Costfinal
Costfinal
Costfinal
Nico Parts, Inc., produces electronic products with short life cycles (of less than two years).
Development has to be rapid, and the profitability of the products is tied strongly to the
ability to find designs that will keep production and logistics costs low. Recently,
management has also decided that post-purchase costs are important in design decisions.
Last month, a proposal for a new product was presented to management. The total market
was projected at 200,000 units (for the two-year period). The proposed selling price was
$130 per unit. At this price, market share was expected to be 25 percent. The
manufacturing and logistics costs were estimated to be $120 per unit.
Upon reviewing the projected figures, Brian Metcalf, president of Nico, called in his chief
design engineer, Mark Williams, and his marketing manager, Cathy McCourt. The following
conversation was recorded:
BRIAN: Mark, as you know, we agreed that a profit of $15 per unit is needed for this
new product. Also, as I look at the projected market share, 25 percent isn’t
acceptable. Total profits need to be increased. Cathy, what suggestions do you
have?
CATHY: Simple. Decrease the selling price to $125 and we expand our market share
to 35 percent. To increase total profits, however, we need some cost reductions as
well.
BRIAN: You’re right. However, keep in mind that I do not want to earn a profit that is
less than $15 per unit.
MARK: Does that $15 per unit factor in preproduction costs? You know we have
already spent $100,000 on developing this product. To lower costs will require more
expenditure on development.
BRIAN: Good point. No, the projected cost of $120 does not include
the $100,000 we have already spent. I do want a design that will
provide a $15-per-unit profit, including consideration of preproduction
costs.
2. Assume that the two features that are apparently not valued by consumers
will be eliminated. Also assume that the selling price is lowered to $125.
a. Calculate the target cost for the $125 price and 35 percent market share.
c. What are the total life-cycle profits now projected for the new product?
d. Describe the three general approaches that Nico can take to reduce the
projected cost to this new target. Of the three approaches, which is likely to
produce the most reduction?
3. Suppose that the Engineering Department has two new designs: Design
A and Design B. Both designs eliminate the two nonvalued features. Both
designs also reduce production and logistics costs by an additional $8 per
unit. Design A, however, leaves post-purchase costs at $10 per unit, while
Design B reduces post-purchase costs to $4 per unit. Developing and
testing Design A costs an additional $150,000, while Design B costs an
additional $300,000. Assuming a price of $125, calculate the total life-cycle
profits under each design. Which would you choose? Explain. What if the
design you chose cost an additional $500,000 instead of $150,000 or
$300,000? Would this have changed your decision?
a. Calculate the target cost for the $125 price and 35% market share.
b. How much more cost reduction is needed?
c. What are the total life cycle profits now projected for the new
product?
d. Describe the three general approaches that Nico can take to reduce
the projected cost to this new target. Of the three approaches,
which is likely to produce the most reduction?
a. New target cost = $125 – $15 = $110 per unit
b. T h e c u r r e n t p r o j e c t e d c o s t i s $ 11 5 . 4 3
--->[$120 + ($100,000/70,000) – $6].
**$120-$6-$8 =$106
*POST-PURCHASE COSTS ARE LESS THAN $5 PER UNIT WHICH MEANS THE MARKET
$ 1,080,000 $ 1,500,000
Y= $200,000 + $10X1
Within 2 days, the engineering dept. proposed a new design that would reduce unit variable cost from $10 per
machine hour to $8 per machine hour (Design Z). The chief engineer, upon reviewing the design, questioned the
validity of the controller’s cost formula. He suggested a more careful assessment of the proposed design’s effect
on activities other than machining. Based on this suggestion, the ff. revised cost formula was developed. This cost
formula reflected the cost relationships of the most recent design (Design Z).
X1 = Machine Hours
X2 = Number of batches
X3 = Number of engineering change orders
Based on scheduling and inventory considerations, the product would be produced in batches of 1,000; thus, 25
batches would be need over the product’s life cycle. Furthermore, based on past experience, the product would
likely generate about 20 engineering change orders.
This new insight into the linkage of the product with its underlying activities led to a different design (Design W). This
second design also lowered the unit-level cost by $2 per unit but decrease the number of design support requirements
from 20 orders to 10 orders. Attention was also given to the setup activity, and the design engineer assigned to the
product created a design that reduced setup time and lowered variable setup costs from $5,000 to $3000 per setup.
Furthermore Design W also creates excess activity capacity for the setup activity, and resource spending for setup
activity capacity can be released by $40,000, reducing the fixed cost component equation by this amount.
Design W was recommended and accepted. As prototype of the design were tested, an additional benefit emerged.
Based on test results, the post-purchase cost dropped from an estimated $0.70 per unit sold to $0.40 per unit sold.
Using this information, the marketing dept., revised the projected market share upward from 50% to 60% (with no
price decrease)
Required
1. Calculate the expected gross profit per unit for Design Z using the controller’s original cost formula. According
to this outcome, does Design Z reach the target unit profit? Repeat, using the engineer’s revised cost formula.
Explain why design Z failed to meet the targeted profit. What does this say about the use of unit-based costing for
life-cycle cost management?
2. Calculate the expected profit per unit using Design W. Comment on the value of activity information for life cycle
cost management.
3. The benefit of the post-purchase cost reduction of Design W was discovered in testing. What direct benefit did it
create for Feagan Company (in dollars)? Reducing post-purchase cost was not a specific design objective. Should it
have been? Are there any other design objectives that should have been considered?
Given:
Y= $140,000+ $8X1 +$5,000X2 + ● $40,000 is reduced from the fixed cost component
$2,000X3 Design Z
● in batches of 1,000: 25 batches
● 20 engineering change orders.
OR
X2 = Number of batches
X3 = Number of engineering change orders
Requirement 1
Calculate the expected gross profit per unit for Design Z using the controller’s original cost formula. According to
this outcome, does Design Z reach the target unit profit? Repeat, using the engineer’s revised cost formula. Explain
why design Z failed to meet the targeted profit. What does this say about the use of unit-based costing for life-cycle
cost management?
Engineer’s formula:
● Total cost = $140,000 + $8(25,000) + $5,000(25) + $2,000(20) = $505,000
● Unit cost = $505,000/25,000 = $20.20
● Unit gross p(l) = $20 – $20.20 = $(0.20)
Requirement 2 and 3
Calculate the expected profit per unit using Design W. Comment on the value of activity information for life cycle
cost management.
The benefit of the post-purchase cost reduction of Design W was discovered in testing. What direct benefit did it
create for Feagan Company (in dollars)? Reducing post-purchase cost was not a specific design objective. Should it
have been? Are there any other design objectives that should have been considered?