Mini PROJECT SOIL
Mini PROJECT SOIL
Mini PROJECT SOIL
1) INTRODUCTION.
The compaction test is generally performed to obtain the values of compaction test
parameters, namely the optimum moisture content and the maximum dry unit weight,
which are required for achieving maximum densification of the soil in field with a given
compaction energy per unit volume of the soil. Soil placed as engineering fill is compacted to
a dense state to obtain satisfactory engineering properties such as, shear strength,
compressibility, or permeability. In addition, foundation soils are often compacted to
improve their engineering properties. Laboratory compaction tests provide the basis for
determining the percent compaction and moulding water content needed to achieve the
required engineering properties, and for controlling construction to assure that the required
compaction and water contents are achieved.
Determination of field density of cohesion less soil is not possible by core cutter
method, because it is not possible to obtain a core sample. In such situation, the sand
replacement method is employed to determine the unit weight. In sand replacement
method, a small cylindrical pit is excavated and the weight of the soil excavated from the pit
is measured. Sand whose density is known is filled into the pit. By measuring the weight of
sand required to fill the pit and knowing its density the volume of pit is calculated. Knowing
the weight of soil excavated from the pit and the volume of pit, the density of soil is
calculated. Therefore, in this experiment there are two stages, namely:
The California Bearing Ratio Test (CBR Test) is a penetration test developed by California
State Highway Department (U.S.A.) for evaluating the bearing capacity of subgrade soil
for design of flexible pavement. The results obtained by CBR test are used with the empirical
curves to determine the thickness of different layers of flexible pavement like subgrade, sub
base and base courses. This is the most widely used method for the design of flexible
pavement. CBR value is used to quantify the response of the pavement foundation and
subgrade to loading. CBR does not provide any data regarding the properties of the soil
except as to compare its resistance to penetration to the base crushed rock’s resistance to
penetration. Although CBR test is empirical and has some limitations but it is still used
around the world due to its low equipment requirement, ease of performance prediction
and history of use. The two empirical methods for pavement design used now days are CBR
method and Group Index Method. In CBR method beside many other steps one step is to
determine the CBR value. This test allows the Engineer to design the Capping Layer and the
sub-base layer by determining the strength of the underlying soil.
FAKULTI KEJURUTERAAN AWAM
UNIVERSITI TEKNOLOGI MARA
PERMATANG PAUH
OBJECTIVE.
1. To determine the compaction parameters of the soil in laboratory
2. To determine the field density test of the soil and find out the relative compaction
of the site.
3. To conduct an empirical test for estimating the bearing value of the road bases
2) SUMMARY OF PROCEDURE.
A) Compaction test
All experiments was conducted according to standard procedure BS1377-4:1990.
This experiment was carried out as listed in the flowchart:
The mould and base plate are cleaned. Then, the mould and base plate are
weight and recorded as W1.
About 3 kg of dried soil is taken into a tray. The dried soil is poured with
distilled water of 5% from the total weight of dried soil and then the dried soil
is mixed.
The mixed soil is filled into mould that attached with the collar by 3 layer. Each
layer is compacted using the hammer with 27 blows. The collar is separated
from the mould and the excess soil at the top of mould is cut with straight
edge. The mould with compacted soil is weighed and recorded as W2.
FAKULTI KEJURUTERAAN AWAM
UNIVERSITI TEKNOLOGI MARA
PERMATANG PAUH
The compacted soil is taken from the mould by using extruder. A small of soil
specimen is kept into the oven for water content determination.
The steps of the procedure is repeated by adding the distilled water of 8%,
11%, 14%, 17% and 20% from the total weight of dried soil.
Part 1
All the required apparatus such as Sand pouring cylinder, Calibrating can,
Place back the W2 amount of sand into the SPC, so that its weight
Metal tray with a central
becomes hole, Dry to
equal sandW1.(passing
The SPC through 600 micron
concentrically aresieve),
place on top of the
Balance, Moisture content bins,can.
calibrating Metal
Thetray,
slit Scraper tool
are open to sets was
allow thecollected.
sand to The
run down until the
dimensions of the sand
calibrating
flow can
stopsarebymeasured
itself. Theandslititsare
internal
close volume are weighed with
again and
computed. remaining sand as W3
FAKULTI KEJURUTERAAN AWAM
UNIVERSITI TEKNOLOGI MARA
PERMATANG PAUH
The sand pouring cylinder (SPC) is filled with sand with 1 cm top clearance and
are weighed as W1
The SPC is placed on a glass plate, the slit above the cone is opened by
operating valve and allowed the sand to run down. The sand freely run down
and the conical portion is filled. The slit is closed when there is no further
downward movement of sand in SPC. The weight of sand required to fill the
cone are weight as W2
The W2 amount of sand is placed into the SPC, so that its weight becomes
equal to W1. The SPC is concentrically placed on top of the calibrating can. The
slit is opened to allow the sand to run down until the sand flow stops by itself.
Then the slit is closed again and weighed with remaining sand as W3
FAKULTI KEJURUTERAAN AWAM
UNIVERSITI TEKNOLOGI MARA
PERMATANG PAUH
Part 2
The ground surface where the field density is determined, cleaned and
levelled.
The tray with a central hole was placed over the portion of the soil had tested .
Through the hole in the plate, a pit is excavated into the ground 15 cm
deep.
The excavated soil is collected into the tray and weighed as (W)
The SPC had the latest weight of W1 is placed over the pit so that the base
of the cylinder covered the pit concentrically
The slit of the SPC is opened to allow the sand to run into the pit freely until
there is no downward movement of sand level in the SPC and then the slit
is closed.
A) Compaction Test
No. 1 2 3 4 5 6
Percentage water 5 8 11 14 17 20
added (%)
MC = Empty can (kg) 0.014 0.014 0.014 0.015 0.015 0.015
MCMS = Can + Moist 0.043 0.069 0.041 0.060 0.045 0.070
soil (kg)
MCDS = Can + dry soil 0.041 0.065 0.040 0.050 0.040 0.060
(kg)
MS = Mass of Soil 0.027 0.051 0.027 0.035 0.025 0.045
Solid (kg)
MW = Mass of pore 0.002 0.004 0.0003 0.005 0.005 0.010
FAKULTI KEJURUTERAAN AWAM
UNIVERSITI TEKNOLOGI MARA
PERMATANG PAUH
water (kg)
W = Water content 6 8 11 14 20 22
(%)
Mass of soil solids, MS = (Mass of can + dry soil, MCDS) - Mass of empty can, MC
Mass of pore water, MW = (Mass of can + moist soil, MCMS) - (Mass of can + dry
soil, MCDS)
Volume of mould = PI x r2 x h
= PI x 0.052 x 0.11
= 8.64 x 10-4 m3
Added water = 17 %
Mass of mould + Compacted soil, M2 = 6.325 kg
Water content = 20 %
ρ b = M2 – M1
V
= 6.325 – 4.29
8.64 x 10-4
= 2401.62 kg/m3
ρd = ρb
(1 + W)
= 2401.62
(1+ 0.2)
= 2001.35 kg/m3
= 2 Mg/m3
Added water = 20 %
Mass of mould + Compacted soil, M2 = 6.285 kg
Water content = 22 %
FAKULTI KEJURUTERAAN AWAM
UNIVERSITI TEKNOLOGI MARA
PERMATANG PAUH
ρ b = M2 – M1
V
= 6.285 – 4.29
8.64 x 10-4
=2309.03 kg/m3
ρd = ρb
(1 + W)
= 2309.03
(1+ 0.22)
= 1892.65 kg/m3
= 1.89 Mg/m3
Part 1
W2 = weight of sand pouring cylinder and sand filled up to 10mm from top
edge
= 9.301 kg
= 1.178 x 10-3 m3
Part 2
Sample A
MC = Empty can (kg) 0.015
MCMS = Can + Moist soil (kg) 0.047
MCDS = Can + dry soil (kg) 0.043
MS = Mass of soil solid (kg) 0.028
MW = Mass of pore water 0.004
FAKULTI KEJURUTERAAN AWAM
UNIVERSITI TEKNOLOGI MARA
PERMATANG PAUH
(kg)
W = Water content (%) 14.3
(iv) In-situ dry bulk density of the excavated soil , ρ d soil = ρ b soil
(1 + W)
= 2135.37
(1 + 0.143)
= 1868.22 kg/m3
Volume of mould =
= PI x 0.07052 x 0.07
= 1.09 x 10-3 m3
ρ b = M2 – M1
V
= 12.035 – 7.085
1.09 x 10-3
= 4541.28 kg/m3
ρd = ρb
(1 + W)
= 4541.28
(1+ 0.6)
= 2838.3 kg/m3
= 2.8 Mg/m3
4) DISCUSSION.
5) CONCLUSION.
6) REFERENCES.