01 - CCTV Mos
01 - CCTV Mos
01 - CCTV Mos
REVISION DETAILS
Reviewed by APPROVED BY
REV.00 Prepared by Construction rd
3 Party Distribution
QA/QC HSE Environmental Project Manager Consultant
Manager T&C
Name Sub-contractor
Signature
Company
Date
TABLE OF CONTENTS
01. PURPOSE 3
03. REFERENCES
• Approved Material Submittal for CCTV System: YSD-P02-0008-SS-SJF-MS-F0001
• Approved Material Sample for CCTV System: YSD-P02-0008-SS-SJF-MX-F0004
• Approved related Shop Drawings: YSD-P02-0208-SS-SJF-DG-FS0000
• Submitted QA/QC Plan: YSD-P02-0208-QM-SJF-PL-F0001
• Submitted HSE Plan: YSD-P02-0208-HS-SJF-PL-F0002
• Approved Early Mobilization Logistics Plan: YSD-P02-0208-PM-SJF-LT-F0095
04. ABBREVIATIONS
• JV - Joint Venture
• QCP - Quality Control Procedure
• ITP - Inspection & Test Plan
• ITA - Independent Testing Agency
• AFC - Approved for Construction
• HSE - Health, Safety and Environment
• PPE - Personal Protective equipment
• RA - Risk Assessment
• CEMP - Construction Environmental Management Plan
• CCTV - Closed Circuit Television
• IDF - Intermediate Distribution Frame
• MDF - Main Distribution Frame
• HDD - Hard Disk Drive
• PDU - Power Distribution Unit
• UPS - Uninterruptable Power Supply
• WIR - Work Inspection Request
• MIR - Material Inspection Report
• MS - Method Statement
05. RESPONSIBILITY
Construction Manager:
• Overall responsible for the implementation of the Method Statement and ensure that his team of
Engineers and foreman are aware of this MS.
• Ensuring that all constraints on operations have been identified and precautions are taken.
• Ensure all resources are available to carry out the works as planned, without any delay.
Site Engineer:
• Responsible in carrying out the works as per the approved Method Statement and specifications.
• Ensuring that the work area is safe and clear.
• Conduct Tool Box Talk & explain briefly to all operatives involved about Method Statement & Risk
Assessments.
• Responsible for implementing the approved HSE Plan on site.
• Ensure all manpower is wearing appropriate PPE such as safety shoes / helmets / gloves / goggles and
protected as per safety plan.
QA/QC Engineer:
• Ensure that work is done in accordance with the approved Method Statement and Project
Specifications.
• Responsible for implementing the approved QA/QC Plan on site.
• Ensure that inspections are done in accordance with the ITP's & offer works for the Engineer's
inspection.
• Ensures that all test equipment including surveying equipment is calibrated and suitable for use on
site.
Safety Engineer:
• Monitor the Safety Tool Box Talk meetings being conducted by the Site Engineer.
• Monitor the implementation of the approved HSE Plan on site.
• Monitor the site to ensure all manpower is wearing appropriate PPE such as safety shoes / helmets /
gloves / goggles and protected as per safety plan.
• To strictly monitor the workers so as to be assured that all safety regulations & procedures are
implemented.
Site foreman:
• Supervise & execute the installation according to the approved shop drawings & method statement.
• Coordinate with the discipline engineer for site execution and during the final inspection.
• Coordinate with the crew on implementation of safety procedures at the site.
06. MANPOWER
• Site Engineer
• System Engineer
• Safety Officer
• QA/QC Engineer
• Site Foreman
• Technicians
• Labours
Trained Engineers and Technicians will be deployed for this specific job. The work method statement and risk
assessments will be briefed to all the staff and operatives involved, prior to commencing the activity, and then
recorded as having been given, dated and confirmed.
08. MATERIALS
• Fiber and Copper Cables and accessories for CCTV.
• Media Converters and Extenders.
• CCTV Camera and their Mounting brackets.
• Workstations, Servers, Storage and Monitors.
• Network Switches and Firewall for CCTV.
• Equipment Racks, UPS and PDU
09. WORK PROCEDURE
Pre-Installation Activity
• Confirm that the material submission is approved.
• Confirm that the related shop drawing is approved.
• Check if the area is clear & clean before starting the work.
• Liaising with the Main Contractor to ensure the site is ready for carrying out the installation work.
• Ensure all operatives have passed the safety induction and have been briefed on the Method
Statement and understood this method statement before the start of the work on site.
• Ensure all relevant material submittal, MIR, MS, AFC Shop Drawings are available for Site Installation
team.
• Ensure necessary resources in terms of labour, plant, equipment, tools and task lighting are arranged
to carry out the job.
• Check if the work permit is ready.
• Thoroughly review the information provided in Safety Guidelines and Warnings of the products.
• Coordinate with other services & trades.
Surveying Activities
• Proper access and egress to the work area to be provided.
• Ensure all safety requirements are complied.
• Adequate lighting shall be available.
• Trunking, Containment, Conduits and Back boxes are available as per AFC Shop Drawings.
Installation Steps
• Cable Pulling
o Pull Fiber and CAT6A Cables as per the approved shop drawings and in line with the approved
method statement.
o Make sure while pulling the cables that the pathways are free from sharp bends and turns.
o Make sure that the manufacturers recommended pulling tension and minimum bend radius shall
not be exceeded.
o Use of cable lubricants as when deemed necessary will significantly reduce friction and speed us
cable installation especially within conduits.
o Use temporary labelling for identification while pulling.
o Raise WIR for the Cable Pulling for Consultant approval.
• Cable Termination
o Cable termination involves the organizing of cables by destination, forming and dressing cables,
and labelling, as well as actually creating a connection with a copper or fibre conductor.
o Cable termination preparation not only improves the quality of the job but also decreases the
amount of time required for termination.
o The performance of pre-termination functions involves organizing the cable by destination. Cable
to be terminated should be placed at the point of termination and must also be identified to
ensure it is terminated in the designated position. Cable connection is not complete until all
terminations are identified and labelled.
Manufacturer Recommendation
• Respect the installation bend radius of the cable. Never exceed the recommended maximum pulling
load of the cables.
• Cables must be selected and installed following the environmental classification of operation of the
product with appropriate containment and installation technique.
• Provide proper earth bonding for the Equipment Racks.
• If the installation is a mixture of copper and fibre optic cabling install the copper cabling first.
• Plan the occupation of cabling in the containment and along the route so that crossovers are
eliminated and entry points into and exits from the containment are not congested.
• Protect the edges of the basket or tray before starting to install the cable to ensure no damage is
caused.
• Ensure that the edges of the tray or basket have a bend radius that exceeds the installation Bend
Radius of the cable concerned.
• Over tightening of the screws should be avoided when installation the equipment.
• Use protective caps on unplugged optical ports to prevent dust from contaminating them. Missing
this can cause them to get accidentally damaged.
• Ensure that the optimal temperature and humidity levels are maintained in the installation and
storage areas of the installation sites. In addition, see the installation guides that support specific data
networking equipment for the minimum and maximum allowed values for temperature and humidity.
Commissioning Engineer:
An Employee of******* is responsible for the correct testing & commissioning of systems and to ensure that
records are accurate and legible. He is also responsible to ensure that this procedure is followed.
Representative:
• An employee of ****** who is in a position of responsibility to sign testing & commissioning results.
• In addition, it is also his responsibility to ensure that all documentation is available, test sheets are
accurately completed and issued to the Client as per Contract requirements and that all coordination
is carried out prior to testing and commissioning commences.
Prior to any testing and commissioning the following documentation will be available:
Commissioning Prerequisites:
The standard pre-commissioning checks comprise of the following aspects:
• Visual inspection to ensure that all installation works are complete as per the requirements.
• All cables for the CCTV system have been installed and tested for continuity.
• Ensure that each camera is tested for proper image capturing.
• All instruments/test kits should have a valid calibration certificate. Copies to be produced during the
test.
• Permanent power is available.
• All workers shall wear appropriate P.P.E required for the job.
• Keep the working area clean and neat at all times.
• The perimeter of the work area should be barricaded by warning tapes.
• Only workers assigned for the job should enter the work areas.
• All required work permits should be acquired by the assigned Safety Engineers prior to the operation.
• Banksmen shall be provided for all vehicles reversing.
• Training will be provided to employees in regards to Vibration and potential problems.
• Conduct appropriate Health surveillance as required.
• Assessment of tools will be conducted and vibration assessed using schedule calculations.
• Each employee involved in the task shall undergo project specific HSE induction by Site Safety
representative.
• The entire work will be carried out as per the guidelines established in the Project Specific HSE Plan.
14. ATTACHMENTS
A. INSPECTION TEST PLAN
B. HAZARD + RISK ASSESSMENT
C. INSPECTION CHECK LIST
APPENDIX A