JMS PIPING REPLACEMENT IWR BT2 2016 Dec 147 (P3) Rev01
JMS PIPING REPLACEMENT IWR BT2 2016 Dec 147 (P3) Rev01
JMS PIPING REPLACEMENT IWR BT2 2016 Dec 147 (P3) Rev01
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
Open
RESOURCE (MAN) MANHOURS RESOURCE (EQPT)
AWL F1 F2 GW RI HW FW WEL PNT CBT MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS MHRS
NO TASKID No TAPHASE TASK TASKNOTE OWNER CONTR DATA DUR (HRS) (AWL) (F1) (F2) (GW) MHRS (HW) (FW) (WEL) (PNT) (CBT) SCAFFOLDING (M3) INSULATION (M2)
(RI)
MHRS MHRS CRANE GEN SET WELDING SET HTW/HBT COMPRESSOR
1 IWR/BT2/2016/Dec/147 3/4''-WU-224264-1801X-NI PIPE REPLACEMENT & PAINTING
1 1-Pre Execution Material delivery INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
2 1-Pre Execution Material inspection by AIMD Inspector INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
3 1-Pre Execution Spool fabrication, NDT Inspection by AIMD at workshop HRSB 0 0 0 0 0 0 0 0 0 0 0 0
4 1-Pre Execution Perform HT and Withness by AIMD Inspector INSP 0 0 0 0 0 0 0 0 0 0 0 0
5 1-Pre Execution Perform blasting and painting on new spool 0.26m2 HRSB 0 0 0 0 0 0 0 0 0 0 0 0
6 1-Pre Execution Painting inspection by AIMD INSP HRSB 0 0 0 0 0 0 0 0 0 0 0 0
7 1-Pre Execution Erect external scaffolding HRSB 0 0 0 0 0 0 0 0 0 0 0 0
8 1-Pre Execution Remove insulation HRSB 0 0 0 0 0 0 0 0 0 0 0 0
Open
REMAKS
Open
REMAKS
Open
EIS (above to 12" Nom Bore) DURATION HRS
BLIND NO SIZE RATING BLINDING DE.BLIND FIL HLP
0.00 0.00 2 1
0.00 0.00 2 1
TOTAL 0.0 0.0
DURATION HRS
qty
piping
Remove/
weld type SIZE sch fit up weld
Install
TRD 3/4 80 0.4 1
TRD 3/4 80 0.4 1
duration
QTY xtvt vol.m2 TOTAL SS FW
(hrs)
DURATION
Site pre 0.26 1 1
Surface prep 0.26 2 0.52432125 1 1
SP Insp. 0.26 1 0.262160625
1st coat 0.26 1.5 0.3932409375 1
curing 0.26 8 2.097285
1st coat Insp 0.26 1 0.262160625
2nd coat 0.26 1 0.262160625 1
curing 0.26 4 1.0486425
2nd coat Insp 0.26 1 0.262160625
Final coat 0.26 1 0.262160625 1
curing 0.26 4 1.0486425
Final coat Insp 0.26 1 0.262160625
TOTAL 0.00 0.00
CLEANING FORMULA
ID H π D
SHELL 4.88 28.4 3.142 4.88
SHELL 3 20.315 4.142 3
ELLIP TOP 3 1 1.084 3
ELLIP BOTTOM 4.88 1 1.084 4.88
D
ELLIP SHELL bottom 4.942 1 1.084
1.084 0
CLEANING LGHT ID π TOTAL QTY PLATE
PERIMETER
CLEANING FORMULA
ID H π D
TRAY 4.942 3.142 4.942
TRAY 3 3.142 3
D
1.084 0
1.084 0
NDT
NO TYPE QTY DURATION TOTAL DUR
1 BORO 0.083 0.0
2 IRIS 0.367 0.0
3 RFET 0.083 0.0
TOTAL (HR) 0.53 0.0
INT.SCAFFOLDING DURATION
L W H M3 ERECT DISMANTLE
5 5 4 100 25 25 bottom
5 5 2.5 63 16 16 tray 35#
0 0 0
TOTAL 163 41 41
RIG
0.00
TOTAL 0.0
HRS FOR
WELD
ONLY
RIG
RIG
1
1
TOUCH UP
1 Site pre
1 Surface prep
1 SP Insp.
1 1st coat
curing
1 1st coat Insp
1 2nd coat
curing
1 2nd coat Insp
1 Final coat
curing
1 Final coat Insp
RIG
ORMULA DURATION
AREA M2
H WIRE BRUSH COTTON RAG POWER BRUSH
28.4 435.46 217.73 145.15 72.58
20.32 252.43 126.22 84.14 42.07
1 3.25 1.63 1.08 0.54
1 5.29 2.64 1.76 0.88
D
0.00 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
TOTAL 696.43 348.22 232.14 73.46
DURATION
TOTAL
WELMENT TOTAL
QTY PLATE WELDMENT POWER BRUSH
TOP ELLIP VESSEL
& LENGTH
BOTTOM
ELLIP
15.53 23.67 582.29 97.0
12.43 16.93 340.39 56.7
9.43 0.83 61.27 10.2
15.53 0.83 100.93 16.8
0.00 0.00 0.00 0.0
TOTAL 271.22 45.2 25% TOTAL WELDMENT
ORMULA DURATION
AREA M2
H WIRE BRUSH COTTON RAG POWER BRUSH
0 124.22 62.11 41.41 20.70
0 61.27 30.63 20.42 10.21
D
0 0.00 0.00 0.00 0.00
0 0.00 0.00 0.00 0.00
TOTAL 185.49 92.75 61.83 30.92
0.00 1 1
0.0
DURATION HRS
Total
duration
vol.m2 duration
(hrs)
(hrs)
1 1
0.02 2 0.04
0.02 1 0.02
0.02 1.5 0.03
0.02 8 0.16
0.02 1 0.02
0.02 1 0.02
0.02 4 0.08
0.02 1 0.02
0.02 1 0.02
0.02 4 0.08
0.02 1 0.02
TOTAL 0.11
flushing
TOTAL WELDMENT
4 4 1
2 2 1
PCOGD SDN BHD TURNAROUND 2019
NO WORK ID LINE NO JOINT SIZE SCH WELD TYPE FW/SW F/U V/I DPI RT RT 1 HT PAINTING REMARKS
IWR/BT2/2016/Dec/147 3/4''-WU-224264-1801X-NI
1 3/4''-WU-224264-1801X-NI 1 0.75 80 TH FW 3/4 @ 0.75
3/4''-WU-224264-1801X-NI 2 0.75 80 TH FW 3/4 @ 0.75
Fit-up Joint Dia inch Fit-up Joint Dia inch DPI Done RT Done Ht Done PAINTING
Welded Weld Done
0 0 0 0 0 0 0 0
WORK REQUERST
TOTAL TOTAL DIA
SHOP FIELD SHOP FIELD JOINT INCH (Overall)
(Overall)
SW BW SW BW TH TH
JOINT 0 0 0 0 0 2 2
DIA INCH 0.00 0 0 0 0 1.5 1.50
TOTAL JT 0 TOTAL JT 0
TOTAL Ø
TOTAL Ø INCH 0 INCH 0 RT (total) RT (SHOP) RT (FIELD)
JOINT SW TOTAL JOINT SHOP/FIELD 0 0 0 0
AND BW DIA INCH JOINT SHOP/FIELD 0
#DIV/0!
MTO
Sch/
Item Qty Unit Size Description Rate (RM)
Rating
1 PIPE
2 2.5 m 3/4" SCH80 API5LGR.B/GALV SMLS T&C SCH80
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Total (RM)