Determining The Best Feasible Mining Sequence and Phase Design
Determining The Best Feasible Mining Sequence and Phase Design
Determining The Best Feasible Mining Sequence and Phase Design
Page 1
Determining the Best Feasible Mining Sequence and Phase Design
pit design that are spatially, quantitatively, and qualitatively similar and that meet any
tolerances defined by the company or financing organization.
Pit phases are designed within the ultimate LG or pit design to facilitate mine plan scheduling.
Phases within the ultimate LG or ultimate pit design will be mining economic material but
some locations within the ultimate LG are more valuable than other locations. Ideally, the
profit per ton for the first phase in the sequence is the greatest to maximize the Net Present
Value (NPV) and each following phase will be of lesser value per ton. The discussion in the
next section will describe how to achieve a desirable phase/pushback sequence.
Page 2
Determining the Best Feasible Mining Sequence and Phase Design
methodology is acceptable as a guideline for phase design. The FC may create a more
confined shell. Sometimes the decision is predicated on deadlines or company/department
policy, machine run time, or complexity of parameters in use. The phase geometry sequence
should typically reflect pit shells of decreasing profit within the ultimate pit geometry.
Careful attention should be given to phase design deviations from the LG/FC phases as
these may result in more or less NPV within the phases.
MSEP can consider various mining conditions at the same time while producing an
ultimate pit limit and the best starting pit location. A series of pushback price shells (i.e.,
PIT02 through PIT09 below) can also be produced to show the direction of phase mining
and offer a series of shells from which an acceptable set of phase geometries can be selected
for phase design.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
MULTP is a design strategy in MSEP that facilitates the generation of scheduling shells
with minable width criteria which follow the best mining direction. MULTP can use shells
generated by other methods to be used as a starting or limiting surface to control the
generation of shells. In the following example, it will be shown how to obtain a series of
Page 3
Determining the Best Feasible Mining Sequence and Phase Design
incremental pits with an approximate mining width of 130 meters. Usually, the mining
width for each phase is driven by the limitations imposed by equipment size to allow
adequate access and operating space. As well, the smaller the mining width for the phase
the faster the ore can be mined which results in a higher NPV.
For example, the starting surface obtained from the price sensitivity analysis (PIT02) can be
used as the starting surface in MULTP as shown below. The outer shell is the ultimate pit.
Similarly, MULTP offers options to limit the rows/columns/benches used for the pit
optimization calculations as shown in the window and section below. This option will limit
the location of the ore blocks to be evaluated for the generation of the cones. Therefore, the
physical location of the phases to be generated can be further controlled by this restriction.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 4
Determining the Best Feasible Mining Sequence and Phase Design
Using the previous shell as the starting surface (PIT20) and a limiting surface (PIT04) can
also help control the location and direction of the next shell (PIT21).
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 5
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
The pictures below show how PIT21 is expanding towards the southwest (best mining
Since
direction), while its expansion towards the northeast is being limited by an existing surface
1970
located at a practical physical location (PIT04), resulting in a common face wall on the
northeast area.
Page 6
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 7
Determining the Best Feasible Mining Sequence and Phase Design
It should be noted that the last column is limited to 85 resulting in the PIT23 shown below.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
If this restriction is relaxed, then PIT23 would extend beyond the desired area on the eastern
portion of the pits as shown below.
Page 8
Determining the Best Feasible Mining Sequence and Phase Design
The next shell, which corresponds to PIT24, expands from PIT23 towards the final pit limits
on the south portion of the pit. This is accomplished by using PIT23 as the starting surface
and by limiting the rows used to a maximum value of 55. This will cause PIT24 to expand
south to the final pit shell.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 9
Determining the Best Feasible Mining Sequence and Phase Design
PIT24 is shown below with model blocks indicating the row limiting.
The last increment (PIT25) will extend from PIT24 towards the final pit limits towards the
north. Similar to the previous step, this was accomplished by using PIT24 as the starting
surface. No row restriction was necessary for PIT25 to extend towards the final pit limits.
Mintec, Inc.
Global
Mining
An example of the final phase sequencing shells is shown below in plan and section. This Software
phase sequence is more reasonable than the first set of shells created from incremental Solutions
commodity prices. Since
1970
Page 10
Determining the Best Feasible Mining Sequence and Phase Design
Page 11
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
After running MSVALP with the same parameters for the two sets of shells, the following
results were obtained.
Page 12
Determining the Best Feasible Mining Sequence and Phase Design
As seen above, MSEPc can chart the results from multiple MSVALP runs. It can also be used
to display any of the detailed information produced for any particular schedule. The chart
below shows a variety of scheduled tonnage and cutoff grade information.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 13
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Although it is unlikely that all of these phases would be used for scheduling purposes, it
would be interesting to evaluate the impact of the jump from Pit02 to Pit30 in the early
periods. MSVALP was run to evaluate Pits 2, 30, 31, 32, 33, 34 and 35. The results are
shown below.
Page 14
Determining the Best Feasible Mining Sequence and Phase Design
What to Consider and Expect During the MSOPIT and Phase Design Process
When estimating overall slope, consider the anticipated number of ramps in the pit walls
and pit slope design parameters such as:
Single or multi-bench mining, variable single- or multi-bench mining
Ramp widths and min/max grade range, single- and two-lane ramp plans
When using MSOPIT to create potential pushback surfaces, use the pushback width option
to approximate pushback widths. Also consider running an additional set of pushback
shells using a different overall slope or different sector slopes to try to account for different
numbers of ramps in pit pushback walls.
Expect to use a combination of both a top-down and bottom-up design processes in the
pit expander tool. Ramp switchbacks are common and intersections of three and four
ramps are not uncommon. Allow for consideration of in-pit construction that occurs when
actively mining.
When the pushback wall being designed should exactly match a wall in another pushback,
consider designing the pushback in air (inside the previous pushback) rather than trying to
manually add or move individual points with the snap function to make a coincident wall
Mintec, Inc. surface. Remember that the pushback design surface will later be merged with the previous
Global pushback topography. Any part of the pushback design that is in air will have no effect on
the resulting pushback surface merged into topography.
Mining
Software Expect to design pushbacks at least twice to achieve the correct geometry, pit exit locations,
Solutions merging of ramps, and ore extraction.
Since Consider cumulating the pushback designs to serve as the ultimate pit design instead of a
1970 separate ultimate pit design.
Expect to change the phasing sequence and regenerate reserve files for MSSP scheduling
at least once. If the mining schedule cannot achieve the target tonnage, grade, value, or
smoothed stripping, expect to redesign or re-sequence some pushbacks.
Remember: It is easy to start over.
Page 15
Determining the Best Feasible Mining Sequence and Phase Design
Page 16
Determining the Best Feasible Mining Sequence and Phase Design
Configure the cursor for easy visual measurements (Viewer | Cursor Tool).
Mintec, Inc.
Global
Mining
Software
Solutions
Define the parameters to report in the MS3D desktop status bar (File | Project settings |
Since Status Bar) for coordinate, orientation, and distance facts.
1970
Page 17
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 18
Determining the Best Feasible Mining Sequence and Phase Design
The Optional tab is used to define any pre-loaded model codes or values, or a table of sector
slope values that the Pit Expansion Tool is to use in lieu of the default wall and face slopes
and berm width entered on the Required tab.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 19
Determining the Best Feasible Mining Sequence and Phase Design
The Parameter Set tab contains saved responses for each tab that once saved, can be used
again. If properly named, these responses can document the parameters used in the Pit
Expansion Tool.
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 20
Determining the Best Feasible Mining Sequence and Phase Design
The Expansion tab is used to control the number of expansion steps, addition and deletion
of base strings, and making edits to any of the pit expander created polygons and polylines.
Page 21
Determining the Best Feasible Mining Sequence and Phase Design
Edit the base polygon to represent the new phase limit. In this example, no further edits to
the ramp entrance are needed, but the right side of the base polygon will need to be moved
into the air on the inside of the phase 2 pushback.
Mintec, Inc.
Global
Mining
Software
Solutions
On the Roads tab, create a new road. Use the user cam option to digitize both sides of the Since
ramp. Then expand down to the bottom of the phase including two switchbacks. The two 1970
Road tab windows below show the first and final road segment entries.
Page 22
Determining the Best Feasible Mining Sequence and Phase Design
The following pictures show the ramp extending down the next two benches below 2585
elevation.
Mintec, Inc.
Global
Mining
Software
Solutions The completed pit design from the 2585 elevation to the bottom of the phase is shown
Since below:
1970
Page 23
Determining the Best Feasible Mining Sequence and Phase Design
The next step is to expand a pit up and out from the 2585 elevation. The top-down design
object can continue to be used for the bottom-up design, or a new object can be created. The
original 2585 base polygon will first need to be offset outward to represent the beginning
toe line. Some editing will be necessary at the ramp entrance to match the existing ramp
previously created. This portion of the design above 2585 will not need a ramp and is shown
top of nexr page:
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 24
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 25
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Merge Phase Surface and Create Solid (Surface | Merge) Global
Mining
Merge the new phase 3 surface with the prior merged phase 2 surface topography and then
Software
contour the surface to check if it is correct.
Solutions
When merging topography surfaces, consistently use the same type of beginning Since
topography surfaces that will be used to calculate reserve and to compare with other results. 1970
Use the option to limit by polygons if necessary.
Use the Surface Intersector Tool (Surface | Intersect Surfaces Tool). Choose the phase 2
merged topography, which is the starting topography, to be the primary surface and choose
the phase 3 pit design surface as the secondary surface. Select the ‘cut surface difference’
operation.
Page 26
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Then use the Contour Tool (Polyline | Contour Tool) to contour the new merged surface
Page 27
Determining the Best Feasible Mining Sequence and Phase Design
If no adjustments are necessary to the pit design, use the Surface Intersector Tool to make
a solid of the phase 3 material to be mined.
Mintec, Inc.
Global
Mining
Calculate Phase Reserves [MineSight® Compass™ (MSCompass)] Software
Reserves will be calculated with the MSCompass procedure Pitres. Pitres can use Solutions
partial files created from surface geometries, special gridded surface files views or solids, Since
and it can directly use special gridded surface files. This example creates a partials file from 1970
the above solid (Surface | Generate Partials Tool). You only need to select the solid and
the appropriate model view and provide an output filename and extension.
Page 28
Determining the Best Feasible Mining Sequence and Phase Design
In the Pitres procedure, if using special gridded surface file surfaces, enter upper and
lower surface item names and use option 4 type of input. If using the partials file created in
MS3D, enter the file name and extension, and select option 1 type of input.
Be careful when using topography percent. Know when and when not to use it. If the
surfaces you are reporting were created from the gridded surface file item PIT00, use
topography percent in the calculations. If the surfaces being used are based on a typical
topography surface, then do not use topography percent in the calculations.
We recommend selecting the option to treat missing grades as zero so that an entire block
will not be wasted.
Mintec, Inc. Below is the Pitres window that shows both the surface and partials file selection options
Global entered for presentation purposes only. Remember to only use one of the two options.
Mining
Software
Solutions
Since
1970
Page 29
Determining the Best Feasible Mining Sequence and Phase Design
3-Phase Project
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 30
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 31
Determining the Best Feasible Mining Sequence and Phase Design
5-Phase Project
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 32
Determining the Best Feasible Mining Sequence and Phase Design
7-Phase Project
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 33
Determining the Best Feasible Mining Sequence and Phase Design
EL 2585 – EL 2570
EL 2555 - EL 2540
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 34
Determining the Best Feasible Mining Sequence and Phase Design
9-Phase Project
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 35
Determining the Best Feasible Mining Sequence and Phase Design
Mintec, Inc.
Global
Mining
Software
Solutions
Since
1970
Page 36