Gantt Charts - Problems
Gantt Charts - Problems
Gantt Charts - Problems
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 --- 12/06/2015 13/06/2015 2 Days
2 1 14/06/2015 16/06/2015 3 Days
3 2 17/06/2015 20/06/2015 4 Days
4 3 21/06/2015 21/06/2015 1 Days
5 3 21/06/2015 22/06/2015 2 Days
6 5 23/06/2015 24/06/2015 2 Days
7 4, 6 25/06/2015 28/06/2015 4 Days
8 3 21/06/2015 23/06/2015 3 Days
Critical path is in red colour
22 columns
10 rows
Problem
The following table shows the tasks, dependencies, and estimated times a project manager might input to a basic GANTT chart for a software development project.
Problem No. 2
https://teams1.pressbooks.com/chapter/gantt-chart/
Problem No. 3