequate in general.
The utility grid is characterized by two categories of para- Another practice is to define the grid impedance as an in-
meters: The first category is the background, or ambient, vol- ductance and resistance defined by the fundamental-frequency
tage distortion present at the point of interconnection without short-circuit impedance. This is reasonably accurate for fre-
the wind plant connected. The second is the driving-point quencies below the first resonance of the transmission system.
69
5
Transmission systems, however, often have resonances in the ance. Studies to define transmission system impedance need
same range of frequencies as the harmonics of greatest interest to consider the range of normal and contingency system condi-
(i.e., 5th and 7th). tions. This may result in a large number of possible imped-
Determination of the harmonic impedance of the transmis- ance values to be considered.
sion system requires detailed modeling. The extent of the
transmission system, which must be discretely modeled, de-
pends on the frequency range of most interest, and the re-
quired degree of accuracy. Modeling in the lower order har-
monic range (e.g., 3rd, 5th, 7th) requires a more extensive
transmission model than that needed for similar accuracy in
analysis of higher-order harmonics. For a small wind plant in
a stiff transmission system, the sensitivity of results to the grid
impedance representation is less significant, and thus a less
extensive transmission model can be justified.
If a load flow model or a short circuit model, of the trans-
mission system is available, then it is often possible to convert
these large models into an electro-magnetic transient (EMT)
model or harmonics model using data conversion utilities.
The use of an EMT type or harmonic programs allows calcula-
tion of the frequency and impedance of each network reson-
ance point.
Harmonic impedance analysis requires that the frequency-
dependent characteristics of the external grid components be
Fig. 7. Range of harmonic impedance at a typical point of interconnection
accurately represented. Damping is an important determinant
of resonance severity, and proper representation of grid com- (Inductive)
ponent damping at harmonic frequencies is essential. For ex-
ample, a transformer is represented in fundamental-frequency
studies as a series inductance and resistance. Such a model, if
Reactance
used for harmonic analysis, would exhibit an X/R ratio that Resistance
would monotonically increase with increasing frequency,
without bound. In reality, a transformer reaches its maximum
X/R at a frequency of one or two hundred Hertz, and the X/R Individual
decreases continuously for higher frequencies. Thus, the sim- configuration
plified series resistance-inductance representation is clearly results
(Capacitive)
inadequate for harmonic analysis. Proper harmonic analysis Fig. 8. Harmonic impedance range defined as a sector
requires that a model which properly represents damping of
transformers and other components be used. Sufficiently ac- To make harmonic analysis manageable, boundaries of the
curate models of the network components for harmonic analy- harmonic impedance ranges can be defined as a shape, such as
sis are discussed in [7]. a pie-shaped sector or polygon, in the R-X plane. Figure 8
The harmonic impedance of a transmission system can be illustrates a pie-shaped sector, defined by a minimum and
highly dependent on the specific system configuration. Out- maximum impedance magnitude, and a minimum and maxi-
ages of lines and transformers, even ones that are moderately mum impedance angle. Critical resonance conditions will al-
distant from the point of wind plant interconnection, can sig- ways fall on the boundaries of such a shape that surrounds all
nificantly change the impedance at certain harmonics. In ad- actual harmonic impedance loci. The application of shapes to
dition to such contingencies, routine system variations such as define grid harmonic impedance range is a routine practice in
the status of capacitor banks and generating unit commitment transmission technologies where harmonic performance is
can also have a large impact. Thus, the transmission system critical (e.g., HVDC). Some European transmission system
impedance cannot be considered as a single value for each operators provide similar harmonic impedance envelopes. This
harmonic. The impedance varies over a range in the R-X is usually provided separately for the 2nd-5th harmonics and for
plane, depending on system condition. Figure 7 illustrates the the 6th and higher order harmonics. For the 2nd-5th harmonics
rather wide range of harmonic impedance and impedance an- the impedance plot is defined as a square bounded to the area
gle for an actual transmission system, over the range of ordi- between Rmin- Rmax and Xmax-Xmin. For the 6th and higher order
nary contingencies and operating conditions. Thorough har- harmonics the envelope consists of a semicircle with its radius
monic analysis of wind plant harmonic performance requires in the origin, and a square to the right of the semicircle.
consideration of every possible transmission system imped- Caution and discretion needs to be applied when using
70
6
harmonic impedance ranges in studies of ambient transmission harmonic source of the grid. Series resonance from the collec-
distortion amplification within wind plants. Ambient voltage tor cable capacitance can easily result in an idle wind power
distortion, applied as a voltage source behind the transmission plant absorbing more harmonic current than prescribed by the
system impedance, is usually defined as a maximum, or a IEEE Std 519 recommended limits.
range of values, determined from monitoring. High values of Facility compliance is evaluated at the point of common
ambient distortion may be the result of resonant conditions in coupling (PCC), and although individual wind turbines may be
the transmission system, that would tend to have a high source certified as IEEE Std 519 compliant, the aggregate facility
impedance. The harmonic impedance range, however, may may not meet emission limits. Section 10 of IEEE Std 519
include low impedance values that are the result of other con- outlines the current distortion limits for individual and total
harmonics for various grid voltages as a function of a facilities
ditions. The impedance value range is usually defined by sys-
ratio of short circuit current to the maximum fundamental load
tem harmonic analysis studies that are performed independent
current. The current distortion is based upon the maximum
of monitoring used to define ambient voltage distortion mag-
demand load current (fundamental frequency). This percen-
nitude. The correlation between particular background distor- tage calculation is referred to as the Total Demand Distortion
tion values and particular impedance values is thus not gener- (TDD). It is often convenient to convert the current limits
ally known. Use of the highest magnitude ambient voltage from percentage values to Amperes, allowing direct compari-
distortion combined with a source impedance that results in a son with measured values. An example of harmonic current
worst-case resonance within the wind plant is conservative, limits at a wind power plant (WPP) is given in Table I.
but also potentially conservative to an excess degree.
TABLE I
3) Representation of Reactive Compensation Equipment HARMONIC CURRENT LIMITS AT A WPP INTERCONNECTION
The representation of the reactive compensation equipment Example Wind Power Plant
71
7
Fig.10. Trend of the harmonic voltage distortion at a wind power plant inter- 80
connection
Impedance (Ohms)
60
40
20
0
0 10 20 30 40 50
Harmonic Frequency
th
Fig. 12. Example frequency response of a single-tuned (4.7 harmonic) filter
on a wind power plant 34.5 kV main bus
Fig. 11. Statistical analysis of harmonic voltage distortion measurements A C-Type filter configuration is shown in Fig. 13. It is de-
signed so that the reactor and smaller (“c-stage”) capacitor are
In preconstruction, harmonic studies are often commis- impedance matched, so that a minimal amount of fundamental
sioned using estimates of background harmonics from the grid frequency power is dissipated across the damping resistor.
72
8
VI. ACKNOWLEDGEMENTS
The publication of this paper was the result of two years of
concerted effort by the authors and the IEEE PES Wind and
Solar Plant Collector System Design working group--
gathering information, preparing drafts, arguing amongst the
interested parties, restarting drafts, arguing some more, and
finally coming to agreement. The authors sincerely hope that
this and other working group papers are found to be valuable
to those who will plan, design, analyze, construct, and operate
wind power plants. Recognition is given to the authors and
their employers for contributing the resources for the prepara-
tion of this work.
For more information on available materials, or to find out
how to participate in this working group’s activities, please
see: http://grouper.ieee.org/groups/td/wind
Fig. 13. Oneline configuration of a C-Type harmonic filter
VII. REFERENCES
While, it presents more complications for the system design [1] T.E. McDermott, “Distributed Wind Evaluation Metho-
and protection, it does have certain advantages. (1) It provides dology,” AWEA WindPower 2009.
further system damping of unintended resonance conditions [2] J. Arrillaga, B. C. Smith, N. R. Watson, and A. R. Wood,
over a wide frequency range. (2) It is an excellent choice for Power System Harmonic Analysis. New York: Wiley,
capacitors banks installed on transmission systems, especially 1997.
where there are other banks on nearby buses. (3) It can also [3] D. L. Dickmander, S. Y. Lee, G. L. Desilets, and M.
be a good choice for 34.5 kV systems, where additional capa- Granger, “AC/DC harmonic interactions in the presence
citor banks (for reactive power) are installed without harmonic of GIC for the Quebec–New Englandphase II HV dc
filters. Figure 14 shows an example of the effect of a C-Type transmission,” IEEE Trans. Power Delivery, vol. 9, pp.
filter on a system frequency response. 68–78, Jan. 1994.
[4] R. C. Dugan, M. C. McGranaghan, S. Santoso, H. Wayne
C-Filter Frequency Response Beatty, Electrical Power System Quality, New York:
McGraw-Hill, 2004.
100
60
quirements for Harmonic Control in Electric Power Sys-
tems”.
40
[7] IEEE Tutorial Course on Harmonic Modeling and Simu-
lation, Course text TP-125-0, February 1998.
20 [8] IEEE 1547-2003 “Standard for Interconnecting Distri-
buted Resources with Electric Power Systems”.
[9] IEC 61000-4-30 (2008) Electromagnetic compatibility
0
0 10 20 30 40 50 (EMC) - Part 4-30: Testing and measurement techniques -
Harmonic Frequency
Fig. 14. Typical frequency response of a C-Type harmonic filter at a wind Power quality measurement methods.
power plant 34.5 kV main bus [10] Guide to the specification and design evaluation of AC
filters for HVDC systems, CIGRE Technical Brochure,
V. CONCLUSION WG 14.30, 1999.
[11] Wind Plant Collector Design WG, “Characteristics of
This paper has presented harmonics and resonance issues
Wind Turbine Generators for Wind Power Plants,” Pro-
for wind power plants in an overview and summary fashion.
ceedings of 2009 IEEE Power and Energy Society Gener-
This included an introduction to series and parallel resonances,
al Meeting, Calgary, Canada, July 2009
frequency scan analysis, and the harmonic source characteris-
tics of WTGs and of utility interconnections. Further, the is-
sue of compliance with the power quality standard IEEE Std
519 was presented, as was an overview of harmonic filters.
73
Appendix 1
Christopher Brooks, Wayne Dilling, Charles J. Murray, Nestor Castillo, Gary Engmann, Michael Starke
Abbreviation Meaning
I. INTRODUCTION BA Balancing Area
BIL Basic Insulation Level
This paper presents a basic list of the abbreviations and BOP Balance of Plant
terms used in the papers produced by the Wind and Solar Plant BOP Balance of Plant
Collector working group, specifically for the eleven papers BWEC Bats & Wind Energy Cooperative
included in this compendium. Included are abbreviations and CAIR Clean Air Interstate Rate
terms unique to the wind industry as well as those more gener- CAMR Clean Air Mercury RLe
ally used throughout the energy industry. The paper is in two CAPX Capital Expenditures
parts. The first is a set of abbreviations that may be found CCGT Combined Cycle Gas Turbine
when researching WPP technology. CF Capacity Factor
CIP Critical Infrastructure Protection
The second part is a set of terms that have been discussed CLR Current Limiting Reactor
in the working group on WPP collector systems. The terms COD Commercial Operation Date
are listed with references to the specific paper(s) in this com- Cp Performance Coefficient (of turbine)
pendium. Rather than list the definitions here, we invite the CP Cumulative Probability
CP95% CP 95% Level
reader to look to the appropriate paper(s) for an understanding
CPC Certificate of Public Convenience
of the term, particularly within the wind collector context. CREZ Competitive Renewable Energy Zone
Note that some terms have very specific definitions pub- Ct Thrust Coefficient (of turbine)
lished by the IEEE. No attempt is made here to duplicate, CT Combustion Turbine
DEP Diurnal Energy Production
compete, or redefine any generic term that is officially pub-
DETC De-energized Tap Changer
lished by the IEEE; term references are provided for consider- DFAG Doubly Fed Asynchronous Generator
ation within the context of wind power plants. The reader is DFG or
encouraged to search, examine, review, use, and study the Doubly-Fed Induction Generator
DFIG
official IEEE published terms, which can be found at: EHV Extra High Voltage
EIR Environmental Impact Report
www.ieee.org/go/standardsdictionary
EIS Environmental Impact Study
ELCC Effective Load-Carrying Capacity
The paper hopes to help the reader to more quickly grasp EMT Electromagnetic Transients
the technology concepts in this field. It is meant to be helpful EMTP Electromagnetic Transients Program
to those beginning to understand wind power in general and EPC Engineering, Procurement and Construction
wind power plants (WPP) collector systems, specifically. EPR Ethylene Propylene Rubber
ERCOT Electric Reliability Council of Texas
II. ABBREVIATIONS FERC Federal Energy Regulatory Commission
FOTT Fiber optic transfer trip
Abbreviation Meaning XLPE-TR Cross Linked Polyethylene-Tree Retardant
ACE Area Control Error GADS Generating Availability Data System
ACSR Aluminum cable steel reinforced GOES Geostationary Operations Environmental Satellites
AEP Annual Energy Production HAWT Horizontal-Axis Wind Turbine
AGC Automatic Generation Control HV High Voltage
AMT Alternative Minimum Tax HVDC High Voltage Direct Current
ANPR Advance Notice of Proposal Rulemaking HVRT High Voltage Ride-Through
ANSI American National Standards Institute I&C Instrumentation and Controls
ASI Above Sea Level IA Interconnection Agreement
ASOS Automated Surface Observing System IAV Inter-Annual Variation
ATC Available Transfer Capability ICAP Installed Capacity
AVR Automatic Voltage Regulator ICT Independent Coordinator of Transmission
IEA International Energy Agency
IEC International Electrotechnical Commission
Working group document
74
Appendix 2
75
Appendix 3
76
Appendix 4
77
Appendix 5
78