Gantt Charts - Problems

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

ID Predecessor Start Date Finish date Duration June 2015

12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 --- 12/06/2015 13/06/2015 2 Days
2 1 14/06/2015 16/06/2015 3 Days
3 2 17/06/2015 20/06/2015 4 Days
4 3 21/06/2015 21/06/2015 1 Days
5 3 21/06/2015 22/06/2015 2 Days
6 5 23/06/2015 24/06/2015 2 Days
7 4, 6 25/06/2015 28/06/2015 4 Days
8 3 21/06/2015 23/06/2015 3 Days
Critical path is in red colour

Slack Time = Activity 4 is having 3 days slack 22, 23, 24/06/2015

Activity 8 is having slack of 5 days = 24, 25, 26, 27, 28/06/2015

22 columns

10 rows

Problem

The following table shows the tasks, dependencies, and estimated times a project manager might input to a basic GANTT chart for a software development project.

Project start date: 12 June 2015


Task Identifier Task Description Predecessor Task(s) Time (days)
1 Establish project ---- 2 Days
2 Establish customer requirements 1 3 Days
3 Produce software specification documents 2 4 Days
4 Write test plans 3 1 Days
5 Write code 3 2 Days
6 Developer testing 5 2 Days
7 System testing 4, 6 4 Days
8 Write customer documentation 3 3 Days
Draw a Gantt chart for a software development project. Also Calculate EF, LF, Slack and Critical path activity
Project start date: 12 June 2015
Task Identifier Task Description Predecessor Task(s) Time (days) EF LF Slack Critical Path
1 Establish project ---- 2 Days 2 2 0 yes
2 Establish customer requirements 1 3 Days 3 3 0 yes
3 Produce software specification documents 2 4 Days 4 4 0 yes
4 Write test plans 3 1 Days 1 4 3 Days No
5 Write code 3 2 Days 2 2 0 yes
6 Developer testing 5 2 Days 2 2 0 yes
7 System testing 4, 6 4 Days 4 4 0 yes
8 Write customer documentation 3 3 Days 3 8 5 Days No

Problem No. 2

https://teams1.pressbooks.com/chapter/gantt-chart/

Problem No. 3

Draw a Gantt Chart for the tasks shown in the table

Activity Preceding Activity Expected Duration


A --- 4
B A 5
C A 6
D A 7
E A, D 6
F C, E 5
G D, E 4
H E 3
I F, G 4
J H, I 5
Also calculate EF, LF, Slack and Critical path activity