Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
Activity Predecessor a m b Te s V=(s) 2
A NIL 2 3 10 4 8/6 1.78
B A 1 2.5 7 3 1 1.00
C A 4 5 6 5 2/6 0.11
D B,C 0.5 1.5 5.5 2 5/6 0.69
11 2.58
CP= A + C + D = 11 d (of Tes)
sCP = Square Root of (Summation of Variance of Critical paths) = 2.58
sCP = (2.58) ½
= 1.6
Z = (Expected Completion Date – CP) / sCP
Z = (12 – 11) / 1.6
=0.622171
Z most of the time equals one of the 1 sigma, 2 sigma, 3 sigma, …, 6 sigma
Sigma and Probability Distribution 8
1. 1 Sigma (1σ) = 11 1.6 = 9.4 - 12.6 (probability of (68.2%) to be within this estimates)
2. 2 Sigma (2σ) = 11 3.2 = 7.8 - 14.2 (probability of (95.4%) to be within this estimates)
3. 3 Sigma (3σ) = 11 4.8 = 6.2 - 15.8 (probability of (99.7%) to be within this estimates)
4. 4 Sigma (4σ) = 11 6.4 = 4.6 - 17.4 (probability of (99.9%) to be within this estimates)
Te
68.2%
95.4%
99.7%
99.9%
σ
Mean
-4 -3 -2 -1 +1 +2 +3 +4
B -- 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B,C 3 4 5
G B,C 1 1.5 5
H E,F 5 6 7
I E,F 2 5 8
K G,I 3 5 7
1. What is the probability the project will be completed within (24) time unit?
2. What is the probability the project will be completed within (25.8) time
unit?
11
PERT
Activity Expected Time Variance
A 6 4/9
B 4 4/9
C 3 0
D 5 1/9
E 1 1/36
F 4 1/9
G 2 4/9
H 6 1/9
I 5 1
J 3 1/9
K 5 4/9
ACFIK 23 2
12
PERT
1. Case of 24
Vpath = VA + VC + VF + VI + VK
= 4/9 + 0 + 1/9 + 9/9+ 4/9
=2
spath = (2)1/2 = 1.414
Z = (X- CP) / spath
2. Case of 25.8
Probability the project will be completed within (25.8) time unit
Means 2s, so Probability = 0.5 + 95.4% / 2 = 0.977