Joints PDF
Joints PDF
Joints PDF
UNIT IV
JOINTS IN STRUCTURAL MEMBERS
Compiled by,
C.AMARNATH M.E;
ASSISTANT PROFESSOR
DEPARTMENT OF CIVIL ENGINEERING
SRI VIDYA COLLEGE OF ENGINEERING & TECHNOLOGY
VIRUDHUNAGAR
UNIT IV
JOINTS IN STRUCTURAL MEMBERS
One of the most intricate and most difficult problems to be solved in both design
of construction of structures assembled of prefabrication members is the joining.
It is highly important that the construction of the joints should be easy that
unavoidable smaller inaccuracies and deviations within dimensional tolerances should
neither influence the designed stresses in a detrimental manner nor cause is admissible
changes in the stress distribution of the structures.
The forming and construction of joints requires owing to their intricacy, great
increased control joints which cannot be inspected should be omitted.
When solving the problem of joints the properties of reinforced concrete must be
taken into consideration. This means in other words, that the design of the construction of
the joint should harmonize with the materials to be used. The properties of steel of timber
are quite different from those of concrete and reinforced concrete. Therefore joints
similarly to those used in timber and steel construction are generally not appropriate for
the purpose.
Joints of reinforced concrete structures which should be omitted are shown
These joints have to be seen. This is a solution resembling a butt joint with
splayed table as used in timber construction. This doesn’t comply with the nature of the
material of so is not good for this purpose. The imitating a joint used in steel
construction, is not appropriate either. The steel structure like joint as seen in which the
component structural parts are welded to the reinforcement is also not sufficient
adequate. The two halves of the steel structure forming the main constituents of the joints
have to be concrete into the ends of the jointed. The slightest rotational displacement is
sufficient to hinder the teeth to one another and the placing of the pins.
The joints can be rigid hinge-like or shed rigid joints are adequate in addition to
the bearing the tensile, compressive of shear forces for resistance.
Design of class based an efficiency of the material used:
The plastic concrete can be used for the subsequent concrete of joints of
the fluid cement mortar cast or pressed into the gaps less part of their water during the
setting time of shrink, after setting the shrinkage of the insite concrete of mortar continue.
With respect to two phase of shrinkage same codes on reinforced concrete
construction permit only reduced stresses for a subsequent insite concrete of a mortar
casting. There are generally determined as a function of width of the joint on the gap to
be concrete as cast.
Joints must be designed of executed so that compensation for the allowed
dimensional tolerances is ensured. A relative displacement of the joined member should
be impossible even as a result of a blow or of any other unfavourable force effect. The
length of the section determined for the transmission of forces should be as short as
possible but should excluded any excess of the permissible stress.
The joints can be rigid hinge like or shed. Rigid joints are adequate in addition to
the bearing of tensile, compressive of shear forces for resisting to bending moments too.
These joints make relative displacement and relative relation impossible. Hinge like
joints can transmit forces passing through the hinge itself and also allow a certain motion
and rotation.
Rigid joints are generally used for the junction of column to footings, but they can
also be applied for joining of individual groups with one another. The joints generally
used in the construction with precast members are usually hinge like. Their execution is
simpler and requires less working lime than rigid joints “shed joints” are only
exceptionally used in industrial construction of are justified for a long span only. These
joints are chiefly used in bridge construction for long span bridges depending on the
necessity of insite concreting; two kinds of joints can be distinguished.
a) Dry joints = joint accomplished by simple placing of two members on
each other of fasting.
b) Wet joints = joint require not only casting with cement mortar but also
subsequent concreting.
The disadvantages of the calyx joint are more suitable for small columns. In the
case of large columns requiring a calyx depth of which is greater than 1 m.
(b) JOINING OF COLUMN TO BEAM AT AN INTERMEDIATE
JUNCTION:
The functions of beams can be affected either by overlapping the protracting steel
bars or by welding them together.
Fig. shows the hinge like joint of purlins. In this method the whole shear must be
borm by both cantilevers (i.e.) by two separate structures therefore it is expedient to form
this joint at least for large girders.
The method illustrated in the fig presents a dry joint of beams which is called a
bolted front. The advantages of this joint are immediate bearing capacity.
(e) FORMING OF FUNCTIONS OF ARCHED STRUCTURES:
Precast arches are usually produced and assembled in the form of three hinged
structures. When the constant load has already been applied the centre joint is frequently
eliminated. The omission of the centre joint increases the rigidity of the structures.
Naturally arched structures can also be precast in a piece i.e. in the form of two hinged
ones.
Hinges of arched structures can be made by using either steel shors are more
expensive, but the centre transmission of forces is enhanced by their use of forming of
joints on an arched structure.
The arrangement of the Centre junction and the end hinge of an arched structure.
This method was used in the construction of the hall for the middle rolling train in
D.O.Sgyor. The structure was precast of assembled in the form of a three-hinged arched
transformed lates into a two-hinged one.
(f) DESIGN OF JOINTS FOR POST TENSIONED STRUCTURES:
Post tensioned structure can generally be joined for more simply then the usual
reinforced concrete structures, by using post tensioning it can be ensured that in the entire
structure. The joints included only compressive can develop consequently the problem of
joining can be solved in a very easy manner namely by placing plane surfaces side by
side and then filling the gaps with cement mortar by so doing longer beams can also be
produced from shorter precast member. Thus is post tensioned structures the forming of
joints does not cause difficulties.
Sketches on solution of principles relating to the joining of post tensioned
structure are to be illustrated in the fig. all these joints are of course rigid and moment
bearing. It is not permissible for the mortar which is to be poured into the ducts of the
stressing cables to avoid this cable ducts are joined by placing a shore piece of tube or
rubber ring into the duct itself.
A rigid point of these kind established between a column two girders supported by
the former after the casting of the gaps and hardening of the mortar, the short inserted
cables and stressed and so rigid joint is established.
(g) JOINING OF PRECAST TO MONOLITHIC REINFORCED
CONCRETE STRUCTURES:
Lower Performance
High rubber wall thickness and fiber pack make product less flexible
Undesired radial and axial expansion under pressure.