Chapter 1
Chapter 1
Chapter 1
Introduction
1.1About Company
GSEG is operating a 156 MW Combined Cycle Power Plant based on Natural Gas at Mora,
District Surat, Gujarat. During the financial year 2015-16, GSEG declared availability 68.12
% due to non-availability of gas at cheaper rate. The Profit after tax was approx. Rs 104.5
Cores for the same financial year [1]. GSEG also undertook expansion by installing another
Combined Cycle Gas Based Project of capacity 351 MW at its existing Site at cost of Rs 1160
Crores. Commercial operation of the Expansion Project was declared on March 22, 2012.This
plant will be operationalized after allocation of domestic natural gas.
They have been operating facilities ranging from small cogeneration plants to power plants
sites with several 1,000 MW of installed capacity for decades now. Planning, constructing and
operating our own and third-party power plants result in extensive knowledge based on fossil
fuels and renewable energies.Their Service portfolio includes everything from consulting
support through to the complete assumption of responsibility for technical and commercial
operation management [1].
Area: Gujarat
Kind of Fuel: Natural Gas, Naphta
Power Capacity: 156 MW (3 x 52 MW)
Owner: Gujarat State Energy Generation Limited (GSEG)
Shareholders: Gujarat State Petroleum Corporation (GSPC)
Activity since: 2001
Customer GUVNL: (Gujarat Urja Vidhyut Nigam Limited)[1]
1
1.2 Scope and Purpose of Plant
GSEG (Gujarat State Energy Generation Ltd.) is a Special Purpose Vehicle (SPV) formed by
GSPC (Gujarat State Petroleum Corporation) to generate power in Gujarat by harnessing the
eco-friendly and economical natural gas. GSEG is part of the GSPC Group's overall strategy
of establishing a presence in both the upstream and downstream segments of the energy value
chain. The company is committed to using innovative, advanced and reliable technology for
producing gas-based power [2].
GSEG was set up in 1998 as a power generation company. GSEG owns and operates a gas
based power plant in Hazira that was commissioned in 2002. The plant was set up to provide
electricity for the Gujarat state grid, with all electricity currently produced at the plant sold to
Gujarat Urja Vikas Nigam Limited (GUVNL), a Government of Gujarat owned electricity
company.
GSEG is in the process of extending the capacity of its Hazira plant. It has entered into a gas
purchase contract with us to provide the gas required for the expanded plant, effective for 20
years from commissioning, with the gas to be bought at mutually agreed prices. The
additional power to be generated will be bought by GUVNL pursuant to a 20 year
procurement contract effective from commissioning.
1.3 Actualization
Association with other state sector companies and central sector PSUs like
KRIBHKO and GAIL.
Alstrom Power India awarded with EPC for the plant.
The plant available both as modularized, pre-engineered packages
Development for a156.1 MW, two 52 MW gas turbine (GT8C2), one 52.1 MW
steam turbine and two heat recovery steam generator-combined cycle
Power generation project begins at Surat.
30th September,2001 successful initial test firing and synchronizing of the first gas
turbine
1st Dec, 2001. Plant operational in open cycle mode.
The plant in combined cycle mode (156.1) MW is commercially operational since
1st June 2002.
2
Plant Layout
A Figure 1.1 shown below gives over all idea of plant layout and flow of all the process in
power plant [3]
3
1.4 Concept of CCPP
Working principle of combined cycle power plant is explained in Figure 1.2 [4]
The gaszturbinezcompresses air and mixeszitzwith fuel that iszheated toza very high
temperature. zThezhotzair-fuel mixturezmoves throughzthe gas turbine blades, making them
spin.The fast-spinning turbine drives azgenerator thatzconverts a portion ofzthe spinning
energy into electricity
A Heat Recovery Steam Generator (HRSG) zcaptureszexhaust heat from the gas turbine that
would otherwise escape through the exhaust stack [4].The HRSGzcreates steam from the
gaszturbine exhaust heat and delivers it to the steam turbine.
4
1.5 Turbine specification [3]
Specifications of turbine ALSTOM GT8C2 are given in Table 1.1
5
Chapter 2
Literature Review
As shown in Figure 2.1 the fuel is supplied by GSPC in the form of natural gas naphtha.
Compressors suck the air from the atmosphere and compress it up to 45bar which is further
supplied for combustion in combustion chamber. In combustion chamber with the help of
spark the mixture gets ignite and high temperature gas is produce of around 2000 c and
further runs gas turbine. After work done in GT temperature of gas is around 570 degree. This
high temperature exhaust gas is further utilized in HRSG to produce steam. Steam produced
by HRSG is used to run steam turbine and at the end final temperature of gas is around 110
degree [3].
Dimensional Specifications - The fractured blade: length: 20cm; average width: 5 cm;
thickness: 5mm. Figure 2.2 shows the damaged blade.
7
Chemical Specifications - The Chemical composition show the type of alloy is Stainless Steel
450 Alloy UNS S45000. Below Table 2.1 shows the weight per cent of the elements of this
alloy.
Macro Hardness test - The test is done at the root of the blade by Vikers standard. Figure 3
shows places of the hardness test. We observe the thickness of the upper part of the root (the
place of the fracture) is more.
Fractography- The study of the level of the fracture gives the states, the cause and the
condition of the fracture .In Fractography, the most important point is taking proper
microscopic and macroscopic photos which have proper marks of the determination of the
8
type of the fracture. The fraction of azbladezresults in the damage of thezother blades. One
overhaul was done. The done PT testzon thezsecond rowzblades of thiszturbine showedzsome
ofzthese zhavezcrack onztheirzair foilzcorner of thezroot.
Figure 2.6 Beach marks and the Figure 2.7 Fatigue cracks in
section of the fracture of the fracture surface [5]
fatigue [5]
9
Finite Element Model- In order to simulatezthe model, solidworks softwarezis used, and thenzit
is analysiszthe finite element by Ansys software. The usedzelementszin this model are solid
186- type, which have well precision forzanalysis of suchzproblems. Figure 2.8 shows this
model is made of by solid works.
Figure 2.9 Von-misses stress on pressure Figure 2.10 Von-misses stress on suction
side [5] side [5]
10
Figure 2.11 Stress concentration point at the leading edge near the
platform of the blade under the third natural mode shape [5]
Results
The result of observation of thezFractography and finitezelement analysis, zmeanszthat the
fatiguezcrack iszgrown from twozcornerszof the air foil, and because of thezcontact with an
outside objectzwhich might be azfragment of anotherzfractured blade, zthe edges of thezblade
arezbroken andzthe bladezhas changed.
11
Chapter 3
Problem Specification
During plant visit with mentors in DM plant abnormal noise and high vibration is
observed. Apart from noise leakage from impeller eye is noticed.
Technical specifications and range of centrifugal pump of DM plant are given in Table 3.1
12
3.2 Problem 2- Blade Failure of Compressor of Gas Turbine (GT-12)
During Operation
(a)
(b)
Figure 3.2 Filter House
13
Figure 3.3 Air Intake Manifold
Filter Housing
• Corrosion spots seen on the filter house flooring before the pulse filters
• All the screws and bolting in the filter house structure found intact
• Filter house flooring found with dust deposits
Filters Condition
• No maintenance was carried out by customer on the filtered during this shutdown.
• Installed filters are from Dallinger- S65R-U18A9-SPX
14
Silencer Housing
• Area after pulse filters seen with old water puddle marks Filter house flooring found
with dust deposits
• Minor corrosion spots seen after silencers near the retaining plates.
Silencers
• All the silencers retaining plates found intact.
This circumferential plot of axial flow compressor shows various defects and its severity on
circumference of the compressor. It gives idea about the location of various defects and no of
blade which id defected or gets worn out. This plot is prepared using F-chart.
15
Vane row 4 impact damage overview
Impact of damage and parameter of defect on vane 5 is shown in Figure 3.7 and 3.8
Figure 3.7 Sheared off Vane row 5 - Figure 3.8 Vane row 5 impact damage overview
#4 16
Vane row 6 impact damage overview
rthgnfnfnm
17
Vane row 8 impact damage overview
(a) (b)
18
Vane row OGV impact damage overview
19
3.3 Problem 3- Performance and Maintenance of Cooling Tower
3.3.1 Identification of Problem
During visit of power plant in working condition it is observed that at the edges of every
cooling tower water gets accumulated due to fill defect, and at various places in CT fill gets
damaged, due to this maintenance issue performance of CT gets affected and its effectiveness
reduces[6]
3.3.2 Defects in CT
System Concerns
Cooling towers are dynamic systems because of the nature of their operation and the
environment they function within. Tower systems sit outside, open to the elements, which
makes them susceptible to dirt and debris carried by the wind. Their structure is also popular
for birds and bugs to live in or around [7]
Corrosion
Corrosion is an electro-chemical or chemical process that leads to the destruction of the system
metallurgy. There are different types of corrosion encountered in cooling tower systems
including pitting, galvanic, microbiologically influenced and erosion corrosion, among others
Loss of system metallurgy, if pervasive enough, can result in failed heat exchangers, piping, or
portions of the cooling tower itself
20
Fouling
Scaling
Scaling iszthe precipitationzof dissolved minerals components that have become saturated
inzsolution.Figure 3.18z illustrates calcium carbonatezscalezcollecting on a faucet head.
Factors that contribute tozscalingztendencies include water quality, pH, and temperature.
Scale formation reduceszthe heat exchangezability of thezsystem becausezof the
insulatingzproperties ofzscale, zmaking thezentirezsystemzwork harder tozmeetzthe
coolingzdemand.
21
Microbiological Activity
Microbiological activity is micro-organisms that live and grow in the cooling tower and
cooling system. Coolingztowers present thezperfect environmentzfor biologicalzactivity due
to the warm, moist environment. They havezstrong insulating properties, they contribute
tozfouling andzcorrosion, and the bi-products they create that contribute to further micro-
biological activity.
Figure 3.19 Bio fouled Heat Exchanger (Source: Taprogge GmbH) [7]
22
3.3.3 Fill Defects in CT
Defects of fill in cooling tower of power plant are shown in below Figures from (3.20 to3.24)
[8].
As shown in figure above it shows defect in CT, due to uneven wrap at equal distance at the
end of fill stack reduces cooling capacity and effectiveness of CT.
23
As this plant is located in industrial area various dust and foreign particles are available in the
atmosphere, and this particle gets into the gap between fills and clog fills, due to which proper
cooling and contact of air and water does not take properly hence effectiveness reduces.
24
This defect as shown in figure above is due to uneven flow of water into the fill stacks due to
this some of the fill gets displaced and come down
25
Chapter 4
This is the procedure by which maintenance of DM pump will be carried out step by step in
power plant by Figure 4.1
Identification of problem
By leakage and abnormal sound during observation. During plant visit with mentors in DM
plant abnormal noise and high vibration is observed. Apart from noise leakage from impeller
eye is noticed.
26
Causes of Problem
All of the above are predicted causes for problem out of which some of the causes are critical
which are shown in red outline, due to which leakage and abnormal sound are observed
during visit. This fish bone diagram gives us idea about all the possible available causes to the
problem and made easy to identify main and critical cause to problem
Checking of Inventory
27
Overhauling
As discuss in previous section after findings of critical causes of the problem abnormal noise
and vibrations of pump it is concluded that mechanical seal is damaged and two bearings was
worn out , so to replace those parts overhauling is carried out in the sequence as shown in
figure above. First of all bearing housing is to be removed as shown in Figure 4.1 then
bearing seal and oil seal is to be removed and their condition is observed after that closed
impeller is removed and then at last mechanical seal and movable casing is dissembled as
shown in figure.
28
Maintenance Activity
Maintenance activity includes replacement and cleaning of various worn parts of the pump,
which are as follows [9]
After cleaning and changing of parts assembly of pump was carried out and during testing of
pump it was observed that the problem regarding vibration and leakage is no more.
29
4.2 Solution 2 - Damage Assessment of Compressor Failure
4.2.1 Causes Of Problem
Filters Condition
Carry out replacement of the pulse filters as
No maintenance was carried out by customer per OEM maintenance manual as well as
on the filtered during this regularly monitor the dp across the filters.
shutdown.
Installed filters are from Dallinger- S65R-
U18A9-SPX
Silencer Housing
Clean the filter house
Area after pulse filters seen with old water area.
puddle marks Filter house flooring found Remove corrosion and repaint the affected
with dust deposits areas
Minor corrosion spots seen after silencers
near the retaining plates.
Stream of dust seen after the silencer housing
Silencers
31
4.2.3 Solution / Recommendation
32
Table 4.3 Compressor Vanes Findings Related to Damage Assessment &
Recommendations
Compressor Vanes Findings Related To Recommendation
Damage Assessment
Compressor Vane Row 4
Medium tip rubbing seen. Replace complete set of compressor
All the vanes TE found with impact damage vane row 4 along with new assembly
near platform. Material.
Medium Impact (19 vanes): 8,9,10,12, Ensure proper preservation techniques
18,19,20, 26, 27, 28, 30, 34, 40 as per OEM specification document
Significant Impact (30 vanes) 1,2,3,5,6, 7, HTCT690086, when the customer is not
13,14,15,16, 22,23,24, 29, 31, 32, 33, 35, intending to run the machine over a
36, 37, 38, 39, 41, 42, 43, 44, 45, 46, 47, 48 Period of long time.
No dislocation of intermediate pieces seen
Compressor Vane Row 5
Medium tip rubbing seen. Replace complete set of compressor
All the vanes TE found with significant vane row 5 along with new assembly
impact damage approx. 25mm near platform material
Vane #4 completely sheared off. Remaining Ensure new vane tip clearances are
foot piece intact is 10mm checked during installation and if
No dislocation of intermediate pieces seen required vane tip grinding to be carried
Out as per OEM specifications.
Compressor Vane Row 6
Medium tip rubbing seen. Replace complete set of compressor
All the vanes LE found with impact damage vane row 6 along with new assembly
approx. 10-25mm near platform. Material.
LE Medium Impact seen on (18 vanes) : 36, Ensure new vane tip clearances are
36, 40, 41, 42, 43, 44, 45, 47, 50, 52, 53, checked during installation and if
55, 56, 57, 59, 62, 63 required vane tip grinding to be carried
Significant impact damage seen on (31 vanes) out as per OEM specifications
:1,2,3,4,5,7,8,9,10,11,12,15,16,17,22,28,32,
33, 34, 37, 38, 39, 46, 48, 49, 51, 54, 58,
60, 61, 64
No dislocation of intermediate pieces seen or
tip burring found
Compressor Vane Row 7
Vane row 7 found loose Replace complete set of compressor
Medium tip rubbing seen. No burring seen vane row 7 along with new assembly
LE found with light impact on (11 vanes) # 1, Material.
16, 36, 43, 45, 53, 54, 56, 58, 59, 60, Ensure new vane tip clearances are
LE found with medium impact damage on (3 checked during installation and if
vanes) – 8, 31, 47, required vane tip grinding to be carried
LE Significant impact on ( 4 vanes) out as per OEM specifications
# 4: impact -20x3mm at LE near mid-section
# 22 LE impact – 20mm in length near foot
# 26: TE impact- 20mm in length near foot
# 29: TE impact- 15mm in length near foot
33
Table 4.3 Compressor Vanes Findings Related to Damage Assessment &
Recommendations
34
Table 4.3 Compressor Vanes Findings Related to Damage Assessment &
Recommendations
OGV(Outer Guide Vanes)
Medium tip rubbing seen. No burring seen Replace complete set of compressor
LE found with light impact on (2 vanes) # 2, vane OGV along with new assembly
14 Material.
LE seen with medium impact damage on (8 Ensure new vane tip clearances are
vanes) # 12, 13, 20, 25, 26, 27, 45, 57 checked during installation and if
LE found with significant impact damage on required vane tip grinding to be carried
( 3 vanes): out as per OEM specifications.
# 11 Location- 12mm from foot. Impact- 5X3
mm),
# 28 – Impact – 5 X3 near foot and 25mm air
foil bent at TE
# 56- Impact 5X5mm at LE mid-section
TE mid-section found with light impact
damage on : # 6,
TE mid-section found with medium impact
damage on (6 vanes) # 14, 22, 28, 29, 50,
64
Compressor Casing
Lower and UH Smoothen the sharp edges.
Impact marks seen on compressor casing
between row 5 and 6
No fresh rubbing seen on LH and UH
35
4.3 Performance and Maintenance of Cooling Tower
4.3.1 Performance of CT
• The mass flow rate of the water flowing through the tower (kg/sec)
• The specify heat capacity of the water (kJ/kg.K)
• The change in temperature of the water (RANGE of the Tower).
• Where:
• THUS: Q = M c Δť
Description values
Number of CT Cells 8
36
THUS,
Q = M Cp Δť
6.7kg/sx4.19kJ/kg Kx6K
6.7x4.19x6
For 8 CT
=1347.44KW
Approach
The approach is the difference of the water leaving the tower and the temperature of the air
entering the tower.
= 28°C - 24°C
= 4K
Range
The range is the difference between the temperature of the water entering the tower and the
water leaving the tower.
=6K
Effectiveness
𝑟𝑎𝑛𝑔𝑒
𝐶𝑇 𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒𝑛𝑒𝑠𝑠 =
𝑟𝑎𝑛𝑔𝑒 + 𝑎𝑝𝑝𝑜𝑎𝑐ℎ
= 60%
37
Evaporation Loss
= 216.7398 m3/hrs
COC = 8.25
evoporation loss
𝑩𝒍𝒐𝒘 𝒅𝒐𝒘𝒏 =
(coc − 1)
=29.89 m3/hr
38
4.3.2 Preventive Maintenance of CT [9]
Followings are the procedure of maintenance for cooling tower and its inspection frequency
derived after FMECA analysis and experience of operators and engineers.
39
Chapter 5
Conclusions
Conclusions
In the present study of various critical and non-critical equipment’s of power plant such as
centrifugal pump, Cooling tower, Gas turbine and Compressor, problems were identified
during visit by observation and possible efforts were made to solve those problems with
recommendations and suggestions. The major conclusions made from the study are as under:
After study of various causes of problem it was found that the main cause of problem
was in mechanical seal and all the bearings were worn out due to which vibration and
noise arises
After damage assessment of various modules of gas turbine (GT) various observations
were made and based on observations changes were recommended. Apart from this
with the help of p-chart software circumferential defect chart for vanes of compressor
were made and based on its decisions of replacement or rework of vanes and blades
was taken.
It was concluded that the main cause of failure was presence of pieces of blades found
inside the compressor casing and debris below combustor casing.
The cooling capacity, range, approach, effectiveness of cooling tower were found as
1347.44KW, 6K, 4K, and 60 %
Preventive maintenance schedule of cooling tower was made with the appropriate
inspection frequency based on FMECA analysis and experience of operators.
40
References
https://en.m.wikipedia.org/wiki/Gujarat_State_Energy_Generation
[2] https://www.steag.in/en/
[4] https://www.ge.com/power/resources/knowledge-base/combined-cycle-power-plant-how-
it-works
[5] Crack of a first stage blade in a steam turbine M. Nurbanasari a,*, Abdurrachim
[6] Code of Practice for Water-cooled Air Conditioning Systems ,2006 Edition
investigation of the failure of low pressure steam turbine blades. J Eng Fail Anal
1998;5:181–93.
41
42
43
44