Inspection & Test Plan For Piping Systems: Doc. No.: Rev No.: 0
Inspection & Test Plan For Piping Systems: Doc. No.: Rev No.: 0
Inspection & Test Plan For Piping Systems: Doc. No.: Rev No.: 0
INSPECTION BY
CHARACTERISTICS TO BE REF. TESTING INSPECTION FORMAT
SR. NO. EXTEND OF CHECK
CHECKED DOCUMENTS INSTRUMENTS SUB- NO.
CONTRAC
TOR
Root Gauge,
4.5 Fit up Inspection & Preheat (If Reqd.) Random verification Approved WPS
Weld gauge
H RW RW
Name
Signature
Date
INSPECTION & TEST PLAN FOR PIPING SYSTEMS
INSPECTION BY
CHARACTERISTICS TO BE REF. TESTING INSPECTION FORMAT
SR. NO. EXTEND OF CHECK
CHECKED DOCUMENTS INSTRUMENTS SUB- NO.
CONTRAC
TOR
5.2 Visual Inspection of Welds 100% Welds TCE Specifications Weld gauge H W W
Name
Signature
Date
INSPECTION & TEST PLAN FOR PIPING SYSTEMS
INSPECTION BY
CHARACTERISTICS TO BE REF. TESTING INSPECTION FORMAT
SR. NO. EXTEND OF CHECK
CHECKED DOCUMENTS INSTRUMENTS SUB- NO.
CONTRAC
TOR
7.1 Pre Fabricated Spools verification Random Verification Approved Drawings Visual H W S
Verification of erected Piping System for
7.2 its Completeness and Mechanical 100% Verification Approved Drawings Visual H W S
Clearance
Spool to Spool Fit up Inspection, Joint Approved Drawings
7.3 No. Welder Id
100% Verification WPS Root gauge H RW S
8.2 Fit up & Welding 100% Verification Approved WPS Root Gauge H W RW
Approved Drawing
8.6 Bolting & Torqueing 100% Verification TCE Specifications
Torque Wrench H W H
Name
Signature
Date
INSPECTION & TEST PLAN FOR PIPING SYSTEMS
INSPECTION BY
CHARACTERISTICS TO BE REF. TESTING INSPECTION FORMAT
SR. NO. EXTEND OF CHECK
CHECKED DOCUMENTS INSTRUMENTS SUB- NO.
CONTRAC
TOR
Visual
9.1 Supports Erection 100% Verification Approved Drawing
Measuring Tape
H W RW
Approved Drawings
10.2 Release for Hydrotest 100% Verification P&ID and LHS
Nil H W W
10.3 Line walk & Punch Points 100% Verification Approved Drawings Visual H W W
Approved Drawings
10.4 Flushing of pipe system 100% Verification TCE Specification Visual H W S
VTKN/9001/TP/004,
11.0 Painting 100% Verification As Per approved Elcometer H W W
Painting FQP
Approved Drawings,
& As per approved
12.0 Insulation (As required) 100% Verification Insulation FQP
Visual H W W
13.0 Piping Test Pack Clearence 100% Verification Approved Drawings Visual H W H
Name
Signature
Date
INSPECTION & TEST PLAN FOR PIPING SYSTEMS
INSPECTION BY
CHARACTERISTICS TO BE REF. TESTING INSPECTION FORMAT
SR. NO. EXTEND OF CHECK
CHECKED DOCUMENTS INSTRUMENTS SUB- NO.
CONTRAC
TOR
Legends:
H: Hold Point is a mandatory inspection point and work shall not proceed without the presence of a representative of the organization. Activity designated as Hold must
be signed off by the Owner’s Representative.
W: Witness Inspection Point: Designated Witness Points for the involved personnel, which are required to be signed off by the personnel who witnessed. All activities, which
have a W point, will require a written notification to owner representative. In the event the owner representative does not attend within an agreed period the work may
proceed. In such cases, the owner representative will record in the appropriate signature space on the forms as “Not Witnessed”, and sign off.
RW: Witness Inspection point: Designated % witness points assigned by the owner’s representative, which will require written notification from the owner representative. In the
event owner representative does not attend within agreed the work, may proceed. In such cases, the owner representative will record in the appropriate signature space
on the forms as “Not Witnessed”, and sign off. The percentage means a minimum of 10% inspection over all. However this may be increased at the discretion of
construction manager or his designee.
S: Surveillance Over seeing or monitoring of activities by visiting. Activities designated as surveillance will Not be signed off by the owner’s representative.
DR: Document Review: This entails review of appropriate documentation and does not require signature of owner representative.
Name
Signature
Date