Materials System Specification
Materials System Specification
Materials System Specification
Contents
1 Scope ................................................................ 2
2 Conflicts and Deviations ................................... 2
3 References........................................................ 2
4 Purchase Order Information .............................. 5
5 Material Requirements ...................................... 5
6 Requirements for Design, Cutting and Fitting ... 7
7 Bending ........................................................... 10
8 Welding ........................................................... 10
9 Inspection and Tests ....................................... 11
10 Supplementary Requirements
for Fabricated Laterals .................................... 12
11 Product Marking and Preparation
for Shipment.................................................... 12
Revision Summary.................................................. 14
1 Scope
1.1 This specification defines the minimum mandatory requirements governing the
fabrication of steel pipe spools, including welding, heat treatment, and testing.
1.2 This specification may be used for piping made of alloy steels for low and high
temperature applications. In this case, exceptions and additions to this
specification will be stated in the Purchase Order or its attachments.
1.3 The governing code shall be ASME B31.3 unless B31.1, B31.4 or B31.8 is
specified in the Purchase Order as required.
Commentary Note:
Manufacturing of CRA clad pipe spools and clad piping components are covered
in 01-SAMSS-044 and 02-SAMSS-012, respectively.
2.1 Any conflicts between this document and other applicable Mandatory Saudi
Aramco Engineering Requirements (MSAERs) shall be addressed to the
EK&RD Coordinator.
2.2 Any deviation from the requirements herein shall follow internal company
procedure SAEP-302.
3 References
The purchase and manufacture of material covered by this specification shall comply with
the latest edition (as per the purchase order date) of the references listed below, unless
otherwise noted:
5 Material Requirements
All materials supplied by the Vendor for piping elements or structural attachments shall
conform to the requirements of the applicable Saudi Aramco mandatory documents and
industry code, and shall be traceable to mill certificates. All piping components used an
integral part of the pipe spools shall be manufactured and procured from Saudi Aramco
approved sources. Materials of unknown specification and sources are not permitted.
5.1 Pipe
5.1.3 ERW pipe (electric resistance welded), HFI pipe (high frequency
induction welded), or spiral weld pipe shall not be used to fabricate this
commodity.
5.1.4 Materials for stainless steel pipes shall conform to the requirements of
01-SAMSS-046.
5.2.2 Pipe sizes of 1½-inch and smaller in vibration service, shall have bracing
in accordance with Standard Drawing AB-036521. Where bracing cannot
be effectively provided, nipples with Schedule 160 shall be installed.
5.3 Flanges
5.4 Fittings
Unless otherwise shown on the Purchase Order drawings, the pipe fittings shall
be as follows:
5.4.1 Butt welding pipe fittings shall be used for nominal pipe sizes 2-inch and
larger. Butt welding pipe fittings shall be in accordance with
02-SAMSS-005 for carbon steel and 02-SAMSS-013 for stainless steel
and nickel alloy fittings. The material grade of butt welding fittings shall
match, or be equivalent in strength to, that of the adjoining pipe.
5.4.3 All unions shall conform to MSS-SP-83, with pressure class per design
requirement but not less than class 3000 for nominal pipe sizes 1½” and
smaller. The material shall be carbon steel per
ASTM A105N, ASTM A350 LF2 or alloy steel per ASTM A182,
depending on design requirements.
5.4.4 For nominal pipe sizes 1 ½” and smaller, forged steel welding bosses
shall conform to either Standard Drawing AE-036175 or AD-036643 or
Steel plate used for reinforcing pads, sleeves, saddles and other structural
attachments shall conform to a code listed plate material with specified
minimum yield strength of 241.3 MPa (35,000 psi) or greater, depending on
design requirements.
5.6.1 Pipes shall meet the sour service requirements of 01-SAMSS-035 (with
Annexes K & H of API SPEC 5L), 01-SAMSS-043 or 01-SAMSS-046,
depending on the type of pipe material.
6.1 Drawings
6.1.1 The Vendor shall prepare detailed shop fabrication drawings based on
the Purchase Order drawings. The shop drawings shall be submitted to
the Buyer for approval prior to fabrication.
6.1.2 Any details not shown on Buyer's drawings shall be designed by the
Vendor in accordance with the applicable ASME piping code, with the
review and approval by the Buyer.
6.1.3 Standard piping symbols used on Piping Detail Sheets and Isometric
Detail Sheets are identified on Standard Drawing AB-036227.
6.1.4 Approval of Vendor's drawings by the Buyer does not relieve the Vendor
of the responsibility for compliance with the code, this specification and
the Purchase Order requirements.
6.2.1 The reinforcement pad shall be in accordance with the Standard Drawing
AB-036719.
6.2.2 A 3-6 mm weep hole shall be provided for each reinforcing. The weep
hole shall not be mechanically plugged nor seal welded but can be
plugged with grease after the required testing.
Mitered bends or miter pipe joints are not permitted. A mitered joint is defined
as a joint with an angular offset larger than three degrees.
6.4.1 For butt-weld connections of wall thickness ratio of joined pipes greater
than 1.5, end preparations and geometry shall comply with ASME B16.25.
6.4.2 Threaded and socket welded joints shall be limited to 1-1/2” and smaller.
For socket-welded connections, the axial gap between male and female
component, as shown in Figure 328.5.2C of ASME B31.3 code, shall be
maximum of 3 mm and minimum of 1.5 mm.
6.4.3 Seal welding is required of all threaded joints up to the first block valve
except in the following services:
a) Thermowells.
b) Bar stock plugs downstream of a seal-welded block valve.
c) Special devices such as access fittings and scraper signals.
d) Joints which require frequent disassembly and are located
downstream of a seal welded block valve, e.g. sample connections.
e) Instrument piping downstream of the primary instrument isolation
valve.
f) Pipe union ring threads and joints with elastomer O-rings.
g) Threaded joints, downstream of a seal welded root valve, which
discharge directly to an open drainage system or to the atmosphere.
h) Extended body valves with integrally reinforced welding end per
API STD 602.
6.5.1 Pipe unions shall not be installed in the pipe section between the main
pipe run and root valve.
6.5.2 Integrally reinforced fittings shall be designed to abut the pipe wall with
a full penetration weld.
6.5.4 The use of Saudi Aramco approved proprietary pipe coupling is limited
to piping 2 inch maximum for instrument air, nitrogen, and water
service.
6.5.5 Bushings with one size reduction shall not be used. Only hex head steel
bushings shall be used. Flush steel bushings are not permitted.
6.6.1 The ends of pipe and pipe spools to be joined by girth welds during field
installation, shall be prepared and matched to facilitate fit-up in the field
unless it is indicated in the drawing where extra length is to be cut back
in the field for adjustment. Corresponding welding ends shall be clearly
marked.
6.6.2 All welding ends shall be beveled with an angle of 35 degrees, ±5 degrees,
and a root face of 1.6 mm, unless otherwise detailed in the PO or governed
by the applicable design code. Joint preparation shall comply with the
requirements of applicable Saudi Aramco welding standard (SAES-W-
011, SAES-W-012, SAES-W-016) as referenced in para 8.1, and
drawings. The end plane shall be normal to the pipe axis as defined on the
piping drawing, within 0.25 degrees.
6.7.2 Lateral offset of branches and connections from centerline of run shall
not exceed ±1.6 mm.
6.7.3 Flange bolt holes shall straddle the established centerlines. Rotation of
flanges, measured as the offset between elevation of bolt holes on
opposite sides of a flange centerline shall not exceed ±1.6 mm.
6.7.4 The tilt of a flange measured at the periphery across any diameter shall
not exceed 1 mm from the square position.
6.7.6 Pipe spools and bends shall be checked and corrected after heat
treatment to assure proper alignment of flanges and correct centerline
dimensions. The alignment correction procedure shall be submitted to
Saudi Aramco Inspection Representative for review.
6.7.7 Bend tolerances are: bend angle ±0.5 degree and bend radius ±1% unless
otherwise indicated on Company drawing or Purchase Order.
7 Bending
Furnace hot bends or induction bends shall comply with the requirement of
01-SAMSS-039.
8 Welding
8.1 All joint preparation, welding, heat treating, and non-destructive testing shall be
in accordance with the following specifications:
a) SAES-W-011 for ASME B31.3 applications.
b) SAES-W-012 for ASME B31.4 and ASME B31.8 applications.
c) SAES-W-016 for welding of special corrosion-resistant piping materials.
Welds in stainless steel shall be pickled and passiviated as per ASTM A380.
8.2 Repairs
Unsuccessful weld repairs after the second attempt shall be cut out as a cylinder
and shall be replaced with a new section of pipe and/or fittings.
All inspection and testing shall be performed in line with Saudi Aramco Inspection
Requirements Form 175-013100 per a detailed Inspection & Testing Plan (ITP).
Positive Material Identification (PMI) shall be conducted in accordance with the
requirements of SAES-A-206 as applicable.
9.1.1 When all openings on a pipe spool are either flanged or threaded, the
spool shall be hydrostatically tested. When no test pressure is indicated
in the Purchase Order, the hydrostatic test pressure shall be based on the
flange rating as shown in ASME B16.5, but not less than the minimum
test pressure per ASME B31.3 paragraph 345.4.2 or other applicable
codes.
9.1.2 The Vendor shall provide the necessary blind flanges, plugs, caps, or
plates required for the hydrotest.
9.1.3 For pipe spools made from austenitic stainless steel, chloride content of
water shall not exceed 50 ppm.
9.1.4 After hydrotest, the spools shall achieve the required lay-up per SAES-
A-007.
9.1.5 Pipe spools which have welding ends shall not be pressure tested unless
provisions for test ends have been indicated in the Purchase Order
documents. For pipe spools which are not to be pressure tested, all weld
joints shall be 100% inspected by using the NDT methods specified in
the Purchase Order.
9.2 Inspection
The Vendor shall give an advance notice in writing to the Buyer for all tests
required for the fabrications. All materials, certificates, fabrication, testing and
examinations shall be subjected to verification by Buyer's Inspector in
accordance with ASME B31.3 Chapter VI or other applicable codes for full
compliance with this Specification and the Purchase Order drawings and other
requirements. Inspection shall be carried out at the place of manufacture.
Saudi Aramco: Company General Use
©Saudi Aramco 2018. All rights reserved Page 11 of 14
Document Responsibility: Materials Engineering Standards Committee 01-SAMSS-010
Issue Date: 9 July 2018
Next Planned Update: 9 July 2021 Fabricated Steel Piping
10.1 Laterals shall be used only when required by Saudi Aramco standards. They
should be used for low pressure system (less than 150 psig) such as flare lines.
10.2 Fabricated laterals made by welding the branch pipe directly to the run pipe
shall have a complete encirclement reinforcement, and shall be designed and
tested according to the code and SAES-L-110.
10.3 The design drawings shall include detailed design calculations for Buyer
approval prior to fabrication.
10.4 The vendor shall utilize skilled ASME Section IX qualified welders with
rejection rate of less than five (5) percent on a joint basis or 0.2% on a linear
basis in the most recent past twelve (12) months. Saudi Aramco approved
Welding Procedure Specification (WPS) shall be used. Application of robotic
welding is encouraged.
10.5 The detailed Inspection and Test Plan (ITP) for laterals shall also cover the
following minimum supplementary requirements:
10.5.1 Visual inspection of the the fit-up, gap, weld root, filling and cap passes
during the welding process.
10.5.2 Performing 100% NDT on the welds. This includes dye penetrant
(PT)/Magnetic particle (MT) of the root pass in addition to visual
examination. For the groove weld joining the branch with the run pipe,
the weld shall be subjected to both volume and surface examinations.
Where welds cannot be ultrasonically inspected, in-process examination
shall be carried out as specified in paragraph 344.7, ASME B31.3 and
the examination methods shall include dye penetrant (PT)/Magnetic
particle (MT) in addition to visual inspection.
10.6 Hydrostatic test of fabricated laterals shall comply with the requirements of
SAES-L-110.
11.1 Identification
11.1.1 Each spool shall be marked with the purchase order number and spool
number painted at the ends as shown on the drawings. The numbers
shall not be less than 25 mm in height. In addition, the spool number
shall be die-stamped on the rim of each flange.
11.2 Cleaning
All loose foreign material and weld spatter shall be removed from the inside and
outside of the spool. The spool shall be clean and dry.
11.3 Painting
Unless otherwise specified in the Purchase Order, the pipe spools shall not be
painted or coated.
11.4 Protection
10.4.1 When spools are supplied with blind flanges, they shall be bolted on
with the specified gaskets and stud bolts. Other flange faces shall be
protected by a suitable cover bolted to the flange.
11.4.2 Threaded bosses shall be fitted with steel bar stock plugs. Threaded pipe
ends shall be provided with steel or malleable iron pipe caps as
temporary closure. Threads shall be coated with a graphite and oil paste.
11.4.3 Welding ends shall be protected against damage during handling and
shipment by means of a securely fastened bevel protector.
11.4.4 Pipe and fittings shall not be stored directly on the ground.
11.4.7 Lined and coated pipe and fittings shall be lifted with wide fabric or
rubber-covered slings.
Revision Summary
9 July 2014 Revised the Next Planned Update, reaffirmed the content of the document, and reissued as
major revision. As directed by the new SAEP-301, the document was routed to affirm the
contents are up-to-date.
8 July 2018 Major revision (refer to Summary of Change Form).