3059-CABLE TERMINATION, LOOP TEST, LEAK TEST, PRE-COMMISSIONING Mod 5
3059-CABLE TERMINATION, LOOP TEST, LEAK TEST, PRE-COMMISSIONING Mod 5
3059-CABLE TERMINATION, LOOP TEST, LEAK TEST, PRE-COMMISSIONING Mod 5
MDR PROJECT - CABLE TERMINATION, LOOP TEST, LEAK TEST, PRE-COMMISSIONING, TESTING AND CALIBRATION OF
Job Title
INSTRUMENTS AT MODULE 5 AREA
Status Approved
1 Hamdan Bin Osman Health, Safety & Environment Reviewed 28/04/2016 03:25
3 Awang Jidel bin Awang Lee Operations Department Reviewed 29/04/2016 17:50
Contractors
HYPERWAVE - LP CONSORTIUM
Worksheet
2.0 Working inside Main Field Station Electrocuted People The cabinet door/cover is to be opened by MLNG Work leader
authorized personnel.
System
Asset To be accompanied by Company PMT Work Leader
interruption
Pinch point People To wear semi-leather / cotton hand gloves. Work leader
Preparation/ execution work of To wear semi leather / cotton hand glove and safety
cable glanding and cable shoes.
3.0 termination : Work Leader
Hand Injuries People To coordinate work and communicate in correct work
sequence.
4.0 Field Loop check Preparation: Electrocuted People The cabinet door/cover is to be opened by MLNG Work leader
authorized personnel.
Open wrong
To refer and confirmed AFC drawings prior commence
panel/ cabinet/ Asset Work Leader
work.
junction box
a) Opening of Panels /
Marshalling cabinet / Junction Box
Pinch point People To wear semi leather hand glove. Work leader
b) Cable preparation prior to Wrong cable To refer and confirmed AFC drawings prior commence
perform testing. Asset Work Leader
disconnected cable dismantling work.
c) Disconnect both ends of To use wire stripper for stripping work.
cable
To use cotton gloves with rubber coated.
Work Leader
Hand injuries People
To coordinate work and communicate in correct work
sequence.
5.0 Cable continuity test (Mulitmeter/ The cabinet door/cover is to be opened by MLNG
Process meter), Loop Test ( Hart Electrocuted while authorized personnel.
Communicator and Insulation working inside
Resistance test (Megger Tester) existing
People Work leader
marshalling/
power distribution
· Disconnect Cable To be vigilant not to touch the existing live termination
board
inside the panel.
· Insulation test and continuity
test Touching existing Asset To notify MLNG authorized personnel prior to work Work leader
live cable (short
commence
circuit) To refer and confirmed AFC drawings prior commence
work.
People
· Re-terminate the cable Both ends of cable being tested must be protected from
accidently touch by personnel until the test is
· Close back the panel completed
Electric Shock People Discharged tested cable to the earth at the end of test Work leader
6.0 Dismantle cable glanding and Electrocution People LOTO on main DB/isolator and to be switched off by Work leader
disconnect cable termination MLNG AIN
· To apply LOTO and De- Ensure test meter are certified and calibrated.
LOTO to electrical equipment
Ensure only competent person to carry out the work
Damaged to
Asset To coordinate work and communicate in correct work Work leader
Cable
sequence.
Disconnect wrong Asset To confirm the cable identification (size, rating, type, Work leader
cable color, voltage) service for the cables and location of the
termination points/terminal block as per cable schedule
and As-built drawings.
Environment
Work Leader
Equipment Ensure only competent person to carry out the work
10.0 Calibrate Instruments Asset
Damage
Perform calibration as per manufacturer’s instructions.
12.0 Housekeeping Slip, trip and fall People To clear debris at end of each working day. Work leader
General Notes
1. Emergency contact number:
Prepared By
Contractors
HYPERWAVE - LP CONSORTIUM