Welcome To A Discussion On: M.V. Raghu
Welcome To A Discussion On: M.V. Raghu
Welcome To A Discussion On: M.V. Raghu
M.V. Raghu,,
Retd. Controller, KPTCL / CESC
Mysore
1
What is Price Variation?
As per the terms of the contract, amounts
payable / recoverable from the contractor /
vendor consequent to fluctuation in the WPI
(Wholesale Price Index) (inflation / deflation) of
the raw materials used in manufacture of
materials supplied against work award /
purchase order.
2
When price variation is applicable?
Projects costing Rs.100 Lakhs and above & the period
of completion is 6 months and above. Order No.
KPTCL / B37 / 6426 / 2005-06 dt. 05-10-2005.
Circular
3
Documents required for calculation of PV
Circular
DWA (Detailed Work Award) with special reference to
Schedule 2 (2 of 2) for taxes and duties, Schedule 21
for materials sourced out side the State of Karnataka.
(Scanned copy)
9
Calculation of PV (Contd.)
(B) For Erection / Civil Portion
• Base Date will be Techno Commercial bid opening
date
• Contractual Completion Date will be the date
indicated in the letter of Chief Engineer concerned
Note:
o DWA rates are available / similar materials are
supplied as per DWA.
o Certificate of necessity / justification by the Zonal
CEE / SEE / EEE for admitting PV is required
subject to approval of Work-slip / Variation by
Competent Authority.
10
Calculation of PV (Contd.)
For Non-DWA materials:
(A) For Supply Portion:
• Date on which Turnkey agency has been intimated by KPTCL or
actual date of supply whichever is earlier is treated as “Base
Date”
• “Contractual Delivery Date” will be the actual date of supply.
11
CONTROL CHART
Sl. Particulars
No.
1 Name of the work / Project
Description of Price Variation Bill (Supply,
2
Erection or Civil)
3 Name of the Material
Base Date as per DWA (Techno Commercial
4
Bid Opening Date)
5 Price Bid Opening Date
6 Date of LOI
12
CONTROL CHART (Contd.)
Sl. No. Particulars
11 Schedule 2 (2 of 2)
Amount = Ex(1+0.1036+0.055+0.005698)
Amount = Ex(1.164298)
= Amount
Ex-Works
1.164298
14
Calculation of Ex-Works price when quoted price is inclusive of
Taxes and Duties (10.36 ED;14.5% VAT)
Amount = Ex(1+0.1036+0.145+0.015022)
Amount = Ex(1.263622)
= Amount
Ex-Works
1.263622
15
Materials for which PV is admissible
i. Power Transformers
Circular
ii. Circuit Breakers / Switchgears
iii. Conductors and Ground Wires (CACMAI)
iv. Lightening Arrestors
v. Transformer Oil
vi. Tower Parts / Station Structures
vii. Control Cables
viii. HT / EHT U.G. Cable
ix. Conductor Hardware
x. Battery
xi. Battery Chargers
xii. Instrument Transformers
xiii. Insulators
xiv. Civil works
16
POWER TRANSFORMER – 10 MVA & above AND
VOLTAGE 33 Kv ABOVE
IEEMA formula:
P=P0/100(13+23(C/C0)+28(ES/ES0)+7(IS/IS0)+7(IM/IM0)+7(TB/TB0)+15(W/W0)
Circular
W.E.F. 01-06-2010
P=P0/100(13+23(C/C0)+28(ES/ES0)+7(IS/IS0)+7(IM/IM0)+7(TO/TO0)+15(W/W0)
o IS hither too which was “Iron & Steel” is changed as IS “Ferrous Metals”
17
Switchgear / Circuit Breaker above 36 KV
IEEMA formula:
P=P0/100(25+17(IS/IS0)+18(C/C0)+10(Al/Al0)+13(In/In0)+17(W/W0)
P=P0/100(19+17(IS/IS0)+17(C/C0)+13(AL/AL0)+19(IN/IN0)+15(W/W0)
“In – price of epoxy resin” is replaced by “IN- IEEMA index for Insulator”
18
Switchgear / Circuit Breaker above 36 KV
Contd…
P=P0/100(19+17(IS/IS0)+17(C/C0)+13(AL/AL0)+19(IN/IN0)+15(W/W0)
19
Lightning Arrestor
IEEMA formula:
W.E.F. 01-09-2001 Circular
P=P0/100(20+15(ZN/ZN0)+15(CO/CO0)+10(BI/BI0)+10(BC/BC0)+10(FP/FP0)+15(W/W0)+
5(AL/AL0)
W.E.F. 01-06-2010
There is no change in the formula.
FP hither too which was “whole sale price index for Fuel, Power, Light
and Lubricant” is changed as FP “Power and Light”
If the project commenced prior to 01-06-2010 but continued after this
date revised WPI is to be used in the formula.
20
Transformer Oil
IEEMA formula:
W.E.F. 01-01-2000 Circular
21
STATION / MOUNTING STRUCUTRES /
TOWER PARTS
IEEMA formula effective from: 01-01-2002 Circular
In respect of Transmission Line Towers using both Heavy and Lighter Angles:
P=P0/100(15+18(HA/HA0)+40(LA/LA0)+16(Zn/Zn0)+11(W/W0)
22
STATION / MOUNTING STRUCUTRES Contd….
23
STATION / MOUNTING STRUCUTRES Contd….
24
STATION / MOUNTING STRUCUTRES Contd….
In such an event calculate “P” using the IEEMA formula effective from 1st
July 2010 up to April 2014. Then substitute the value of “P” so arrived as
“P0” in the formula effective from 01-04-2014.
25
TRANSMISSION LINE ACCESSORIES
AND HARD WARE
As on date IEEMA formulae for this has been revised three times
26
TRANSMISSION LINE ACCESSORIES
AND HARD WARE Contd. ….
IEEMA formula effective from: 01-09-2008 Circular
“Fe – whole sale price index for Iron & Steel has been substituted with “LA –
Lighter Angles”
In such an event calculate “P” using the IEEMA formula shown on the
previous slide up to September 2008. Then substitute the value of “P” so
arrived as “P0” in the formula effective from 01-09-2008.
27
TRANSMISSION LINE ACCESSORIES
AND HARD WARE Contd. ….
IEEMA formula effective from: 01-09-2008 Circular
“Fe – whole sale price index for Iron & Steel has been substituted
with “LA – Lighter Angles”
In respect of Accessories and Hardware using both Aluminum and Steel:
P=P0/100(20+40(AL/AL0)+5(Zn/Zn0)+20(LA/LA0)+15(W/W0)
28
TRANSMISSION LINE ACCESSORIES
AND HARD WARE Contd. ….
IEEMA formula effective from: 01-03-2011 Circular
“LA – Lighter Angles” has been substituted with “SBI – Steel Billets”
In such an event calculate “P” using the IEEMA formula shown on the
previous slide up to March 2011. Then substitute the value of “P” so
arrived as “P0” in the formula effective from 01-03-2011.
29
TRANSMISSION LINE ACCESSORIES
AND HARD WARE Contd. ….
IEEMA formula effective from: 01-03-2011 Circular
“LA – Lighter Angles” has been substituted with “SBI – Steel Billets”
30
STATION BATTERIES
IEEMA formula:
P=P0/100(40+30(LD/LD0)+30(W/W0)
31
BATTERY CHARGER
IEEMA formula:
P=P0/100(20+50(IN-BTR-CHRG/IN0-BTR-CHRG)+30(W/W0)
32
INSTRUMENT TRANSFORMERS – CT / PT / VT
33
INSTRUMENT TRANSFORMERS – CT / PT / VT Contd.
…
IEEMA formula effective from: 01-06-2010 Circular
However “IS- Whole sale price index for iron & steel” has
been replaced by “IS-Ferrous Metals”
34
INSULATORS
IEEMA formula:
35
CIVIL WORKS AND ERECTION
In respect of Concreting:
In respect of Erection :
36
CIVIL WORKS AND ERECTION Contd. …
37
PVC and XLPE Insulated Cables
W.e.f. 01-01-2001 Circular
38
Insulated Cables Circular
W.e.f. 01-01-2007
39
Conductor and Ground Wire Circular
At present the formula will be as per the DWA of the concerned work to be followed:
For example formulae from one of the DWA is as follows:-
41
ACSR conductor Accessories &
HARDWARE – Material Content
Vibration Damper, T & S clamp, Post insulator
clamp, PG clamp, MSC joint has Steel &
aluminum content
Pre formed Armored Rods, Repair Sleeve has
only aluminum content
Tension clamp, Suspension clamp, PG clamp,
MSC joint, Hardware relating to ground wire
has only STEEL content
42
TRANSMISSION LINE TOWERS
where Heavy Angles are used
43
TRANSMISSION LINE TOWERS
where Heavy and Lighter Angles are used
44
TRANSMISSION LINE TOWERS
where only Lighter Angles are used
45
EXERCISE
46
Thank you
47