Building Condition Survey Checklist

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Chennai Metro Rail Limited

Existing Building Condition Survey Phase II Corridor 3 Package- 01

Building Condition Survey Checklist


Project Details

Project Name Chennai Metro Rail Phase II, Corridor 3

Client Chennai Metro Rail Limited

Subject Existing Building Condition Survey

Consultant AECOM

Building Identification and Ownership

Building ID 7E033

Date of Survey 13.06.2019

Location Perambur to Aynavaram, CH .5390m(Approx.)


&Chainage
Building Address No.2,
Semathamman colony,
Perambur,
Chennai -12.
Name of Mrs.Maheswari
Property Owner 9444283408
and Contact (Owner)
Details

General Building Details

Year of 2011– 8years


Construction
and Age of
Building
No. of – No. of Storeys G+2(tiled)
Basements
Type of Building
(Tick the
þResidential Public
þCommercial Industrial Other

First floor and Ground floor


appropriate)
Second floor

Approximate L=6.14m
H =9.5m(Approx.) Area =55.66sq.m
Area & Height B=6.09m
Type of
Structure
Load Bearing
þFramed Composite Steel
Structure
Other

(Tick the
appropriate)
Type of
construction
Brick work
þRCC Composite Steel Wooden Other

With Brick infill


material (Tick
the appropriate)
Exterior Cover
(Tick the
None
þPlaster Stone Cladding Tile
Cladding
Other

appropriate)

1 of 7
Chennai Metro Rail Limited
Existing Building Condition Survey Phase II Corridor 3 Package- 01
Cracks Minor cracks Moderate cracks Severe cracks
Number of
- 1 -
External Cracks
Number of
- - -
Internal Cracks
Roadways Semathamman colony main road, Cement concrete road, 15ft wide
Distance of the
structure from
Above the tunnel
the centre line
of the tunnel
Drawings
available No, building layout drawings are not provided by the owner/owner representative
(Yes/No)
Any subsequent No,subsequent changes or alterations were made in the building.
changes/
alteration
(Yes/No)
Dampness No, dampness was not observed in the building.
(Yes/No)
Exposed No, exposed reinforcement wasnot observed in the building.
reinforcement
(Yes/No)
Peeling of No, peeling of plaster was not observed in the building.
plaster/ spalling No, spalling of concrete was not observed in the building.
of concrete
(Yes/No)
Number, Depth No Bore well available Water Not available
&Dia of Bore well (As per owner’s verbal information) sump, If
(Based on owner Any
verbal info)

Type of
Foundation
þMasonry Open Raft
þIsolated Footing Strip
Footing
Pile Details
Foundation , if any
Depth=7 ft
(Tick the
(As per owner’s
appropriate)
verbal information)
Presence of
machine/ þNone Light Medium Heavy Description
, If any
equipment (Tick
the appropriate)
Geotechnical No geotechnical investigation was carried out in the building
Investigation
report (Yes/No)
Verticality & No signs of verticality & deflection in the building
Deflection
(Yes/No)

2 of 7
Chennai Metro Rail Limited
Existing Building Condition Survey Phase II Corridor 3 Package- 01

Damage Category Good


Assessment
þSatisfactory Poor

Surveyor Details

Head Details Signature

Date of Survey 13.06.2019 -

Balakrishnan/Manikandan Balakrishnan/Manikandan
Name of Surveyor

Name of Owner /Owner Mrs.Maheshwari Maheshwari


Representative

1. Photographs and significant defects

Photo ID:7E033 _01: - Front view of the building Photo ID:7E033 _02: - View of the Shop

3 of 7
Chennai Metro Rail Limited
Existing Building Condition Survey Phase II Corridor 3 Package- 01
Photo ID:7E033 _03: - View of left side wall in hall Photo ID:7E033 _04: - View of Room in terrace

Photo ID:7E033 _05: - View of storage room Photo ID:7E033 _06: - View of kitchen

Photo ID:7E033 _07: - View of water storage tank Photo ID:7E033 _08: - View of crack below the water
storage tank

4 of 7
Chennai Metro Rail Limited
Existing Building Condition Survey Phase II Corridor 3 Package- 01

5 of 7
Chennai Metro Rail Limited
Existing Building Condition Survey Phase II Corridor 3 Package- 01

6 of 7
Chennai Metro Rail Limited
Existing Building Condition Survey Phase II Corridor 3 Package- 01

7 of 7
Scanned by CamScanner
Scanned by CamScanner