ITEM 100 Latest 2012 (M) Final
ITEM 100 Latest 2012 (M) Final
ITEM 100 Latest 2012 (M) Final
This item shall consist of clearing, grubbing, removing and disposing all
vegetation and debris as designated in the Contract, except those objects that are
designated to remain in place or are to be removed in consonance with other
provisions of this Specification. The work shall also include the preservation from
injury or defacement of all objects designated to remain.
Construction Requirements
General
The Engineer will establish the limits of work and designate all trees,
shrubs, plants and other things to remain. The Contractor shall preserve all
objects designated to remain.
All surface objects and all trees, stumps, roots and other protruding
obstructions, not designated to remain, shall be cleared and/or grubbed, including
mowed as required, except as provided below:
(1) Removal of undisturbed stumps and roots and nonperishable solid
objects with a minimum depth of one (1) meter below subgrade or
slope of embankment will not be required.
(2) In areas outside of the grading limits of cut and embankment areas,
stumps and nonperishable solid objects shall be cut off not more than
150 mm (6 inches) above the ground line or low water level.
(3) In areas to be rounded at the top of cut slopes, stumps shall be cut off
flush with or below the surface of the final slope line.
(4) Grubbing of pits, channel changes and ditches will be required only to
the depth necessitated by the proposed excavation within such area
Description
This Item shall consist of the removal wholly or in part, and satisfactory
disposal of all buildings, fences, structures, old pavements, abandoned pipe lines,
and any other obstructions which are not designated or permitted to remain,
except for the obstructions to be removed and disposed off. It shall also include
the salvaging of designated materials, and backfilling the resulting trenches, holes
and pits.
Construction Requirements
General
The Contractor shall perform the work described above, within and
adjacent to the roadway, on Government land or easement, as shown on the
Plans or as directed by the Engineer. All designated salvable material shall be
removed, without unnecessary damage, in sections or pieces which may be
readily transported, and shall be stored by the Contractor at specified places on
the project.
All existing culverts and other drainage structures in use by traffic shall not
be removed until satisfactory arrangements have been made to accommodate
traffic. The removal of existing culverts within embankment areas will be required
only as necessary for the installation of new structures or pipelines. Abandoned
culverts shall be broken down, crushed and sealed or plugged. All retrieved
culvert for future use as determined by the Engineer shall be carefully removed
and all precautions shall be employed to avoid breakage or structural damage to
any of its part. All sections of structures removed which are not designated for
stockpiling or re-laying shall become the property of the Government and be
removed from the project or disposed off in a manner approved by the Engineer.
Unless otherwise provided, all pipes shall be carefully removed and every
precaution taken to avoid breakage or damaged. Pipes to be re-laid shall be
removed and stored when necessary so that there will be no loss of damage
before re-laying. The Contractor shall replace sections lost from storage or
damage by negligence, at his own expense.
III. EXCAVATION
Description
This Item shall consist of trench excavation, and the disposal of material in
accordance with this Specification and in conformity with the lines, grades and
dimensions shown on the Plans or established by the Engineer.
Construction Requirements
General
Conservation of Topsoil
All excess materials, including rock and boulders that cannot be used in
embankments shall be disposed off as directed.
Prewatering
Borrow Areas
All borrow areas shall be bladed and left in such shape as to permit
accurate measurements after excavation has been completed. The Contractor
shall not excavate beyond the dimensions and elevations established, and no
material shall be removed prior to the staking out and cross-sectioning of the site.
The finished borrow areas shall be approximately true to line and grade
established and specified and shall be finished, as prescribed in the approved
detailed engineering plans
Description
This Item shall consist of the necessary excavation for foundation of
bridges, other structures not otherwise provided for in the Specifications. The
backfilling of completed structures and the disposal of all excavated surplus
materials, shall be in accordance with these Specifications and in reasonably
close conformity with the Plans or as established by the Engineer.
It shall also include the furnishing and placing of approved foundation fill
material to replace unsuitable material encountered below the foundation
elevation of structures.
Construction Requirements
Excavation
(1) General, all structures. The Contractor shall notify the Engineer
sufficiently in advance of the beginning of any excavation so that
cross-sectional elevations and measurements may be taken on the
undisturbed ground. The natural ground adjacent to the structure shall
not be disturbed without permission of the Engineer.
(2) Structures other than pipe culverts. All rock or other hard foundation
materials shall be cleaned of all loose materials, and cut to a firm
surface, either level, stepped, or serrated as directed by the Engineer.
All seams or crevices shall be cleaned and grouted. All loose and
disintegrated rocks and thin strata shall be removed. When the footing
is to rest on material other than rock, excavation to final grade shall
not be made until just before the footing is to be placed. When the
foundation material is soft or mucky or otherwise unsuitable, as
determined by the Engineer, the Contractor shall remove the
unsuitable material and backfill with approved granular material. This
foundation fill shall be placed and compacted in 150 mm layers up to
the foundation elevation.
When foundation piles are used, the excavation of each pit shall be
completed before the piles are driven and any placing of foundation fill
shall be done after the piles are driven. After the driving is completed,
all loose and displaced materials shall be removed, leaving a smooth,
solid bed to receive the footing.
(3) Pipe Culverts. The width of the pipe trench shall be sufficient to permit
satisfactory jointing of the pipe and thorough tamping of the bedding
material under and around the pipe.
Cofferdams
Description
Material Requirements
3
(e) Soils with very low natural density, 800 kg/m or lower.
Construction Requirements
General
Embankments and backfills shall contain no muck, peat, sod, roots or other
deleterious matter. Rocks, broken concrete or other solid, bulky materials shall not
be placed in embankment areas where piling is to be placed or driven.
Where shown on the Plans or directed by the Engineer, the surface of the
existing ground shall be compacted to a depth of 150 mm and to the specified
requirements of this Item.
Methods of Construction
Each layer shall be leveled and smoothed with suitable leveling equipment
and by distribution of spalls and finer fragments of earth.
Protection of Structure
After the roadbed has been substantially completed, the full width shall be
conditioned by removing any soft or other unstable material that will not compact
properly or serve the intended purpose. The resulting areas and all other low
sections, holes or depressions shall be brought to grade with suitable selected
material. Scarifying, blading, dragging, rolling, or other methods of work shall be
performed or used as necessary to provide a thoroughly compacted roadbed
shaped to the grades and cross-sections shown on the Plans or as staked by the
Engineer.
All earth slopes shall be left with roughened surfaces but shall be
reasonably uniform, without any noticeable break, and in reasonably close
conformity with the Plans or other surfaces indicated on the Plans or as staked by
the Engineer, with no variations therefrom readily discernible as viewed from the
road.
Description
This Item shall consist of the preparation of the subgrade for the support of
overlying structural layers. It shall extend to full width of the roadway. Unless
authorized by the Engineer, subgrade preparation shall not be done unless the
Contractor is able to start immediately the construction of the pavement structure.
Material Requirements
Unless otherwise stated in the Contract and except when the subgrade is in
rock cut, all materials below subgrade level to a depth 150 mm.
Construction Requirements
Prior Works